Académique Documents
Professionnel Documents
Culture Documents
INTERNSHIP REPORT
I am Very Thankful to TATA Consulting Engineers Limited for having given me the
opportunity to Undertake my Summer Training at their prestigious office at Sheriff
centre, Bangalore. It was a very good learning experience for me to have worked on
Internship Assignments.
The time I spent in TCE as an intern for two Months was a memorable one for me as
it was rich in Knowledge gaining and helped me discover my potential.
This report would not have been possible without the contribution and collaboration
of others. I would like to express my sincere gratitude towards Mr Suresh
Nagasandra , General Manager – Mechanical and Mr Manu C, Project Manager for
his technical support and constant supervision which contributed immensely to my
personal development. I also thank them for their guidance which was a remarkable
force that enabled me to successfully complete the internship program, I would also
like to thank HR Team Mrs Divya Sonali Minz and Mr Deepak in ensuring my social
and professional integration with TCE staff.
ABSTRACT
Areas of business
TCE offers integrated engineering consultancy services in key industry sectors.
Energy
Power: Generation (fossil fuel fired, hydro and renewable energy)
Transmission and distribution
Nuclear energy: Fuel fabrication, spent fuel processing, waste management
Modernisation and plant upgrades
Process
Chemical: Oil and gas, petrochemicals and refineries, food and pharmaceuticals,
chemicals- speciality, agro chemicals and paints, paper and pulp, cement, fertilisers
Steel, metal and mining: Ferrous and non-ferrous metals, geology and mining,
beneficiation, material handling
Infrastructure
Built environment (urban planning, smart cities, manufacturing facilities)
Waste, water and environment
Transportation
Services
Design and engineering, procurement management, project management,
construction management services, safety services
Advanced technologies and special projects
Digital engineering
Engineering solutions in IIOT
Special projects in applied engineering
Opex-related services, annuity-based solutions, renovation and modernisation, plant
asset management solutions, brownfield capacity expansion, outage management,
etc.
Location
TCE has design and project offices in Mumbai, Pune, Gandhinagar (Gujarat), Delhi
NCR, Jamshedpur, Kolkata, Bengaluru, Chennai, New Jersey (USA), Abu Dhabi,
Kenya, Ethiopia, Nepal and the Netherlands.
AS
SIGNME
1. Study of A Guide to The Project Management Body of Knowledge
Summary
Project management has been proven to be the most effective method of delivering
products within cost, schedule, and resource constraints.
This Book gave a detailed explanation of how to identify and manage the product
scope, build a work breakdown structure, create a project plan, create the project
budget, define and allocate resources, manage the project development, identify and
manage risks, and understand the project procurement process.
This Book gave a detailed knowledge of the following:
Identify the key characteristics of a project
Learning Outcome
It covers bodies of knowledge, things we should think about when we're running the
project. Within each body of knowledge there are processes we should consider
following. And each process has inputs, tools and techniques, an output. And all the
way through, all the way through this book, once we get beyond the first three
chapters, that's how it works. it's really important to understand that secret. Because,
understanding the relationships between those processes and the inputs, and the
tools, and the techniques, and the outputs. Those are some of the keys to how we
successfully run our projects.
First I will list out what are all the Important things in Project planning and
Scheduling that I learnt
3. Project Scheduling
– Breaking down the scope of work into manageable portions; namely its
activities.
– Estimating each activity duration
– Establishing sequence relationships among activities.
– Finding the earliest and latest possible times for the execution of each activity.
– Looking up the project’s critical sequence of activities.
– Reviewing, optimizing, communicating, updating, and in general, using the
Schedule.
Learning Outcome
LEARNING OUTCOME
Did the Work Breakdown Structure of Technical Report Of 300MW Coal Fired Power
Plant at MAAMBA, Zambia.
I was assigned to study two Projects, the first project was MAPNA Power plant, the
project was the Construction of 500 MW Combined Power Plants, The location of the
project was Iran, The organisation of the Project was TCE and MAPNA group. I have
prepared a detailed Technical Project Synopsis which is attached along this report,
the second Project which I was Assigned was of MAAMBA Collieries Limited, the
Project Title was 300MW Coal Fired Power Plant at Maamba, Zambia. The
Organisations Involved in this Project were Maamba Collieries Limited, M/S SEPCO
Electric Power Corp, M/S TATA Consultancy Engineers Limited, M/S Shandong
Electric Power Engineering Consulting Institute Corp. I have prepared a detailed
Project Synopsis for this Project attached along with this Report.
