Académique Documents
Professionnel Documents
Culture Documents
1
CERTIFICATIONS & TESTS
• PID-Free, Thresher Test, Long-Term Sequential Test, and ATLAS 25+
• IEC 61646 1500V, IEC 61730 1500V, CE
• IEC 61701 Salt Mist Corrosion, IEC 60068-2-68 Dust and Sand Resistance
• ISO 9001:2008 and ISO 14001:2004
• UL 1703 1500V Listed Class B Fire Rating (Class A Spread of Flame)
• CSI Eligible, FSEC, MCS, CEC Listed (Australia), SII, InMetro
END-OF-LIFE RECYCLING
• Recycling services available through First Solar’s industry-leading
recycling program or customer-selected third party.
2
MODULE WARRANTY
100% • 25-Year Linear
97%
95%
Performance
Power Output
Warranty3
90%
• 10-Year Limited
85%
Product Warranty
80%
0 5 10 15 20 25
Years
MECHANICAL DESCRIPTION MODULE NUMBERS AND RATINGS AT STANDARD TEST CONDITIONS (1000W/m2, AM 1.5, 25°C)4
Length 1200mm FS-4107-3 FS-4110-3 FS-4112-3 FS-4115-3 FS-4117-3 FS-4120-3
NOMINAL VALUES
Width 600mm FS-4107A-3 FS-4110A-3 FS-4112A-3 FS-4115A-3 FS-4117A-3 FS-4120A-3
Weight 12kg Nominal Power 5 (-0/+5W) P MPP (W) 107.5 110.0 112.5 115.0 117.5 120.0
Thickness 6.8mm Voltage at P MAX VMPP (V) 67.0 67.8 68.5 69.3 70.1 70.8
Area 0.72m2 Current at P MAX IMPP (A) 1.61 1.62 1.64 1.66 1.68 1.70
Leadwire 2.5mm2, 610mm Open Circuit Voltage VOC (V) 85.8 86.4 87.0 87.6 88.1 88.7
Connectors MC4 8 Short Circuit Current ISC (A) 1.82 1.82 1.83 1.83 1.83 1.84
Bypass Diode None Module Efficiency % 14.9 15.3 15.6 16.0 16.3 16.7
Cell Type Thin-film CdTe Maximum System Voltage VSYS (V) 1500 6,7
semiconductor, Limiting Reverse Current IR (A) 4.0
up to 216 cells
Maximum Series Fuse ICF (A) 4.0
Frame Material None
RATINGS AT NOMINAL OPERATING CELL TEMPERATURE OF 45°C (800W/m2, 20°C air temperature, AM 1.5, 1m/s wind speed) 4
Front Glass 3.2mm heat
strengthened Nominal Power P MPP (W) 81.4 83.2 85.1 87.0 89.0 90.8
TM
Series 4A includes Voltage at P MAX VMPP (V) 63.1 63.5 64.5 64.9 65.9 66.3
anti-reflective coating Current at P MAX IMPP (A) 1.29 1.31 1.32 1.34 1.35 1.37
Back Glass 3.2mm
Open Circuit Voltage VOC (V) 81.0 81.6 82.1 82.7 83.2 83.7
tempered
Short Circuit Current ISC (A) 1.47 1.47 1.47 1.48 1.48 1.48
Encapsulation Laminate material
with edge seal TEMPERATURE CHARACTERISTICS
Load Rating 2400Pa9 Module Operating Temperature Range (°C) -40 to +85
Temperature Coefficient of P MPP TK (P MPP) -0.28%/°C [Temperature Range: 25°C to 75°C]
Temperature Coefficient of VOC TK (VOC) -0.28%/°C
Temperature Coefficient of ISC TK (ISC) +0.04%/°C
100
4.0%
CdTe Relative Energy Gain over c-Si
Dubai, UAE 95
3.0% More Energy for Same
Durban, South Africa 90 Nameplate Watts
Atlanta, USA
2.0% 85
Frankfurt, Germany External Quantum Efficiency
Linear (First Solar)
FS Series 4V3 PV Module Type
1.0% 100 80 Linear (Multicrystalline Si)
Quantum Efficiency (%)
80
75
60
0.0% 20 30 40 50 60 70
40
Module Temperature (°C)
20
-1.0%
0
300 500 700 900
MECHANICAL DRAWING
Wavelength (nm)
-2.0%
0 10 20 30 40 50 60 70 80 90
firstsolar.com | info@firstsolar.com
PV MODULE DRAWING (THIN FILM) - First Solar Series 4 PV Module (Datasheet)
User Guide
User Guide:
First Solar Series 4 Module
Global
REV 2.3
PD-5-200-04 | 0348_UG_A4_9FEB16
Series 4 Module User Guide—Global | Page i of 14
Table of Contents
1 Introduction....................................................................................................................................................................1
1.3 Safety................................................................................................................................................................2
2 Regulatory Compliance...................................................................................................................................................3
3 Electrical Specifications..................................................................................................................................................4
4 Installation......................................................................................................................................................................5
4.1 Mounting...........................................................................................................................................................5
7 Service..........................................................................................................................................................................12
9 Notice...........................................................................................................................................................................13
10 Document References...................................................................................................................................................14
1 Introduction
First Solar Series 4 and Series 4A Modules are manufactured in state-of-the-art facilities using a highly innovative process
that rapidly deposits thin films of semiconductor on glass. Series 4A modules are constructed identically to Series 4 modules
and add anti-reflective coated glass to Series 4 modules. The modules have been designed to have a long operating life
and high energy yield when installed, operated, and serviced in accordance with the instructions in this User Guide and
the System Design and Application Document (PD-2-303). First Solar Series 4 and Series 4A Modules are electrically and
mechanically compatible with one another, provided appropriate system design practices are employed. Series 4 and Series
4A Modules are not compatible with First Solar Series 3 Modules within the same interconnected string.
Failure to maintain proper operating condition requirements for the modules will void the applicable warranties.
This user guide addresses typical module installation and usage globally. Certain regions may have additional requirements
or concerns. Please contact First Solar (technicalsupport@firstsolar.com) or visit www.firstsolar.com for additional regional
User Guides that may be available, or for additional support.
For details on product box handling and storage please reference PD-5-801.
Guidelines related to system construction are beyond the scope of this document and are not covered in this document.
1.3 Safety
The Series 4 and Series 4A Modules may produce voltage up to 110 Volts DC (VDC) or current up to 3.0 Amps
when exposed to sunlight. A single module could create a lethal shock hazard during hours of daylight, including
periods of low light levels. The danger increases as modules are connected together in series and/or parallel.
To avoid fire and/or injury due to ground fault and associated electrical hazards:
• Do not unplug PV module connections while under load. Do not disconnect the module connectors
during daylight hours unless the module is in an open circuit condition or all modules in series and
parallel are covered with an opaque material, such as a tarp or blanket.
• Repair or replace damaged wires immediately. Keep all array wiring out of reach of non-qualified
personnel.
• Never allow the PV array system voltage to exceed 1500VDC under any condition.
• Do not work on modules or systems when the modules or wiring are wet.
Reverse currents higher than the rated values for a First Solar module (reverse current overload), may result in
module failure, including module breakage. Extreme and continuous reverse current overload conditions may
cause a fire or create electrical shock hazards. To avoid reverse current overload:
• Maintain equivalent voltage in parallel strings by installing an equal number of modules per string within
the same source circuit. Failure to install modules with balanced voltage in parallel strings can result in
voltage imbalance.
• Comply with all practices as stated in this document and repair ground faults.
Wear safety glasses (ANSI Z87.1-2003) and cut-resistant gloves when working on non-interconnected modules or
systems.
Wear electrically rated PPE when working on interconnected modules or system components.
Series 4 and Series 4A Modules are not compatible with Series 3 Modules within the same interconnected string.
• To avoid risk of fire, do not interconnect Series 4/4A Modules within the same interconnected string as
Series 3 Modules.
2 Regulatory Compliance
It is the responsibility of the installer and/or system integrator to ensure compliance with all local electrical codes which may
be applicable to the installation and use of First Solar Series 4 and Series 4A Modules.
• Before beginning the PV system design and installation, contact appropriate local authorities to determine local
code, permit, and inspection requirements.
Series 4 and Series 4A Modules meet the requirements of Safety Class II for 1000VDC systems and Safety Class 0 for
1500VDC systems. Series 4 and Series 4A Modules are tested and certified per IEC 61730 Application Class A up to a
maximum system voltage of 1000V and Application Class B up to a maximum system voltage of 1500V, both with maximum
overcurrent protection ratings of 4.0A.
Series 4 and Series 4A Modules are tested and certified per IEC 61646 for a maximum system voltage of 1500V.
3 Electrical Specifications
See the Series 4 and Series 4A Module datasheet (PD-5-401-04) and module label for all electrical ratings of the module. All
electrical ratings are listed at Standard Test Conditions (irradiance of 1000 W/m2, AM 1.5 spectrum, and a cell temperature
of 25°C).
As defined in the National Electric Code and IEC 62548 , the maximum system voltage for a Photovoltaic System is
determined using the open circuit voltage of the PV modules. First Solar’s Series 4 family of modules have unique
performance characteristics that result in an increased open circuit voltage at low operating temperatures. The open circuit
voltage should be multiplied by a low temperature correction factor as specified in Application Note PD-5-435 NA in addition
to the 1.25 factor mentioned above. This low temperature correction factor should be based on the site specific design
temperature profile.
4 Installation
4.1 Mounting
Physically damaged modules may cause ground faults and associated electrical hazards. To avoid these
! conditions:
! Do not install the modules during high wind or wet conditions to reduce the likelihood of injury.
Wear safety glasses (ANSI Z87.1-2003) and cut-resistant gloves when working on non-interconnected modules or
! systems.
! Wear electrically rated PPE when working on interconnected modules or system components.
• Handle modules with care during installation, as heavy impact on the front, back, or edges could result in damage
to the module. Do not walk or stand on modules or retaining clips.
• Do not stack or carry multiple modules on top of one another after removal from factory packaging to minimize
the risk of breakage.
• Do not lift or pull on modules using lead wires or strain relief wire loops to minimize the risk of wire damage.
Mounting of the Series 4 and Series 4A Module to a suitable structure can be done by attaching the module directly to the
structure using retaining clips (see Figure 5.1).
