Vous êtes sur la page 1sur 227

PRELIMINARIES

PROJECT : 0 OWNER : 0

LOCATION : 0 DATE : July 15, 2009

LINE UNIT OF
No. I T E M MEA- QUANTITY
SURE

A. MOBILIZATION lot 1.000 25-100T 140,000.00


B. TEMPORARY FACILITIES
B1. Offices 70,000.00
Furniture lot 1.000
Aircondition unit 2.000 15 000 x
Electrical lot 1.000 10 000 x Nos. of Mos. =
Computer / Printer lot 1.000 20 000
Telephone unit 1.000 3000 x Nos. of Mos. = -
Fax Machine unit 1.000 5 000 40,000.00
Xerox Machine unit 1.000 3 000 x Nos. of Mos. = -
Office Supplies lot 1.000 3 000 x Nos. of Mos. = -
40,000.00
B2. Barracks lot 1.000 50-100T 50,000.00
B3. Fabrication Shed -
B4. Portalet unit 1.000 5 500 x Nos. of Mos. = 34,000.00
B5. Safety Equipment lot 1.000 10-20T 20,000.00
B6. Warehouse & Storage lot 1.000 10- 30 T 50,000.00
134,000.00

C. TRANSPORTATION lot 1.000 20-50T 80,000.00

D. EQUIPMENT
Tower Crane unit 1.000 12,000.00
Excavator unit 1.000 12,000.00
Grader unit 1.000 12,000.00
Crane unit 1.000 12,000.00
Bulldozer unit 1.000 3 5 000 x Nos. of Mos. 12,000.00
Road Roller unit 1.000 12,000.00
Payloader unit 1.000 12,000.00
DumpTruck unit 1.000 12,000.00
Generator unit 1.000 12,000.00
Dewatering unit 1.000 12,000.00
120,000.00
E. CONSTRUCTION STAFF 1-PE x 20 K x Nos. of Mos.
Project Engineer mo 1.000 1-Asst PE x 20 K x Nos. of Mos. 120,000.00
Bodegero / Timekeeper mo 1.000 2 WM x 12 K x Nos. of Mos. 90,000.00
210,000.00
Security Guard shift 1.000
4 SG x 15 000 x Nos. of Mos. 150,000.00

F. TEMPORARY FENCE lm 1.00 0.4-0.5T 500 x Total LM 30,000.00

Gen. Reqmts. Prelims


Prepared by Ricky
Page 1
PRELIMINARIES
PROJECT : 0 OWNER : 0

LOCATION : 0 DATE : July 15, 2009

LINE UNIT OF
No. I T E M MEA- QUANTITY
SURE

G. PERMITS & LICENCES


ECC / LLDA lot 1.000 -
Building Permit sm 1.000 P40-80 x Total Covered Area 223,408.00
PEZA / IND'L PARK sm 1.000 -
Occupancy Permit sm 1.000 10-80T x Total Covered Area 60,000.00
283,408.00
H. ELECTRICAL
Electrical Connection lot 1.000 80 000 60,000.00
Electric Meter lot 1.000 20,000.00
Power Consumption mo 1.000 10-35T x Nos of Mos. 90,000.00
Temporary Lighting lot 1.000 25,000.00
195,000.00
I. WATER SUPPLY
Water Connection lot 1.000 30 000 15,000.00
Water Meter lot 1.000 -
Water Consumption lot 1.000 5-20T x Nos. f Mos. 50,000.00
Temporary Waterline lot 1.000 5-20T -
65,000.00
J. BONDS & INSURANCES
Performance Bond P T.C. x 20% X 0.006820 35,000.00
Guarantee Bond P T.C. x 20% X 0.007436 38,000.00
All Risk Bond P T.C. x 100 x 0.002590 100.00
73,100.00
K. LIQUIDATED DAMAGES P/day = 1/10 of 1 % of T.C. 100.00

L. Clearing/Disposal of Debris lot 1.000 20-50T 50,000.00

M. SAMPLING & TESTING


Rebar / Concrete / RCP lot 1.000 5-25T 15,000.00
Welding lot 1.000 5-25T 15,000.00
SPT / FDT / MDD lot 1.000 20-90T 15,000.00
45,000.00
N. AS BUILT DRAWING lot 1.000 5-20T 10,000.00

O. DEMOBILIZATION lot 1.000 25-80T 80,000.00

P. RE-SURVEY lot 1.000 25-50T -


Q BILLBOARDS & SIGNAGES LOT 1.000 5-10 T -

Gen. Reqmts. Prelims


Prepared by Ricky
Page 2
PRELIMINARIES
PROJECT : 0 OWNER : 0

LOCATION : 0 DATE : July 15, 2009

LINE UNIT OF
No. I T E M MEA- QUANTITY
SURE

SUMMARY OF GENERAL REQUIREMENTS

1 Mobilization/ Demobilization 220,000.00

2 Permits 283,408.00

3 Bonds & Insurances 73,100.00

4 Temporary Power & Utilities 260,000.00

5 Temporary Facilities
Field office
Warehouse and Storage
Fabrication Shed
Barracks/ Mesh Halls
Temporary Fence
Temporary Toilet
Billboards & Signages
204,000.00
6 Security / Safety / Protection 170,000.00

7 Survey -

8 Construction Drawings/ As Built


Drawings and Shop Drawings 10,000.00

9 Power Tools & Heavy Equipt.


and Transportation 200,000.00

10 House Keeping & Removal


of Debris 50,000.00

11 Material Sampling &Testings 45,000.00

12 Site Management & Expenses 210,000.00

1,725,508.00

Gen. Reqmts. Prelims


Prepared by Ricky
Page 3
PRELIMINARIES
PROJECT : 0 OWNER : 0

LOCATION : 0 DATE : July 15, 2009

LINE UNIT OF
No. I T E M MEA- QUANTITY
SURE

Gen. Reqmts. Prelims


Prepared by Ricky
Page 4
UNIT COST OF CIVIL& STRUCTURAL WORKS
PROJECT : - OWNER : -
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST
No. I T E M MEA- QUANTITY
SURE UNIT TOTAL UNIT TOTAL

A EARTHWORKS

1 LAY-OUT, BATTER BOARDS & STAKES m2 1.00 5.00 15.00

2 EXCAVATION ( Mechanical with Manual Trimming )


Sraight Cut, H <= 1.0 m m3 1.00 - 178.00
Inclined Cut
1.0 < H <= 2.0 m m3 1.00 - 188.00
2.0 < H <= 3.0 m m3 1.00 - 207.00

3 BACK FILL Quantities must have the corresponding swell factors.


m3 1.00 - 54.00
4 COMPACTION
By Vibratory Roller m3 1.00 - 64.00
By Rammer or Plate Compactor m3 1.00 - 62.00

5 CUT & FILL m3


Cut m3 1.00 120.00
Fill m3 1.00 80.00

6 GRAVEL BED
Slab on Fill ( Mech'l ) m3 1.00 570.00 70.00
Footing Pits ( Manual ) m3 1.00 570.00 131.00

7 BASE COURSE w/ COMPACTION Quantities must have the corresponding swell factors.
Driveway, Base course (Mech'l) m3 1.00 510.00 64.00
Sidewalk, Base course (Manual) m3 1.00 510.00 131.00
Sub-base COURSE w/ Binder ( Mech'l ) m3 1.00 300.00 64.00

8 FILLING MATERIALS w/ COMPACTION Quantities must have the corresponding swell factors.
Selected Fill- Crushed Rock, (Mech'l) m3 1.00 200.00 64.00
Selected Fill- Escombro/Lastillas, (Mech'l) m3 1.00 329.00 64.00
Common Fill- Excavated , (Mech'l) m3 1.00 120.00 64.00

9 VAPOR BARRIER
6 Mils PE Sheet m2 1.00 15.00 3.00
Area must have an allowance of 3% for Lapping & Wastage

10 CHEMICAL SOIL TREATMENT


Semi Comprehensive m2 1.00 40.00
Comprehensive m2 1.00 60.00

Structural
Prepared by Ricky Page 5
UNIT COST OF CIVIL& STRUCTURAL WORKS
PROJECT : - OWNER : -
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST
No. I T E M MEA- QUANTITY
SURE UNIT TOTAL UNIT TOTAL

11 RC PIPE LAYING

B CONCRETE WORKS ( Cost of Cement in Bulk* CF + Batching Fee with Sand & Gravel )
CONCRETING ( 3% Wastage for Footing & FTB, rest
2%)
No additional Cost up to 5th Level
1 6,000 PSI Cement Factor
Footing / FTB m3 1.00 17.00 3,986.10 220.00
Columns m3 1.00 18.00 4,120.80 850.00
Mezz Beams & Slab m3 1.00 18.00 4,120.80 220.00
Ramps m3 1.00 18.00 4,120.80 220.00
Mid Beams m3 1.00 18.00 4,120.80 850.00
Gutter/Parapet/Corbel/Rbeam m3 1.00 18.00 4,120.80 1,250.00
Stairs m3 1.00 18.00 4,120.80 1,300.00
1 5,000 PSI Cement Factor
Footing / FTB m3 1.00 15.00 3,635.90 220.00
Columns m3 1.00 16.00 3,774.00 850.00
Mezz Beams & Slab m3 1.00 16.00 3,774.00 220.00
Ramps m3 1.00 16.00 3,774.00 220.00
Mid Beams m3 1.00 16.00 3,774.00 850.00
Gutter/Parapet/Corbel/Rbeam m3 1.00 16.00 3,774.00 1,250.00
Stairs m3 1.00 16.00 3,774.00 1,300.00
2 4,000 PSI Cement Factor
Footing / FTB m3 1.00 11.75 3,066.83 220.00
Columns m3 1.00 12.75 3,210.45 850.00
Mezz Beams & Slab m3 1.00 12.75 3,210.45 220.00
Ramps m3 1.00 12.75 3,210.45 220.00
Mid Beams m3 1.00 12.75 3,210.45 850.00
Gutter/Parapet/Corbel/Rbeam m3 1.00 12.75 3,210.45 1,250.00
Stairs m3 1.00 12.75 3,210.45 1,300.00
RcWall m3 1.00 12.75 3,210.45 850.00
3 3,000 PSI
Footing / FTB m3 1.00 9.00 2,585.30 220.00
Columns m3 1.00 10.00 2,733.60 850.00
Mezz Beams & Slab m3 1.00 10.00 2,733.60 220.00
Ramps m3 1.00 10.00 2,733.60 220.00
Mid Beams m3 1.00 10.00 2,733.60 850.00
Gutter/Parapet/Corbel/Rbeam m3 1.00 10.00 2,733.60 1,250.00
Stairs m3 1.00 10.00 2,733.60 1,300.00
RcWall m3 1.00 10.00 2,733.60 850.00
Driveway m3 1.00 9.00 2,560.20 200.00
4 2,500 PSI 999.60
Slab on Fill / Sidewalk m3 1.00 8.00 2,410.20 200.00
Curb and Gutter m3 1.00 9.00 2,585.30 250.00

Structural
Prepared by Ricky Page 6
UNIT COST OF CIVIL& STRUCTURAL WORKS
PROJECT : - OWNER : -
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST
No. I T E M MEA- QUANTITY
SURE UNIT TOTAL UNIT TOTAL

Fence Footing m3 1.00 8.00 2,410.20 250.00


Fence Col / Miscellaneous m3 1.00 9.00 2,560.20 550.00
5 Pump Design Effect
Additional Cement m3 1.00 1.50 255.00
6 Concrete Placing (G-5th flr.) m3 1.00 140.00
7 Cement Finishing
Finishing , Rough m3 1.00 45.00
Finishing, Smooth m3 1.00 60.00
Finishing , with Hardener m3 1.00 70.00
8 Pump Charge m3 1.00 200.00
9 w/o Pump but with Assistance m3 1.00 30.00

C REBAR WORKS
Labor Cost plus 50 Cents every floor level staring 3/F

1 Grade 33, Discounted kg 1.00 35.00 35.00


Delivery Charge kg 1.00 0.37 0.37
Tie Wire kg 1.00 0.66 0.66
TOTAL COST PER KG P 36.03
Wastage, 2 % kg 0.72
Total Cost W/ Wastage 36.75 4.00

2 Grade 40, Discounted kg 1.00 35.00 35.00


Delivery Charge kg 1.00 0.37 0.37
Tie Wire kg 1.00 0.66 0.66
TOTAL COST PER KG P 36.03
Wastage, 2% kg 0.72
Total Cost W/ Wastage 36.75 4.00

3 Grade 60, Discounted kg 1.00 35.00 35.00


Delivery Charge kg 1.00 0.37 0.37
Tie Wire kg 1.00 0.66 0.66
TOTAL COST PER KG P 36.03
Wastage, 2% kg 0.72
Total Cost W/ Wastage 36.75 4.00

D FORMWORKS
Labor Cost plus 5 % every floor starting 3rd level

1 Footing m2
Ply wood 1/2' Ord. pc 0.50 480.00 240.00
Coco Lumber, Class A BF 16.40 13.50 221.40
CW Nail kg 0.30 33.00 9.74
Tie Wire roll 0.00 1,312.50 5.38
Form Oil li 0.13 33.00 4.29
480.81

Structural
Prepared by Ricky Page 7
UNIT COST OF CIVIL& STRUCTURAL WORKS
PROJECT : - OWNER : -
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST
No. I T E M MEA- QUANTITY
SURE UNIT TOTAL UNIT TOTAL
Wastage ( 3%) 495.24
2-3 Uses 165.08 180.00

2 Slab On Fill lm
Ply wood 1/2' Ord. pc 0.13 480.00 62.40
Coco Lumber, Class A BF 10.00 13.50 135.00
CW Nail kg 0.18 33.00 5.94
Tie Wire roll 0.00 1,312.50 3.28
Form Oil li 0.13 33.00 4.29
210.91
Wastage ( 3%) 217.24
2-3 Uses 217.24 120.00

3 Suspended Slab m2
Phenolic 1/2' pc 0.50 1,400.00 700.00
Coco Lumber, Class A BF 25.00 13.50 337.50
CW Nail kg 0.45 31.00 13.95
Tie Wire roll 0.01 1,312.50 8.20
Form Oil li 0.13 33.00 4.29
1,063.94
Wastage ( 3%) 1,095.86
2-3 Uses 365.29 200.00

4 Beams m2
Phenolic, 1/2 pc 0.50 1,400.00 700.00
Coco Lumber, Class A BF 34.00 13.50 459.00
CW Nail kg 0.61 33.00 20.20
Tie Wire roll 0.01 1,312.50 11.16
Form Oil li 0.13 33.00 4.29
1,194.64
Wastage ( 3%) 1,230.48
2-3 Uses 410.16 200.00

5 Columns m2
Phenolic, 1/2 pc 0.50 1,400.00 700.00
Coco Lumber, Class A BF 33.00 13.50 445.50
CW Nail kg 0.59 33.00 19.60
Tie Wire roll 0.01 1,312.50 10.83
Form Oil li 0.13 33.00 4.29
1,180.22
Wastage ( 3%) 1,215.63
2-3 Uses 405.21 200.00

6 RC Walls m2
Phenolic, 1/2 pc 0.50 1,400.00 700.00
Coco Lumber, Class A BF 19.00 13.50 256.50
CW Nail kg 0.34 33.00 11.29
Tie Wire roll 0.00 1,312.50 6.23

Structural
Prepared by Ricky Page 8
UNIT COST OF CIVIL& STRUCTURAL WORKS
PROJECT : - OWNER : -
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST
No. I T E M MEA- QUANTITY
SURE UNIT TOTAL UNIT TOTAL
Form Oil li 0.13 33.00 4.29
978.31
Wastage ( 3%) 1,007.66
2-3 Uses 335.89 180.00

7 Stairs m2
Ply wood 1/2' Ord. pc 0.50 480.00 240.00
Coco Lumber, Class A BF 35.00 13.50 472.50
CW Nail kg 0.63 33.00 20.79
Tie Wire roll 0.01 1,312.50 11.48
Form Oil li 0.13 33.00 4.29
749.06
Wastage ( 3%) 771.54
2-3 Uses 257.18 300.00

8 Corbel / Gutter m2
Ply wood 1/2' Ord. pc 0.50 480.00 240.00
Coco Lumber, Class A BF 30.00 13.50 405.00
CW Nail kg 0.54 33.00 17.82
Tie Wire roll 0.01 1,312.50 9.84
Form Oil li 0.13 33.00 4.29
676.95
Wastage ( 3%) 697.26
2-3 Uses 232.42 300.00

Structural
Prepared by Ricky Page 9
Labor Cost References
5, 2009

LINE Productivity Table J. capadosa ABSantiago Builders Satuna Construction

TOTAL

20.00 5.00 - 10.00

178.00 178.00 150.00 60.00 75.00

188.00 188.00
207.00 207.00

54.00 54.00 E Q U I P M E N T 80.00

64.00 64.00
62.00 62.00 40.00 100.00 100.00

120.00 120.00
80.00 80.00 20.00

640.00 60.00 70.00 120.00 150.00


701.00 131.00 100.00 120.00 150.00

574.00 64.00 50.00 100.00 50.00


641.00 131.00 50.00 100.00 50.00
364.00 64.00 50.00 100.00 50.00

264.00 64.00 50.00 80.00 20.00


393.00 64.00 50.00 80.00 20.00
184.00 64.00 50.00 80.00 20.00

18.00 3.00 3.00 - -

40.00
60.00

Structural
Prepared by Ricky Page 10
Labor Cost References
5, 2009

LINE Productivity Table J. capadosa ABSantiago Builders Satuna Construction

TOTAL

4,206.10 199.00 180 / 500 2,000.00 150.00


4,970.80 800.00 800.00 800.00 250.00
4,340.80 215.00
4,340.80 215.00 180.00
4,970.80 800.00 800.00 800.00 500.00
5,370.80 1,200.00 1,200.00 1,000.00 700.00
5,420.80 1,225.00 1,200.00 1,000.00 250.00

3,855.90 199.00 180 / 500 2,000.00 150.00


4,624.00 800.00 800.00 800.00 250.00
3,994.00 215.00
3,994.00 215.00 180.00
4,624.00 800.00 800.00 800.00 500.00
5,024.00 1,200.00 1,200.00 1,000.00 700.00
5,074.00 1,225.00 1,200.00 1,000.00 250.00

3,286.83 199.00 180 / 500 2,000.00 150.00


4,060.45 800.00 800.00 800.00 250.00
3,430.45 215.00
3,430.45 215.00 180.00
4,060.45 800.00 800.00 800.00 500.00
4,460.45 1,200.00 1,200.00 1,000.00 700.00
4,510.45 1,225.00 1,200.00 1,000.00 250.00
4,060.45 811.00 800.00 800.00 450.00

2,805.30 199.00 180 / 500 2,000.00 150.00


3,583.60 800.00 800.00 800.00 250.00
2,953.60 215.00 180.00
2,953.60 215.00 180.00
3,583.60 800.00 800.00 800.00 500.00
3,983.60 1,200.00 1,200.00 1,000.00 700.00
4,033.60 1,225.00 1,200.00 1,000.00 250.00
3,583.60 811.00 800.00 800.00 450.00
2,760.20 188.00 120.00 250.00 150.00

2,610.20 188.00 120.00 250.00 150.00


2,835.30 250.00 120.00 250.00 150.00

Structural
Prepared by Ricky Page 11
Labor Cost References
5, 2009

LINE Productivity Table J. capadosa ABSantiago Builders Satuna Construction

TOTAL
2,660.20 210.00 180.00
3,110.20 500.00 500.00 500.00 150.00

255.00
140.00 140.00

45.00 45.00
60.00 60.00 60.00
70.00 70.00 60.00
200.00
30.00 30.00

40.75 4.07 3.00 2.50 3.00

40.75 4.07 3.00 2.50 3.00

40.75 4.07 3.00 2.50 3.00

Structural
Prepared by Ricky Page 12
Labor Cost References
5, 2009

LINE Productivity Table J. capadosa ABSantiago Builders Satuna Construction

TOTAL

345.08 173.00 90.00 - 150.00

337.24 100.00 90.00 40.00 50.00

565.29 175.00 150.00 150.00 150.00

610.16 175.00 120.00 150.00 250.00

605.21 177.00 120.00 150.00 150.00

Structural
Prepared by Ricky Page 13
Labor Cost References
5, 2009

LINE Productivity Table J. capadosa ABSantiago Builders Satuna Construction

TOTAL

515.89 176.00 90.00 150.00 100.00

557.18 254.00 240.00 220.00 250.00

532.42 280.00 240.00 2000/set 250.00

Structural
Prepared by Ricky Page 14
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
MASONRY WORKS
CHB LAYING : 8" (w/o plastering) m2
8" x 8" x 16" CHB pcs 12.50 31.50 393.75
1:3 mix, Cement bag 0.55 180.00 99.00
Sand m3 0.05 660.00 33.00
Total cost per sq.m. P 525.75
Wastage of 3% lot 1.00 15.77
Total cost per sq.m. w/ wastage P 541.52
Rebars, 12 mm dia. (.60m Vert) kg 1.89 36.03 68.14 4.00 7.57 75.71
Rebars, 10 mm dia. (.60m Hor.) kg 1.32 36.03 47.71 4.00 5.30 53.01
Cost of Rebars per sq.m. P 115.85
Total cost per sq.m. w/ wastage & rebars P 657.38 110.00 767.38 118.00

CHB LAYING : 6" (w/o plastering) m2


6" x 8" x 16" CHB pcs 12.50 17.50 218.75
1:3 mix, Cement bag 0.55 180.00 99.00
Sand m3 0.05 660.00 33.00
Total cost per sq.m. P 350.75
Wastage of 3% lot 1.00 10.52
Total cost per sq.m. w/ wastage P 361.27
Rebars, 12 mm dia. (.60m Vert) kg 1.89 36.03 68.14 4.00 7.57 75.71
Rebars, 10 mm dia. (.60m Hor) kg 1.32 36.03 47.71 4.00 5.30 53.01
Cost of Rebars per sq.m. P 115.85
Total cost per sq.m. w/ wastage & rebars P 477.13 110.00 587.13 126.67

CHB LAYING : 4" (w/o plastering) m2


4" x 8" x 16" CHB pcs 12.50 14.20 177.50
1:3 mix, Cement bag 0.55 180.00 99.00
Sand m3 0.05 660.00 33.00
Total cost per sq.m. P 309.50
Wastage of 3% lot 1.00 9.29
Total cost per sq.m. w/ wastage P 318.79
Rebars, 12 mm dia.(Vert.) kg 1.89 36.03 68.14 4.00 7.57 75.71
Rebars, 10 mm dia. (.60m Hor.) kg 1.32 36.03 47.71 4.00 5.30 53.01
Cost of Rebars per sq.m. P 115.85
Total cost per sq.m. w/ wastage & rebars P 434.64 110.00 544.64 99.00

0.15 X 0.30 M LINTEL BEAMS & COLUMNS l.m


Concrete cu.m. 0.05 2,560.20 115.21 850.00 38.25
Rebars w/ Ties (4- 12 & 10 dia.@ 0.20 m ) kg 6.02 36.03 216.73 4.00 24.06
Forms m2 0.60 200.00 120.00 200.00 200.00
Total cost per l.m. 451.94 262.31 714.26
Wastage 3% 13.56
Total Cost per l.m.w/ wastage 465.50 727.82

Architectural
Prepared by Ricky Page 15
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL

0.10 x 0.20 M LINTELS BEAMS & COLUMNS l.m


Concrete cu.m. 0.02 2,560.20 51.20 850.00 17.00
Rebars w/ Ties ( 4-12& 10 dia.@ 0.20 m ) kg 5.09 36.03 183.45 4.00 20.37
Forms m2 0.40 200.00 80.00 200.00 80.00
Total cost per l.m. 314.65 117.37 432.02
Wastage 3% 9.44
Total Cost per l.m.w/ wastage 324.09 441.46

CONCRETE TOPPING
CONCRETE TOPPING 75 MM THK. m2
Thickness, 1:3 mix mm 75.00
Cement bag 0.90 180.00 162.00
Sand m3 0.08 660.00 49.50
Ga.10, 4"x4" w.w.mesh sht 0.12 450.00 54.00
Total cost per sq.m. P 265.50
Wastage of 3% lot 1.00 7.97
Total cost per sq.m. w/ wastage P 273.47 110.00 383.47 70.00

CONCRETE TOPPING 40 MM THK. m2


Thickness, 1:3 mix mm 40.00
Cement bag 0.48 180.00 86.40
Sand m3 0.04 660.00 26.40
Total cost per sq.m. P 112.80
Wastage of 3% lot 1.00 3.38
Total cost per sq.m. w/ wastage P 116.18 110.00 226.18 70.00

FLOOR FINISHES

PLAIN CEMENT FINISH m2


Thickness, 1:3 mix mm 15.00
Cement bag 0.18 180.00 32.40
Sand m3 0.02 660.00 9.90
Additional Cement kg 3.00 4.50 13.50
Total cost per sq.m. P 55.80
Wastage of 3% lot 1.00 1.67
Total cost per sq.m. w/ wastage P 57.47 60.00 117.47 55.00

STRAIGHT TO FINISH m2
Total cost per sq.m. 60.00 60.00 60.00

PLAIN CEMENT COLORED FINISH m2


Thickness, 1:3 mix mm 15.00
Cement bag 0.18 180.00 32.40
Sand m3 0.02 660.00 9.90
Additional Cement kg 3.00 35.00 105.00

Architectural
Prepared by Ricky Page 16
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
Total cost per sq.m. P 147.30
Wastage of 3% lot 1.00 4.42
Total cost per sq.m. w/ wastage P 151.72 72.00 223.72 72.00

VINYL TILES, 3 x 300mm sq. m2


Vinyl Tiles pcs 12.00 29.00 348.00 4.00 48.00
Adhesive m2 1.00 20.50 20.50
TOTAL COST PER S.M. P 368.50 48.00 416.50 51.00

VINYL PLANKS, 6"x 36"x3mm m2


Vinyl Planks pcs. 7.29 100.00 729.00 10.00 72.90
Adhesive m2 1.00 20.50 20.50
TOTAL COST PER S.M. P 749.50 72.90 822.40

VINYL PLANKS, 4"x 36"x3mm m2


Vinyl Planks pcs. 10.94 44.00 481.36 4.50 49.23
Adhesive m2 1.00 20.50 20.50
TOTAL COST PER S.M. P 501.86 49.23 551.09

PVC NOSING l.m. 1.00 100.00 20.00 120.00 16.50

NON-SKID TILES, 200mm sq. m2


Tiles pcs 25.00 8.00 200.00
Adhesive, ABC kg 5.00 8.96 44.79
Grout, ABC kg - 25.00 -
Thickness, 1:3 mix, Mortar Bed mm 40.00
Cement bag 0.48 180.00 86.40
Sand m3 0.04 660.00 26.40
Total cost per sq.m. P 357.59
Wastage of 3% lot 1.00 10.73
Total cost per sq.m. w/ wastage P 368.32 210.00 578.32 154.00

UNGLAZED CERAMIC TILES, 200mm sq. m2


Tiles pcs 25.00 15.00 375.00
Adhesive, ABC kg 5.00 8.96 44.79
Grout, ABC kg 0.30 25.00 7.50
Thickness, 1:3 mix, Mortar Bed mm 30.00
Cement bag 0.36 180.00 64.80
Sand m3 0.03 660.00 19.80
Total cost per sq.m. P 511.89
Wastage of 3% lot 1.00 15.36
Total cost per sq.m. w/ wastage P 527.25 190.00 717.25 234.00

Architectural
Prepared by Ricky Page 17
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL

UNGLAZED CERAMIC TILES, 300mm sq. m2


Tiles pcs 11.11 35.00 388.89
Adhesive, ABC kg 5.00 8.96 44.79
Grout, ABC kg 0.30 25.00 7.50
Thickness, 1:3 mix, Mortar Bed mm 30.00
Cement bag 0.36 180.00 64.80
Sand m3 0.03 660.00 19.80
Total cost per sq.m. P 525.78
Wastage of 3% lot 1.00 15.77
Total cost per sq.m. w/ wastage P 541.56 190.00 731.56 234.00

UNGLAZED CERAMIC TILES, 108mm sq. m2


Tiles pcs 100.00 6.00 600.00
Adhesive, ABC kg 5.00 8.96 44.79
Grout, ABC kg 0.30 25.00 7.50
Thickness, 1:3 mix, Mortar Bed mm 20.00
Cement bag 0.24 180.00 43.20
Sand m3 0.02 660.00 13.20
Total cost per sq.m. P 708.69
Wastage of 3% lot 1.00 21.26
Total cost per sq.m. w/ wastage P 729.95 190.00 919.95 234.00

PEBBLE WASHED OUT FINISH m2


Mortar Bed mm 35.00
Cement bag 0.40 180.00 72.00
Sand m3 0.04 660.00 26.40
Washed Out Mixture
Cement m3 0.40 180.00 72.00
# 10 Pebbles pail 0.67 90.00 60.30
( 1 pail = 2sacks = 1 cu.ft.)
Toatl Cost Per sq.m. 230.70
Wastage of 3% lot 1.00 6.92
Total cost per sq.m. w/ wastage P 237.62 220.00 457.62 232.00

FLOOR HARDENER APPLICATION m2


Colored
(Floor Hardener, Florgard by Rebtrade kg 30 kg/bag 975.00
Light Traffic kg 3.00 97.50 107.50
Medium Traffic kg 4.00 130.00 140.00
Heavy trafic kg 5.00 162.50 172.50
Extra Heavy Traffic kg 6.00 195.00 10.00 205.00
Natural Color
Floor Hardener, Florgard by Rebtrade kg 30 kg/bag 850.00
Light Traffic kg 3.00 85.00 95.00
Medium Traffic kg 4.00 113.33 123.33

Architectural
Prepared by Ricky Page 18
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
Heavy trafic kg 5.00 141.67 151.67
Extra Heavy Traffic kg 6.00 170.00 10.00 180.00

CONTROL JOINTS
CONTRACTION JOINTS l.m.
Bostik " Seal N Flex" Sealant tube 420.00
l.m. 1.00 93.33 93.33 5.00 5.00
Soft Cut/ Saw Cut l.m. 1.00 25.00 25.00 25.00
TOTAL COST PER L.M. 93.33 30.00 123.33

ISOLATION JOINTS l.m.


Bostik " Seal N Flex" Sealant tube 420.00
l.m. 1.00 93.33 93.33 5.00
Rubber Filler l.m. 1.00 80.00 80.00 5.00
173.33 10.00 183.33

WALL FINISHES

PLAIN CEMENT PLASTERED FINISH m2


Thickness, 1:3 mix mm 20.00
Cement bag 0.36 180.00 64.80
Sand m3 0.02 660.00 13.20
Additional Cement kg 3.00 4.50 13.50
Total cost per sq.m. P 91.50
Wastage of 3% lot 1.00 2.75
Total cost per sq.m. w/ wastage P 94.25 100.00 194.25 120.00
TOTAL COST PER L.M. P 47.12 50.00 97.12 60.00

GLAZED CER. TILES, 200 mm sq. m2


Tiles pcs 25.00 15.00 375.00
Adhesive, ABC kg 5.00 8.96 44.79
Grout, ABC kg 0.30 25.00 7.50
Thickness, 1:3 mix, Mortar mm 20.00
Cement bag 0.24 180.00 43.20
Sand m3 0.02 660.00 13.20
Total cost per sq.m. P 483.69
Wastage of 3% lot 1.00 14.51
Total cost per sq.m. w/ wastage P 498.20 210.00 708.20 262.00
GLAZED CER.TILES, 300 mm sq. m2
Tiles pcs 11.11 35.00 388.89

Architectural
Prepared by Ricky Page 19
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL
Adhesive, ABC kg 5.00 8.96 44.79
Grout, ABC kg 0.30 25.00 7.50
Thickness, 1:3 mix, Mortar mm 20.00
Cement bag 0.24 180.00 43.20
Sand m3 0.02 660.00 13.20
Total cost per sq.m. P 497.58
Wastage of 3% lot 1.00 14.93
Total cost per sq.m. w/ wastage P 512.51 210.00 722.51 262.00

GLAZED CER.TILES, 108 mm sq. m2


Tiles pcs 100.00 6.00 600.00
Adhesive, ABC kg 5.00 8.96 44.79
Grout, ABC kg 0.30 25.00 7.50
Thickness, 1:3 mix, Mortar mm 20.00
Cement bag 0.24 180.00 43.20
Sand m3 0.02 660.00 13.20
Total cost per sq.m. P 708.69
Wastage of 3% lot 1.00 21.26
Total cost per sq.m. w/ wastage P 729.95 210.00 939.95 262.00

PVC TILE TRIM lm 1.00 80.00 80.00 10.00 90.00 14.00

CEILING FINISHES

RUBBED CONCRETE FINISH m2


Cement bag 0.07 4.50 0.32
Sand cu.m. 0.01 660.00 6.60
Grinding sm 1.00 8.50 8.50
P 15.42
3% Wastage 0.46
TOTAL COST PER S.M. 15.88 50.00 65.88 51.00
TOTAL COST PER L.M. P 7.94 25.00 32.94 25.50

MARBLE SLAB COUNTERS m2

Marble Material sm 1.00 1,200.00 1,200.00


Cement & Sand for Mortar Bedding sm 1.00 116.18 116.18
Polituff & Wax sm 1.00 38.73 38.73
P 1,354.91
Countertop Slab lm 1.00 250.00 250.00
Splash Board Slab lm 1.00 250.00 250.00
Fascia /Senepa Board Slab lm 1.00 250.00 250.00
Ovaline Holes lm 1.00 300.00 300.00

Architectural
Prepared by Ricky Page 20
UNIT COST OF ARCHITECTURAL WORKS
PROJECT : - OWNER : - Labor Co
LOCATION : - DATE : July 15, 2009
LINE UNIT OF
MATERIAL COST LABOR COST LINE
Productivity
No. I T E M MEA- QUANTITY Table
TOTAL
SURE UNIT TOTAL UNIT TOTAL

0.15 X 0.20 M LINTEL BEAMS & COLUMNS m2


Concrete cu.m. 0.03 2,560.20 76.81 - -
Rebars w/ Ties (4- 12 & 10 dia.@ 0.30 m ) kg 5.52 36.03 198.98 - -
Forms m2 0.40 200.00 80.00 - 200.00
Total cost per l.m. 355.79 200.00 555.79
Wastage 3% 10.67
Total Cost per l.m.w/ wastage 366.46 566.46

0.10 x 0.20 M LINTELS BEAMS & COLUMNS l.m.