MAAMBA COLLIERIES LIMITED DRAFT REPORT
PROJECT Information
Actual Weighted
Schedul Weighted
Sl. % Weight Schedule
Package e% Actual %
no Progres age %
Progress Progress
s Progress
TOTAL 100% 100% 99.17%
1 Engineering 100.00% 95.00% 10% 10% 9.50%
Procurement ,
2 Manufacturing & 100.00% 99.99% 69% 69% 68.99%
Delivery
Construction &
3 100.00% 99.59% 16% 16% 15.93%
Erection
4 Commissioning 100.00% 94.93% 5% 5% 4.75%
2 PROJECT S CURVE
MILESTONE SCHEDULE
3. Civil Construction 14Th Jul 13 14th Oct 14 29th Sep 29th Dec
Drawing Completion 15 15
4. Mechanical Erection 4th Aug 13 14th Oct 14 20th Sep 29th Dec
Drawing Completion 15 15
5. Electrical Drawing 23rd Jul 13 25th Sept 5th Aug 15 5th Aug 15
Completion 14
4. Hydraulic Test 28th Mar 14 20th Feb 15 18th Jan 15 18th Jan 15
5. Chimney ready for LUP 1st Jun 14 2nd May 15 26th Nov 02nd Feb
15 16
Sl. MILESTONES Scheduled Schedule Schedule Schedule Remarks
Date d Date d Date d Date
No
SEPCO
. (As per L3 (As per L3 (As per L3
MPR-
Schedule) Schedule Schedule
Jun 17
Baseline Baseline 1 Baseline 2
Actual/
(Jul 2012) (Jun 2014) (Aug 2015)
Expected
E COMMISSIONING & STARTUP ACTIVITIES
1. DCS Readiness 14th Feb 14 10th Jan 15 22nd Nov 18th Jan 16
15
2. IDCT trial run 10th Mar 14 14th Apr 15 17th Dec 03rd Jun 16
15
3. DM water Available 26th Mar 14 15th Feb 15 20th Jan 16 09th Apr 16
5. CW System Readiness 3rd April 14 30th May 2nd Jan 16 22nd Apr 16
15
6. Boiler First light Up 17th Jul 14 3rd Jul 15 1st Apr 16 07th Aug 16
7. Steam Blowing 19th Jul 14 18th Jul 15 16th Apr 16 13th Aug 16
8. TG on Barring Gear 14th Aug 14 24th Jul 15 28th Apr 16 04th Aug 16
9. Rolling of Turbine 20th Aug 14 6th Aug 15 4th May 16 23rd Jul 16
10. Synchronization 24th Aug 14 7th Aug 15 5th May 16 24th Jul 16
11. Trial Operations 25th Aug 14 6th Sept 15 7th June 16 19th Aug 16
12. Provisional performance 27th Oct 14 10th Oct 15 31st Jul 16 15th Feb 17
guarantee test and
provisional performance
acceptance
2.2 MILESTONE SCHEDULE FOR MAIN PLANT & BOP – UNIT 2
1. DCS Readiness 13th May 14 1st Mar 15 1st Jan 16 18th Jan 16
2. IDCT trial run 15th Jun 14 18th Apr 17th Dec 03rd Jun 16
15 15
3. CW System readiness 28th June 14 30th May 1st Jan 16 23rd May
15 16
Scheduled Schedule Schedule Schedule Remarks
Date d Date d Date d Date
SEPCO
Sl. (As per L3 (As per (As per L3
MILESTONES MPR -
Schedule) L3 Schedule
No
Schedule Jun 17
. Baseline Baseline
Baseline 2 Actual/
(Jul 2012
1
(Aug Expected
2015)
4. Boiler first light Up 16th Oct 14 4th Aug 15 17th Apr 16 09th Jun 16
5. Steam Blowing 19th Oct 14 19th Aug 1st April 16 07th Aug
15 16
6. TG on Barring Gear 12th Nov 14 31st Aug 28th Apr 16 04th Aug
15 16
7. Rolling of Turbine 18th Nov 14 8th Sept 4th May 16 26th Aug
15 16
10. Provisional performance 25th Jan 15 10th 31st Jul 16 23rd Feb
guarantee test and Nov15 17
provisional performance
acceptance
2. Steel Tower Assembly & Erection 16th Sept 2013 20th Aug 14
start
Sl. Scheduled Scheduled Date Remarks
MILESTONES
Date (As per EPCO MPR
No
L2
. Actual/Expected
Schedule)
3. Transmission Conductor pulling 20th Dec 2013 10th Dec 15
complete
1. Erection of Pontoon 30th Sep 25th Nov 14 10th Oct 15 10th Oct 15
Arrangement 2013
2. Completion of laying MS 13th Feb 19th Dec 14 5th Sept 15 5th Sept 15
pipe& testing 2013
3. Construction of raw 7th Nov 2013 21st Nov 13 21st Nov 15 21st Nov 15
water reservoir
4. Trial operation & PG test 29th Mar 30th Jan 5th Jan 16 24th Jul 16
2014 15
1 ENGINEERING
Weighte
Sl
Schedule d Actual
. Actual% Weighta
Package % %
N Progress ge
Progress Progres
o.
