Académique Documents
Professionnel Documents
Culture Documents
for
Proposed By
Prepared By
M/s NGC Energy India Private Limited (NGC) is proposing to set up a new Refrigerated
Propane/Butane/LPG import Terminal, jetty to terminal pipelines & associated facilities at
Krishnapatnam Port, District SPSR Nellore, Andhra Pradesh. Two above ground, full
integrity double walled tanks of capacity 16,600 MT each, shall be provided to store propane
and butane in a refrigerated condition. In addition, two mounded bullets of capacity 370 MT
each, shall also be provided for Propane/Butane/LPG storage. The proposed terminal and
associated facilities shall be approved by PESO, and comply with other statutory
requirements.
The Terminal is proposed to be constructed within a plot of ~ 4.91 Hectares (12.14 Acres)
on land sub-leased from M/s Krishnapatnam Port Corporation Limited (KPCL). This facility
will be set up within the Liquid Cargo Terminal area being developed by KPCL.
NGC have appointed M/s. ULTRA TECH Environmental Consultancy & Laboratory
(MoEFCC recognized and NABET accredited), Thane, to carry out study of the impacts of
the project on the local environment and for obtaining Environmental Clearance. ULTRA
TECH is an established Consultancy in the field of Environmental Services for the past 30
years.
NGC has proposed to set up a new refrigerated Propane/Butane/LPG import Terminal and
associated facilities with two refrigerated tanks of capacity 16,600 MT each, and two
Mounded Bullets of Capacity 370 MT each at Village Krishnapatnam, District SPSR Nellore,
Andhra Pradesh. The project location is well connected with Krishnapatanam railway station
within a distance of 8.6 km (W). The total plot area for the terminal is approximately ~
4.91Hectares (12.14 Acres).
b) During Operations (Post Commissioning): 10 KLD for domestic consumption and a small
quantity for process and fire water make up
Management 15
There is no manufacturing process involved in the Terminal. The Process Flow Chart and
description of the main operations of the Terminal are as below:
Receipt: Refrigerated Propane & Butane imported in ocean tankers shall be received through
insulated pipelines from Jetty to the Terminal.
Storage: These will be stored in two separate above-ground tanks and two mounded bullets.
The tanks and bullets will be designed as per applicable Indian and international standards.
Dispatch: LPG, blended from Propane & Butane will be dispatched in LPG tank trucks by
road within India and in ships to regional markets.
The entire operation of Receipt, Storage and Dispatch of Propane, Butane, & LPG will be
carried out in a completely closed system thereby eliminating risk of leak and spillage of the
product.
Receipt to NGC’s Terminal at Krishnapatnam port shall come from imports in refrigerated
ocean tankers. These ships will berth at the multi-purpose Liquids jetty to be constructed by
KPCL, and discharge Propane & Butane through dedicated marine un-loading arms at the
jetty connected to insulated pipelines that will run from the jetty to the terminal.
Storage of Propane and Butane discharged from ships will be in two dedicated refrigerated
tanks of 16,600 MT capacity each. Additionally, two mounded bullets of capacity 370 MT
each shall be provided. The design of the Terminal will be in accordance with Petroleum
Rules, PESO standards, and relevant OISD guidelines. The details of storage Tanks are as
shown in Table 4.
Dispatch of LPG through tank trucks is expected to progressively grow in volume post
terminal start-up. On average, at sustained operation, about 150 trucks per day are expected
to be loaded and dispatched from the terminal. Plan is to build a loading gantry shed with 8
bays, with provision to add another 8 bays in future. Supply from the terminal is expected to
serve the growing LPG demand around the Krishnapatnam hinterland market, primarily in
the states of Andhra Pradesh, Telangana, Karnataka and Tamilnadu.
4.5 Plant and Non Plant Buildings and Other Civil Works
The list of major Plant and Non-Plant Buildings proposed is given in Table 5.
• Two above-ground refrigerated Propane and Butane storage tanks of double wall full
integrity design, both rated for Propane, designed as per API 620 or equivalent.
• Two mounded bullets on Propane/Butane/LPG service, designed as per IS 2825 or
ASME Sec VIII, Division II, or equivalent.
• One above ground vertical cone roof diesel storage tank for DG’s and fire water
pumps’ engines fuel storage
• Two fire water storage tanks of total capacity 10,000 m3 to meet fire-fighting
requirements as per applicable codes and OISD guidelines, shall be provided in
addition to the hydrocarbon storage tanks listed in Table 4.
Major pipelines and pipeline systems outside and inside terminal battery limits are as below.
These will all be designed as per applicable piping codes like ANSI B 31.3 and 31.4. All
pipeline work will include in its scope required flanges, metallic gaskets, fire safe valves,
safety and other fittings. The design will also consider and cater to the need for easy
inspection and maintenance of the pipelines.
