Académique Documents
Professionnel Documents
Culture Documents
PROJECT : 0 OWNER : 0
LINE UNIT OF
No. I T E M MEA- QUANTITY
SURE
D. EQUIPMENT
Tower Crane unit 1.000 12,000.00
Excavator unit 1.000 12,000.00
Grader unit 1.000 12,000.00
Crane unit 1.000 12,000.00
Bulldozer unit 1.000 3 5 000 x Nos. of Mos. 12,000.00
Road Roller unit 1.000 12,000.00
Payloader unit 1.000 12,000.00
DumpTruck unit 1.000 12,000.00
Generator unit 1.000 12,000.00
Dewatering unit 1.000 12,000.00
120,000.00
E. CONSTRUCTION STAFF 1-PE x 20 K x Nos. of Mos.
Project Engineer mo 1.000 1-Asst PE x 20 K x Nos. of Mos. 120,000.00
Bodegero / Timekeeper mo 1.000 2 WM x 12 K x Nos. of Mos. 90,000.00
210,000.00
Security Guard shift 1.000
4 SG x 15 000 x Nos. of Mos. 150,000.00
LINE UNIT OF
No. I T E M MEA- QUANTITY
SURE
LINE UNIT OF
No. I T E M MEA- QUANTITY
SURE
2 Permits 283,408.00
5 Temporary Facilities
Field office
Warehouse and Storage
Fabrication Shed
Barracks/ Mesh Halls
Temporary Fence
Temporary Toilet
Billboards & Signages
204,000.00
6 Security / Safety / Protection 170,000.00
7 Survey -
1,725,508.00
LINE UNIT OF
No. I T E M MEA- QUANTITY
SURE
A EARTHWORKS
6 GRAVEL BED
Slab on Fill ( Mech'l ) m3 1.00 570.00 70.00
Footing Pits ( Manual ) m3 1.00 570.00 131.00
7 BASE COURSE w/ COMPACTION Quantities must have the corresponding swell factors.
Driveway, Base course (Mech'l) m3 1.00 510.00 64.00
Sidewalk, Base course (Manual) m3 1.00 510.00 131.00
Sub-base COURSE w/ Binder ( Mech'l ) m3 1.00 300.00 64.00
8 FILLING MATERIALS w/ COMPACTION Quantities must have the corresponding swell factors.
Selected Fill- Crushed Rock, (Mech'l) m3 1.00 200.00 64.00
Selected Fill- Escombro/Lastillas, (Mech'l) m3 1.00 329.00 64.00
Common Fill- Excavated , (Mech'l) m3 1.00 120.00 64.00
9 VAPOR BARRIER
6 Mils PE Sheet m2 1.00 15.00 3.00
Area must have an allowance of 3% for Lapping & Wastage
Structural
Prepared by Ricky Page 5
UNIT COST OF CIVIL& STRUCTURAL WORKS
PROJECT : - OWNER : -
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST
No. I T E M MEA- QUANTITY
SURE UNIT TOTAL UNIT TOTAL
11 RC PIPE LAYING
B CONCRETE WORKS ( Cost of Cement in Bulk* CF + Batching Fee with Sand & Gravel )
CONCRETING ( 3% Wastage for Footing & FTB, rest
2%)
No additional Cost up to 5th Level
1 6,000 PSI Cement Factor
Footing / FTB m3 1.00 17.00 3,986.10 220.00
Columns m3 1.00 18.00 4,120.80 850.00
Mezz Beams & Slab m3 1.00 18.00 4,120.80 220.00
Ramps m3 1.00 18.00 4,120.80 220.00
Mid Beams m3 1.00 18.00 4,120.80 850.00
Gutter/Parapet/Corbel/Rbeam m3 1.00 18.00 4,120.80 1,250.00
Stairs m3 1.00 18.00 4,120.80 1,300.00
1 5,000 PSI Cement Factor
Footing / FTB m3 1.00 15.00 3,635.90 220.00
Columns m3 1.00 16.00 3,774.00 850.00
Mezz Beams & Slab m3 1.00 16.00 3,774.00 220.00
Ramps m3 1.00 16.00 3,774.00 220.00
Mid Beams m3 1.00 16.00 3,774.00 850.00
Gutter/Parapet/Corbel/Rbeam m3 1.00 16.00 3,774.00 1,250.00
Stairs m3 1.00 16.00 3,774.00 1,300.00
2 4,000 PSI Cement Factor
Footing / FTB m3 1.00 11.75 3,066.83 220.00
Columns m3 1.00 12.75 3,210.45 850.00
Mezz Beams & Slab m3 1.00 12.75 3,210.45 220.00
Ramps m3 1.00 12.75 3,210.45 220.00
Mid Beams m3 1.00 12.75 3,210.45 850.00
Gutter/Parapet/Corbel/Rbeam m3 1.00 12.75 3,210.45 1,250.00
Stairs m3 1.00 12.75 3,210.45 1,300.00
RcWall m3 1.00 12.75 3,210.45 850.00
3 3,000 PSI
Footing / FTB m3 1.00 9.00 2,585.30 220.00
Columns m3 1.00 10.00 2,733.60 850.00
Mezz Beams & Slab m3 1.00 10.00 2,733.60 220.00
Ramps m3 1.00 10.00 2,733.60 220.00
Mid Beams m3 1.00 10.00 2,733.60 850.00
Gutter/Parapet/Corbel/Rbeam m3 1.00 10.00 2,733.60 1,250.00
Stairs m3 1.00 10.00 2,733.60 1,300.00
RcWall m3 1.00 10.00 2,733.60 850.00
Driveway m3 1.00 9.00 2,560.20 200.00
4 2,500 PSI 999.60
Slab on Fill / Sidewalk m3 1.00 8.00 2,410.20 200.00
Curb and Gutter m3 1.00 9.00 2,585.30 250.00
Structural
Prepared by Ricky Page 6
UNIT COST OF CIVIL& STRUCTURAL WORKS
PROJECT : - OWNER : -
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST
No. I T E M MEA- QUANTITY
SURE UNIT TOTAL UNIT TOTAL
C REBAR WORKS
Labor Cost plus 50 Cents every floor level staring 3/F
D FORMWORKS
Labor Cost plus 5 % every floor starting 3rd level
1 Footing m2
Ply wood 1/2' Ord. pc 0.50 480.00 240.00
Coco Lumber, Class A BF 16.40 13.50 221.40
CW Nail kg 0.30 33.00 9.74
Tie Wire roll 0.00 1,312.50 5.38
Form Oil li 0.13 33.00 4.29
480.81
Structural
Prepared by Ricky Page 7
UNIT COST OF CIVIL& STRUCTURAL WORKS
PROJECT : - OWNER : -
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST
No. I T E M MEA- QUANTITY
SURE UNIT TOTAL UNIT TOTAL
Wastage ( 3%) 495.24
2-3 Uses 165.08 180.00
2 Slab On Fill lm
Ply wood 1/2' Ord. pc 0.13 480.00 62.40
Coco Lumber, Class A BF 10.00 13.50 135.00
CW Nail kg 0.18 33.00 5.94
Tie Wire roll 0.00 1,312.50 3.28
Form Oil li 0.13 33.00 4.29
210.91
Wastage ( 3%) 217.24
2-3 Uses 217.24 120.00
3 Suspended Slab m2
Phenolic 1/2' pc 0.50 1,400.00 700.00
Coco Lumber, Class A BF 25.00 13.50 337.50
CW Nail kg 0.45 31.00 13.95
Tie Wire roll 0.01 1,312.50 8.20
Form Oil li 0.13 33.00 4.29
1,063.94
Wastage ( 3%) 1,095.86
2-3 Uses 365.29 200.00
4 Beams m2
Phenolic, 1/2 pc 0.50 1,400.00 700.00
Coco Lumber, Class A BF 34.00 13.50 459.00
CW Nail kg 0.61 33.00 20.20
Tie Wire roll 0.01 1,312.50 11.16
Form Oil li 0.13 33.00 4.29
1,194.64
Wastage ( 3%) 1,230.48
2-3 Uses 410.16 200.00
5 Columns m2
Phenolic, 1/2 pc 0.50 1,400.00 700.00
Coco Lumber, Class A BF 33.00 13.50 445.50
CW Nail kg 0.59 33.00 19.60
Tie Wire roll 0.01 1,312.50 10.83
Form Oil li 0.13 33.00 4.29
1,180.22
Wastage ( 3%) 1,215.63
2-3 Uses 405.21 200.00
6 RC Walls m2
Phenolic, 1/2 pc 0.50 1,400.00 700.00
Coco Lumber, Class A BF 19.00 13.50 256.50
CW Nail kg 0.34 33.00 11.29
Tie Wire roll 0.00 1,312.50 6.23
Structural
Prepared by Ricky Page 8
UNIT COST OF CIVIL& STRUCTURAL WORKS
PROJECT : - OWNER : -
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST
No. I T E M MEA- QUANTITY
SURE UNIT TOTAL UNIT TOTAL
Form Oil li 0.13 33.00 4.29
978.31
Wastage ( 3%) 1,007.66
2-3 Uses 335.89 180.00
7 Stairs m2
Ply wood 1/2' Ord. pc 0.50 480.00 240.00
Coco Lumber, Class A BF 35.00 13.50 472.50
CW Nail kg 0.63 33.00 20.79
Tie Wire roll 0.01 1,312.50 11.48
Form Oil li 0.13 33.00 4.29
749.06
Wastage ( 3%) 771.54
2-3 Uses 257.18 300.00
8 Corbel / Gutter m2
Ply wood 1/2' Ord. pc 0.50 480.00 240.00
Coco Lumber, Class A BF 30.00 13.50 405.00
CW Nail kg 0.54 33.00 17.82
Tie Wire roll 0.01 1,312.50 9.84
Form Oil li 0.13 33.00 4.29
676.95
Wastage ( 3%) 697.26
2-3 Uses 232.42 300.00
Structural
Prepared by Ricky Page 9
Labor Cost References
5, 2009
TOTAL
188.00 188.00
207.00 207.00
64.00 64.00
62.00 62.00 40.00 100.00 100.00
120.00 120.00
80.00 80.00 20.00
40.00
60.00
Structural
Prepared by Ricky Page 10
Labor Cost References
5, 2009
TOTAL
Structural
Prepared by Ricky Page 11
Labor Cost References
5, 2009
TOTAL
2,660.20 210.00 180.00
3,110.20 500.00 500.00 500.00 150.00
255.00
140.00 140.00
45.00 45.00
60.00 60.00 60.00
70.00 70.00 60.00
200.00
30.00 30.00
Structural
Prepared by Ricky Page 12
Labor Cost References
5, 2009
TOTAL
Structural
Prepared by Ricky Page 13
Labor Cost References
5, 2009
TOTAL
Structural
Prepared by Ricky Page 14
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
MASONRY WORKS
CHB LAYING : 8" (w/o plastering) m2
8" x 8" x 16" CHB pcs 12.50 31.50 393.75
1:3 mix, Cement bag 0.55 180.00 99.00
Sand m3 0.05 660.00 33.00
Total cost per sq.m. P 525.75
Wastage of 3% lot 1.00 15.77
Total cost per sq.m. w/ wastage P 541.52
Rebars, 12 mm dia. (.60m Vert) kg 1.89 36.03 68.14 4.00 7.57 75.71
Rebars, 10 mm dia. (.60m Hor.) kg 1.32 36.03 47.71 4.00 5.30 53.01
Cost of Rebars per sq.m. P 115.85
Total cost per sq.m. w/ wastage & rebars P 657.38 110.00 767.38 118.00
Architectural
Prepared by Ricky Page 15
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
CONCRETE TOPPING
CONCRETE TOPPING 75 MM THK. m2
Thickness, 1:3 mix mm 75.00
Cement bag 0.90 180.00 162.00
Sand m3 0.08 660.00 49.50
Ga.10, 4"x4" w.w.mesh sht 0.12 450.00 54.00
Total cost per sq.m. P 265.50
Wastage of 3% lot 1.00 7.97
Total cost per sq.m. w/ wastage P 273.47 110.00 383.47 70.00
FLOOR FINISHES
STRAIGHT TO FINISH m2
Total cost per sq.m. 60.00 60.00 60.00
Architectural
Prepared by Ricky Page 16
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
Total cost per sq.m. P 147.30
Wastage of 3% lot 1.00 4.42
Total cost per sq.m. w/ wastage P 151.72 72.00 223.72 72.00
Architectural
Prepared by Ricky Page 17
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
Architectural
Prepared by Ricky Page 18
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
Heavy trafic kg 5.00 141.67 151.67
Extra Heavy Traffic kg 6.00 170.00 10.00 180.00
CONTROL JOINTS
CONTRACTION JOINTS l.m.
