Final Product Air At 5mtr level platform Tie member end cleat fixing
185 EL 5.0Mtr
Slide balance at places.
Final Product Air At 5mtr level platform Tie member end cleat portion
186 EL 5.0Mtr
Slide welding balance at places.
Final Product Air Below 591AS5 final product air slide portion grating to be
192 EL 3.0Mtr
Slide fixed.
Final Airslide conveyor Gallery bottom tie member
193 EL 8.0Mtr Conveyor Gallery
[ISMC150] over head welding balance.
Bag Filter Bag Filter 591BF2 stool stiffner plate overhead welding
194 EL 10.0Mtr
591BF2 balance.
195 EL 8.0Mtr Airline piping Final Airslide airline pipe full painting balance
Roof Truss of All Roof Truss bottom gusset plate area overhead welding
198 EL 14.3.0Mtr
gallery balance.
199 EL 8.0Mtr Conveyor gallery Gallery side runner joint area splice angle to be provided.
Page 1 of 5
PUNCH POINT
202 EL 10.0Mtr Expansion Joint All expansion joint area clamp to be removed.
Airslide inclined Hand rail toe guard fixing balance at Air slide platform
205 EL 16.0Mtr
platform 12mtr level.
Airslide inclined 16mtr to 12mtr Air slide platform stud column base plate
206 EL 16.0Mtr
platform area welding balance at places.
Extension platform at 14mtr level [E6-7] area toe guard
207 EL 14.3Mtr Platform
fixing pending
208 EL 14.3Mtr Platform At 14mtr level hand rail finishing work pending.
210 EL 25.0Mtr Product Airslide Airslide bottom cover plate fixing balance at places.
211 EL 25.0Mtr Product Airslide Airslide support str welding & finishing balance at places.
212 EL14.3Mtr Air Slide 591AS1 Painting balance air areation pipe line of Air slide 591AS1
213 EL14.3Mtr Air Slide 591AS2 Painting balance air areation pipe line of Air slide 591AS2
214 EL14.3Mtr Air Slide 591AS3 Painting balance air areation pipe line of Air slide 591AS3
215 EL14.3Mtr Air Slide 591AS4 Painting balance air areation pipe line of Air slide 591AS4
216 EL16.28Mtr Air Slide 591AS3 Air slide 591AS3 end cover plate bolt tightening balance.
Page 2 of 5
PUNCH POINT
217 EL16.28Mtr Air Slide 591AS4 Air slide 591AS4 end cover plate bolt tightening balance.
Bag Filter Bag Filter at 14mtr level base plate welding balance with
222 EL 14.3Mtr
591BF1 Insert plate.
Bag Filter Bag Filter duct line "Round" type support fixing balance at
223 EL 14.3Mtr
591BF1 14mtr level
Bag Filter
224 EL 14.3Mtr Bag Filter duct line painting balance.
591BF1
Bag Filter Bag Filter ID fan inlet & outlet duct area nut bolt full
225 EL 14.3Mtr
591BF1 tightening required.
Bag House
226 EL 18.6Mtr All opening at 18mtr level to be closed by chequered plate.
Platform
Bag House
227 EL 18.6Mtr Hand Rail Grinding & finishing balance at 18mtr level
Platform
Bag House
228 EL 18.6Mtr Toe gurad fixing balance at places.
Platform
Bag House Walkway with Grating & handrail erection pending at Row
229 EL 18.6Mtr
Platform D-E, axis 4 area.
Bag House Walkway with Grating & handrail erection pending at Row
230 EL 18.6Mtr
Platform D-E, axis 9 area.
Bag House Bag Filter duct line "Round" type support fixing balance at
231 EL 18.6Mtr
Platform 18mtr level
Bag House
232 EL 18.6Mtr House keeping pending at 18mtr level
Platform
Page 3 of 5
PUNCH POINT
Bag House
235 EL 18.6Mtr Touch up painting balance at 18mtr level.
Platform
Bag House
236 EL 21.4Mtr At 21mtr level handrail toe guard fixing balance at places.
Platform
Tie member [MC200] one side end cleat fixed at site, As
Bag House
237 EL 21.4Mtr per standard drawing both side cleat mentioned in
Platform
drawing
Bag House
238 EL 21.4Mtr Hand rail welding & cleaning balance.
Platform
Bag House
239 EL 21.4Mtr Touch up painting balance at 21mtr level.
Platform
Bag House
240 EL 21.4Mtr House keeping pending at 21mtr level
Platform
Bag House Additional 1 no walkway required in between hopper "L"
241 EL 21.4Mtr
Platform & "R" portion in axis 6-7 area.
Bag House At 24mtr level Hand rail welding & finishing work
243 EL 24.4Mtr
Platform pending.
Bag House
244 EL 24.4Mtr Toe gurad fixing balance at places
Platform
Bag House
245 EL 24.4Mtr Handrail Touch up painting balance.
Platform
Bag House
246 EL 24.4Mtr House keeping pending at 24.4mtr level.
Platform
Bag House Staircase from 0 level to 24mtr level all landing area toe
247 EL0.0Mtr
Staircase guard fixing balance.
Bag House
248 EL0.0Mtr Staircase hand rail bend portion connection pending.
Staircase