The interface of the mounting structure to the module (including the retaining clip and rubber insulator) must meet the
technical requirements specified in First Solar Application Note PD-5-320-04 and must be approved for use by First Solar
prior to installation. The mounting system design must provide adequate support for the module to prevent damage from
occurring when the module is subjected to pressures of 2400 Pa (which equates to wind pressure of 130 km/hour, with a
safety factor of 3 for gusty conditions based on IEC 61646). The location of the clips shall be along the 1200mm length of
the module and the center point of the clip shall be located between 250mm and 300mm from the module edge. See Figure
5.1 for allowed location. Rubber insulator material, or equivalent must be used between the module and both the clip and
mounting structure to provide adequate protection of the module and must meet all requirements described in PD-5-320-04
Module Mounting. No direct contact of rigid structures is permitted against the surface or edges of the module.
All mounting structures must provide a flat plane for the modules to be mounted on, and must not cause any twist or stress
to be placed on the module.
Modules should not be installed in a way that restricts air circulation to the underside of the module. Modules generate
heat and require adequate airflow for cooling.
Installation locations and module support structures should be selected to ensure modules and connectors (open or mated)
are never submersed in standing water. First Solar modules are tested and certified for applications involving pressures
from snow/ice/wind up to 2400 Pa when mounted properly. Snow drifts could result in a nonuniform loading of the modules
which exceeds the tested pressure. If it is expected that loads will exceed 2400 Pa, it is recommended to clear snow from
modules, and ensure that ice/thaw/freeze cycles under snow drifts do not result in excessive stresses on the module.
Heavy construction and trenching should be completed prior to module installation to minimize debris and dust.
Ensure any site preparation or maintenance chemicals (soil binding agents or chemicals used for on-site dust control or weed
control) do not spray, splash, or drift onto the surface of the modules or its associated components.
Maximum allowable pressure on modules may not exceed 2400 Pa without additional module support that must be tested
and approved by First Solar.
For rooftop mounting, modules must be mounted over a fire resistant roof covering rated for the application. The
recommended minimum standoff height is 8cm.
During handling and installation, avoid abrasive contact with top glass surface to prevent scratches of anti-reflective coating
on Series 4A modules.
Do not remove cardboard separator paper before removing modules from box. Doing so may result in scratches of the ARC
film when pulling modules out of the box.
When cleaning Anti-Reflective Coated modules, specific module cleaning guidelines documented in PD-5-804 Module
Cleaning Guidelines must be followed. Failure to comply with the Module Cleaning Guidelines may void warranty.
• Low pressure non-contact water cleaning may be used with unlimited cycles (i.e. water spray is allowed, but scrubbing
or brushing with water is prohibited).
• Wet contact cleaning (i.e. combining water with mops, brushes, squeegees)
• Dry contact cleaning with anything other than soft cloths or mops (i.e. bristle brushes, sponges, or squeegees).
PV performance modeling software should be used to determine the optimum orientation and tilt angle for each location.
For tilted free-field applications where there is row to row shading, modules shall be installed in landscape orientation.
Please refer to First Solar Application Note PD-5-425-03 for additional information.
1. Resting or adhering slender objects (tools, brooms, clothing, wires, tape) on sunny side of operating modules, or when
nearer than ~1.5-2 meters above operating modules, especially when shadow oriented parallel to cells.
2. Fixed objects within ~1.5-2 meters above operating modules that cast a shadow over the long dimension of the cells
should be avoided. Close objects like posts, ropes, signs, fences, or equipment can begin to increase risk of partial
shading of full cells when nearer than ~1.5-2 meters from the sunny-side of operating module.
4. A support frame or mounting method on the short edge(s) of modules that fully shades the entire length of a cell (either
partially or completely).
5. Cleaning apparatuses, including cleaning robots and other mechanisms that traverse the module repeatedly while the
system is operating (unless evaluated and approved by First Solar).
Modules with different FS Series numbers (i.e. FS 3 vs. FS 4) have significantly different electrical operating
! characteristics and should not be interconnected within the same inverter or MPPT to prevent power output loss
and voltage imbalance conditions that may create the risk of reverse current overload.
Damaged wires, connectors, or junction boxes may cause ground faults, and associated electrical hazards,
! including electrical shock. To avoid these conditions:
• Protect unmated connectors from dust and moisture by using sealing caps (not provided, available from connector
manufacturer).
• Do not pull lead wires tight at any time. After installation, the connected wire must not be under stress or tension.
• Do not use junction box assembly or lead wire strain relief loops to secure excess wire or to bear weight greater
than that of a (properly wire managed) module’s own wire and mated connector pair.
• Connector bodies and cables should not be tightly secured at both ends to any mounting structure to allow for
thermal expansion and contraction.
• Secure wire or connected components so that no loose wires or components are hanging within 0.46m (1.5 feet)
of the ground in free field applications, and so that wire/components are hanging clear of roof coverings or pooled
water in rooftop applications.
• Ensure wire securement methods, such as use of cable ties, do not damage wire insulation. The minimum module
lead wire bend radius is 5 times wire diameter. Observe minimum bend radius specifications on all other PV
system wiring.
• Ensure wires are not in contact with sharp edges of the mounting structure to avoid abrading the wire sheath.
• Inspect and maintain wire management requirements over the life of the plant.
Module-to-module and module-to-harness interconnection is advised to be done between same manufacturer and type
of connectors. The First Solar module warranty is not affected by the interconnection of different supplier connectors,
however, First Solar cannot guarantee that different connector types will be mateable in every connection instance.
Components used to interconnect the modules must be compatible with the connectors, and provide proper system
operation and fault protection as required by any applicable codes and standards.
When selecting an inverter, system bias conditions and grounding should also be considered. FS Series PV Modules can be
used in negative-grounded or ungrounded installations. Use in bi-polar systems should be reviewed in detail by First Solar
prior to approval. FS Series PV Modules should not be used in positive-grounded systems.
When connecting First Solar Series 4 and/or Series 4A Modules in a series string, ensure that the system design voltage
and inverter design specifications are not exceeded. First Solar application note PD-5-435 NA should be referenced when
determining the site specific maximum open-circuit system voltage (Voc) seen by the inverter. For 1000VDC applications,
this is typically ensured by limiting series strings to 10 modules or less. For 1500VDC applications, this is typically ensured by
limiting series strings to 15 modules or less.
The Maximum Power Point (MPP) voltage of a module array must be considered for compatibility with the specified MPP
window of the inverter. Similar to the maximum open-circuit voltage, the MPP voltage of the array is dependent on ambient
conditions, and the system should be designed to ensure that the MPP voltage of the array remains within the MPP window
for expected operating conditions.
First Solar Series 4 and Series 4A Modules can be used in grounded, ungrounded, floating, and bi-polar system architectures,
provided all appropriate design requirements are met and approved by First Solar.
PV systems should be designed to comply with and provide module overcurrent protection consistent with local codes as
appropriate for the intended application class of the system.
Connection of parallel strings must incorporate measures to protect modules against reverse currents exceeding their rating
as described in FS Application Note PD-5-308.
Please refer to FS Application Note PD-5-308 for additional information on module overcurrent protection.
Important: Failure to maintain proper operating condition requirements for the modules will void the applicable
warranties.
Requirements:
• Short circuit operation is permitted only during short duration system safety testing or in fail-safe system states.
• All electronic components that are interconnected to modules must have an operating voltage window that matches
the maximum power point of the array, and be capable of operating the array at the maximum power point at all
times.
• All electronic components that are interconnected to modules must be rated for the maximum operating voltage of
the array.
• Modules must have adequate ventilation and airflow to prevent operating temperatures above 85°C.
• Modules must not be partially shaded by obstructions at times of high irradiance (typically between 9:00am and
3:00pm). Module row-to-row shading in landscape orientation is acceptable; Module row-to-row shading in portrait
orientation is prohibited.
• If module cleaning is undertaken, modules must be cleaned only when in open circuit – either disconnected from
load, or during times when inverter is turned off and otherwise in accordance with PD-5-804 “FS Series PV Module
Cleaning Guidelines”.
• Series 4A Modules include anti-reflective coated glass. Use of prohibited cleaning methods can reduce the energy
enhancing effects of the anti-reflective coated glass and void warranty. Please consult PD-5-804 “FS Series PV
Module Cleaning Guidelines” for allowable cleaning methods compatible with Series 4A Modules.
• Module boxes must be handled per PD-5-801 Box Handling and Storage. Failure to follow the Box Handling and
Storage guidelines may result in damage to modules that would not be covered under the Module Warranty Terms
and Conditions.
7 Service
Cleaning activities create risk of damage to the modules and array components, as well as the potential for electric
shock. Large amounts of dust and dirt on the surface of the module can reduce the power produced. Natural
!
rainfall will typically remove most dust. Should auxiliary cleaning be required, please refer to the Module Cleaning
Guidelines (PD-5-804) for additional information. Failure to comply with the Module Cleaning Guidelines may void
warranty.
Broken modules should be replaced immediately. Periodically, annually at a minimum, inspect modules for any
! signs of damage or broken glass. If broken modules are found, place material into a closed container for return
to First Solar recycling program, or dispose of module in accordance with local requirements. Please visit www.
firstsolar.com/recycling for further details on the recycling program.
• It is normal for the modules to exhibit visual irregularities which do not impact power. Series 4A Modules with anti-
reflective coated glass are more likely to exaggerate the visual appearance of normal scratches, fingerprints, and
other blemishes due to the optical properties of the glass interface.
• Check that all electrical connections are tight and corrosion free.
The most common causes of lower than expected PV system power output are:
• Inverter failure
9 Notice
Changes to certain components of the module are common as First Solar continuously strives for product improvements.
Changes may be a result of component improvements or changes by a supplier, or by minor design modifications initiated
by First Solar. All products within the same model classification remain functionally equivalent and fully compatible with
one another, even though there may be slight differences, provided appropriate system design practices are employed.
Modifications that do not impact the functionality of the product will typically be made without customer notification.
Internal testing, and review or retesting by a certifying agency, will be completed before component or design changes are
introduced into the manufacturing process.
First Solar reserves the right to make changes in solar module design and/or specifications at any time without notice.
Accordingly, the reader is cautioned to verify that data sheets are current before placing orders or finalizing system
permitting and/or design. Information furnished by First Solar is believed to be accurate and reliable. However, no
responsibility is assumed by First Solar or its subsidiaries for its use; nor for any infringements of patents or other rights of
third parties which may result from its use. No license is granted by implication or otherwise under any patent or patent
rights of First Solar or its subsidiaries.
In the event of a conflict between this module User Guide and the instructions of one of the system component
manufacturers, the system component instructions should prevail.
