Académique Documents
Professionnel Documents
Culture Documents
(Deliverable 4.3)
Lead Beneficiary:
EFACEC
Deliverable 4.3
Planning of Advanced System Protections
AUTHORS:
European Commission X
Public
2/97
Deliverable 4.3
Planning of Advanced System Protections
Executive Summary
The SuSTAINABLE project, which is funded under the 7th Framework
Programme for Research and Technological Development (FP7) and connects 8
partners, will develop and demonstrate a new operation paradigm, leveraging
information from smart meters and short-term localized predictions to manage
distribution systems in a more efficient and cost-effective way, enabling a large-
scale deployment of variable distributed resources.
In this deliverable, the functionalities to be developed and implemented within
the task of planning of advanced system protections are described. These
functionalities have the goal of enabling off-the-shelf protection relays to become
adaptive to specific operational conditions that may occur in the presence of high
penetration levels of DG.
Due to the high complexity level of these functionalities and the obvious
limitation to simulate real faults on the network, proof-of-concept demonstrations
(simulations) are held at laboratory test sites in Greece (ICCS) and Portugal
(INESCP).
3/97
Deliverable 4.3
Planning of Advanced System Protections
Table of Contents
EXECUTIVE SUMMARY ............................................................................................................. 3
TABLE OF CONTENTS................................................................................................................ 4
LIST OF FIGURES ...................................................................................................................... 6
LIST OF TABLES ........................................................................................................................ 8
LIST OF ACRONYMS AND ABBREVIATIONS ................................................................................ 9
1 INTRODUCTION .................................................................................................................. 12
2 DISTRIBUTION NETWORK: SYSTEM PROTECTION ................................................................. 13
2.1 Faults in the Distribution Network ............................................................................... 13
2.2 Medium Voltage Protection Functions ......................................................................... 14
2.2.1 Protection against phase-faults ................................................................................................ 15
2.2.2 Protection against earth-faults ................................................................................................. 16
2.2.3 Frequency Protection ............................................................................................................... 18
2.2.4 Broken Conductor .................................................................................................................... 18
2.2.5 Synchronous and Voltage Check .............................................................................................. 18
2.2.6 Reclosing ............................................................................................................................. 19
2.3 Protection Functions: Distributed Generation connection point .................................... 21
2.3.1 Under- and Overvoltage Protection ......................................................................................... 23
2.3.2 Neutral Overvoltage Protection ............................................................................................... 24
2.3.3 Under- and Overfrequency Protection ..................................................................................... 24
2.3.4 Overcurrent Protection ............................................................................................................ 24
3 DISTRIBUTION NETWORK MODELLING ................................................................................ 26
3.1 Rhodes System Modelling ............................................................................................ 26
3.2 Évora System Modelling............................................................................................... 30
4 IMPACT OF DISTRIBUTED GENERATION ON DISTRIBUTION SYSTEM PROTECTION ................. 33
4.1 Protection Blinding ...................................................................................................... 33
4.1.1 Quantitative Analysis ................................................................................................................ 34
4.2 Sympathetic Tripping ................................................................................................... 39
4.2.1 Quantitative Analysis ................................................................................................................ 41
4.2.2 Design of Adaptive Protection Scheme for Sympathetic Tripping ........................................... 43
4.2.2.1 Smart Substation Controller for Sympathetic Tripping ....................................... 45
4.3 Failed Auto-Reclosing .................................................................................................. 47
4.4 Loss-of-mains protection ............................................................................................. 50
4.4.1 Unintentional Islanding ............................................................................................................ 50
4.4.2 Islanding Detection Methods ................................................................................................... 52
4.4.2.1 Remote Techniques ............................................................................................ 52
4/97
Deliverable 4.3
Planning of Advanced System Protections
5/97
Deliverable 4.3
Planning of Advanced System Protections
List of Figures
Figure 1 – Phase To Phase vs. Earth Faults in the MV Distribution Network (Portugal) ................................. 14
Figure 2 – Fault Clearing Time in the MV Distribution Network (Portugal)..................................................... 14
Figure 3 – Production and Transmission System of Rhodes ............................................................................ 26
Figure 4 – Substation of Gennadi .................................................................................................................... 28
Figure 5 – Feeder R-22..................................................................................................................................... 28
Figure 6 – Feeder R-26..................................................................................................................................... 29
Figure 7 – Distribution network in Évora ......................................................................................................... 30
Figure 8 – Évora Substation ............................................................................................................................. 31
Figure 9 – F3 Feeder of Évora Substation. ....................................................................................................... 31
Figure 10 – Fault current contributions in case of protection blinding ........................................................... 34
Figure 11 – Equivalent per-phase distribution system without DG connection .............................................. 35
Figure 12 – Equivalent per-phase distribution system with DG connection ................................................... 35
Figure 13 – Ratio between main grid fault current contributions, with and without DG connection ............ 37
Figure 14 – Ratio between total fault currents, with and without DG connection ......................................... 39
Figure 15 – Fault current contributions in case of sympathetic tripping ........................................................ 40
Figure 16 – Equivalent per-phase system for the sympathetic tripping case ................................................. 41
Figure 17 – Ratio of the total fault current to the DG partial contribution ..................................................... 43
Figure 18 – Adaptive Protection Scheme for Medium Voltage distribution network ..................................... 44
Figure 19 – Flowchart of Smart Substation Controller concept for sympathetic tripping .............................. 45
Figure 20 – Auto-reclosing procedure during a transient fault [9] .................................................................. 48
Figure 21 – Auto-reclosing procedure during a permanent fault [9] .............................................................. 48
Figure 22 – DG-penetrated distribution network protected by recloser ........................................................ 49
Figure 23 – The first shot of a typical reclosing sequence during a fault ........................................................ 49
Figure 24 – Islanded mode of a distribution system ....................................................................................... 51
Figure 25 – Classification of islanding detection methods .............................................................................. 52
Figure 26 – Non–Detection Zone (NDZ) .......................................................................................................... 57
Figure 27 – Portuguese Fault Ride-through Voltage versus time curve .......................................................... 57
Figure 28 – Portuguese Fault Ride-through Reactive current injection curve ................................................ 58
Figure 29 – FRT protection function flowchart................................................................................................ 60
Figure 30 – Logic diagram of FRT protection function .................................................................................... 61
Figure 31 – FRT curve programmed in the digital relay .................................................................................. 61
Figure 32 – TPU S220 protection relay ............................................................................................................ 64
Figure 33 – Changing the active setting group in the local interface of the relay ........................................... 65
Figure 34 – Example of user-defined program that changes active setting groups ........................................ 67
Figure 35 – Testbed configuration; DI: Digital Input, DO: Digital Output ........................................................ 68
Figure 36 – The developed testbed in ICCS ..................................................................................................... 69
Figure 37 – The ICCS RTDS cubicle ................................................................................................................... 70
Figure 38 – Set-up of the ICCS digital protection system ................................................................................ 71
Figure 39 – Components of the ICCS Control Unit .......................................................................................... 74
Figure 40 – The developed DG-penetrated distribution network in RSCAD ................................................... 75
Figure 41 – Control scheme of simulated DG units in RSCAD ......................................................................... 75
