PROJECT TITLE :

CONDENSATE FRACTIONATION PLANT & ASSOCIATED FACILITIES


CAPACITY 4000 BBL/DAY
AT RASHIDPUR, BAHUBOL, HABIGANJ, BANGLADESH
EMPLOYER :

SYLHET GAS FIELDS LIMITED

DOCUMENT TITLE :

PRESSURE TEST EXECUTION


PLAN FOR STORAGE TANK

DOCUMENT STATUS
Approved
:

Approved
: as Noted

Not Approved

C Mar 23, 2019 ISSUED FOR APPROVAL


B Mar 10, 2019 ISSUED FOR REVIEW
A Mar 4, 2019 ISSUED FOR INFORMATION
ENG. EM PM
REV. DATE DESCRIPTION PREPARED
CHECKED APPROVED

TOTAL OR PARTIAL REPRODUCTION AND / OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN


WITHOUT WRITTEN AUTHORIZATION OF THE OWNER

EMPLOYER : EMPLOYER CONTRACT NO. : SGFL/4000CFP/EPC/C-1 CONTRACTOR :

CONTRACTOR JOB NO. : C – 222 / 2015

CONTRACTOR DOC. NO. :

EMPLOYER DOC. NO. :


SYLHET GAS FIELDS LIMITED
PAGE NO. : 1 of 12
EMPLOYER :
PROJECT TITLE : CONTRACTOR :
` CONDENSATE FRACTIONATION PLANT & ASSOCIATED
FACILITIES, CAPACITY 4000 BBL/DAY
AT RASHIDPUR, BAHUBOL, HABIGANJ, BANGLADESH

PRESSURE TEST EXECUTION


SYLHET GAS FIELDS LIMITED PLAN FOR STORAGE TANK
REV. C

Revision No.: C

Rev. Date Name Description

A Mar 23, 2019 For Approval

B Mar 10, 2019 For Review

A Mar 4, 2019 For Information

Rev. C

Name Date
Prepared: Jubayer
Sheet 2
Checked:
Of 12
QA Approved:
Approved:
EMPLOYER :
PROJECT TITLE : CONTRACTOR :
` CONDENSATE FRACTIONATION PLANT & ASSOCIATED
FACILITIES, CAPACITY 4000 BBL/DAY
AT RASHIDPUR, BAHUBOL, HABIGANJ, BANGLADESH

PRESSURE TEST EXECUTION


SYLHET GAS FIELDS LIMITED PLAN FOR STORAGE TANK
REV. C

TEBULATION OF REVISED PAGES


Revision Revision
Sheet Sheet
A B C

1 x x x
2 x x x
3 x x x
4 x x
5 x x
6 x x
7 x x x
8 x x
9 x x
10 x x
11 x x
12 x x x
13
14
15
16
17
18
19
20
21
22

PAGE | 3
EMPLOYER :
PROJECT TITLE : CONTRACTOR :
` CONDENSATE FRACTIONATION PLANT & ASSOCIATED
FACILITIES, CAPACITY 4000 BBL/DAY
AT RASHIDPUR, BAHUBOL, HABIGANJ, BANGLADESH

PRESSURE TEST EXECUTION


SYLHET GAS FIELDS LIMITED PLAN FOR STORAGE TANK
REV. C

Table of Contents

S.N DESCRIPTION Page No


1.0 SCOPE 5

2.0 REFERENCE 5

3.0 PREPARATION OF TESTING 5

4.0 HEALTH & SAFETY 5

5.0 TOOLS & EQUIPMENT 5

6.0 PRESSURE TEST BY NITROGEN 6

6.1 PRESSURE TESTING IN EMPTY TANKS (NOT IN OPERATION) 7

6.2 PRESSURE TESTING IN PARTIALLY FILLED TANKS (IN OPERATION) 7

7.0 RECORDS 8

7.1 CHECKLIST PRIOR TO START PRESSURE TEST BY NITROGEN 8

7.2 PRESSURE TESTING CHECKLIST 9

7.3 CHECKLIST AFTER FINISHING PRESSURE TEST 10

8.0 ATTACHMENT 10

8.1 PRESSURE TEST REPORT 11

8.2 PRESSURE TEST OF TANK EXECUTION SCHEDULE 12

PAGE | 4
EMPLOYER :
PROJECT TITLE : CONTRACTOR :
` CONDENSATE FRACTIONATION PLANT & ASSOCIATED
FACILITIES, CAPACITY 4000 BBL/DAY
AT RASHIDPUR, BAHUBOL, HABIGANJ, BANGLADESH

PRESSURE TEST EXECUTION


SYLHET GAS FIELDS LIMITED PLAN FOR STORAGE TANK
REV. C

1. SCOPE

This procedure describes the method of pressure testing by nitrogen with documentation of tank for the
the project of CONDENSATE FRACTIONATION PLANT & ASSOCIATED FACILITIES
CAPACITY 4000 BBL/DAY AT RASHIDPUR, BAHUBOL, HOBIGONJ, BANGLADESH.

