Government of Kerala
Department of Electrical Inspectorate
Office of the Chief Electrical Inspector
Housing Board Buildings, Shanthi Nagar
Thiruvananthapuram 695 001
Phone: 0471 2331104 , 0471 2331159
Email : cei@ceikerala.gov.in
Website:www.ceikerala.gov.in
Order No. H1- 5729 / 2018 / CEI Dated: 01/ 08/ 2018
As per the direction in the Government Order read (4) above, the existing fee rates of all
services rendered by the Department of Electrical Inspectorate has been enhanced by 5% w.e.f 01/04/2018
vide order referred (5). The detailed revised fee structure applicable to various services w.e.f 01/04/2018 is
as given below.
IV. Testing fee for electrical instruments in the Meter Testing and Standards
Laboratory
A. In House Testing
Sl. Equipment Existing rate Revised Rate
No. (in Rupees) (in Rupees)
200/range 210/range
(Calibration (Calibration
1 Ammeter
certificate as per certificate as
NABL norms) NABL norms)
200/range 210/range
(Calibration (Calibration
2 Voltmeter
certificate as per certificate as per
NABL norms) NABL norms)
3 Wattmeter
400/range 420/range
(Calibration (Calibration
(a) D.C
certificate as per certificate as per
NABL norms) NABL norms)
400/range 420/range
(Calibration (Calibration
(b) Single Phase A/C
certificate as per certificate as per
NABL norms) NABL norms)
600/range 630/range
(Calibration (Calibration
(c) Poly Phase A/C
certificate as per certificate as per
NABL norms) NABL norms)
4 Power factor Meter
315/range
(a) Single Phase 300/range (Ordinary
(Ordinary Report) Report)
420/range
(b) Poly Phase 400/range (Ordinary
(Ordinary Report) Report)
500/range 525/range
(Calibration (Calibration
5 Frequency Meter
certificate as per certificate as per
NABL norms) NABL norms)
6 Energy Meter
300 (Ordinary 315 (Ordinary
Report) Report)
500 (Calibration 525 (Calibration
Single Phase ( 4 points)
(a) certificate as per certificate as per
Active energy % error
NABL norms) NABL norms)
16 HT Current Transformer
2000 (ordinary
(b) Polarisation Index
report) 2100 (ordinary
report)
2000 (ordinary 2100 (ordinary
(c) Insulation Resistance (measurement) report) report)
8
(d) Routine tests as per IS 2026 Part 1 Rs. 25,000/- Rs. 26,250/-
(Measurement of winding resistance,
Measurement of voltage ratio and
check of Vector group; Measurement of
short circuit impedance; Measurement
of no load loss and current) and
measurement of insulation resistances,
measurement of dissipation factor (tan
ð) of the insulation system
capacitances and measurement of
polarisation index.
(e) High Voltage test 5000/- 5250/-
21 High Voltage Test
2000/cable(ordinary 2100/cable
(a) Cables
report) (ordinary report)
2000/pair (ordinary 2100/pair
(b) Rubber Gloves
report) (ordinary report)
3000/VCB (ordinary 3150/VCB
(c) VCB
report) (ordinary report)
22 HT Potential Transformers
24 Relay testing
Using secondary injection except 500/element 525/element
(a)
differential relay (ordinary report) (ordinary report)
250/element 265/element
(b) Auxiliary & tripping relay
(ordinary report) (ordinary report)
2000/element 2100/element
(c) Differential relay
(ordinary report) (ordinary report)
2000/element 2100/element
(d) Negative sequence relay (ordinary report) (ordinary report)
25 LED Testing
26 Battery Testing
(a) Capacity Test 3000/- 3,150/-
(b) Deep Cycle Test 3000/- 3,150/-
MCCB (contact Resistance + Timing 1050/- per
27 1000/- per breaker
+ Coil currents) breaker
28 Primary injection test at site (testing 10,000/- 10,500/-
of protection CT & control wiring will (ordinary report)
be charged extra)
500 each (ordinary 525 each
(a) Protection CT
report) (ordinary report)
500/relay (ordinary 525/relay
(b) Control wiring
report) (ordinary report)
25000 (ordinary 26250 (ordinary
29 Harmonic Analysis
report) report)
30 Mobile Testing Actual testing fee + Actual testing fee
15% of Testing fee + 15 % of
subject to a Testing fee
minimum of subject to a
Rs.5000/- minimum of
Rs.5250/-
31 Any other test To be fixed by To be fixed by
Chief Electrical Chief Electrical
Inspector Inspector
10
B. On Site Testing
Sl.