Figure 42 – Single-phase to symmetrical three-phase current transformation in RSCAD .............................. 76
Figure 43 – Digital input blocks in RSCAD for monitoring the status of the two simulated breakers ............. 76
Figure 44 – Control blocks for voltage zero-crossing detection & fault regulation in RSCAD ......................... 77
Figure 45 – HIL tests by means of the ICCS testbed ........................................................................................ 78
Figure 46 – Relay secondary testing by means of the RTDS ............................................................................ 79
Figure 47 – Synoptic DC Schematic of the SEL-311B protection relay ............................................................ 80
Figure 48 – Synoptic DC Schematic of the SIMATIC S7-300 PLC ...................................................................... 80
Figure 49 – Adaptive selection of the proper setting group using the AcSELarator Quickset® ....................... 81
Figure 50 – Évora – Casinha feeders’ layout.................................................................................................... 83
6/97
Deliverable 4.3
Planning of Advanced System Protections
7/97
Deliverable 4.3
Planning of Advanced System Protections
List of Tables
Table 1 – Settings of phase overcurrent protection (Portugal) [62] ............................................................... 15
Table 2 – Settings of directional earth-fault overcurrent protection [62]....................................................... 17
Table 3 – Modes of operation of the auto-reclosing function [6] ................................................................... 20
Table 4 – Parameters of the rapid reclosing [1] .............................................................................................. 20
Table 5 – Parameters of the first slow reclosing [1] ........................................................................................ 21
Table 6 – Parameters of the second reclosing [1] ........................................................................................... 21
Table 7 – Protection scheme for DGs following option A [1] .......................................................................... 22
Table 8 – Protection scheme for DGs following option B [1] .......................................................................... 22
Table 9 – Installed DG per feeder of Rhodes Distribution System .................................................................. 27
Table 10 – Rhodes Wind Farms ....................................................................................................................... 27
Table 11 – Overcurrent protection relay settings of feeders R-22, R-26......................................................... 29
Table 12 – PVs found in F3 Feeder of Évora Substation. ................................................................................. 30
Table 13 – F3 Feeder protection relay settings. .............................................................................................. 32
Table 14 – Communication-based methods for LOM protection.................................................................... 52
Table 15 – Passive methods for LOM protection ............................................................................................ 54
Table 16 – Active methods for LOM protection .............................................................................................. 55
Table 17 – Specifications of the ICCS RTDS ..................................................................................................... 70
Table 18 – Specifications of the ICCS PLC ........................................................................................................ 73
Table 19 – Binary signals in the ICCS HIL testbed according to each operating state ..................................... 79
Table 20 – EFACEC TPU S220 Relay functions ................................................................................................. 82
Table 21 – Data of HV Grid .............................................................................................................................. 95
Table 22 – Data of Substation Transformer .................................................................................................... 95
Table 23 – Data of Distribution Lines .............................................................................................................. 95
Table 24 – Load Data ....................................................................................................................................... 96
Table 25 – Data of DG Interconnection Transformer ...................................................................................... 96
Table 26 – Data of DG Unit .............................................................................................................................. 96
Table 27 – Network feeder data ...................................................................................................................... 97
Table 28 – Network load ................................................................................................................................. 97
Table 29 – DG transformer data ...................................................................................................................... 97
8/97
Deliverable 4.3
Planning of Advanced System Protections
4Q Four Quadrant
CB Circuit Breaker
CT Current Transformer
DG Distributed Generation
EB Smart Meter
FE Frontend
HD Harmonic Detection
HI Harmonic Injection
9/97
Deliverable 4.3
Planning of Advanced System Protections
HIL Hardware-In-the-Loop
HV High Voltage
LV Low Voltage
MV Medium Voltage
NI Normally Inverse
PI Proportional Integral
PV Photovoltaic
RF Radio-Frequency
10/97
Deliverable 4.3
Planning of Advanced System Protections
SC Switchable Capacitor
SI Standard Inverse
VI Very Inverse
VS Vector Surge
VT Voltage Transformer
WF Wind Farm
WP Work Package
WT Wind Turbine
11/97
Deliverable 4.3
Planning of Advanced System Protections
1 Introduction
Description of the Task 4.3 “Planning of Advanced System Protections” from
the DoW:
Task 4.3 Planning of Advanced System Protections (Task leader: EFACEC; INESCP, ICCS, EDP, HEDNO)
Advanced protection system will be proposed by incorporating flexible schemes for distribution network protection and
grid interconnection protection of DG units, in order to minimise/avoid protection misoperation and failure. The
protection schemes will be selective to allow fault-ride-through capability to be adopted by all installed DG without
compromising selectivity in the detection of faults at the feeders where these units are installed. This will require the
identification of, and adoption of additional protection relays and protection strategies with adaptive settings, e.g.
ROCOF (Rate of change of Frequency), teleprotection, etc. In order to ensure required selectivity of different protection
relays, some of pre-defined settings may need to be changed taking into account the configuration of the network and
the presence of DG units in the grid, as well as the neutral to ground connection solution adopted in the distribution grid
(e.g., direct neutral to ground connection or connection through an impedance). The location and characteristics of
protection devices will be particularly investigated in order to assess the costs effectiveness of the advanced protection
functionalities and protection strategies. These new protection relays and protection strategies will be evaluated through
a range of characteristic tests on an RTDS (Real Time Power System Simulation) hardware / software simulation
platform where several failure conditions can be evaluated namely: unsuccessful reclosing sequences due to DG units
connected to faulted sections of the network; no operation of feeder protection due to protection blinding; loss of
directional criteria in relay coordination; change of protection reach and fault resistance coverage due to changes in
short circuit power.
• Failed reclosing
DG unit may interrupt the auto-reclosing sequence performed by the feeder relay. The reclosing settings used must be
coordinated with the operation of DG protection to avoid problems.
• Sympathetic tripping
It may occur when a fault is located outside the feeder including DG. In such a case, the DG unit contributes to the fault
and feeds a fault current ‘upstream’ towards the fault, which may trip the relay located at the beginning of the DG
feeder. Coordination algorithms for co-operation of feeder relays and DG protection will be developed.
• Protection blinding
The operation of feeder over current protection may become interrupted when DG unit is located between the fault point
and the feeding substation. To avoid increase of fault levels, selective coordination will be adapted.
• Loss-of-mains protection
DG units are not able to maintain an adequate level of quality in the network during unintended islanding. Islanding will
be detected by voltage and frequency relays located at the DG unit terminal. Methods based for instance on ROCOF
(rate of change of frequency) or vector surge will be developed to provide reliable islanding detection.
Because DG-units interfere with the protective system of the distribution grid, they should be immediately disconnected
in case of a fault, restoring the operation with only one source of supply and functioning the protective system as it was
designed to do. Under-voltage relay protective scheme will be proposed to detect the voltage dip propagating through
the grid and disconnect the DG-units.
12/97
Deliverable 4.3
Planning of Advanced System Protections
13/97
Deliverable 4.3
Planning of Advanced System Protections
28%
72%
Figure 1 – Phase To Phase vs. Earth Faults in the MV Distribution Network (Portugal)
3,5
Percentage of trips
3
2,5
2
1,5
1
0,5
0
150
220
290
360
430
500
570
640
710
780
850
920
990
1060
1130
1200
1270
1340
1410
1480
1550
1620
1690
1760
1830
1900
1970
10
80
14/97
Deliverable 4.3
Planning of Advanced System Protections
Portugal and according to [1], the IED protecting the MV feeder (main circuit
breaker) should have the following protection functionalities:
Operation Time
Level of detection 10 kV 15 kV 30 kV
– Top (s)
15/97
Deliverable 4.3
Planning of Advanced System Protections
corresponds to the time interval between the detection of the current violation and
the transmission signal to open the circuit breaker.
The phase overcurrent protection function (I>> and I>>>) should be blocked if
the percentage of second harmonic in phase current signals is higher than a pre-
defined value. The maximum ratio between the second harmonic and the
fundamental frequency component is 15% [1]. When a load is connected to the
distribution network a transitory phenomenon that produce inrush current and may
cause instantaneous trip of phase overcurrent protection can occur [2][3].
The phase overcurrent protection should also be able to trigger the reclosing
function (see Section 2.2.6) with rapid and/or slow reclosing of the circuit breaker
[4].
𝐼𝑜𝑝 = 2 𝐴
𝑇𝑀 = 0,4
where 𝐼𝑜𝑝 is the operational current, also designated as pick-up current, and 𝑇𝑀 is
the time multiplier. The minimum operation time of the large resistance earth-faults
protection should be limited to [1.23s; 2.53s]. According to [1] it is preferable to
use the value 1.23s.
3 IEC is the International Standards and Conformity Assessment for all electrical, electronic and
related technologies.