Bostik " Seal N Flex" Sealant tube 420.00
l.m. 1.00 93.33 93.33 5.00 5.00
Soft Cut/ Saw Cut l.m. 1.00 25.00 25.00 25.00
TOTAL COST PER L.M. 93.33 30.00 123.33
WALL FINISHES
Architectural
Prepared by Ricky Page 19
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
Adhesive, ABC kg 5.00 8.96 44.79
Grout, ABC kg 0.30 25.00 7.50
Thickness, 1:3 mix, Mortar mm 20.00
Cement bag 0.24 180.00 43.20
Sand m3 0.02 660.00 13.20
Total cost per sq.m. P 497.58
Wastage of 3% lot 1.00 14.93
Total cost per sq.m. w/ wastage P 512.51 210.00 722.51 262.00
CEILING FINISHES
Architectural
Prepared by Ricky Page 20
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
Architectural
Prepared by Ricky Page 21
Labor Cost References
ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction
Architectural
Prepared by Ricky Page 22
Labor Cost References
ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction
56.00 120.00
- - 60.00
Architectural
Prepared by Ricky Page 23
Labor Cost References
ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction
56.00
150.00 200.00
Architectural
Prepared by Ricky Page 24
Labor Cost References
ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction
100.00 200.00
Architectural
Prepared by Ricky Page 25
Labor Cost References
ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction
7.00 20.00
15.00
Architectural
Prepared by Ricky Page 26
Labor Cost References
ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction
Architectural
Prepared by Ricky Page 27
Labor Cost References
ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction
Architectural
Prepared by Ricky Page 28
PAINTING SYSTEM COST BY BOYSEN
As of August 2006
PRICE RANGE
PAINT SYSTEM
PER SQUARE METER
Roofing
Roof Guard P 160.00 - P 165.00
Metal Surfaces
Quick Drying Enamel System w/ B-370 P 135.00 - P 140.00
Quick Drying Enamel System w/ B-320 P 132.00 - P 140.00
Quick Drying Enamel System w/ B-4310 P 120.00 - P 125.00
Acqua Epoxy System ( Green ) P 255.00 - P 265.00
Acqua Epoxy System ( Other Color ) P 240.00 - P 250.00
Epoxy Enamel ( White & Red ) P 265.00 - P 275.00
Epoxy Enamel ( Other Color) P 240.00 - P 250.00
Plastering
Skimkote ( No Top Coat ) P 100.00 - P 105.00
P Li P
Oil : 1705.00 x 0.50 = 852.50
Li Hr. Li
P
1220.30
Li
P m3 Hr. Hr. P
= 1220.30 div 20.00 x 8.00 div 7.00 = 69.73
Li Hr. day day m3
P P P
Total EquipCost = 74.29 + 69.73 x 80% = 115.21
m3 m3 m3
Laborer
Labor Cost : U. Rate Productivity
P m3 P
= 300.00 div 1.00 = 300.00
M-D M-D m3
P
Total Labor Cost = 300.00 x 20% = 60.00
m3
P
175.21
m3
EXCAVATION ( Inclined Cut,1.0<H>2.0 m)
P Li P
Oil : 1705.00 x 0.50 = 852.50
Li Hr. Li
P
1220.30
Li
P m3 Hr. Hr. P
= 1220.30 div 18.00 x 8.00 div 7.00 = 77.48
Li Hr. day day m3
P P P
Total EquipCost = 82.54 + 77.48 x 80% = 128.02
m3 m3 m3
ProdRate Page 33
Labor Cost : U. Rate Productivity
P m3 P
Laborer = 300.00 div 0.65 = 461.54
M-D M-D m3
P
Total Labor Cost = 461.54 x 20% = 92.31
m3
P
220.32
m3
P Li P
Oil : 1705.00 x 0.50 = 852.50
Li Hr. Li
P
1220.30
Li
P m3 Hr. Hr. P
= 1220.30 div 15.00 x 8.00 div 7.00 = 92.98
Li Hr. day day m3
P P P
Total EquipCost = 99.05 + 92.98 x 80% = 153.62
m3 m3 m3
P
Total Labor Cost = 461.54 x 20% = 92.31
m3
P
245.93
m3
BACKFILL
Equipment Cost: Rental Rate Productivity Efficiency
P m3 Hr. Hr. P
Backhoe = 1300.00 div 40.000 x 8.00 div 7.00 = 37.14
Hr. Hr. day day m3
Fuel Price Consumption
P Li P
Diesel : 36.78 x 10.00 = 367.80
Li Hr. Li
P Li P
Oil : 1705.00 x 0.50 = 852.50
Li Hr. Li
P
1220.30
Li
ProdRate Page 34
P m3 Hr. Hr. P
= 1220.30 div 40.00 x 8.00 div 7.00 = 34.87
Li Hr. day day m3
P P P
Total EquipCost = 37.14 + 34.87 = 72.01
m3 m3 m3
P Li P
Oil : 1705.00 x 0.50 = 852.50
Li Hr. Li
P
1220.30
Li
P m3 Hr. Hr. P
= 1220.30 div 20.00 x 8.00 div 7.00 = 69.73
Li Hr. day day m3
P P P
Total EquipCost = 24.24 + 69.73 = 93.97
m3 m3 m3
Equipment Cost :
Tamping P P
= 1500.00 = 1500.00
Rammer E-D E-D
P Li P
Fuel = 36.78 x 9.00 = 331.02
Li E-D E-D
Labor Cost :
P M-D P
Operator = 300.00 x 1.00 = 300.00
M-D E-D E-D
P m3 P
2131.02 div 32.00 = 66.59
E-D E-D m3
P
66.59
m3
HAUL OUT
Equipment Cost :
P Hr. P
B'Hoe = 1300.00 x 8.00 x 1.00 = 10,400.00
Hr. Day Day
Dump P Hr. P
= 800.00 x 8.00 x 2.00 = 12,800.00
Truck Hr. Day Day
Fuel
P Li P
Diesel = 36.78 x 10.00 x 8.00 = 2942.40
Li Hr. Day
P Li P
= 36.78 x 10.00 x 8.00 = 2942.40
Li Hr. Day
P Li P
Oil = 1705.00 x 0.50 x 8.00 = 6820.00
Li Hr. Day
ProdRate Page 35
P Li P
= 1705.00 x 0.25 x 8.00 = 3410.00
Li Hr. Day
P
39,314.80
Day
Total P m3
= 39,314.80 div 269.00
Cost Day E-D
P
146.15
m3
GRAVEL BEDDING
P
137.50
m3
SOIL POISONING
Unit Rate Productivity
P m2 P
Labor = 300.00 div 90.00 = 3.33
M-D M-D m2
FORM WORKS
COLUMNS
Unit Rate Productivity
P m2 P
Carpenter = 350.00 div 1.98 = 176.77
M-D M-D m2
ProdRate Page 36
P m2 P
Carpenter = 350.00 div 2.03 = 172.41
M-D M-D m2
CORBEL/GUTTER/RBEAM/ PARAPET
Unit Rate Productivity
P m2 P
Carpenter = 350.00 div 1.25 = 280.00
M-D M-D m2
STAIRS
Unit Rate Productivity
P m2 P
Carpenter = 350.00 div 1.38 = 253.62
M-D M-D m2
REBARS
Grade 33
Unit Rate Productivity
P kg P
Steelman = 350.00 div 65.00 = 5.38
M-D M-D kg
Grade 60
Unit Rate Productivity
P kg P
Steelman = 350.00 div 100.00 = 3.50
M-D M-D kg
Equipment Cost:
ProdRate Page 37
P kg P
992 div 3000 = 0.33
E-D E-D kg
CONCRETING
COLUMNS
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 0.38 = 800.00
M-D M-D m3
BEAMS/ GIRDER
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 0.38 = 800.00
M-D M-D m3
FOOTING/TIE BEAMS
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 1.51 = 198.68
M-D M-D m3
RC WALLS
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 0.37 = 810.81
M-D M-D m3
GUTTERS/PARAPET/ CORBEL/RBEAM
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 0.25 = 1224.49
M-D M-D m3
STAIRS
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 0.25 = 1200.00
M-D M-D m3
ProdRate Page 38
Pouring Crew = 300.00 div 1.60 = 187.50
M-D M-D m3
DRIVEWAY
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 1.75 = 171.43
M-D M-D m3
MASONRY
Below 5m
CHB 8" thk. Unit Rate Productivity
Installation P m2 P
Mason = 350.00 div 4.45 = 78.65
M-D M-D m2
Hauling
Unit Rate Productivity
CHB P m2 P
Helper = 300.00 div 20.00 = 15.00
M-D M-D m2
Mortar P m3 m3 P
Helper = 300.00 div 4.20 x 0.05 = 3.57
M-D M-D m2 m2
Job Mix P m3 m3 P
Helper = 280.00 div 4.20 x 1.05 = 20.00
M-D M-D m2 m2
P
38.57
m2
P
117.22
m2
above 5m
Installation and Hauling Cost Plus P
117.22
m2
Additional Lifting Cost P
11.72
m2
Equipment
P m3 P
Mixer = 20.00 x 0.03 = 0.60
m2 m2 m2
ProdRate Page 39
Helper = 280.00 div 4.20 x 1.05 = 20.00
M-D M-D m2 m2
P
38.57
m2
P
108.57
m2
above 5m
Installation and Hauling Cost Plus P
108.57
m2
Additional Lifting Cost P
10.86
m2
Equipment
P m3 P
Mixer = 20.00 x 0.03 = 0.60
m2 m2 m2
Below 5m
CHB 4" thk. Unit Rate Productivity
Installation P m2 P
Mason = 350.00 div 5.93 = 59.02
M-D M-D m2
Hauling
Unit Rate Productivity
CHB P m2 P
Helper = 300.00 div 20.00 = 15.00
M-D M-D m2
Mortar P m3 m3 P
Helper = 300.00 div 4.20 x 0.05 = 3.57
M-D M-D m2 m2
Job Mix P m3 m3 P
Helper = 280.00 div 4.20 x 1.05 = 20.00
M-D M-D m2 m2
P
38.57
m2
P
97.59
m2
above 5m
Installation and Hauling Cost Plus P
97.59
m2
Additional Lifting Cost P
9.76
m2
Equipment
P m3 P
Mixer = 20.00 x 0.03 = 0.60
m2 m2 m2
P
Equipment = 2.50
m2
ProdRate Page 40
142.50 P
PLASTERING
Exterior Plastering
below 3m
Unit Rate Productivity
P m2 P
Mason = 350.00 div 4.00 = 87.50
M-D M-D m2
Hauling
Mortar P m3 m3 P
Helper = 300.00 div 2.00 x 0.05 = 7.50
M-D M-D m2 m2
Job Mix P m3 m3 P
Helper = 280.00 div 2.00 x 1.05 = 20.00
M-D M-D m2 m2
P
115.00
above 5m m2
P
= 126.50
m2
ProdRate Page 41
Equipment Unit Rate
P m3 P
Mixer = 4.20 x 0.03 = 0.13
m2 m2 m2
TOPPING
Unit Rate Productivity
P m2 P
Mason = 350.00 div 5.00 = 70.00
M-D M-D m2
P m2 P
= 350.00 div 5.33 = 65.63
M-D M-D m2
STRAIGHT TO FINISH
Unit Rate Productivity
P m2 P
Mason = 350.00 div 8.75 = 40.00
M-D M-D m2
VINYL TILES
Unit Rate Productivity
P m2 P
Installer = 350.00 div 6.88 = 50.91
M-D M-D m2
FLOOR TILES
Unit Rate Productivity
P m2 P
Tile Setter = 350.00 div 1.50 = 233.33
M-D M-D m2
WALL TILES
Unit Rate Productivity
P P
Tile Setter = 350.00 div 1.34 = 261.19
M-D M-D m2
TILE TRIM P L.M. P
Tile Setter = 350.00 div 25.00 = 14.00
M-D M-D L.M.