Concrete cu.m. 0.02 2,560.20 51.20 - -
Rebars w/ Ties ( 4-12& 10 dia.@ 0.30 m ) kg 4.78 36.03 172.35 - -
Forms m2 0.40 200.00 80.00 - -
Total cost per l.m. 303.55 - 303.55
Wastage 3% 9.11
Total Cost per l.m.w/ wastage 312.66 312.66

Architectural
Prepared by Ricky Page 21
Labor Cost References

ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction

100.00 90.00 100.00 90.00

100.00 90.00 100.00 90.00

100.00 90.00 100.00 90.00

80.00 220.00 244.00

Architectural
Prepared by Ricky Page 22
Labor Cost References

ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction

80.00 220.00 244.00

100.00 50.00 120.00 60.00

100.00 50.00 120.00 60.00

56.00 120.00

- - 60.00

Architectural
Prepared by Ricky Page 23
Labor Cost References

ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction

56.00

150.00 200.00

150.00 175.00 180.00 200.00

Architectural
Prepared by Ricky Page 24
Labor Cost References

ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction

150.00 180.00 200.00


175.00

150.00 175.00 180.00 200.00

100.00 200.00

Architectural
Prepared by Ricky Page 25
Labor Cost References

ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction

7.00 20.00
15.00

90.00 85.00 100.00 90.00


40.00 55.00 50.00 45.00

150.00 165.00 200.00 200.00

Architectural
Prepared by Ricky Page 26
Labor Cost References

ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction

150.00 165.00 200.00 200.00

150.00 165.00 200.00 200.00

5.00 50.00 20.00

40.00 50.00 60.00 60.00


40.00 35.00 60.00 30.00

Architectural
Prepared by Ricky Page 27
Labor Cost References

ABSantiago Satuna
J. Capadosa T. Paubsanon
Builders Construction

80.00 220.00 244.00

80.00 220.00 244.00

Architectural
Prepared by Ricky Page 28
PAINTING SYSTEM COST BY BOYSEN
As of August 2006
PRICE RANGE
PAINT SYSTEM
PER SQUARE METER

Interior & Exterior Concrete Finishes


Plain Finish
Interior
Permacoat Latex System
( Spot Putty : B-7311 ) P 130.00 - P 135.00
( Full Putty : B-7311 ) P 157.00 - P 165.00
Exterior - -
Permacoat Latex System - -
( Spot Putty : B-1711 ) P 168.00 - P 175.00
Permacoat Wall Guard System P 197.00 - P 205.00
Acrytex System P 220.00 - P 230.00
Tile Kote Polyurethane ( Poly U-2K System ) P 300.00 - P 315.00
- -
Textured Finish - -
Acrytex System P 385.00 - P 395.00
Acrytex System with Latex Topcoat P 323.00 - P 335.00
Acrytex System with" Tile Kote "Topcoat P 495.00 - P 520.00
Plexibond with Latex Top Coat P 365.00 - P 375.00
Plexibond with Acrytex Top Coat P 438.00 - P 450.00
Plexibond with "Tile Kote" Top Coat P 577.00 - P 600.00
Modified Stonetek Finish P 555.00 - P 575.00
- -
Concrete Flooring - -
Acqua Epoxy System ( Green ) P 258.00 - P 270.00
Acqua Epoxy System ( Other Color ) P 245.00 - P 255.00
Epoxy Enamel ( White & Red ) P 275.00 - P 285.00
Epoxy Enamel ( Other Color) P 252.00 - P 265.00

Interior Concrete Finishes


Plain Finish
Permacoat Lo-Odor System ( Interior Repainting ) P 82.00 - P 92.00
Flat Wall Enamel System P 150.00 - P 155.00
Quick Drying Enamel System P 155.00 - P 160.00
Oil Wood Stain w/ Varnish P 415.00 - P 425.00
Automotive Lacquer Finish (Ducco) P 560.00 - P 580.00
Xyladecor w/ Varnish Finish P 495.00 - P 510.00
- -
Plain Finish with Design - -
Multi -fleck Finish - Sparse P 225.00 - P 235.00
Multi -fleck Finish - Medium Dense P 250.00 - P 260.00
Multi -fleck Finish - Super Dense P 390.00 - P 400.00
DECORe Finish ( without Border ) P 355.00 - P 365.00
DECORe Border ( per linear meter ) P 90.00 - P 130.00
PRICE RANGE
PAINT SYSTEM
PER SQUARE METER

Textured Finish w/ Design - -


Permatex P 285.00 - P 295.00
Permatex with Top Coat P 395.00 - P 405.00
Wooden Surfaces
Plain Finish
Flat Wall Enamel System P 150.00 - P 155.00
Quick Drying Enamel System P 155.00 - P 160.00
Oil Wood Stain w/ Varnish P 415.00 - P 425.00
Automotive Lacquer Finish (Ducco) P 560.00 - P 580.00
Xyladecor w/ Varnish Finish P 495.00 - P 510.00
- -
Plain Finish w/ Design - -
Multi -fleck Finish - Sparse P 225.00 - P 235.00
Multi -fleck Finish - Medium Dense P 250.00 - P 260.00
Multi -fleck Finish - Super Dense P 390.00 - P 400.00
DECORe without Border P 355.00 - P 365.00
DECORe Border ( per linear meter ) P 90.00 - P 130.00
- -
Textured Finish w/ Design - -
Permatex P 285.00 - P 295.00
Permatex with Top Coat P 395.00 - P 405.00

Roofing
Roof Guard P 160.00 - P 165.00

Metal Surfaces
Quick Drying Enamel System w/ B-370 P 135.00 - P 140.00
Quick Drying Enamel System w/ B-320 P 132.00 - P 140.00
Quick Drying Enamel System w/ B-4310 P 120.00 - P 125.00
Acqua Epoxy System ( Green ) P 255.00 - P 265.00
Acqua Epoxy System ( Other Color ) P 240.00 - P 250.00
Epoxy Enamel ( White & Red ) P 265.00 - P 275.00
Epoxy Enamel ( Other Color) P 240.00 - P 250.00

Plastering
Skimkote ( No Top Coat ) P 100.00 - P 105.00

Coverage = 25 sq.m. / 4 liters


LABOR COST DERIVATION
( Based on Productivity Rate )

EXCAVATION ( Straight Cut)

Equipment Cost: Rental Rate Productivity Efficiency


P m3 Hr. Hr. P
Backhoe = 1300.00 div 20.000 x 8.00 div 7.00 = 74.29
Hr. Hr. day day m3
Fuel Price Consumption
P Li P
Diesel : 36.78 x 10.00 = 367.80
Li Hr. Li

P Li P
Oil : 1705.00 x 0.50 = 852.50
Li Hr. Li
P
1220.30
Li
P m3 Hr. Hr. P
= 1220.30 div 20.00 x 8.00 div 7.00 = 69.73
Li Hr. day day m3

P P P
Total EquipCost = 74.29 + 69.73 x 80% = 115.21
m3 m3 m3

Laborer
Labor Cost : U. Rate Productivity
P m3 P
= 300.00 div 1.00 = 300.00
M-D M-D m3

P
Total Labor Cost = 300.00 x 20% = 60.00
m3

P
175.21
m3
EXCAVATION ( Inclined Cut,1.0<H>2.0 m)

Equipment Cost: Rental Rate Productivity Efficiency


P m3 Hr. Hr. P
Backhoe = 1300.00 div 18.000 x 8.00 div 7.00 = 82.54
Hr. Hr. day day m3
Fuel Price Consumption
P Li P
Diesel : 36.78 x 10.00 = 367.80
Li Hr. Li

P Li P
Oil : 1705.00 x 0.50 = 852.50
Li Hr. Li
P
1220.30
Li

P m3 Hr. Hr. P
= 1220.30 div 18.00 x 8.00 div 7.00 = 77.48
Li Hr. day day m3
P P P
Total EquipCost = 82.54 + 77.48 x 80% = 128.02
m3 m3 m3

ProdRate Page 33
Labor Cost : U. Rate Productivity
P m3 P
Laborer = 300.00 div 0.65 = 461.54
M-D M-D m3

P
Total Labor Cost = 461.54 x 20% = 92.31
m3
P
220.32
m3

EXCAVATION ( Inclined Cut,2.0<H>3.0 m)

Equipment Cost: Rental Rate Productivity Efficiency


P m3 Hr. Hr. P
Backhoe = 1300.00 div 15.000 x 8.00 div 7.00 = 99.05
Hr. Hr. day day m3
Fuel Price
P Li P
Diesel : 36.78 x 10.00 = 367.80
Li Hr. Li

P Li P
Oil : 1705.00 x 0.50 = 852.50
Li Hr. Li
P
1220.30
Li

P m3 Hr. Hr. P
= 1220.30 div 15.00 x 8.00 div 7.00 = 92.98
Li Hr. day day m3
P P P
Total EquipCost = 99.05 + 92.98 x 80% = 153.62
m3 m3 m3

Labor Cost : U. Rate Productivity


P m3 P
Laborer = 300.00 div 0.65 = 461.54
M-D M-D m3

P
Total Labor Cost = 461.54 x 20% = 92.31
m3
P
245.93
m3

BACKFILL
Equipment Cost: Rental Rate Productivity Efficiency
P m3 Hr. Hr. P
Backhoe = 1300.00 div 40.000 x 8.00 div 7.00 = 37.14
Hr. Hr. day day m3
Fuel Price Consumption
P Li P
Diesel : 36.78 x 10.00 = 367.80
Li Hr. Li

P Li P
Oil : 1705.00 x 0.50 = 852.50
Li Hr. Li
P
1220.30
Li

ProdRate Page 34
P m3 Hr. Hr. P
= 1220.30 div 40.00 x 8.00 div 7.00 = 34.87
Li Hr. day day m3
P P P
Total EquipCost = 37.14 + 34.87 = 72.01
m3 m3 m3

COMAPACTION BY VIBRATORY ROLLER

Equipment Cost: Rental Rate Productivity Efficiency


P m3 Hr. Hr. P
Roller = 1400.00 div 66.000 x 8.00 div 7.00 = 24.24
Hr. Hr. day day m3
Fuel Price Consumption
P Li P
Diesel : 36.78 x 10.00 = 367.80
Li Hr. Li

P Li P
Oil : 1705.00 x 0.50 = 852.50
Li Hr. Li
P
1220.30
Li
P m3 Hr. Hr. P
= 1220.30 div 20.00 x 8.00 div 7.00 = 69.73
Li Hr. day day m3

P P P
Total EquipCost = 24.24 + 69.73 = 93.97
m3 m3 m3

COMPACTION BY TAMPING RAMMER OR PLATE COMPACTOR

Equipment Cost :
Tamping P P
= 1500.00 = 1500.00
Rammer E-D E-D

P Li P
Fuel = 36.78 x 9.00 = 331.02
Li E-D E-D
Labor Cost :
P M-D P
Operator = 300.00 x 1.00 = 300.00
M-D E-D E-D
P m3 P
2131.02 div 32.00 = 66.59
E-D E-D m3
P
66.59
m3

HAUL OUT
Equipment Cost :
P Hr. P
B'Hoe = 1300.00 x 8.00 x 1.00 = 10,400.00
Hr. Day Day
Dump P Hr. P
= 800.00 x 8.00 x 2.00 = 12,800.00
Truck Hr. Day Day
Fuel
P Li P
Diesel = 36.78 x 10.00 x 8.00 = 2942.40
Li Hr. Day
P Li P
= 36.78 x 10.00 x 8.00 = 2942.40
Li Hr. Day
P Li P
Oil = 1705.00 x 0.50 x 8.00 = 6820.00
Li Hr. Day

ProdRate Page 35
P Li P
= 1705.00 x 0.25 x 8.00 = 3410.00
Li Hr. Day
P
39,314.80
Day
Total P m3
= 39,314.80 div 269.00
Cost Day E-D

P
146.15
m3

VAPOR BARRIER ( Polyethelene Sheet, 10 mils)


Unit Rate Productivity
P m2 P
Labor = 300.00 div 100.00 = 3.00
M-D M-D m2

GRAVEL BEDDING

Labor Cost : Unit Rate Productivity


P m3 P
Helper = 300.00 div 3.00 = 100.00
M-D M-D m3

Equipment Cost Rental rate Productivity


Plate P m3 P
= 1500.00 div 40.00 = 37.50
Compactor E-D E-D m3

P
137.50
m3

SOIL POISONING
Unit Rate Productivity
P m2 P
Labor = 300.00 div 90.00 = 3.33
M-D M-D m2

FORM WORKS

COLUMNS
Unit Rate Productivity
P m2 P
Carpenter = 350.00 div 1.98 = 176.77
M-D M-D m2

BEAMS/GIRDERS Unit Rate Productivity


P m2 P
Carpenter = 350.00 div 2.00 = 175.00
M-D M-D m2

FOOTING /TIE BEAMS Unit Rate Productivity

ProdRate Page 36
P m2 P
Carpenter = 350.00 div 2.03 = 172.41
M-D M-D m2

SUSPENDED SLAB Unit Rate Productivity


P m2 P
Carpenter = 350.00 div 2.00 = 175.00
M-D M-D m2

RC WALL Unit Rate Productivity


P m2 P
Carpenter = 350.00 div 1.99 = 175.88
M-D M-D m2

CORBEL/GUTTER/RBEAM/ PARAPET
Unit Rate Productivity
P m2 P
Carpenter = 350.00 div 1.25 = 280.00
M-D M-D m2
STAIRS
Unit Rate Productivity
P m2 P
Carpenter = 350.00 div 1.38 = 253.62
M-D M-D m2

CURB & GUTTER


Unit Rate Productivity
P m2 P
Carpenter = 350.00 div 2.915 = 120.07
M-D M-D m2

REBARS
Grade 33
Unit Rate Productivity
P kg P
Steelman = 350.00 div 65.00 = 5.38
M-D M-D kg

Grade 40 Unit Rate Productivity P


3.74
P kg P kg
Steelman = 350.00 div 150.00 = 2.33
M-D M-D kg average of various grades

Grade 60
Unit Rate Productivity
P kg P
Steelman = 350.00 div 100.00 = 3.50
M-D M-D kg
Equipment Cost:

Electric Bar Cutter = 344


Manual Bar Cutter D28 = 152
Manual Bar CutterD17 = 152
Electric Bar Bender = 344

ProdRate Page 37
P kg P
992 div 3000 = 0.33
E-D E-D kg

CONCRETING

COLUMNS
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 0.38 = 800.00
M-D M-D m3

BEAMS/ GIRDER
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 0.38 = 800.00
M-D M-D m3

SUSPENDED SLAB WITH BEAMS


Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 1.40 = 214.29
M-D M-D m3

FOOTING/TIE BEAMS
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 1.51 = 198.68
M-D M-D m3

RC WALLS
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 0.37 = 810.81
M-D M-D m3

GUTTERS/PARAPET/ CORBEL/RBEAM
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 0.25 = 1224.49
M-D M-D m3

STAIRS
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 0.25 = 1200.00
M-D M-D m3

SLAB ON FILL/SIDE WALK


Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 1.60 = 187.50

ProdRate Page 38
Pouring Crew = 300.00 div 1.60 = 187.50
M-D M-D m3

DRIVEWAY
Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 1.75 = 171.43
M-D M-D m3

CURB & GUTTER


Unit Rate Productivity
P m3 P
Pouring Crew = 300.00 div 1.20 = 250.00
M-D M-D m3

MASONRY
Below 5m
CHB 8" thk. Unit Rate Productivity
Installation P m2 P
Mason = 350.00 div 4.45 = 78.65
M-D M-D m2
Hauling
Unit Rate Productivity
CHB P m2 P
Helper = 300.00 div 20.00 = 15.00
M-D M-D m2
Mortar P m3 m3 P
Helper = 300.00 div 4.20 x 0.05 = 3.57
M-D M-D m2 m2
Job Mix P m3 m3 P
Helper = 280.00 div 4.20 x 1.05 = 20.00
M-D M-D m2 m2
P
38.57
m2
P
117.22
m2
above 5m
Installation and Hauling Cost Plus P
117.22
m2
Additional Lifting Cost P
11.72
m2
Equipment
P m3 P
Mixer = 20.00 x 0.03 = 0.60
m2 m2 m2

Ave Cost = 117.37


Below 5m
CHB 6" thk. Unit Rate Productivity
Installation P m2 P
Mason = 350.00 div 5.00 = 70.00
M-D M-D m2
Hauling
Unit Rate Productivity
CHB P m2 P
Helper = 300.00 div 20.00 = 15.00
M-D M-D m2
Mortar P m3 m3 P
Helper = 300.00 div 4.20 x 0.05 = 3.57
M-D M-D m2 m2
Job Mix P m3 m3 P
Helper = 280.00 div 4.20 x 1.05 = 20.00

ProdRate Page 39
Helper = 280.00 div 4.20 x 1.05 = 20.00
M-D M-D m2 m2
P
38.57
m2
P
108.57
m2
above 5m
Installation and Hauling Cost Plus P
108.57
m2
Additional Lifting Cost P
10.86
m2
Equipment
P m3 P
Mixer = 20.00 x 0.03 = 0.60
m2 m2 m2

Ave Cost = 109.10

Below 5m
CHB 4" thk. Unit Rate Productivity
Installation P m2 P
Mason = 350.00 div 5.93 = 59.02
M-D M-D m2
Hauling
Unit Rate Productivity
CHB P m2 P
Helper = 300.00 div 20.00 = 15.00
M-D M-D m2
Mortar P m3 m3 P
Helper = 300.00 div 4.20 x 0.05 = 3.57
M-D M-D m2 m2
Job Mix P m3 m3 P
Helper = 280.00 div 4.20 x 1.05 = 20.00
M-D M-D m2 m2
P
38.57
m2
P
97.59
m2
above 5m
Installation and Hauling Cost Plus P
97.59
m2
Additional Lifting Cost P
9.76
m2
Equipment
P m3 P
Mixer = 20.00 x 0.03 = 0.60
m2 m2 m2

Ave Cost = 98.23

CONCRETE LOUVER BLOCK


Unit Rate Productivity
P m2 P
Mason = 350.00 div 2.50 = 140.00
M-D M-D m2

P
Equipment = 2.50
m2

ProdRate Page 40
142.50 P
PLASTERING

Interior Plastering @ Ground Floor


below 5m Unit Rate Productivity
P m2 P
Mason = 350.00 div 4.00 = 87.50
M-D M-D m2
Hauling
Mortar P m3 m3 P
Helper = 300.00 div 3.00 x 0.05 = 5.00
M-D M-D m2 m2
Job Mix P m3 m3 P
Helper = 300.00 div 3.00 x 1.05 = 20.00
M-D M-D m2 m2
P
112.50
Interior Plastering above 5m m2
P
= 123.75
m2

Equipment Unit Rate


P m3 P
Mixer = 4.00 x 0.03 = 0.12
m2 m2 m2
P
112.62
m2

Exterior Plastering
below 3m
Unit Rate Productivity
P m2 P
Mason = 350.00 div 4.00 = 87.50
M-D M-D m2
Hauling
Mortar P m3 m3 P
Helper = 300.00 div 2.00 x 0.05 = 7.50
M-D M-D m2 m2
Job Mix P m3 m3 P
Helper = 280.00 div 2.00 x 1.05 = 20.00
M-D M-D m2 m2
P
115.00
above 5m m2
P
= 126.50
m2

Equipment Unit Rate


P m3 P
Mixer = 4.20 x 0.03 = 0.13
m2 m2 m2

RUBBED CONCRETE FINISH


below 3m
Unit Rate Productivity
P m2 P
Mason = 350.00 div 6.96 = 50.29
M-D M-D m2
P
50.29
above 5m m2
P
= 55.32
m2

ProdRate Page 41
Equipment Unit Rate
P m3 P
Mixer = 4.20 x 0.03 = 0.13
m2 m2 m2

TOPPING
Unit Rate Productivity
P m2 P
Mason = 350.00 div 5.00 = 70.00
M-D M-D m2

PLAIN CEMENT FINISH/COLORED CEMENT FINISH


Unit Rate Productivity
P m2 P
Mason = 350.00 div 6.40 = 54.69
M-D M-D m2

P m2 P
= 350.00 div 5.33 = 65.63
M-D M-D m2

STRAIGHT TO FINISH
Unit Rate Productivity
P m2 P
Mason = 350.00 div 8.75 = 40.00
M-D M-D m2

VINYL TILES
Unit Rate Productivity
P m2 P
Installer = 350.00 div 6.88 = 50.91
M-D M-D m2

NON SKID TILES FOR DRIVEWAY


Unit Rate Productivity
P m2 P
Installer = 350.00 div 2.29 = 153.13
M-D M-D m2

FLOOR TILES
Unit Rate Productivity
P m2 P
Tile Setter = 350.00 div 1.50 = 233.33
M-D M-D m2
WALL TILES
Unit Rate Productivity
P P
Tile Setter = 350.00 div 1.34 = 261.19
M-D M-D m2
TILE TRIM P L.M. P
Tile Setter = 350.00 div 25.00 = 14.00
M-D M-D L.M.

PEBBLE WASHED OUT


Unit Rate Productivity
P m2 P
Mason = 350.00 div 1.51 = 231.88
M-D M-D m2

MARBLE COUNTERS GRANITE COUNTERS

Setting / Installation

ProdRate Page 42
Counter Tops 250 450 Italian Granite - 4500- 5500 / sq.m.
lm lm China Granite - 1500-2500 / sq.m.
Splash Board 250 450 Marbles - 950-1200 / sq.m.
lm lm

Fascia Board 250 450


lm lm
Ovaline Provision 300 1000
hole hole
Bull Nose Design 300 800
lm lm
Cutting none 80
DOORS & WINDOWS lm

Wooden Door & Jamb, Standard Size & 1-Panel

Unit Rate Productivity


P m2 P
Carpenter = 350.00 div 1.20 = 291.67
M-D M-D m2

Steel Windows / Steel Louver


Unit Rate Productivity
P m2 P
Installer = 350.00 div 1.70 = 205.88
M-D M-D m2
Steel Door w/ Jamb, Standard Size & I-Panel

Unit Rate Productivity


P m2 P
Installer = 350.00 div 0.73 = 479.45
M-D M-D m2
Lockset
Unit Rate Productivity
P set P
Installer = 350.00 div 2.50 = 140.00
M-D M-D set

Door Closer
Unit Rate Productivity
P set P
Installer = 350.00 div 2.00 = 175.00
M-D M-D set
Indicator Lock
Unit Rate Productivity
P set P
Installer = 350.00 div 3.20 = 109.38
M-D M-D set

Flush Bolt
Unit Rate Productivity
P nos P
Installer = 350.00 div 4.00 = 87.50
M-D M-D nos.

Push Plate
Unit Rate Productivity
P nos P
Installer = 350.00 div 6.00 = 58.33
M-D M-D nos.

LAYING OF CONCRETE PIPES

1. 4" TO 18 " diameter Productivity P


71.26

ProdRate Page 43
71.26
Concrete Pipe Layer = 300.00 P l.m. = l.m.
div 4.21
M-D M-D

2. 24" diameter Productivity P


150.00
Concrete Pipe Layer = 300.00 P l.m. = l.m.
div 2.00
M-D M-D

3. 36" diameter Productivity P


240.00
Concrete Pipe Layer = 300.00 P l.m. = l.m.
div 1.25
M-D M-D

4. 48" diameter Productivity P


400.00
Concrete Pipe Layer = 300.00 P l.m. = l.m.
div 0.75
M-D M-D

4. 72" diameter Productivity P


666.67
Concrete Pipe Layer = 300.00 P l.m. = l.m.
div 0.45
M-D M-D

ProdRate Page 44
BASIC
PROJECT : OWNER :

LOCATION : DATE : July 15, 2009


LINE UNIT OF
No. I T E M MEA- QUANTITY

SURE

A Concrete
Batching Fee : cement -excluded
Batching Fee : agreggates -included cu.m. 1.00 980.00
Cement in Bulk bag 1.00 170.00
Cement in Bags bag 1.00 180.00
Sand cu.m. 1.00 660.00
Gravel, G-1 cu.m. 1.00 570.00
Gravel, 3/4 cu.m. 1.00 660.00
Sand , S-1 cu.m. 1.00 500.00
Pump Charge ( per 50 cu.m. ) cu.m. 1.00 200.00
Rubber Filler, 1/2" x 6" l.m. 1.00 80.00
6" Waterstop lm 1.00 350.00
Structural Epoxy sq.m. 1.00 1,400.00
Bostik Sealant, 600 ml - 0.0006 m3 tube 1.00 420.00
Sealocrete, 16 liters ═ 16 000 cc = 1 pail pail 1.00 2,400.00 40 cc per bag of Cement
Sahara, 950 grams/bag bag 1.00 22.00 1 pack per bag of Cement

B Base Preparation
Base Coarse cu.m. 1.00 510.00
Sub Base Coarse cu.m. 1.00 300.00
Selected Fill (Crushed Rock) cu.m. 1.00 200.00
Selected Fill (1 part Escombro, 2 parts Lastillas) cu.m. 1.00 329.00
Common Fill ( Excavated Soil Mat'ls.) cu.m. 1.00 120.00

C Masonry Works
CHB, 4" Load Bearing ( 700 psi) pc 1.00 19.50
CHB, 6" Load Bearing( 700 psi ) pc 1.00 21.00
CHB, 8" Load Bearing( 700 psi ) pc 1.00 31.50
Louver Blocks, 6 x 6 x 12" pc 1.00 15.00
CHB, 4" Non-Load ( 400 psi ) pc 1.00 14.20
CHB, 6" Non-Load ( 400 psi ) pc 1.00 17.50
Ga.10, 4"x 4" w.mesh, 6'x20' sht 1.00 950.00
6"x 6" x 5.5 mm w.mesh, 6'x20' sht 1.00 450.00
Colored Cement kg 1.00 35.00
Pebbles # 10 sack 1.00 90.00 1-1/2 pail = 1 sack = 1 cu.ft.
Grinding Disc, 7" pc 1.00 85.00

D Civil Works
Soil Poisoning sm 1.00 65.00

MaterialBasicCost
Prepared by Ricky Equipt.Rates Page 45
Wages
BASIC
PROJECT : OWNER :

LOCATION : DATE : July 15, 2009


LINE UNIT OF
No. I T E M MEA- QUANTITY

SURE

P.E. Sheet, 6 mils kg. 1.00 120.00


Turfing sm 1.00 35.00
Concrete Drainage Pipes
4 " dia. NRCP pc. 1.00 130.00
6 " dia. NRCP pc. 1.00 160.00
8 " dia. NRCP pc. 1.00 185.00
12 " dia. NRCP pc. 1.00 300.00
15" dia. RCP pc. 1.00 400.00
18" dia. RCP pc. 1.00 500.00
21 dia. RCP pc. 1.00 600.00
24 dia. RCP pc. 1.00 700.00
30" dia. RCP pc. 1.00 1,000.00
36" dia. RCP pc. 1.00 1,790.00
48" dia. RCP pc. 1.00 3,321.00
72" dia. RCP pc. 1.00 8,425.80
E Tile Works & Other Allied Finishes
Vinyl : 2.0 mm pc 1.00 29.00 Armstrong
2.4 mm pc 1.00 33.00 Armstrong 2.5 mm
3.0 mm pc 1.00 41.00 Armstrong
Adhesive gal 1.00 410.00
Vinyl Planks, 3.0 mm thk.
6" x 36 " pc 1.00 100.00
4" x 36 " pc 1.00 44.00
Vinyl Cove Base,100mmx50m roll 1.00 3,800.00
Vinyl Nosing, ( 20 ft.) roll 1.00 600.00
Ceramic Wall Tile, Premium
400 x 400 mm pc 1.00 50.00
300 x 300 mm pc 1.00 35.00
200 x 200 mm pc 1.00 15.00
202 x 300 mm pc 3.00 20.00
Ceramic Floor Tiles, Premium
400 x 400 pc 1.00 50.00
300 x 300 pc 1.00 35.00
200 x 200 mm pc 1.00 14.00
108 x 108 mm pc 1.00 6.00
Tile Adhesive, ABC 25 kg bag 1.00 223.97 4 - 5 sm per bag
Tile Grout, ABC 5 kg bag 1.00 125.00 16 - 18 sm per bag
PVC Tile Trim lm 1.00 80.00
Marble, CDS Polished sm 1.00 1,200.00
Stainless Steel Stair Nosing lm 1.00 1,100.00
Brass Stair Nosing lm 1.00 246.00
Non Skid Tiles pc 1.00 8.00
Carborandum Strips lm 1.00 156.00
Floor Hardener ( Colored Florgard, 30 kg/bag) bag 1.00 975.00 3kgs/sm. - light

MaterialBasicCost
Prepared by Ricky Equipt.Rates Page 46
Wages
BASIC
PROJECT : OWNER :

LOCATION : DATE : July 15, 2009


LINE UNIT OF
No. I T E M MEA- QUANTITY

SURE

Floor Hardener ( Natural Florgard, 30 kg/bag) bag 1.00 850.00 4kgs/sm. - medium
5kgs/sm. - heavy
6kgs/sm. - extra heavy
Carborandum Strips lm 1.00

F Carpentry

Prevailing
G Rebars Base Price Plus/Minus (%)
Price
Grade 33 kg 1.00 20.00 28.03
Grade 40 kg 1.00 21.90 1.28 28.03
Grade 60 kg 1.00 22.60 1.26 28.48
Delivery Charge ton 1.00 370.00 370.00
Ga. 16 Tie Wire ( PhP 35@ 37.5 kg per roll ) roll 1.00 1,312.50 1,312.50

H PVC Doors Price Thick Thin


600 x 2100 mm set 1.00 2,400.00 less 25% less 35 %
700 x 2100 mm set 1.00 2,650.00 less 25% less 35 %
800 x 2100 mm set 1.00 3,450.00 less 25% less 35 %

I Hardwares
(Yale) (Schlage)
Med Heavy Med Heavy
Lockset, Metal Door pc 1.00 2,500.00 5,500.00 3,000.00 8,300.00
Lockset, Wooden Door pc 1.00 900.00 2,300.00 3,000.00
Door Closer pc 1.00 1,500.00 3,700.00
Panic Device pc 1.00 2,500.00 9,500.00
Loose Pin Hinges, 3-1/2 x 3-1/2 pc 1.00 75.00 217.50
Loose Pin Hinges, 4" x 4" pc 1.00 125.00
Kick Plates, Stainless pc 1.00 975.00
Stainless Grab Bar,6 ft. pc 1.00 6,600.00
Floor & Wall Stops ( Ives) pc 1.00 200.00
Push Plates ( Hager ) pc 1.00 570.00
Flush Bolts ( Hager ) pc 1.00 345.00

J Plumbing Fixtures
Wooden Mouldings and Cornices
1x3 l.f. 1.00 11.50
1x4 l.f. 1.00 15.50
1x6 l.f. 1.00 24.20

K Paints

MaterialBasicCost
Prepared by Ricky Equipt.Rates Page 47
Wages
BASIC
PROJECT : OWNER :

LOCATION : DATE : July 15, 2009


LINE UNIT OF
No. I T E M MEA- QUANTITY

SURE

Boysen Neutralizer # 44 gal 1.00 283.00


B. Permacoat Latex # 701 gal 1.00 365.00
B. Acrytex Cast # 1711 gal 1.00 290.00
B. Permacoat Latex Topcoat gal 1.00 428.00
Gloss # 701 (710)
Boysen Patching Compound sack 1.00 305.00
B. Flatwall Enamel # 800 gal 1.00 395.00
Plasolux Primer Surfacer # 307 gal 1.00 412.00
Plasolux Glazing Putty # 311 gal 1.00 425.00
Quick Dry Red Lead Primer # 370 gal 1.00 465.00
B. QDE # 600 gal 1.00 440.00
Plexibond gal 1.00 545.00

L Forms
1/2" Thk . Ordinary Plywood pc 1.00 480.00
3/4 " Thk. Ordinary Plywood pc 1.00 750.00
1/2 " Thk Phenolic Board pc 1.00 1,400.00
3/4 " Thk. Phenolic Board pc 1.00 1,850.00
CW Nails
2" kg 1.00 33.00
3" kg 1.00 31.00
4" kg 1.00 30.00
Concrete Nail 3" kg 1.00 50.00
Form Oil kg 1.00 33.00
Coco Lumber Class B Class A
2x3 BF 1.00 11.50 13.50
2x4 BF 1.00 10.50 13.50

M Equipt. & Power Tools (Rate per Hour)


Bulldozer hr 1.00 1,600.00
Backhoe hr 1.00 1,300.00
Backhoe with Breaker hr 1.00 1,600.00
Crane hr 1.00 1,200.00
Dump Truck hr 1.00 800.00
Vibratory Roller hr 1.00 1,400.00
One bagger Mixer hr 1.00
Plate Compactor /Tamping Rammer day 1.00 1,500.00
Mob & Demob lot 1.00 10,000.00
N Fuel Consumables

Diesel li 1.00 36.78


Oil # 40 li 1.00 1,705.00
Oil# 10 li 1.00 1,733.00

MaterialBasicCost
Prepared by Ricky Equipt.Rates Page 48
Wages
BASIC
PROJECT : OWNER :

LOCATION : DATE : July 15, 2009


LINE UNIT OF
No. I T E M MEA- QUANTITY

SURE

O Wages ( Based On Region/ Project Location)


H.E. Operators day 1.00 370.00
Carpenter day 1.00 350.00
Mason day 1.00 350.00
Tile Setter day 1.00 350.00
Steel Man day 1.00 350.00
Laborer day 1.00 300.00

MaterialBasicCost
Prepared by Ricky Equipt.Rates Page 49
Wages
WORK DIVISION FOR ESTIMATES
a ARCHITECTURAL WORKS ( Quantity Take-Off ) - One (1) Estimator

All Architectural Finishing Works


Masonry
Floor/Wall/Ceiling/ Stair-Finishes
Doors & Windows
Thermal & Moisture Protection
Tinsmithry
Woodworks & Cabinetry
Finishing Hardwares
Toilet Fixtures
Counter Finishes
Arch'l Metal Works ( Railings, Grilles, Ladders , etc.)
Painting

b STRUCTURAL WORKS ( Quantity Take-Off )

VERTICAL - One (1) Estimator


1 Columns
2 Stairs
3 RC Walls ( Shear/ Retaining Wall )
4 Parapet/ Drop Walls
5 Footing / Wall Footing / Tie Beams
6 Earthworks

HORIZONTAL - One (1) Estimator


1 Beams
2 Suspended Slab
3 Slab On Fill
4 Misc. ( Counters, Slop Sink, etc. )

c SPECIALTY/ SUBCON - c/o MEPFS Dept.