No. Nature of service Existing rate Revised Rate
1 Energy Meter (Active Energy, % a) 500 (single Phase) a) 525 (single Phase)
Error at 4 different load points) b) 1000 (Three Phase) b) 1050 (Three Phase)
2 TOD Meter (Active and Reactive 2000/- 2100/-
Energy, % Error at different load
points
3 Net Meter (Active and Reactive 4000/- 4200/-
Energy @ Export and Import mode,
% Error at different load points)
4 Testing of LT CT's (Ratio Error and 500 per Core 525 per Core
Phase Angle error)
5 Testing of HT CT's (Ratio Error 2000 per Core 2100 per Core
and Phase Angle error)
6 Testing of Circuit Breakers
HT/EHT breaker ( IR value before 10000/- per Breaker 10500/- per Breaker
(a) and after Hipot + Hipot testing +
contact Resistance + Timing + Coil
currents)
ACB (contact Resistance + Timing
(b) + Coil currents) 2000/- per Breaker 2100/- per Breaker
(i)
Rs.5/- per KVA/KW/KVAr Rs.5.25/- per
Extra High Voltage/ High Voltage
(a) subject to a maximum of KVA/KW/KVAr subject to
equipment
Rs.30000/- a maximum of Rs.31500/-
Medium Voltage/Low Voltage Rs.10/- per Rs.10.50/- per
(b)
equipment KVA/KW/KVAr KVA/KW/KVAr
(c) Earth Electrodes Rs.50/- per electrode Rs.55/- per electrode
(d) Earth Mat Nil Rs. 5/- per sq.m
Rs.2/- per Ampere per Rs.2.10/- per Ampere per
(e) Bus Duct 20M length or part there 20M length or part there
of of
Rs.2/- per Ampere per Rs.2.10/- per Ampere per
(f) Breakers/Switches/Switch Boards
incomer or outgoing incomer or outgoing
(g)
Lightning Protection Rs.2500/- Building Rs.2625/- Building
(h)
Overhead lines/ABC Rs.25/- per KM 26.25/KM
11
(v) Renewal fee of scheme approval Seventy five percent Seventy five percent
if application is received after the (75%) of initial inspection (75%) of initial inspection
expiry date of validity of approved fee fee
scheme. (for two years)
(vi) Valuation of Electrical Rs.2000/- + 0.5% of Rs.2100/- + 0.5% of
Installations valuation amount valuation amount
(vii ) Fees for Technical Advice/ Consultancy
(a) Detailed engineering, preparation of Three percent (3%) of Four percent (4%) of
technical drawings and estimates estimated cost of works estimated cost of works
and specification of the equipment
and technical scrutiny of tenders
(b) Supervision, Inspection and control Four percent (4%) of total Five percent (5%) of total
during execution cost of works cost of works
(c) Construction of new works including Fifteen percent (15%) of Sixteen percent (16%) of
detailed engineering total cost of works plus total cost of works plus
actual cost of actual cost of
establishment employed establishment employed
and actual expenses and actual expenses
(d) Giving opinion on plans estimates Seventy Five percent Seventy Five percent
and specifications (75%) of initial inspection (75%) of initial inspection
fee fee
(e) Scrutiny fee for advice/final scheme Seventy Five percent Seventy Five percent
approval for two years (75%) of initial inspection (75%) of initial inspection
fee fee
13
NB: - All total amount calculated shall be rounded to the next higher multiple of 5.
All fees above and included in the G.O read above are subjected to minimum of Rs. 525/- per day.
Sd/-
Chief Electrical Inspector
To,
The Deputy Chief Electrical Inspector / The Electrical Inspector,
………………………………………………………….
Copy to:
1. Principal Secretary, Power Department, Government Secretariat,
Thiruvananthapuram(with C/L).
2. Principal Secretary, Finance department, Government Secretariat,
Thiruvananthapuram(with C/L).
3. All Deputy Chief Electrical Inspectors / Electrical Inspectors
4. A, B, G, section
5. Stock file/Spare.