Setting / Installation
ProdRate Page 42
Counter Tops 250 450 Italian Granite - 4500- 5500 / sq.m.
lm lm China Granite - 1500-2500 / sq.m.
Splash Board 250 450 Marbles - 950-1200 / sq.m.
lm lm
Door Closer
Unit Rate Productivity
P set P
Installer = 350.00 div 2.00 = 175.00
M-D M-D set
Indicator Lock
Unit Rate Productivity
P set P
Installer = 350.00 div 3.20 = 109.38
M-D M-D set
Flush Bolt
Unit Rate Productivity
P nos P
Installer = 350.00 div 4.00 = 87.50
M-D M-D nos.
Push Plate
Unit Rate Productivity
P nos P
Installer = 350.00 div 6.00 = 58.33
M-D M-D nos.
ProdRate Page 43
71.26
Concrete Pipe Layer = 300.00 P l.m. = l.m.
div 4.21
M-D M-D
ProdRate Page 44
BASIC
PROJECT : OWNER :
SURE
A Concrete
Batching Fee : cement -excluded
Batching Fee : agreggates -included cu.m. 1.00 980.00
Cement in Bulk bag 1.00 170.00
Cement in Bags bag 1.00 180.00
Sand cu.m. 1.00 660.00
Gravel, G-1 cu.m. 1.00 570.00
Gravel, 3/4 cu.m. 1.00 660.00
Sand , S-1 cu.m. 1.00 500.00
Pump Charge ( per 50 cu.m. ) cu.m. 1.00 200.00
Rubber Filler, 1/2" x 6" l.m. 1.00 80.00
6" Waterstop lm 1.00 350.00
Structural Epoxy sq.m. 1.00 1,400.00
Bostik Sealant, 600 ml - 0.0006 m3 tube 1.00 420.00
Sealocrete, 16 liters ═ 16 000 cc = 1 pail pail 1.00 2,400.00 40 cc per bag of Cement
Sahara, 950 grams/bag bag 1.00 22.00 1 pack per bag of Cement
B Base Preparation
Base Coarse cu.m. 1.00 510.00
Sub Base Coarse cu.m. 1.00 300.00
Selected Fill (Crushed Rock) cu.m. 1.00 200.00
Selected Fill (1 part Escombro, 2 parts Lastillas) cu.m. 1.00 329.00
Common Fill ( Excavated Soil Mat'ls.) cu.m. 1.00 120.00
C Masonry Works
CHB, 4" Load Bearing ( 700 psi) pc 1.00 19.50
CHB, 6" Load Bearing( 700 psi ) pc 1.00 21.00
CHB, 8" Load Bearing( 700 psi ) pc 1.00 31.50
Louver Blocks, 6 x 6 x 12" pc 1.00 15.00
CHB, 4" Non-Load ( 400 psi ) pc 1.00 14.20
CHB, 6" Non-Load ( 400 psi ) pc 1.00 17.50
Ga.10, 4"x 4" w.mesh, 6'x20' sht 1.00 950.00
6"x 6" x 5.5 mm w.mesh, 6'x20' sht 1.00 450.00
Colored Cement kg 1.00 35.00
Pebbles # 10 sack 1.00 90.00 1-1/2 pail = 1 sack = 1 cu.ft.
Grinding Disc, 7" pc 1.00 85.00
D Civil Works
Soil Poisoning sm 1.00 65.00
MaterialBasicCost
Prepared by Ricky Equipt.Rates Page 45
Wages
BASIC
PROJECT : OWNER :
SURE
MaterialBasicCost
Prepared by Ricky Equipt.Rates Page 46
Wages
BASIC
PROJECT : OWNER :
SURE
Floor Hardener ( Natural Florgard, 30 kg/bag) bag 1.00 850.00 4kgs/sm. - medium
5kgs/sm. - heavy
6kgs/sm. - extra heavy
Carborandum Strips lm 1.00
F Carpentry
Prevailing
G Rebars Base Price Plus/Minus (%)
Price
Grade 33 kg 1.00 20.00 28.03
Grade 40 kg 1.00 21.90 1.28 28.03
Grade 60 kg 1.00 22.60 1.26 28.48
Delivery Charge ton 1.00 370.00 370.00
Ga. 16 Tie Wire ( PhP 35@ 37.5 kg per roll ) roll 1.00 1,312.50 1,312.50
I Hardwares
(Yale) (Schlage)
Med Heavy Med Heavy
Lockset, Metal Door pc 1.00 2,500.00 5,500.00 3,000.00 8,300.00
Lockset, Wooden Door pc 1.00 900.00 2,300.00 3,000.00
Door Closer pc 1.00 1,500.00 3,700.00
Panic Device pc 1.00 2,500.00 9,500.00
Loose Pin Hinges, 3-1/2 x 3-1/2 pc 1.00 75.00 217.50
Loose Pin Hinges, 4" x 4" pc 1.00 125.00
Kick Plates, Stainless pc 1.00 975.00
Stainless Grab Bar,6 ft. pc 1.00 6,600.00
Floor & Wall Stops ( Ives) pc 1.00 200.00
Push Plates ( Hager ) pc 1.00 570.00
Flush Bolts ( Hager ) pc 1.00 345.00
J Plumbing Fixtures
Wooden Mouldings and Cornices
1x3 l.f. 1.00 11.50
1x4 l.f. 1.00 15.50
1x6 l.f. 1.00 24.20
K Paints
MaterialBasicCost
Prepared by Ricky Equipt.Rates Page 47
Wages
BASIC
PROJECT : OWNER :
SURE
L Forms
1/2" Thk . Ordinary Plywood pc 1.00 480.00
3/4 " Thk. Ordinary Plywood pc 1.00 750.00
1/2 " Thk Phenolic Board pc 1.00 1,400.00
3/4 " Thk. Phenolic Board pc 1.00 1,850.00
CW Nails
2" kg 1.00 33.00
3" kg 1.00 31.00
4" kg 1.00 30.00
Concrete Nail 3" kg 1.00 50.00
Form Oil kg 1.00 33.00
Coco Lumber Class B Class A
2x3 BF 1.00 11.50 13.50
2x4 BF 1.00 10.50 13.50
MaterialBasicCost
Prepared by Ricky Equipt.Rates Page 48
Wages
BASIC
PROJECT : OWNER :
SURE
MaterialBasicCost
Prepared by Ricky Equipt.Rates Page 49
Wages
WORK DIVISION FOR ESTIMATES
a ARCHITECTURAL WORKS ( Quantity Take-Off ) - One (1) Estimator
1.0
1.00 SITE WORKS
1.01 Excavation
Machine Excavation
Sand 0.800 m-h/cm
Soil 1.100 m-h/cm
Granular Back Fill 1.200 m-h/cm
Granular Soil Back Fill 1.500 m-h/cm 2.0
Manual Excavation
Sand 4.000 m-h/cm
Soil 6.500 m-h/cm
Backfill 5.500 m-h/cm
1.02 Site Grading Manual 1.300 m-h/cm
1.03 Fine Grading & Finishing 3.0
1.04 Paving & Surfacing
Finishing Soil Surface 1.550 m-h/sm
Road Works
Base Course 0.120 m-h/sm
Curb & Gutter 1.500 m-h/sm
Concrete Road
4" thk. Road 1.300 m-h/sm
6" thk. Road 1.400 m-h/sm 4.0
8" thk. Road 1.500 m-h/sm
Trowel Finish 0.320 m-h/sm
Special Topping
4" thk. Stone or Gravel Road 0.320 m-h/sm
6" thk. Stone or Gravel Road 0.400 m-h/sm
8" thk. Stone or Gravel Road 0.520 m-h/sm 5.0
Asphalt Paving
Fine Grading 0.400 m-h/sm
Place Base Course 0.200 m-h/sm
Asphalt 0.250 m-h/sm
1.05 Site Development
Underground Piping ( Steel ) 0.184 m-h/ kg
Concrete Trenches 40.500 m-h/cm.
