Vous êtes sur la page 1sur 3

Nominated or Named?

Brian E. Rawling, Brian E. Rawling & Associates (BERA)

Nominated subcontractors are often closely Standard Form of Building Contract


aligned with the consultants assisting in provides:-
design and overcoming co-ordination and
technical problems arriving at an end "Provided that the Architect shall not
product which is aesthetically and nominate any person as a subcontractor
functionally what a consultant requires. against whom the Main Contractor shall
Nominated subcontractors are often make reasonable objection".
involved in a project before the main
contractor is appointed and the project is Therefore, a main contractor's objection to
often designed around a nominated an architect's nomination proposal only has
subcontractors' features, e.g. lift shaft sizes, to be "reasonable" for him to succeed with
curtain walling features and the like. an objection.

Clause 27 of the HKIA Standard Form of Vetting a Nomination Proposal


Building Contract deals with nominated
subcontractors. This form of contract was A prudent main contractor will carefully
based upon the UK JCT 63, which itself was inspect an architect's nomination proposal
based upon earlier RIBA standard forms of and investigate the proposed nominated
contract. Nominated subcontracting, subcontractor. Programme and performance
therefore, has a long history. obligations are obvious aspects to check but
also the proposed nominated subcontractor's
Reasonable Objection financial standing is an important aspect to
be investigated.
In traditional main contract tenders,
nominated subcontract works will form the BERA have recently had to advise main
subject of a description of a prime cost sum contractor clients to also investigate the
and some preliminary drawings may be financial viability of the proposed
provided. Main contract tenderers, subcontract price to determine if the
therefore, have little information concerning proposed nominated subcontractor can
the nominated subcontract works and yet, actually carry out the tendered work
increasingly, main contract tenderers are profitably as an unprofitable subcontractor
being required to take on liabilities such as is far more difficult to deal with (and can go
design, fitness for purpose and even the into bankruptcy) than a profitable
risks of performance by the unknown, yet to subcontractor.
be nominated, subcontractor. Once a main
contractor has accepted the architect's There are many justifiable reasons that a
nomination proposal he becomes main contractor can put forward to reject an
responsible for that subcontractor, just as he architect's nomination proposal. Take for
would his own domestic subcontractors example, a nomination proposal for a
(excepting an obligation to re-nominate in curtain walling subcontract which the main
certain circumstances). Therefore, a fair contractor has investigated and found the
contract should provide protection for the proposed nominated subcontractor to be
main contractor and allow him to insist financially insecure and, in addition, the
upon certain conditions and requirements proposed nominated subcontractor reduced
when the architect issues his nomination his initial tender price by 20% with no
proposal. Clause 27(a) of the HKIA reduction in work content or specification.
A main contractor would be fully justified
in objecting to a nomination proposal if been accepted, the subcontract awarded and
such circumstances occurred (and they do work commenced, the main contractor
occur frequently) or if he felt that the complains that the nominated subcontractor
proposed tender sum was too low. is failing to perform. He issues notices
under clause 20 of the RICS standard form
Then what happens if, for instance, an of nominated sub-contract, the
architect has used the curtain walling subcontractor's performance does not
subcontractor's preliminary design for improve, so the main contractor determines
structural design, aesthetic appearance, the subcontractor's employment. When this
interface arrangements or any number of occurs, the employer has to procure that his
other arrangements? architect re-nominates another subcontractor
to complete the outstanding works by a date
In such circumstances, the contractor has a which will enable the main contractor to
strong bargaining position. A skillful main complete the main contract works by the
contractor can obtain indemnities and original date for completion. Delays will
waivers from the employer on the basis that occur in the re-nomination process and time
if he refuses the nomination proposal on could be rendered at large if there is an
valid grounds then the project could grind to unavoidable delay to completion of the main
a halt. Where a main contractor has valid contract works. Whatever else happens, the
grounds for objection, and insists upon his employer will incur additional expense.
rights, then an employer will have to
provide whatever indemnities and waivers Named SubContracting
are negotiable otherwise he will incur even
more expense if he elects for determination It was due to such risks that in the late
of the main contractor's employment under 1980's, Swire Properties Limited introduced
the contract. into its contracts the concept of named
subcontracting, to replace traditional
No Right to Object nominated subcontracting with its potential
risks to an employer.
Incidentally, if clause 27(a) of the HKIA
Standard Form of Building Contract has The named subcontracting concept requires
been amended to delete the main names of would-be subcontractors to be
contractor's right to raise reasonable furnished at the main contract tender stage
objection, then the architect's nomination by the consultants, for the main contractor
proposal will almost certainly be construed to issue tender enquiries and for him to
as a warranty at law that the proposed select the proposed named subcontractor.
nominated subcontractor is capable of Further, after the award of the subcontract,
performing the subcontract works as the named subcontractor is treated like any
provided in clause 27. If the nominated other domestic subcontractor and the
subcontractor then fails, the main contractor employer/architect have no obligation to re-
could claim against the employer for nominate.
misrepresentation by his agent, the architect.
Therefore, any loss incurred by the main Main Features
contractor could be recoverable from the
employer. The main features of named subcontracting
are:
Failure to Perform
• The tender documents include lists of
In another scenario of potential risk to an the names of potential named
employer, after the nomination proposal has subcontract tenderers. Main contract
tenderers have the opportunity to object • The main contractor is only paid the
to any named subcontractor on the list of rates in the accepted subcontract or
proposed named subcontract tenderers, lowest tender even if he has to find a
but that objection must be made at replacement subcontractor.
tender stage. • There is no obligation on an employer or
• Main contractors lead the named an architect to re-nominate.
subcontract tender process, for each
named subcontract package the main Since its introduction in the late 1980's,
contractor assembles the tender Swire Properties Limited have successfully
documents (including programme used the named subcontracting policy on all
requirements and their own conditions), of its traditional contracts, although some
issues tender documents, receives the fine-tuning of the provisions for named
tenders, reviews tenders, holds post subcontracting were made to allow an
tender meetings and makes a proposal to architect to select a tenderer, rather than
the architect if any tenderer, other than allow a main contractor to make proposals.
the tenderer who submitted the lowest
price, is to be appointed. However, whichever concept is adopted,
• The Architect has a right to veto any nominated or named, both an employer's
proposed appointment and can issue an and a main contractor's profitability are
instruction to the main contractor to compromised by a subcontract tenderer who
accept any of the tenderers. makes promises he cannot possibly achieve.
• After the nominated subcontract is The time for careful diagnosis is prior to
awarded, the named subcontractor is, for acceptance.
all intents and purposes, a domestic
subcontractor. (adopted from the HKIS Newsletter 10(5)b June
2001)

Vous aimerez peut-être aussi