16/97
Deliverable 4.3
Planning of Advanced System Protections
The setting of this protection depends on the neutral and the following settings
are recommended:
Reactance Reactance
Resistance Neutral Isolated
300 A 1000 A
Iop (A) 40 40 40 2
α (°) 10 15 45 90
𝑉 +𝑉 +𝑉
where 𝑉ℎ = 𝐴 𝐵 𝐶 corresponds to the zero sequence voltage and 𝑉𝑁 is the
3
maximum nominal voltage.
According to [1], for the values calculated for the reactance 300 A and 1000 A,
it was considered a relationship X/R of 3 [5]. In case of greater values, directional
earth-phase overcurrent may not detect the fault.
Earth-Fault Overcurrent:
The earth-fault overcurrent protection function is similar to the previous
function. The difference lies on the fact that this one does not have directionality
and also the setting of this protection function does not depend on the neutral
system of the installation. According to [1], the following settings should be used:
𝐼𝑜𝑝 = 90 𝐴,
𝑡𝑜𝑝 = 0.15 𝑠.
17/97
Deliverable 4.3
Planning of Advanced System Protections
capacitive current [1]. According to [5], at a substation with a neutral reactance for
300 A, it is considered a maximum capacitive contribution of 100 A. If the
substation has isolated neutral it can also be considered the previous value. On
the other hand, if the neutral regime of the substation is limited by a reactance for
1000 A, the operational current will be three times bigger than the one presented.
According to [1], the broken conductor function does not provoke the trip of the
associated circuit breaker, but instead it is used for issuing an alarm to the control
centre.
Before closing a circuit breaker, it must first be verified if the two network
sections that are going to be reconnected are in synchronism conditions, meaning
that the difference between the two voltage signals in terms of magnitude, phase
angle and frequency is within pre-defined tolerances. The lack of synchronism
between both sides of the circuit breaker, typically a busbar and a line (or
transformer), or two different busbars, may seriously compromise power system
stability when the circuit breaker is closed.
18/97
Deliverable 4.3
Planning of Advanced System Protections
In case there are voltage detectors at the HV/MV substation they should have
the following settings [1]:
2.2.6 Reclosing
Reclosing consists on an automatic control for closing the circuit breaker, after
a trip provoked by the actuation of any protection function. The primary objective
of this function is to eliminate the non-permanent faults (70% to 80% of the total
faults). It allows automatic service reestablishment after short time interruptions.
This way, it is possible to reduce the number of interruptions of the network,
without having to isolate the line in case of a non-permanent fault. However, in
case of a permanent fault the circuit breaker should be able to isolate the faulty
line.
According to [6], there are two types of reclosing in the distribution network:
rapid reclosing and slow reclosing. The rapid reclosing is characterised by having
a reduced time of isolation, normally not over 0.4 seconds. The slow reclosing is
characterised for having an isolation time in the order of tens of seconds and not
over 120 seconds. The same author also defines the possible modes of operation
for these types of reclosing, as presented in Table 3.
19/97
Deliverable 4.3
Planning of Advanced System Protections
0 Inhibited reclosing
4 1 rapid reclosing
2 1 slow reclosing
3 2 slow reclosings
Interlock time 60
4
Distribution System Operator is responsible for ensuring the exploitation, maintenance, planning
and construction of the distribution network, among others.
20/97
Deliverable 4.3
Planning of Advanced System Protections
Isolation Time 15
Interlock time 60
Isolation Time 30
Interlock time 60
The ownership entity of the receiving network is responsible for the setting of
the interconnection protection functions. The Portuguese DSO adopted two
5
The production of electricity of special regime producers is an activity, under special legal
regimes, of the production of electricity, namely through the use of renewable endogenous
resources or technologies that produce both heat and electricity.
21/97
Deliverable 4.3
Planning of Advanced System Protections
different protection schemes for DGs. Thus, the DG developers have the
possibility to choose either one or the other protection scheme, usually designated
as option A (on Table 7) and option B (on Table 8).
6
In case the normal operating regime of the interconnection substation is neutral isolated then
Uo > is 50%Vn .
7
In case the normal operating regime of the interconnection substation is neutral isolated then
Uo > is 50%Vn with top=1.65s and Uo ≫ deactivated.
22/97
Deliverable 4.3
Planning of Advanced System Protections
Vblock 20%VN -
In case of a fault, option A isolates the DG unit instantaneously. This way the
DG is disconnected before the reclosing of the circuit breaker of the MV feeder.
This avoids a situation of parallelism, due to rapid reclosing (maximum duration of
300 ms), between the network and the DG unit, in which synchronism conditions
may not be in place. However, in case of a fault on an adjacent line to the one that
contains the DG unit, the circuit breaker at the point of interconnection may
suddenly actuate. This may happen because the protection of the DG unit sees
the voltage drop, due to the fault, provoking an unnecessary trip of the circuit
breaker.
The time since the violation of the limit and the transmission of the command
signal to the circuit breaker, for the over- and underfrequency protection function is
0.07 seconds, and for the other protection functions is 0.03 seconds [7].
The voltage protection function allows the disconnection of the DG unit when
its terminal voltage exceeds the pre-defined limits. When the superior limit of the
8
Ilig (in Portuguese nomenclature) corresponds to the current at the point of interconnection
between the DG and the distribution network.
23/97
Deliverable 4.3
Planning of Advanced System Protections
voltage is exceeded the overvoltage protection function actuates and the circuit
breaker at the point of interconnection of the DG to the network opens. On the
other hand, if the measured voltage drops below the inferior limit stipulated, then
the undervoltage protection function actuates and the DG unit is disconnected by
the opening of the circuit breaker.
The variation of the frequency means that the generation and consumption are
unbalanced. This variation can cause serious problems or even damage the
equipment connected to the network and the equipment of the network itself [2].
The overfrequency and underfrequency protection functions trips the circuit
breaker at the point of connection of the DG unit to the network, when the
frequency upper and lower limits are exceeded, respectively.
The overcurrent protection function is used to protect the DG unit and the
point of connection to the network in case of overload and emerging high currents
24/97
Deliverable 4.3
Planning of Advanced System Protections
due to short-circuits. In this cases if the current is superior to the maximum limit
stipulated, the overcurrent protection function sends an order to open the circuit
breaker isolating the DG unit.
25/97
Deliverable 4.3
Planning of Advanced System Protections
26/97
Deliverable 4.3
Planning of Advanced System Protections
SUBSTATION FEEDER
Installed Installed Installed
Number Number
Name Capacity Name Capacity Capacity
of PVs of WFs
DG (kW) PV (kW) WF (kW)
R-26 2 199.59
R-27 2 199.30
R-28 1 99.11
AFANTOU 12937.28
R-32 6 594.13
R-34 8 795.14
R-36 1 11050
R-22 20 1993.63 1 3000
R-23 8 756.51
R-24 2 199.20
GENNADIOU 11682.58 R-25 3 204.93
R-26 56 3578.31
R-28 1 4950
R-29 1* 4950
R-29 3 299.88
R-31 3 299.64
R-33 1 99.96
IALYSOU 2676.43 R-34 17 1683.86
R-35 7 218.69
R-36 3 59.40
R-37 1 15.00
R-26 2 107.82
R-28 2 119.64
RODINIOU 333.75
R-29 1 99.36
R-38 1 6.93
R-22 2 144.66
R-23 16 1515.30
R-24 27 2685.90
SORONIS 18235.14 R-25 18 1789.72
R-26 1 99.56
R-27 1** 6000
R-28 1** 6000
TOTAL 45865.18 SUBTOTALS 213 17865.18 4 31000
* Future Installation
** One WF with total installed capacity 12 MW
Installed Capacity
No Location Substation Feeder
(kW)
1 Archipoli, Municipality of Afantou 11050 Afantou R-36
Chalatas, Municipality of South
2 3000 Gennadiou R-22
Rhodes
6000 R-28
3 Pithanitis, Municipality of Attavirou Soronis
6000 R-27
Vigla Kattavias, Municipality of
4 4950 Gennadiou R-28
South Rhodes
27/97
Deliverable 4.3
Planning of Advanced System Protections
28/97
Deliverable 4.3
Planning of Advanced System Protections
Reclosers,
Fuses,
Sectionalizers.