Sump Pits 173.500 m-h/cm
Sleeve Crossing 24.720 m-h/cm 6.0
Small Retaining Structures 30.970 m-h/cm
3.00 MASONRY
4.01 Fabrication
Light Weight 0.130 m-h/kg
Heavy Weight 0.090 m-h/kg
Gratings, 1-1/4 x 3/16 0.030 m-h/kg
Stair Thread Gratings 0.040 m-h/kg
Misc. Steel 0.120 m-h/kg
4.02 Erection
Light Weight 0.100 m-h/kg
Heavy Weight 0.060 m-h/kg
Stack ( End, Full Weld ) 0.300 m-h/kg 14.0
Tanks ( End, Full Weld ) 0.210 m-h/kg
Welding ( One Pass Only ) 0.200 m-h/lm
Painting ( 1 coat ) 1.200 m-h/lm
4.03 Structural Steel Framing 0.120 m-h/kg
4.04 Metal Decking 0.206 m-h/kg
4.05 Ornamental Metal 0.150 m-h/kg
5.00 WOODS
5.01 0.970 m-h/bf
5.02 Rough Carpentry
Floor Framings 0.430 m-h/bf
Wooden Post Erection 0.350 m-h/bf
Truss Fabrication 0.800 m-h/bf
Girt Installation 0.210 m-h/bf
Plates Installation 0.130 m-h/bf
Purlins Installation 0.530 m-h/bf
Ceiling Frame Works 1.350 m-h/sm
Siding Frame Works 1.200 m-h/sm
5.03 Finish Carpentry
Plywood Partition 0.500 m-h/sm
T & G Flooring and Siding 0.140 m-h/bf
Fascia Board Installation 0.500 m-h/bf
1/4 " x 3/4 in thk. Plywood 0.420 m-h/sm
Ceiling Plywood Installation 1.000 m-h/sm
Cabinet Boarding 0.150 m-h/bf
Cabinet Framing 0.180 m-h/bf
Wood Wall Partitions 0.600 m-h/sm
Panel Wall 7.000 m-h/sm
Forming Weight Anchor Bolts 4.500 m-h/sm
8.00 Finishes
COMPACTION
2.1 Manual ( Using Tamping Rammer) 3.00 cu.m/ m-day
2.2 Roller / Compactor ( 6 Passes) 30.00 cu.m/ m-day
FORMWORKS
4.1 Sub- Structure 3.00 sq.m. / m-day
4.2 Super Structure 2.00 sq.m. / m-day
STEEL WORKS
5.1 Reinforcing Bars ( Fabrication & Installation ) 150.00 kg/ m- day
5.2 Structural Steel ( Installation only ) 350.00 kg/ m- day
5.3 Steel Deck Plate ( Installation only ) 10.00 kg/ m- day
5.4 Anchor Bolt ( 450 mm long ) 8.00 kg/ m- day
5.5 Welded Wire Fabfic 20.00 kg/ m- day
WALL FINISHES
8.1 Plain Cement, Troweled Finish 5.00 sq.m. / m-day
8.2 Bush Hammered Synthetic Adobe 3.00 sq.m. / m-day
8.3 Pebble Washout 2.00 sq.m. / m-day
8.4 Sandblast Finish on Concrete 24.00 sq.m. / m-day
8.5 Mortar Float Finish 6.00 sq.m. / m-day
8.6 Ceramic Tiles including Mortar Bedding 1.50 sq.m. / m-day
8.7 Metal Lath 14.00 sq.m. / m-day
8.8 Base Boards
8.8.1 Vinyl Asbestos 25.00 l.m. / m-day
8.8.2 Mortar Baseboard 8.00 l.m. / m-day
8.8.3 Wooden Baseboard 15.00 l.m. / m-day
FLOOR FINISHES
9.1 Topping with Plain Cement 8.00 sq.m. / m-day
9.2 Pebble Washout 3.00 sq.m. / m-day
9.3 Ceramic Tiles including Mortar bed 2.50 sq.m. / m-day
9.4 Vinyl Tiles 22.00 sq.m. / m-day
9.5 Marble Tiles 2.00 sq.m. / m-day
9.6 Concrete Tiles 4.00 sq.m. / m-day
9.7 Mosaic Tiles with Bedding 2.50 sq.m. / m-day
9.8 Carpet 20.00 sq.m. / m-day
CEILING FINISHES
10.1 Rubbed Concrete Finish 18.00 sq.m. / m-day
10.2 Plain Cement Plaster 4.00 sq.m. / m-day
10.3 Acoustic Board with Metal Suspension 7.00 sq.m. / m-day
10.4 Gypsum Board with Metal Suspension 5.00 sq.m. / m-day
CARPENTRY FINISHES
11.1 T & G Wood Ceiling on 2 x 2 Wood Frame 2.50 sq.m. / m-day
11.2 Plywood Ceiling on 2 x 2 Wood Frame 3.50 sq.m. / m-day
11.3 Plywood Wall Panel on 2 x 2 Wood Studs ( Single ) 6.00 sq.m. / m-day
11.4 Plywood Wall Partition on 2 x 2 Wood Frames 3.50 sq.m. / m-day
DOORS & WINDOWS ( Installation Only )
12.1 Wooden Door including Jamb 1.20 sq.m. / m-day
12.2 Steel Doorincluding Jamb 1.00 sq.m. / m-day
12.3 Aluminum Door 1.00 sq.m. / m-day
12.4 Roll Up Door 0.75 sq.m. / m-day
12.5 Steel Window / Steel Louver 1.70 sq.m. / m-day
12.6 Aluminum Window / Louver 1.70 sq.m. / m-day
HARDWARES
13.1 Locksets 2.50 nos/m-day
13.2 Door Closer 2.00 nos/m-day
13.3 Door Stop 5.00 nos/m-day
13.4 Flush Bolt 4.00 nos/m-day
13.5 Push Plate 6.00 nos/m-day
13.6 Door Viewer 10.00 nos/m-day
13.7 Towel Rack 10.00 nos/m-day
13.8 Non Slip Nosing 15.00 l.m. / day
PAINTING
14.1 Masonry Surfaces 14.00 sq.m. / m-day
14.2 Steel Surfaces 12.00 sq.m. / m-day
14.3 Wooden Surfaces, Varnish 8.00 sq.m. / m-day
14.4 Wooden Surfaces, QDE 10.00 sq.m. / m-day
14.5 Stucco Painting 5.00 sq.m. / m-day
PRODUCTIVITY RATE PER MANDAY
7.00 BACKFILLING
Common - manual 9.76 cu.m.
Gravel Fill manual 1.60 cu.m.
8.00 COMPACTION
Mechanical Compaction 56.00 cu.m
Plate Compaction 144.00 cu.m
Spreading, tamping and grading 16.72 cu.m
Escombro Backfilling 38.24 cu.m
Placing Binder-Gravel 75.68 cu.m
19.00 W-Panel
Installation 20.00 pcs
31.00 PLASTERING
Scratch Coat
Finish Coat
32.00 PAINTING
Exterior Concrete or Bricks ( Brush )
Primer + 1 Coat 45.00 sqm
Primer + 2 Coat 33.00 sqm
Exterior Wood Sidings (including puttying/Brush)
Primer + 1 Coat 60.00 sqm
Primer + 2 Coat 40.00 sqm
Wood Trim (including, Puttying/Brush)
Primer + 1 Coat 30.00 sqm
Primer + 2 Coat 20.00 sqm
Windows & Doors (Brush)
Primer + 1 Coat 55.00 sqm
Primer + 2 Coat 32.00 sqm
Interior Plaster or Dry Wall (Brush)
Primer + 1 Coat 30.00 sqm
Primer + 2 Coat 20.00 sqm
Walls and Ceiling (Including puttying/Roller)
Primer + 1 Coat 80.00 sqm
Primer + 2 Coat 60.00 sqm
Interior Woodworks (Putty/Brush)
Primer + 1 Coat 60.00 sqm
Primer + 2 Coat 45.00 sqm
Interior Masonry or Concrete (Brush)
Primer + 1 Coat 45.00 sqm
Primer + 2 Coat 32.00 sqm
Structural Steel (Spray) Primer excluding
Brushing and Putty 100.00 sqm
Structural Steel (Spray) 2 Coat 50.00 sqm
Varnish (1coat, 1Sealer) 80.00 sqm
FLOOR FINISHES
1.0 Plain Cement ( Finished Topping 5/8" thk. Ave. )
a. Topping : Cement 0.27 bag
Sand 0.03 cu.m.
b. Finish Coat @ 1 bag / sq.m. 0.17 bag
WALL FINISHES
B Wall Finishes
Tiles pc. plus 10%
Capping pc. plus 10%
Marble sq.m. plus 5%
Baseboard LF plus 10%
Grout kilo 4 sq.m. / kilo
Cement kilo 10 sq.m. / kilo
Plywood sheet
Nailers BF
Nails kilo
Pebble Washed Out sq.m.
PVC Base Board LF
C Floor Finishes
Marble sq.m. plus 5%
Parquet Tiles sq.ft plus 5%
Wood Planks sq. m plus 15%
Tiles pc plus 5%
Vinyl Tiles pc plus 5%
Washed Out sq.m.
Washed Out with Tiles sq.m.
Colored Cement kilo 2 sq.m. / kilo
Plain Cement kilo 3 sq.m. / kilo
Grout kilo 4 sq.m. / kilo
Rugby gal 200 pcs./ gal
T & G Flooring BF plus 5%
Nailer for T & G BF 4.92 BF/ sq.m.
Nail kilo 5 sq.m. / kilo
Brass Nosing LF
CDS Marbles sq.m.
Threaded Nailer BF plus 5%
Coal Tar gal 20 sq.m. / gal
D Ceiling Finishes
Plywood 1/4 x 4 x 8 Sheet plus 10 %
Plywood 3/4 x 4 x 8 Sheet plus 5 %
Joist 2" x2" BF plus 10 % BF= Area x 6.417
Hanger 2" x 3" BF plus 10 % BF= Area x 3.00
Concrete Nail kilo
Nail kilo
Moulding BF
Glue quart
T Runner LF
Diffuser sq.ft.
Spandrel LS
T&G B.F. plus 10 % 14 BF/sq.m.
Wall Paper sq.m.
Others:
Acoustic Board plus 10 %
Spandrel
Curve Moulding pc
E Plastering
Sand cu.m. Thickness 1-1/2"
Cement bag 1:16 0.038 sq.m.
Water Prrofing Compound CHB Wall
RC Wall
Toilet Wall
Parapet Wall
Drop Wall
Plant Box
Patio
F Doors & Jambs
Flush Door sq.ft. plus 3.281% Use Commercial
Panel Door sq.ft. Use Commercial
Louver Door sq.ft. Use Commercial
Jambs BF
Nails 4" kilo 2kilo/Jamb
Coal Tar gal 0.20 gal/ Jamb
Door Casing, Two Sides BF plus 5%
Glue gal
PVC Door sq.m.
Sliding Track LF
Roller pcs
Handle pcs
Stopper pcs
1 Earthworks
Excavation cu.m. plus 10 %
Filling Materials cu.m. plus 20 %
Gravel Bed cu.m. plus 10 %
Backfilling cu.m. plus 10 %
Soil Poisoning quart 50 sq.m/quart
Hauling TL
Sheet Piles 2" x 10 " x 8 ' BF
Others:
Grading & Compaction sq.m.
2 Concreting
6,000 psi cu.m. plus 2%
5,000 psi cu.m. plus 2%
4,000 psi cu.m. plus 2%
3,000 psi cu.m. plus 2%
2,500 psi cu.m. plus 2%
3 Rebar
36 mm dia. pc
32mm dia. pc
28 mm dia. pc
25 mm dia. pc
20 mm dia. pc
16 mm dia. pc
12 mm dia. pc
10 mm dia. pc
Tie Wires roll 3000 kg/roll
4 Pile Work
Piles LF
Splice Can pc
Piles
5 Masonry
6 " CHB pcs
4" CHB pcs
Sand for 6" CHB cu.m.
Sand for 4" CHB cu.m.
Cement bag
Rebars pc.