For information regarding First Solar and its products, please visit www.firstsolar.com. For technical support, please contact
technicalsupport@firstsolar.com.
Global
10 Document References
Module Characterization Response of First Solar FS Series 3 and FS Series 4 PV Modules to Partial
PD-5-425-03
Shading
PD-5-331 Compatible Inverters for FS2, FS3, and FS4 Series Modules without Galvanic Isolation
PD-5-332 Compatible Inverters for FS2, FS3, and FS4 Series Modules with Galvanic Isolation
Application Note
FS Series 4 PV Module Mounting
The information contained in this application note is intended to provide designers of First Solar PV
module mounting and support systems with both minimum requirements and recommendations for the
development of mounting solutions which will satisfy First Solar’s technical and mechanical
requirements to provide a safe and approved solution for the installation of all First Solar FS Series 4
laminate PV modules (i.e. FS-4XXX, FS-4XXX-A, etc…). North American users requiring the use of
Underwriters Laboratories (UL) listed components please reference PD-5-320-04 NA.
The information contained in this document is not exhaustive and does not consider all technical design
requirements. It rather provides the minimum required mounting provisions to ensure First Solar FS
Series PV Modules perform in a safe, compliant and reliable manner.
Compliance with these recommended requirements will not, by itself, result in a fully approved PV
System design.
Important: It is the responsibility of vendors, customers , installers, design professionals, and engi-
neers to follow a due diligence process to ensure the structure meets applicable structural
and electrical code requirements of the jurisdiction where the product will be sold or in-
stalled. First Solar is not responsible for bonding failure, breakage, damage, wear or mod-
ule performance issues that are deemed to be caused by design or installation practices.
First Solar is not responsible for the cost associated with the development or manufacture of
prototypes. Please see the appropriate First Solar FS Series PV Module User Guide (PD-5-200-XX) for
further information about the First Solar laminate PV module product in your region of application.
The retaining clip and mounting system (retaining system) shall not compromise the integrity of
the module under the applied load as defined in IEC 61646, 10.16.
The retaining system shall not deflect more than 0.01 mm/mm [0.01 inch/inch].
The clip and support rail retaining system shall be designed in combination with one another
and must have a gap on the vertical edge to the module of 1mm [0.04 inches] to allow for ther-
mal expansion in the width and length of the module glass. See Figure 3
A minimum gap of 10mm [0.4 inch] between two modules is required to prevent the contact be-
tween the modules
The retaining clip shall have a “hard stop” that limits the top and bottom surfaces of the insula-
tor material compression by a maximum of 10% at maximum torque of fastening hardware.
The retaining clip shall provide a gap of less than 6.8mm +/-0.2 [0.27 in +/-0.008in] to allow for
the thickness of the module and when installed, the insulator material shall compress in a range
of 5% to 10% at maximum hardware torque.
Figure 3. Example of a module 1mm apart from the vertical edge of the clip
A module surface contact length of 70mm [2.76 inches] (80mm [3.15 inches] preferred)
n
tio
ec
ot
pr
e
id
sl
ith
w
1 Description used for the mounting system description in the System Design and Application request form.
X Y
Detail A Detail B
Figure 5. One-part and Two-part clips
If a two-part clip design is used, then the width of the underlying module rail is not relevant, but the
module rail shall not exceed the maximum deflection specified.
If a one-part clip design is used, Table 1 below defines the support rail width and contact surface area
width for the two typical module support rail orientations. Alternate rail width needs individual review,
testing and approval for specific application. The module rail deflection shall not exceed the maximum
deflection specified.See Figure 6 Details A, B, C, and D for examples of module rails and the required
module surface contact.
Detail C Detail D
Figure 6. Module rail sample profiles and critical dimensions
Module support rails, clips and rubber shall be fabricated from corrosion and UV resistant materials (ex.
pre-galvanized steel, hot dipped galvanized steel, aluminum, stainless steel, powder-coated steel, etc.)
that will maintain structural integrity over the lifespan of the modules (minimum 25 years).
Fasteners
It is the responsibility of vendors, customers, installers, design professionals, and engineers to follow a
due diligence process to ensure fasteners used prevent galvanic corrosion, environmental corrosion, and
provide electrical bonding between the clip and underlying structure as defined by local codes and
jurisdictions. First Solar does not make recommendation or test fasteners for these requirements.
Fasteners used in the mounting system testing provided by vendors, customers, installers, design
professionals, and engineers are expected to meet all these and necessary mechanical strength
requirements.
Insulator materials shall be UV resistant and designed to maintain integrity over the lifespan of the
modules (minimum 25 years). Typical rubber durometers range from 45 to 75 on the Shore A scale.
In addition, the module structure should be designed to maximize air flow under the module to control
the module operating temperature.
It is the responsibility of vendors, customers, installers, design professionals, and engineers to perform
static load test as defined in IEC 61646, 10.16 and verify compliance prior to submitting samples to First
Solar for approval.
Any mounting solution that deviates from the dimensional guidance for the clip, rails, or mounting con-
figuration as specified above shall be considered to be in compliance with this document if it has been
proven with high confidence (sample size >5 per configuration) to pass the test procedures defined in
IEC 61646 10.16 (Mechanical Load Test to 2400Pa), IEC 61730 MST 32 (Module Breakage Test), UL 1703
section 41 (Mechanical Loading Test to 2154Pa), IEC 62782 Dynamic Mechanical Loading and/or other
tests deemed appropriate by First Solar. A detailed test report that documents the test setup, method
and results shall be provided to First Solar for review and approval.
Part drawing(s) of the proposed retaining clips, insulator, fasteners and number of support rails
with critical dimensions
Assembly drawing(s) of the proposed module, retaining clip, and support rail assembly with criti-
cal dimensions and specified fasteners
Assembly instructions with mounting location and fastener torque specifications
Detailed description of any special tools or equipment needed for assembly.
Upon receiving the above items, First Solar will review the proposed design and decide to either accept
to test or reject the proposed design. If the design is accepted, First Solar will request all of the following
to mount two modules as shown in Figure 4 Details A and B:
Samples of the clips (4 end clips, 2 mid clips) with rubber inserts
All hardware and fasteners needed for mounting the two modules.
If the testing is successful, First Solar will provide an FS Clip Number (PD-5-321-XXX) and a confirmation
of compliance.
A copy of all submitted drawings and samples will be retained by First Solar for historical record. First
Solar reserves the right to charge for mounting system approval and testing.
Failure to follow these recommended handling guidelines may result in damage to modules that will not be
covered under the First Solar FS Series module warranty.
54 Pack
Length: 1330 mm (52.375 in)
Width: 1076 mm (42.375 in)
Height: 692.15 mm (27.25 in)
Weight: Not to exceed 671 kg (1480 lbs.)
NOTE: All dimensions in centimeters [inches]. Dimensions should be used for general guidance only. First Solar
may update or modify box without notice.
845mm
1067mm
1372mm
Modules should be packed starting in the center of the 50/54-pack box and moving outward symmetri-
cally towards the front and back to ensure weight balance is maintained - Figure 6.
Two persons should be use to load modules when one person cannot walk into the box for safe lifting.
Modules should be packed face to face in pairs within each slot, along with re-used paper separator to
minimize breakage risk due to transport/vibration. The clip shown in Figure 7 is only used to keep the
paper separator in place until another module can be placed in the slot.
Figure 6: Modules packed for even weight Figure 7: Reusable paper separator to be placed
distribution between front faces of modules
www.jinkosolar.com
(4BB)
JKM320PP-72-V
305-320 Watt
POLY CRYSTALLINE MODULE
Positive power tolerance of 0/+3%
ISO9001:2008、ISO14001:2004、OHSAS18001
certified factory.
IEC61215、IEC61730 certified products.
KEY FEATURES
System Voltage:
The maximum voltage is promoted to 1500V and the module strings are
extended by 50% which reduces the overall system BOS.
The Eagle module can pass maximum voltage 1500V PID testing under 60℃/85%RH
condition to ensure the outdoor durability and energy output via high-voltage
resistance technology.
High Efficiency:
High module conversion efficiency (up to 16.49%), through innovative
manufacturing technology.
Low-light Performance:
Advanced glass and solar cell surface texturing allow for excellent
performance in low-light environments.
MCS
linear performance warranty
100%
Guaranteed Power Performance
80.7%
years
1 5 12 25
Engineering Drawings Electrical Performance & Temperature Dependence
992 40 942
Ⅱ
Current-Voltage & Power-Voltage Temperature Dependence
Junction box Curves (305W) of Isc,Voc,Pmax
100
XXXXXXXXXXXXXXXXXXXX
Ⅰ
Ⅲ Label
Installing Holes
10 315
L
1956
4 9
Ø
2- 270
1360
860
8
Grounding Holes
7 225 Isc
6
180 Voc
5
Cathode - + Anode 4
135 Pmax
Connector
A A 3 90
2
45
1
0 0
0 5 10 15 20 25 30 35 40 45
XXXXXXXXXXXXXXXXXXXX
Ⅰ Ⅲ
9 5.5
Mechanical Characteristics
CellType Poly-crystalline156×156mm(6inch)
40
55 5 7.7
4.
3
8
No.ofcells 72(6×12)
55
14
Dimensions 1956×992×40mm(77.01×39.05×1.57inch)
35
Ⅱ Weight 26.5kg(58.4lbs.)
FrontGlass 4.0mm,HighTransmission,LowIron,TemperedGlass
Packaging Configuration Frame AnodizedAluminiumAlloy
(Twoboxes=Onepallet) JunctionBox IP67Rated
25pcs/box,50pcs/pallet,600pcs/40'HQContainer OutputCables TÜV1×4.0mm,Length:900mmorCustomizedLength
²
SPECIFICATIONS
OperatingTemperature(℃) -40℃~+85℃
Maximumseriesfuserating 15A
Powertolerance 0~+3%
TemperaturecoefficientsofPmax -0.40%/℃
TemperaturecoefficientsofVoc -0.30%/℃
TemperaturecoefficientsofIsc 0.06%/℃
Nominaloperatingcelltemperature(NOCT) 45±2℃
* Powermeasurementtolerance:±3%
The company reserves the final right for explanation on any of the information presented hereby. EN-MKT-320P-V_1.0_rev2015
PV MODULE DRAWING (CRYSTALLINE) - JinKo – Installation Manual
JinkoSolar
Photovoltaic Module
Installation Manual
1 General Information 1
1.1 Overview 1
Contents 1.2 Applicable Products 1
1.3 Warnings 4
2. Installation 6
2.1 Installation safety 6
2.2 Installation Condition 7
2.2.1 Climate condition 7
2.2.2 Site selection 7
2.2.3 Tilt angle selection 8
2.3 Mechanical Installation introduction 8
2.3.1 Fixation with screws 9
2.3.2 Fixation with clamps at long sides of frames 13
2.3.3 Fixation with clamps at short side of the frames 19
5 Electrical specification 25
16 6 Disclaimer of Liability 26
Edition 03/2015
1. General Information
1.1 Overview
Thanks for choosing Jinko Solar PV modules. In order to ensure the PV modules to
be installed correctly, please read the following operation instructions carefully before
modules installed and used.