The protection settings of feeders R-22 and R-26 are given in Table 11.
R-22
600/5 ZIV / CPI – T2R 162 0.14 NI 390 100 36 0.7 VI 120 100 3
(P220)
R-26
600/5 ZIV / CPI – T2R 162 0.1 NI 360 100 36 0.7 VI 120 100 3
(P260)
29/97
Deliverable 4.3
Planning of Advanced System Protections
The chosen feeder, F3, has a total length of 4.9 km, 26 MV/LV Substations
with an installed power of 14.770 kVA. Spread through the grid are 7 PVs
totalising an installed power of 23 kW.
30/97
Deliverable 4.3
Planning of Advanced System Protections
31/97
Deliverable 4.3
Planning of Advanced System Protections
Fuses;
Sectionalizers.
EFACEC
F3 400/5 400 1,0 800 0,5 2000 0,1
TPU S220
32/97
Deliverable 4.3
Planning of Advanced System Protections
33/97
Deliverable 4.3
Planning of Advanced System Protections
BUS MV
BUS 1 BUS 2
HV GRID If,gridDG < If,gridno DG
R1
IfDG > Ifno DG
If,DG
LOAD2
DG1 LOAD1
The protection blinding issue can be quantified, investigating the major factors
that affect its intensity, such as DG capacity, DG location and fault location. Short-
circuit current and voltage values at any node of the network can be calculated
using the superposition theorem, which sums the pre-fault values with the variation
of currents or voltages during the short circuit. The faulted network is assumed to
be unloaded before occurrence of the fault [17], [18], since the changes in node
voltages and branch currents are much higher than their pre-fault values. In the
absence of loads, no pre-fault (load) currents flow, and there are no voltage
differences across the branch impedances. Thus, all bus voltages throughout the
network are equal to V f , the pre-fault voltage at the fault point.
34/97
Deliverable 4.3
Planning of Advanced System Protections
BUS 1 BUS 2 Vf
ZSys ZL Vf ZTh
no DG If,gridno DG = Ifn
If,grid = Ifno DG
BUS 1 BUS 2
ZSys ZL Vf
If,gridDG IfDG
ZDG
If,DG
Vf
I no DG
I no
f ,grid
DG
. (1)
Z Sys Z L
f
Vf
I DG
f . (2)
Z Sys Z DG
ZL
Z Sys Z DG
Z Sys Z DG
From (1) and (2) it can be deduced that I DG I no DG
since Z Sys ,
Z Sys Z DG
f f
35/97
Deliverable 4.3
Planning of Advanced System Protections
The fault current contributions from main grid and DG plant can be calculated
as below, by means of the Kirchhoff’s current and voltage laws, considering the
main grid and DG pre-fault voltages equal to V f , as mentioned previously:
f ,grid I f ,DG I f ,
I DG DG
(3)
V f Z Sys I DG
f ,grid Z DG I f ,DG V f 0 Z Sys I f ,grid Z DG I f ,DG ,
DG
(4)
V f Z L I DG
f Z DG I f ,DG 0. (5)
V f Z L I DG
I f ,DG
f ,grid
, (6)
Z L Z DG
Vf
f ,grid
I DG . (7)
Z
Z Sys L 1 Z L
Z DG
f ,grid I f ,grid
I DG no DG
Comparing (1) and (7), it can be inferred that since
Z
Z Sys L 1 Z L Z Sys Z L . To sum up, the previous analysis demonstrates
Z DG
that the total fault current increases while the mains contribution decreases, when
a conventional DG unit is connected to the distribution network, revealing the
major issue of feeders’ protection blinding.
Moreover, DG capacity and location, as well as fault location, influence the
performance of protective devices and the probability of protection blinding
occurrence. To investigate the impacts of these factors on short-circuit currents,
the DG and distribution feeder impedances are expressed in proportion to main
grid impedance [16], as below:
Z DG mZ Sys , (8)
Z L nZ Sys . (9)
The ratio of the mains contribution, with and without DG, is derived from (1),
(7)–(9) as follows:
Vf
Z
Z Sys L 1 Z L
m mn
DG
I f ,grid
Z DG . (10)
I no DG
f ,grid
Vf m n mn
Z Sys Z L
36/97
Deliverable 4.3
Planning of Advanced System Protections
m mn
Figure 13 shows the 3-D plot of ratio k (m,n) against factors m
m n mn
and n.
Figure 13 – Ratio between main grid fault current contributions, with and without DG connection
As can be observed in Figure 13, when n=0 (fault at the point of common
coupling, PCC), the ratio k (m,n) is equal to 1, since the same short-circuit current
will be fed by the grid substation in both cases. Considering now the coefficient n
constant (constant value of line impedance), the ratio k (m,n) decreases with
decreasing m. Indeed, if a large DG plant with considerably low impedance is
connected to the feeder, there will be further reduction of substation fault current
contribution in comparison with the case of a smaller DG unit. Moreover, if m is
constant, it is verified that, as the line impedance or the fault distance from the
substation increases the ratio k (m,n) decreases.
I no DG
I PU
f ,grid
, (11)
N
37/97
Deliverable 4.3
Planning of Advanced System Protections
where, I PU represents the pickup current setting of the overcurrent relay, and N is
a safety factor (usually N 3 ), which corresponds to the desired protection
sensitivity.
I DG m mn
N slim ,
f ,grid
(12)
I PU m n mn
Vf
Z Sys Z DG
ZL
I DG Z Sys Z DG (1 m)n m 1
f
. (13)
I no
f
DG
Vf (1 m)n m
Z Sys Z L
(1 m)n m 1
The ratio l m,n is plotted against m and n in Figure 14. It is
(1 m)n m
evident that the total fault current increases rapidly as the impedances of the DG
unit and the distribution feeder decrease. On the other hand, if m,n 1 , then l 1 ,
which means that there is no considerable variation in the fault current despite the
DG presence.
38/97
Deliverable 4.3
Planning of Advanced System Protections
Figure 14 – Ratio between total fault currents, with and without DG connection
39/97
Deliverable 4.3
Planning of Advanced System Protections
Considering that the relay installed at the terminals of the DG unit cannot
foresee the origin of the fault event, it becomes difficult to differentiate the situation
where the fault is located in the feeder where the DG is connected to and the
situation where the fault is located in a neighbouring feeder. The rationale behind
this task consists on creating an intelligent protection scheme in order to avoid
sympathetic tripping situations.
Sympathetic tripping refers to the undesirable operation of the feeder relay
due to unbalanced or high-load condition, which frequently follows an out-of-zone
fault [19], [20], or due to DG backfeed to a fault on an adjacent feeder [11], [12],
[16], [21] and [22]. This phenomenon is also called false tripping [11], [16], and
belongs to the wide class of nuisance tripping problems triggered by various root
causes (e.g. motor starting, magnetising inrush current during transformer
energisation, cold-load pickup, voltage sag or swell etc.). In this report, we will
focus on the sympathetic tripping scenario, encountered by the feeder relay due to
upstream DG fault current contribution for faults beyond feeder protection zone.
As it has been discussed in recent literature, DG units can cause false tripping
and undesirable disconnection of an adjacent healthy feeder. The basic principle
of sympathetic tripping can be explained in Figure 15, where a fault occurs at
Feeder 2 and the DG unit connected to Feeder 1 feeds the short-circuit through
the substation bus. If the DG contribution is particularly large, the tripping
mechanism of circuit breaker R1 may be initiated before R2 takes action and
clears the fault. This is possible when non-directional overcurrent relays are used
for feeder protection, which cannot discriminate the change to fault current
direction (reverse fault). The utilization of non-directional overcurrent relays is a
long-established protection practice for most of distribution utilities, due to their
single-fed radial nature, unlike modern multi-source distribution systems with bi-
directional current flow. Therefore, the installation of numerical directional
overcurrent relays at main feeders with embedded DG could be a cost-effective
solution to this problem.