GI Wire roll 3500 pcs/CHB per roll
Others
Rebars
Total CHB x 0.55 + 0.55 + Total x 0.51 / 3.281 / Commercial Length
6 Scaffoldings
Perimeter X Height x (6.56 ) x 1/2 = BF
7 Tendons
P = KN convert to kips
P = KN x Kip/4.448 KN
P = No of Tendons
Textured Finish
Acrytex System P 335.00 - P 345.00
Acrytex System w/ Latex Topcoat P 275.00 - P 285.00
Acrytex System w/ Poly-U 2K Topcoat P 425.00 - P 445.00
Plexibond w/ Latex Topcoat P 350.00 - P 355.00
Plexibond w/ Acrytex Topcoat P 410.00 - P 420.00
Plexibond w/ Poly-U 2K Topcoat P 525.00 - P 540.00
Concrete Flooring
Acqua Epoxy System (Green) P 265.00 - P 270.00
Acqua Epoxy System (Other color) P 245.00 - P 250.00
Epoxy Enamel (Blue, Green, Red) P 260.00 - P 270.00
Epoxy Enamel (White, Black, Gray) P 250.00 - P 260.00
Roofing
Boysen Roofgard P 150.00 - P 155.00
Metal Surfaces
Quick Drying Enamel System w/ B-370 P 140.00 - P 145.00
Quick Drying Enamel System w/ B-320 P 140.00 - P 145.00
Quick Drying Enamel System w/ B-4310 P 140.00 - P 145.00
Acqua Epoxy System (Green) P 250.00 - P 260.00
Acqua Epoxy System (Other color) P 235.00 - P 245.00
Epoxy Enamel (Blue, Green, Red) P 235.00 - P 245.00
Epoxy Enamel (White, Black, Gray) P 230.00 - P 240.00
2
Escalated Cost /
sq.m (2009)
P 165.92
191.44
210.59
242.49
268.02
382.88
440.32
363.74
567.95
453.08
536.04
689.19
344.60
319.07
344.60
331.83
191.44
210.59
255.26
459.46
446.70
382.88
268.02
325.45
178.68
185.06
497.75
625.38
593.47
229.73
268.02
427.55
446.70
382.88
261.64
325.45
197.82
185.06
185.06
185.06
331.83
312.69
312.69
306.31
WORK DIVISION FOR ESTIMATES
a ARCHITECTURAL WORKS ( Quantity Take-Off ) - One (1) Estimator
PROJECT :
OWNER :
LOCATION :
I Building
A Floor Finishes
1 Plain cement straight to finish
2 Plain cement floor finish (40mm thk.)
3 Plain cement with epoxy paint finish
4 Plain cement with floor hardener
5 Plain cement colored finish
6 Plain cement roller finish
7 Plain cement with groove
8 Broom finish
9 Rough cement finish
10 40mm thk. concrete topping
11 75mm thk. Conrete topping with wiremesh
12 Unglazed ceramic tiles
13 Granite tiles
14 Homogenous synthetic granite tiles
15 Non skid tiles
16 Vinyl tiles
17 Pebble washout finish
18 HDF laminated flooring
19 Carpet tiles
20 Carpet tiles
21 Angle bar nosing
22 Brass nosing
23 Control joints (isolation and contraction)
24 Rubber bumper
25 Expansion gap
B Wall finishes
1 Plain cement plaster finish (CHB and concrete)
2 Rubbed concrete finish
3 Adobe stone facing with repellant
4 Double wall partition with studs (gypsum or fibercement board)
5 Glazed tiles
6 GI sidings double wall with insulation
7 Aluminum composite panel
8 Groove (verify size)
9 baseboard
10 tile trim
11 pipe chase (chb, ficem bd, gypsum, plywood)
12 miscellaneous mouldings, arks, fascia bd
C Ceiling finishes
1 Rubbed concrete finish
2 Acoustic ceiling board
3 Metal spandrel
4 PVC ceiling
5 Aluminum ceiling
6 Aluminum composite panel
7 Moisture resistant gypsum board on aluminun frame
8 Gypsum board on aluminum frame
9 Fibercement board on metal furring
10 Cornice
11 Dripmold
E Doors
1 Steel
2 Wood
3 PVC
F Windows
1 Steel with glass and glazing
2 Aluminum
H Painting
1 Concrete and masonry
2 Wood
3 Structural steel
4 Miscellaneous steel
5 Luminous paint
6 Traffic paint
I Masonry
1 100mm and 150mm thk. CHB (load bearing and non load bearing)
2 CHB dowel
3 Lintel beam
4 Lintel column
5 Header
6 Zocalo
7 Masony soft joint (1-styropor, 2-backer rod and sealant)
K Carpentry
1 Cabinets (low and high)
2 Counter
3 Stair
Miscellaneous steel
L (Stainless steel or ordinary steel)
1 Stair (main, access, fire exit with platform and others)
2 Ladder (maintenance, fire exit and others)
3 Railing (mainrail, handicapped, handrail, grab rail and others)
4 Foot rail
5 Manhole (maintenance and fire exit)
6 Partition (cyclone, steel matting and others)
M Cistern
1 Rubbed concrete finish
2 Membrane waterproofing
3 Capillary waterproofing
4 Epoxy tank lining
5 Stainless steel manhole
6 stainless steel ladder rung
N Others
1 Laminated toilet partition
2 Laminated urinal partition
3 Signage
II Site Development
A Driveway
1 Broom finish
2 cement finish
3 Piedra paving tiles
4 Bomanite tiles
5 Control joints (isolation and contraction)
6 traffic paint
7 luminous paint
1 Cement finish
2 Broom finish with groove
C Plant box
1 Plain cement finish
2 Painting
E Fence
1 CHB
2 Plain cement plaster finish
3 Cyclone wire fence
4 Painting (concrete and steel)
G Landscaping
s
( 4d ) F
180o d
B or D F
d
F
90o
( 12d )
( 12d + 1/2F + d )
BOTTOM BARS
ENGLISH METRIC KGS./ M @ .10 O.C.B.W 2.50 BARS / S.M.
AT SUPPORT
DENSITY OF STEEL = 7850 KG / M3 @ .10 O.C.B.W 20 BARS / S.M.
WALL FTG.
+2 6MM 0.222 @ .10 O.C.B.W 13.33 BARS / S.M.
FTG TIE BEAMS
BOTTOM BARS
+3 10 MM 0.616 @ .10 O.C.B.W 10 BARS / S.M.
AT MIDSPAN
TOP BARS AT
+4 12MM 0.888 @ .10 O.C.B.W 8 BARS / S.M.
SUPPORT
+5 16MM 1.579 @ .10 O.C.B.W 6.66 BARS / S.M.
SIZES
45 deg hook 90 deg hook 135 deg hook 180 deg hook
10 mm 0.09 0.14 0.1 0.127
12 mm 0.09 0.2 0.127 0.152
16 mm 0.01 0.23 0.15 0.178
20 mm 0.114 0.267 0.1778 0.25
25 mm 0.165 0.366 - 0.28
28 mm 0.17 0.42 - 0.33
32 mm 0.216 0.47 - 0.355
36 mm 0.228 0.52 - -
STANDARD
DESCRIPTION QUANTITY
CONCRETE :
fc' - 4000 psi 12.75 bag / cu.m.
3000 psi 10 bags / cu.m.
2500 psi 8 bags / cu.m.
WALL FINISH :
Plastering 0.25 bags / sq.m.
Tool Joint 0.125 bags / sq.m.
Rough conc. 1/4" thk. 0.10 bags / sq.m.
FLOOR FINISH :
Plain cement floor finish/
Topping 2" thk. 0.80 bags / sq.m.
FORMWORKS :
Lumber ( 2 uses ) 130 bd.ft. / vol. conc.
Plywood ( 2 uses ) 1 pc. / vol. conc.
Rough Hardaware 1000 bd.ft. / kegs
G.I. Wire I roll / 2000 kgs
###
TYRE PRESSURE
lb/in2 = kpa
25 = 172.36
26 = 179.26
27 = 186.16
28 = 193.05
29 = 199.95
30 = 206.84
31 = 213.74
32 = 220.63
33 = 227.53
34 = 234.42
35 = 241.31
kpa = lb/in2
155 = 22.48
160 = 23.20
165 = 23.93
170 = 24.66
175 = 25.38
180 = 26.11
FORMULAE WEIGHTS, MEASURES AND TEMPERATUR
Inches Millimetres Metric
Multiply by 0.03937 1 25.40 Measure
25.4 0.07874 2 50.80 LINEAR MEASURE:
25.4 0.11811 3 76.20 1 centimetre (cm)
2.54 0.15748 4 101.60 1 metre (m)
0.0254 0.19685 5 127.00
304.8 0.23622 6 152.40 1 kilometre (km)
30.48 0.27559 7 177.80
0.3048 0.31496 8 203.20
0.914 0.35433 9 228.60 SURFACE MEASURE:
1.8288 1 square metre (m2)
20.1148 Inches Millimetres
201.148 0.393700 1 2.54000 1 hectare (ha)
1609.334 0.787402 2 5.08000 1 square kilometer (km2)
1.852 1.181102 3 7.62000
1.574803 4 10.16000
1.968504 5 12.70000 VOLUME AND LIQUID MEASURE:
Multiply by 2.362205 6 15.24000 1 litre = 1000 cm3
6.387464 2.755906 7 17.78000
0.016387 3.149606 8 20.32000
0.0283448 3.542307 9 22.86000
28.3167
0.562613 LENGTH 1 hectolitre (hl) = 100 l
0.1369725 Feet Metres
0.7645149 3.280840 .4. 0.3048
4.54609 6.561680 .2. 0.6096
0.0045041 9.842520 .3. 0.9144
8.413043 13.123359 .4. 1.2192
16.404199 .5. 1.524
19.685038 .6. 1.8288
Multiply by 22.965878 .7. 2.1336 1 cubic decimetre (dm3)
645.16 26.246718 .8. 2.4384
6.4516 29.527558 .9. 2.7432 1 cubic metre (m3) = 1000 l
929.0304
0.092903 Yards Metres
0.8356127 1.096313 .1. 0.91440
0.0083613 2.187336 .2. 1.82880 WEIGHTS:
4046.8564 3.280839 .3. 2.74320 1 gramme (g)
0.4046856 4.374452 .4. 3.65760
2.589988 5.488065 .5. 4.57200
6.561878 .6. 5.48640
7.655291 .7. 6.40080 1 kilogramme (kg) = 1000 g
Multiply by 8.748904 .8. 7.31520
64.78991 9.842517 .9. 8.22960
0.323995
0.064799 Miles Kilometres
1.555174 0.621371 .1. 1.60934
28.349523 1.242742 .2. 3.21869 1 quintal (q) = 100 kg
31.103477 1.864113 .3. 4.82803
0.0283495 2.485840 .4. 6.43783
0.4535924 3.106855 .5. 8.04672 1 metric ton (t) = 10g
6.3502932 3.728226 .6. 9.65606 = 1000 kg
50.802345 4.349597 .7. 11.26541
1016.0469 4.970968 .8. 12.87475
1.01605 5.592339 .9. 14.48410
37.799
0.60479 VOLUME & CAPACITY
Cu. Inches Cu. Centimetres
0.061024 .1. 16.38706
Multiply by 0.122048 .2. 32.77413
1.35587 0.183072 .3. 49.16119
745.7 0.244909 .4. 65.54820
0.001356 0.305120 .5. 81.93592
0.7457 0.366144 .6. 98.32238
1.01387 0.427168 .7. 114.70495
0.488192 .8. 131.09651
URES 0.549216 .9. 147.43858
MILLIMETRES
419.1 x 533.4 Fluid Ounces Cu. Centimetres
444.5 x 571.5 0.03520 .1. 28.4131
457.2 x 584.2 0.07039 .2. 56.8261
508 x 635 0.10559 .3. 85.2392
508 x 762 0.14078 .4. 113.6522
0.17598 .5. 142.0653
0.21117 .6. 170.4784
841 x 1189 0.24637 .7. 198.8914
594 x 841 0.28156 .8. 227.3045
420 x 694 0.31676 .9. 255.7176
297 x 420
210 x 297 Cu. Feet Litres
418 x 210 0.035315 .1. 28.3168
0.070630 .2. 56.6337
0.105940 .3. 84.9505
0.140588 .4. 113.2674
0.293 kwh 0.176574 .5. 141.5842
1 them 0.211888 .6. 169.9011
0.7457 kw 0.247203 .7. 198.2179
0.282518 .8. 226.5346