1 Plumbing & Sanitary
2 Electrical
3 Fire Pro
4 Mechanical A/C
5 Other Specialty Trades

d COST DERIVATIONS & COSTING ( Direct Cost ) - c/o Cost Dept.


e BOQ & COST BREAKDOWN - c/o QS Team Leader
am Leader
LABOR PRODUCTIVITY TABLE FOR SELECTED WORK ITEMS
ILO
PHASE OF WORK UNIT OF PRODUCTIVITY

1.0
1.00 SITE WORKS
1.01 Excavation
Machine Excavation
Sand 0.800 m-h/cm
Soil 1.100 m-h/cm
Granular Back Fill 1.200 m-h/cm
Granular Soil Back Fill 1.500 m-h/cm 2.0
Manual Excavation
Sand 4.000 m-h/cm
Soil 6.500 m-h/cm
Backfill 5.500 m-h/cm
1.02 Site Grading Manual 1.300 m-h/cm
1.03 Fine Grading & Finishing 3.0
1.04 Paving & Surfacing
Finishing Soil Surface 1.550 m-h/sm
Road Works
Base Course 0.120 m-h/sm
Curb & Gutter 1.500 m-h/sm
Concrete Road
4" thk. Road 1.300 m-h/sm
6" thk. Road 1.400 m-h/sm 4.0
8" thk. Road 1.500 m-h/sm
Trowel Finish 0.320 m-h/sm
Special Topping
4" thk. Stone or Gravel Road 0.320 m-h/sm
6" thk. Stone or Gravel Road 0.400 m-h/sm
8" thk. Stone or Gravel Road 0.520 m-h/sm 5.0
Asphalt Paving
Fine Grading 0.400 m-h/sm
Place Base Course 0.200 m-h/sm
Asphalt 0.250 m-h/sm
1.05 Site Development
Underground Piping ( Steel ) 0.184 m-h/ kg
Concrete Trenches 40.500 m-h/cm.
Sump Pits 173.500 m-h/cm
Sleeve Crossing 24.720 m-h/cm 6.0
Small Retaining Structures 30.970 m-h/cm

2.00 CONCRETE WORKS

2.01 Placing Concrete


Slab On Fill 5.000 m-h/cm
Slip Form 25.000 m-h/cm
Floor Finish Underhardened 1.000 m-h/cm
Concrete Finish Hardened 1.430 m-h/cm

2.02 Rebar Works


Ground Floor Installation 0.070 m-h/ kg 7.0
Upper Floor Installation 0.850 m-h/ kg
Fabrication 0.120 m-h/ kg

2.03 Manual Mixing 16.000 m-h/cm


Machine Mixing 1.000 m-h/cm

2.04 More than 1.80 cm Concrete Pour 8.0


Chute fromTruck 7.000 m-h/cm
Crane & Bucket 14.000 m-h/cm
Wheeling ( Buggies) 18.000 m-h/cm
Finishing 2.000 m-h/cm

2.05 Concrete Pour on Elevator and Shored Slab


Forming, Chute and Bucket 21.000 m-h/cm

2.06 Formworks Installation


Wall on Ground 2.000 m-h/sm
Wall Above Ground 2.350 m-h/sm
Beams 3.080 m-h/sm
Columns 2.350 m-h/sm
Suspended Slab 1.670 m-h/sm
0 to 18 inches 3.530 m-h/sm 9.0
18 to 36 inches
Elevated and Short Slab Forming 8.600 m-h/sm
Forming only 11.000 m-h/sm
Forming & Shoring 0.500 m-h/sm
2.07 Formwork Fabrication 1.080 m-h/sm
2.08 Stripping of Form works
Wall on Ground 0.250 m-h/sm
Wall Above Ground 1.300 m-h/sm
Beams 1.030 m-h/sm
Columns 0.580 m-h/sm
Suspended Slab m-h/sm
0 to 18 inches 0.830 m-h/sm 10.0
18 to 36 inches 1.080
Elevated and Short Slab Forming
Forming only 3.500 m-h/sm
Forming & Shoring
Floor Slab 2.800 m-h/sm

3.00 MASONRY

3.01 Grouting and Plastering 1.670 m-h/sm


3.02 Pebble Washout 2.860 m-h/sm
3.04 Marble Installation 4.000 m-h/sm
3.05 1/4 " x 2" x 8" Red Bricks 10.000 m-h/sm
3.06 Glazed Tiles 10.530 m-h/sm 11.0
3.07 Unglazed Tiles 4.350 m-h/sm
3.08 Concrete Block Exterior Wall 4.500 m-h/sm
3.09 Concrete Block Interior Wall 4.000 m-h/sm
3.10 Brick Work 1.500 m-h/sm
3.12 Plaster Wall & Ceiling 2.000 m-h/sm
3.13 Hollow Tile Wall 2.000 m-h/sm 12.0
3.14 Unglazed or Mosaic Fllor Tile 8.500 m-h/sm
3.15 Laying of Adobe 2.500 m-h/sm
3.16 Cement Finish
6" CHB 1.600 m-h/sm
4" CHB 1.350 m-h/sm
8" CHB 1.800 m-h/sm
3.17 Vitrified Floor Tiles 5.350 m-h/sm
3.18 Glazed Ceramic Tiles 5.950 m-h/sm

4.00 METAL WORKS 13.0

4.01 Fabrication
Light Weight 0.130 m-h/kg
Heavy Weight 0.090 m-h/kg
Gratings, 1-1/4 x 3/16 0.030 m-h/kg
Stair Thread Gratings 0.040 m-h/kg
Misc. Steel 0.120 m-h/kg
4.02 Erection
Light Weight 0.100 m-h/kg
Heavy Weight 0.060 m-h/kg
Stack ( End, Full Weld ) 0.300 m-h/kg 14.0
Tanks ( End, Full Weld ) 0.210 m-h/kg
Welding ( One Pass Only ) 0.200 m-h/lm
Painting ( 1 coat ) 1.200 m-h/lm
4.03 Structural Steel Framing 0.120 m-h/kg
4.04 Metal Decking 0.206 m-h/kg
4.05 Ornamental Metal 0.150 m-h/kg

5.00 WOODS
5.01 0.970 m-h/bf
5.02 Rough Carpentry
Floor Framings 0.430 m-h/bf
Wooden Post Erection 0.350 m-h/bf
Truss Fabrication 0.800 m-h/bf
Girt Installation 0.210 m-h/bf
Plates Installation 0.130 m-h/bf
Purlins Installation 0.530 m-h/bf
Ceiling Frame Works 1.350 m-h/sm
Siding Frame Works 1.200 m-h/sm
5.03 Finish Carpentry
Plywood Partition 0.500 m-h/sm
T & G Flooring and Siding 0.140 m-h/bf
Fascia Board Installation 0.500 m-h/bf
1/4 " x 3/4 in thk. Plywood 0.420 m-h/sm
Ceiling Plywood Installation 1.000 m-h/sm
Cabinet Boarding 0.150 m-h/bf
Cabinet Framing 0.180 m-h/bf
Wood Wall Partitions 0.600 m-h/sm
Panel Wall 7.000 m-h/sm
Forming Weight Anchor Bolts 4.500 m-h/sm

6.00 TERMAL AND MOISTURE


6.01 Water Proofing
6.02 Dam Proofing
6.03 Insulation
6.04 Roof Accessories
6.05 Corrugated GI Sheet
Lifting 1.080 m-h/sm
Installation 3.060 m-h/sm
Installation of Alum. GI Sheet 0.080 m-h/lm
Installation of Asbestos Roofing 1.000 m-h/sheet
Fabrication of GI Gutter 0.470 m-h/lm
Copper Cladding Roof Deck 0.510 m-h/lm
Installation of Gutter 0.160 m-h/lm
Gutter Cut and Shape 0.970 m-h/lm
Down Spout Cut and Shape 0.890 m-h/lm
Down Spout Installation 0.130 m-h/lm
Corr. GI Roofing 0.130 m-h/sm
Corr. Alum.Roofing 1.800 m-h/sm
Built Up Roofing 4 Ply 8.500 m-h/sm
Protected Metal 2.000 m-h/sm
Corr. Asbestos Installation, Lifting & Hauling 1.700 m-h/sm
Leaders & Gutters 0.600 m-h/sm
6.06 Sealants 0.100 m-h/lm

7.00 Doors & Windows

7.01 Door & Jamb


W Panel Installation 0.400 m-h / pc.
Steel Window Installation 2.000 m-h/pc
Louver Window Installation
Fixed Asbestos 4.630 m-h/sm
Fixed Metal Louvers 3.120 m-h/sm
Fixed GI Sheet 4.630 m-h/sm
Fixed Glass 3.120 m-h/sm
Fixed Wooden 3.500 m-h/sm
Alum. Framed Windows 10.000 m-h/ea
Sliding Glass Door 12.000 m-h/ea
Hollow Metal Door 10.000 m-h/ea
Roll Up Door 25.000 m-h/ea
Fixed Window 0.630 m-h/sf

Door Lockset 1.500 m-h/set


Door Jamb
Fabrication 0.300 m-h/bf
Installation 0.350 m-h/bf
Cyclone Wire Installation 3.600 m-h/m

8.00 Finishes

8.01 Lath & Plaster


8.02 Gypsum Drywall
8.03 Tile & Terrazo
8.04 Ceiling Finishes
Acoustic Tile Ceiling with Plywood Ceiling 2.900 m-h/sm
Concealed Acoustic Tile on Alum. T -Runners 3.000 m-h/sm
Asbestos Ceiling 2.000 m-h/sm
8.05 Floor Finishes
Plain Cement Finish 1.250 m-h/sm
Colored Cement Finish 1.500 m-h/sm
Steel Trowelled Finish 1.450 m-h/sm
Steel Trowel with Hardener 1.800 m-h/sm
Vitrified Fllor Tiles 4.500 m-h/sm
Vigan Floor Tiles 5.000 m-h/sm
Cobbled Stone 8.000 m-h/sm
Marble Slab Finish 7.000 m-h/sm
Granolithic Slab Finish 9.000 m-h/sm
Cement Tile Finish 4.500 m-h/sm
Vinyl Tile Finish 0.800 m-h/sm
Wood Parquet Finish 1.200 m-h/sm
Non Skid Tile Driveway 3.500 m-h/sm
Paving Bricks 4.860 m-h/sm
Pebble Washout Finish 5.300 m-h/sm
Luna Rock Finish 3.800 m-h/sm
Slate Stone Ashlar 6.000 m-h/sm
Phil. Granite Finish 12.000 m-h/sm
Java Negra Stone Finish 10.000 m-h/sm
Piedra China Stones 12.000 m-h/sm
Java Blanca Stone Finish 10.000 m-h/sm
8.06 Wall Finishes
Boown Stiple Finish 1.600 m-h/sm
Cement Plaster Finish 1/2 " 2.000 m-h/sm
Escombro Ashlar Rubble 8.000 m-h/sm
Glass Washed Out 4.000 m-h/sm
Marble Tiles 8.000 m-h/sm
Mosaic Tiles 6.000 m-h/sm
ILO LABOR PRODUCTIVITY RATES

EXCAVATION ( Ordinary Soil )


1.1 Manual 1.00 cu.m/ m-day
1.2 Machine ( Bulldozer/ 1-Operator/1- Spotter ) 200.00 cu.m/ m-day
( Backhoe/ 1-Operator/1- Spotter ) 120.00 cu.m/ m-day

COMPACTION
2.1 Manual ( Using Tamping Rammer) 3.00 cu.m/ m-day
2.2 Roller / Compactor ( 6 Passes) 30.00 cu.m/ m-day

CONCRETING ( Readymixed Concrete with Pumpcrete )


3.1 Lean Concrete ( 50 mm thk. ) 3.00 cu.m/ m-day
3.2 Sub -Structure ( Foundation ) 6.00 cu.m/ m-day
3.3 Super Structure 4.50 cu.m/ m-day
3.4 Curb & Gutters 2.00 cu.m/ m-day

FORMWORKS
4.1 Sub- Structure 3.00 sq.m. / m-day
4.2 Super Structure 2.00 sq.m. / m-day

STEEL WORKS
5.1 Reinforcing Bars ( Fabrication & Installation ) 150.00 kg/ m- day
5.2 Structural Steel ( Installation only ) 350.00 kg/ m- day
5.3 Steel Deck Plate ( Installation only ) 10.00 kg/ m- day
5.4 Anchor Bolt ( 450 mm long ) 8.00 kg/ m- day
5.5 Welded Wire Fabfic 20.00 kg/ m- day

ROOFING WORK / THERMAL WORK


6.1 Corrugated G.I. Sheet 7.00 sq.m. / m-day
6.2 Corrugated Asbestos 5.50 sq.m. / m-day
6.3 Roof Tiles 2.50 sq.m. / m-day
6.4 Eaves Gutter 6.00 sq.m. / m-day
6.5 Down Spouts 6.00 sq.m. / m-day
6.6 P.E Sheet ( Damproofing ) 150.00 sq.m. / m-day
6.7 Membrane Type H20 Proofing 8.00 sq.m. / m-day
6.8 Fiberglass Insulation ( 2" thk. ) 25.00 sq.m. / m-day
CONCRETE BLOCK WORKS
7.1 100 mm thk. CHB 5.00 sq.m. / m-day
7.2 150 mm thk. CHB including rebar & Mortar filler 4.00 sq.m. / m-day
7.3 200 mm thk. CHB 3.00 sq.m. / m-day

WALL FINISHES
8.1 Plain Cement, Troweled Finish 5.00 sq.m. / m-day
8.2 Bush Hammered Synthetic Adobe 3.00 sq.m. / m-day
8.3 Pebble Washout 2.00 sq.m. / m-day
8.4 Sandblast Finish on Concrete 24.00 sq.m. / m-day
8.5 Mortar Float Finish 6.00 sq.m. / m-day
8.6 Ceramic Tiles including Mortar Bedding 1.50 sq.m. / m-day
8.7 Metal Lath 14.00 sq.m. / m-day
8.8 Base Boards
8.8.1 Vinyl Asbestos 25.00 l.m. / m-day
8.8.2 Mortar Baseboard 8.00 l.m. / m-day
8.8.3 Wooden Baseboard 15.00 l.m. / m-day

FLOOR FINISHES
9.1 Topping with Plain Cement 8.00 sq.m. / m-day
9.2 Pebble Washout 3.00 sq.m. / m-day
9.3 Ceramic Tiles including Mortar bed 2.50 sq.m. / m-day
9.4 Vinyl Tiles 22.00 sq.m. / m-day
9.5 Marble Tiles 2.00 sq.m. / m-day
9.6 Concrete Tiles 4.00 sq.m. / m-day
9.7 Mosaic Tiles with Bedding 2.50 sq.m. / m-day
9.8 Carpet 20.00 sq.m. / m-day

CEILING FINISHES
10.1 Rubbed Concrete Finish 18.00 sq.m. / m-day
10.2 Plain Cement Plaster 4.00 sq.m. / m-day
10.3 Acoustic Board with Metal Suspension 7.00 sq.m. / m-day
10.4 Gypsum Board with Metal Suspension 5.00 sq.m. / m-day

CARPENTRY FINISHES
11.1 T & G Wood Ceiling on 2 x 2 Wood Frame 2.50 sq.m. / m-day
11.2 Plywood Ceiling on 2 x 2 Wood Frame 3.50 sq.m. / m-day
11.3 Plywood Wall Panel on 2 x 2 Wood Studs ( Single ) 6.00 sq.m. / m-day
11.4 Plywood Wall Partition on 2 x 2 Wood Frames 3.50 sq.m. / m-day
DOORS & WINDOWS ( Installation Only )
12.1 Wooden Door including Jamb 1.20 sq.m. / m-day
12.2 Steel Doorincluding Jamb 1.00 sq.m. / m-day
12.3 Aluminum Door 1.00 sq.m. / m-day
12.4 Roll Up Door 0.75 sq.m. / m-day
12.5 Steel Window / Steel Louver 1.70 sq.m. / m-day
12.6 Aluminum Window / Louver 1.70 sq.m. / m-day

HARDWARES
13.1 Locksets 2.50 nos/m-day
13.2 Door Closer 2.00 nos/m-day
13.3 Door Stop 5.00 nos/m-day
13.4 Flush Bolt 4.00 nos/m-day
13.5 Push Plate 6.00 nos/m-day
13.6 Door Viewer 10.00 nos/m-day
13.7 Towel Rack 10.00 nos/m-day
13.8 Non Slip Nosing 15.00 l.m. / day

PAINTING
14.1 Masonry Surfaces 14.00 sq.m. / m-day
14.2 Steel Surfaces 12.00 sq.m. / m-day
14.3 Wooden Surfaces, Varnish 8.00 sq.m. / m-day
14.4 Wooden Surfaces, QDE 10.00 sq.m. / m-day
14.5 Stucco Painting 5.00 sq.m. / m-day
PRODUCTIVITY RATE PER MANDAY

Item Work Description Rate/MD Unit Remarks


1.00 CEILING
Installation of Frames 6.00 sqm
Installation of Plywood 8.00 sqm

2.00 FLUSH DOOR FABRICATION- standard size 0.67 sqm


DOOR JAMB x 2" x 6"
Fabrication 1.78
Installation 1.33 bdft

3.00 METAL DOORS - 2.1m X .9m


Fabrication 0.33 pc
Installation 1.00 pc

4.00 MANUAL CLEARING AND GRUBBING


Clearing undergrowth & trees 80.00 sqm
Clearing undergrowth & Shrubs 160.00 sqm

5.00 EXCAVATION - MANUAL


Common Earth 1.00 cu.m.
Leam of sand 6.00 cu.m.
Clay or Heavy Soil 4.88 cu.m.
Rock 3.00 cu.m.

6.00 EXCAVATION - MECHANICAL


Common Earth 1.20 cu.m.
Rock with Jackhammer 0.48 cu.m.

7.00 BACKFILLING
Common - manual 9.76 cu.m.
Gravel Fill manual 1.60 cu.m.

8.00 COMPACTION
Mechanical Compaction 56.00 cu.m
Plate Compaction 144.00 cu.m
Spreading, tamping and grading 16.72 cu.m
Escombro Backfilling 38.24 cu.m
Placing Binder-Gravel 75.68 cu.m

9.00 PLACING OF CONCRETE


Slab on Fill 1.60 cu.m.
Slipform 0.32 cu.m.
Floor Fin Unhardened 8.00 cu.m.
Concrete Fin Hardened 5.60 cu.m.

Water Stop Installation 12.00 lm


Caulking Slab Point 40.00 lm
Aspahalting 10.00 sqm
Grouting & Tol plastering 4.80 sqm
Pebble Finish 5.60 sqm
Marble Slab 4.00 sqm
Red Bricks 3/4 x 2 x 8 1.60 sqm
Glazed Tiles 1.52 sqm
Unglazed tiles 1.84 sqm

10.00 FORMWORKS FABRICATION 6.64 sqm

11.00 FORMWORKS INSTALLATION


Walls on Ground 4.00 sqm
Walls above 3.00 m 3.40 sqm
Beams 2.60 sqm
Columns 3.40 sqm
Suspended Slab
0 - 5.5 m Height 4.80 sqm
5.6 - 12 m Height 3.20 sqm
above 12 m 2.40 sqm

12.00 FORMWORKS STRIPPING


Walls on Ground 32.00 sqm
Walls above 3.00 m 6.20 sqm
Beams 7.80 sqm
Columns 9.40 sqm
Suspended Slab
0 - 5.5 m Height 14.40 sqm
5.6 - 12 m Height 9.60 sqm
above 12 m 7.40 sqm

13.00 REBARS INSTALLATION


Foundation 90.00 kgs
Slab On Fill 110.00 kgs
Columns, Beams, RC Walls 65.00 kgs
Cast-in Place Culverts, Manhole 60.00 kgs

14.00 REBARS FABRICATION 150.00 kgs

15.00 LAYING RCP WITH ( 1 GRP = 8 MAN)


24' Ø 16.00 lm
36' Ø 10.00 lm
48' Ø 6.00 lm
6' -16' Ø 48.00 lm

16.00 CARPENTRY WORKS


Plywood Partition 23.04 sqm
T & G Flooring and Sidings 56.00 bdft
Ceiling Frameworks 22.00 bdft
Siding Frameworks 30.00 bdft
Floor Framing 16.52 bdft
Wooden Post Erection 18.76 bdft
Wooden Trusses Fabrication 23.00 bdft
Wooden Trusses Installation 10.00 bdft
Girts Installation 37.52 bdft
Plates Installation 60.00 bdft
Purlins Installation 30.00 bdft
Facia Board Installation 17.52 bdft
1/2 or 3/4 Plywood Cabinet
Manual Cutting 11.48 sqm
Assembly 9.60 sqm

17.00 CONCRETE DEMOLITION 0.48 cu.m.

18.00 CONCRETE HOLLOW BLOCKS LAYING


6" CHB - 1 mason + 1 helper 10.00 sqm
4" CHB - 1 mason + 1 helper 12.00 sqm
8" CHB - 1 mason + 1 helper 8.00 sqm

19.00 W-Panel
Installation 20.00 pcs

20.00 STEEL WINDOWS


Installation 4.00 pcs.

21.00 DOOR LOCKSET 5.00 set

22.00 WATER PROOFING - Rubberized 14.52 sqm

23.00 LOUVER WINDOWS INSTALLATION


Fixed Asbestos 1.73 sqm
Fixed Metal Louver 2.60 sqm
Fixed G.I. Sheet 1.73 sqm
Fixed Glass 2.60 sqm
Fixed Wooden 2.37 sqm

24.00 CYCLONE WIRE INSTALLATION 0.03 sqm

25.00 DISPOSAL OF SOIL 4.72 cu.m

25.00 HAULING OF SOIL 8.00 cu.m

26.00 GRAVEL FILL 3.90 cu.m

27.00 DEMOLITION OF ADOBE WALL 5.00 cu.m

28.00 VITRIFIED TILES - FLOOR 1.50 sqm

29.00 VITRIFIED TILES - WALLS 1.34 sqm

30.00 METAL/ROOFING WORKS


Corrugated GI Sheets 11.35 sqm
Ridge Roll (18") 30.48 lm
Gutters (24") 35.84 lm
Downspouts 3.17 lm
Flashing 10.51 lm

31.00 PLASTERING
Scratch Coat
Finish Coat
32.00 PAINTING
Exterior Concrete or Bricks ( Brush )
Primer + 1 Coat 45.00 sqm
Primer + 2 Coat 33.00 sqm
Exterior Wood Sidings (including puttying/Brush)
Primer + 1 Coat 60.00 sqm
Primer + 2 Coat 40.00 sqm
Wood Trim (including, Puttying/Brush)
Primer + 1 Coat 30.00 sqm
Primer + 2 Coat 20.00 sqm
Windows & Doors (Brush)
Primer + 1 Coat 55.00 sqm
Primer + 2 Coat 32.00 sqm
Interior Plaster or Dry Wall (Brush)
Primer + 1 Coat 30.00 sqm
Primer + 2 Coat 20.00 sqm
Walls and Ceiling (Including puttying/Roller)
Primer + 1 Coat 80.00 sqm
Primer + 2 Coat 60.00 sqm
Interior Woodworks (Putty/Brush)
Primer + 1 Coat 60.00 sqm
Primer + 2 Coat 45.00 sqm
Interior Masonry or Concrete (Brush)
Primer + 1 Coat 45.00 sqm
Primer + 2 Coat 32.00 sqm
Structural Steel (Spray) Primer excluding
Brushing and Putty 100.00 sqm
Structural Steel (Spray) 2 Coat 50.00 sqm
Varnish (1coat, 1Sealer) 80.00 sqm

33.00 FINISHING WORKS


Parquet Floor Tile Installation incl. Finishing 10.00 sqm
Monolithic Terrazzo Finishing 5/8" thk, 4" Slab 10.00 sqm
Precast Terrazzo Tile (1"x12"x12:) 3.00 sqm
Synthetic Marble Tile (12 x 12) 3.00 sqm
Quarry Tile Installation (1/2" thk)
4"x4" 5.00 sqm
6"x6" 7.00 sqm
4"x8" 6.00 sqm
Window Glass Installation 22.00 sqm
Suspended Ceiling Fame System Aluminum T-
runner, 2"x4" 35.00 sqm
Acoustical Board Ceiling 37.00 sqm

34.00 PLUMBIG FIXTURES


Bath Tub 10.00 MH/set
Floor Drain 4.00 MH/set
Kitchen Sink
single 8.00 MH/set
double 12.00 MH/set
Lavatory wall hung 8.00 MH/set
Shower Head 3.00 MH/pcs
Urinal
Wall 8.00 MH/set
Pedestal Drain 10.00 MH/set
Water Closet and Tank 7.00 MH/set
MATERIAL ESTIMATES
WORK ITEM NET FACTOR / SQ.M.
MASONRY BLOCKWORKS

1.0 4" CHB Wall


a. Mortar : Cement 0.55 bag
Sand 0.05 cu.m.
b. 4" CHB 12.50 pcs.
c. Reinforcement 4.50 kgs
d. Tie Wire # 16 @ 40 kg./roll 0.0012 roll

2.0 6" CHB Wall


a. Mortar Cement 0.80 bag
Sand 0.07 cu.m.
b. 4" CHB 12.50 pcs.
c. Reinforcement 4.50 kgs
d. Tie Wire # 16 @ 40 kg./roll 0.0015 roll

3.0 8" CHB Wall


a. Mortar Cement 1.20 bag
Sand 0.16 cu.m.
b. 4" CHB 12.50 pcs.
c. Reinforcement 6.00 kgs
d. Tie Wire # 16 @ 40 kg./roll 0.0025 roll

4.0 Inclined 6" CHB Wall ( 30 degrees slant )


a. Mortar Cement 0.87 bag
Sand 0.10 cu.m.
b. 4" CHB 12.50 pcs.
c. Reinforcement 4.50 kgs
d. Tie Wire # 16 @ 40 kg./roll 0.0015 roll

5.0 Masonry Soft Joints


a. Backing Rod = lm(2) 0.90 l.m.
Sealant = lm(2) 0.90 l.m.
Styrophor = lm(2) 0.90 l.m.

FLOOR FINISHES
1.0 Plain Cement ( Finished Topping 5/8" thk. Ave. )
a. Topping : Cement 0.27 bag
Sand 0.03 cu.m.
b. Finish Coat @ 1 bag / sq.m. 0.17 bag

2.0 Plain Cement Topping with Hardener


a. Mortar : Cement 0.40 bag
Sand 0.04 cu.m.
b. Hardener
Light Duty 3.33 lbs.
Medium Duty 6.67 lbs.
Heavy Duty 11.11 lbs.

3.0 Pebble Washout Floor Finish


a. Mortar 3/4 " thk. : Cement 0.40 bag
Sand 0.04 cu.m.
b. Washout Mixture : Cement 0.40 bag
# 10 Pebble 0.67 pail
where : 1 Pail = 1 cu.ft
1 Sack = 2 pails

4.0 Vinyl Floor Tiles


a. Scratch Coat 3/8 " thk. : Cement 0.55 bag
Sand 0.55 cu.m.
b. Adhesive
Dalflex : 1 gal / 10 sq.m. 0.10 gal.
N&H: 1 gal / 10 sq.m.
c. Wax Emulsion
Dalflex : 1 gal /150 sq.m. - -
d. Vinyl Tiles , 12" x 12" 11.00 pcs.

5.0 Vitrified Unglazed Tiles


a. Scratch Coat 3/8 " thk. : Cement 0.15 bag
Sand 0.02 cu.m.
b. Tiles, 4-1/4 x 4- 1/4 " 86.50 pcs.
c Tile Attachment
Adhesive : 1 gal / 7 sq.m. 0.14 gal.
For Attachment : Cement 0.09 bag
For Attachment : Sand 0.01 cu.m.
Grout @ Joints : 1 bag / 6 sq.m. 0.17 bag

7.0 Cement Tiles


a. Mortar 3/4 " thk. : Cement 0.55 bag
Sand 0.30 cu.m.
b. Cement Tiles : 8" x 8 " 25.00 pcs.
9" x 9 " 19.50 pcs.
10 " x 10 " 16.00 pcs.
12" x 12" 11.00 pcs.

8.0 Marble Slabs


a. Mortar 3/4 " thk. : Cement 0.55 bag
Sand 0.30 cu.m.
b. Marble Slabs 4" x 8 " 49.00 pcs.
8" x 12 " 16.50 pcs.
8 " x 16 " 12.50 pcs.
16" x 16" 6.30 pcs.
24" x 24" 3.00 pcs.

WALL FINISHES

1.0 Rubbed Concrete ( Plain Cement )


a. Retouch 3/4 " thk. Ave. : Cement 0.07 bag
Sand 0.01 cu.m.

2.0 Plain Cement Plaster Finish


a. Plaster 3/4 " thk. Ave. : Cement 0.40 bag
Sand 0.04 cu.m.

3.0 CHB Tool Joint Finish ( Flushed or Grooved )


a. Mortar 1/8 " thk. Ave. : Cement 0.07 bag
Sand 0.01 cu.m.

4.0 Vitrified Glazed Tiles


a. Scratch Coat 3/8" thk. : Cement 0.20 bag
Sand 0.02 cu.m.
b. Tiles 4-1/2 x 4-1/2 " 86.50 pcs.
c Tile Attachment
Adhesive : 1 gal / 7 sq.m. 0.14 gal.
For Attachment : Cement 0.09 bag
For Attachment : Sand 0.01 cu.m.
Grout @ Joints : 1 bag / 6 sq.m. 0.17 bag

5.0 Synthetic Adobe Finish


a. Mortar 1/8 " thk. Ave. : Cement 0.20 bag
Sand 0.02 cu.m.
b. Synthetic Adobe : 1 pail / 0.05 sq.m. 2.00 pails

6.0 Bush Hammered Concrete Finish


a. Scratch Coat 1/4 " thk. Ave. : Cement 0.15 bag
Scratch Coat 1/4 " thk. Ave. : Sand 0.02 cu.m.

7.0 Colored Sprayed Concrete Finish


a. Scratch Coat 1/4 " thk. Ave. : Cement 0.40 bag
Scratch Coat 1/4 " thk. Ave. : Sand 0.04 cu.m.
b. Waterproof Plaster Paint : 1 gal / 5 sq.m. 0.20 gal
c. Colored Cement : 1 bag / 8 sq.m. 0.13 bag

8.0 Shell Piqueta Finish


a. Retouch 3/4 " thk. Ave. Cement 0.40 bag
Sand 0.04 cu.m.
b. Waterproofing Solution ( Silicon Sol'n )
where : 1 gal / 15 sq.m. 0.07 gal.
c. Shell : 1 pail/ 6 sq.m.
where : 1 pail = 1 cu.ft. 0.17 pail
9.0 Rip Rap Stone Facing
a. Concrete Class AA 3" thk. Cement
Sand
b. 6" to 8" Stone
6 pcs./ sq.m.
400 pcs. / Delivery Truck 0.02 DT

10.0 Marble Wall Finish


a. Scratch Coat 3/4 " thk. Cement 0.40 bag
Sand 0.04 cu.m.
b. Marble 6" x 12" x 3/4 " thk. 22.00 pcs.
12" x 12" x 3/4 " thk. 11.00 pcs.
1 m x 1 m x 3/4 " thk. 1.00 pcs.
c. Crazy Cut Marble 1.00 pcs.
d. White/ Colored Cement at Joints 0.17 bag

CARPENTRY WALL FINISHES

1.0 Double Wall Plywood Panelling


a. Frames on 2" x 3" @ 24" o.c. 8.20 BF
on 2" x 4" @ 24" o.c. 9.00 BF
b. Nails 0.015 kg. / pc. 0.25 kg.
c. Plywood Panels, 1/4" x 4' x 8" 0.70 sheet

2.0 Single Wall Plywood Panelling


a. Frames on 2" x 2" @ 24" o.c. 3.00 BF
on 2" x 4" @ 24" o.c. 5.00 BF
on 2" x 3" @ 24" o.c. 7.00 BF
b. Nails 0.015 kg. / pc. 0.15 kg.
c. Plywood Panels, 1/4" x 4' x 8" 0.35 sheet

3.0 Stone Cut or V Cut Wood Sidings


a. Sidings 4" width = 38 lf/ sq.m. 13.00 BF
6" width = 24 lf/ sq.m. 12.00 BF
8" wiith = 18 lf / sq.m. 12.00 BF
b Nails 0.15 kg.

4.0 V Cut Sidings 1" thk.


a. Sidings 6" width = 24 lf 12.00 BF
b Nails 0.15 kg.

CARPENTRY CEILING FINISHES

1.0 Plywood / Lawanit/ Asbestos Ceiling on Wood Frame


a. Frames on : 2"x 2"@ 16 " o.c. ( with hanger) 7.65 BF
2"x 4"@ 48 " o.c. ( with hanger) 5.00 BF
b. Nails 0.20 kg.
c. Hangers 0.80 kg.
d. Panels , 4'x 8' 0.35 sht.

2.0 Acoustic Tile / Board Ceiling on Wood Frame


a. Frames on : 2"x 2"@ 16 " o.c. ( with hanger) 7.65 BF
2"x 4"@ 48 " o.c. ( with hanger) 5.00 BF
b. Acoustic Tile 2' x 4' 10.76 Sq.ft.
c. Adhesive Rugby, 1 gal / 8 sq.m. 0.13 gal.
3.0 Acoustic Tile / Board Ceiling on Alum.T - Runners
Suspension Systems
a. Acoustic Tile 10.76 Sq.ft.
b. Hangers Ga. # 3 Wires @ 24" o.c. 0.02 roll
c. Aluminum T-Runners 12" x 24" 18.50 l.ft.
24" x 24" 13.00 l.ft.
24" x 48" 9.50 l.ft.

4.0 T & G Wood Finish ( excluding frames )


a. 1"x 4" KD Tanguile 12.70 BF
b. Nails 0.10 kg.

5.0 Gypsum / Acoustic Board


a. Gypsum Board @ 4' x 8' 0.34 pc
b. Acoustic Board @ 2' x 3' 1.80 pcs.
c. Flat Type @ 3.93 l.m. / pc. 1.02 pcs.
d. 1" Kin Head Self Taping Screw 0.21 gross
e. Joint Comp. 0.04 gal.

CARPENTRY FLOOR FINISHES

1.0 T & G Floor Finish


a. 1" x 4" KD Tanguile 13.85 sq.ft.
b. 1" x 6" KD Tanguile 13.20 sq.ft.
c. Nails 0.20 kg.

2.0 Parquet Flooring ( Narra ) @ Concrete Slab


a. Scratch Coat 1/2 " Thk. Ave. : Cement 0.20 bag
Sand 0.02 cu.m.
b. Adhesive Parquet Glue : 1 gal / 2.5 sq.m. 0.04 gal.
c. Fin. Parquet Flooring 10.76 sq.ft.

3.0 Parquet Flooring ( Narra) on 1' x 6" Diagonal Flooring


KD Tanguile
a. 1" x 6" KD Tanguile 12.50 BF
b. Adhesive Parquet Glue : 1 gal / 2.5 sq.m. 0.04 gal.
c. Fin. Parquet Flooring 10.76 sq.ft.
Factors in Estimating

Work Description Units Factor Remarks

Architectural Finishing Works


A Topping
Sand cu.m. Stair, Gutter, All Floors
Cement bags 10 bags/cu.m. of Sand shall be 0.05 m thk.
Wire Mesh sq.m.

B Wall Finishes
Tiles pc. plus 10%
Capping pc. plus 10%
Marble sq.m. plus 5%
Baseboard LF plus 10%
Grout kilo 4 sq.m. / kilo
Cement kilo 10 sq.m. / kilo
Plywood sheet
Nailers BF
Nails kilo
Pebble Washed Out sq.m.
PVC Base Board LF

C Floor Finishes
Marble sq.m. plus 5%
Parquet Tiles sq.ft plus 5%
Wood Planks sq. m plus 15%
Tiles pc plus 5%
Vinyl Tiles pc plus 5%
Washed Out sq.m.
Washed Out with Tiles sq.m.
Colored Cement kilo 2 sq.m. / kilo
Plain Cement kilo 3 sq.m. / kilo
Grout kilo 4 sq.m. / kilo
Rugby gal 200 pcs./ gal
T & G Flooring BF plus 5%
Nailer for T & G BF 4.92 BF/ sq.m.
Nail kilo 5 sq.m. / kilo
Brass Nosing LF
CDS Marbles sq.m.
Threaded Nailer BF plus 5%
Coal Tar gal 20 sq.m. / gal

Included in Stair Finishes


Narra Planks BF plus 15 % 3.33 BF/ sq.m. spaced at 200 mm OC
Plank Nailers, 1-1/2 x 2 BF plus 5 %
Washed Out Pebbles sq.m.
Marble sq.m.
Cement 1.5 sq.m./bag

D Ceiling Finishes
Plywood 1/4 x 4 x 8 Sheet plus 10 %
Plywood 3/4 x 4 x 8 Sheet plus 5 %
Joist 2" x2" BF plus 10 % BF= Area x 6.417
Hanger 2" x 3" BF plus 10 % BF= Area x 3.00
Concrete Nail kilo
Nail kilo
Moulding BF
Glue quart
T Runner LF
Diffuser sq.ft.
Spandrel LS
T&G B.F. plus 10 % 14 BF/sq.m.
Wall Paper sq.m.
Others:
Acoustic Board plus 10 %
Spandrel
Curve Moulding pc

E Plastering
Sand cu.m. Thickness 1-1/2"
Cement bag 1:16 0.038 sq.m.
Water Prrofing Compound CHB Wall
RC Wall
Toilet Wall
Parapet Wall
Drop Wall
Plant Box
Patio
F Doors & Jambs
Flush Door sq.ft. plus 3.281% Use Commercial
Panel Door sq.ft. Use Commercial
Louver Door sq.ft. Use Commercial
Jambs BF
Nails 4" kilo 2kilo/Jamb
Coal Tar gal 0.20 gal/ Jamb
Door Casing, Two Sides BF plus 5%
Glue gal
PVC Door sq.m.
Sliding Track LF
Roller pcs
Handle pcs
Stopper pcs

Structural Roughing Works

1 Earthworks
Excavation cu.m. plus 10 %
Filling Materials cu.m. plus 20 %
Gravel Bed cu.m. plus 10 %
Backfilling cu.m. plus 10 %
Soil Poisoning quart 50 sq.m/quart
Hauling TL
Sheet Piles 2" x 10 " x 8 ' BF
Others:
Grading & Compaction sq.m.