Please remember that the products would generate electricity and certain safety
measures need to be taken to avoid danger.
- 1-
JKMxxxP-72 (xxx=250-340, in steps of 5, 72 cells)
JKMxxxP-72-J (xxx=250-340, in steps of 5, 72 cells)
JKMxxxPP-72 (xxx=250-340, in steps of 5, 72 cells)***
JKMxxxPP-72-J (xxx=250-340, in steps of 5, 72 cells)
JKMxxxP-72-J4 (xxx=250-340, in steps of 5, 72 cells)***
JKMxxxPP-72-J4 (xxx=250-340, in steps of 5, 72 cells)
JKMxxxP-72(Plus) (xxx=250-340, in steps of 5, 72 cells)
JKMxxxPP-72(Plus) (xxx=250-340, in steps of 5, 72 cells)
JKMxxxP-60-I (xxx=210-280, in steps of 5, 60 cells)
JKMxxxP-60 (xxx=210-280, in steps of 5, 60 cells)
JKMxxxP-60-J(xxx=210-280, in steps of 5, 60 cells)
JKMxxxPP-60 (xxx=210-280, in steps of 5, 60 cells)
JKMxxxPP-60-J (xxx=210-280, in steps of 5, 60 cells)
JKMxxxP-60-J4 (xxx=210-280, in steps of 5, 60 cells)
JKMxxxPP-60-J4 (xxx=210-280, in steps of 5, 60 cells)
JKMxxxP-60(Plus) (xxx=210-280, in steps of 5, 60 cells)
JKMxxxPP-60(Plus) (xxx=210-280, in steps of 5, 60 cells)
JKMxxxP-48 (xxx=170-225, in steps of 5, 48 cells)
JKMxxxPP-48 (xxx=170-225, in steps of 5, 48 cells)
JKMxxxPP-48-J (xxx=170-225, in steps of 5, 48 cells)
JKMxxxPP-48(Plus) (xxx=170-225, in steps of 5, 48 cells)
JKMxxxPP-48-J4 (xxx=170-225, in steps of 5, 48 cells)
JKMxxxP-72B (xxx=250-340, in steps of 5, 72 cells)
JKMxxxP-60B (xxx=210-280, in steps of 5, 60 cells)
JKMSxxxP-72 (xxx=250-340, in steps of 5, 72 cells)
JKMSxxxP-72-J (xxx=250-340, in steps of 5, 72 cells)
JKMSxxxP-72-J4 (xxx=250-340, in steps of 5, 72 cells)
JKMSxxxP-72(Plus) (xxx=250-340, in steps of 5, 72 cells)
JKMSxxxP-60(xxx=210-280, in steps of 5, 60 cells)
JKMSxxxP-60-J (xxx=210-280, in steps of 5, 60 cells)
JKMSxxxP-60-J4 (xxx=210-280, in steps of 5, 60 cells)
JKMSxxxP-60(Plus) (xxx=210-280, in steps of 5, 60 cells)
JKMSxxxP-48-J (xxx=170-225, in steps of 5, 48 cells)
JKMSxxxP-48-J4 (xxx=170-225, in steps of 5, 48 cells)
JKMSxxxP-48(Plus) (xxx=170-225, in steps of 5, 48 cells)
Notes:
*B: module with black back sheet
**JKMS: the smart module
***L: module with quasi-mono cell
***PP: the EAGLE Series module
***-J4:with solar cell types with 4 busbars
*** (Plus):the eagle+ Series module
Make sure the array of modules installed within the Maximum permitted system
voltage and the rating current and voltage of the sub-equipments such as regulators
and inverters. The maximum permitted system voltage (DC) of the modules sold in
Europe is 1000V
The assembly is to be mounted over a fire resistant roof covering rated for the
application. Before mounting the module, please consult your local building
department to determine approved roofing materials.
The modules are qualified for application class A: Hazardous voltage (IEC 61730:
higher than 50V DC; EN 61730: higher than 120V), hazardous power applications
(higher than 240W) where general contact access is anticipated (Modules qualified
for safety through EN IEC 61730-1 and -2 within this application class are considered
to meet the requirements for Safety Class II.
- 3-
1.3 Warnings
To reduce the risk of electrical shocks or burns, modules may be covered with an
opaque material during installation to avoid shocks or burns.
The installation work of the PV array can only be done under the protection of
sun-sheltering covers or sunshades and only qualified person can install or
perform maintenance work on this module.
Follow the battery manufacture„s recommendations if batteries are used with
module.
Do not use this module to replace or partly replace roofs and walls of living
buildings.
Do not install modules where flammable gas may be present.
Do not touch live terminals with bare hands. Use insulated tools for electrical
connections.
- 4-
Use insulated tools for
electrical connection
Do not remove any part installed by Jinko Solar or disassemble the module.
All instructions should be read and understood before attempting to install, wire,
operate and maintain the module.
Please don‟t lift up PV modules using the attached cables or the junction box.
All PV systems must be earthed. If there is no special regulation, please follow
the National Electrical Code or other national code.
Under normal conditions, a photovoltaic module is likely to experience conditions
that produce more current and/or voltage than reported at standard test
conditions. Accordingly, the value of Isc and Voc marked on this module should
be multiplied by 1.25 when determining component voltage ratings, conductor
current ratings, fuse sizes, and size of controls connected to the PV output.
Once the PV module has been shipped to the installation site, all of the parts
should be unpacked properly with care.
Do not stand or step on the PV module like below pictures show, this is prohibited
and there can be risks of micro-crack which may cause a sharp decline of
module‟s power performance; what‟s more, it may threat your safety.
Only PV modules with the same cell size should be connected in series.
During all transportation situations, please make sure no huge shock for the
vehicle or the modules, as this may damage the module or lead the cell to be
crack.
During all transportation situation, never let the module fall down from the vehicle,
house or hands. This will break the cells of the modules.
- 5-
Do not clean the glass with chemicals.
Do not disconnect any of the modules when it is under load.
2. Installation
Always wear protective head gear, insulating gloves and safety shoes (with
rubber soles).
Keep the PV module packed in the carton until installation.
Do not touch the PV module unnecessarily during installation. The glass surface
and the frame may be hot. There is a risk of burns and electric shock.
Do not work in rain, snow or windy conditions.
Due to the risk of electrical shock, do not perform any work if the terminals of the
PV module are wet.
Use insulated tools and do not use wet tools.
When installing PV modules, do not drop any objects (e.g., PV modules or tools).
Make sure flammable gasses are not generated or present near the installation
site.
Insert interconnect connectors fully and correctly. Check all connections.
The interconnect cable should be securely fastened to the module frame, Cable
support should be done in a way to avoid the connector from scratching or
impacting the back sheet of the module.
Do not touch the terminal box and the end of the interconnect cables (connectors)
with bare hands during installation or under sunlight, regardless of whether the
PV module is connected to or disconnect from the system.
Do not expose the PV module to excessive loads on the surface of the PV
module or twist the frame.
Do not hit or put excessive load on the glass or back sheet, this may break the
cells or cause micro crack.
During the operation, don‟t use sharp tools to wipe the back sheet and glass. It
would leave scratch on the module.
Do not drill holes on the frame. It may cause corrosion of the frame.
For roof mounting structure, when install the modules, please try to follow the
“from top to bottom” and/or “from left to right” principle, and don‟t step on the
module, that will damage the module and would be dangerous for personal
safety.
- 6-
2.2 Installation Condition
﹡Note: The mechanical load bearing (include wind and snow loads) of the module is
based on the mounting methods. The professional system installer must be
responsible for mechanical load calculation according to the system design.
- 7-
generate hydrogen gas when charging, which can be explosive. Do not light matches
or create sparks near the battery bank. When a battery is installed outdoors, it should
be placed in an insulated and ventilated battery case specifically designed for the
purpose.
Do not install the PV module in a location where it would be immersed in water or
continually exposed to water from a sprinkler or fountain etc.
The tilt angle of the PV module is measured between the surface of the PV module
and a horizontal ground surface (Figure 1). The PV module generates maximum
output power when it faces the sun directly.
For standalone systems with batteries where the PV modules are attached to a
permanent structure, the tilt angle of the PV modules should be selected to optimize
the performance based on seasonal load and sunlight. In general, if the PV output is
adequate when irradiance is low (e.g., winter), then the angle chosen should be
adequate during the rest of the year. For grid-connected installations where the PV
modules are attached to a permanent structure, PV modules should be tilted so that
the energy production from the PV modules will be maximized on an annual basis.
Solar PV modules usually can be mounted by using the following methods: screws
and clamps.
- 8-
﹡Note:
1) All installation methods herein are only for reference, and Jinko solar will not
provide related mounting components, the system installer or trained professional
personnel must be responsible for the PV system‟s design, installation, and
mechanical load calculation and security of the system.
2) Before installing, you should confirm below important things:
1) Visual check before installation, to make sure there is no bug in the packing
and junction box as well as the surface of module, If have , remove and clean
it .
2) Check the series number is right or not.
3) The modules installed at screws and the normal PV modules installed at the long
sides with clamps are designed to meet a maximum positive (or downward)
pressure of 5400Pa and negative (or upward) pressure of 2400 Pa (Refer to the
mentioned module type in Table 1 and 2 in this manual). The light PV module and
the modules installed at the short sides with clamps are designed to meet a
maximum positive (or downward) pressure of 2400Pa and negative (or upward)
pressure of 2400 Pa (Refer to the mentioned module type in Table 3 and 4 in this
manual). When mounting modules in snow-prone or high-wind environments,
Special care should be taken to mount the modules in a manner that provides
sufficient design strength while meeting local code requirements.