0.317832 .9. 254.8516
42 US gallons
39.37 UK gallons Cu. Feet Cu. Metres
0.159 cu. Metre 35.31467 .1. 0.02832
70.62934 .2. 0.05664
implies pure metal 105.94401 .3. 0.08496
200 milligrams 141.25868 .4. 0.11328
480 grains 176.57335 .5. 0.14160
31.1035 grams 211.88802 .6. 1.16992
247.20269 .7. 0.19824
282.51736 .8. 0.22656
eights 1 kilogram 317.83203 .9. 0.25488
eights 1 tonne
eights 10.022 lb Cu. Yards Cu. Metres
weights 10.3 lb 1.30795 .1. 0.76455
2.61590 .2. 1.52910
3.62385 .3. 2.29365
5.23180 .4. 3.05820
6.53975 .5. 3.82275
7.84770 .6. 4.58730
9.15565 .7. 6.35185
10.46390 .8. 6.11640
11.79155 .9. 6.88095
MASS
Ounces Grams
0.035274 .1. 28.349523
0.070548 .2. 56.699046
0.105812 .3. 85.048569
0.141096 .4. 113.980920
0.176370 .5. 141.747615
0.211644 .6. 170.097138
0.246918 .7. 198.446661
0.282192 .8. 226.796184
0.317466 .9. 255.145707
Grains Grams
15.5324 .1. 0.06480
30.8848 .2. 0.12960
43.2972 .3. 0.19440
61.7296 .4. 0.25920
77.1620 .5. 0.32400
92.5944 .6. 0.38880
108.0268 .7. 0.45360
123.4592 .8. 0.51840
138.8916 .9. 0.58320
Pounds Kilograms
2.204622 .1. 0.453592
4.409244 .2. 0.907184
6.613866 .3. 1.360776
8.818488 .4. 1.814368
11.023110 .5. 2.267960
13.227732 .6. 2.721552
15.432354 .7. 3.175144
17.636976 .8. 3.628736
19.841598 .9. 4.082328
CWT Kilograms
0.019684 .1. 50.80234
0.039368 .2. 101.60469
0.059052 .3. 152.40704
0.078736 .4. 203.20938
0.098420 .5. 254.01173
0.118104 .6. 304.81408
0.137788 .7. 355.61642
0.157472 .8. 406.41977
0.177156 .9. 457.22112
Tons Kilograms
0.000984 .1. 1016.0469
0.001968 .2. 2032.0938
0.002952 .3. 3046.1407
0.039360 .4. 4064.1876
0.004920 .5. 5080.2345
0.005904 .6. 6095.2814
0.006888 .7. 7112.3283
0.007872 .8. 8128.3752
0.008856 .9. 9144.4221
ELEVATION
16,404 5,000
9,843 4,000
6,562 2,000
3,281 1,000
1,640 500
656 200
0 0
Feet Metres
WEIGHTS, MEASURES AND TEMPERATURE SCALES
Equivalent in British British Equivalent
or American Measure or American Measure Metric Measure
LINEAR MEASURE:
0.394 inch (in) 1 inch (in.) 2.540 cm
3.281 feet (ft) 1 foot (ft.) 30.480 cm
1.094 yards (yd) 1 yard (yd.) (3 ft. = 36 in.) 91.440 cm
0.621 mile (mi) (32m = 35 yds)
0.540 nautical mile 1 mile (statute ml.) = 1.760 yd. 1.609 km
1 nautical mile (int'l.) 1,852 m
WEIGHTS:
15.432 grains 1 Gr. 0.065 g
0.643 pennyweight (dwt.) 1 dwt. (24 gr.) 1.555 g
0.035 advp ounces (oz.) 1 avdp. oz.
(437.5 gr. = 1/10 avdp. lb.) 0.028 kg = 28.350 g
35.151 troy ounces (tr. oz.) 1 tr. oz. (1/12 engl. tr. lb.) 0.031 kg = 31.104 g
2.205 advp pounds (lb) 1 avdp. lb. (16 oz.) 0.454 kg = 453.592 g
0.157 stone (st.) 1 st. (14 lb.) 6.350 kg
0.079 quarter 1 qt. (28 lb.) 12.701 kg
220.462 advp pounds 1 Ct. (100 lb.) = 1 US Hdw. 0.454 q = 45.359 kg
1 Hdw. (4 qt. = 112 lb.) 0.508 q = 50.802 kg
2.205 centals (US hundredweights) 1 sh. tn. (2000 lb.) 0.907 t = 907.185 kg
1.968 hundredweights (cwt.) 1 l. tn. (20 hundredweights)
= 80 qt. = 2240 lb. 1.106 l = 1.016047 kg
1.102 short tons (sh. tn.)
0.984 long or gross ton (l. tn.)
GUIDELINES FOR SITE INSPECTION
SITE INVESTIGATION
1.0 Accessibility :
1.1 Local transportation, type routes
1.2 Access roads, type, right of ways
1.3 Temporary road, if necessary, for movement of equipment & materials to jobsite
2.0 Area :
2.1 Soil
2.11 Type of soil (Adobe, ordinary soil, clay, swamp) stability
2.12 Clearing & grubbing works to be done
Note : Thickness of top soil to be stripped
2.13 Is area reclaimed , on fill, cut ? Do we have to backfill (determine average
depth) grade or cut. Note also nearest source of filling materials.
2.2 Surrounding
2.21 Security - is area fenced? Note natural boundaries
2.12 Adjoining lots - slum area, commercial, traffic area. Do we talk to owner of
of adjoining land so as to work peacefully.
2.13 Drainage-Is there natural drainage? Where does storm water flow? Is area
easily flooded or becomes muddy during rains? Water table elevation during
rainy or ordinary days. Months of wet and dry seasons.
2.14 Obstructions - excavations, high tension electric wires, clearances,
vegetation growth, and existing boulders or structures.
2.15 Take note of possible or designated area for dumping excess or unsuitable
materials.
2.3 Facilities
2.31 Construction water and electric light, indicate type of source and location.
Note also water natural sources like creeks and rivers.
2.32 Space for mobility of equipment for erection.
2.33 Space for temporary facilities, office, shop for equipment, batching area and
storage area.
2.34 Availability of housing and source of food.
WOOD JOISTS
Wood joist (Waste factor and solid bridging considered)
Note :
1. In computing for board feet, subtract first all floor openings from gross floor area
and multiply the factors above.
2. Other structural wooden beams such as girders, girts, ties and the like should be
estimated by direct count.
Painting
Metals
Enamel 0.20 10%
Zinc White 0.20 10%
White Lead 0.20 10%
Wood
Enamel 0.20 10%
Zinc White 0.20 10%
White Lead 0.20 10%
Varnish 0.20 10%
Flat 0.20 10%
Gloss 0.20 10%
CONCRETE PAINTS
* Materials for white wash : 50lbs of hydrated lime plus 6 to 6-1/2 gallon of water = 8 gallon
of white wash.
PAINTS COVERING CAPACITY
Interior Painting
Priming paint Wood 46
Metal primer Metal 55
Undercoat Over primer 37
Flat Finish coat 46
Semi gloss enamel Finish coat 42
Satin gloss enamel Finish coat 42
Floor enamel Floor 46
Aluminum paint First coat 55
Aluminum paint Second coat 65
Spar varnish Finishing wood work 55
Clear gloss varnish Finishing wood work 55
Lacquer Over stain 42
Interior stain Wood work 1st coat 46
Interior stain Wood work 2nd coat 55
Interior stain Wood work 3rd coat 65
Miscellaneous
Barn, red oil paint Repaint barn 42
Rust inhibitor Metal 60
(zinc paint)
Furniture sealer Unpaint furniture 55
and paint
Materials Quantity
Acoustic Tile
Tile 10%
Cement 25 gal/1000 sf 20%
Glass
8" x 12" 75 panes / box 10%
10" x 16" 45 panes / box 10%
12" x 20" 30 panes / box 10%
14" x 24" 22 panes / box 10%
16" x 24" 16 panes / box 10%
Boards
Typical sizes
4' x 8' 0.34 per sm
3' x 6' 0.60 per sm
4' x 4' 0.67 per sm
2' x 2' 2.70 per sm
2' x 4' 1.36 per sm
Caulking
Primer 2.00 gal/1000lf 10%
Compound (1/2" x 1/2") 13.00 gal/1000lf 10%
FENESTRATIONS
A. Window Sash
1. For sliding type : Add 10% to the total window area
Roundings
100 or less - 1 sm
over 100 - 5 sm
2. For casement and projected type . Solve only for
100 or less - 1 sm
over 100 - 5 sm
B. Door Sash
1. Classify as to type and solve for the total area per type
2. Roundings
100 or less - 1 sm
over 100 - 5 sm
C. Window Glass
1. Classify windows as to glass type. General glass type as follows :
Plain
Frosted
Ribbed
Florentine
Plate
2. Solve for total window sash area under each glass type. Note that sliding
window sash area would have to be increased by 10%.
3. Solve for glass area by multiplying respective total sash area by 85%.
Round to 10 sq.ft.
D. Fenestration Framework
This includes : Door and window heads, jambs, sills, mullions
1. Solve for the actual length.
2. Add 15% for wastage and overlaps.
3. Roundings :
100 or less - 10 bd.ft.
over 100 - 50 bd.ft.
Procedure : Get sloped area of roof (see table at pitched area). Solve for purlin
quantities by using above factors. Round up estimates to closest 10 board
feet.
Purlin Size Strap Size Pcs. of straps per plain G.I. roll
(36" x 8'-0")
2" x 3" 1" x 9" 380.00
2" x 4" 1" x 10" 340.00
2" x 5" 1" x 11" 310.00
2" x 6" 1" x 12" 285.00
7. G.I. roofing flashing (based on 8'-0" (240cm) long plain galvanized iron sheets)
Effective Length M
a.Rideg rolls, ridges and valleys 7'-0" 2.14
b. Gutter and downspouts 7'-6" 2.29
c. Gutter flashings
Based on number of gutters , convert into rolls, divide quantity by following
factors.
18" Wide - divide by 2
12" Wide - divide by 3
d. Senepa Flashing
Factor - 7-0" or 2.135 meters
NAILS
1. Ceiling
4" 0.03 kg/sm of ceiling joist
2-1/2" 0.13 kg/sm of nailing strip
2" 0.07 kg/sm of nailing board
2-1/2" 0.02 kg/sm of ceiling area
2. Floor
6" 0.07 kg/sm
4" 0.06 kg/sm for girders
2" 0.16 kg/sm of 1" x 4" T & G flooring
4" 0.06 kg/sm for joist
2-1/2" 0.02 kg/sm for fascia
Total 0.36 kg/sm of floor area
3. Exterior Wall
4" 0.03 kg/sm of wall for stud for H & V studs
2-1/2" 0.08 kg/sm of finishing
2" 0.07 kg/sm of V-cut siding
Total 0.18 kg/sm of wall
4. Interior Wall
4" 0.04 kg/sm of wall
2-1/2" 0.08 kg/sm of wall finishing nails
1-1/2" 0.08 kg/sm of plywood single wall
Total 0.20 kg/sm of wall
5. Roof Framing
4" 0.02 kg/sm of wall using nails and bolts
3.00 kg/sm truss (purlins included)
6. Roofing
1/4" dia. x 1/2" G.I. rivets - 8' Corrugated G.I. 0.80 kg/sht plus
and cont.