BUS 1
R1 FEEDER 1
If,DG
HV GRID BUS MV
LOAD1
DG1
BUS 2
DG
If,grid
R2 FEEDER 2
40/97
Deliverable 4.3
Planning of Advanced System Protections
ZDG
BUS 1 If,DG
ZL1
Vf
ZSys ZL2
In the initial operating condition without DG presence, the total fault current,
which is fed only by the main system, is:
Vf
I no DG
I no
f ,grid
DG
. (14)
Z Sys Z L 2
f
41/97
Deliverable 4.3
Planning of Advanced System Protections
Vf
I DG . (15)
f
Z Sys Z DG Z L1
ZL2
Z Sys Z DG Z L1
Vf
I DG
f . (16)
Z Sys Z DG
ZL2
Z Sys Z DG
The main system and DG contributions to the fault are obtained using the
Kirchhoff laws:
Vf
f ,grid
I DG , (17)
Z
Z Sys 1 Sys ZL2
Z DG
Vf
I f ,DG . (18)
Z
Z DG 1 DG Z L 2
Z Sys
impedance of Feeder 2. For example, the closer fault location to the substation the
higher fault current contributions from the main system and the DG unit.
Furthermore, the ratio of DG fault current contribution to the total fault current can
be obtained combining (8), (9), (16) and (18), as follows:
Vf
Z
Z DG 1 DG Z L 2
Z Sys m n mn
I f ,DG
. (19)
I DG
f
Vf (1 m)m (1 m) 2 n
Z Z
Z L 2 Sys DG
Z Sys Z DG
m n mn
The ratio r m,n is plotted in Figure 17 as a function of
(1 m)m (1 m)2 n
factors m and n. As can be observed, a small value of m (ratio of DG to system
impedance) leads to a DG short-circuit contribution close to the total fault current,
since m 0 when r 1 , according to (19). In this case, feeder relays R1 and R2
(Figure 15) may have almost identical tripping times, if the same pickup current
and time dial settings are selected. Even worse, R1 may trip faster than R2, if
42/97
Deliverable 4.3
Planning of Advanced System Protections
43/97
Deliverable 4.3
Planning of Advanced System Protections
tripping from happening, considering the real-time state of the network. The SSC
also interacts with the centralised SCADA/DMS9.
SCADA/DMS (Figure 18) represents the control centre that performs network
assessment tasks over the whole network. SCADA allows a utility operator to
monitor and control processes that are distributed among various remote sites.
The operational assessment carried out at the SCADA/DMS level determines in
which mode of operation the SSC will be, e.g. by having information about the
equipment status, such as circuit breakers, the network state and its configuration.
The SCADA/DMS assigns a tag to the SSC stating its mode of operation. By
receiving such tag the SSC becomes aware about is role for protection
coordination setup: disabled, enabled or advisory (see Section 4.2.2.1).
9
Supervisory Control and Data Acquisition/Distribution Management System
44/97
Deliverable 4.3
Planning of Advanced System Protections
In a) the SSC collects certain measurements from the network. It reads the
following variables:
45/97
Deliverable 4.3
Planning of Advanced System Protections
The currents and voltages are necessary to determine the load in the system.
To make an accurate analysis of the short-circuit current, the actual load in the
system should be considered.
The most pertinent data for the analysis of a short-circuit is the capacity of the
DG and the technology of the machines. The higher DG capacity, the more likely it
is for sympathetic tripping to happen, due to higher current contribution from the
DG to the fault. Depending on the type of DG source which will have a smaller or
bigger contribution to the fault, being synchronous generators the ones that most
contribute to a fault. This way, it is necessary to assess the total capacity of the
machines working at the wind park and the type of technology of those machines.
These data comes from the SCADA/DMS and is only necessary to be available to
the SSC when there are changes in the number of machines working at the wind
park (dotted lines in Figure 18).
In b) the SSC performs a short-circuit analysis for the worst case scenario: a
three-phase fault at the beginning of line 2 (Figure 18). The short-circuit calculation
is made with the measurements collected by the SSC and with the rest of the
parameters of the network, e.g. line parameters, that are pre-programmed in the
SSC.
While enabled, the SSC is authorised to perform the adaptive protection. For
the network in Figure 18 this will consist in the changing of the setting group of
protective relay R1 or protective relay R2 or both, depending on what it is required
to prevent sympathetic tripping. While in advisory mode, and if the SSC detects a
situation of potential sympathetic tripping, then the SSC sends a signal to the
SCADA/DMS stating that the change of setting group should be performed. An
authorised user will then remotely perform, or not, that change according to the
information provided and his experience. While in disabled mode, the SSC only
reports to the SCADA/DMS the telemetry in the network. This function is also
performed in the others situations described. The SSC exchanges data with the
SCADA/DMS independently of the SSC mode of operation.
46/97
Deliverable 4.3
Planning of Advanced System Protections
47/97
Deliverable 4.3
Planning of Advanced System Protections
48/97
Deliverable 4.3
Planning of Advanced System Protections
BUS
HV GRID MV
If,grid
Rec1 Rec2
If,DG
DG1
1
If (kA)
0
DG must disconnect here
-1
-2
-3
-4
-5
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5
t(sec)
The potential failure of reclosing to clear the fault means that some of the
customers will now see a sustained interruption, whereas they should have been
subjected to only a momentary one. Thus, the reliability of the power delivery
system is slightly degraded. A more complicated issue is the fact that many utilities
49/97
Deliverable 4.3
Planning of Advanced System Protections
use “instantaneous” reclosing for power quality purposes. This reclosing interval is
nominally 0.5 s, but can be as short as 0.2 s. The utilities that use this short
interval intend to improve the power quality for their customers. However, this
practice increases the probability that the DG will not disconnect in time.
Removal of the DG plants is normally accomplished by the operation of an
underfrequency (81), undervoltage (27), or reverse power relay (32), which tends
to have longer tripping times. As the operating time for these devices may be
slower to remove the connected generator than the relays that detected and
cleared the fault, auto-reclosing times may need to be extended to allow these
devices to operate. We recommend against using instantaneous reclose on feeder
sections that contain synchronous-based DG unit. A reclosing interval of 1 s or
more would be preferable. This will dramatically reduce the chances of DG failures
to separate in time, but will also result in decreased power quality to some
customers. On the other hand, generation that is connected to the system by
means of a power electronic converter can be self-protecting. Such units can be
disconnected from the system before the re-energisation of the circuit, and
therefore an auto-reclosing process would not be a matter of concern.
Furthermore, the active power unbalance during the dead time of the reclosing
sequence, can lead to frequency variation in the islanded part of the distribution
grid, and generators may drift away from the synchronism with respect to the main
system [16], [21]. In this scenario, a reclosing attempt would couple two
asynchronously operating systems. For a rotating machine, which is the most
common type of generator, owners can expect damage to the shaft, the coupler,
and the prime mover, due to out-of-phase switching. Power electronic converters
have much less inertia and would normally be less susceptible to out-of-phase
reclosing, assuming proper protection against current surges. Moreover,
conventional reclosers are designed to reconnect the circuit only if the substation
side is energised and the opposite side is unenergised. In case of DG integration,
there would be active sources on both sides of the recloser, thus hampering its
proper operation.
50/97
Deliverable 4.3
Planning of Advanced System Protections
MAIN
BUS MV
SYSTEM
OPEN
CLOSED
The utility might not be able to control the voltage and the frequency in the
island, causing probably damage to owner’s equipment.
Utilities can be found liable for electrical damage to owner’s equipment
connected to their lines, which may result from voltage or frequency
excursions outside the acceptable ranges.
Islanding may create a hazard for utility personnel or the public, since a
distribution line, assumed to be disconnected from any power source, remains
energised.
Out-of-phase reclosing into an island may cause irreparable damage to the
owner’s property or to distribution elements.
Islanding may interfere with the manual or automatic restoration of normal
service.
51/97
Deliverable 4.3
Planning of Advanced System Protections
The basic operating principles of islanding detection techniques are, firstly, the
monitoring of main system and DG operating parameters, and secondly, the
decision on whether there is an islanding situation or not, based on the parameter
variations. Anti-islanding methods are mainly classified as remote and local, with
local methods further categorised as passive and active, as shown in Figure 25.