The frame of each module has 8 mounting holes (Length* Width: 14mm*9mm) used
to secure the modules to support structure. Always use all the eight mounting holes to
secure the modules. The module frame must be attached to a mounting rail using M8
corrosion-proof screws together with spring washers and flat washers in eight
symmetrical locations on the PV module. The applied torque should be big enough to
fix it steadily. Please find detailed mounting information in the below illustration,
- 9-
Figure 2: PV module installed with Screw fitting method
- 10 -
JKMXXXP-60
JKMXXXP-60-I Module:1650*992
JKMXXXP-60-J Frame:40*30 & 40*35 & 45*35 & 50*35
JKMXXXPP-60 & 35*35
JKMXXXPP-60-J
6 inch Poly 6*10 210~280Wp
JKMxxxP-60-J4
JKMxxxPP-60-J4
Module:1650*990
JKMxxxP-60(Plus)
Frame: 40*35
JKMxxxPP-60(Plus)
JKMXXXP-60B
JKMXXXM-60
Module:1650*992
JKMXXXM-60-J
6 inch Mono 6*10 210~280Wp Frame:40*30 & 40*35 & 45*35 & 50*35
JKMxxxM-60-(Plus)
& 35*35
JKMXXXM-60B
JKMXXXP-72
JKMXXXP-72-J
JKMXXXPP-72
Module:1956*992
JKMXXXPP-72-J 6 inch Poly 6*12 250~340Wp
Frame: 40*30 & 40*35 & 50*35
JKMSxxxP-72-J4
JKMSxxxP-72(Plus)
JKMXXXP-72B
JKMXXXM-72
JKMXXXM-72-J Module:1956*992
6 inch Mono 6*12 250~335Wp
JKMxxxM-72(Plus) Frame: 40*30 & 40*35 & 50*35
JKMXXXM-72B
6 inch Module:1956*992
JKMXXXP-72L 6*12 255~330Wp
Quasi-mono Frame: 40*30 & 40*35 & 50*35
6 inch Module:1650*992
JKMXXXP-60L 6*10 215~275Wp
Quasi-mono Frame:40*30 & 40*35 & 50*35 & 35*35
Module:1580*808
JKMSXXXM-72
5 inch Mono 6*12 160~215 Frame:35*35 & 40*30 & 40*35 & 45*35
JKMSXXXM-72-J
& 50*35
JKMSXXXM-96 Module:1575*1082
5 inch Mono 8*12 210~280
JKMSXXXM-96-J Frame: 40*30 & 40*35 & 45*35 & 50*35
JKMSXXXP-60
JKMSXXXP-60-J Module:1650*992
6 inch Poly 6*10 210~280
JKMSxxxP-60-J4 Frame: 40*30 & 40*35 & 45*35 & 50*35
JKMSxxxP-60(Plus)
- 11 -
JKMSXXXP-72
JKMSXXXP-72-J Module:1956*992
6 inch Poly 6*12 250~340
JKMSxxxP-72-J4 Frame: 40*30 & 40*35 & 50*35
JKMSxxxP-72(Plus)
JKMSXXXM-72
Module:1956*992
JKMSXXXM-72-J 6 inch Mono 6*12 250~335
Frame: 40*30 & 40*35 & 50*35
JKMSxxxM-72(Plus)
6 inch
Module:1956*992
JKMSXXXP-72L Quasi- 6*12 255~330
Frame: 40*30&50*35
Mono
6 inch Module:1650*992
JKMSxxxP-60L 6*10 215~275
Quasi-mono Frame: 40*30 & 50*35
JKMxxxM-48 Module:1324*992
6 inch Mono 6*8 170~220
JKMxxxM-48-J Frame: 40*35
JKMSxxxM-48-J Module:1324*992
6 inch Mono 6*8 170~220
JKMSxxxM-48(Plus) Frame: 40*35
JKMxxxP-48
JKMxxxPP-48
Module:1324*992
JKMxxxPP-48-J4 6 inch Poly 6*8 170~225
Frame: 40*35
JKMxxxPP-48-J
JKMxxxPP-48(Plus)
JKMSxxxP-48-J
Module:1324*992
JKMSxxxP-48-J4 6 inch Poly 6*8 170~225
Frame: 40*35
JKMSxxxP-48(Plus)
- 12 -
2.3.2 Fixation with clamps at long sides of frames
The applicable Products please refer to Table 2, and only allow using clamps at long
side of frames.
The module clamps should not come into contact with the front glass and must not
deform the frame. Be sure to avoid shadowing effects from the module clamps. The
module frame is not to be modified under any circumstances. When choosing this
type of clamp-mounting method, please be sure to use at least four clamps on each
module, two clamps should be attached on each long sides of the module. Depending
on the local wind and snow loads, if excessive pressure load is expected, additional
clamps or support would be required to ensure the module can bear the load. The
applied torque should be big enough to fix it steadily(about 8 Nm), for safety, you‟d
better follow the clamps manufacture‟s recommendation. Please find detailed
mounting information in the below illustration, the mounting place distance is
suggested bigger than J and less than K,as shown below.
- 13 -
Figure 3: PV module installed at long side with Clamp fitting method
JKMSXXXP-72
JKMSXXXP-72-J 6 inch 40*20 & 40*30 & 50*35
6*12 250~335 1956*992 280 480
JKMSxxxP-72-J4 Poly & 40*35
JKMSxxxP-72(Plus)
JKMSXXXM-72
6 inch 40*20 & 40*30 & 50*35
JKMSXXXM-72-J 6*12 250~335 1956*992 280 480
Mono & 40*35
JKMSxxxM-72(Plus)
6 inch
JKMSxxxP-60L Quasi- 6*10 215~275 1650*992 280 420 35*25 & 40*30 & 40*35
mono
6 inch
JKMSXXXP-72L 6*12 255~330 1956*992 280 480 40*30 & 40*35
Poly
- 14 -
JKMXXXM-72
35*25 & 30*20 & 35*35
JKMXXXM-72-I 5 inch
6*12 160~215 1580*808 300 400 & 40*30 & 40*35 &
JKMXXXM-72-J Mono
45*35 & 50*35
JKMXXXM-72B
JKMXXXM-96
JKMXXXM-96-I 5 inch 40*20 & 40*30 & 40*35
8*12 210~285 1575*1082 280 400
JKMXXXM-96-J Mono & 45*35 & 50*35
JKMXXXM-96B
JKMXXXP-60
JKMXXXP-60-I 35*25 & 40*30 &
JKMXXXP-60-J 1650*992 40*20 & 40*35 &
JKMXXXPP-60 45*35 & 50*35
JKMXXXPP-60-J 6 inch
6*10 210~280 280 420
JKMxxxP-60-J4 Poly
JKMxxxPP-60-J4
JKMxxxP-60(Plus) 1650*990 40*20 & 40*35
JKMxxxPP-60(Plus)
JKMXXXP-60B
JKMXXXM-60
35*25 & 40*30 &
JKMXXXM-60-J 6 inch
6*10 210~280 1650*992 280 420 40*20 & 40*35 &
JKMxxxM-60-(Plus) Mono
45*35 & 50*35
JKMXXXM-60B
JKMXXXP-72
JKMXXXP-72-J
JKMXXXPP-72
6 inch 40*30 & 40*20 & 40*35
JKMXXXPP-72-J 6*12 250~340 1956*992 280 480
Poly & 50*35
JKMSxxxP-72-J4
JKMSxxxP-72(Plus)
JKMXXXP-72B
JKMXXXM-72
JKMXXXM-72-J 6 inch 40*20 & 40*30 & 50*35
6*12 250~335 1956*992 280 480
JKMxxxM-72(Plus) Mono & 40*35
JKMXXXM-72B
6 inch
JKMXXXP-60L 6*10 215~275 1650*992 280 420 35*25 & 40*30 & 40*35
Poly
6 inch
JKMXXXP-72L 6*12 255~330 1956*992 280 480 40*30 & 40*35
Poly
JKMxxxM-48 6 inch
6*8 170~220 1324*992 240 270 40*35
JKMxxxM-48-J Mono
- 15 -
JKMSxxxM-48-J 6 inch
6*8 170~220 1324*992 240 270 40*35
JKMSxxxM-48(Plus) Mono
JKMxxxP-48
JKMxxxPP-48
6 inch
JKMxxxPP-48-J4 6*8 170~225 1324*992 240 270 40*35
Poly
JKMxxxPP-48-J
JKMxxxPP-48(Plus)
JKMSxxxP-48-J
6 inch
JKMSxxxP-48-J4 6*8 170~225 1324*992 240 270 40*35
Poly
JKMSxxxP-48(Plus)
Max. Pressure: 5400Pa mechanical load
Table 2: Mechanical dimensions when modules installed at long side with Clamp fitting method
2) Light PV module:
- 16 -
Figure 4: Light PV module installed at long side with Clamp fitting method
Dimension (mm*mm)
- 18 -
2.3.3 Fixation with clamps at short side of the frames
The applicable Products please refer to Table 4, only refer to the Normal PV module,
and only allow using clamps at short side of frames.
The considerations and requirements about mounted by using clamps, please refer to
the instructions in 2.3.2, and find detailed mounting information in the below
illustration, the mounting place distance is suggested bigger than J and less than K,
as shown below.