150/K -6' Corrugated G.I. 0.40 k/sheet 6' long
Lead washers (72/K) -8' = 0.17K/sheets, 6' 0.085 k/sheet
G.I. washer (200/K) -8' = 0.12K/sheets, 6' 0.06 k/sheet
G.I. Plain straps -0.055 sheet/8' got corrugated G.I.
2-1/2" G.I. nails (72K) -8' = 0.17K/sheets, 6' 0.085 k/sheet
Lead washer -8' = 0.17K/sheets, 6' 0.085 k/sheet
For 22" wide sheet -0.81M 0.635M effective for 2-1/2 corrugation lap
-0.70 effective for 1-1/2 corrugation lap
For 31" -0.79M 0.63M effective for 2-1/2 corrugation lap
-0.70 effective for 1-1/2 corrugation lap
One corrugation equals 3"
Corrugated G.I. roofing only 0.83 sheet/sm of roof area
1 1,030
1-1/8 988
1-1/4 852
1-1/2 748
1-1/8 (3/8" head) 922
9. Lathing Nails
7d 11 307
8d 9 218
10d 10 152
8d 11 271
6 1 20
7 5/16 13
8 9/8 9
9 3/8 7-1/2
10 3/8 6-1/2
12 3/8 5-1/2
Masonry
1. For every 70 pcs. of 8" x 8" tiles - required one bag of cement.
2. For every 100 pcs. of 6" x 6" tiles - required one bag of cement.
3. For every 1,000 pcs. of adobe 15 sacks of cement, 20 sacks of lime.
Weight of Metals
1. Aluminum Sheets
Thickness B & S (Gauge) Weights (Kgs/sm)
0.020 24 1.38
0.025 22 1.72
0.032 20 2.20
0.040 18 2.75
0.051 16 3.51
0.064 13 4.41
2. Aluminum Plates
0.250 1/4 17.22
0.375 3/8 25.81
0.600 1/2 34.50
CONCRETE WORKS
40kg
Concrete mixes, materials Net Factor per Net Factor per /
only per BPW specifications / cum.. cum..
Considering 94 Considering 88
lbs/bags of cement lbs/bags of
cement
1. Class AAA. 1:1:2 Mix (3,500 PSI)
Cement 13.30 bags 14.20
Sand 0.40 cum 0.40
Gravel 0.80 cum 0.20
= 3 ( 8 hrs./day) = 1.72 MH
14 sm / day
ARCHITECTURAL WORKS
1. Floor Finishes Net Factor / sm
A. Masonry Floor Finishes
1. Plain Cement (per sm)
a. Materials
Cement 1 bag/6 sm 0.17
b. Labor
Spread Cement 1M/32 sm / day 0.25
Troweling 2M/32 sm / day 0.50
b. Labor
Topping application 2M/21 sm / day 0.70
Finishing application 2M/21 sm / day 0.76
b. Labor
Scratchcoat application 2M/21 sm/day 1.52
Tile installation 1M/8 sm/day 2.00
2. Wall Finishes
A. Masonry Wall Finishes
1. Rubbed concrete (plain cement) finish, retouch
a. Materials
.01. Retouch T2: 1/8" average
Cement 0.003 cum/sm (18.69 bags/cum) 0.056
Sand 0.003 cum/sm (0.93 cum/cum) 0.003
b. Labor
Application 1M/10 sm/day 0.80
b. Labor
Interior wall application 1M/10 sm/day 0.80
Exterior wall application 2M/9 sm/day 0.90
3. Ceiling Finishes
A. Carpentry ceiling finishes
1. Plywood / lawanit / asbestos ceiling on wood frame
a. Materials
.01. Frames
a) 2" x 2" @ 16" o.c. 3.65
b) 2" x 4" @ 48" o.c. 4.55
.02. Nails
3-1/2" cw 65 pcs / sheet 0.15
1" F 130 pcs / sheet 0.016
.03. Hangers
#3 Plain RB @ 48" o.c. 0.75
.04. Panels (4' x 8')
b. Labor
Frame installation 2C/18 sm /day 0.90
Panel installation 2C/25 sm/day 0.65
2. Acoustic tile / board ceiling finish on wood framing
a. Materials
.01. Frames
a) 2" x 2" @ 16" o.c. 3.65
b) 2" x 4" @ 48" o.c. 4.55
.02. Acoustic tile 10.75
.03. Adhesive rugby glue (1 gal/9sq.m) 0.11
b. Labor
Frame installation 2C/18 sm /day 0.90
Panel installation 2C/25 sm/day 1.10
A. MASONRY WORKS
Mortar Mixes - Materials only (per cm)
1. TYPE 1 - Plain 1:1 (Plaster Retouch)
C (Cement) 22.00
SI 29.3 CF 0.83
TYPE 1 - With Lime 1:1:2
C (Cement) 12.00
SI 33 CF 0.93
2. TYPE 2 - Plain 1:2 (Plaster, Retouch, Scratchcoat)
C (Cement) 17.50
SI 33 CF 0.93
TYPE 2 - With Lime 1:1:4
C (Cement) 9.00
SI 33 CF 0.93
3. TYPE 3 - Plain 1:3 (CHB Filler, Topping, Scratchcoat)
C (Cement) 13.00
SI 33 CF 1.05
TYPE 3 - With Lime 1:1:6
C (Cement) 7.00
SI 33 CF 1.05
4. Mortar Additives
Integral Waterproofing
a. Sika Plaster Weld (Dose-2 Fld.)
0.02 per bag of cement ###
Per bag of cement
b. Hydrite (Dose-1lb per bag of cement)
0.02 per bag of cement 1
Per bag of cement
C. CONCRETE WORKS
1. Formworks : Substructure (Per Contact Area)
a) Footing (Per sm)
M: Consider 5' x 5' x 12" Eff.A = 5x4x1 = 20 sf 1.86
Plywood 1/2" : 2.97 sm/sht 0.34
Framings 2" x 3" : (2x3x15)/12x4x1/1.86 16.20
Nails 4"C : (80/65)(1/1.86) 0.66
1-1/2"C : (92/650)(1/1.86) 0.08
Formoil : 1 Gal/24 sm 0.045
Braces 2" x 4" : (2x4x6)/12x1/1.86 23.00
PAINTING
A. Metal
Enamel 10 0.2 gal / 100 sf
Zinc White 10 0.2 gal / 100 sf
White Lead 10 0.2 gal / 100 sf
B. Wood
Enamel 10 0.2 gal / 100 sf
Zinc White 10 0.2 gal / 100 sf
White Lead 10 0.2 gal / 100 sf
Varnish 10 0.2 gal / 100 sf
Flat 10 0.2 gal / 100 sf
Gloss 10 0.2 gal / 100 sf
C. Brick, Concrete, Plaster
Enamel 10 0.2 gal / 100 sf
Zinc White 10 0.2 gal / 100 sf
Varnish 10 0.2 gal / 100 sf
Flat 10 0.2 gal / 100 sf
Gloss 10 0.3 gal / 100 sf
Size 10 0.4 gal / 100 sf
Primer 10 0.3 gal / 100 sf
Calcimine 10 0.4 gal / 100 sf
o owner of
ation during
unsuitable
ng area and
onry blocks,
35cm. (14inch)
bd.ft/sm
floor area
should be
% Wastage
(sm/gal.)
18 sm/lb
12 sm/lb
12 sm/lb
Capacity
(sm/ gal)
-1/2 kg/sm
g of cement
m (2 coats)
g of cement
of cement
bag of cement
g of cement
% Wastage
% Wastage
that sliding
Total Area in %
t 10 board
Area (sm)
ain G.I. roll
G flooring
kg/sht plus
and cont.
k/sheet 6' long
of roof area
mate No./kg.
ate No./kg.
Net Factor per /
Considering 88
lbs/bags of
cement
bags
cum
cum
bags
cum
cum
bags
cum
cum
bags
cum
cum
bags
cum
cum
bags
cum
cum
bags
cum
cum
bags
cum
bags
cum
bags
cum
bags
cum
bags
cum
bags
cum
bags
cum
bags
cum
bags
cum
bags
cum
pcs
kg
kg
roll
MH
bags
cum
pcs
kg
kg
kg
kg
roll
MH
bags
cum
pcs
kg
kg
roll
MH
bags
cum
kg
MH
bag
MH
MH
bag
cum
cum
MH
MH
bag
cum
lbs
lbs
lbs
MH
MH
bag
cum
bag
pail
lbs
MH
MH
bag
cum
sf
pcs
pcs
pcs
pcs
gal
bag
cum
bag
MH
MH
bag
cum
gal
pcs
pcs
pcs
MH
MH
bag
cum
pcs
pcs
pcs
pcs
MH
MH
bf
kg
bf
kg
mh
bf
kg
gal
sf
gal
mh
bag
cum
gal
sf
mh
mh
bag
cum
mh
bag
cum
mh
mh
bag
cum
mh
mh
bag
cum
sf
pcs
pcs
pcs
pcs
pcs
gal
bag
cum
bag
mh
mh
mh
Net factor / sm
bag
cum
mh
mh
mh
mh
bag
cum
mh
bag
cum
gal
bag
mh
mh
bag
cum
gal
pail
mh
mh
bag
cum
cum
DT
mh
mh
bag
cum
pcs
pcs
sm
sm.