s
PROCUREMENT,
MANUFACTURING & 100.0% 99.99%
DELIVERY
1 Main Plant & BOP 100.00% 99.99% 85.50% 85.49%
2 330 kV Transmission Line 100.00% 100.00% 5.80% 5.80%
Kariba Lake Water Intake
3 100.00% 100.00% 8.70% 8.70%
System
2.2 ORDERS PLACED DURING THE MONTH
Sl.
Schedule
N PACKAGE ORDERED Actual Name of Vendor
d
o.
I Main Plant & BOP Nil Nil
II 330 kV Transmission Line Nil Nil
Kariba Lake Water Intake
III Nil Nil
System
Sl.
Scheduled
No ITEMS STARTED/COMPLETED Actual Finish
Finish
.
I Main Plant & BOP
II 330 kV Transmission Line
III Kariba Lake Water Intake System
3 PROJECT CONSTRUCTION& ERECTION
Reviewed 1"C"
ScopeOriginal
ScopeRevised
drawingsTotal no c. of
Reviewed 3"C"
drawingsTotal
'A'/ 'G'Approved in
"B" Approved in
PACKAGE
Sl.
No.
Reviewed 2"C"
Reviewed 1"C"
ScopeOriginal
ScopeRevised
drawingsTotal
'A'/ 'G'Approved in
"B" Approved in
Reviewed 3"C"
PACKAGE
Sl.
No.
Structure +
Hydraulic
Structures)
8 Mechanical 505 1027 1027 1027 1027 0 0 0 0
9 Electrical 620 1019 1019 1019 1019 0 0 0 0
10 Instrument &
478 794 794 794 794 0 0 0 0
Control
11 Coal Handling
140 445 445 445 445 0 0 0 0
System
12 Ash Handling
132 256 256 256 256 0 0 0 0
System
13 Water System 227 549 549 549 549 0 0 0 0
14 HVAC 155 236 236 236 236 0 0 0 0
15 Chemical 134 340 340 340 340 0 0 0 0
16 Telephone Line /
42 78 78 78 78 0 0 0 0
Communication
17 Commissioning
2 55 55 55 55 0
Procedures
18 Project
21 21 21 21 21
Management
19 Review of EPC
Contractors Monthly 36 36 36 36 0 0 0
Reports
330kV
II 78 95 95 95 95
Transmission
Kariba Lake Water
III 175 443 443 384 384
Pumping System
IV Buildings
V Colony
TOTAL 4032 8515 8515 8456 8456 0 0
BOP
Ash Cooler, Bucket Chain Conveyor, Bucket Elevator, Drag Chain Conveyor of
Boiler#1 has been completed.
ESP#1 Rectifier Transformer Cable Laying, Testing (OC, SC Testing) has been
Completed.
FA Silo MCC A&B Installation, Testing and commissioning has been completed
CHP
TT-01, 02, 03, Coal Yard PC-A&B, CHP Complex Building, Primary Crusher,
Primary Screen, Secondary Crusher, Secondary Screen MCC-A&B Installation
and Testing, Charging has been completed.
Trail Run of CHP Motors, 3B, 6A, 6B, 4A, 4B, 5A, 5B, 7A, and 7B has been
completed.
Reservoir - RWPH
Lighting installation & Fire alarm and detection installation has been completed.
330kV Switchyard
Testing of BAY-1 Equipment’s, Relays at NCB has been completed.
SCADA Configuration and communication with Muzuma Relays has been
through
C&I work
Unit#01
Anti-Climbing device, Circuit & Name plate, Phase identification, Warning boards
installation has been completed