- 19 -
Cell Cell Pmax Dimension(mm)
Module type
type quantity (Wp) A*B J K Frame
JKMSXXXP-60
JKMSXXXP-60-J 6 inch
6*10 210~280 1650*992 50 240 40*35
JKMSxxxP-60-J4 Poly
JKMSxxxP-60(Plus)
JKMSXXXM-60
6 inch
JKMSXXXM-60-J 6*10 210~280 1650*992 50 240 40*35
Mono
JKMSxxxM-60(Plus)
JKMSXXXP-72
JKMSXXXP-72-J 6 inch
6*12 250~335 1956*992 50 240 40*35
JKMSxxxP-72-J4 Poly
JKMSxxxP-72(Plus)
JKMSXXXM-72
6 inch
JKMSXXXM-72-J 6*12 250~335 1956*992 50 240 40*35
Mono
JKMSxxxM-72(Plus)
6 inch
JKMSxxxP-60L Quasi- 6*10 215~275 1650*992 50 240 40*35
mono
6 inch
JKMSXXXP-72L 6*12 255~330 1956*992 50 240 40*35
Poly
JKMXXXM-72
JKMXXXM-72-I 5 inch
6*12 160~215 1580*808 50 200 40*35
JKMXXXM-72-J Mono
JKMXXXM-72B
JKMXXXM-96
JKMXXXM-96-I 5 inch
8*12 210~285 1575*1082 50 260 40*35
JKMXXXM-96-J Mono
JKMXXXM-96B
JKMXXXP-60
JKMXXXP-60-I
JKMXXXP-60-J 1650*992 40*35
JKMXXXPP-60
JKMXXXPP-60-J 6 inch
6*10 210~280 50 240
JKMxxxP-60-J4 Poly
JKMxxxPP-60-J4
JKMxxxP-60(Plus) 1650*990 40*35
JKMxxxPP-60(Plus)
JKMXXXP-60B
- 20 -
JKMXXXM-60
JKMXXXM-60-J 6 inch
6*10 210~280 1650*992 50 240 40*35
JKMxxxM-60-(Plus) Mono
JKMXXXM-60B
JKMXXXP-72
JKMXXXP-72-J
JKMXXXPP-72
6 inch
JKMXXXPP-72-J 6*12 250~340 1956*992 50 240 40*35
Poly
JKMSxxxP-72-J4
JKMSxxxP-72(Plus)
JKMXXXP-72B
JKMXXXM-72
JKMXXXM-72-J 6 inch
6*12 250~335 1956*992 50 240 40*35
JKMxxxM-72(Plus) Mono
JKMXXXM-72B
6 inch
JKMXXXP-60L 6*10 215~275 1650*992 50 240 40*35
Poly
6 inch
JKMXXXP-72L 6*12 255~330 1956*992 50 240 40*35
Poly
JKMxxxM-48 6 inch
6*8 170~220 1324*992 50 240 40*35
JKMxxxM-48-J Mono
JKMSxxxM-48-J 6 inch
6*8 170~220 1324*992 50 240 40*35
JKMSxxxM-48(Plus) Mono
JKMxxxP-48
JKMxxxPP-48
6 inch
JKMxxxPP-48-J4 6*8 170~225 1324*992 50 240 40*35
Poly
JKMxxxPP-48-J
JKMxxxPP-48(Plus)
JKMSxxxP-48-J
6 inch
JKMSxxxP-48-J4 6*8 170~225 1324*992 50 240 40*35
Poly
JKMSxxxP-48(Plus)
Max. Pressure: 2400Pa mechanical load
Table 4: Mechanical dimensions when modules installed at short side with Clamp fitting method
- 21 -
3. Wiring and connection
a) Before this procedure, please read the operation instructions of the PV system
carefully. Make wiring by Multi-connecting cables between the PV modules in
series or parallel connection, which is determined by user‟s configuration
requirement for system power, current and voltage.
b) PV module connected in series should have similar current. Modules must not be
connected together to create a voltage higher than the permitted system
voltage(1000VDC), as reference the maximum number of modules in series (N)
can be easily calculated by dividing the Maximum System Voltage of the modules
by the respective Voc value of the module. Any more please always take into
consideration the variation of the voltage under different temperatures, the Voc of
the modules will be rise when the temperature drops.
For example: with JKM190M-72 modules (Max. System voltage is 1000V) the
maximum series modules configuration number should NEVER can exceed N= 22
(1000V/45.2V = 22.1)
c) PV module connect in parallel should have similar voltage. As reference the
maximum number of modules in parallel (M) can be easily calculated by dividing
the maximum rated current (indicated in the electrical specification below) by Isc
value of the module, and then plus 1. Any more please always take into
consideration the variation of the current under different temperatures, the Isc of
the modules will be rise when the temperature goes up.
For example: with JKM190M-72 modules (the maximum rated current is 10A) the
maximum parallel modules configuration number should never exceed M= 2
(10A/5.56A+1=2.8).
d) Open the connection box of the control system and connect the cabled from the PV
arrays to the connection box in accordance with the installation indication of the PV
control systems. The cross-sectional area and cable connector capacity must
satisfy the maximum short-circuit of PV system (For a single component, we
recommended the cross-sectional area of cables is 4mm2 and the rated current of
connectors is more than 10A), otherwise cables and connectors will become
overheating for large current. Please pay attention: the temperature limit of cables
is 85℃ and the temperature limit of connector is 105℃
e) All module frames and mounting racks must be properly grounded in accordance
- 22 -
with local and national electrical codes. Attach the equipment grounding conductor
to the module frame using the hole and hardware provided. Not that a stainless
steel star washer is used between the ground wire and module frame (see picture
below).This washer is used to avoid corrosion due to dissimilar metals. Tighten the
screw securely.
- 23 -
4. Maintenance and care
Inspect the Modules visually to find whether there are appearance defects, the
following need to be paid more attention especially:
a) Whether the glass is broken;
b) No sharp objects are in contact with the PV module surfaces
c) PV modules are not shaded by unwanted obstacles and/or foreign material
d) Corrosion along the cells‟ bus-bar. The corrosion is caused by the dampness
infiltrated into the Modules because that the surface encapsulation materials are
damaged during the installation or transportation.
f) Whether there is burning vestige on the backsheet.
g) Check fixing screws and mounting brackets are tight, adjust and tighten as
necessary.
4.2 Cleaning
a) A built up of dust or dirt on the module(s) front face will result in a decreased
energy output. Clean the panel(s) preferably once per annum if possible
(depend on site conditions) using a soft cloth dry or damp, as necessary. Water
with high mineral content may leave deposits on the glass surface and is not
recommended.
b) Never use abrasive material under any circumstances.
c) In order to reduce the potential for electrical and thermal shock, Jinko
recommends cleaning PV modules during early morning or late afternoon hours
when solar radiation is low and the modules are cooler, especially in regions
with hotter temperatures.
d) Never attempt to clean a PV module with broken glass or other signs of
- 24 -
exposed wiring, as this presents a shock hazard.
5. Electrical specification
The module electrical rating are measured under Standard Test Conditions, which
are 1000W/m2, irradiance with AM 1.5 spectrum and 25 deg (77°F) ambient
temperature. The module might produce more or less voltage or current than rating
value in uncertainty condition. Accordingly, the values of ISC and VOC marked on this
module should be multiplied by a factor of 1.25 when determining component voltage
ratings, conductor current ratings, fuse sizes, and size of controls connected to the
PV output.
- 25 -
6. Disclaimer of Liability
Because the use of the manual and the conditions or methods of installation,
operation, use and maintenance of photovoltaic (PV) product are beyond
Jinko‟s control, Jinko does not accept responsibility and expressly disclaims
liability for loss ,damage, or expense arising out of or in any way connected
with such installation, operation, use or maintenance.
No responsibility is assumed by Jinko for any infringement of patents or other
rights of third parties, which may result from use of the PV product. NO license
is granted by implication or otherwise under any patent or patent rights.
The information in this manual is based on Jinko‟s knowledge and experience
and is believed to be reliable, but such information including product
specification (without limitations) and suggestions do not constitute a warranty,
expresses or implied. Jinko reserve the right to change the manual, the PV
produce, the specifications, or product information sheets without prior notice.
Note
- 26 -
Global Sales & Marketing Center Jiangxi Manufacture Base Zhejiang Manufacture Base
16F, Building No.2 No.1 Jinko Road, No.58 Yuanxi Road,
428# South Yang Gao Road, Shangrao Economic Development Zone, Haining Yuanhua Industrial Park,
Shanghai, China 200127 Jiangxi Province, China 334100 Zhejiang Province, China 314416
Tel: +86 21 6061 1799 Tel:+86 793 858 8188 Tel: +86 573 8798 5678
Fax: +86 21 6876 1115 Fax:+86 793 846 1152 Fax: +86 573 8787 1070
Installation Manual of
Ground Mounting System
1
Contents
1. Safety instruction .................................................................................................................................... 1
5. Mounting structure Plane Layout and Helical Screw Pile Installation.................................................. 14
5.1 Determination of Helical Screw Pile Installation Position and Size ............................................... 14
2
6.2 Installation Steps ............................................................................................................................. 17
12.1 Appendix 1: Solar Philippines PV Mounting Structure Design V1.0 ........................................... 29
3
1. Safety instruction
The mounting structure can only be installed, operated and maintained by professional personnel passing
the relevant training.
During the installation, operation and maintenance of the equipment, the operators must adhere to local
safety specification and relevant operation instruction, or it may cause personal injury or equipment
damage. Safety precautions mentioned in the manual can only be regarded as the supplement of local safety
specification.
The company will assume no responsibility caused by any violation against general safety operation
requirement, or equipment design, production and usage safety standards.
1
2. Installation Engineering Preparation
Abstracts
It mainly introduces necessary external conditions and unpacking inspection process prior to installation.
Helmet -
Gloves -
2
Total station -
Gradienter -
Meter rule,
5m, 30m
Tape measure
Pen -
3
Unpacking inspection:
1) Check if the packing box has any damage, and make records.
2) Open the packing box according to unpacking steps.
3) Check if the goods quantity in the box is correct according to packing list attached in the packing box.
4) Check if all goods in the box are in good condition. Damaged goods can be replaced by spare parts or
identical objects in the standby goods, and then making request to change the goods timely.
5) Make relevant records.
Inspection records such as Unpacking Acceptance Report shall go through countersigning by company staff
and customers, and return to market engineering department and its responsible office.
4
3. Installation Procedure
Abstracts
Detailed procedures for Solar Philippines 200Mw PV Project mounting structure installation will be
introduced below.
Column installation
Main-Rail installation
Strut installation
Rail installation
PV module installation
Acceptance
5
3.2 Determine Installation Size
It gives detailed introduction to plane layout size.
See Article IV for concrete content.
6
3.10 Installation Precautions
(1) Please read relevant drawings and installation manual carefully prior to installation.
(2) During installation, it shall strictly abide by relevant operation method and steps, and make
corresponding protection measures to guarantee personal safety.
(3) Check the mounting size after the installation.
7
4. Parts list
Pre-assembled Helical
6 TBD Q235B 16
Screw Pile
8
9 Angle steel 75×50×8×50 Q345B 32
Pre-assembled Middle
11 50×28×80 6063-T6 80
Clamp
SUS 304
16 Self-tapping screw ST5.5x25 32
+SCM435
9
2 Hinged Base 190×158×3.0 Q235B 190 1
10
3 Hexagon flange Bolt M10×30 8.8 2
3 PE Block - PE 1
7. Pre-assembled M10x30
8. Pre-assembled Connector
No. Part P/N Mat. Len.(mm) Qua.
11
No. Part P/N Mat. Len.(mm) Qua.