2. REFERENCES
 API 650

3. PREPARATION OF TESTING
 Tank has been hydro‐tested, drained, cleaned, and dried.
 Verify that no impurity (solid or Liquid) are left in the tank.
 The supervisor has declared the tank is ready to take the petro-product for storage.
 The inside of the tank shall be cleaned.
 The external piping shall be isolated by closing the isolation valve.
 Tank should be installed with Breather Valve, Pressure gauge and drain valve.
 All thread connection are plugged except one which is the lowest the drain valve. This valve shall
be in closed position.
 A manometer should be installed in top of the tank to measuring pressure.
 Nitrogen hose must contain a regulator.

4. HEALTH & SAFETY

 The area of the tank and nitrogen vehicles & arrangement should be cordoned off.
 A sign must be posted which mentioned only “Authorized Personnel Can Entry”.
 Safety officer have to be present during the test.
 Before starting the test a checklist have to fill.
 All the tools, hose and safety valves must be checked prior to start the job.
 Check the function ability of the regulator installed in the nitrogen filling line.
 Manometer, Gas analyzer & regulator have to be calibrated.

5. TOOLS & EQUIPMENT

 Manometer
 Nitrogen regulator
 Nitrogen Tanker
 Pressure Gauge
 Gas Analyzer/ Tester

PAGE | 5
EMPLOYER :
PROJECT TITLE : CONTRACTOR :
` CONDENSATE FRACTIONATION PLANT & ASSOCIATED
FACILITIES, CAPACITY 4000 BBL/DAY
AT RASHIDPUR, BAHUBOL, HABIGANJ, BANGLADESH

PRESSURE TEST EXECUTION


SYLHET GAS FIELDS LIMITED PLAN FOR STORAGE TANK
REV. C

6. PRESSURE TEST BY NITROGEN


6.1 PRESSURE TESTING IN EMPTY TANKS (NOT IN OPERATION)

a) For empty tank, nitrogen will be filled from bottom shell N2 nozzle point.
b) Filling with nitrogen should be started to ensure that the pressure in the tank is gradually
increased to .02 barg (15 mmHg or 20 mbar)
c) At first once 5 mbar pressure achieved, filling will be stopped.
d) Holding time is 30 Minutes with soap testing at curb angle to roof plate welding.
e) If there is no leakage then again start filling with nitrogen.
f) Once 10 mbar pressure achieved, filling will be stopped and holding the pressure for 30
minutes with soap testing at curb angle to roof plate welding.
g) If there is no leakage then again start filling with nitrogen.
h) Once 15 mbar pressure achieved, filling will be stopped and holding the pressure for 30
minutes with soap testing at curb angle to roof plate welding.
i) If there is no leakage then the breather valves will be deactivated.
j) The nitrogen will be filling carefully to reach the pressure 20 mbar.
k) Final holding time is 60 Minutes with soap testing at curb angle to roof plate welding.
l) After satisfactory result, pressure will be released by opening the vent valve up to 15mbar.
m) Then BV will be activated.
n) After that, remove hose connection of nitrogen supply.
o) Remove the fittings of the manometer from the tank top.
p) Careful control and monitoring is required for changes of pressures & temperature during this
testing.

PAGE | 6
EMPLOYER :
PROJECT TITLE : CONTRACTOR :
` CONDENSATE FRACTIONATION PLANT & ASSOCIATED
FACILITIES, CAPACITY 4000 BBL/DAY
AT RASHIDPUR, BAHUBOL, HABIGANJ, BANGLADESH

PRESSURE TEST EXECUTION


SYLHET GAS FIELDS LIMITED PLAN FOR STORAGE TANK
REV. C

6.2 PRESSURE TESTING IN PARTIALLY FILLED TANKS (IN OPERATION)


a) For partially filled tank with petro-product i.e. condensate, motor spirit etc., nitrogen will be
filled from tank top observation nozzle with a NPT blind flanges with a valve actuator.
b) Filling with nitrogen should be started to ensure that the pressure in the tank is gradually
increased to .02 barg (15 mmHg or 20 mbar)
c) At first once 5 mbar pressure achieved, filling will be stopped.
d) Holding time is 30 Minutes with soap testing at curb angle to roof plate welding.
e) If there is no leakage then again start filling with nitrogen.
f) Once 10 mbar pressure achieved, filling will be stopped and holding the pressure for 30
minutes with soap testing at curb angle to roof plate welding.
g) If there is no leakage then again start filling with nitrogen.
h) Once 15 mbar pressure achieved, filling will be stopped and holding the pressure for 30
minutes with soap testing at curb angle to roof plate welding.
i) If there is no leakage then the breather valves will be deactivated.
j) The nitrogen will be filling carefully to reach the pressure 20 mbar.
k) Final holding time is 60 Minutes with soap testing at curb angle to roof plate welding.
l) After satisfactory result, pressure will be released by opening the vent valve up to 15mbar.
m) Then BV will be activated.
n) Remove the fittings of the manometer from the tank top.
o) Careful control and monitoring is required for changes of pressures & temperature during this
testing.