ISLANDING DETECTION
PASSIVE ACTIVE
52/97
Deliverable 4.3
Planning of Advanced System Protections
53/97
Deliverable 4.3
Planning of Advanced System Protections
54/97
Deliverable 4.3
Planning of Advanced System Protections
ACTIVE METHODS
OPERATING CONCEPT
[26], [27], [29]–[31]
Harmonic Injection Typically, a small current at a certain harmonic order is injected into
the grid and the resulting voltage harmonic is measured to detect the
(HI) islanding event.
55/97
Deliverable 4.3
Planning of Advanced System Protections
PDG
VPCC VPCC . (20)
PLOAD
If PDG PLOAD , an increase in the voltage amplitude occurs, while if PDG PLOAD the
voltage amplitude decreases. Respectively, the reactive power is given by:
1
' C VPCC
.
2
QLOAD QDG (21)
' L
The following equations describe the power imbalance in the system after a
LOM event:
The worst case for islanding detection arises when there is balance of the
active and reactive power, i.e. P Q 0 , and thus there is no change in
voltage amplitude and frequency. It is straightforward that a small P results in an
insufficient change in voltage amplitude, whereas a small Q leads to an
inadequate change in frequency to effectively prevent islanding. It is possible to
calculate the NDZ area from the mismatches of active and reactive power, and
then to set proper threshold values for frequency and voltage elements. However,
the possibility of P and Q falling into the NDZ can be considerably high.
Consequently, the standard voltage and frequency protection elements are
generally considered to provide insufficient anti-islanding protection, and thus they
should be combined with other islanding detection methods.
56/97
Deliverable 4.3
Planning of Advanced System Protections
57/97
Deliverable 4.3
Planning of Advanced System Protections
58/97
Deliverable 4.3
Planning of Advanced System Protections
59/97
Deliverable 4.3
Planning of Advanced System Protections
60/97
Deliverable 4.3
Planning of Advanced System Protections
a
voltage Reset
Comparator
a<b
b
Vpick
t1
a Breaker
voltage Tripping
Comparator AND
a<b Signal
b
V1
1
OR
n
Reset
tn
a
voltage
Comparator AND
a<b
b
Vn
61/97
Deliverable 4.3
Planning of Advanced System Protections
Adapt the fault detection thresholds to the actual short-circuit levels in each
location, according for instance to the topology of the distribution network
and the presence of distributed generation.
Desensitise protection functions according to the amount of distributed
generation in the same feeder, which can largely vary during a relatively
short time period.
Adapt the protection behavior to changes in the type of neutral connection
(for example, from low-impedance to ungrounded neutral when the neutral
reactance is disconnected).
Activate the directional element or change the direction of protection
functions according to the power flow in the feeders.
Coordinate the protection functions of the substation relay with other
downstream devices, such as reclosers, sectionalizers or fuses, located
along the Medium Voltage lines and in the MV/LV substations, and
62/97
Deliverable 4.3
Planning of Advanced System Protections
63/97
Deliverable 4.3
Planning of Advanced System Protections
64/97
Deliverable 4.3
Planning of Advanced System Protections
The active setting group for each group of functions can be changed in one of
several possible ways:
Manually by the user in the local interface of the protection relay (both the
display and the web interface).
This option should be used mainly for initialisation of the active setting
group, during testing or in case of maintenance actions or other user
intervention.
Figure 33 – Changing the active setting group in the local interface of the relay
65/97
Deliverable 4.3
Planning of Advanced System Protections
By issuing a remote control from the control center, using the SCADA/DMS
system.
Besides providing remote manual control over the active setting groups,
this method also enables the automatic redefinition of protection settings
based on the network configuration and a set of relevant entities as well as
other influencing factors (for example, weather condition) that can be
accessed at the SCADA level.
66/97
Deliverable 4.3
Planning of Advanced System Protections
67/97
Deliverable 4.3
Planning of Advanced System Protections
6 Testbed integration
In recent years, modern adaptive protection schemes, capable of addressing
all the previous protection challenges, are being developed by protection
engineers and researchers. Adaptive protection has been defined in [33] as “a
protection philosophy which adjusts the settings of various protection functions in
order to make them more attuned to prevailing power system conditions”. For this
reason, the functionality of adaptive schemes is based on using multiple groups of
protection element settings, as has been described in relative literature [34]–[38].
Low-Level Interface
Voltage & Current Phasors
DI/DO
24Vdc
AUXILIARY RELAYS
POWER SUPPLIES
24Vdc 48Vdc
68/97
Deliverable 4.3
Planning of Advanced System Protections
In this section, the various components constituting the developed testbed are
presented, and their hardware specifications are outlined.
69/97
Deliverable 4.3
Planning of Advanced System Protections
70/97
Deliverable 4.3
Planning of Advanced System Protections
71/97
Deliverable 4.3
Planning of Advanced System Protections
programmable output contacts, and also an alarm output contact to implement the
required control schemes.
In our application, the SEL-311B relay undertakes the supervision and
protection of a specific distribution feeder, adapting properly its setting group in
case of change in the network configuration.
The SEL-587 digital relay provides current differential protection combined
with two groups of full-featured overcurrent elements, and is commonly used to
protect two-terminal power equipment (e.g. two-winding power transformers,
generators, large motors, reactors etc.) [43]. Moreover, the SEL-587 package has
two optoisolated inputs, four programmable output contacts, and also an alarm
output contact for logic schemes. The two groups of overcurrent elements
provided by this protective device include:
72/97
Deliverable 4.3
Planning of Advanced System Protections
73/97
Deliverable 4.3
Planning of Advanced System Protections
The model of the distribution network under examination was designed in the
RSCAD environment, and used in a series of simulations. It represents a simplified
single-phase configuration of the Rhodes HV/MV Substation “Gennadi”, and its
outgoing feeders R-22 and R-26. The developed distribution network consists of
two feeders, with distributed generation and loads. The network parameters can
be found in Appendix A.
The distributed generation, either synchronous-based or inverter-interfaced,
was modelled as a controllable current source. In case of synchronous-based DG
unit, a current source with equivalent short-circuit behaviour was derived, due to
the small number of single-phase nodes available. The setpoint of DG units
changes according to the state of the system (whether the fault was active or not),
employing a phase-locked loop (PLL). The bus loads were modelled as constant-
impedance lumped loads. Moreover, the option of simulating symmetrical (three-
phase) short circuits at all buses was added, as can be seen in Figure 40.
A current transformer (CT) was installed at the beginning of each feeder (CTA
and CTA2), to monitor the flowing current, and feed its corresponding hardware
protection relay. The ratios of CTA and CTA2 were taken equal to 800/5 and
800/1, respectively.
74/97
Deliverable 4.3
Planning of Advanced System Protections
Figure 41 shows the control scheme, which imposes the setpoint and
regulates the power production of the connected DGs. The setpoint of simulated
DG units is also used to determine their circuit breaker status, which is the main
information needed by the adaptive protection algorithm.
75/97
Deliverable 4.3
Planning of Advanced System Protections
The hardware relays of the proposed testbed are fed with three-phase current
phasors in their input, in contrast to the modelled system which is an equivalent
single-phase network, calculating and supplying only one-phase current signals.
This restriction can be overcome with the derivation of two additional current
signals delayed by 120o and 240o with reference to the calculated one, forming a
set of symmetrical current phasors, Figure 42. Thus, the simulation of three-phase
short circuits at buses and along lines, as well as the testing of hardware relays
performance under such fault conditions, is achieved.
Figure 43 – Digital input blocks in RSCAD for monitoring the status of the two simulated breakers
76/97
Deliverable 4.3
Planning of Advanced System Protections
Last but not least, the symmetrical fault conditions were modelled with
adjustable duration and time of occurrence. Hence, the user has the flexibility of
customising the nature of the fault to be simulated. Furthermore, a zero-crossing
detection method for the node voltages was implemented. Making use of this
technique, the fault was always applied to the simulated electrical network when
the voltage waveform was crossing the zero voltage value. In Figure 44, the
implemented control circuits are illustrated.