4 Flat Washer M8 A2 1
5 Spring Washer M8 A2 1
4 Flat Washer M8 A2 1
5 Spring Washer M8 A2 1
M12x25 Puller blot
Spring Washer
Flat Washer
Nut
Spring Washer
PE Block
Nut Block
12
Pre-assembled Back Column Pre-assembled Strut
Joint connector Joint connector
Strut
Column 900/1500 900/1100
Hexagon Bolt M8x65
Hexagon Bolt M8x45
Flat Washer
Flat Washer
Spring Washer
Spring Washer
Side Clamp Middle Clamp
Nut block
Nut Block
M10x25 Puller blot
connector
Note:Pre-assembled in workshop
13
5. Mounting structure Plane Layout and
Helical Screw Pile Installation
Abstracts
5.1.1 Determine the Installation Position and Size of Helical Screw Pile
14
3. Determine installation position of Helical Screw Pile according to module layout drawing (as shown
in the figure).
Installation Tolerance:
Layout (2x21)
Lateral Section
(3) Piling machine and its working diagram (as shown in the figure)
15
16
6. Column Installation
6.1 Brief Introduction to Foundation
Column specification: Φ60mm×2.5mm (as shown in the figure):(Column 900/1500mm)
17
(2) Install the seal ring on the top of the Helical Screw Pile;
(3) Insert the column in the Helical Screw Pile, and adjust the position, fasten the puller Bolt, fasten the
puller Bolt with spanner in 40N.m torque.
(4) After the rail installation, install the self-tapping screw st5.5(About 200mm length the bottom of the
Column to top of the screw pile, as shown below). ( See appendix 3:Tapping screw operation notes)
(5) Check mounting size as per engineering drawing, and make sure the connection between column and
Helical Screw Pile is fastened.
Column
Connector
M12×25Puller Bolt
Seal ring
18
6.3 Result Diagram after installing groups of columns
19
7. Main-Rail Installation
7.1Material Specification
Main-Rail specification is U41mm×62mm×2.0mm, L=3200mm(as shown in the figure).
7.2Installation Steps
(1) Connect the main-Rail 3200 with column 900 and 1500, both columns shall be connected with Bolts,
whose nuts shall be fastened by wrench, torque moment is 25N.m(as shown in the figure). And then,
fasten nuts on U Connector-2 with wrench, torque moment is 25N.m.
Main-Rail 3200
Column 1500
Column 900
20
(2) Check the mounting size as per engineering drawing; Main-Rail and Column shall be fastened
soundly (as shown in the figure).
21
8.Strut Installation
8.1 Material Specification
Strut specification is Φ40x2.0, 900/1100.
(2) Mount the strut on to the column with the connector, with Hexagon flange Bolt M10×30.
(4) Check the mounting size as per engineering drawing; strut, Main-Rail and post shall be fastened
soundly (as shown in the figure).
Column
Connector
Strut
22
9.Sub-Rail Installation
9.1 Material Specification
1. Sub-Rail specification is C40x80x2.5mm(as shown in the figure)
4. Pre-assembled Nut block and Pre-assembled Bolt M10×30(as shown in the figure)
23
9.2 Installation Steps
1) Adopt L connector for the butt joint of Sub-Rail, and fasten it with Pre-assembled Hexagon flange Bolt
M10×30.
Flat Washer
Spring Washer
Nut 0~20mm gap between beam to beam
Sub-Rail U connector
Hexagon flange
Bolt M10×30
2) Put Nut block with PE Block into Mail-Rail; Cross the well-connected rail over Main-Rail vertically,
Connect them with Hexagon flange Bolt M10×30; Check the position as per engineering drawing, and then,
fasten them with wrench, torque 25N.m.
Sub-Rail Pre-assembled Nut block
Main-Rail
3)Check the mounting size as per engineering drawing, trial beam and rail shall be connected soundly(as
shown in the figure).
24
Main-Rail
Sub-Rail
25
10.Module Installation
10.1 Module Specification:
The specification is 1960mm×990mm×40mm(as shown in the figure)
Nut Block
Nut Block
26
10.2 Installation Steps
1) Put the PV module horizontally on the rail.
Check if the installation sizes are correct, and connect the modules soundly with Clamps (Mid-clamp
and Side-clamp), torque 13N.m; (See appendix 4: Attention on stainless steel fastener installation )
27
11. Installation Inspection and Acceptance
11.1 Installation Inspection and Acceptance
The overall inspection after mounting includes inspection on overall sizes and soundness.
28
12. Appendix
12.1 Appendix 1: Solar Philippines PV Mounting Structure Design
V1.0
29
12.2 Appendix 2: Fasteners installation torque:
M10×30 2004
M10×65 2004
M12×25 2004
M8×60(45) 2004
30
12.3 Appendix 3: Tapping screw operation notes
1. Preparation before operation
(1) The operating personnel should wear protective glasses in advance and avoid debris flying into the eye to
cause accidents during operation.
(2) Before operation, it must check the power is consistent with voltage on the power tool, which avoid connect
the wrong power source.
(3) Please double‐check the machine is in insulation protection situation and make sure screw do not loose.
(4) Drilling tool must be put into magnetic sleeve as per self‐tapping screw specifications requirement.
(5) It must protect machine wire and prevent rolling and cutting all around the floor, also not allow pull the wire
onto oil‐water and cause corrosion.
(6) When machine replace the drill bit, it should unplug the machine off, then use special wrench and drill key, it
must prevent use non‐specialized tool to beat the drill.
(7) Remember not to overexert or skewed operated when drilling, make sure attach suitable drill bit, use
uniform force while operation..
(8) Master and skillfully operate control mechanism, loose screws and other functions.
2. Operating tips:
(1) Use formal magnetic sleeve to ensure self‐tapping screw sleeve can rely on its own magnetic force,
adsorbed on the sleeve, do not fall off and skew because of its own gravity during tapping.
(2) The operator should directly facing the nail holes to ensure self‐tapping screw exactly align to pile hole, the
hand drill is located in front of the body, in order to support stability.
(3) Two hands clench hand drill, one clench hand grip, the other clench other handle (or intermediate cover),
keep vertical as much as possible, in order to ensure smooth and maximum force;
(4) Tapping force should be uniform, when screw wire is completely screwing, closing force and release the
trigger switch, use electric drill inertia and screw remaining wire, otherwise it’s easy to make the operator
injured, even produce rigid damage for screw.
31
3. Safety considerations:
(1) Always wear protective glasses when operation, if use hammer drill, it wear a dust mask depending on
operating conditions.
(2) It should not wear loose clothing when working, if necessary, wear the sleeves, not wear work gloves, avoid
clothes or gloves to be involved in the rotating drill and caused injury.
(3) When use drilling tool, the required power outlets may not access lines, the power source should have
leakage protection switch to prevent short circuit.
(4) Do not use the drill bit which exceeding the range.
(5) It must completely stop rotating when replace the drill machine, and unplug the power source.
Deadlock often occurred in stainless steel, aluminum alloy and titanium alloy bolts. These alloy material has
anti‐corrosion performance. When the surface damage, they will produce a thin oxide layer to prevent further
corrosion. When the stainless steel bolt is locked tight, pressure between the threads and the heat will destroy
this oxide layer, which makes blocking or shear occur between threads, and adherent phenomenon happens
then. When this phenomenon continues, it will make the stainless steel fasteners completely locked and cannot
be removed or continue to lock any more. Usually a series of blocking – shear ‐ adherent –deadlock actions
occur just in a few seconds, so we have to prevent this phenomenon by the correct understanding to use this
kind of fasteners.
Operating considerations
1. Check the threads are coarse or not before using, any scrap iron or dirt between threads, these things
often leads to self‐lock.
2. Lubrication can be done before using fasteners: it is recommended to use butter, molybdenum disulfide,
mica, graphite, or talcum powder for lubrication. Currently paraffin processing is common for lubrication to
prevent locking.
3. The speed and power to screw‐in should be appropriate. It can’t be too fast and too much. Choose torque
32
wrench or socket wrench if possible, and avoid using adjustable wrench or electric wrench. Over‐quick
speed can lead to temperature rising sharply and lock.
4. The direction of force application must be noted, nuts must be perpendicular to the axis of the bolts when
screw‐in.
Attention on installation
1. See if there is any deformation, crevasse, iron filings, or dirt between the screw threads before to use,
these things often lead to deadlock.
2. Before installation, check whether there is damage on bolt antirust coating, bolts which antirust coating
has been damaged can’t be used.
3. When installation, torque should be follow torque meter of "appendix 2", not violent installation.
4. The speed and power to screw‐in should be appropriate. It can’t be too fast and too much. Choose torque
wrench or socket wrench if possible, and avoid using adjustable wrench or electric wrench. Over‐quick
speed will damage the surface of antirust coating.
5. The direction of force application must be noted, nuts must be perpendicular to the axis of the bolts
when screw‐in.
6. After the installation, the damage condition of bolt head should be checked, such as coating damaged,
need to replace the bolt, or spraying antirust coating (such as epoxy zinc‐rich paint).
Attention on maintenance:
1. According to the "ground structure maintenance manual", regularly inspect the bolts’ fastening situation
and rust situation.
2. When loose bolts have been found, Locking shall be done in accordance with the "appendix 2" torque
table.
3. If fasteners is rusty, rust removing and antirust treatment should be done according to the "ground
structure maintenance manual”;
33
12.6 Appendix 6: Warranty statement
Powerway Renewable Energy Co., Ltd ‐ Structure warranty statement
【Customer Information】
Company name
Installation Add
Installation product
【Customer Notice 】
1. About the warranty statement (hereinafter referred to as the "statement".), based on the content of
application by the applicant (including agents), Powerway issues. If the statement recorded content errors,
Powerway will not be able to admit warranty, so if recorded incorrectly, please put forward directly.
2. This statement guaranties free structure repair for the customer written in this statement. If the structures
resell and the owner changed, please submit the owner change notification.
3. If commission within the guarantee period, please show us your statement if you need free repair. (Please
note that if you can't show us this statement, we will be unable to guarantee.)
4. As this statement can't be issued again, please don't lost, keep safe.
5.When Commission repair, if the object part is not within the objects in this statement, business trip expenses
(the actual costs), and various funds will need to charge.
34
【Warranty Content】
1. The mounting structures produced by Powerway Renewable Energy Co.,Ltd (below,named【Powerway】.)
ensure wind speed below m/s.
(Due to Powerway, design wind speed has to be changed, we will ensure the wind speed after corresponding
benchmark change.)