PAGE | 7
EMPLOYER :
PROJECT TITLE : CONTRACTOR :
` CONDENSATE FRACTIONATION PLANT & ASSOCIATED
FACILITIES, CAPACITY 4000 BBL/DAY
AT RASHIDPUR, BAHUBOL, HABIGANJ, BANGLADESH

PRESSURE TEST EXECUTION


SYLHET GAS FIELDS LIMITED PLAN FOR STORAGE TANK
REV. C

7. RECORDS
7.1 CHECKLIST PRIOR TO PRESSURE TEST BY NITROGEN

CHECKLIST PRIOR TO START PRESSURE TEST BY NITROGEN


SL # DESCRIPTION OF ITEMS YES NO N/A
01 Confirm Tank General Arrangement drawing’s availability. □ □ □
02 Confirm Report of Water-fill Hydrostatic Test of Tank has been □ □ □
available.
03 Check No impurity (solid or Liquid) are left in the tank □ □ □
04 Confirm manometer, pressure regulator and gas analyzer are □ □ □
calibrated & valid
05 Check Breather Valve, Pressure gauge, isolation valves and drain □ □ □
valves are installed properly.
06 Confirm all the isolation valves are closed. □ □ □
07 Confirm all the thread openings are plugged. □ □ □
08 Confirm all the drain valves are closed. □ □ □
09 Confirm the breather valves are properly working. □ □ □
10 Confirm the vent valve is properly working. □ □ □
11 Confirm Pressure gauges is working properly. □ □ □
12 Confirm all flanges or gaskets have been installed as per design □ □ □
requirement.
13 Confirm proper size nut, bolts have been used for flanges & all nut- □ □ □
bolts were properly tighten for pressure test.
14 Confirm manometer is installed in the roof observation nozzle with a □ □ □
valve.
15 Confirm manometer is working properly □ □ □
16 Confirm correct flow direction through all items. □ □ □
17 Confirm nitrogen filling & manometer hoses are tied down properly. □ □ □
18 Confirm that pressure regulator on the nitrogen hose is working □ □ □
properly
19 Confirm that nitrogen tank are checked and settled in a safe distance □ □ □
properly
20 Segregate the tank location and surround the area with safety caution □ □ □
tape.
21 Set appropriate safety warning signs & assign proper people to check □ □ □
the area.

PAGE | 8
EMPLOYER :
PROJECT TITLE : CONTRACTOR :
` CONDENSATE FRACTIONATION PLANT & ASSOCIATED
FACILITIES, CAPACITY 4000 BBL/DAY
AT RASHIDPUR, BAHUBOL, HABIGANJ, BANGLADESH

PRESSURE TEST EXECUTION


SYLHET GAS FIELDS LIMITED PLAN FOR STORAGE TANK
REV. C

7.2 PRESSURE TEST CHECKLIST

PRESSURE TEST CHECKLIST


Description Yes No N/A
1. Confirm approved work-permit has been available. □ □ □
2. Confirm all the crew involving with pressure testing attended tool-box meeting. □ □ □
3. Confirm approved pressure testing method statement available for review and □ □ □
clearly understood.
4. Confirm the checklist Prior to Start pressure test by nitrogen is understood and □ □ □
followed.
5. Confirm necessary arrangements present to vent if system exceed excess pressure. □ □ □
6. Confirm Nitrogen availability in the tanker. □ □ □
7. Confirm Nitrogen tanks are in safe distance. □ □ □
8. Confirm Check Breather Valve, Pressure gauge, isolation valves and drain valves □ □ □
are working properly.
9. Confirm tank zone is properly barricaded with caution tape & necessary sign. □ □ □
10. Confirm the valve of nitrogen filling line is open. □ □ □
11. Confirm all testing accessories (hoses, connection fittings, flanges, blinds, □ □ □
isolation valves and test pumps accessories etc.) identified and working
12. Confirm all the isolation valve is closed during pressure testing. □ □ □
13. Confirm calibration certificates for manometer is available. □ □ □
14. Confirm the tank operator operating from outside of exclusion zone. □ □ □
15. Ensure that the pressure in the tank is maintained as per desired pressure. □ □ □
16. Ensure a check valve/non return valve been installed correctly in nitrogen tanker □ □ □
side.
17. Ensure holding time has been maintained □ □ □
18. Ensure soap testing at curb angle to roof plate welding has been conducted during □ □ □
holding time