2 Concreting
6,000 psi cu.m. plus 2%
5,000 psi cu.m. plus 2%
4,000 psi cu.m. plus 2%
3,000 psi cu.m. plus 2%
2,500 psi cu.m. plus 2%
3 Rebar
36 mm dia. pc
32mm dia. pc
28 mm dia. pc
25 mm dia. pc
20 mm dia. pc
16 mm dia. pc
12 mm dia. pc
10 mm dia. pc
Tie Wires roll 3000 kg/roll

4 Pile Work
Piles LF
Splice Can pc
Piles

5 Masonry
6 " CHB pcs
4" CHB pcs
Sand for 6" CHB cu.m.
Sand for 4" CHB cu.m.
Cement bag
Rebars pc.
GI Wire roll 3500 pcs/CHB per roll
Others

Rebars
Total CHB x 0.55 + 0.55 + Total x 0.51 / 3.281 / Commercial Length

6 Scaffoldings
Perimeter X Height x (6.56 ) x 1/2 = BF

7 Tendons
P = KN convert to kips

P = KN x Kip/4.448 KN

P = Kip divide by 24.80

P = Kip x tendon/ 24.80 kip

P = No of Tendons

Cost = No.of Tendons x Span of Beam x Prevailing Price


REBAR CUT - OFF
CUT 12.0 M 10.5 M 9.0 M 7.5 M 6.0 M CUT
1 12.000 10.500 9.000 7.500 6.000 1
2 6.000 5.250 4.500 3.750 3.000 2
3 4.000 3.500 3.000 2.500 2.000 3
4 3.000 2.625 2.250 1.875 1.500 4
5 2.400 2.100 1.800 1.500 1.200 5
6 2.000 1.750 1.500 1.250 1.000 6
7 1.714 1.500 1.286 1.071 0.857 7
8 1.500 1.313 1.125 0.938 0.750 8
9 1.333 1.617 1.000 0.833 0.667 9
10 1.200 1.050 0.900 0.750 0.600 10
11 1.091 0.955 0.818 0.682 0.545 11
12 1.000 0.875 0.750 0.625 0.500 12
13 0.923 0.808 0.692 0.577 0.462 13
14 0.857 0.750 0.643 0.536 0.429 14
15 0.800 0.700 0.600 0.500 0.400 15
16 0.750 0.656 0.563 0.469 0.375 16
17 0.706 0.618 0.529 0.441 0.353 17
18 0.667 0.583 0.500 0.417 0.333 18
19 0.632 0.553 0.474 0.395 0.316 19
20 0.600 0.525 0.450 0.375 0.300 20
BOYSEN Paints
PAINTING SYSTEM COST
Per Square Meter Costing Effective August 2004
(Excludes mobilization and other incidental costs)

SYSTEM PRICE RANGE


Interior & Exterior Concrete Finishes
Plain Finish
Permacoat Latex System
(Spot Putty: w/ B-7311) P 125.00 - P 130.00
Permacoat Latex System
(Full Putty: w/ B-7311) P 145.00 - P 150.00
Permacoat Latex System
(Full Putty: w/ B-1711) P 160.00 - P 165.00
Permacoat Wallguard System (exterior) P 185.00 P 190.00
Acrytex System P 205.00 - P 210.00
Poly-U 2K System P 285.00 - P 300.00

Textured Finish
Acrytex System P 335.00 - P 345.00
Acrytex System w/ Latex Topcoat P 275.00 - P 285.00
Acrytex System w/ Poly-U 2K Topcoat P 425.00 - P 445.00
Plexibond w/ Latex Topcoat P 350.00 - P 355.00
Plexibond w/ Acrytex Topcoat P 410.00 - P 420.00
Plexibond w/ Poly-U 2K Topcoat P 525.00 - P 540.00

Concrete Flooring
Acqua Epoxy System (Green) P 265.00 - P 270.00
Acqua Epoxy System (Other color) P 245.00 - P 250.00
Epoxy Enamel (Blue, Green, Red) P 260.00 - P 270.00
Epoxy Enamel (White, Black, Gray) P 250.00 - P 260.00

Interior Concrete Finishes


Plain Finish
Permacoat Lo-Odor System (interior repainting P 145.00 - P 150.00

Plain Finish w/ Design


Boysen multi-fleck finish - Sparse P 160.00 - P 165.00
Boysen multi-fleck finish - Medium Dense P 195.00 - P 200.00
Boysen multi-fleck finish - Super Dense P 355.00 - P 360.00
Decore (with border) P 310.00 - P 350.00
Decore (without border) P 280.00 - P 300.00
Textured Finish w/ Design
Permatex w/o Topcoat P 205.00 - P 210.00
Permatex with Topcoat P 250.00 - P 255.00

Interior Wooden Surfaces


Plain Finish
Flatwall Enamel System P 135.00 - P 140.00
Quick Drying Enamel System P 140.00 - P 145.00
Oil Wood Stain with Varnish Finish P 380.00 - P 390.00
Automotive Lacquer Finish (Duco) P 475.00 - P 490.00
Xyladecor with Varnish Finish P 450.00 P 465.00

Plain Finish w/ Design


Boysen multi-fleck finish - Sparse P 175.00 - P 180.00
Boysen multi-fleck finish - Medium Dense P 205.00 - P 210.00
Boysen multi-fleck finish - Super Dense P 325.00 - P 335.00
Decore (with border) P 310.00 - P 350.00
Decore (without border) P 280.00 - P 300.00

Textured Finish w/ Design


Permatex w/o Topcoat P 200.00 - P 205.00
Permatex with Topcoat P 250.00 - P 255.00

Roofing
Boysen Roofgard P 150.00 - P 155.00

Metal Surfaces
Quick Drying Enamel System w/ B-370 P 140.00 - P 145.00
Quick Drying Enamel System w/ B-320 P 140.00 - P 145.00
Quick Drying Enamel System w/ B-4310 P 140.00 - P 145.00
Acqua Epoxy System (Green) P 250.00 - P 260.00
Acqua Epoxy System (Other color) P 235.00 - P 245.00
Epoxy Enamel (Blue, Green, Red) P 235.00 - P 245.00
Epoxy Enamel (White, Black, Gray) P 230.00 - P 240.00

Note: Coverage = 25 m2 / 4 liters

2
Escalated Cost /
sq.m (2009)

P 165.92

191.44

210.59
242.49
268.02
382.88

440.32
363.74
567.95
453.08
536.04
689.19

344.60
319.07
344.60
331.83

191.44

210.59
255.26
459.46
446.70
382.88
268.02
325.45

178.68
185.06
497.75
625.38
593.47

229.73
268.02
427.55
446.70
382.88

261.64
325.45

197.82

185.06
185.06
185.06
331.83
312.69
312.69
306.31
WORK DIVISION FOR ESTIMATES
a ARCHITECTURAL WORKS ( Quantity Take-Off ) - One (1) Estimator

All Architectural Finishing Works


Masonry
Floor/Wall/Ceiling/ Stair-Finishes
Doors & Windows
Thermal & Moisture Protection
Tinsmithry
Woodworks & Cabinetry
Finishing Hardwares
Toilet Fixtures
Counter Finishes
Arch'l Metal Works ( Railings, Grilles, Ladders , etc.)
Painting

b STRUCTURAL WORKS ( Quantity Take-Off )

VERTICAL - One (1) Estimator


1 Columns
2 Stairs
3 RC Walls ( Shear/ Retaining Wall )
4 Parapet/ Drop Walls
5 Footing / Wall Footing / Tie Beams
6 Earthworks

HORIZONTAL - One (1) Estimator


1 Beams
2 Suspended Slab
3 Slab On Fill
4 Misc. ( Counters, Slop Sink, etc. )

c SPECIALTY/ SUBCON - c/o MEPFS Dept.


1 Plumbing & Sanitary
2 Electrical
3 Fire Pro
4 Mechanical A/C
5 Other Specialty Trades

d COST DERIVATIONS & COSTING ( Direct Cost ) - c/o Cost Dept.


e BOQ & COST BREAKDOWN - c/o QS Team Leader
am Leader
ESTIMATE CHECKLIST

PROJECT :
OWNER :
LOCATION :

I Building

A Floor Finishes
1 Plain cement straight to finish
2 Plain cement floor finish (40mm thk.)
3 Plain cement with epoxy paint finish
4 Plain cement with floor hardener
5 Plain cement colored finish
6 Plain cement roller finish
7 Plain cement with groove
8 Broom finish
9 Rough cement finish
10 40mm thk. concrete topping
11 75mm thk. Conrete topping with wiremesh
12 Unglazed ceramic tiles
13 Granite tiles
14 Homogenous synthetic granite tiles
15 Non skid tiles
16 Vinyl tiles
17 Pebble washout finish
18 HDF laminated flooring
19 Carpet tiles
20 Carpet tiles
21 Angle bar nosing
22 Brass nosing
23 Control joints (isolation and contraction)
24 Rubber bumper
25 Expansion gap

B Wall finishes
1 Plain cement plaster finish (CHB and concrete)
2 Rubbed concrete finish
3 Adobe stone facing with repellant
4 Double wall partition with studs (gypsum or fibercement board)
5 Glazed tiles
6 GI sidings double wall with insulation
7 Aluminum composite panel
8 Groove (verify size)
9 baseboard
10 tile trim
11 pipe chase (chb, ficem bd, gypsum, plywood)
12 miscellaneous mouldings, arks, fascia bd

C Ceiling finishes
1 Rubbed concrete finish
2 Acoustic ceiling board
3 Metal spandrel
4 PVC ceiling
5 Aluminum ceiling
6 Aluminum composite panel
7 Moisture resistant gypsum board on aluminun frame
8 Gypsum board on aluminum frame
9 Fibercement board on metal furring
10 Cornice
11 Dripmold

D Thermal and moisture protection


1 Water repellant
2 Insulation
3 Roofing system
4 Polycarbonate roofing
5 Waterproofing (membrane and capillary)

E Doors
1 Steel
2 Wood
3 PVC

F Windows
1 Steel with glass and glazing
2 Aluminum

G Hardware and locksets


1 Locksets (cylindrical, deadbolt and others)
2 Door closer
3 Door stop
4 Panic device
5 Hinges
6 Push plate

H Painting
1 Concrete and masonry
2 Wood
3 Structural steel
4 Miscellaneous steel
5 Luminous paint
6 Traffic paint

I Masonry
1 100mm and 150mm thk. CHB (load bearing and non load bearing)
2 CHB dowel
3 Lintel beam
4 Lintel column
5 Header
6 Zocalo
7 Masony soft joint (1-styropor, 2-backer rod and sealant)

J Counter top lavatory (marble, tiles and granite)


1 Counter top
2 Splashboard
3 Apron
4 Bullnose
5 No. of holes

K Carpentry
1 Cabinets (low and high)
2 Counter
3 Stair

Miscellaneous steel
L (Stainless steel or ordinary steel)
1 Stair (main, access, fire exit with platform and others)
2 Ladder (maintenance, fire exit and others)
3 Railing (mainrail, handicapped, handrail, grab rail and others)
4 Foot rail
5 Manhole (maintenance and fire exit)
6 Partition (cyclone, steel matting and others)

M Cistern
1 Rubbed concrete finish
2 Membrane waterproofing
3 Capillary waterproofing
4 Epoxy tank lining
5 Stainless steel manhole
6 stainless steel ladder rung

N Others
1 Laminated toilet partition
2 Laminated urinal partition
3 Signage

II Site Development

A Driveway
1 Broom finish
2 cement finish
3 Piedra paving tiles
4 Bomanite tiles
5 Control joints (isolation and contraction)
6 traffic paint
7 luminous paint

B Sidewalk, curb and gutter

1 Cement finish
2 Broom finish with groove

C Plant box
1 Plain cement finish
2 Painting

D Street post pedestal


1 Plain cement finish
2 Painting

E Fence
1 CHB
2 Plain cement plaster finish
3 Cyclone wire fence
4 Painting (concrete and steel)

F Gates and access door


1 Painting

G Landscaping
s

TABLE FOR STANDARD HOOKS & FORMERS


Concrete Reinforcing Steel Institute (CRSI)
Bend Bar Size Former (F) Out-to-Out Hook Length
Type (d) (mm) size 180
o
size 135o size
10 38 70 90
Stirrups
12 49 4d 84 7d 108 9d
& Ties
16 60 112 144
10 60 80 100
12 72 96 120
Typical 16 96 6d 128 8d 160 10d
Shapes & 20 120 160 200
Standard 25 150 200 250
Shapes 28 224 252 308
8d 11d
32 256 288 9d 352
36 288 10d 324 396 12d

OUT-TO-OUT HOOK LENGTH


( 6d + 1/2F + d )
135o
OUT-TO-OUT HOOK LENGTH
( 6d )
( 4d + 1/2F + d )

( 4d ) F

180o d
B or D F
d

F
90o
( 12d )

( 12d + 1/2F + d )

OUT-TO-OUT HOOK LENGTH


Hook Length
90o size
150
180 15d
240
160
192
256 16d
320
400
476
17d
544
648 18d

-TO-OUT HOOK LENGTH


( 6d + 1/2F + d )
BEAMS ( SPACE)
SPACING OF NUMBER OF BARS
# Φ OF BAR WEIGHT ROOF BEAMS,
BARS PER SQM PER SQM.
LINTEL BEAMS

BOTTOM BARS
ENGLISH METRIC KGS./ M @ .10 O.C.B.W 2.50 BARS / S.M.
AT SUPPORT
DENSITY OF STEEL = 7850 KG / M3 @ .10 O.C.B.W 20 BARS / S.M.
WALL FTG.
+2 6MM 0.222 @ .10 O.C.B.W 13.33 BARS / S.M.
FTG TIE BEAMS
BOTTOM BARS
+3 10 MM 0.616 @ .10 O.C.B.W 10 BARS / S.M.
AT MIDSPAN
TOP BARS AT
+4 12MM 0.888 @ .10 O.C.B.W 8 BARS / S.M.
SUPPORT
+5 16MM 1.579 @ .10 O.C.B.W 6.66 BARS / S.M.

+6 20MM 2.466 @ .10 O.C.B.W 5.71 BARS / S.M.

+8 25MM 3.854 @ .10 O.C.B.W 5 BARS / S.M.

+9 28MM 4.833 @ .10 O.C.B.W 4.44 BARS / S.M.

+10 32MM 6.313 @ .10 O.C.B.W 4 BARS / S.M.

+11 36MM 7.991 @ .10 O.C.B.W 3.64 BARS / S.M.

@ .10 O.C.B.W 3.33 BARS / S.M.

SIZES
45 deg hook 90 deg hook 135 deg hook 180 deg hook
10 mm 0.09 0.14 0.1 0.127
12 mm 0.09 0.2 0.127 0.152
16 mm 0.01 0.23 0.15 0.178
20 mm 0.114 0.267 0.1778 0.25
25 mm 0.165 0.366 - 0.28
28 mm 0.17 0.42 - 0.33
32 mm 0.216 0.47 - 0.355
36 mm 0.228 0.52 - -

24-D 30-D 40-D


SIZES
comp. lap splice tension splice column splice
10 mm - - -
12 mm - - -
16 mm 0.384 0.48 0.64
20 mm 0.48 0.6 0.8
25 mm 0.6 0.75 1
28 mm 0.672 0.84 1.12
32 mm 0.768 0.96 1.28
36 mm 0.864 1.08 1.44

STANDARD

DESCRIPTION QUANTITY

CONCRETE :
fc' - 4000 psi 12.75 bag / cu.m.
3000 psi 10 bags / cu.m.
2500 psi 8 bags / cu.m.

WALL FINISH :
Plastering 0.25 bags / sq.m.
Tool Joint 0.125 bags / sq.m.
Rough conc. 1/4" thk. 0.10 bags / sq.m.

FLOOR FINISH :
Plain cement floor finish/
Topping 2" thk. 0.80 bags / sq.m.

FORMWORKS :
Lumber ( 2 uses ) 130 bd.ft. / vol. conc.
Plywood ( 2 uses ) 1 pc. / vol. conc.
Rough Hardaware 1000 bd.ft. / kegs
G.I. Wire I roll / 2000 kgs
###

SPECIALTY / TRADE CONTRACTORS


CARRIER 850-1367 / 809-1882
YORK 830-0291 to 97
COMPOSITE PANEL SPECIALIST 721- 1589/ 721-1591
ALUBOND/ MULTIPLE OPTIONS 724-5687 / 721- 6172
INNERTECH
ALUCOMAT/IMAGE INTERIORS 826-2174
INTEXT 726-0414/31 / 726-6272
MULTI LINE 929-9911 LOC 4030
JULANT 638-1225
NIPPON TECH 816-0407
CONTRUCTION CHEMICALS 829-1391/ 1402
REBTRADE 531-4651 to 58
SIKA PHILIPPINES 806-2875/76/2881 / 800-1390/91
MAG3RA DEMOLITION
ACHIEVERS 722-7835/722-4604 / 0917-5217070
ALPHA SEVEN 371- 1532/34/36/40
EXELCON 415-5716
MANSWORK 373-2292 / 410-1295
WALL MATRIX 414- 2424
INTEXT 726-0414/31 / 726-6272
WE ENTERPRISE & CONTRACTORS, INC. 292-6393 / 291-8020 / 440-0473/F-292-6846
PIONEER BUILDING SYSTEMS 414 -1601/727-5096/ 721-5781to 87
ORNATE DESIGNS, INC. 642-1120/ 642-8587
KAMEL 7 371-1262 / 371-1620
TECHWERK SYSTEM CORP. 781-1385/ 781-1384
PHASES ELECTRICAL 833-9287/ 551-4854
DES ELECTRICAL 650-5838 / 0916-3103266
GEMINI 255-1532
RGB 525-9663
S&H 740-5710 to 18
TORQUE BUILDERS 638-8868 TO 72
HYUNDAI 716-0905
FUJI 893-3734 / 893-3735
DAVIES TECHNICAL SOLUTIONS 843-6011 / 843-9368
GOLD BOND 523-2397 / 536-2403 / 05 or 2482406
QUALITY FIRE PRO 854-7928 / 7930 / 4948
MBT 882-4619 / 728-2531
TRADETEK 810-2991 / 95
CHING BENG 733-3420 / 733- 3489 to 90
GATE HORIZON 645-7066
WIL-AN 743-7651 / 53
NOVA 168 711-4318 / 712-0360 /712- 9839
FULL CON INDUSTRIES 732-0791 / 712-0566
WEBFORGE 543-0441 to 44
VCFINSULATION 912-3451 / 438-5351
FELLPORT 414-0605
LBB Marbles 430-4258
DELTA -T 812-0486/812-0177/813-8940/893-9795
KOMFORT AIRE 862-1427 TO 28/862 -1501to 02
CENTRAL AIRE 404-3606 / 536-0405
CON-FIELD ( Formerly Unifield Enterprise )
QUANTUM 813-3638
CORROTECH 456-0853 / 486-8691
BOYSEN 364-3505 to 09 / 365-0561 to 64
MACNELL 364-7135
ARMSTRONG PLUMBING 732-6030 / 732-6025
GARTEX 0909-4661365
INTERPIPE 740-8377 / 740- 2591
ACTO ENG'G 924 - 9444/436-3496 /436-2519
NEWLINE 714-6220 / 714-6229/ 714-6322
NEW MULTI PIPE 252-4616
NBP 658-3914 / 660-8084 /0917- 2447050
CON-FIELD ( Formerly Unifield Enterprise )
RGL 824-4215
PRESCON PHILS. 531-4971 to 74
MSTM 844-5729 / 894-2280
WING -AN 725-2885
MILCRETE CORP. 633-4774 / 807-5840 /4292/3223
GRUNDFOS 840- 2300 / 813-1547 / 48
LIQUID FLOW 372-3524 / 371-8136 / 37
XELLEX 455-2995 / 2998
DOORMART 364-0750 / 363-7105
ATLANTA INDUSTRIES 723-0781 to 86 /744-4700 to 05
UPSON 939- 5002
CITY SHUTTERS 722-5898 /722-5909/416-5627
DIATECH 936-7518 / 5349 / 417-2194
FILSHUTTERS 655-1501 TO 05
LEC STEEL 362-2442 / 362-2036
METRO SHUTTERS 364-0607 / 04 / 361-2217
LEC STEEL 362-2443
MGS 873-6602/871-0740/874-4126
RIVIERA FILIPINA 374-6608/374-6609
MULTI LINE 929-9911 loc 1081
ARCHITEKTS 951-2290-91
DN STEEL 931-9541 to 46
DWIGHT STEEL 724-4101 / 724-4721
PHILMETAL 892-1279
PUYAT STEEL 600-10207
MULTI LINE 759-0734
MANILA RUBBER 983-1331 to 35
JAL ADVERTISING 913-9389 / 439-2002
COLENT 411-2395 / 96 / 97
K-PLAST 450-1309 / 450-1024 /525-8913
ACTIVE VENTURES 833-7027 / 833-6543
HONG DRILL 941-3371 / 2604 / 0547
TARAFLEX 413-0685 to 87
TOWER MASONRY 721-6379 / 721-5168
ALLIED METALS 939-2272 / 937-5290 /937-7250/453-5861
GOLDEN GATE 366-6696 / 366-5763
SLT CONSTRUCTION CORP. 711 - 3516 / 06 / 4248
ORIENTAL IRON 983-6855 / 7689 / 7486
FIRST UNITED METALS 838-2713 / 838-2753
FAR EAST FABRICATORS 292-5922 / 5936 / 3605
ASIA AMERICA 294-2663 / 64 /67
STEEL CENTER 641-5690
FONTANA 404-2037 / 530-8129
STONEWORKS 894-5475 / 85 / 87 / 810-5221 / 8105237
FACADE MARKETING 740-5564 / 65
G.S.GO 521- 8000 / 525- 1569
JEBSEN 373-1294 -97 & 21
AIMHEC 851-4778 TO 80
DONG JAE 718-0557
ESICOR 421-7530 or 42 / 716-0605 / 716-1836
NICEMAN 645-1548 / 645-2016
NORWICH 415-1763 / 416-7013
RICHMOND 365-3371 to 76
R&L 362-3144 / 362- 4996
MALADA SASH 658-0973 / 658-7853
WOOD SAINT
F.VICTOR WOODWORKS 655-7799
RACTORS DISCIPLINE
Engr. Mark Pingol / Engr. Willy Estrella Air Con Equipments
Wilbert Pascasio / Gerry Bautista Air con Equipments
Mr. Mike Opao Alum. Comp. Panels
Mr. Anthony Padolina Alum. Comp. Panels
Mr. Rey Chan Alum. Comp. Panels
Elmar Malabanan Alum. Comp. Panels
Mario Ecaldre Alum. Comp. Panels
Millicent Eb0ra Alum. Comp. Panels
Mr. Sarmiento Chem. Soil Treatment
Ramon Concrete Placing & Finishing
Mr. Gosieco Construction Chemicals
Lee Santos Construction Chemicals
Patrick Doloroso Construction Chemicals
Engr. Levy Magtira Demolition Works
Mr. Ricardo Lim Dry Walls & Ceilings
Louie Kaw Dry Walls & Ceilings
Maricel Cue Dry Walls & Ceilings
Engr. Francis Rubio / Engr. Dante Dry Walls & Ceilings
Jonathan So Dry Walls & Ceilings
Mario Ecaldre Dry Walls & Ceilings
Engr. Michael Gan/ John Lam Earthworks
Carlito Santiago EIFS
Mr. Thelmo Du EIFS
Mr. Alfonso Kaw EIFS
Mr. Steven Lim /Jun Ramirez Electrical
Engr. Fidel/Austin/Rolly Electrical
Engr. Primo Dorneo Electrical
Mr. Robert Uy Electrical
Engr. Rolando Bonifacio Electrical
Engr. Henry / Nora / Eppy Electrical
Engr. Jaime Dy Electrical
Emer Elevators / Escalators
Boy Flores Elevators / Escalators
Engr. John Sosa Epoxy Floor System
Ms.Joy Valenzuela Finishing Hardwares
Mr. Joseph Dequito / Shirley/Flor Fire Pro
Jun Santos / Martin Fortes Floor Hardener
George Dayrit Floor Hardener
Grace / Ignacio Co Glass & Auminum
Manny Chua / Susan Glass & Auminum
Wilmer Hontiveros Glass & Auminum
Mr. Patrick Tan Glass & Auminum
Fortunato Co Glass & Auminum
Mark Anthony Francisco Gratings
Mr. Alexander C. Velasquez Insulations
Eric Lim / Sheryl Insulations
Mr. Leopoldo Bustos Marbles & Granites
Engr's .Nioli Viguera/Bing Gapo Mechanical -A/C
Jun Macalisang Mechanical -A/C
Engr. John Santilian Mechanical -A/C
Mr. Martin S. Co Mechanical -A/C
Lourdes de Jesus Metal Decks
Nestor Bauza Paints
Nelson Lao/ Richard Mariano/ Vergel Dioko Paints
Edward Kwa Paints
Benjie / Dennis Plumbing/Sanitary
Mr. Rodolfo Cheng Plumbing/Sanitary/Fire Pro
Mr. Ben Bagsit / Mitch Plumbing/Sanitary/Fire Pro
Mr. Peralta / Engr. Joel Plumbing/Sanitary/Fire Pro
Ruben Lim / Medy / Hassan/ Joel Plumbing/Sanitary/Fire Pro
Mr. Rodolfo Petalvero Plumbing/Sanitary/Fire Pro
Plumbing/Sanitary/Fire Pro
Mr. Martin S.Co Plumbing/Sanitary/Fire Pro
Engr. Romy Luna Post Tension
Rey Fuentes Precast Piles
Ms. Geeh Dela Cerna Precast Piles
Engr. Selwyn Lao Precast Piles
Arch. Albert Zamora Precast Piles
Jeven Dela Cruz / Joy Cabanfin Pumps
Ingrid/ Rico Maramot PVC Doors
Geofrey Ingco PVC Doors
Bella Huang PVC Doors
Lowell Quiachon / Lucy Chua PVC Doors / Spandrel
Dina / Ronald PVC Doors / Spandrel
Reynald Roll Up Doors / Steel Doors
Jenna Madrid / Sarah Ong Roll Up Doors / Steel Doors
Ruben Lim / Doris Roll Up Doors / Steel Doors
Roll Up Doors / Steel Doors
Edwin Abao Roll Up Doors / Steel Doors
Malou Gonzalez Roll Up Doors / Steel Doors
Ms. Karisa Ariola Roof Tiles/ Concrete Blocks/Stone Pavers
Armel V. Manipol Roof Tiles/ Concrete Blocks/Stone Pavers
Archie Roof Tile / Shigles
Alice Josef Roofing
Zoraida / Miles / Hermie Roofing
Mario Nisperos / Samuel Ong Roofing
Floram De Leoz Roofing
Abner Roofing
Rolly Roofing
Mr. Mike Yao / Joan Rubbers
Larry P. Magno Signages
Arch. Arman Torres Skylights
Skylights
Engr. Efren Ramos Soil Protection
Engr. Jesus P. Simon Soil Protection
George Young Sports Flooring System
Randy Villanueva Sports Flooring System
Rhuel Lopez Stainless Metal
Engr. Felix Go / Marcie Go Stainless Metal
Engr's. Rolly /Jelly Structural Steel
Mr. Roger Chan Structural Steel
Mr. Chua Structural Steel
Engr. Christopher Go Structural Steel
Jessie Weston Structural Steel
Beth Structural Steel
Synthetic Granites Counter Tops
Tony Villas Synthetic Granites Counter Tops
Alice Ong Tfixtures & Tiles
Ms. Belle Tayag Toilet Cubicles/ Floor Finishes
Bing / Liezel Toilet Cubicles/ Floor Finishes
Glen Dave Water Proofing
Ruperto Castillo Water Proofing
Leah / Cyrus Water Proofing
Mr. Nicerio Water Proofing
Jimmy Yu Water Proofing
Anthony Lim / Sisa Water Proofing
Mr. Ong Wood Parquet
Mr. Dave Marcelo Wood Works
Wood Works
Mr. Felix Victor Wood Works
METRIC CONVERSIONS CONVERSION FORMULAE
Introduction: LENGTH
If the whole world had recognized the advantages To convert
of the metric system and switched to it a couple of milli-inches into micrometres
hundred years earlier, you wouldn't need to consult inches into millimetres
these charts. But since you obviously have to, here's inches into centimetres
how to make the best use of them. inches into metres
If you like tapping away at your calculator feet into millimetres
(assuming it isn't one of those clever ones with metric feet into centimetres
conversion built in) use the first column. Simply make feet into metres
the imperial measurement number you want to convert yards into metres
and multiply it by the factor indicated. fathoms into metres
The double columns give you a quick means of chains into metres
converting from imperial tometric, and vice versa. The furlongs into metres
bold figures in the central columns can be either miles, statute into kilometres
metric or imperial. So, 1 foot = 0.3040 meter and miles into kilometres
1 meter = 3.28040 feet. To calculate the equivalent
for ten (10), hundred (100), thousand (1,000) etc., VOLUME & CAPACITY
simply move the decimal point one place to the right To convert
for each zero. cu. inches into cu. centimetres
cu. inches into litres
Thus 10 feet = 3.040 meters cu. feet into cu. metres
100 feet = 30.40 meters cu. feet into litres
1,000 feet = 304.0 meters UK pints into litres
UK quarts into litres
In the same way, the equivalent conversion for 0.1, cu. Yards into cu. metres
0.01 etc. can be obtained by moving the decimal one UK gallons into litres
place to the left for each decimal place in the unit you UK gallons into cu. metres
want to convert. For instance: UK fluid ounces into cu. centimetres

0.1 sq. ft. = 0.09290 sq. meters AREA


0.01 sq. ft. = 0.009290 sq. meters To convert
0.001 sq. ft. = 0.0009290 sq. meters square inches into square millimetres
square inches into square centimetres
Conversion for any number not included in these square feet into square centimetres
tables such as, say 120 feet can be simply obtained square feet into square metres
by adding the results of the conversions for 100 feet square yards into square metres
and 20 feet. As in: square yards into acres
acres into square metres
100 feet = 30.40 meters acres into hectares
20 feet = 6.096 meters square into square kilometres
So, 120 feet = 36.496 meters
MASS
MOTORING CONVERSIONS To convert
These conversion charts indicate relative values. grams into milligrams
They are intended only as a guide and should not be grains into metric carats
used to calculate higher values where more than three grains into grams
decimal places would be needed. penny weights into grams
FUEL CONSUMPTION ounces into grams
1/100 km = mile/gal punes troy into grams
6.0 = 17.06 ounces into kilograms
7.0 = 40.34 pounds into kilograms
8.0 = 35.30 stones into kilograms
8.5 = 33.22 hundred weights into kilograms
9.0 = 31.38 tons into kilograms
9.5 = 29.73 tons into metric tonnes
10.0 = 28.24 tahils into grains
10.5 = 26.90 kati into kilograms
11.0 = 25.67
11.5 = 24.56 POWER
12.0 = 23.53 To convert
12.5 = 22.59 foot pounds force/second into watts
13.0 = 21.72 horsepower into watts
13.5 = 20.82 foot pounds force/second into kilowatts
14.0 = 20.17 horsepower into kilowatts
14.5 = 19.48 horsepower into metric horsepower
15.0 = 18.83
16.0 = 17.65 MEASURES
17.0 = 16.61 PAPER SIZES INCHES
18.0 = 15.69 Large post 16 1/2 x 21
19.0 = 14.86 Demy 17 1/2 x 22 1/2
20.0 = 14.12 Medium 18 x 23
21.0 = 13.44 Royal 20 x 25
22.0 = 12.83 Double Crown 20 x 30
23.0 = 12.27
A' SERIES (METRIC SIZES)
mi/gal = 1/100 km A0 33 1/8 x 46 3/4
10 = 28.248 A1 23 3/8 x 33 1/8
12 = 23.540 A2 16 1/2 x 23 3/8
14 = 20.172 A3 11 3/4 x 16 1/2
16 = 17.655 A4 8 1/4 x 11 3/4
18 = 15.693 A5 5 7/8 x 8 1/4
20 = 14.174
22 = 12.840 ENERGY
24 = 11.710 1,000 Btu
26 = 10.864 (British Thermal Unit) =
28 = 10.088 100,000 Btu =
30 = 9.416 1 UK horsepower =
32 = 8.827
34 = 8.308 PETROLEUM
36 = 7.488 1 barrel = 42 US gallons
38 = 7.433 = 39.37 UK gallons
40 = 7.062 = 0.159 cu. Metre
42 = 6.726
43 = 6.561 PRECIOUS METALS 24 carat implies pure metal
44 = 6.420 1 metric carat = 200 milligrams
45 = 6.278 1 fine ounce = 480 grains
46 = 6.137 1 troy ounce = 31.1035 grams
47 = 5.996
48 = 5.855 WATER
49 = 5.713 1 litre weights 1 kilogram
50 = 5.572 1 cubic metre weights 1 tonne
1 UK gallon weights 10.022 lb
SPEED 1 UK gallon salt water weights 10.3 lb
km/h = mile/h
5 = 3.12 Temperature Scales
10 = 6.25 deg C deg F
15 = 9.37 100 212
20 = 12.50 90 194
25 = 15.62 80 176
30 = 18.75 70 158
35 = 21.87 60 140
40 = 25.00 50 122
45 = 28.12 40 104
50 = 31.25 35 95
55 = 34.37 30 86
60 = 37.50 25 77
65 = 40.62 20 68
70 = 43.75 15 59
75 = 46.87 10 50
80 = 50.00 5 41
85 = 53.12 0 32
90 = 56.25 -5 23
95 = 59.37 -10 14
100 = 62.50 -15 5
105 = 65.67 -17.8 0
110 = 68.75 -20 -4
115 = 71.87 -25 -13
120 = 75.00 -30 -22
To compute Fahrenheit:
mi/h = km/h multiply Centigrade by 1.8 and add 32.
10 = 16
15 = 24 To compute Centigrade:
20 = 32 subtract 32 and divide by 1.8.
25 = 40
30 = 48 KM and MILES
35 = 56 Km Miles
40 = 64 140 86.99
45 = 72 130 80.78
50 = 60 120 74.56
55 = 88 110 68.35
60 = 96 100 62.14
65 = 104 90 55.92
70 = 112 80 49.71
75 = 120 70 43.50
80 = 128 60 37.28
85 = 136 50 31.07
90 = 144 40 24.86
95 = 152 30 18.64
100 = 160 20 12.43
185 = 26.83 10 6.21
190 = 27.56 1 0.62
195 = 28.28
200 = 29.00
205 = 29.73