Figure 44 – Control blocks for voltage zero-crossing detection & fault regulation in RSCAD
77/97
Deliverable 4.3
Planning of Advanced System Protections
and PHIL is the power exchange between the HuT and the simulated system. As a
result, in case of PHIL, a power amplifier is required for the interconnection of the
RTS with the power equipment.
Concerning the ICCS testbed, the implemented HIL testing configuration is
illustrated in Figure 45, where the simplified distribution grid is simulated by the
RTDS and the outgoing feeders are protected by the hardware relays.
78/97
Deliverable 4.3
Planning of Advanced System Protections
simulated circuit breaker in RTDS, in order to clear the fault. The previous
description is made clear by the schematics in Figure 47 and Figure 48.
Table 19 – Binary signals in the ICCS HIL testbed according to each operating state
79/97
Deliverable 4.3
Planning of Advanced System Protections
+ 48 V DC
IN IN IN IN IN IN OUT
SEL-311B 101 102 103 104 105 106 101
- 48 V DC
RTDS
TRIP CB
+ 24 V DC
RTDS OUTPUT Bit ‘1’ Bit ‘2’ Bit ‘3’ Bit ‘4’
BINARY STRING
SIMATIC DI DI DI DI DO DO DO DO DO
1 2 3 4 1 2 3 4 5
S7-300
- 24 V DC
80/97
Deliverable 4.3
Planning of Advanced System Protections
Figure 49 – Adaptive selection of the proper setting group using the AcSELarator Quickset®
81/97
Deliverable 4.3
Planning of Advanced System Protections
For the sake of the closed-loop tests performed in this task only phase
overcurrent (50/5) and phase undervoltage (27) functions should be used.
82/97
Deliverable 4.3
Planning of Advanced System Protections
83/97
Deliverable 4.3
Planning of Advanced System Protections
Feeder 1
DG
Load 1
Feeder 2
Load 2
Figure 51 – Simplified Distribution network modelled in RTDS
84/97
Deliverable 4.3
Planning of Advanced System Protections
Vdc
Pgen
Gr
id
Vdc Id
max
The INESC Porto RTDS testbed schematic is illustrated in Figure 53. The
network modelled case was modelled in the RTDS software, the RSCAD. Then it
is compiled and sent to the RTDS hardware simulator. Additionally to the grid
model, the user defines the outputs to be delivered to external devices, allocating
processors’ tasks to these I/O function. For this specific case, in order to
interconnect the digital protective relay, three phase voltage and current
measurements were delivered at the RTDS output socket.
The RTDS output signals come limited to ±10V. Then, the amplifier is
responsible to adapt these signals to the adequate range (according to user
adjustment) to be used as input of the EFACEC relay. The EFACEC relay was
programed accordingly to the test with the respective protection functionality and
the respective parameterisation. The relay output (tripping signal) interacts with
the simulation by controlling the position of the DG connection line breaker
(opened or closed).
85/97
Deliverable 4.3
Planning of Advanced System Protections
RTDS
Simulator
3ph voltage and Amplified voltage
current signals Voltage & Current and current signals
Amplifier
EFACEC
S220
DG
Load 1
Load 2
To test the SSC concept a real time closed-loop test with a commercial
protective relay was set. The commercial protective relay used was EFACEC TPU
S220. Figure 54 represents the interaction between the components involved in
the closed-loop test.
Figure 54 shows the bidirectionality between the software and the simulator. As
mentioned before, it is possible to send command orders to the simulation and
receive the results from the simulation running in the simulator. The simulator has
an analogue connection with the relay through which it sends the required
analogue signals. It also has a digital connection with the relay that allows digital
86/97
Deliverable 4.3
Planning of Advanced System Protections
There are seven conductors coming out from the simulator. Three of them
correspond to each phase voltage from the MV busbar, and the other three
correspond to each phase currents of the line protected by the corresponding
relay. These analogue signals are inputs to the digital relay, allowing it to monitor
the voltage and current in the MV feeder. The last signal coming out from the
simulator corresponds to the control digital signal that makes the change of setting
group ordered by the SSC when the conditions for that are in place (see
Section 4.2.2.1). The signal coming out from the relay corresponds to the digital
signal sent by the relay to open the circuit breaker in case there is a violation of
any limit of the protection functions. The phase overcurrent protection function was
configured to be the only one active in the commercial relay since it is the only
protection function necessary to perform the required study.
87/97
Deliverable 4.3
Planning of Advanced System Protections
88/97
Deliverable 4.3
Planning of Advanced System Protections
7 KPI Analysis
According to Deliverable 2.4 of the SuSTAINABLE Project (KPI Assessment
Methodology) the SF9 functionality has impacts on Power Quality (KPI 5),
Reduction of DER due to congestion (KPI 7) and Optimized use of assets (KPI 8).
The KPI quantitative analysis depends on the amount of unwanted trips or
undetected faults that may occur in the network. The dependence of a large
number of variables ranging from network planning procedures, type of DER
technology, inverter short-circuit behaviour lack of standardization, type of faults,
location of faults and economical drivers for DER installation does not allow for an
accurate estimation of the number of unwanted trips or undetected faults.
Regarding Power Quality impact, the loss of a large amount of DER from the
network will cause an undervoltage over the remaining network.
If issues like sympathetic tripping and protection blinding are tackled through
advanced protection system then there will be no need to limit installed DER
through planning rules. Therefore, it will contribute to KPI 7 by increasing the
amount of DER that is possible to install in the network. That will also affect KPI 8
(Optimized use of assets).
The quantification of these KPIs will be assessed on Deliverable 5.3.
89/97
Deliverable 4.3
Planning of Advanced System Protections
8 Conclusions
This deliverable presents the details about the implementation of the
functionalities that compose the advanced protection systems of the project
SuSTAINABLE. A description of the grid used to model the test systems at ICCS
and INESC were used. This limited but extremely flexible setting allows all the
functionalities to be tested, creating all the adequate scenarios for the validation of
the implementations.
After a comprehensive description of all the possible faults in MV distribution
networks and how these can be affected by the presence of high penetration
levels of DG, the protection functions adequate to tackle these challenges are
documented. Furthermore, the impact of distributed generation on the current off
the shelf protection relays is analysed specifically for the following 5 issues:
- Protection Blinding
- Sympathetic Tripping
- Failed Auto-Reclosing
- Loss-of-mains Protection
- Fault Ride-though
90/97
Deliverable 4.3
Planning of Advanced System Protections
9 References
[1] M. L., Guia Geral de Proteção e Automação da RND: EDP Distribuição, 2011.
[2] J. L. Ferreira, “Os Órgãos de Corte de Rede de 3ª Geração nas Redes de Distribuição de
Média Tensão”, Master of Science, Department of Electrical and Computer Engineering,
University of Porto, 2013.
[3] B. M. Coelho, “Classificação de Tipologia de rede da EDP Distribuição”, Master of
Engineering, Department of Electrical and Computer Engineering, University do Porto, 2012.
[4] DEF-C13-570/N. INSTALAÇÕES AT E MT. SUBESTAÇÕES DE DISTRBITUIÇÃO.
Sistemas de Proteção, Comando e Controlo Numérico (SPCC). Funções de Proteção -
Especificação funcional. Available: www.edpdistribuicao.pt -> profissional -> Documentos
Normativos ->DEF-C13-570, access on 11 May.
[5] M. F. Louro, “O sistema de proteções na perspectiva da segurança de pessoas em redes de
MT”, Master of Science, Department of Electrical and Computer Engineering, University
Técnica de Lisboa, 2008.
[6] DEF-C13-551/N. INSTALAÇÕES AT E MT. SUBESTAÇÕES DE DISTRIBUIÇÃO. Função
de automatismo: “religação rápida e/ou lenta de disjuntores,” - Espeficação Funcional.
Available: www.edpdistribuicao.pt -> profissional -> Documentos Normativos -> DEF-
C13-551, access on 14 May.