bag
mh
mh
mh
m-d
bf
bf
kg
kg
sht
sht
sht
mh
mh
bf
bf
kg
kg
sht
mh
mh
bf
bf
bf
kg
mh
bf
kg
mh
bf
bf
kg
kg
kg
mh
mh
bf
bf
sf
gal
mh
mh
suspension
sf
roll
lf
lf
mh
mh
bf
kg
mh
bf
bf
bf
kg
mh
mh
bags
cm
bags
cm
bags
cm
bags
cm
bags
cm
bags
cm
gal
lb
blocks
blocks
blocks
cum
cum
cum
kg
kg
kg
kg
lf
lf
sm
sht/sm
bf/sm
kg/sm
kg/sm
gal/sm
bf/sm
mh/sm
mh/sm
mh/sm
sm
sht/sm
bf/sm
kg/sm
kg/sm
gal/sm
bf/sm
mh/sm
mh/sm
mh/sm
sm
sht/sm
bf/sm
kg/sm
kg/sm
gal/sm
bf/sm
mh/sm
mh/sm
mh/sm
bf/lm
bf/lm
bf/lm
kg/lm
gal/sm
mh/lm
mh/lm
bf/lm
bf/lm
bf/lm
kg/lm
gal/sm
mh/lm
mh/lm
sm
sht/sm
bf/sm
kg/sm
kg/sm
gal/sm
bf/sm
mh/sm
mh/sm
mh/sm
sm
sht/sm
bf/lm
bf/lm
bf/lm
bf/lm
bf/lm
kg/sm
kg/sm
gal/sm
mh/sm
mh/sm
mh/sm
mh/sm
sm
sht/sm
bf/lm
bf/lm
kg/sm
kg/sm
gal/sm
mh/sm
mh/sm
mh/sm
mh/sm
sm
sht/sm
bf/lm
bf/lm
bf/lm
bf/lm
kg/sm
kg/sm
gal/sm
mh/sm
mh/sm
mh/sm
CHB/sm
bag/sm
cm/sm
kg/sm
kg/sm
roll/sm
mh/sm
pcs/mh
CHB/sm
CHB/sm
bag/sm
cm/sm
kg/sm
kg/sm
roll/sm
mh/sm
pcs/mh
CHB/sm
CHB/sm
bag/sm
cm/sm
kg/sm
kg/sm
roll/sm
mh/sm
CHB/sm
bag/sm
cm/sm
kg/sm
roll/sm
mh/sm
bag/sm
mh/sm
mh/sm
bag/sm
cm/sm
bag/sm
mh/sm
mh/sm
bag/sm
cm/sm
lbs/sm
lbs/sm
lbs/sm
mh/sm
mh/sm
CONVERSION
08600 SKYLIGHTS
610 Roof Windows
620 Unit Skylights
630 Metal Framed Skylights
08700 HARDWARE
710 Door Hardware
720 Weatherstripping and Seals
740 Electro Mechanical Hardware
750 Window Hardware
770 Door and Window Accessories
780 Special Function Hardware
790 Hardware Restoration
08800 GLAZING
810 Glass
830 Mirrors
840 Plastic Glazing
850 Glazing Accessories
890 Glazing Restoration
0890 GLAZED AND CURTAIN WALL
910 Metal Framed Curtain Wall
950 Translucent Wall and Roof Assemblies
960 Sloped Glazing Assemblies
970 Structural Glass Curtain Walls
990 Glazed Curtain Wall Restoration
DIV. 09 FINISHES
09050 BASIC FINISH MATERIALS AND METHODS
09100 METAL SUPPORT ASSEMBLIES
110 Non Load Bearing Wall Framing
120 Ceiling Suspension
130 Acoustical Suspension
190 Metal Frame Restoration
09200 PLASTER AND GYPSUM BOARD
205 Furring and Lathing
210 Gypsum Plaster
220 Portland Cement Plaster
230 Plaster Fabircations
250 Gypsum Board
260 Gypsum Board Assemblies
270 Gypsum Board Accessories
280 Plaster Restoration
09300 TILE
305 Tile Setting Materials and Accessories
310 Ceramic Tile
330 Quarry Tile
340 Paver Tile
350 Glass Mosaics
360 Plastic Tile
370 Metal Tile
380 Cut Natural Stone Tile
390 Tile Restoration
09400 TERRAZZO
410 Portland Cement Terrazzo
420 Precast Terrazzo
430 Conductive Terrazzo
440 Plastic Matrix Terrazzo
490 Terrazzo Restoration
09500 CEILINGS
510 Acoustical Ceilings
545 Specialty Ceilings
550 Mirror Panel Ceilings
560 Textured Ceilings
570 Linear Wood Ceilings
580 Suspended Decorative Grids
590 Ceiling Assembly Restoration
09600 FLOORINGS
610 Floor Treatment
620 Specialty Flooring
630 Masonry Flooring
640 Wood Flooring
650 Resilient Flooring
660 Static control Flooring
670 Fluid Applied Flooring
680 Carpet
690 Flooring Restoration
09700 WALL FINISHES
710 Acoustical Wall Finishes
720 Wall Covering
730 Wall Carpet
740 Flexible Wood Sheets
750 Stone Facing
760 Plastic Blocks
770 Special Wall Surfaces
790 Wall Finish Restoration
09800 ACOUSTICAL TREATMENT
810 Acoustical Space Units
820 Acoustical Insulation and Sealants
830 Acoustical Barriers
840 Acoustical Wall Treatment
09900 PAINTS AND COATINGS
910 Paints
930 Stains and Transparent Finishes
940 Decorative Finishes
960 High Performance Coatings
970 Coatings for Steel
980 Coatings for Concrete and Masonry
990 Paint Restoration
DIV. 10 SPECIALTIES
10100 VISUAL DISPLAY BOARDS
110 Chalkboards
115 Markerboards
120 Tackboard and Visual Aid Boards
130 Operable Board Units
140 Display Track Assemblies
145 Visual Aid Board Units
10150 COMPARTMETNS AND CUBICLES
160 Metal Toilet Compartments
165 Plastic Laminate Toilet Compartments
170 Plastic Toilet Compartments
175 Plastic Toilet Compartments
180 Stone Toilet Compartments
185 Shower and Dressing Compartments
190 Cubicles
DIV. 11 EQUIPMENT
11010 MAINTENANCE EQUIPMENT
Floor and Wall Cleaning Equipment
Housekeeping Carts
Vacuum Cleaning Systems
Window Washing Systems
11020 SECURITY AND VAULT EQUIPMENT
Safe Depoist Boxes
Sales
Vault Doors and Day Gates
DIV. 12 FURNISHING
12050 FABRICS
12100 ART
110 Murals
120 Wall Decorations
140 Sculptures
170 Art Glass
190 Ecclesiastical Art
12300 MANUFACTURED CASEWORK
310 Manufactured Metal Casework
320 Manufactured Wood Casework
350 Specialty Casework
12400 FURNISHING AND ACCESSORIES
410 Office Accessories
420 Table Accessories
430 Portable Lamps
440 Bath Furnishings
450 Bedroom Furnishings
460 Furnishing Accessories
480 Rugs and Mats
490 Window Treatments
12500 FURNITURE
510 Office Furnitures
520 Seating
540 Hospitality Furniture
timesing AREA VOLUME Unit weight FINAL WEIGHT FINAL LENGTH COST/ KG COST/ LM
6.000 3.045 0.037 7850.000 330.80 60.20 29,771.91 7,525.00
4.000 0.700 0.006 7850.000
21.000 2.670 0.112 7850.000 1,211.41 257.20 109,027.08 32,150.00
7.000 1.680 0.024 7850.000
4.000 1.230 0.010 7850.000
7.000 0.630 0.009 7850.000
timesing AREA VOLUME Unit weight FINAL WEIGHT FINAL LENGTH COST/ KG COST/ LM
6.000 5.460 0.066 7850.000 602.25 109.60 54,202.68 13,700.00
8.000 0.700 0.011 7850.000
30.000 3.645 0.219 7850.000 2,260.80 480.00 203,472.00 60,000.00
11.000 1.800 0.040 7850.000
4.000 1.650 0.013 7850.000
11.000 0.750 0.017 7850.000
timesing AREA VOLUME Unit weight FINAL WEIGHT FINAL LENGTH COST/ KG COST/ LM
7.000 5.460 0.076 7850.000 2,069.57 109.20 186,261.66 13,650.00
208.000 0.450 0.187 7850.000 2,508.78 532.65 225,790.34 66,581.25
11.000 0.765 0.017 7850.000
18.000 1.980 0.071 7850.000
16.000 1.215 0.039 7850.000
5.000 0.540 0.005 7850.000
timesing AREA VOLUME Unit weight FINAL WEIGHT FINAL LENGTH COST/ KG COST/ LM
1.000 82.000 0.123 7850.000 965.55 410.00 - 51,250.00
0.000 0.000 7850.000 labor 15,375.00
0.000 0.000 7850.000 painting 5,740.00
0.000 0.000 7850.000 profit mesc. De 14,473.00
0.000 0.000 7850.000 86,838.00
86,899.50
AISC MEMBER DIMENSIONS AND PROPERTIES
W, S, M, HP Shapes C, MC Shapes WT, ST, MT Shapes
W16x31 MC10x22 WT4x20
46.24 kg/m 32.67 kg/m 29.73
Double Angles
2L5x3-1/2x3/8SLBB
30.89 kg/m
AISC MEMBER DIMENSIONS AND PROPERTIES VIEWER
W, S, M, HP Shapes C, MC Shapes WT, ST, MT Shapes Single Angles Double Angles Rectangular HSS
Y Y Y
k1=0.75 Y Y Y
k=0.842 tf=0.44 tf=0.575 b=5 t=0.349
bf=8.07 t=0.375
y(bar)=0.735 x(bar)=0.836
x(bar)=0.99 tf=0.56 d=3 t=0.25 X
d=15.9 T X d=1 X X d=3.5 h=8 X
d=4.13 X y(bar)=0.836
tw=0.275 tw=0.29 tw=0.36 b=3
(0, 3/8, or 3/4
bf=5.53 bf=3.32 gap) b=6
A = 1 A = 1
B = -0.129348 B - 4AC
2
= 0.128466
C = 5.68E-05 C = 5.68E-05
Volume 2 Weight
m³ kg
0.00200 7.37
0.00314 9.83
0.00477 14.29
0.00724 18.96
0.01059 23.93
0.01585 31.96
0.02679 54.01
0.03902 69.58
0.05911 94.11
0.09000 128.52
0.12705 165.05
0.22068 252.62
0.34135 367.57
0.48436 472.92
0.65289 593.64
0.85278 775.55
1.06503 869.51
1.31643 1,085.89
1.84314 1,151.39
- -
** Considerations of Structural Elements
Roof Beams
(200x400)mm 4.4 55.00
6.5 0.2 0.4 6 3.12 39
8 0.2 0.4 2 1.28 16
GFA 156.00
Analysis
Concrete (m3) 34.32 0.22
Rebar( kg) 3,432.00 100.00
Formworks (m2) 296.40 1.90
Formworks Rebars (kgs)- STEEL Ratio (kg/m³) FORM Ratio (m²/m³)
(m²)- by ratio by ratio
min max min max
27.00 243.00 45 40 80 5 4 6
314.00 3496.20
m2
m3/m2 GFA
kg/m3 concrete
m2/m2 GFA
** Considerations of Structural Elements
Roof Beams
(200x400)mm 4.4 55.00
6.5 0.2 0.4 6 3.12 39
8 0.2 0.4 2 1.28 16
GFA 156.00
Analysis
Concrete (m3) 49.92 0.32
Rebar( kg) 6,489.60 130.00
Formworks (m2) 466.44 2.99
Formworks Rebars (kgs)- STEEL Ratio (kg/m³) FORM Ratio (m²/m³)
(m²)- by ratio by ratio
min max min max
27.00 243.00 45 40 80 5 4 6
476.75 6100.20
m2
m3/m2 GFA
kg/m3 concrete
m2/m2 GFA
Concrete Estimate
I. CONCRETE SLAB
Given:
length: 0 m
width: 0 m
thickness: 0 m
Computation:
1 Vol = 0 cu.m
2 Cement = 0 bags
sand = 0 cu.m
gravel 3/4 = 0 cu.m
Computation:
1 Vol. Post = 0.918 cu.m
Vol. Footing = 1.575 cu.m
------
2 Total Vol. = 2.493 cu.m
IV. MASONRY
Given Height = 6.6 m
Length = 82.8 m
--------
Area = 546.48 sq.m
1 divide the height of the wall by the height of one block = 33 layers
2 divide the length of the wall by the length of one block = 207 pcs.
Computation
1 Volume = 0 cu.m
2 cement : = 0 bags
sand : = 0 cu.m
gravel : = 0 cu.m
SUMMARY
CEMENT = 676.15 bags x 160 = 108184
SAND = 55.492 cu.m x 350 = 19422.1
GRAVEL 3/4 = 8.4636 cu.m x 550 = 4654.98
CHB = 7173 pcs. x 5.2 = 37297.3
------------
P 169558
48.6
pcs
Estimate of Reinforcement
I. Reinforcement for Concrete Hollow Blocks (10mmØ bars)
Given :
length = 13.7 m
height = 2.7 m
Computation
1 Solve for the area of the fence
Area = 36.99 sq.m
Computation
4 width = 0
length = 0
______
0 meters
CONCRETE POST
summary of materials
use of formworks
1/2"x4'x8' plywood 32.279 pcs 1/2"x4'x8' plywood
2"x3" good lumber 514.58 bd.ft 86 pcs 2"x3"
2"x2" good lumber 1908.9 bd.ft 477 pcs 2"x2"
cwn assorted 52.919 kgs
134.2
4'x8' plywood
pcs
bdft