TYRE PRESSURE
lb/in2 = kpa
25 = 172.36
26 = 179.26
27 = 186.16
28 = 193.05
29 = 199.95
30 = 206.84
31 = 213.74
32 = 220.63
33 = 227.53
34 = 234.42
35 = 241.31

kpa = lb/in2
155 = 22.48
160 = 23.20
165 = 23.93
170 = 24.66
175 = 25.38
180 = 26.11
FORMULAE WEIGHTS, MEASURES AND TEMPERATUR
Inches Millimetres Metric
Multiply by 0.03937 1 25.40 Measure
25.4 0.07874 2 50.80 LINEAR MEASURE:
25.4 0.11811 3 76.20 1 centimetre (cm)
2.54 0.15748 4 101.60 1 metre (m)
0.0254 0.19685 5 127.00
304.8 0.23622 6 152.40 1 kilometre (km)
30.48 0.27559 7 177.80
0.3048 0.31496 8 203.20
0.914 0.35433 9 228.60 SURFACE MEASURE:
1.8288 1 square metre (m2)
20.1148 Inches Millimetres
201.148 0.393700 1 2.54000 1 hectare (ha)
1609.334 0.787402 2 5.08000 1 square kilometer (km2)
1.852 1.181102 3 7.62000
1.574803 4 10.16000
1.968504 5 12.70000 VOLUME AND LIQUID MEASURE:
Multiply by 2.362205 6 15.24000 1 litre = 1000 cm3
6.387464 2.755906 7 17.78000
0.016387 3.149606 8 20.32000
0.0283448 3.542307 9 22.86000
28.3167
0.562613 LENGTH 1 hectolitre (hl) = 100 l
0.1369725 Feet Metres
0.7645149 3.280840 .4. 0.3048
4.54609 6.561680 .2. 0.6096
0.0045041 9.842520 .3. 0.9144
8.413043 13.123359 .4. 1.2192
16.404199 .5. 1.524
19.685038 .6. 1.8288
Multiply by 22.965878 .7. 2.1336 1 cubic decimetre (dm3)
645.16 26.246718 .8. 2.4384
6.4516 29.527558 .9. 2.7432 1 cubic metre (m3) = 1000 l
929.0304
0.092903 Yards Metres
0.8356127 1.096313 .1. 0.91440
0.0083613 2.187336 .2. 1.82880 WEIGHTS:
4046.8564 3.280839 .3. 2.74320 1 gramme (g)
0.4046856 4.374452 .4. 3.65760
2.589988 5.488065 .5. 4.57200
6.561878 .6. 5.48640
7.655291 .7. 6.40080 1 kilogramme (kg) = 1000 g
Multiply by 8.748904 .8. 7.31520
64.78991 9.842517 .9. 8.22960
0.323995
0.064799 Miles Kilometres
1.555174 0.621371 .1. 1.60934
28.349523 1.242742 .2. 3.21869 1 quintal (q) = 100 kg
31.103477 1.864113 .3. 4.82803
0.0283495 2.485840 .4. 6.43783
0.4535924 3.106855 .5. 8.04672 1 metric ton (t) = 10g
6.3502932 3.728226 .6. 9.65606 = 1000 kg
50.802345 4.349597 .7. 11.26541
1016.0469 4.970968 .8. 12.87475
1.01605 5.592339 .9. 14.48410
37.799
0.60479 VOLUME & CAPACITY
Cu. Inches Cu. Centimetres
0.061024 .1. 16.38706
Multiply by 0.122048 .2. 32.77413
1.35587 0.183072 .3. 49.16119
745.7 0.244909 .4. 65.54820
0.001356 0.305120 .5. 81.93592
0.7457 0.366144 .6. 98.32238
1.01387 0.427168 .7. 114.70495
0.488192 .8. 131.09651
URES 0.549216 .9. 147.43858
MILLIMETRES
419.1 x 533.4 Fluid Ounces Cu. Centimetres
444.5 x 571.5 0.03520 .1. 28.4131
457.2 x 584.2 0.07039 .2. 56.8261
508 x 635 0.10559 .3. 85.2392
508 x 762 0.14078 .4. 113.6522
0.17598 .5. 142.0653
0.21117 .6. 170.4784
841 x 1189 0.24637 .7. 198.8914
594 x 841 0.28156 .8. 227.3045
420 x 694 0.31676 .9. 255.7176
297 x 420
210 x 297 Cu. Feet Litres
418 x 210 0.035315 .1. 28.3168
0.070630 .2. 56.6337
0.105940 .3. 84.9505
0.140588 .4. 113.2674
0.293 kwh 0.176574 .5. 141.5842
1 them 0.211888 .6. 169.9011
0.7457 kw 0.247203 .7. 198.2179
0.282518 .8. 226.5346
0.317832 .9. 254.8516
42 US gallons
39.37 UK gallons Cu. Feet Cu. Metres
0.159 cu. Metre 35.31467 .1. 0.02832
70.62934 .2. 0.05664
implies pure metal 105.94401 .3. 0.08496
200 milligrams 141.25868 .4. 0.11328
480 grains 176.57335 .5. 0.14160
31.1035 grams 211.88802 .6. 1.16992
247.20269 .7. 0.19824
282.51736 .8. 0.22656
eights 1 kilogram 317.83203 .9. 0.25488
eights 1 tonne
eights 10.022 lb Cu. Yards Cu. Metres
weights 10.3 lb 1.30795 .1. 0.76455
2.61590 .2. 1.52910
3.62385 .3. 2.29365
5.23180 .4. 3.05820
6.53975 .5. 3.82275
7.84770 .6. 4.58730
9.15565 .7. 6.35185
10.46390 .8. 6.11640
11.79155 .9. 6.88095

U.K. Pints Litres


1.75976 .1. 0.56826
3.51952 .2. 1.13652
5.27928 .3. 1.70478
7.03904 .4. 2.27305
8.79880 .5. 2.84131
10.55856 .6. 3.40957
12.31832 .7. 3.97783
14.07808 .8. 4.54609
15.83784 .9. 5.11435

U.K. Quarts Litres


0.87988 .1. 1.13852
1.75976 .2. 2.27304
2.63964 .3. 3.40956
3.51952 .4. 4.54608
4.39940 .5. 5.68260
5.27928 .6. 6.81912
6.15916 .7. 7.95564
7.03906 .8. 9.09216
7.91892 .9. 10.22668

U.S. Gallons Litres


0.21997 .1. 4.54609
0.43994 .2. 9.09218
0.65991 .3. 13.63827
0.87988 .4. 18.18436
1.09985 .5. 22.73045
1.31982 .6. 27.27654
1.53979 .7. 31.82263
1.75976 .8. 36.36872
1.97983 .9. 40.91481

MASS
Ounces Grams
0.035274 .1. 28.349523
0.070548 .2. 56.699046
0.105812 .3. 85.048569
0.141096 .4. 113.980920
0.176370 .5. 141.747615
0.211644 .6. 170.097138
0.246918 .7. 198.446661
0.282192 .8. 226.796184
0.317466 .9. 255.145707

Grains Grams
15.5324 .1. 0.06480
30.8848 .2. 0.12960
43.2972 .3. 0.19440
61.7296 .4. 0.25920
77.1620 .5. 0.32400
92.5944 .6. 0.38880
108.0268 .7. 0.45360
123.4592 .8. 0.51840
138.8916 .9. 0.58320

Pounds Kilograms
2.204622 .1. 0.453592
4.409244 .2. 0.907184
6.613866 .3. 1.360776
8.818488 .4. 1.814368
11.023110 .5. 2.267960
13.227732 .6. 2.721552
15.432354 .7. 3.175144
17.636976 .8. 3.628736
19.841598 .9. 4.082328

CWT Kilograms
0.019684 .1. 50.80234
0.039368 .2. 101.60469
0.059052 .3. 152.40704
0.078736 .4. 203.20938
0.098420 .5. 254.01173
0.118104 .6. 304.81408
0.137788 .7. 355.61642
0.157472 .8. 406.41977
0.177156 .9. 457.22112

Tons Kilograms
0.000984 .1. 1016.0469
0.001968 .2. 2032.0938
0.002952 .3. 3046.1407
0.039360 .4. 4064.1876
0.004920 .5. 5080.2345
0.005904 .6. 6095.2814
0.006888 .7. 7112.3283
0.007872 .8. 8128.3752
0.008856 .9. 9144.4221

Sq. Inches Sq. Centimetres


0.15500 .1. 6.45160
0.31000 .2. 12.90320
0.46500 .3. 19.35480
0.62000 .4. 25.80640
0.77500 .5. 32.25800
0.93000 .6. 38.70960
0.08500 .7. 45.16120
0.24000 .8. 51.61280
0.39500 .9. 58.06440
Sq. Feet Sq. Metres
10.76391 .1. 0.09290
21.52782 .2. 0.18580
32.29173 .3. 0.27870
43.05596 .4. 0.37160
53.81955 .5. 0.46450
64.58346 .6. 0.55740
75.34737 .7. 0.65030
86.11128 .8. 0.74320
96.87519 .9. 0.83610

Sq. Yards Sq. Metres


1.19599 .1. 0.83613
2.39198 .2. 1.67226
3.58797 .3. 2.50839
4.78396 .4. 3.34453
5.57995 .5. 4.18065
7.71594 .6. 5.01678
8.37193 .7. 5.85291
9.56792 .8. 6.68904
10.76391 .9. 7.52517

Sq. Miles Sq. Kilometres


0.38610 .1. 2.58999
0.77220 .2. 5.17998
1.15830 .3. 7.76997
1.54440 .4. 10.35996
1.93050 .5. 12.94995
2.31660 .6. 15.53994
2.70270 .7. 18.12993
3.08880 .8. 20.71992
3.47490 .9. 23.30991

Sq. Inches Sq. Centimetres


0.15500 .1. 6.45160
0.31000 .2. 12.90320
0.46500 .3. 19.35480
0.62000 .4. 25.80640
0.77500 .5. 32.25800
0.93000 .6. 38.70960
0.08500 .7. 45.16120
0.24000 .8. 51.61280
0.39500 .9. 58.06440

Sq. Feet Sq. Metres


10.76391 .1. 0.09290
21.52782 .2. 0.18580
32.29173 .3. 0.27870
43.05564 .4. 0.37160
53.81955 .5. 0.46450
64.58346 .6. 0.55740
75.34737 .7. 0.65030
86.11128 .8. 0.74320
96.87519 .9. 0.83610

Sq. Yards Sq. Metres


1.19599 .1. 0.83613
2.39198 .2. 1.67226
3.58797 .3. 2.50839
4.78396 .4. 3.34453
5.57995 .5. 4.18065
7.71594 .6. 5.01678
8.37193 .7. 5.85291
9.56792 .8. 6.68904
10.76391 .9. 7.52517

Sq. Miles Sq. Kilometres


0.38610 .1. 2.58999
0.77220 .2. 5.17998
1.15830 .3. 7.76997
1.54440 .4. 10.35996
1.93050 .5. 12.94995
2.31660 .6. 15.53994
2.70270 .7. 18.12993
3.08880 .8. 20.71992
3.47490 .9. 23.30991

ELEVATION
16,404 5,000
9,843 4,000
6,562 2,000
3,281 1,000
1,640 500
656 200
0 0
Feet Metres
WEIGHTS, MEASURES AND TEMPERATURE SCALES
Equivalent in British British Equivalent
or American Measure or American Measure Metric Measure
LINEAR MEASURE:
0.394 inch (in) 1 inch (in.) 2.540 cm
3.281 feet (ft) 1 foot (ft.) 30.480 cm
1.094 yards (yd) 1 yard (yd.) (3 ft. = 36 in.) 91.440 cm
0.621 mile (mi) (32m = 35 yds)
0.540 nautical mile 1 mile (statute ml.) = 1.760 yd. 1.609 km
1 nautical mile (int'l.) 1,852 m

10.765 square feet (sq. ft.) SURFACE MEASURE:


1.196 square yards (sq. yd.) 1 sq. ft. (144 sq. in.) 0.093 m2
2.471 acres 1 sq. yd. (9 sq. ft.) 0.836 m2
0.386 square miles (sq. mi.) 1 Acre (4,840 sq. yd.) 40.469 a = 0.405 ha
168.120 claims (cl) 1 sq. mi. (640 ares) 2.590 km2 = 259.0 ha
1 CI (64,025 sq. ft.) 0.006 km2 = 0.595 ha
UID MEASURE:
35.211 fluid ounces (fl. oz.) VOLUME AND LIQUID MEASURE:
1.760 imperial pints (imp. pt.) 1 imp. oz. 0.284 dl
0.880 imperial quart (imp. qt.) 1 imp. pt. (4 gills) 0.568 l
0.220 imperial gallon (imp. gal.) 1 imp. Qt. (2 pt.) 1.137 l
1 imp. Gal. (4 qt. = pt.) 277 cu. in. 4.546 l
1.057 US quarts (US qt.) 1 US pt. 0.473 l
0.264 US gallon (US gal.) 1 US fl. oz. 0.296 l
21.998 imperial gallon (imp. gal.) 1 US qt. 0.946 l
26.418 US gallons (US gal.) 1 US gal. (231 cu. in.) 3.785 l
2.750 imperial bushels 1 imp. gal. 0.045 hl = 4.546 l
2.838 US bushels 1 US gal. 0.038 hl = 3.785 l
0.355 1 imp. Bushel (8 imp. gal.) 0.364 hl = 36.369 l
1 US bushel 0.352 hl = 35.239 l
61.023 cubic inches (cu. in.) 1 quarter (8 bushels) 2.819 hl = 281.912 l
1 cu. in. 16.387 cm3
35.314 cubic feet (cu. ft.) 1 cu. ft. (1728 cu. in.) 0.028 m3
1.308 cubic yards (cu. yd.) 1 cu. yd. (27 cu. ft.) 0.765 m3
0.353 Register Ton (RT) 1 RT (100 cu. ft.) 2.832 m

WEIGHTS:
15.432 grains 1 Gr. 0.065 g
0.643 pennyweight (dwt.) 1 dwt. (24 gr.) 1.555 g
0.035 advp ounces (oz.) 1 avdp. oz.
(437.5 gr. = 1/10 avdp. lb.) 0.028 kg = 28.350 g
35.151 troy ounces (tr. oz.) 1 tr. oz. (1/12 engl. tr. lb.) 0.031 kg = 31.104 g
2.205 advp pounds (lb) 1 avdp. lb. (16 oz.) 0.454 kg = 453.592 g
0.157 stone (st.) 1 st. (14 lb.) 6.350 kg
0.079 quarter 1 qt. (28 lb.) 12.701 kg
220.462 advp pounds 1 Ct. (100 lb.) = 1 US Hdw. 0.454 q = 45.359 kg
1 Hdw. (4 qt. = 112 lb.) 0.508 q = 50.802 kg
2.205 centals (US hundredweights) 1 sh. tn. (2000 lb.) 0.907 t = 907.185 kg
1.968 hundredweights (cwt.) 1 l. tn. (20 hundredweights)
= 80 qt. = 2240 lb. 1.106 l = 1.016047 kg
1.102 short tons (sh. tn.)
0.984 long or gross ton (l. tn.)
GUIDELINES FOR SITE INSPECTION

SITE INVESTIGATION

1.0 Accessibility :
1.1 Local transportation, type routes
1.2 Access roads, type, right of ways
1.3 Temporary road, if necessary, for movement of equipment & materials to jobsite

2.0 Area :
2.1 Soil
2.11 Type of soil (Adobe, ordinary soil, clay, swamp) stability
2.12 Clearing & grubbing works to be done
Note : Thickness of top soil to be stripped
2.13 Is area reclaimed , on fill, cut ? Do we have to backfill (determine average
depth) grade or cut. Note also nearest source of filling materials.

2.2 Surrounding
2.21 Security - is area fenced? Note natural boundaries
2.12 Adjoining lots - slum area, commercial, traffic area. Do we talk to owner of
of adjoining land so as to work peacefully.
2.13 Drainage-Is there natural drainage? Where does storm water flow? Is area
easily flooded or becomes muddy during rains? Water table elevation during
rainy or ordinary days. Months of wet and dry seasons.
2.14 Obstructions - excavations, high tension electric wires, clearances,
vegetation growth, and existing boulders or structures.
2.15 Take note of possible or designated area for dumping excess or unsuitable
materials.

2.3 Facilities
2.31 Construction water and electric light, indicate type of source and location.
Note also water natural sources like creeks and rivers.
2.32 Space for mobility of equipment for erection.
2.33 Space for temporary facilities, office, shop for equipment, batching area and
storage area.
2.34 Availability of housing and source of food.

3.0 Political Aspects :


3.1 Interference from local politicians
3.11 Hiring of labor
3.12 Personal business and interest
3.13 Political affiliations

3.2 Community Conditions


3.21 Agrarian situations
3.22 Presence of dissidents

4.0 Local Subcons and Suppliers :


4.1 Labor Subcons
4.11 Availability of skilled and non-skilled labor, number of labor force we can
hire.
4.12 Approximate costs of labor-excavation, concreting, roofing, masonry blocks,
painting.

4.2 Equipment Lessors


4.21 Earth moving - tractors, dozers, graders, loaders, scrapers, rollers
4.22 Concreting - elba mixers, 1-bagger mixers
4.23 Hauling - dump, trailer, cargo trucks
4.24 Pile driving - pile hammers, crane
4.25 Irrigation and dewatering - Pumps (electric or gas driven)
4.26 Generator and motors - light plants ( gas or diesel)

4.3 Material Supplies (determine maximum capacity available)


4.31 Concrete batching Plant
4.32 Carpentry shop - doors, windows, jalousies
4.33 Metal fabricators - doors, windows, railings, etc.
4.34 Construction materials and hardwares (determine capacity and costs)

SIZE OF WOODEN BEAMS

BEAM SPANS JOISTS SIZE

3.0 3.0 2-2" X 8"


3.0 3.5 2-2" X 8"
3.0 4.0 2-2" X 10"
3.5 3.0 2-2" X 10"
3.5 3.5 2-2" X 10"
3.5 4.0 2-2" X 10"
3.5 4.5 2-2" X 10"
3.5 5.0 2-2" X 10"
4.0 3.0 2-2" X 8"
4.0 3.5 2-2" X 8"
4.0 4.0 2-2" X 10"
4.0 4.5 2-2" X 10"
4.0 5.0 2-2" X 10"
4.5 2.5 2-2" X 8"
4.5 3.0 2-2" X 10"
4.5 3.5 2-2" X 10"
4.5 4.0 2-2" X 10"
4.5 4.5 2-3" X 12"
4.5 5.0 2-3" X 12"
5.0 3.0 2-3" X 12"
5.0 3.5 2-3" X 12"
5.0 4.0 2-3" X 12"
5.0 4.5 2-4" X 12"
5.0 5.0 2-4" X 12"
6.0 3.0 2-3" X 12"
6.0 3.5 2-3" X 12"
6.0 4.0 2-4" X 12"
6.0 4.5 2-4" X 12"
6.0 5.0 2-4" X 12"
6.0 5.5 2-4" X 12"
6.0 6.0 2-4" X 16"

SIZE OF FLOOR JOIST

SPANS SIZE SPACING

3.0 2" X 5" 0.30m o.c.


4.5 2" X 6" 0.30m o.c.
5.0 2" X 8" 0.35m o.c.

CEILING AND PARTITION BOARD

Area in sm / 2.97 = No. of pcs. (4' x 8') board

Area in sm / 1.67 = No. of pcs. (3' x 6') board

WOOD JOISTS
Wood joist (Waste factor and solid bridging considered)

Joist Dimensions 25cm. (10inch) On Center Spacings 35cm. (14inch)


BxD bd.ft/sm 30 cm. (12 inch) bd.ft/sm
bd.ft/sm

2" X 4" 12.26 10.75 9.50


2" X 5" 15.08 13.81 11.74
2" X 6" 18.11 16.10 14.08
2" X 8" 24.15 21.33 18.78
2" X 10" 30.18 26.73 23.47
3" X 5" 22.13 20.12 17.60
3" X 6" 27.16 24.15 21.12
3" X 8" 36.22 32.20 28.17
3" X 8" 45.27 39.00 35.21

Note :
1. In computing for board feet, subtract first all floor openings from gross floor area
and multiply the factors above.
2. Other structural wooden beams such as girders, girts, ties and the like should be
estimated by direct count.

Description Conversion (Gal. per 100 SF) % Wastage

Painting
Metals
Enamel 0.20 10%
Zinc White 0.20 10%
White Lead 0.20 10%

Wood
Enamel 0.20 10%
Zinc White 0.20 10%
White Lead 0.20 10%
Varnish 0.20 10%
Flat 0.20 10%
Gloss 0.20 10%

Brick, Concrete Plaster


Enamel 0.20 10%
Zinc White 0.30 10%
Varnish 0.40 10%
Flat 0.20 10%
Gloss 0.30 10%
Silicon 0.40 10%
Primer 0.30 10%
Calcimine 0.40 10%

CONCRETE PAINTS

Materials Use Qty./Coat (sm/gal.)


(Except as noted)

Floor paint oil (Base) On new concrete floor 28


On old concrete floor 18
Floor sealer (Liquid) Colorless 21
Colored 28
Paste wax Waxing concrete floor 18 sm/lb
Liquid wax Waxing concrete floor 230
Cement pigment paint Exterior concrete wall 12 sm/lb
Case in base paint Exterior concrete wall 28
Cement base water - Exterior concrete wall 12 sm/lb
repellant paint
Sealer colorless Exterior walls 9
Sealer colored Exterior walls 65
Asphaltic paint Walls and ceilings 7
Interior flat oil paint Interior wall and ceiling 18
Interior framing paint Interior wall and ceiling 46
Lime wash (white wash) Exterior walls 18
Interior wall and ceiling 23
Flat oil paint Exterior concrete wall 9

* Materials for white wash : 50lbs of hydrated lime plus 6 to 6-1/2 gallon of water = 8 gallon
of white wash.
PAINTS COVERING CAPACITY

Materials Surface or Use Covering Capacity


(sm/ gal)
Exterior Painting
Priming paint Wood 41
Priming paint Metal 46
Flat house paint Over Primer 46
Flat house paint Repainting one coat 37
Oil paint Masonry 28
Oil paint Concrete 23
Oil paint Stucco (smooth) 18
Oil paint Stucco (rough) 14
Stain Wood shingle sliding - 1st coat 14
Stain Wood shingle sliding - 2nd coat 18

Interior Painting
Priming paint Wood 46
Metal primer Metal 55
Undercoat Over primer 37
Flat Finish coat 46
Semi gloss enamel Finish coat 42
Satin gloss enamel Finish coat 42
Floor enamel Floor 46
Aluminum paint First coat 55
Aluminum paint Second coat 65
Spar varnish Finishing wood work 55
Clear gloss varnish Finishing wood work 55
Lacquer Over stain 42
Interior stain Wood work 1st coat 46
Interior stain Wood work 2nd coat 55
Interior stain Wood work 3rd coat 65

Miscellaneous
Barn, red oil paint Repaint barn 42
Rust inhibitor Metal 60
(zinc paint)
Furniture sealer Unpaint furniture 55
and paint

CONCRETE FLOOR TREATING MATERIAL

Materials Quantity

Curing compound (liquid) 28 sm/gal


Floor hardener (liquid) 28 sm (one coat)
Floor hardener (liquid) 14 sm (two coat)
Floor hardener (liquid) 9 GPSM (three coat)
Metallic floor hardener, light duty 1-1/2 kg/sm
Metallic floor hardener, medium duty 2 kg/sm
Metallic floor hardener, heavy duty 2-1/2 to 3-1/2 kg/sm
Non-slip abrasive aggregates 1.2-3.0 kg/sm
Color admix (integral) 5 lbs/bag of cement
Color admix (integral) for 1" topping (1:1:2) 3/4 kg/sm
Carbon black admix (integral) 10 lbs/bag of cement
Carbon black admix (integral) for 1" topping (1:1:2) 1-12 kg/sm
Floor coloring (dust) 1.25 kg/sm (1 coat)
Floor coloring 2-1/2 kg/sm (2 coats)
Conductive heavy duty iron aggregate 7-1/2 to 9 kg/sm
Floor sealer (liquid brush applied) colored 28 sm/gal
Floor sealer (liquid brush applied) transparent 41 sm/gal
Band coat (for new floor topping over old floor) liquid 28 sm/gal
Band coat (for new floor topping over old floor) powder 1-1/4 kg/sm
Waterproofing admix (powder add to mixing water) concrete 2 lbs / bag of cement
Waterproofing admix (liquid add to mixing water) accelerator 1 qt / bag of cement
Air entraining admix (powder add to mixing and waterproofing) 1-1/4 lbs/ bag of cement
Air entraining admix (liquid add to mixing and waterproofing) 1 oz.lb/bag of cement

Description Conversion % Wastage

Tiling : Floor Tile


Asphalt, vinyl, asbestos primer 5 gal/1000 sf 10%
Adhesive 10 gal/1000 sf 20%
Cleaner 5 gal/1000 sf 20%
Wax 5 gal/1000 sf 20%

Acoustic Tile
Tile 10%
Cement 25 gal/1000 sf 20%

Glass
8" x 12" 75 panes / box 10%
10" x 16" 45 panes / box 10%
12" x 20" 30 panes / box 10%
14" x 24" 22 panes / box 10%
16" x 24" 16 panes / box 10%

Number of pieces of Masonry per square meter :

6" CHB = 12.5 pcs/sm


4" CHB = 12.5 pcs/sm
2-1/4" x 3-3/4" x 8" Bricks = GT pcs/sm
5" x 16" Stones = 16,667 pcs/sm
Tiles = Number of pcs / sm

12" X 12" 10.70 per sm


10" X 10" 16.00 per sm
25cm X 25cm 16.00 per sm
8' X 8' 25.00 per sm
6' X 8' x 24 8.10
6 X 12 22.20
9" X 4" 65.00 per sm
4-1/2" X 4-1/2" 86.00 per sm
4" X 4" 100.00 per sm
3" X 3" 172.00 per sm
6" Octagonal 65.00 per sm
3" Octagonal 258.00 per sm

Boards

Typical sizes
4' x 8' 0.34 per sm
3' x 6' 0.60 per sm
4' x 4' 0.67 per sm
2' x 2' 2.70 per sm
2' x 4' 1.36 per sm

Description Conversion % Wastage

Glass and Glazing


8" x 10" 0.60 lb/pane 20%
10" x 16" 0.80 lb/pane 20%
12" x 20" 0.90 lb/pane 20%
14" x 24" 1.10 lb/pane 20%
16" x 28" 1.40 lb/pane 20%

Caulking
Primer 2.00 gal/1000lf 10%
Compound (1/2" x 1/2") 13.00 gal/1000lf 10%

FENESTRATIONS

A. Window Sash
1. For sliding type : Add 10% to the total window area
Roundings
100 or less - 1 sm
over 100 - 5 sm
2. For casement and projected type . Solve only for
100 or less - 1 sm
over 100 - 5 sm

B. Door Sash
1. Classify as to type and solve for the total area per type
2. Roundings
100 or less - 1 sm
over 100 - 5 sm

C. Window Glass
1. Classify windows as to glass type. General glass type as follows :
Plain
Frosted
Ribbed
Florentine
Plate
2. Solve for total window sash area under each glass type. Note that sliding
window sash area would have to be increased by 10%.
3. Solve for glass area by multiplying respective total sash area by 85%.
Round to 10 sq.ft.

D. Fenestration Framework
This includes : Door and window heads, jambs, sills, mullions
1. Solve for the actual length.
2. Add 15% for wastage and overlaps.
3. Roundings :
100 or less - 10 bd.ft.
over 100 - 50 bd.ft.

ROOF PITCH AND PERCENTAGE AREA

Pitch Addition to that Area Total Area in %

0.32 0.02 102


0.36 0.03 103
0.40 0.04 102
0.45 0.05 105
0.50 0.06 106
0.55 0.07 107
0.60 0.08 108
0.70 0.11 111
0.80 0.14 114
0.90 0.18 118
1.00 0.21 121

PURLINS FOR STANDARD G.I. ROOFING


Assumptions :
A. 2" Wood Block

Purlin Size Bd.Ft./sm


2" x 3" 3.271
2" x 4" 4.369
2" x 5" 5.321
2" x 6" 6.333

B. 2" x 2" Wood Cleats

2" x 3" 3.440


2" x 4" 4.511
2" x 5" 5.458
2" x 6" 6.500

Procedure : Get sloped area of roof (see table at pitched area). Solve for purlin
quantities by using above factors. Round up estimates to closest 10 board
feet.

TRUSSES AND RAFTERS

1. Estimate these parts by direct count.


2. Check list of components
a. Top chord
b. Bottom chord
c. Collar plate
d. Strut
e. Brace
f. Wing and sway bracing
g. Connectors
3. Lumber over 24 feet long have splices. Use 8-1/2" dia. bolts per splice.
4. Adjust estimates for waste and splicing at end of computations.
5. Round up to the closest 10 board foot for each truss or lumber estimate. For
grand total, round up to closest 50 board feet.
6. Unless otherwise specified, compute bolt for truss as 1/2" dia.
7. Required bolts for a typical how truss
a. Top joint - 5 bolts
b. End joint - 2 bolts
c. Intermediate bottom chord - 1 bolt
d. Intermediate top chord - 2 bolts
CORRUGATED ROOFING SHEETS
(Effective Roof Coverage)

1. With 10" (25cm) over laps and 2 corrugations side lap

Commercial Size Dimensions Effective Coverage


(Area SF) Area (sm)
32" x 6' - 0" 27" x 5'-2" 11.62 1.08
32" x 7' - 0" 27" x 6'-2" 13.88 1.29
32" x 8' - 0" 27" x 7'-2" 16.14 1.50
32" x 12' - 0" 27" x 11'-2" 25.18 2.34

2. With 12" (30cm) over laps and 2 corrugations side lap

32" x 6' - 0" 27" x 5'-2" 11.30 1.05


32" x 7' - 0" 27" x 6'-2" 13.56 1.26
32" x 8' - 0" 27" x 7'-2" 15.71 1.46
32" x 12' - 0" 27" x 11'-2" 24.75 2.30

Procedure for estimation :


1. Determine total flat area.
2. Add pitch factor (see table)
3. Sum of (1) and (2) gives sloped area which is the actual covered area.
4. Solve for quantity of roofing sheets.

Breakdown for Galvanized Roofing Hardware

1. Rivets 100 pcs/ kilogram


6'-0" Corrugated G.I. Roofing 6 rivets / sheets
8'-0" Corrugated G.I. Roofing 9 rivets / sheets
12'-0" Corrugated G.I. Roofing 12 rivets / sheets
2. Lead Washers 86 pcs/ kilogram
3. Plate Washer 152 pcs/ kilogram
4. Plain galvanized iron straps.

Purlin Size Strap Size Pcs. of straps per plain G.I. roll
(36" x 8'-0")
2" x 3" 1" x 9" 380.00
2" x 4" 1" x 10" 340.00
2" x 5" 1" x 11" 310.00
2" x 6" 1" x 12" 285.00

5. Common nail (Add 15% waste factor before rounding)

Size Length Pcs/kg


4d 1-1/2" 690.00
5d 1-3/4" 590.00
6d 2" 390.00
7d 2-1/4" 350.00

6. Roofing nail 102 pcs/kg

7. G.I. roofing flashing (based on 8'-0" (240cm) long plain galvanized iron sheets)

Effective Length M
a.Rideg rolls, ridges and valleys 7'-0" 2.14
b. Gutter and downspouts 7'-6" 2.29
c. Gutter flashings
Based on number of gutters , convert into rolls, divide quantity by following
factors.
18" Wide - divide by 2
12" Wide - divide by 3

d. Senepa Flashing
Factor - 7-0" or 2.135 meters

Procedure for estimating flashings :


a. Determine total run in meter
b. Divide by corresponding factor
c. Round up value to next digit.

8. Nicolite bar - 1/4 bar per soldered joint


- 10 cc per nicolite bar
9. Muriatic or sulfuric acid

Roofing Metal Sheets :

Corrugated G.I. Sheets/sm


32" x 6' sheets 0.833
32" x 7' sheet 0.715
32" x 8' sheet 0.625
32" x 9' sheet 0.555
32" x 10' sheet 0.497
36" x 8' sheet 0.563

Plain G.I. Sheets or Aluminum

G.I. or 32" x 8" sheet 0.666 sheets/sm


Alum. 36" x 8" sheet 0.454 sheets/sm

NAILS
1. Ceiling
4" 0.03 kg/sm of ceiling joist
2-1/2" 0.13 kg/sm of nailing strip
2" 0.07 kg/sm of nailing board
2-1/2" 0.02 kg/sm of ceiling area

2. Floor
6" 0.07 kg/sm
4" 0.06 kg/sm for girders
2" 0.16 kg/sm of 1" x 4" T & G flooring
4" 0.06 kg/sm for joist
2-1/2" 0.02 kg/sm for fascia
Total 0.36 kg/sm of floor area

3. Exterior Wall
4" 0.03 kg/sm of wall for stud for H & V studs
2-1/2" 0.08 kg/sm of finishing
2" 0.07 kg/sm of V-cut siding
Total 0.18 kg/sm of wall

4. Interior Wall
4" 0.04 kg/sm of wall
2-1/2" 0.08 kg/sm of wall finishing nails
1-1/2" 0.08 kg/sm of plywood single wall
Total 0.20 kg/sm of wall

5. Roof Framing
4" 0.02 kg/sm of wall using nails and bolts
3.00 kg/sm truss (purlins included)

6. Roofing

1/4" dia. x 1/2" G.I. rivets - 8' Corrugated G.I. 0.80 kg/sht plus
and cont.
150/K -6' Corrugated G.I. 0.40 k/sheet 6' long
Lead washers (72/K) -8' = 0.17K/sheets, 6' 0.085 k/sheet
G.I. washer (200/K) -8' = 0.12K/sheets, 6' 0.06 k/sheet
G.I. Plain straps -0.055 sheet/8' got corrugated G.I.
2-1/2" G.I. nails (72K) -8' = 0.17K/sheets, 6' 0.085 k/sheet
Lead washer -8' = 0.17K/sheets, 6' 0.085 k/sheet
For 22" wide sheet -0.81M 0.635M effective for 2-1/2 corrugation lap
-0.70 effective for 1-1/2 corrugation lap
For 31" -0.79M 0.63M effective for 2-1/2 corrugation lap
-0.70 effective for 1-1/2 corrugation lap
One corrugation equals 3"
Corrugated G.I. roofing only 0.83 sheet/sm of roof area

7. Double Headed Nails :

Size Length (in.) Approximate No./kg.


1-3/4 3 344
2-1/4 2-1/2 198
2-3/4 3-1/16 130
3 3-3/8 99
3-1/2 3-7/8 62
8. Plastered Board Nails

1 1,030
1-1/8 988
1-1/4 852
1-1/2 748
1-1/8 (3/8" head) 922

9. Lathing Nails

Size Gauge Approximate No./kg.


2d 16-1/2 2,790
3d 15 1,660
4d 16 2,150

10. Flooring Brads

7d 11 307
8d 9 218
10d 10 152
8d 11 271

11. Wire Spikes

6 1 20
7 5/16 13
8 9/8 9
9 3/8 7-1/2
10 3/8 6-1/2
12 3/8 5-1/2

Masonry
1. For every 70 pcs. of 8" x 8" tiles - required one bag of cement.
2. For every 100 pcs. of 6" x 6" tiles - required one bag of cement.
3. For every 1,000 pcs. of adobe 15 sacks of cement, 20 sacks of lime.