[7] TPU-S220. Protecção e Controlo para Sistemas de Distribuição de Energia Eléctrica e
Indústria. Available: www.efacec.pt. -> Áreas de Negócio -> Catálogo -> IED de
Protecção, Automação e Controlo da Série 220.
[8] J. L. Blackburn and T. J. Domin, Protective Relaying, Principles and Applications, 3rd ed.,
CRC Press, Taylor & Francis Group, LCC, 2007.
[9] Network Protection & Automation Guide, Areva T&D, 2002.
[10] R. C. Dugan and T. E. McDermott, “Distributed Generation”, IEEE Ind. Appl. Mag., vol. 8, no.
2, pp. 19–25, 2002.
[11] J. Morren and S.W.H. de Haan, “Impact of distributed generation units with power electronic
converters on distribution network protection”, in 2008 Inter. Conf. on Devel. in Power Syst.
Prot. (DPSP), pp. 664–669.
[12] A. R. Haron, M. Azah, H. Shareef, and H. Zayandehroodi, “Analysis and Solutions of
Overcurrent Protection Issues in a Microgrid”, in 2012 IEEE Power and Energy Inter. Conf.
(PECon), pp. 644–649.
[13] I. Xyngi, A. Ishchenko, M. Popov, and L. V. D. Sluis, “Protection Issues in Distribution
Networks with Dispersed Generation”, in 2008 Medit. Conf. on Power Gen., Trans. Distr. and
Energy Conv. (MEDPOWER), pp. 1–6.
[14] V. A. Papaspiliotopoulos, V. A. Kleftakis, P. C. Kotsampopoulos, G. N. Korres, and N. D.
Hatziargyriou, “Hardware-In-the-Loop simulation of protection blinding and sympathetic
tripping phenomena in modern distribution grids”, in 2014 Medit. Conf. on Power Gen.,
Trans. Distr. and Energy Conv. (MEDPOWER), pp. 1–6.
[15] F. Coffele, C. Booth, A. Dysko, and G. Burt, “Quantitative analysis of network protection
blinding for systems incorporating distributed generation”, IET Gener. Transm. Distrib., vol.
6, no. 12, pp. 1218–1224, 2012.
[16] K. Kauhaniemi and L. Kumpulainen, “Impact of distributed generation on the protection of
distribution networks”, in 2004 Inter. Conf. on Devel. in Power Syst. Prot. (DPSP), pp. 315–
318 (vol. 1).
[17] J. J. Grainger and W. D. Stevenson Jr., Power System Analysis, McGraw-Hill, Inc., 1994.
[18] H. Saadat, Power System Analysis, 3rd ed., PSA Publishing, 2010.
[19] J. Roberts, T. L. Stulo, and A, Reyes, “Sympathetic tripping problem, analysis and solutions”,
SEL publications, Technical papers, 2002.
91/97
Deliverable 4.3
Planning of Advanced System Protections
92/97
Deliverable 4.3
Planning of Advanced System Protections
93/97
Deliverable 4.3
Planning of Advanced System Protections
[60] R. K. Rajeev Kumar, M. L. Dewal, and K. Saini, “Utility of SCADA in power generation and
distribution system”, in Proc. 2010 3rd IEEE Inter. Conf. Computer Science and Information
Technology (ICCSIT), pp. 648–652.
[61] I. Ferreira, "Sistemas de Controlo e Supervisão de Sistemas Embebidos - Tipo SCADA",
Master of Science, Department of Electrical and Computer Engineering, University of Porto,
2008.
[62] M. L., Guia Geral de Proteção e Automação da RND: EDP Distribuição, 2011.
[63] J. L. Ferreira, “Os Órgãos de Corte de Rede de 3ª Geração nas Redes de Distribuição de
Média Tensão”, Master of Science, Department of Electrical and Computer Engineering,
University of Porto, 2013.
[64] B. M. Coelho, “Classificação de Tipologia de rede da EDP Distribuição”, Master of
Engineering, Department of Electrical and Computer Engineering, University do Porto, 2012.
[65] DEF-C13-570/N. INSTALAÇÕES AT E MT. SUBESTAÇÕES DE DISTRBITUIÇÃO.
Sistemas de Proteção, Comando e Controlo Numérico (SPCC). Funções de Proteção -
Especificação funcional. Available: www.edpdistribuicao.pt -> profissional -> Documentos
Normativos ->DEF-C13-570, access on 11 May.
[66] M. F. Louro, “O sistema de proteções na perspectiva da segurança de pessoas em redes de
MT”, Master of Science, Department of Electrical and Computer Engineering, University
Técnica de Lisboa, 2008.
[67] DEF-C13-551/N. INSTALAÇÕES AT E MT. SUBESTAÇÕES DE DISTRIBUIÇÃO. Função
de automatismo: “religação rápida e/ou lenta de disjuntores” - Espeficação Funcional.
Available: www.edpdistribuicao.pt -> profissional -> Documentos Normativos -> DEF-
C13-551, access on 14 May
[68] A. R. Oliveira, “Validação das Funções de Proteção de uma Saída de Média Tensão com
Produção Renovável Eólica usando CAPE Software”, Master of Science, Department of
Electrical and Computer Engineering, University of Porto, Porto, 2011.
[69] H. Leite, P. Ramalho, B. Silva, and R. Fiteiro, “Distributed Generation protection scheme to
permit ride-through fault”, in Electricity Distribution - Part 1, 2009. CIRED 2009. 20th
International Conference and Exhibition on, 2009, pp. 1–4.
[70] “Guia de Aplicação das Condições Técnicas de Ligação às Redes de Distribuição das
Instalações de Produção de Energia Eléctrica em Regime Especial”, ed: Direção-Geral de
Energia, 2002.
[71] RTDS User’s Manual Set, 2005 Version, RTDS Technologies.
[72] EFACEC TPU S220 Catalog – available in:
http://www.efacec.pt/PresentationLayer/efacec_produto_01.aspx?idioma=2&area=2&idProd
uto=515
[73] Doble amplifier information available in: http://www.doble.com/products/f6350.html
[74] A. Bernardo, N. Silva, N. Delgado, R. Jorge, and A. Carrapatoso, “DG behaviour and
protection schemes in case of disturbances within the concept of Distribution Grid Area”, in
2012 CIRED Workshop: Integration of Renewables into the Distribution Grid, pp. 1–4.
94/97
Deliverable 4.3
Planning of Advanced System Protections
Parameter Value
Short-circuit MVA, Ssc 3000 MVA
R/X 0
Parameter Value
Voltage Ratio 150 kV/20 kV
Rated Apparent Power, SrT 40 MVA
Impedance, Z (ukr) 12.8%
Total Winding Losses, PkrT 148 kW
Vector Group Dyn1
95/97
Deliverable 4.3
Planning of Advanced System Protections
Parameter Value
Voltage Ratio 20 kV/0.4 kV
Rated Apparent Power, SrT 2.5 MVA
Impedance, Z (ukr) 6%
Total Winding Losses, PkrT 17 kW
Vector Group Dyn1
Parameter Value
Rated Voltage, Vr 0.4 kV
Rated Apparent Power, Sr 2.1 MVA
Power Factor, cosφ 0,85
Direct-axis Synchronous Reactance (saturated), Xd 271.3%
Direct-axis Transient Reactance (saturated), Xd’ 18.6%
Direct-axis Subtransient Reactance (saturated), Xd’’ 11.7%
Quadrature-axis Subtransient Reactance (saturated), Xq’’ 14.8%
Direct-axis Transient open circuit Time Constant, Td0’ 6.021 s
Direct-axis Transient short circuit Time Constant, Td’ 0.349 s
Direct-axis Subransient short circuit Time Constant, Td’’ 0.0291 s
96/97
Deliverable 4.3
Planning of Advanced System Protections
Parameter Value
Line 1 Resistance 3.645 Ω
Parameter Value
Voltage Ratio 15 kV/0.69 kV
Rated Apparent Power 8 MVA
Impedance, Z (ukr) 6%
97/97