PAGE | 9
EMPLOYER :
PROJECT TITLE : CONTRACTOR :
` CONDENSATE FRACTIONATION PLANT & ASSOCIATED
FACILITIES, CAPACITY 4000 BBL/DAY
AT RASHIDPUR, BAHUBOL, HABIGANJ, BANGLADESH

PRESSURE TEST EXECUTION


SYLHET GAS FIELDS LIMITED PLAN FOR STORAGE TANK
REV. C

7.3 CHECKLIST AFTER FINISHING PRESSURE TEST

CHECKLIST AFTER FINISHING PRESSURE TEST


SL # DESCRIPTION OF ITEMS YES NO N/A
01 Confirm Manometer is removed properly. □ □ □
02 Confirm the vent valve is closed. □ □ □
03 Check Breather Valve, Pressure gauge, isolation valves are in opened □ □ □
position.
04 Confirm drain valve of nitrogen line has been closed. □ □ □
05 Confirm pressure regulator is removed □ □ □
06 Confirm all blinds are installed and tightened properly. □ □ □
07 Confirm all flanges or gaskets have been installed as per design requirement. □ □ □
08 Confirm proper size nut, bolts have been used for flanges & all nut- bolts □ □ □
were properly tighten for pressure test.
09 Confirm nitrogen filling & Manometer hoses are removed properly. □ □ □
10 Confirm that nitrogen tank are valves are closed. □ □ □
11 Confirm report has been signed by proper person □ □ □
12 Confirm work permit has been closed and sent to proper authority □ □ □
13 House-keep the area before removing safety caution tape. □ □ □

8. ATTACHMENT
8.1 PRESSURE TEST REPORT
8.2 PRESSURE TEST OF TANK EXECUTION SCHEDULE

PAGE | 10
CONDENSATE FRACTIONATION PLANT AND
ASSOCIATED FACILITIES CAPACITY 4000
BBL/DAY, at RASHIDPUR, BAHUBOL, HABIGANJ -
SYLHET GAS FIELDS
BANGLADESH
LIMITED Rev. C

TITLE: PRESSURE TEST REPORT Report No. Date. Page


ge
TANK NO :

P&ID NO.

DESIGN PRESSURE :

TEST PRESSURE :

CHECK CALIBRATION
1. PRESSURE GAUGE
2. PRESSURE REGULATOR
3. MANOMETER
PRE-TEST INSPECTION CHECKLIST REF. NO :
DURING INSPECTION CHECKLIST:
AFTER INSPECTION CHECKLIST:
PRESSURE TEST RECORD :
DATE STARTING TIME FINISHING TIME PRESSURE HOLD (min) REMARKS

TEST RESULT : ACCEPTED NOT ACCEPTED

Comment :

Contractor Client
Authority
Sub. Contractor EPGL ARIHANT IKL tSGFL
Name :
Signature :
Date :
Page 11
Pressure Testing of Tanks Execution Time Schedule

Sl Tank Name of The Tanks Capacity (CuM) Days Starting Date Finshing Date 15-Mar 22-Mar 29-Mar 5-Apr 12-Apr 19-Apr 26-Apr

1 T-514 Liquid Chemical Tank 1200 1 27-Mar 27-Mar


2 T-511 MTT Production Tank 2000 2 28-Mar 29-Mar
3 T-502 Condensate Stabilized Tank 8000 2 30-Mar 31-Mar
4 T-503 Condensate Feed Tank 8000 2 1-Apr 2-Apr
5 T-505 Hydrotreated Motor Spirit Tank 6000 2 3-Apr 4-Apr
6 T-506 Motor Spirit Stabilized Tank 6000 2 7-Mar 8-Mar
7 T-512 Blended Motor Spirit Production Tank 6000 3 9-Apr 11-Apr
8 T-513 Blended Motor Spirit Delivery Tank 6000 3 12-Apr 14-Apr
9 T-504 Motor Spirit RCFP Receiving Tank 6000 3 15-Apr 17-Apr
10 T-501 Condensate Receiving Tank 8000 3 18-Apr 20-Apr
11 T-515 Hydrotreated Motor Spirit Tank 6000 3 19-Apr 21-Apr
12 T-516 Octane Production Tank 6000 3 22-Apr 24-Apr
13 T-517 Octane Delivery Tank 6000 3 25-Apr 27-Apr

NOTE:
1. This schedule will depend on the availability of the nitrogen.
2. It may vary depends upon weather condition (i.e. if rainy or too hot nitrogen filling has to stop)