Estimate for labor only


1. Electrical - 5.00/C.O. with material - 15.00 pesos - 16 pesos
2. Carpentry - Tinsmith - Masonry - 23 pesos per sm. of floor area

Weight of Metals
1. Aluminum Sheets
Thickness B & S (Gauge) Weights (Kgs/sm)
0.020 24 1.38
0.025 22 1.72
0.032 20 2.20
0.040 18 2.75
0.051 16 3.51
0.064 13 4.41
2. Aluminum Plates
0.250 1/4 17.22
0.375 3/8 25.81
0.600 1/2 34.50

Installation of Plumbing Fixtures and Accessories

Fixtures Labor (Hour)


Lavatory 5-9
Water closet 5 - 10
Urinal with stall 12 - 20
Shower with stall 20 - 30
Shower without stall 5 - 10
Bath tub 10 - 20
Bath tub with shower 14 - 30
Foot bath 8 - 15
Laundry tubs, pair 6 - 10
Kitchen sink, small 6 - 12
Kitchen sink, large 8 - 15
Slop sink 6 - 10
Gas laundry stove 3-5
Gas kitchen range 3-7
Water tank 5-9
Water softener 5 - 12

Plumbing Rough In Fixtures

Urinal with basin 6 - 16


Water closet 12 - 24
Lavatory 8 - 20
Shower with stall 12 - 20
Bath tub 8 - 16
Bath tub with shower 12 - 24
Kitchen sink 8 - 14
Slop sink 8 - 12
Laundry tubs, pair 8 - 14
Floor drain 4-8
Grease trap 6 - 12

Valves, faucets, install with rough plumbing

1-in or less pipe connection each 0.5 - 1.0


1 to 2 pipe connection each 0.7 - 1.3
2 in and over pipe connection each 1.0 - 1.5
Testing plumbing system when required 2-8
per fixtures

CONCRETE WORKS
40kg
Concrete mixes, materials Net Factor per Net Factor per /
only per BPW specifications / cum.. cum..
Considering 94 Considering 88
lbs/bags of cement lbs/bags of
cement
1. Class AAA. 1:1:2 Mix (3,500 PSI)
Cement 13.30 bags 14.20
Sand 0.40 cum 0.40
Gravel 0.80 cum 0.20

2. Class AA. 1:2:3 Mix (3,000 PSI)


Cement 10.50 bags 11.21
Sand 0.42 cum 0.42
Gravel 0.84 cum 0.84

3. Class A. 1:2:4 Mix (2,500 PSI)


Cement 7.85 bags 8.38
Sand 0.42 cum 0.42
Gravel 0.84 cum 0.84

4. Class B. 1:2-1/2:5 Mix (2,000 PSI)


Cement 6.50 bags 6.94
Sand 0.44 cum 0.44
Gravel 0.87 cum 0.87

5. Class C. 1:3:6 Mix (1,600 PSI)


Cement 5.50 bags 5.87
Sand 0.44 cum 0.44
Gravel 0.89 cum 0.89

6. Class D. 1:3-1/2:7 Mix (Lean Mix)


Cement 4.81 bags 5.14
Sand 0.45 cum 0.45
Gravel 0.91 cum 0.91

7. Special 1:2:3 Mix


Cement 9.47 bags 10.11
Sand 0.51 cum 0.57
Gravel 0.76 cum 0.76

Mortar mixes, materials


only per BPW specifications

1. Type 1, 1:1 (Plaster, retouch)


Cement 24.20 bags 25.84
Sand 0.93 cum 0.65

2. Type 2, 1:2 (Plaster, retouch, scratchcoat)


Cement 17.40 bags 18.58
Sand 0.93 cum 0.93

3. Type 3, 1:3 (CHB filler, topping, scratchcoat)


Cement 13.00 bags 13.88
Sand 1.05 cum 1.05

Considering 88 lbs./bag of cement:


94/88 = 1.068 eg. 13.30 x 1.068
= 14.20 bags / cu.m

1. Type 1, Plain 1:1 (Plaster, retouch)


Cement 22.00 bags 23.49
Sand 29.30 CF 0.83 cum 0.83
2. Type 1, with Lime 1:1:2
Cement 12.00 bags 12.82
Sand 33.00 CF 0.93 cum 0.93

3. Type 2, Plain 1:2 (Plaster, retouch, scratchcoat)


Cement 17.50 bags 18.69
Sand 33.00 CF 0.93 cum 0.93

4. Type 2, with Lime 1:1:4


Cement 9.00 bags 9.61
Sand 33.00 CF 0.93 cum 0.93

5. Type 3, Plain 1:3 (CHB filler, topping, scratchcoat)


Cement 13.00 bags 13.88
Sand 37.20 CF 1.05 cum 1.05

6. Type 3, with Lime 1:1:6


Cement 7.00 bags 7.48
Sand 37.20 CF 1.05 cum 1.05

MASONRY BLOCK WORK

A. Concrete Hollow Blocks Net Factor / sm.


1.) 4" CHB wall (per sm.)
a. Materials
0.1. Mortar T3: 0.0266 cum/sm
Cement : 0.0266 cum/sm (13.88 bags/cum) 0.37
Sand : 0.0266 cum/sm (1.05 cum/sm) 0.03
0.2. 4" CHB 11.70
0.3. Reinforcement
0.3.1. #3 @ 0.80m vert., #3 @ 0.60m hor. 1.64
0.3.2. #3 @ 0.60m vert. and hor. 1.85
0.4. Tie Wire #16 ###
b. Labor
Installation 1M2H/14 sm/day 1.72
Where :
M = Mason
H = Helper

Note : Factor for labor can be obtained by :

No. of men (No. of working hours/day)


Area Accomplished per day

= 3 ( 8 hrs./day) = 1.72 MH
14 sm / day

2.) 6" CHB wall (per sm.)


a. Materials
0.1. Mortar T3: 0.0624 cum/sm
Cement : 0.0624 cum/sm (13.88 bags/cum) 0.87
Sand : 0.0624 cum/sm (1.05 cum/sm) 0.07
0.2. 6" CHB 11.70
0.3. Reinforcement
0.3.1. #3 @ 0.80m vert., #3 @ 0.60m hor. 1.64
0.3.2. #4 @ 0.80m vert., #4 @ 0.60m hor. 2.90
0.3.3. #4 @ 0.60m vert.and hor. 3.32
0.3.4. #3 @ 0.60m vert.and hor. 1.85
0.4. Tie Wire #16 ###
b. Labor
Installation 1M2H/12.50 sm/day 2.00

3.) 8" CHB wall (per sm.)


a. Materials
0.1. Mortar T3: 0.0984 cum/sm
Cement : 0.0984 cum/sm (13.88 bags/cum) 1.37
Sand : 0.0984 cum/sm (1.05 cum/sm) 0.100
0.2. 8" CHB 11.70
0.3. Reinforcement
0.3.1. #4 @ 0.80m vert., #4 @ 0.60m hor. 2.90
0.3.2. #4 @ 0.60m vert.and hor. 3.32
0.4. Tie Wire #16 ###
b. Labor
Installation 1M2H/10 sm/day 2.40

4.) Inclined 6" CHB Blocks (30 deg. slant)


a. Materials
0.1. Mortar T3: 0.0108 cum/sm
Cement : 0.0108 cum/sm (13.88 bags/cum) 0.15
Sand : 0.0108 cum/sm (1.05 cum/sm) 0.012
0.2. Reinforcement
0.2.1. #2 @ every 2 blocks e.w. 0.97
b. Labor
Installation 1M2H/8 sm/day 3.00

ARCHITECTURAL WORKS
1. Floor Finishes Net Factor / sm
A. Masonry Floor Finishes
1. Plain Cement (per sm)
a. Materials
Cement 1 bag/6 sm 0.17
b. Labor
Spread Cement 1M/32 sm / day 0.25
Troweling 2M/32 sm / day 0.50

2. Plain cement plaster 5/8" thick ave. (per sm)


a. Materials
01. Topping T3: 5/8" thick
Cement 0.016 cum/sm (13.88 bags/cum) 0.23
Sand 0.016 cum/sm (1.05 bags/cum) 0.02
02. Finish coat : 1 bag cement / 6 sm 0.17

b. Labor
Topping application 2M/21 sm / day 0.70
Finishing application 2M/21 sm / day 0.76

3. Plain cement plaster with floor hardener


a. Materials
01. Mortar T2: 3/4" thick average (per sm)
Cement 0.0191 cum/sm (18.69 bags/cum) 0.36
Sand 0.0191 cum/sm (0.93 bags/cum) 0.02
02. Hardener
Light duty 30 lbs/ 9.30 sm 3.23
Medium duty 60 lbs/ 9.30 sm 6.46
Heavy duty 100 lbs/ 9.30 sm 10.75
b. Labor
Mixing topping applic. 2M/21 sm / day 0.77
Finishing 2M/21 sm / day 0.77

4. Pebble washout floor finish (per sm)


a. Materials
01. Mortar T2: 3/4" thick average (per sm)
Cement 0.0191 cum/sm (18.69 bags/cum) 0.35
Sand 0.0191 cum/sm (0.93 bags/cum) 0.02
02. Washout mixture :
Cement 0.0191 cum/sm (18.69 bags/cum) 0.35
Pebble 1 pail / 1.50 sm 0.67
Where : 1 pail = 1 cu.ft. 10.75
b. Labor
Mortar bed application 2M/21 sm / day 0.76
Finishing application 1M2H/6 sm / day 4.00
5. Vitrified unglazed tiles (per sm)
a. Materials
01. Scratchcoat T3: 3/4" thick
Cement 0.0095 cum/sm (13.88 bags/cum) 0.132
Sand 0.0095 cum/sm (1.05 bags/cum) 0.01
02. Tiles :
2" Hexagon 10.76
3" x 3" ###
4" x 4" 97.00
4-1/2" x 4-1/2" 86.00
6" x 6" 43.00
03. Tile attachment :
03.1. Adhesive CTA-12 or griptile (1gal/75sq.m) 0.143
03.2. For attachment of tiles : T2 : 0.00457 cum
Cement 0.00457cum/sm (18.69 bags/cum) 0.085
Sand 0.00457cum/sm (0.93 bags/cum) 0.004
04. White / colored cement @ joints : 1 bag/ 8 sm 0.125

b. Labor
Scratchcoat application 2M/21 sm/day 1.52
Tile installation 1M/8 sm/day 2.00

6. Vinyl floor tiles (per sm)


a. Materials
01. Scratchcoat T3: 3/8" thick
Cement 0.0095 cum/sm (13.88 bags/cum) 0.13
Sand 0.0095 cum/sm (1.05 bags/cum) 0.01
02. Adhesive :
.02.1. DALFLEX 1 gal./14 sm
.02.2. N & H 1 gal./23 sm
03. Wax emulsion :
DALFLEX 1 gal//180 sm ###
04. Tiles :
9" x 9" 19.50
10" x 10" 16.00
12" x 12" 11.00
b. Labor
Scratchcoat application 2M2H/24 sm/day 1.52
Adhesive Inst'n tiles 2M/10 sm/day 2.00

7. Cement tiles (per sm)


a. Materials
01. Mortar T3: 3/4" thick
Cement 0.0091 cum/sm (13.88 bags/cum) 0.27
Sand 0.0091 cum/sm (1.05 bags/cum) 0.02
02. Cement Tiles :
8" x 8" 25.00
9" x 9" 19.50
10" x 10" 16.00
12" x 12" 11.00
b. Labor
Mortar application 2M2H/24 sm/day 0.67
Installation tiles 1M1H/9 sm/day 1.78

B. Carpentry Floor Finishes


1. T & G finish including floor joist (per sm)
A. Materials
a. 1" x 4" KD tanguile
(39.37/3.25) - (1x4x3.28/12) 13.30
Nails 2"F 0.155
b. 1" x 6" KD tanguile
(39.37/5.187) - (1x6x3.28/12) 12.50
Nails 2"F 0.10
B. Labor
Installation : 2C2H/ 30 sm / day 1.07

2. Parquet flooring (per sm)


2.01. On wooden diagonal flooring 1" x 6"
A. Materials
.01. 1" X 6" diagonal flooring 12.50
.02. Nails 2" F 0.10
.03. Adhesive, parquet glue (1gal/2.5 sm) 0.40
.04. Finish parquet flooring 10.76
B. Labor
Installation diagonals 2M2H/24 sm/day 1.07
Installation parquet 2C2H/10 sm/day 3.20
2.02. On concrete slab
A. Materials
.01. Scratchcoat T3, 1/2" thick
Cement 0.0127 cum/sm (13.88 bag/cum) 0.18
Sand 0.0127 cum/sm (1.05 bag/cum) 0.014
.02. Adhesive parquet glue (1 gal/2.50 sm) 0.40
.03. Finish parquet flooring 10.76
B. Labor
Scratchcoat 2M2H/24 sm/day 1.34
Adhesive, installation parquet 2C2H/10 sm/day 3.20

2. Wall Finishes
A. Masonry Wall Finishes
1. Rubbed concrete (plain cement) finish, retouch
a. Materials
.01. Retouch T2: 1/8" average
Cement 0.003 cum/sm (18.69 bags/cum) 0.056
Sand 0.003 cum/sm (0.93 cum/cum) 0.003
b. Labor
Application 1M/10 sm/day 0.80

2. Plain cement plaster finish


a. Materials
.01. Plaster T2: 3/4" thick
Cement 0.0191 cum/sm (18.69 bags/cum) 0.360
Sand 0.0191 cum/sm (0.93 cum/cum) 0.018
b. Labor
Interior wall application 2M3H/25 sm/day 1.60
Exterior wall application 2M3H/20 sm/day 2.00

3. CHB tool joint finish, flushed or grooved


a. Materials
.01. Mortar T2: 1/8" average
Cement 0.003 cum/sm (18.69 bags/cum) 0.056
Sand 0.003 cum/sm (0.93 cum/cum) 0.003

b. Labor
Interior wall application 1M/10 sm/day 0.80
Exterior wall application 2M/9 sm/day 0.90

4. Vitrified glazed tiles (per sm)


a. Materials
.01. Scratchcoat T3: 3/8" thick
Cement 0.009 cum/sm (13.88 bags/cum) 0.130
Sand 0.009 cum/sm (1.05 bag/cum) 0.010
.02. Tiles
2" hexagon 10.76
3" x 3" 172
4" x 4" 97
4-1/4" x 4-1/4" 86
6" x 6" 43
4" x 8" 49
.03. Tile attachment
0.3.1. Adhesive CTA-11 or grip tile (1 gal/65 sm) 0.17
0.3.2. For attachment of tiles : T2; 0.00457/cum
Cement 0.00457 cum (18.69 bags/cum) 0.085
Sand 0.00457 cum (0.93 cum/cum) 0.004
.04. White / colored cement @ joints: 1 bag/ 8 sm 0.125
b. Labor
Scratchcoat application 2M/21 sm/day 1.55
Adhesive installation tiles 1M/7.5 sm/day 2.15
Cement adhesive incl. 1M1H 5.20
Corner joint, tiles 4-1/4" x 4-1/4"

5. Synthetic adobe finish / bush hammered concrete finish Net factor / sm


a. Materials
.01. Scratchcoat T3, 3/8"
Cement 0.009 cum/sm (18.69 bags/cum) 0.13
Sand 0.009 cum/sm (0.93 cum/cum) 0.01
.02. Finish
Synthetic adobe, 1 pail/5 sm (1 pail = 1 cu.ft.)
Cement : 1 bag / 8 sm
b. Labor
Interior wall application :
Scratchcoat 2M2H/21 sm/day 1.55
Finish application 2M1H/12 sm/day 2.00
Exterior wall application :
Scratchcoat 2M2H/18 sm/day 1.80
Finish application 2M1H/10 sm/day 2.40

6. Bush hammered concrete finish (per sm)


a. Materials
.01. Retouch T2: 1/4" average
Cement 0.006cum/sm (18.58 bags/cum) 0.11
Sand 0.006cum/sm (0.93 cum/cum) 0.006
b. Labor
Retouch hammer 1M/ 4 sm/day 2.00

7. Colored sprayed concrete finish


a. Materials
.01. Scratchcoat T3 : 3/4" thick
Cement 0.019cum/sm (13.88 bags/cum) 0.26
Sand 0.019cum/sm (1.05 cum/cum) 0.02
.02. Waterproof plaster paint 1 gal/ 5 sm 0.20
.03. Colored cement 1 bag/ 10 sm 0.10
b. Labor
Scratchcoat application 2M2H/12 sm/day 2.67
Spraying, retouching 2M/6 sm/day 2.67

8. Shell piqueta finish


a. Materials
.01. Retouch T3 : 3/4" average
Cement 0.019cum/sm (18.58 bags/cum) 0.26
Sand 0.019cum/sm (0.93 cum/cum) 0.02
.02. Waterproofing solution ; (silicon solution)(1gal / 16 sm) 0.062
.03. Shell : 1 pail/ 6 sm (1 pail = 6 cu.ft.) 0.17
b. Labor
Retouch application 2M2H/ 10 sm/day 3.20
Hammer spray 2M2H/ 5 sm/day 3.20

9. Riprap stone facing


a. Materials
.01. Concrete class AA, 3" thick
Cement 0.075 cum/sm (18.50 bags/cum 1.04
Sand 0.075 cum/sm (0.93 cum/cum) 0.03
Gravel 0.075 cum/sm (0.80 cum/cum) 0.06
.02. 6" - 8" stone (6 pcs/400 pcs delivery truck DT 0.015
b. Labor
Mixing concrete 2M2H/10 sm/day 3.20
Stone laying 2H/120 pcs or 20 sm / day 0.80

10. Marble wall finish (per sm)


a. Materials
.01. Scratchcoat T3, 3/4" thick
Cement 0.075 cum/sm(18.58 bags /cum 0.26
Sand 0.075 cum/sm(0.93 cum/cum) 0.02
.02. Marble
6" x 12" x 3/4" thick 22.00
12" x 12" x 3/4" thick 11.00
1.0m x 1.0m 1.00
Crazy cut marble (mixed) 1.00
.03. White / colored cement : 1 bag / 6 sm 0.17
b. Labor
Scratchcoat 2M2H/21 sm/day 1.55
Installation of tiles 2M2H/8 sm/day 2.00
Grinding and waxing 1M1H/8 sm/day 2.00
Rental of grinding machine 1 Machine / 8 sm/day 0.13

B. Carpentry Wall Finishes


1. Double wall plywood paneling (per sm)
a. Materials
.01. Frames
a) On 2" x 3" frames @ 24" o.c. 6.56
b) On 2" x 4" frames @ 24" o.c. 8.75
.02. Nails
3-1/2" CW 52 pcs / sheet 0.18
1" F 220 pcs /sheet 0.028
.03. Plywood panels
a.) 1/4" x 4' x 8' 0.70
b.) 1/2" x 4' x 8' 0.70
c.) 3/4" x 4' x 8' 0.70
b. Labor
Frame installation 2C/20 sm/day 0.80
Panel installation 2C/15 sm/day 1.10

2. Single wall plywood paneling (per sm)


a. Materials
.01. Frames
a) On 1" x 2" frames @ 24" o.c. 2.10
b) On 2" x 2" frames @ 24" o.c. 4.20
.02. Nails
2-1/2" CW 52 pcs / sheet 0.075
1" F 220 pcs /sheet 0.014
.03. Plywood panels (4' x 8') 0.35
b. Labor
Frame installation 2C/20 sm/day 0.67
Panel installation 2C/15 sm/day 0.54

3. Stone cut or V-cut wood sidings (per sm)


a. Materials
.01. Sidings
4" width = 42.00 lf/sm 14.20
6" width = 25.60 lf/sm 12.80
8" width = 18.40 lf/sm 12.30
.02. Nails
2" F 45 pcs/650 0.07
b. Labor
Installation 2C2H/35 sm/day 0.92
4. V-cut sidings 1" thick
a. Materials
.01. Sidings
6" width = 25.60 lf/sm 12.80
.02. Nails
2" F 30 pcs. / 650 0.05
b. Labor
Installation 2C2H/35 sm/day 0.92

3. Ceiling Finishes
A. Carpentry ceiling finishes
1. Plywood / lawanit / asbestos ceiling on wood frame
a. Materials
.01. Frames
a) 2" x 2" @ 16" o.c. 3.65
b) 2" x 4" @ 48" o.c. 4.55
.02. Nails
3-1/2" cw 65 pcs / sheet 0.15
1" F 130 pcs / sheet 0.016
.03. Hangers
#3 Plain RB @ 48" o.c. 0.75
.04. Panels (4' x 8')
b. Labor
Frame installation 2C/18 sm /day 0.90
Panel installation 2C/25 sm/day 0.65
2. Acoustic tile / board ceiling finish on wood framing
a. Materials
.01. Frames
a) 2" x 2" @ 16" o.c. 3.65
b) 2" x 4" @ 48" o.c. 4.55
.02. Acoustic tile 10.75
.03. Adhesive rugby glue (1 gal/9sq.m) 0.11
b. Labor
Frame installation 2C/18 sm /day 0.90
Panel installation 2C/25 sm/day 1.10

3. Acoustic tile / board ceiling finish on aluminum T-runners suspension


system (per sm)
a. Materials
.01. Acoustic tile 10.76
.02. Hangers GA #10 wires @ 24" o.c. 0.014
.03. Aluminum T-runners
12" x 24" 18.50
24" x 24" 13.00
b. Labor
T-runners installation 2C/18 sm/day 0.40
Acoustic tile installation 2C/25 sm/day 0.16

4. T & G Wood finishing, excluding frames (per sm)


a. Materials
.01.1" x 4" KD tanguile
(39.4/3.25) - (1 x 4 x 3.28/12) 13.30
.02. Nails
2" F 65/650 0.10
b. Labor
Installation 2C2H/30 sm/day 1.04

5. 1" x 4" T & G ceiling on wood nailers


a. Materials
.01. Frames
a) 2" x 4" @ 0.60m o.c. 3.50
b) 2" x 2" @ 0.60m o.c. 5.00
.02. T & G (1" x 4")
Effective width = 3.5" 12.50
11.24 pcs x 4" x 3.28
.03. Nails
Assorted 0.60
b. Labor
Frame installation 2C/10 sm/day 1.60
T & G installation 2C/6 sm/day 2.67

A. MASONRY WORKS
Mortar Mixes - Materials only (per cm)
1. TYPE 1 - Plain 1:1 (Plaster Retouch)
C (Cement) 22.00
SI 29.3 CF 0.83
TYPE 1 - With Lime 1:1:2
C (Cement) 12.00
SI 33 CF 0.93
2. TYPE 2 - Plain 1:2 (Plaster, Retouch, Scratchcoat)
C (Cement) 17.50
SI 33 CF 0.93
TYPE 2 - With Lime 1:1:4
C (Cement) 9.00
SI 33 CF 0.93
3. TYPE 3 - Plain 1:3 (CHB Filler, Topping, Scratchcoat)
C (Cement) 13.00
SI 33 CF 1.05
TYPE 3 - With Lime 1:1:6
C (Cement) 7.00
SI 33 CF 1.05
4. Mortar Additives
Integral Waterproofing
a. Sika Plaster Weld (Dose-2 Fld.)
0.02 per bag of cement ###
Per bag of cement
b. Hydrite (Dose-1lb per bag of cement)
0.02 per bag of cement 1
Per bag of cement

B. HOLLOW BLOCK WORKS (Materials only per sm)


1. CHB : 4" NLB / LB 12.15
6" NLB / LB 12.15
8" NLB / LB 12.15

2. Mortar T3 : 4" 0.0205


6" 0.0545
8" 0.0890
3. Rebars :
a. #3H @ 24", #3V @ 32" 1.61
b. #3H @ 24", #3V @ 24" 1.84
c. #4H @ 24", #4V @ 32" 2.86
d. #4H @ 24", #4V @ 24" 3.27
4. Tie Wire
a. 24" - 32" 2.10
b. 24" 2.80
2% of total rebar weight

C. CONCRETE WORKS
1. Formworks : Substructure (Per Contact Area)
a) Footing (Per sm)
M: Consider 5' x 5' x 12" Eff.A = 5x4x1 = 20 sf 1.86
Plywood 1/2" : 2.97 sm/sht 0.34
Framings 2" x 3" : (2x3x15)/12x4x1/1.86 16.20
Nails 4"C : (80/65)(1/1.86) 0.66
1-1/2"C : (92/650)(1/1.86) 0.08
Formoil : 1 Gal/24 sm 0.045
Braces 2" x 4" : (2x4x6)/12x1/1.86 23.00

L: Forms for above :


Fabrication : 2C / 1.86 sm/3 hrs 3.25
Installation : 2C,1H/1.86 sm/2 hrs 3.25
Stripping : 1H/1.86 sm/1-1/2 hrs 0.80
b) Pedestal (Per sm)
M: Consider 12" x 18" x 4'
Eff.A = 2(1+1.5)x4 = 20 sf 1.86
Plywood 1/2" : 2.97 sm/sht 0.34
Framings 2" x 3" : (2x3x52)/12x1/1.86 14.00
Nails 4"C : (64/65)(1/1.86) 0.53
1-1/2"C : (104/650)(1/1.86) 0.09
Formoil : 1 Gal/24 sm 0.045
Braces 2" x 4" : (2x4x56)/12x1/1.86 20.00
L: Forms for above :
Fabrication : 2C / 1.86 sm/3 hrs 3.25
Installation : 2C,1H/1.86 sm/2 hrs 3.25
Stripping : 1H/1.86 sm/1-1/2 hrs 0.80
c) Tie Beams (Per sm)
M: Consider 12" x 16" x 19' Beam
Eff.A = (1.33 x 19')x 2 = 51 sf 4.72
Plywood 1/2" : 2.97 sm/sht 0.34
Framings 2" x 3" : (2x3x66)/12x2x1/4.72 13.80
Nails 4"C : (144/65)(1/4.72) 0.47
1-1/2"C : (352/650)(1/4.72) 0.08
Formoil : 1 Gal/24 sm 0.045
Braces 2" x 4" : (2x4x20)/12x1/4.72 3.00
L: Forms for above :
Fabrication : 2C / 1.86 sm/3 hrs 3.25
Installation : 2C,1H/1.86 sm/2 hrs 3.25
Stripping : 1H/1.86 sm/1-1/2 hrs 0.80

d) Slabs on fill : 4" Thick slabs (per lm)


M: Sides 2" x 4" (2x4x3.28)/12 2.20
Stakes 2" x 4" (2x4x1.50)/12(3.28/1.60) 2.20
Key 2" x 2" (2x2x3.28)/12 1.10
Nails 3-1/2"C : (10/100) 0.10
Formoil : (1/24)(0.102) 0.005
L: Forms for above :
Installation : 2C/40 lm/day 0.40
Stripping : 1C/45lm/day 0.18
e) Slabs on fill : 6" Thick slabs (per lm)
M: Sides 2" x 6" (2x6x3.28)/12 3.30
Stakes 2" x 4" (2x4x1.50)/12(3.28/1.50) 2.20
Key 2" x 2" (2x2x3.28)/12 1.10
Nails 3-1/2"C : (10/100) 0.10
Formoil : (1/24)(0.152) 0.007
L: Forms for above :
Installation : 2C/40 lm/day 0.40
Stripping : 1C/45lm/day 0.18
f) Columns (Per sm)
M: Consider 12" x 12" x 9'
Eff.A = (1 x 9)x 4 = 36 sf 3.35
Plywood 1/2" : 2.97 sm/sht 0.34
Framings 2" x 4" : (2x4x100)/12x1/3.35 20.00
Nails 4"C : (128/65)(1/3.35) 0.60
1"C : (212/1800)(1/3.35) 0.035
Formoil : 1 Gal/24 sm 0.045
Braces 2" x 6" : (2x6x100)/12x1/3.35 36.00
L: Forms for above :
Fabrication : 2C / 3.35 sm/5 hrs 3.00
Installation : 2C,1H/3.35 sm/3 hrs 2.70
Stripping : 2H/3.35 sm/2 hrs 1.20
g) Suspended slab including beams and girders (Per sm)
M: Consider 10' x 20' slab with 12" x 18" Beams
Eff.A = (10 x 20)+(18+38)1.17 = 254 sf 23.70
Plywood 1/2" : 2.97 sm/sht 0.34
Joist : 2" x 6" @ 10"
(2x6x10)/12(24)(1/23.70) 10.13
Frames : 2" x 4"
(2x8x20)/12(4)(1/23.70) 2.40
Beams : 2-2" x 8"
(2x8x20)/12(4)(1/23.70) 4.50
Braces : 2" x 6"
(2x6x18)/12(8)(1/23.70) 6.10
5" x 5"
(5x5x10)/12(8)(1/23.70) 7.00
Nails 4"C : (416/65)(1/23.70) 0.27
1-1/2"C : (750/650)(1/23.70) 0.050
Formoil : 1 Gal/24 sm 0.045

L: Forms for above :


Fabrication : 2C / 7.77 sm/10 hrs 2.70
Installation : Joist and Frames 2.70
2C,2H/5.95 sm/4 hrs
Stripping : 2H/5.95 sm/3 hrs 1.00
6.40
h) Beams and Girders (Per sm)
M: Consider 12" x 18" x 19' Beam
Eff.A = (1+1.17+1.17)(19) = 64 sf 5.95
Plywood 1/2" : 2.97 sm/sht 0.34
Frames : 2" x 4"
(2x4x175)/12(1/5.95) 19.60
Braces : 2" x 6"
(2x6x64)/12(4)(1/5.95) 43.00
Nails 4"C : (368/65)(1/5.95) 0.27
1-1/2"C : (180/650)(1/5.95) 0.050
Formoil : 1 Gal/24 sm 0.045

L: Forms for above :


Fabrication : 2C / 5.95 sm/8 hrs 2.70
Installation : Joist and Frames 2.70
2C,2H/5.95 sm/4 hrs
Stripping : 2H/5.95 sm/3 hrs 1.00
6.40
i) Suspended (Per sm)
M: Consider 9' x 19' = 17.10 sf
Eff.A = 17.10 sf 16.00
Plywood 1/2" : 2.97 sm/sht 0.34
Joist : 2" x 6" @ 10"
(2x6x10)/12(24)(1/16) 15.00
Beams : 2" x 8"
(2x8x20)/12(4)(1/16) 6.70
Braces : 2" x 6"
(2x6x100)/12(1/16) 6.30
5" x 5"
(5x5x10)/12(1/16) 5.20
Nails 4"C : (144/65)(1/16) 0.14
1-1/2"C : (560/650)(1/16) 0.055
Formoil : 1 Gal/24 sm 0.045
L: Forms for above :
Fabrication : 2C,2H/16 sm/12 hrs 3.00
Stripping : 2H/16 sm/6 hrs 0.75
3.75

D. MASONRY BLOCK WORKS


a. Concrete Hollow Blocks : 4" CHB Wall (per sm)
M : 4" CHB , Non-load bearing 12.50
Mortar T3: 0.0266 cm/sm
Cement : 0.0266(13) 0.35
Sand : 0.0266 (1.05) 0.028
Reinforcement :
a.1) #3 @ 0.80V, #3 @ 0.60H 1.64
a.2) #3 @ 0.60V, #3 @ 0.60H 1.85
Tie Wires ###
L : Installation : 1M,2H/14 sm/day 1.72
7.26
b. Concrete Hollow Blocks : 6" CHB Wall (per sm)
M : 6" CHB , Non-load bearing 12.50
6" CHB , Load bearing 12.50
Mortar T3: 0.0624 cm/sm
Cement : 0.0624(13) 0.82
Sand : 0.0624 (1.05) 0.066
Reinforcement :
a.1) #3 @ 0.80V, #3 @ 0.60H 1.64
a.2) #4 @ 0.80V, #4 @ 0.60H 2.90
a.3) #4 @ 0.60V, #4 @ 0.60H 3.32
Tie Wires ###
L : Installation : 1M,2H/12 sm/day 2.00
6.25
c. Concrete Hollow Blocks : 8" CHB Wall (per sm)
M : 8" CHB , Non-load bearing 12.50
8" CHB , Load bearing 12.50
Mortar T3: 0.0984 cm/sm
Cement : 0.0984(13) 1.29
Sand : 0.0984 (1.05) 0.105
Reinforcement :
a.1) #4 @ 0.80V, #4 @ 0.60H 2.90
a.2) #4 @ 0.60V, #4 @ 0.60H 3.32
Tie Wires ###
L : Installation : 1M,2H/10 sm/day 2.40
d. Concrete Hollow Blocks : 8" CHB Wall (per sm)
M : 8" CHB , Non-Load bearing 12.80
Mortar T3: 0.0108 cm/sm
Cement : 0.0108(13) 0.14
Sand : 0.0108 (1.05) ###
Reinforcement :
a.1) #2 @ every 2 blocks E.W. 0.97
Tie Wires ###
L : Installation : 1M,2H/8 sm/day 3.00

E. FLOOR FINISHES (MASONRY FLOOR FINISHES)


a. Plain Cement 0.17
M : Cement 1 bag/6 sm 0.25
L : Spread Cement : 1M/32 sm/day 0.50
Trowelling : 2M/32 sm/day
b. Plain cement plaster : 5/8" Thick Ave. (Per sm)
M : Topping T3 : 0.21
Cement : (0.016)(13) 0.017
Sand : (0.016)(1.05) 0.017
Finish Coat : (1 bag/6 sm 0.67
L : Topping Application : 2M/24 sm/day 0.77
Finishing : 2M/21 sm/day
c. Plain cement plaster with floor hardener, 3/4" thick ave. (per sm)
M : Mortar T2 :
Cement : (0.0191)(17.50) 0.34
Sand : (0.0191)(0.93) 0.018
Hardener : Light duty 30 lbs/9.30 sm 3.23
Medium duty 60 lbs/9.30 sm 6.46
Heavy duty 100 lbs/9.30 sm 10.75
L : Mixing, Topping Application :
2M/21 sm/day 0.77
Finishing : 2M/21 sm/day 0.77

MATERIAL % WASTAGE CONVERSION

PAINTING
A. Metal
Enamel 10 0.2 gal / 100 sf
Zinc White 10 0.2 gal / 100 sf
White Lead 10 0.2 gal / 100 sf
B. Wood
Enamel 10 0.2 gal / 100 sf
Zinc White 10 0.2 gal / 100 sf
White Lead 10 0.2 gal / 100 sf
Varnish 10 0.2 gal / 100 sf
Flat 10 0.2 gal / 100 sf
Gloss 10 0.2 gal / 100 sf
C. Brick, Concrete, Plaster
Enamel 10 0.2 gal / 100 sf
Zinc White 10 0.2 gal / 100 sf
Varnish 10 0.2 gal / 100 sf
Flat 10 0.2 gal / 100 sf
Gloss 10 0.3 gal / 100 sf
Size 10 0.4 gal / 100 sf
Primer 10 0.3 gal / 100 sf
Calcimine 10 0.4 gal / 100 sf

CONCRETE WORKS (Concrete Mixes Only ) ( Per sm)

1. Lean Concrete, Class D : 1:3-1/2:7 Mix


M: C: 4.75 bags
SI : 15.90 cf 0.45 cum
GI : 32.10 cf 0.91 cum
2. 1600 PSI, Class C : 1:3:6, Mix
M: C: 5.50 bags
SI : 15.50 cf 0.44 cum
GI : 32.40 cf 0.89 cum
3. 2000 PSI, Class B : 1:2-1/2:5, Mix
M: C: 6.50 bags
SI : 15.50 cf 0.44 cum
GI : 30.70 cf 0.87 cum
4. 2500 PSI, Class A : 1:2:4, Mix
M: C: 7.50 bags
SI : 14.80 cf 0.42 cum
GI : 30.00 cf 0.85 cum
5. 2500 PSI, Class A : 3/4
M: C: 8.40 bags
SI : 19.40 cf 0.55 cum
GI : 23.70 cf 0.67 cum

6. 3000 PSI, Class AA : 1:1-1/2:3, Mix


M: C: 8.50 bags
SI : 14.80 cf 0.42 cum
GI : 29.30 cf 0.83 cum
7. 3000 PSI, Class AA : 3/4
M: C: 9.50 bags
SI : 19.10 cf 0.54 cum
GI : 23.30 cf 0.66 cum
8. 3000 PSI, Special : 1:2:3: Mix
M: C: 9.00 bags
SI : 19.40 cf 0.55 cum
GI : 23.70 cf 0.67 cum
9. 3500 PSI, Special :
M: C: 9.50 bags
SI : 14.80 cf 0.42 cum
GI : 28.80 cf 0.81 cum
10. 3500 PSI, Special : 3/4
M: C: 10.50 bags
SI : 19.40 cf 0.55 cum
GI : 20.90 cf 0.65 cum
11. 4000 PSI
M: C: 10.75 bags
SI : 14.80 cf 0.42 cum
GI : 27.60 cf 0.78 cum

12. 4500 PSI


M: C: 12.00 bags
SI : 14.80 cf 0.42 cum
GI : 26.50 cf 0.75 cum
13. 5000 PSI
M: C: 13.00 bags
SI : 14.50 cf 0.41 cum
GI : 25.40 cf 0.72 cum
14. Additives / Admixtures
Early Strength
Pozzolith (HE) 10L 0.47 lb/bag cement
15. Retarders
Pozzolith 8 0.235 lb/bag cement

CONCRETE WORKS (Concrete Materials Only)


Per BPW Specifications

1. Class AAA : 1:1:2 Mix (3500 PSI)


M : Cement : 13.30 bags/cum
Sand SI : 0.40 cum/cum
Gravel GI : 0.80 cum/cum
2. Class AAA : 1:1-1/2:3 Mix (3000 PSI)
M : Cement : 10.50 bags/cum
Sand SI : 0.42 cum/cum
Gravel GI : 0.84 cum/cum
3. Class A : 1:2:4 Mix (2500 PSI)
M : Cement : 7.85 bags/cum
Sand SI : 0.42 cum/cum
Gravel GI : 0.84 cum/cum
4. Class B : 1:2-1/2:5 Mix (2000 PSI)
M : Cement : 6.50 bags/cum
Sand SI : 0.44 cum/cum
Gravel GI : 0.87 cum/cum
5. Class C : 1:3:6 Mix (1600 PSI)
M : Cement : 5.50 bags/cum
Sand SI : 0.44 cum/cum
Gravel GI : 0.89 cum/cum
6. Class D : 1:3-1/2:7 Mix (Lean Concrete)
M : Cement : 4.81 bags/cum
Sand SI : 0.45 cum/cum
Gravel GI : 0.91 cum/cum
7. Special Mix : 1:2:3 Mix
M : Cement : 9.47 bags/cum
Sand SI : 0.51 cum/cum
Gravel GI : 0.76 cum/cum

8. Mortar Mixes - Materials Only


Per BPW Specifications

a. Type 1 - 1:1 (Plaster Retouch)


M : Cement : 24.20 bags/cum
Sand SI : 0.65 cum/cum
b. Type 2 - 1:2 (Plaster, Retouch, Scratchcoat)
M : Cement : 17.40 bags/cum
Sand SI : 0.93 cum/cum
c. Type 3 - 1:3 (CHB Filler, Topping, Scratchcoat)
M : Cement : 13.00 bags/cum
Sand SI : 1.05 cum/cum

9. Lean Concrete Class D : 1 : 3-1/2 : 7


M : Cement : 4.75 bags/cum
Sand SI : 0.45 cum/cum
Gravel GI : 0.91 cum/cum

10. 1600 PSI, Class C : 1 : 3 : 6


M : Cement : 5.50 bags/cum
Sand SI : 0.44 cum/cum
Gravel GI : 0.89 cum/cum

11. 2000 PSI, Class B : 1 : 2-1/2 : 5


M : Cement : 6.50 bags/cum
Sand SI : 0.44 cum/cum
Gravel GI : 0.87 cum/cum

12. 2500 PSI, Class A : 1 : 2 : 4


M : Cement : 7.50 bags/cum
Sand SI : 0.42 cum/cum
Gravel GI : 0.85 cum/cum
13. 2500 PSI, Class A : 3/4
M : Cement : 8.40 bags/cum
Sand SI : 0.55 cum/cum
Gravel GI : 0.67 cum/cum

14. 3000 PSI, Class AA : 1 : 1 : 1-1/2 : 3


M : Cement : 8.50 bags/cum
Sand SI : 0.42 cum/cum
Gravel GI : 0.83 cum/cum

15. 3000 PSI, Class AA : 3/4


M : Cement : 9.50 bags/cum
Sand SI : 0.54 cum/cum
Gravel GI : 0.66 cum/cum

16. 3000 PSI, Special : 1 : 2 : 3


M : Cement : 9.00 bags/cum
Sand SI : 0.55 cum/cum
Gravel GI : 0.67 cum/cum

17. 3500 PSI, Special


M : Cement : 9.50 bags/cum
Sand SI : 0.42 cum/cum
Gravel GI : 0.81 cum/cum

18. 3500 PSI, Special : 3/4


M : Cement : 10.50 bags/cum
Sand SI : 0.55 cum/cum
Gravel GI : 0.65 cum/cum

19. 4000 PSI


M : Cement : 10.75 bags/cum
Sand SI : 0.42 cum/cum
Gravel GI : 0.78 cum/cum

20. 4500 PSI


M : Cement : 12.00 bags/cum
Sand SI : 0.42 cum/cum
Gravel GI : 0.75 cum/cum

21. 5000 PSI


M : Cement : 13.00 bags/cum
Sand SI : 0.42 cum/cum
Gravel GI : 0.72 cum/cum
to jobsite

o owner of

ation during

unsuitable

ng area and
onry blocks,
35cm. (14inch)
bd.ft/sm

floor area

should be

% Wastage
(sm/gal.)