• 2 numbers marine unloading and loading arms connected to 2 insulated pipelines from
the jetty to terminal, for receiving Propane and Butane from ocean tankers. These
lines can also be used for loading Propane and Butane from the terminal into ocean
tankers for dispatch to regional markets. Provisions to pig both lines will be provided.
• Pipelines to load Propane/Butane/ LPG from the refrigerated tanks or mounded
bullets into LPG tank trucks at the loading gantry
• Pipelines associated with the tank boil off gas compression, condensation and
recovery system
• Various utility system pipelines for process and potable water, instrument air, sewage
water, etc.
• Fire water system pipelines
• During the construction phase, there will be fugitive emissions due to movement of
equipment at site, dust from leveling, grading, earthwork, foundation work and other
construction related activities. These impacts will however, be marginal and
temporary in nature.
• Sewage generation is envisaged during the operation phase and hence a STP (Sewage
Treatment Plant) is proposed to cater to the sewage load. Sewage from the
administration building will be routed to the septic tanks followed by soak pits and the
sludge generated from the septic tank will be dried and used as manure for the
landscaped plants and greenery within the terminal.
• Storm water drains will be provided at the Terminal. These drains will drain storm
water from Tank dykes and other areas within the Terminal premises to prevent
flooding during rains.
• The DG sets shall be acoustically insulated for reduction of noise as per limits
prescribed by State Pollution Control Board. The exhaust pipe from DG sets shall be
taken above the building as per State Pollution Control norms.
• No manufacturing is involved in the Terminal Operations, and there is no hazardous
waste generated from the operations. The waste oil generated from the DG sets and
fire water pump diesel engines will be collected in drums and stored in a closed shed
for safe disposal. Spent oil, Oily sludge, empty drums of mercaptan and used lead
batteries shall be sent to authorized vendors for disposal.
• All conditions & pre-requisites of water and air consents together with certificate to
handle hazardous products issued by State Pollution Control Board shall be strictly
complied with.
• All requisite clearances shall be obtained from PESO and other statutory authorities
• Meet the provisions as per Manufacture, Storage and Import of Hazardous Chemicals
Rules 1989, as amended in 2000 and the Public Liability Insurance Act for handling
of hazardous chemicals
• The terminal will be provided with gas leak detection and flame detection systems.
These systems will be interlocked with the safety and fire fighting systems of the
terminal
• All the hazardous waste shall be properly treated and disposed of in accordance with
the Hazardous Waste Rules 2008 and its subsequent amendments 2016
• Provision shall be made for maximizing landscaping with plants and green cover
inside the terminal
• Offsite disaster management plan shall be prepared in accordance with PNGRB
guidelines
• Occupational health surveillance of workers shall be conducted and records
maintained as per the Factory Act
• Parking area for the LPG tank trucks waiting to enter the terminal for filling shall be
provided in the Port premises
• A traffic management system shall be developed for the smooth and safe movement
of trucks within the terminal
• Consent To Establish and Consent To Operate shall be obtained prior to construction
and operations of the terminal.
A HAZOP study will be conducted based on which a process control matrix and safety
control matrix will be developed which will be used for managing safe operations of the
terminal. The safety control matrix will be used for emergency shut-down and fire-fighting.
The system architecture shall provide for 100% redundancy of critical Process and Safety
instrumentation. The entire automation system shall be powered with an online UPS of
adequate capacity and battery back-up. The design of Instrumentation and automation for key
systems will consider provision for:
Pumps:
o No flow / dry run protection
o Minimum flow protection
o Overload protection
o Temperature and Pressure measurements
o ROVs
o Soft starters
Compressors:
o Low suction pressure protection
o High discharge pressure protection
o Overload protection
o High temperature protection
o Low lube oil pressure protection
o Soft starters
o ROVs will be provided on Propane / Butane / LPG product pipelines for
remotely managing operations
o Automatic system for blending of Propane and Butane and dosing mercaptan
at desired ratios in a static mixer
o Pressure & temperature transmitters, flow indictors on pipelines to meet
process requirements
Safety:
o Gas detection systems
o Flame detection system
o Fire alarm call point
o Emergency shut-down system
o Emergency local stop
o Grounding system
Other:
o Automatic boil-off gas management system to maintain refrigerated tanks’
pressure within safe limits
o Mass flow meter for monitoring the receipt of Propane and Butane cargoes
o Digital Control System (DCS) with independent programmable logic
controllers (PLCs) for Process and Safety
6.5 Painting
All equipment, structures, pipelines, buildings, sheds, compound wall etc. shall be painted as
per IS-Code and as per standard engineering practice.
6.7 Security
• Security features including CCTV, Access Control System
• Compound Wall Covering entire plot will be provided as per statutory requirements
and safety norms.
• 1.8 m high Chain Link fencing for operational area demarcation based on Electrical
Zone Classification.
• Truck Entry & Exit gate will be provided as per statutory requirements and safety
norms.
• Watch Towers of suitable heights will be provided. depending upon security
requirement for effective coverage of entire Terminal.
• Common LPG Tank Truck inspection platform at entry and exit points.