18 sm/lb

12 sm/lb

12 sm/lb
Capacity
(sm/ gal)
-1/2 kg/sm

g of cement

m (2 coats)

g of cement
of cement
bag of cement
g of cement

% Wastage
% Wastage
that sliding

Total Area in %
t 10 board

Area (sm)
ain G.I. roll
G flooring

d for H & V studs


nails and bolts

kg/sht plus
and cont.
k/sheet 6' long

of roof area

mate No./kg.

ate No./kg.
Net Factor per /

Considering 88
lbs/bags of
cement

bags
cum
cum

bags
cum
cum

bags
cum
cum

bags
cum
cum

bags
cum
cum

bags
cum
cum

bags
cum
cum

bags
cum

bags
cum

bags
cum

bags
cum
bags
cum

bags
cum

bags
cum

bags
cum

bags
cum

bags
cum
pcs

kg
kg
roll

MH
bags
cum
pcs

kg
kg
kg
kg
roll

MH

bags
cum
pcs

kg
kg
roll

MH

bags
cum

kg

MH

bag

MH
MH

bag
cum
cum

MH
MH

bag
cum

lbs
lbs
lbs

MH
MH

bag
cum

bag
pail
lbs

MH
MH

bag
cum

sf
pcs
pcs
pcs
pcs

gal

bag
cum
bag
MH
MH

bag
cum

gal

pcs
pcs
pcs

MH
MH

bag
cum

pcs
pcs
pcs
pcs

MH
MH

bf
kg

bf
kg

mh

bf
kg
gal
sf

gal
mh

bag
cum
gal
sf

mh
mh

bag
cum

mh

bag
cum

mh
mh

bag
cum

mh
mh
bag
cum

sf
pcs
pcs
pcs
pcs
pcs

gal

bag
cum
bag

mh
mh
mh

Net factor / sm

bag
cum

mh
mh

mh
mh

bag
cum
mh

bag
cum
gal
bag

mh
mh

bag
cum
gal
pail

mh
mh

bag
cum
cum
DT

mh
mh

bag
cum

pcs
pcs
sm
sm.
bag
mh
mh
mh
m-d

bf
bf

kg
kg

sht
sht
sht

mh
mh

bf
bf

kg
kg
sht

mh
mh

bf
bf
bf

kg

mh
bf

kg

mh

bf
bf

kg
kg

kg

mh
mh

bf
bf
sf
gal

mh
mh

suspension

sf
roll

lf
lf

mh
mh
bf

kg

mh

bf
bf

bf

kg

mh
mh

bags
cm

bags
cm

bags
cm

bags
cm

bags
cm

bags
cm

gal
lb

blocks
blocks
blocks

cum
cum
cum

kg
kg
kg
kg

lf
lf

sm
sht/sm
bf/sm
kg/sm
kg/sm
gal/sm
bf/sm

mh/sm
mh/sm
mh/sm

sm
sht/sm
bf/sm
kg/sm
kg/sm
gal/sm
bf/sm

mh/sm
mh/sm
mh/sm

sm
sht/sm
bf/sm
kg/sm
kg/sm
gal/sm
bf/sm

mh/sm
mh/sm
mh/sm

bf/lm
bf/lm
bf/lm
kg/lm
gal/sm

mh/lm
mh/lm

bf/lm
bf/lm
bf/lm
kg/lm
gal/sm

mh/lm
mh/lm

sm
sht/sm
bf/sm
kg/sm
kg/sm
gal/sm
bf/sm
mh/sm
mh/sm
mh/sm

sm
sht/sm

bf/lm

bf/lm

bf/lm

bf/lm

bf/lm
kg/sm
kg/sm
gal/sm

mh/sm
mh/sm

mh/sm
mh/sm

sm
sht/sm

bf/lm

bf/lm
kg/sm
kg/sm
gal/sm

mh/sm
mh/sm

mh/sm
mh/sm

sm
sht/sm
bf/lm

bf/lm

bf/lm

bf/lm
kg/sm
kg/sm
gal/sm

mh/sm
mh/sm
mh/sm

CHB/sm

bag/sm
cm/sm

kg/sm
kg/sm
roll/sm
mh/sm
pcs/mh

CHB/sm
CHB/sm

bag/sm
cm/sm

kg/sm
kg/sm

roll/sm
mh/sm
pcs/mh

CHB/sm
CHB/sm

bag/sm
cm/sm

kg/sm
kg/sm
roll/sm
mh/sm

CHB/sm

bag/sm
cm/sm

kg/sm
roll/sm
mh/sm

bag/sm
mh/sm
mh/sm

bag/sm
cm/sm
bag/sm
mh/sm
mh/sm

bag/sm
cm/sm
lbs/sm
lbs/sm
lbs/sm

mh/sm
mh/sm

CONVERSION

0.2 gal / 100 sf


0.2 gal / 100 sf
0.2 gal / 100 sf
0.2 gal / 100 sf
0.2 gal / 100 sf
0.2 gal / 100 sf
0.2 gal / 100 sf
0.2 gal / 100 sf
0.2 gal / 100 sf

0.2 gal / 100 sf


0.2 gal / 100 sf
0.2 gal / 100 sf
0.2 gal / 100 sf
0.3 gal / 100 sf
0.4 gal / 100 sf
0.3 gal / 100 sf
0.4 gal / 100 sf
UPDATED CSI MASTER FORMAT
DIV. 01 GENERAL REQUIREMENTS
01100 SUMMARY
110 Summary of Work
120 Multiple Contract Summary
140 Work Restrictions
180 Project Utility Sources
01200 PRICE AND PAYMENT PROCEDURES
210 Allowances
230 Alternates
240 Value Analysis
250 Contract Modification Procedures
270 Unit Prices
290 Payment Procedures
01300 ADMINISTRATIVE REQUIREMENTS
310 Project Management and Coordination
320 Construction Progress Documentation
330 Submittal Procedures
350 Special Procedures
01400 QUALITY REQUIREMENTS
410 Regulatory Requirements
420 References
430 Quality Assurance
450 Quality Control
01500 TEMPORARY FACILITIES AND CONTROLS
510 Temporary Utilities
520 Construction Facilities
530 Temporary Construction
540 Construction Aids
550 Vehicular Access and Parking
560 Temporary Barriers and Enclosures
570 Temporary Controls
580 Project Identification
01600 PRODUCT REQUIREMENTS
610 Basic Product Requirements
620 Product Options
630 Product Substitution Procedures
640 Owner-Furnished Products
650 product Delivery Requirements
660 Product Storage and Handling Requirements
01700 EXECUTION REQUIREMENTS
710 Examination
720 Preparation
730 Execution
740 Cleaning
750 Starting and Adjusting
760 Protecting Installed Construction
770 Closeout Procedures
780 Closeout Submittals
01800 FACILITY OPERATION
810 Commissioning
820 Demonstration and Training
830 Operation and Maintenance
890 Reconstruction

01900 FACILITY DECOMMISSIONING


Decommissioning Systems and Equipment
Facility Demolition and Removal
Hazardous Materials Abatement
Hazardous Materials Removal and Disposal
Protection of Deactivated Facilites
DIV. 02 SITE CONSTRUCTION
020500 BASIC SITE MATERIALS AND METHODS
055 Soils
060 Aggregate
065 Cement and Concrete
070 Geosynhetics
080 Utility Materials
090 Joint Material
02100 SITE REMEDIATION
105 Chemical Sampling and Analysis
110 Excavation, Removal, and Handling of Hazardous Materials
115 Underground Storage Tank Removal
129 Off-Site Transportation and Disposal
125 Drum Handling
130 Site Decontamination
140 Landfill Construction and Storage
145 Groundwater Treatment Systems
150 Hazardous Waste Recovery Processes
160 Physical Treatment
170 Chemical Treatment
180 Thermal Processes
190 Biological Processes
195 Remudiation Soil Stabilization
02200 SITE PREPARATION
210 Subsurface Investigation
220 Site Demolition
230 Site clearing
240 Dewatering
250 Shoring and Underpinning
260 Excavation Support and Protection
280 Grade Adjustment and Abandonment of Existing Misc. Structures
285 Rebuilt Miscellaneous Structures
290 Site Monitoring
02300 EARTHWORK
310 Grading
315 Excavation and Fill
325 Dredging
330 Embankment
335 Subgrade and Roadbed
340 Soil Stabilization
360 Soil Treatment
370 Erosion and Sedimentation Control
380 Scour Protection
390 Shoreline Protection and Mooring Structures
02400 TUNNELING, BORING AND JACKING
410 Tunnel Excavation
420 Initial Tunnel Support Systems
425 Tunnel Linings
430 Tunnel Grouting
440 Immersed and Sunken Tube Tunnels
441 Microtunneling

442 Cut and Cover Tunnels


443 Tunnel Leak Repairs
444 Shaft Construction
445 Boring or Jacking Conduits
02450 FOUNDATION AND LOAD-BEARING ELEMENTS
455 Driven Piles
465 Bored Piles
475 Caissons
480 Foundation Walls
490 Anchors
495 Instrumentation and Monitoring
02500 UTILITY SERVICES
510 Water Distribution
520 Wells
530 Sanitary Sewerage
540 Septic Tank Systems
550 Piped Energy Distribution
570 Process Materials Distribution Structures
580 Electrical and Communication Structures
590 Site Grounding
02600 DRAINAGE AND CONTAINMENT
610 Pipe Culverts
620 Subdrainage
630 Storm Drainage
640 Culverts and Manufactured Construction
660 Ponds and Reservoirs
670 Constructed Wetlands
02700 BASES, BALLASTS, PAVEMENT & APPUR.
710 Bound Base Courses
720 Unbound Base Courses and Ballasts
730 Aggregate Surfacing
740 Flexible Pavement
750 Rigid Pavement
755 Cement Concrete Shoulders
760 Paving Specialties
770 Curbs and Gutters
775 Sidewalks
780 Unit Pavers
785 Flexible Pavement Coating and Micro-Surfacing
790 Athletic and Recreational Surfaces
795 Porous Pavement
02800 SITE IMPROVEMENTS AND AMENITIES
810 Irrigation System
815 Fountains
820 Fences and Gates
830 Retaining Walls
840 Walk, Road, and parking Appurtenances
850 Prefaricated Bridges
860 Screening Devices
870 Site Furnishings
875 Site and Street Shelters
880 Play Field Equipment and Structures
890 Traffic Signs and Signals
895 Markers and Monuments
02900 PLANTING
905 Transplanting
910 Plant Preparation

920 Lawns and Grasses


930 Exterior Plants
935 Plant Maintenance
945 Planting Accessories
02950 SITE RESTORATION AND REHABILITATION
955 Restoration of Underground Piping
960 Flexible Pavement Surfacing Recovery
965 Flexible and Bituminous Pavement Recycling
975 Flexible and Bituminous Pavement Reinforcement and Crack & Seal.
980 Rigid Pavement Rehabilitation
990 Structure Moving
DIV. 03 CONCRETE
03050 BASIC CONCRETE MATERIALS AND METHODS
03100 CONCRETE FORMS AND ACCESSORIES
110 Structural Cast-in-Place Forms
120 Architectural Cast-in Place Forms
130 Permanent Forms
150 Concrete Accessories
03200 CONCRETE REINFORCEMENT
210 Reinforcing Steel
220 Welded Wire Fabric
230 Stressing Tendons
240 Fibrous Reinforcing
250 Post Tensioning
03300 CAST-IN PLACE CONCRETE
310 Structural Concrete
330 Architectural Concrete
340 Low Density Concrete
350 Concrete Finishing
360 Concrete Finishes
370 Speciallly Placed Concrete
380 Post Tensioned Concrete
390 Concrete Curing
03400 PRECAST CONCRETE
410 Plant Precast Structural Concrete
420 Plant Precast Structural Concrete
430 Site Precast Structural Concrete
450 Plant Precast Architectural Concrete
460 Site Precast Architectural Concrete
470 Tilt Up Precast Concrete
480 Precast Concrete Specialties
490 Glass Fiber Reinforced Precast Concrete
03500 CEMENTITIOUS DECKS AND UNDERLAYMENT
510 Cementitious Roof Deck
520 Lightweight Concrete Roof Insulation
530 Conrete Topping
540 Cementitious Underlayment
03600 GROUTS
03700 MASS CONCRETE
03900 CONCRETE RESTORATION AND CLEANING
910 Concrete Cleaning
920 Concrete Resurfacing
930 Concrete Rehabilitation
DIV. 04 MASONRY
04050 BASIC MASONRY MATERIALS AND METHOD
060 Masonry Mortar
070 Masonry Grout

080 Masonry Anchorage and Reinforcement


090 Masonry Accessories
04200 MASONRY UNITS
210 Clay Masonry Units
220 Concrete Masonry Units
230 Calcium Silicate Masonry Units
270 Glass Masonry Units
290 Adobe Masonry Units
04400 STONE
410 Stone Materials
420 Collected Stone
430 Quarried Stone
04500 REFRACTORIES
550 Flue Liners
560 Combustion Chambers
570 Castable Refractories
580 Refractory Brick
04600 CORROSION-RESISTANT MASONRY
610 Chemical Resistant Brick
620 Vitrified Clay Liner Plates
04700 SIMULATED MASONRY
710 Simulated Brick
720 Cast Stone
730 Simulated Stone
04800 MASONRY ASSEMBLIES
810 Unit Masonry Assemblies
820 Reinforced Unit Masonry Assemblies
830 Non Reinforced Unit Masonry Assemblies
840 Prefabricated Unit Masonry Asemblies
850 Stone Assemblies
880 Masonry Fireplaces
04900 MASONRY RESTORATION AND CLEANING
910 Unit Masonry Restoration
920 Stone Restoration
930 Unit Masonry Cleaning
940 Stone Cleaning
DIV. 05 METALS
05050 BASIC METAL MATERIALS AND METHODS
060 Metal Materials
080 Factory Applied Metal Coatings
090 Metal Fastenings
05100 STRUCTURAL METAL FRAMING
120 Structural Steel
140 Structural Aluminum
150 Wire Rope Assemblies
160 Metal Framing Systems
05200 METAL JOISTS
210 Steel Joists
250 Aluminum Joists
260 Composite Joist Assemblies
05300 METAL DECKS
310 Steel Deck
320 Raceway Deck Systems
330 Aluminum Deck
340 Acoustical Metal Deck

05400 COLD-FORMED METAL FRAMING


410 Load Bearing Metal Studs
420 Cold Formed Metal Joists
430 Slotted Channel Framing
450 Metal Support
05500 METAL FABRICATIONS
510 Metal Stairs and Ladders
520 Handrails and Railings
530 Gratings
540 Floor Plates
550 Stair Treads and Nosings
560 Metal Castings
580 Formed metal Fabrications
05600 HYDRAULIC FABRICATIONS
05650 RAILROAD TRACK AND ACCESSORIES
05700 ORNAMENTAL METAL
710 Ornamental Stairs
715 Fabricated Spiral Stairs
720 Ornamental Handrails and Railings
725 Ornamental Metal Castings
730 Ornamental Formed Metal
740 Ornamental Forged Metal
05800 EXPANSION CONTROL
810 Expansion Joint Cover Assemblies
820 Slide Bearings
830 Bridge Expansion Joint Assemblies
05900 METAL RESTORATION AND CLEANING
DIV. 06 WOOD AND PLASTICS
06050 BASIC WOOD AND PLASTIC MATERIALS
060 Wood Materials
065 Plastic Materials
070 Wood Treatment
080 Factory Applied Wood Coatings
090 Wood and Plastic Fastenings
06100 ROUGH CARPENTRY
110 Wood Framing
120 Structural Panels
130 Heavy Timber Construction
140 Treated Wood Foundations
150 Wood Decking
160 Sheating
170 Prefabricated Structural Wood
180 Glued Laminated Construction
06200 FINISH CARPENTRY
220 Millwork
250 Prefinished Paneling
260 Board Paneling
270 Closet and Utility Wood Shelving
06400 ARCHITECTURAL WOODWORK
410 Custom Cabinets
415 Countertops
420 Paneling
430 Wood Stairs and Railings
440 Wood Ornaments
445 Simulated Wood Ornaments
450 Standing and Running Trim

455 Simulated Wood Trim


460 Wood Frames
470 Screens, Blinds, and Shutters
06500 STRUCTURAL PLASTICS
510 Structural Plastic Shapes and Plates
520 Plastic Structural Assemblies
06600 PLASTIC FABRICATIONS
06900 WOOD AND PLASTIC RESTORATION & CLEANING
910 Wood Restoration and Cleaning
920 Plastic Restoration and Cleaning
DIV. 07 THERMAL AND MOISTURE PROTECTION
07050 BASIC THERMAL AND MOISTURE PROTECTION
07100 DAMPROOFING AND WATERPROOFING
110 Dampproofing
120 Built-Up Bituminous Waterproofing
130 Sheet Waterproofing
140 Fluid Applied Waterproofing
150 Sheet Metal Waterproofing
160 Cementitious and Reactive Waterproofing
170 Bentonite Waterproofing
180 Traffic Coatings
190 Water Repellents
07200 THERMAL PROTECTION
210 Building Insulation
220 Roof and Deck Insulation
240 Exterior Insulation and Finish Systems (EIFS)
260 Vapor Retarders
270 Air Barriers
07300 SHINGLES, ROOF TILES AND ROOF COVERINGS
310 Shingles
320 Roof Tiles
330 Roof Coverings
07400 ROOFING AND SIDING PANELS
410 Metal Roof and Wall Panels
420 Plastic Roof and Wall Panels
430 Composite Panels
440 Faced Panels
450 Fiber Reinforced Cementitious Panels
460 Siding
470 Wood Rood and Wall Panels
480 Exterior Wall Assemblies
07500 MEMBRANE ROOFING
510 Buil-Up Bituminous Roofing
520 Cold Applied Bituminous Roofing
530 Elastomeric Membrane Roofing
540 Thermoplastic Memebrane Roofing
550 Modified Bituminous Membrane Roofing
560 Fluid Applied Roofing
570 Coated Foamed Roofing
580 Roll Roofing
590 Roof Maintenance and Repairs
07600 FLASHING AND SHEET METAL
610 Sheet Metal Roofing
620 Sheet Metal Flashing and Trim
630 Sheet Metal Roofing Specialties
650 Flexible Flashing

07700 ROOF SPECIALTIES AND ACCESSORIES


710 Manufactured Roof Specialties
720 Roof Accessories
760 Roof Pavers
07800 FIRE AND SMOKE PROTECTION
810 Applied Fireproofing
820 Board Fireproofing
840 Firestopping
860 Smoke Seals
870 Smoke Containment Barriers
07900 JOINT SEALERS
910 Preformed Joint Seals
920 Joint Sealants
DIV. 08 DOORS AND WINDOWS
08050 BASIC DOOR AND WINDOW MATERIALS
08100 METAL DOORS AND FRAMES
110 Steel Doors and Frames
120 Aluminum Doors and Frames
130 Stainless Steel Doors and Frames
140 Bronze Doors and Frames
150 Preassembled Metal Door and Frame Units
160 Sliding Metal Doors and Grilles
180 Metal Screen and Storm Doors
190 Metal Door Restoration
08200 WOOD AND PLASTIC DOORS
210 Wood Doors
220 Plastic Doors
250 Preassembled Wood and Plastic Door and Frame Units
260 Sliding Wood and Plastic Doors
280 Wood and Plastic Storm and Screen Doors
290 Wood and Plastic Door Restoration
08300 SPECIALTY DOORS
310 Access Doors and Panels
320 Detention Doors and Frames
330 Coiling Doors and Grilles
340 Special Function Doors
350 Folding Doors and Grilles
360 Overhead Doors
370 Vertical Lift Doors
380 Traffic Doors
390 Pressure Resistant Doors
08400 ENTRANCES AND STOREFRONTS
410 Metal Frames Storefronts
450 All Glass Entrances and Storefronts
460 Automatic Entrance Doors
470 Revolving Entrance Doors
480 Balanced Entrance Doors
490 Sliding Storefronts
08500 WINDOWS
510 Steel Windows
520 Aluminum Windows
530 Stainless Steel Windows
540 Bronze Windows
550 Wood Windows
560 Plastic Windows
570 Composite Windows
580 Special Function Windows
590 Window Restoration and Replacement

08600 SKYLIGHTS
610 Roof Windows
620 Unit Skylights
630 Metal Framed Skylights
08700 HARDWARE
710 Door Hardware
720 Weatherstripping and Seals
740 Electro Mechanical Hardware
750 Window Hardware
770 Door and Window Accessories
780 Special Function Hardware
790 Hardware Restoration
08800 GLAZING
810 Glass
830 Mirrors
840 Plastic Glazing
850 Glazing Accessories
890 Glazing Restoration
0890 GLAZED AND CURTAIN WALL
910 Metal Framed Curtain Wall
950 Translucent Wall and Roof Assemblies
960 Sloped Glazing Assemblies
970 Structural Glass Curtain Walls
990 Glazed Curtain Wall Restoration
DIV. 09 FINISHES
09050 BASIC FINISH MATERIALS AND METHODS
09100 METAL SUPPORT ASSEMBLIES
110 Non Load Bearing Wall Framing
120 Ceiling Suspension
130 Acoustical Suspension
190 Metal Frame Restoration
09200 PLASTER AND GYPSUM BOARD
205 Furring and Lathing
210 Gypsum Plaster
220 Portland Cement Plaster
230 Plaster Fabircations
250 Gypsum Board
260 Gypsum Board Assemblies
270 Gypsum Board Accessories
280 Plaster Restoration
09300 TILE
305 Tile Setting Materials and Accessories
310 Ceramic Tile
330 Quarry Tile
340 Paver Tile
350 Glass Mosaics
360 Plastic Tile
370 Metal Tile
380 Cut Natural Stone Tile
390 Tile Restoration
09400 TERRAZZO
410 Portland Cement Terrazzo
420 Precast Terrazzo
430 Conductive Terrazzo
440 Plastic Matrix Terrazzo
490 Terrazzo Restoration

09500 CEILINGS
510 Acoustical Ceilings
545 Specialty Ceilings
550 Mirror Panel Ceilings
560 Textured Ceilings
570 Linear Wood Ceilings
580 Suspended Decorative Grids
590 Ceiling Assembly Restoration
09600 FLOORINGS
610 Floor Treatment
620 Specialty Flooring
630 Masonry Flooring
640 Wood Flooring
650 Resilient Flooring
660 Static control Flooring
670 Fluid Applied Flooring
680 Carpet
690 Flooring Restoration
09700 WALL FINISHES
710 Acoustical Wall Finishes
720 Wall Covering
730 Wall Carpet
740 Flexible Wood Sheets
750 Stone Facing
760 Plastic Blocks
770 Special Wall Surfaces
790 Wall Finish Restoration
09800 ACOUSTICAL TREATMENT
810 Acoustical Space Units
820 Acoustical Insulation and Sealants
830 Acoustical Barriers
840 Acoustical Wall Treatment
09900 PAINTS AND COATINGS
910 Paints
930 Stains and Transparent Finishes
940 Decorative Finishes
960 High Performance Coatings
970 Coatings for Steel
980 Coatings for Concrete and Masonry
990 Paint Restoration
DIV. 10 SPECIALTIES
10100 VISUAL DISPLAY BOARDS
110 Chalkboards
115 Markerboards
120 Tackboard and Visual Aid Boards
130 Operable Board Units
140 Display Track Assemblies
145 Visual Aid Board Units
10150 COMPARTMETNS AND CUBICLES
160 Metal Toilet Compartments
165 Plastic Laminate Toilet Compartments
170 Plastic Toilet Compartments
175 Plastic Toilet Compartments
180 Stone Toilet Compartments
185 Shower and Dressing Compartments
190 Cubicles

10200 LOUVERS AND VENTS


210 Wall Louvers
220 Louvered Equipment Enclosures
225 Door Louvers
230 Vents
10240 GRILLES AND SCREENS
10250 SERVICE WALLS
10260 WALL AND CORNER GUARDS
10270 ACCESS FLOORING
10290 PEST CONTROL
10300 FIREPLACES AND STOVES
310 Fireplace Specialties and Accessories
320 Stoves
330 Fireplace and Stove Restoration
10340 MANUFACTURED EXTERIOR SPECIALTIES
345 Exterior Specialties Restoration
10350 FLAGPOLES
10400 IDENTIFICATION DEVICES
410 Directories
420 Plaques
430 Exterior Signage
440 Interior Signage
10450 PEDESTRIAN CONTROL DEVICES
10500 LOCKERS
10520 FIRE PROTECTION SPECIALTIES
10530 PROTECTIVE COVERS
10550 POSTAL SPECIALTIES
10600 PARTITIONS
650 Wire Mesh Partitions
610 Folding Gates
615 Demountable Partitions
630 Portable Partitions, Screens and Panels
650 Opertable Partitions
10670 STORAGE SHELVINGS
10700 EXTERIOR PROTECTION
705 Exterior Sun Control Devices
710 Exterior Shutters
715 Storm Panels
720 Exterior Louvers
10750 TELEPHONE SPECIALTIES
10800 TOILET, BATH AND LAUNDRY ACCESSORIES
810 Toilet Accessories
820 Bath Accessories
830 Laundry Accessories
10880 SCALES
10900 WARDROBE AND CLOSET SPECIALTIES

DIV. 11 EQUIPMENT
11010 MAINTENANCE EQUIPMENT
Floor and Wall Cleaning Equipment
Housekeeping Carts
Vacuum Cleaning Systems
Window Washing Systems
11020 SECURITY AND VAULT EQUIPMENT
Safe Depoist Boxes
Sales
Vault Doors and Day Gates

11030 TELLER AND SERVICE EQUIPMENT


Automatic Banking Systems
Money Cart Pass Through
Package Transfer Units
Service and Teller Window Units
Teller Equipment Systems
11040 ECCLESIASTICAL EQUIPMENT
Baptiseries
Chancel Fittings
11050 LIBRARY EQUIPMENT
Automated Book Storage and Retrieval Systems
Book Depositors
Book Theft Protection Equipment
Library Stack Systems
11060 THEATER AND STAGE EQUIPMENT
Acoustical Shells
Folding and Portable Stages
Rigging Systems and Controls
Stage Curtains
11070 INSTRUMENTAL EQUIPMENT
Bells
Carillons
Organs
11080 REGISTRATION EQUIPMENT
11090 CHECKROOM EQUIPMENT
11100 MERCHANTILE EQUIPMENT
Barber and Beauty Shop Equipment
Cash Registers and Checking Equipment
Display Cases
Food Processing Equipment
Food Weighing and Wrapping Equipment
11110 COMMERCIAL LAUNDRY AND DRY CLEANING
Dry Cleaning Equipment
Drying and Conditioning Equipment
Finishing Equipment
Ironing Equipment
Washers and Extractors
11120 VENDING EQUIPMENT
Money Changing Machines
Vending Machines
11130 AUDIO-VISUAL EQUIPMENT
Learning Laboratories
Projection Screens
Projectors
11140 VEHICLE SERVICE EQUIPMENT
Compressed Air Equipment
Fuel Dispensing Equipment
Lubrication Equipment
Tire Changing Equipment
Vehicle Washing Equipment
11150 PARKING CONTROL EQUIPMENT
Coin Machine Units
Key and Card Control Units
Parking Gates
Ticket Dispensers

11160 LOADING DOCK EQUIPMENT


Dock Bumpers
Dock Levelers
Dock Lifts
Portable Ramps, Bridges and Platforms
Seals and Shelters
Truck Restraints
11170 SOLID WASTE HANDLING EQUIPMENT
Bins
Chutes and Collectors
Packaged Incinerators
Pneumatic Waste Equipment
Pulping Machines
Recycling Equipment
Waste Compactors and Destructors
11190 DETENTION EQUIPMENT
11200 WATER SUPPLY AND TREATMENT EQUIPMENT
210 Supply and Treatment Pumps
220 Mixers and Flocculators
225 Clarifiers
230 Water Aeration Equipment
240 Chemical Feed Equipment
250 Water Softening Equipment
260 Disinfectant Feed Equipment
270 Flouridation Equipment
11280 HYDRAULIC GATES AND VALVES
285 Hydraulic Gates
295 Hydraulic Valves
11300 FLUID WASTE TREATMENT AND DISPOSAL
310 Sewage and Sludge Pumps
320 Grit Collecting Equipment
330 Screening and Grinding Equipment
335 Sedimentation Tank Equipment
340 Scum Removal Equipment
345 Chemical Equipment
350 Sludge Handling and Treatment Equipment
360 Filter Press Equipment
365 Trickling Filter Equipment
370 Compressors
375 Aeration Equipment
380 Sludge Digestion Equipment
385 Digester Mixing Equipment
390 Package Sewage Treatment Plants
11400 FOOD SERVICE EQUIPMENT
450 Food Storage Equipment
410 Food Preparation Equipment
415 Food Delivery Carts and Conveyers
420 Food Cooking Equipment
425 Hood and Ventilation Equipment
430 Food Dispensing Equipment
435 Ice Machines
440 Cleaning and Disposal Equipment
11450 RESIDENTIAL EQUIPMENT
Residential Appliances
Residential Kitchen Equipment
Retractable Stairs

11460 UNIT KITCHENS


11470 DARKROOM EQUIPMENT
Darkroom Processing Equipment
Revolving Darkroom Doors
Transfer Cabinets
11480 ATHLETIC, RECREATIONAL AND THERAPEUTIC
Backstops
Bowling Aley Equipment
Exercise Equipment
Gymnasium Dividers
Gymnasium Equipment
Scoreboards
Shooting Range Equipment
Therapeutic Equipment
11500 INDUSTRIAL AND PROCESS EQUIPMENT
11600 LABORATORY EQUIPMENT
11650 PLANETARIUM EQUIPMENT
11660 OBSERVATORY EQUIPMENT
11680 OFFICE EQUIPMENT
11700 MEDICAL EQUIPMENT
710 Medical Sterilizing Equipment
720 Examination and Treatment Equipment
730 Patient Care Equipment
740 Dental Equipment
750 Optical Equipment
760 Operating Room Equipment
770 Radiology Equipment
11780 MOTTUARY EQUIPMENT
11850 NAVIGATION EQUIPMENT
11870 AGRICULTURAL EQUIPMENT
11900 EXHIBIT EQUIPMENT

DIV. 12 FURNISHING
12050 FABRICS
12100 ART
110 Murals
120 Wall Decorations
140 Sculptures
170 Art Glass
190 Ecclesiastical Art
12300 MANUFACTURED CASEWORK
310 Manufactured Metal Casework
320 Manufactured Wood Casework
350 Specialty Casework
12400 FURNISHING AND ACCESSORIES
410 Office Accessories
420 Table Accessories
430 Portable Lamps
440 Bath Furnishings
450 Bedroom Furnishings
460 Furnishing Accessories
480 Rugs and Mats
490 Window Treatments
12500 FURNITURE
510 Office Furnitures
520 Seating
540 Hospitality Furniture

560 Institutional Furniture


580 Residentila Furniture
12600 MULTIPLE SEATING
610 Fixed Audience Seating
620 Portable Audience Seating
630 Stadium and Arean Seating
640 Booths and Tables
650 Multiple-Use Fixed Seating
660 Telescoping Stands
670 Pew and Benches
680 Seat and Table Assemblies
12700 SYSTEMS FURNITURE
710 Panel-Hung Component System Furniture
720 Free-Standing Components System Furniture
730 Beam System Furniture
740 Desk System Furniture
12800 INTERIOR PLANTS AND PLANTERS
810 Interior Live Plants
820 Interior Artificial Plants
830 Interior Planters
840 Interior Landscape Accessories
850 Interior Plant Maintenance
12900 FURNISHING RESTORATION AND REPAIR
DIV. 13 SPECIAL CONSTRUCTION
13010 AIR-SUPPORTED STRUCTURES
13020 BUILDING MODULES
Prison Cells
Hotel and Dormitory Units
13030 SPECIAL PURPOSE ROOMS
Athletic Rooms
Clean Rooms
Cold Storage Rooms
Hyperbaric Rooms
Insulated Rooms
Office Shelters and Booths
Planetariums
Prefabricated Rooms
Saunas
Sound Conditioned Rooms
Steam Baths
Vaults
13080 SOUND, VIBRATION, AND SEISMIC CONTROL
13090 RADIATION PROTECTION
13100 LIGHTNING PROTECTION
13110 CATHODIC PROTECTION
13120 PRE-ENGINEERED STRUCTURES
Cable Supported Structures
Fabric Structures
Glazed Structures
Grandstands and Bleachers
Metal Building Systems
Modular Mezzanines
Observatories
Portable and Mobile Buildings
Pre-Engineered Buildings
Prefabricated Control Booths
Prefabricated Dome Structures

13150 SWIMMING POOLS


Below Grade Swimming Pools
Elevated Swimming Pools
On-Grade Swimming Pools
Recirculating Pool Accessories
Swimming Pool Cleaning Systems
13160 AQUARIUMS
13165 AQUATIC PARK FACILITIES
Water Slides
Wave Pools
13170 TUBS AND POOLS
Hot Tubs
Therapeutic Pools
Whirlpool Tubs
13175 ICE RINKS
13185 KENNELS AND ANIMAL SHELTERS
13190 SITE-CONSTRUCTED INCINERATORS
Sludge Incinerators
Solid Waste Incinerators
13200 STORAGE TANKS
Elevated Storage Tanks
Ground Storage Tanks
Tank Cleaning Procedures
Tank Lining
Underground Storage Tanks
13220 FILTER UNDERDRAINS AND MEDIA
Filter Bottoms
Filter Media
Package Filters
13230 DIGESTER COVERS AND APPURTENANCES
Fixed Covers
Floating Covers
Gasholder Covers
13240 OXYGENATION SYSTEMS
Oxygen Dissolution System
Oxygen Generators
Oxygen Storage Facility
13260 SLUDGE CONDITIONING SYSTEMS
13280 HAZARDOUS MATERIAL REMEDIATION
13400 MEASUREMENT AND CONTROL INSTRUMENTATION
410 Basic Measurement and Control Instrumentation
420 Instruments
430 Boxes, Panels, and Control Centers
440 Indicators, Recorders, and Controllers
450 Central Control
480 Instruments Lists and Reports
490 Measurement and Control Commissioning
13500 RECORDING INSTRUMENTATION
510 Stress Instrumentation
520 Seismic Instrumentation
530 Meteorological Instrumentation
13550 TRANSPORTATION CONTROL INSTRUMENTATION
560 Airport Control Instrumentation
570 Railroad Control Instrumentation
580 Subway Control Instrumentation
590 Transit Vehicle Control Instrumentation

13600 SOLAR AND WIND ENERGY EQUIPMENT


610 Solar Flat Plate Collector
620 Solar Concentrating Collectors
625 Solar Vacuum Tube Collectors
630 Solar Collector Components
640 Packaged Solar Equipment
650 Photovoltaic Collectors
660 Wind Energy Equipment
13700 SECURITY ACCESS AND SURVEILLANCE
Door Answering
Intrusion Detection
Security Access
Video Surveillance
13800 BUILDING AUTOMATION AND CONTROL
Clock Control
Door Control
Elevator Monitoring and Control
Energy Monitoring and Control
Environmental Control
Escalator and Moving Walks
Lighting Control
13850 DETECTION AND ALARM
Fire Alarm
Gas Detection
Leak Detection
Smoke Alarm
13900 FIRE SUPPRESSION
910 Basic Fire Suppresion Materials and Methods
920 Fire Pumps
930 Wet Pipe Fire Suppression Sprinklers
935 Dry Pipe Fire Suppression Sprinklers
940 Pre-Action Fire Suppression Sprinklers
945 Combination Dry-Pipe and Pre-Action Fire Suppression Sprinklers
950 Deluge Fire Suppression Sprinklers
955 Foam Fire Extinguishing
960 Carbon Dioxide Fire Extinguishing
965 Alternative Fire Extinguishing Systems
970 Dry Chemical Fire Extinguishing
975 Standpipes and Hoses

DIV. 14 CONVEYING SYSTEM


14100 DUMWAITERS
110 Manual Dumbwaiters
120 Electric Dumbwaiters
140 Hydraulic Dumpwaiters
14200 ELEVATORS
210 Electric Traction Elevators
240 Hydraulic Elevators
270 Custom Elevator Cabs
280 Elevator Equipment and Controls
290 Elevator Renovation
14300 ESCALATORS AND MOVING WALKS
14400 LIFTS
410 People Lifts
420 Wheelchair Lifts
430 Platform Lifts
440 Sdiewalk Lifts
450 Vehicle Lifts
14500 MATERIAL HANDLING
510 Material Transport
530 Postal Conveying
540 Baggage Conveying and Dispensing
550 Conveyors
560 Chutes
570 Feeder Equipment
580 Pneumatic Tube Systems
14600 HOIST AND CRANES
605 Crane Rails
610 Fixed Hoists
620 Troller Hoists
630 Bridge Cranes
640 Gantry Cranes
650 Jib Cranes
670 Tower Cranes
680 Mobile Cranes
690 Derricks
14700 TURNTABLES
14800 SCAFFOLDING
810 Suspended Scaffolding
820 Rope Climbers
830 Telscoping Platforms
840 Powered Scaffolding
1490 TRANSPORTATION
910 People Movers
920 Monorails
930 Funiculars
940 Aerial Tramways
950 Aircraft Pasenger Loading

DIV. 15A AIRCONDITIONING


15050 BASIC MECHANICAL MATERIALS & METHOD
060 Hangers and Supports
070 Mechanical Sound, Vibration, and Seismic Control
075 Mechanical Identification
080 Mechanical Insulation
090 Mechanical Restoration and Retrofit
15100 BUILDING SERVICES PIPING
105 Pipes and Tubes
110 Valves
120 Piping Specialties
130 Pumps
Water Treatment
140 Domestic Water Piping
150 Sanitary Waste and Vent Piping
160 Storm Drainage Piping
170 Swimming Pool and Fountain Piping
180 Heating and Cool Piping
190 Fuel Piping
15200 PROCESS PIPING
210 Process Air and Gas Piping
220 Process Water and Waste Piping
230 Industrial Process Piping
15500 HEAT GENERATION EQUIPMENT
510 Heating Boilers and Accessories
520 Feedwater Equipment
530 Furnaces

540 Fuel Fired Heaters


550 Breeching, Chimneys, and Stacks
15600 REFRIGERATION EQUIPMENT
610 Refrigeration Compressors
620 Packaged Water Chillers
630 Refrigerant Monitoring Systems
640 Packaged Cooling Towers
650 Field-Erected Cooling Towers
660 Liquid Coolers and Evaporative Condensers
670 Refrigerant Condensing Units
15700 HEATING, VENTILATING AND A/C EQUIP
710 Heat Exchangers
720 Air Handling Units
730 Unitary Air Conditioning Equipment
Packaged Airconditioning
740 Heat Pumps
750 Humidity Control Equipment
760 Terminal Heating and Cooling Units
770 Floor Heating and Snow Melting Equipment
780 Energy Recovery Equipment
15800 AIR DISTRIBUTION
810 Ducts
820 Duct Accessories
830 Fans
840 Air Terminal Units
850 Air Outlets and Inlets
860 Air Cleaning Devices
15900 HVAC INSTRUMENTATION AND CONTROLS
905 HVAC Instrumentation
910 Direct Digital Controls
915 Electric and Electronic Control
920 Pneumatic Controls
925 Pneumatic and Electric Controls
930 Self Powered Controls
935 Building Systems Control
940 Sequence of Operation
15950 TESTING, ADJUSTING AND BALANCING
Demonstration of Mechanical Equipment
Duct Testing, Adjusting, and Balancing
Equipment Testing, Adjusting, and Balancing
Mechanical Equipment Starting
Pipe Testing, Adjusting, and Balancing
DIV. 15A.1 VENTILATION
15050 BASIC MECHANICAL MATERIALS & METHOD
060 Hangers and Supports
070 Mechanical Sound, Vibration, and Seismic Control
075 Mechanical Identification
080 Mechanical Insulation
090 Mechanical Restoration and Retrofit
15800 AIR DISTRIBUTION
810 Ducts
820 Duct Accessories
830 Fans
840 Air Terminal Units
850 Air Outlets and Inlets
860 Air Cleaning Devices
Sound Attenuators

15900 HVAC INSTRUMENTATION AND CONTROLS


905 HVAC Instrumentation
910 Direct Digital Controls
915 Electric and Electronic Control
920 Pneumatic Controls
925 Pneumatic and Electric Controls
930 Self Powered Controls
935 Building Systems Control
940 Sequence of Operation
15950 TESTING, ADJUSTING AND BALANCING
Demonstration of Mechanical Equipment
Duct Testing, Adjusting, and Balancing
Equipment Testing, Adjusting, and Balancing
Mechanical Equipment Starting
Pipe Testing, Adjusting, and Balancing

DIV. 15B SANITARY


15100 BUILDING SERVICES PIPING
140 Domestic Water Piping
Non Potable
Hot Water
150 Sanitary Waste and Vent Piping
160 Storm Drainage Piping
170 Swimming Pool and Fountain Piping
Condensate Drain
15400 PLUMBING FIXTURES AND EQUIPMENT
410 Plumbing Fixtures
440 Plumbing Pumps
450 Potable Water Storage Tanks
460 Domestic Water Conditioning Equipment
470 Domestic Water Filtrating Equipment
480 Domestic Water Heaters
490 Pool and Fountain Equipment
LPG
15950 TESTING, ADJUSTING AND BALANCING
Demonstration of Mechanical Equipment
Equipment Testing, Adjusting, and Balancing
Mechanical Equipment Starting
Pipe Testing, Adjusting, and Balancing

DIV. 15C FIRE PROTECTION


15300 FIRE PROTECTION PIPING
Fire Pumps
Fire Tanks
Sprinkler Heads
Pipings
Control Valves
Pre-Action System
Deluge System
CO2 Extinguishing
ABC Extinguishing
Standpipe and Hose System
15950 TESTING, ADJUSTING AND BALANCING
Demonstration of Mechanical Equipment
Equipment Testing, Adjusting, and Balancing
Mechanical Equipment Starting
Pipe Testing, Adjusting, and Balancing

DIV. 16A LIGHTING & POWER


16050 BASIC ELECTRICAL MATERIALS AND METHODS
060 Grounding and Bonding
070 Hangers and Supports
075 Electrical Identification
080 Electrical Testing
090 Restoration and Repair
16100 WIRING METHODS
120 Conductors and Cables
130 Raceway and Boxes
140 Wiring Devices
150 Wiring Connections
16200 ELECTRICAL POWER
210 Electrical Utility Services
220 Motors and Generators
230 Generator and Assemblies
240 Battery Equipment
260 Static Power Converters
270 Transformers
280 Power Filters and Conditioners
290 Power Measurement and Control
16300 TRANSMISSION AND DISTRIBUTION
310 Transmission and Distribution Accessories
320 High Voltage Switching and Protection
330 Medium Voltage Switching and Protection
340 Medium Voltage Switching and Protection Assemblies
360 Unit Substations
16400 LOW VOLTAGE DISTRIBUTION
410 Enclosed Switches and Circuit Breakers
420 Enclosed Controllers
430 Low Voltage Switchgear
440 Switchboards, Panelboards, and Control Centers
450 Enclosed Bus Assemblies
460 Low Voltage Transformers
470 Power Distribution Units
490 Low Voltage Distribution Components and Accessories
16500 LIGHTING
510 Interior Luminaries
520 Exterior Luminaries
530 Emergency Lighting
540 Classified Location Lighting
550 Special Purpose Lighting
560 Signal Lighting
570 Dimming Control
580 Lighting Accessories
590 Lighting Restoration and Repair

DIV. 16B AUXILLIARIES


16700 COMMUNICATIONS
710 Communication Circuits
720 Telephone and Intercommunication Equipment
740 Communication and Data Processing Equipment
770 Cable Transmission and Reception Equipment
780 Broadcast Transmission and Reception Equipment
790 Microwave Transmission and Reception Equipment
16800 SOUND AND VIDEO
810 Sound and Video Circuits
820 Sound Reinforcement
830 Broadcast Audio Equipment
840 Broadcast Studio Audio Equipment
850 Television Equipment
880 Multimedia Equipment
Structural steel

COST STUDY: Louvered Staircase

1.) Lantern 1 (AT FRONT)

LOUVER UNIT QUANTITY UNIT QUANTITY height width length thickness


75X100 Tubular kgs. 286.84 lm 52.20 0.100 0.075 8.700 0.002
kgs. 43.96 lm 8.00 0.100 0.075 2.000 0.002
50 X 100 Tubular kgs. 880.30 lm 186.90 0.100 0.050 8.900 0.002
kgs. 184.63 lm 39.20 0.100 0.050 5.600 0.002
kgs. 77.24 lm 16.40 0.100 0.050 4.100 0.002
kgs. 69.24 lm 14.70 0.100 0.050 2.100 0.002

2.) Lantern 2 (AT BACK)

LOUVER UNIT QUANTITY UNIT QUANTITY height width length thickness


75X100 Tubular kgs. 514.33 lm 93.60 0.100 0.075 15.600 0.002
kgs. 87.92 lm 16.00 0.100 0.075 2.000 0.002
50 X 100 Tubular kgs. 1,716.80 lm 364.50 0.100 0.050 12.150 0.002
kgs. 310.86 lm 66.00 0.100 0.050 6.000 0.002
kgs. 103.62 lm 22.00 0.100 0.050 5.500 0.002
kgs. 129.53 lm 27.50 0.100 0.050 2.500 0.002

3.) Stairs at FRONT

LOUVER UNIT QUANTITY UNIT QUANTITY height width length thickness


75X100 Tubular kgs. 600.05 lm 109.20 0.100 0.075 15.600 0.002
50 X 100 Tubular kgs. 1,469.52 lm 312.00 0.100 0.050 1.500 0.002
kgs. 132.12 lm 28.05 0.100 0.050 2.550 0.002
kgs. 559.55 lm 118.80 0.100 0.050 6.600 0.002
kgs. 305.21 lm 64.80 0.100 0.050 4.050 0.002
kgs. 42.39 lm 9.00 0.100 0.050 1.800 0.002

Window false frame

LOUVER UNIT QUANTITY UNIT QUANTITY height width length thickness


50 X 50 Tubular kgs. 965.55 lm 1.00 0.050 0.050 410.000 0.0015
kgs. lm 0.050 0.050 0.002
kgs. lm 0.050 0.050 0.002
kgs. lm 0.050 0.050 0.002
kgs. lm 0.050 0.050 0.002
UNIT COST
PER KG 90.00
PER LM 125

timesing AREA VOLUME Unit weight FINAL WEIGHT FINAL LENGTH COST/ KG COST/ LM
6.000 3.045 0.037 7850.000 330.80 60.20 29,771.91 7,525.00
4.000 0.700 0.006 7850.000
21.000 2.670 0.112 7850.000 1,211.41 257.20 109,027.08 32,150.00
7.000 1.680 0.024 7850.000
4.000 1.230 0.010 7850.000
7.000 0.630 0.009 7850.000

timesing AREA VOLUME Unit weight FINAL WEIGHT FINAL LENGTH COST/ KG COST/ LM
6.000 5.460 0.066 7850.000 602.25 109.60 54,202.68 13,700.00
8.000 0.700 0.011 7850.000
30.000 3.645 0.219 7850.000 2,260.80 480.00 203,472.00 60,000.00
11.000 1.800 0.040 7850.000
4.000 1.650 0.013 7850.000
11.000 0.750 0.017 7850.000

timesing AREA VOLUME Unit weight FINAL WEIGHT FINAL LENGTH COST/ KG COST/ LM
7.000 5.460 0.076 7850.000 2,069.57 109.20 186,261.66 13,650.00
208.000 0.450 0.187 7850.000 2,508.78 532.65 225,790.34 66,581.25
11.000 0.765 0.017 7850.000
18.000 1.980 0.071 7850.000
16.000 1.215 0.039 7850.000
5.000 0.540 0.005 7850.000

FINAL COST 808,525.67 193,606.25

34.370 889,378.23 10% contingncies


10,311.00 1,022,784.97 15% profit
12,888.75

timesing AREA VOLUME Unit weight FINAL WEIGHT FINAL LENGTH COST/ KG COST/ LM
1.000 82.000 0.123 7850.000 965.55 410.00 - 51,250.00
0.000 0.000 7850.000 labor 15,375.00
0.000 0.000 7850.000 painting 5,740.00
0.000 0.000 7850.000 profit mesc. De 14,473.00
0.000 0.000 7850.000 86,838.00

86,899.50
AISC MEMBER DIMENSIONS AND PROPERTIES
W, S, M, HP Shapes C, MC Shapes WT, ST, MT Shapes
W16x31 MC10x22 WT4x20
46.24 kg/m 32.67 kg/m 29.73

Rectangular HSS Round HSS & Pipes


HSS8x6x3/8 PIPE8STD
45.43 kg/m 42.54 kg/m
D PROPERTIES
Single Angles
L3x3x1/4
kg/m 7.29 kg/m

Double Angles
2L5x3-1/2x3/8SLBB
30.89 kg/m
AISC MEMBER DIMENSIONS AND PROPERTIES VIEWER
W, S, M, HP Shapes C, MC Shapes WT, ST, MT Shapes Single Angles Double Angles Rectangular HSS

Y Y Y
k1=0.75 Y Y Y
k=0.842 tf=0.44 tf=0.575 b=5 t=0.349
bf=8.07 t=0.375
y(bar)=0.735 x(bar)=0.836
x(bar)=0.99 tf=0.56 d=3 t=0.25 X
d=15.9 T X d=1 X X d=3.5 h=8 X
d=4.13 X y(bar)=0.836
tw=0.275 tw=0.29 tw=0.36 b=3
(0, 3/8, or 3/4
bf=5.53 bf=3.32 gap) b=6

W16x31 MC10x22 WT4x20 L3x3x1/4 2L5x3-1/2x3/8SLBB HSS8x6x3/8


A= 9.13 in.^2 A= 6.45 in.^2 A= 5.87 in.^2 d= 3 in. d= 3.5 in. h= 8 in.
d= 15.900 in. d= 10.000 in. d= 4.130 in. b= 3 in. b= 5 in. b= 6 in.
tw = 0.275 in. tw = 0.290 in. tw = 0.360 in. t= 0.25 in. t= 0.375 in. t= 0.349 in.
bf = 5.530 in. bf = 3.320 in. bf = 8.070 in. k= 0.6250 in. k= 0.8125 in. wt./ft. = 32.50 plf.
tf = 0.440 in. tf = 0.575 in. tf = 0.560 in. wt./ft. = 4.89 plf. wt./ft. = 20.80 plf. A= 8.97 in.^2
T= 13-5/8 in. T= 7-3/8 in. k= 0.9540 in. A= 1.44 in.^2 A= 6.10 in.^2 Ix = 79.10 in.^4
k= 0.8420 in. k= 1.3125 in. Ix = 5.73 in.^4 Ix = 1.23 in.^4 Ix = 6.31 in.^4 Sx = 19.80 in.^3
k1 = 0.7500 in. gage = 2 in. Sx = 1.69 in.^3 Sx = 0.57 in.^3 Sx = 2.38 in.^3 rx = 2.970 in.
gage = 2.75 in. x(bar) = 0.990 in. rx = 0.988 in. rx = 0.926 in. rx = 1.020 in. Iy = 50.60 in.^4
rt = 1.390 in. eo = 1.120 in. y(bar) = 0.735 in. y(bar) = 0.836 in. y(bar) = 0.854 in. Sy = 16.90 in.^3
d/Af = 6.53 d/Af = 5.25 Iy = 24.50 in.^4 Iy = 1.23 in.^4 ry(0) = 2.260 in. ry = 2.380 in.
Ix = 375.00 in.^4 Ix = 102.00 in.^4 Sy = 6.08 in.^3 Sy = 0.57 in.^3 ry(3/8) = 2.390 in. Zx = 24.10 in.^3
Sx = 47.20 in.^3 Sx = 20.50 in.^3 ry = 2.040 in. ry = 0.926 in. ry(3/4) = 2.540 in. Zy = 19.80 in.^3
rx = 6.410 in. rx = 3.990 in. J= 0.558 in.^4 x(bar) = 0.836 in. ro(bar) = 2.56 in. J= 100.00 in.^4
Iy = 12.40 in.^4 Iy = 6.40 in.^4 Cw = 0.715 in.^6 rz = 0.585 in. H= 0.933
Sy = 4.49 in.^3 Sy = 2.75 in.^3 a= 1.82 in. TAN(a) = 1.000 Round HSS & Pipes
ry = 1.170 in. ry = 0.997 in. ro(bar) = 2.31 in. J= 0.0313 in.^4 Y
Zx = 54.00 in.^3 J= 0.51 in.^4 H= 0.961 Cw = 0.0206 in.^6 Plates t=0.322
Zy = 7.03 in.^3 Cw = 110 in.^6 a= 1.31 in. Y
J= 0.46 in.^4 a= 23.63 in. ro(bar) = 1.65 in. t=2.5
Cw = 739 in.^6 ro(bar) = 4.61 in. H= 0.628 X O.D.=8.63 X
a= 64.43 in. H= 0.791 b=39.36
Wno = 21.30 in.^2 I.D.=7.98
Sw = 13.00 in.^4 t= 2.5 in.
Qf = 8.92 in.^3 b= 39.36 in. PIPE8STD
Qw = 26.50 in.^3 wt./ft. = 334.83 plf. O.D. = 8.63 in.
Reference:
A= 98.400 in.^2 I.D. = 7.98 in.
The shapes contained in this database are a
compilation of those listed in the current AISC Ix = 51.250 in.^4 t= 0.322 in.
"Shapes Database" CD-ROM Version 3.0 (June, Sx = 41.000 in.^3 wt./ft. = 28.60 plf.
2001), as well as those listed in the AISC 9th rx = 0.722 in. A= 8.40 in.^2
Edition Manual of Steel Construction (1989). Iy = 12703.519 in.^4 I= 72.50 in.^4
Sy = 645.504 in.^3 S= 16.80 in.^3
ry = 11.362 in. r= 2.940 in.
J= 12754.769 in.^4 J= 145.00 in.^4
NOMENCLATURE FOR AISC MEMBER PROPERTIES AND DIMENSIONS:

A= Cross-sectional area of member (in.^2)


d= Overall depth of member, parallel to Y-axis (in.)
tw = Thickness of web of member (in.)
bf = Width of flange of member (in.)
tf = Thickness of flange of member (in.)
T= Distance between fillets for wide-flange or channel shape (in.) = d-(2*k)
k= Distance from outer face of flange to web toe of fillet (in.)
k1 = Distance from web centerline to flange toe of fillet (in.)
gage = Standard gage (bolt spacing) for member (in.) (Note: gages for angles are available by viewing comment box at cell K18.)
rt = Radius of gyration of compression flange plus 1/3 of compression web area, taken about an axis in plane of web (in.)
d/Af = Ratio of of total depth of member to area of compression flange of member = d/(b f*tf)
Ix = Moment of inertia of member taken about X-axis (in.^4)
Sx = Elastic section modulus of member taken about X-axis (in.^3)
rx = Radius of gyration of member taken about X-axis (in.) = SQRT(I x/A)
Iy = Moment of inertia of member taken about Y-axis (in.^4)
Sy = Elastic section modulus of member taken about Y-axis (in.^3)
ry = Radius of gyration of member taken about Y-axis (in.) = SQRT(I y/A)
Zx = Plastic section modulus of member taken about X-axis (in.^3)
Zy = Plastic section modulus of member taken about Y-axis (in.^3)
J= Torsional constant of member (in.^4)
Cw = Warping constant (in.^6)
a= Torsional property, a = SQRT(E*Cw/G*J)
E= Modulus of elasticity of steel = 29,000 ksi
G= Shear modulus of elasticity of steel = 11,200 ksi
Wno = Normalized warping function at a point at the flange edge (in.^2)
Sw = Warping statical moment at a point on the cross section (in.^4)
Qf = Statical moment for a point in the flange directly above the vertical edge of the web (in.^3)
Qw = Statical moment at the mid-depth of the section (in.^3)
x(bar) = Distance from outside face of web of channel shape to Y-axis (in.)
eo = Horizontal distance from the outer edge of a channel web to its shear center (in.) = (approx.) t f*(d-tf)^2*(bf-tw/2)^2/(4*Ix)-tw/2
xo = x-coordinate of shear center with respect to the centroid of the section (in.)
yo = y-coordinate of shear center with respect to the centroid of the section (in.)
ro(bar) = Polar radius of gyration about the shear center (in.) = SQRT(x o^2+yo^2+(Ix+Iy)/A)
H= Flexural constant, H = 1-(xo^2+yo^2)/ro(bar)^2)
LLBB = Long legs back-to-back for double angles
SLBB = Short legs back-to-back for double angles
STD = Standard weight (Schedule 40) pipe section
XS = Extra strong (Schedule 80) pipe section
XXS = Double-extra strong pipe section
QUADRATIC EQUATION:

A = 1 A = 1
B = -0.129348 B - 4AC
2
= 0.128466
C = 5.68E-05 C = 5.68E-05

X = 0.128907 (+) POSITIVE


X = 0.128907 X = 0.000441 (-) NEGATIVE
(+) POSITIVE
(-) NEGATIVE
G.I. & B.I. PIPES EQUIVALENT WEIGHTS

Pipe Size ( ID ) Pipe Size ( ID ) Length Thickness Area 1 Volume 1 Area 2


Item
inches mm m mm m² m³ m²

1 1/2 15 6 2.8 0.00018 0.00106 0.00033


2 3/4 20 6 2.9 0.00031 0.00188 0.00052
3 1 25 6 3.4 0.00049 0.00295 0.00079
4 1 1/4 32 6 3.6 0.00080 0.00483 0.00121
5 1 1/2 40 6 3.7 0.00126 0.00754 0.00176
6 2 50 6 4 0.00196 0.01178 0.00264
7 2 1/2 65 6 5.2 0.00332 0.01991 0.00447
8 3 80 6 5.5 0.00503 0.03016 0.00650
9 4 100 6 6 0.00785 0.04712 0.00985
10 5 125 6 6.6 0.01227 0.07363 0.01500
11 6 150 6 7.1 0.01767 0.10603 0.02118
12 8 200 6 8.2 0.03142 0.18850 0.03678
13 10 250 6 9.57 0.04909 0.29453 0.05689
14 12 300 6 10.3 0.07069 0.42412 0.08073
15 14 350 6 11.11 0.09621 0.57727 0.10882
16 16 400 6 12.7 0.12566 0.75398 0.14213
17 18 450 6 12.7 0.15904 0.95426 0.17750
18 20 500 6 14.27 0.19635 1.17810 0.21941
19 24 600 6 12.7 0.28274 1.69646 0.30719
20 - - -
GHTS
kg / m³ 7,850.00

Volume 2 Weight
m³ kg

0.00200 7.37
0.00314 9.83
0.00477 14.29
0.00724 18.96
0.01059 23.93
0.01585 31.96
0.02679 54.01
0.03902 69.58
0.05911 94.11
0.09000 128.52
0.12705 165.05
0.22068 252.62
0.34135 367.57
0.48436 472.92
0.65289 593.64
0.85278 775.55
1.06503 869.51
1.31643 1,085.89
1.84314 1,151.39
- -
** Considerations of Structural Elements

Description Dimensions Formworks


Concrete (m³) (m²)
Length Width Height Timesing Actual Actual
Isolated Footing
(1500x1500x300)mm 1.5 1.5 0.3 8 5.40 14.40

Roof Beams
(200x400)mm 4.4 55.00
6.5 0.2 0.4 6 3.12 39
8 0.2 0.4 2 1.28 16

Suspended Slab 8 6.5 0.12 3 18.72 156


(assumed 120mm thk)

Columns 6.2 0.25 0.45 8 5.58 69.44


(250x450) mm

Total 34.10 294.84

GFA 156.00

Analysis
Concrete (m3) 34.32 0.22
Rebar( kg) 3,432.00 100.00
Formworks (m2) 296.40 1.90
Formworks Rebars (kgs)- STEEL Ratio (kg/m³) FORM Ratio (m²/m³)
(m²)- by ratio by ratio
min max min max

27.00 243.00 45 40 80 5 4 6

44.00 528.00 120 100 200 10 8 12

187.20 1497.60 80 70 120 10 8 12

55.80 1227.60 220 150 350 10 8 12

314.00 3496.20

m2

m3/m2 GFA
kg/m3 concrete
m2/m2 GFA
** Considerations of Structural Elements

Description Dimensions Formworks


Concrete (m³) (m²)
Length Width Height Timesing Actual Actual
Isolated Footing
(1500x1500x300)mm 1.5 1.5 0.3 8 5.40 14.40

Footing Tie beam


(200x400)mm 4.40 55.00
6.5 0.2 0.4 6 3.12 39
8 0.2 0.4 2 1.28 16

Beams for Suspended Slabs


(250x500)mm 11.875 118.75
6.5 0.25 0.5 6 4.875 48.75
8 0.25 0.5 7 7 70

Roof Beams
(200x400)mm 4.4 55.00
6.5 0.2 0.4 6 3.12 39
8 0.2 0.4 2 1.28 16

Suspended Slab 8 6.5 0.12 3 18.72 156


(assumed 120mm thk)

Columns 6.2 0.25 0.45 8 5.58 69.44


(250x450) mm

Total 50.38 468.59

GFA 156.00

Analysis
Concrete (m3) 49.92 0.32
Rebar( kg) 6,489.60 130.00
Formworks (m2) 466.44 2.99
Formworks Rebars (kgs)- STEEL Ratio (kg/m³) FORM Ratio (m²/m³)
(m²)- by ratio by ratio
min max min max

27.00 243.00 45 40 80 5 4 6

44.00 704.00 160 100 200 10 8 12

118.75 1900.00 160 100 200 10 8 12

44.00 528.00 120 100 200 10 8 12

187.20 1497.60 80 70 120 10 8 12

55.80 1227.60 220 150 350 10 8 12

476.75 6100.20

m2

m3/m2 GFA
kg/m3 concrete
m2/m2 GFA
Concrete Estimate
I. CONCRETE SLAB
Given:
length: 0 m
width: 0 m
thickness: 0 m

Computation:
1 Vol = 0 cu.m

2 Cement = 0 bags
sand = 0 cu.m
gravel 3/4 = 0 cu.m

II. POST & FOOTING


l w h
Given : POST = 0.4 X 0.15 X 7.65
FOOTING = 1.5 X 1.5 X 0.35
no. of Post & = 2 pcs
Footing

Computation:
1 Vol. Post = 0.918 cu.m
Vol. Footing = 1.575 cu.m
------
2 Total Vol. = 2.493 cu.m

3 Cement = 21.689 bags 21.622


sand = 1.4958 cu.m
gravel 3/4 = 2.9916 cu.m

III. RECTANGULAR BEAM & GIRDER

Given: BEAM = 0.2 X 0.30


Total length = 76 m
76
Computation: 62.67
1 Vol. 4.56 cu.m 8.712

2 Cement = 39.672 bags


sand = 2.736 cu.m
gravel 3/4 = 5.472 cu.m

IV. MASONRY
Given Height = 6.6 m
Length = 82.8 m
--------
Area = 546.48 sq.m
1 divide the height of the wall by the height of one block = 33 layers

2 divide the length of the wall by the length of one block = 207 pcs.

3 Multiply the result of step 1 & 2 = 6831 pcs.

Allowance(5%) = 7173 pcs


V. CEMENT MORTAR (BY AREA METHOD)

size of chb no. per Sq.m B C D Sand


4 10x20x40 12.5 0.525 0.394 0.328 0.0438
6 15x20x40 12.5 1.013 0.759 0.633 0.0844
8 20x20x40 12.5 1.500 1.125 0.938 0.125

1 Find the Area of the wall = 546.48 sq.m

2 cement: = 286.9 bags


sand: = 23.936 cu.m

VI. MORTAR FOR PLASTERING (AREA METHOD)


MIX 16mm 20mm 25mm
A 0.288 0.36 0.45
B 0.192 0.24 0.3
C 0.144 0.18 0.225
D 0.12 0.15 0.188
SAND 0.016 0.02 0.025

Computation (2 FACE OF WALL) = 1093 sq.m

1 find the area of the wall = 1093 sq.m


2 25mm thick plaster class B

cement : = 327.888 bags


sand : = 27.324 cu.m

VII. WALL FOOTING


Given :
length = 0 m
width = 0 m
thickness = 0 m

Computation
1 Volume = 0 cu.m

2 cement : = 0 bags
sand : = 0 cu.m
gravel : = 0 cu.m

SUMMARY
CEMENT = 676.15 bags x 160 = 108184
SAND = 55.492 cu.m x 350 = 19422.1
GRAVEL 3/4 = 8.4636 cu.m x 550 = 4654.98
CHB = 7173 pcs. x 5.2 = 37297.3
------------
P 169558
48.6
pcs
Estimate of Reinforcement
I. Reinforcement for Concrete Hollow Blocks (10mmØ bars)

Given :
length = 13.7 m
height = 2.7 m

Computation
1 Solve for the area of the fence
Area = 36.99 sq.m

2 for vertical reinforcement spaced at .80m distance


refer to table below under column per sq.m

36.99 x 1.6 = 59.184 m long steel bars

3 solve for the horizontal bars at .60m distance


refer to table below under column per sq.m

36.99 x 2.15 = 79.529 m long steel bars

4 add result 1 & 2 = 139 m long

5 Convert this value to the commercial length of steel bars


say we choose 6.00 m long = 23.119 pcs (10mm Ø)

6 Computation for tie wire = 1.5397 kgs

vertical reinf horizontal reinf


spacing per sq.m layers per sq.m
0.4 2.93 2 3.3
0.6 2.13 3 2.15
0.8 1.6 4 1.72

II. SQUARE FOOTING

Given : length of reinforcing cut bar


width = 0 ~ 0.1
length = 0 ~ 0.1
no. of square = 0 pcs
footing

Computation

1 total cut bars in width(by direct counting)


n = 0

2 total cut bars in length( by direct counting)


n = 0

3 total cut bars whole no of footing


n = 0 pcs

4 width = 0
length = 0
______
0 meters

5 divide by 6.00 m length of bar = 0 pcs.(16mmØ bar)

6 Computation for tie wire = 0 kgs


ESTIMATE OF FORMWORKS
given data
answer

CONCRETE POST

GIVEN : ht of column: 7.5 m no of col 12


dimension of post: 0.4 x ###
lateral surface area 9 sq.m

1 total area of col = 108.0 382


2 plywood 4'x8' = 49.7 pcs
3 solve for the frame 2"x2" = 1458 bd.ft 365 pcs 2"x2"x12'

BEAM & GIRDER

GIVEN : length of beams 135 m


dimension of beam: 0.4 x ###

1 find the surface are of 2 sides = 54 sq.m


2 find the area of the bottom surface of the beam = 54 sq.m
3 add 1& 2 = 108 sq.m
4 plywood 4'x8' = 43 pcs 1/2"x4'x8' plywood
5 solve for frame 2"x2" = 691 bd ft. 172.8

scaffolding for columns


given : total length of col = 90

1 vertical support 2"x3" = 630 bd.ft 105 pcs 2"x3"


2 horizontal support 2"x2" = 1890 bd.ft 473 pcs 2"x2" 540
3 diagonal brace 2"x2" = 1053 bd.ft 263 pcs 2"x2"

scaffolding for beams


given : total length of beam = 135 m 168

1 vertical support 2"x3" = 810 bd.ft 135 pcs 2"x3"


2 horizontal support 2"x2" = 634.5 bd.ft 159 pcs 2"x2"

3 scaffolding for slab


given : area = 8 x 0.15
units = 9.5

1 area of conc floor = 11.4 sq.m


2 support 2"x3" = 103.74 bd.ft 17 pcs 2"x3"

3 floor slab form = 3.9583 pcs 1/2"x4'x8' plywood


note 3 use
1/2"x4'x8' plywood 97 pcs 1549.413
2"x3" good lumber 1544 bd.ft
2"x2" good lumber 5727 bd.ft
cwn assorted 158.76 kgs

summary of materials
use of formworks
1/2"x4'x8' plywood 32.279 pcs 1/2"x4'x8' plywood
2"x3" good lumber 514.58 bd.ft 86 pcs 2"x3"
2"x2" good lumber 1908.9 bd.ft 477 pcs 2"x2"
cwn assorted 52.919 kgs
134.2

4'x8' plywood
pcs
bdft

Vous aimerez peut-être aussi