2. The mounting structures produced by Powerway ensure snow thickness below cm.
(Due to Powerway, design snow thickness has to be changed, we will ensure the snow thickness after
corresponding benchmark change.)
3.If the mounting structures produced by Powerway are rust, and corrosion due to the deterioration of the
coating, we only guarantee the situation of obvious broken holes on the surface of steel.
4. If the performance or strength of original structure is in significantly damaged condition, Powerway can
replace some or all of the goods, all fees shall be borne by the Powerway.
【Warranty Period】
From delivery date recorded in this statement to 4 PM the day after year
35
EATON Crouse-Hinds Series – 1500 VDC Collection systems
Commercial Products
1500 VDC
Collection Systems
*Negative fused configurations available for positive grounded arrays. Replace F15 with NF15 in the catalog number.
Standoffs
G Standoffs support the Lexan Shield which covers live components
and protects against risk of shock.
Grounding Bar
I Grounding bar allows for termination of copper or aluminum
E ground inputs. Tin plated for corrosion resistance. Ground output
accepts a maximum of 250 MCM output. Custom ground lugs
available upon request.
A G
I DC Disconnnect Switch
H Rotary DC disconnect switch comes equipped with an external
handle, which allows for lock-out tag out. The disconnect switch is
intended to be used to manually make/break electrical connections
and disconnect modules from downstream components. Available
in 275A and 500A.
†Recommended (not to exceed). Each system is unique and the design should consider all factors including current de-rating.
*Based on labor and material savings versus traditional wiring.
~1/2 in.
Applications: Features:
• Home run harnesses are used to connect DC strings from • Custom-made Sunnector™ home run (sub-array) harnesses
a combiner or string inverter to the solar panels. Various provide flexibility while delivering cost savings to any large solar
configurations are available to support transferring power to a installation
collection system. Primary consideration are made for power loss, • Sunnector™ home run harnesses are designed for high voltage
current handling, string lengths, conduit fill and overall reliability in connection and power delivery to combiner boxes, sub-combiners
the system. or inverters used with monocrystalline and polycrystalline modules
• Designed for exposed or concealed wet or dry locations • Fully tested Sunnector™ home run harnesses arrive terminated,
bundled and spooled, replacing on-site long wire runs, bundling,
Material Characteristics: attachment and connector termination
• FoHS compliant • Home run harnesses can also be manufactured with easy-to-
read identification on each leg and on spools; spools can also be
• Cross linked polyethylene wire (XLPE or XLP)
labeled for proper job site placement
• Flammability meets UL 94 requirements; V0 rated • Fully tested for continuity for dependable field performance
• Improved durability and strain relief over traditional wiring
Certifications and Compliances:
• Available with #12, #10 or #8 AWG wires
• MC4, H4 and UTX Connectors UL certified to UL6703 & UL1703, • IP67 or IP68 waterproof rated dependent on connector type
TUV certified, IP67 or IP68 rated
• UV- and ozone-resistant
• Wire/cable UL certified to UL4703/UL854
• ID labeling available to communicate point-to-point connections in
• #10 AWG wire – 35A current capacity†
the field
• #12 AWG wire – 25A current capacity† • Rated for direct burial
• #14 AWG wire – 20A current capacity† • Rodent proof jacket
• Temperature range: -40°C to +90°C
Solar Home Run Harness Assemblies
Bundled harness assemblies are used to take multiple positive and/or negative wires from the end of a string of modules
back to either a combiner or string inverter (also known as a sub-array harness). Typically consists of 2 to 24 strings using
#10 or #8 AWG PV rated wire and solar certified connectors. Common options include custom string ID labeling, spool or coil
packaging, polarity colored wires, and specialized testing.
†Recommended (not to exceed). Each system is unique and the design should consider all factors including current de-rating.
Max Current
Max Max PV
Max for Greatest Input Conductors Output Conductors NEMA
CCB Series Description Voltage Fuse Module Short
Ambient Number of (Cu Only) (Cu/Al) Rating
Size Circuit Current
Strings
CCB_06 6 String Combiner Box (02-06 Strings) 600/1000/1500 50 15 72 9.6 #14 - #8 25 250 MCM or 350 MCM 325 4X/4/3R
CCB_12 12 String Combiner Box (07-12 Strings) 600/1000/1500 50 15 144 9.6 #14 - #8 25 250 MCM or 350 MCM 325 4X/4/3R
CCB_18 18 String Combiner Box (13-18 Strings) 600/1000/1500 50 15 216 9.6 #14 - #8 25 350 MCM 325 4X/4/3R
CCB_24 24 String Combiner Box (19-24 Strings) 600/1000/1500 50 15 288 9.6 #14 - #8 25 500 MCM 375 4X/4/3R
CCB_36 36 String Combiner Box (25-36 Strings) 600/1000/1500 50 15 433 9.6 #14 - #8 25 500 MCM 375 4X/4/3R
Eaton
1000 Eaton Boulevard
Cleveland, OH 44122
United States
Eaton.com
1500 VDC
Disconnect Combiners
SolarBOS Disconnect Combiners for 1500 VDC photovoltaic systems are ETL listed to UL-1741. They provide direct cost savings
by increasing the number of modules per source circuit(s), resulting in fewer circuits and fewer BOS components. The combiners
feature load break disconnect switches up to 400A and can be customized to fit the solar integrators’ specific needs.
Product Features
• ETL listed to UL-1741
• Up to 36 input circuits
• 75/90C terminals
• NEMA-3R, 4 & 4X enclosures
• Cover doors with poured-in-place seamless gaskets
Available Options
• Transient surge suppression
• Compression lugs / Dual output lugs
• Floating / Bi-polar configurations
• Pre-terminated input conductors
• Touch safe cover over live parts
SolarBOS Disconnect Combiner, 1500VDC, 400A disconnect, 24 input circuits,
transient surge protection, NEMA-4 powder coated steel enclosure
Max Rated Current (ADC Continuous) 250 / 320 / 400 250 / 320 / 400 250 / 320 / 400
* Please note dimensions and weight may vary for floating configurations or any custom solutions. Please contact SolarBOS for details.
Figure 5
Inverter skid configuration:
1 x Inverter Skid [2] - Inverter Part (2xLV5)
Transformer skid configuration:
1 x Transformer Skid [2x]
A3 00
0 1 2 3 4 5 6 7 8 9
5,96
A A
ĂďůĞ>ĞŶŐƚŚс;ϭϮϬϬнϭϲϮͿŵŵсϭϯϲϮŵŵ
ϳϬϬ
ŽŽůŝŶŐ
hŶŝƚ
ŝƌ
ŝƌ
Skid
B B
51 sq m
ϯϴϱϬ
ϯϬϬϬ
ƚƌů͘
ƚƌů͘
ϮdžϭDtĐŽŵƉĂĐƚƐŬŝĚ͕ƐĞĂůĞĚ;ƐƚĂŶĚĂƌĚƐŽůƵƚŝŽŶͿ
ŽŽůŝŶŐ
hŶŝƚ
ŝƌ
C C
ŝƌ
8,59
ϭϮϬϬ
REV
00
ϭϲϮ ϭϲϭ
SHT
ϯϬϬ
Ds^' dƌĂŶƐĨŽƌŵĞƌ
ϮϯϬϬ
ZDh ;ƐĞĂůĞĚͿ
ϭϴϬϬ ϮϯϬϬ
DWG NO
ϮϮϬϬ
ϭϰϬϬ
ŝƌ
E ŝƌ
A3
SIZE
,s
ϰϰϬϬ E
UNLESS OTHERWISE SPECIFIED © COPYRIGHT 2016 GENERAL ELECTRIC COMPANY AND/OR ITS AFFILIATES.
DIMENSIONS ARE IN MILLIMETERS All rights reserved.
F GE
F
CLASS II (GE INTERNAL NON-CRITICAL)
POWER CONVERSION
CUSTOMER PROJECT LV5 Skid SIZE CAGE CODE DWG NO
THIRD ANGLE PROJECTION
UNLESS OTHERWISE CUST ORDER NO N/A CUST DWG NO N/A
INDICATED BY ARROWS
CUST EQUIP REF N/A Germany N/A DRAWN Ernst Schüle DRAWN BY DATE
A3 ----
DO NOT MEASURE (YYYY-MM-DD)
OFF THIS DRAWING TOTAL SHEETS AND REVISION HISTORY SHOWN ON DRAWING INDEX Vincent Schellings, Michael
ENGRG
Chemnitz
2016_04_22 SCALE NONE WEIGHT - SHEET 5 OF 9
0 1 2 3 4 5 6 7 8 9
---- ----
GE
Power Conversion
3.1.1 2MW SKID FOUNDATION
1.4.2 2 MW Foundation
The Foundation of 2 MW configuration with 1 x (2 x 1) MW inverter skid & transformer skid is shown in
Figure 6.
Figure 6
CONTENTS
1. INTRODUCTION .............................................................................................................................................. 3
1.1 ENVIRONMENTAL CONDITION ................................................................................................................................ 3
1.2 DRAWINGS .......................................................................................................................................................................... 3
2. SCOPE OF SUPPLY .......................................................................................................................................... 4
2.2 FREE ISSUED EQUIPMENT............................................................................................................................................. 4
2.3 ASSEMBLY OF POWER STATION ................................................................................................................................ 5
2.3.1 Inverter Base Skid.................................................................................................................................................... 5
2.3.2 Transformer Base Skid .......................................................................................................................................... 5
2.4 ELECTRICAL CABLING ..................................................................................................................................................... 7
2.4.1 Medium Voltage Cabling ...................................................................................................................................... 7
2.4.2 AC Interconnection Cable .................................................................................................................................... 9
2.4.3 DC Interconnection Cables .............................................................................................................................. 11
2.4.4 Auxiliary Power Cable ......................................................................................................................................... 13
2.4.5 Control System Cables ....................................................................................................................................... 14
2.4.6 Earthing and Bonding ........................................................................................................................................ 15
2.5 PACKAGING/LOADING ................................................................................................................................................ 16
2.6 GENERAL REQUIREMENTS ......................................................................................................................................... 17
2.6.1 Bolting and Fixing ................................................................................................................................................. 17
2.6.2 Cable Glands ........................................................................................................................................................... 17
2.6.3 Wood Products ...................................................................................................................................................... 17
3. TESTING AND INSPECTION ......................................................................................................................... 18
3.1 INSPECTION ..................................................................................................................................................................... 18
3.2 CONTRACTOR TESTING ............................................................................................................................................... 18
3.3 GE POWER CONVERSION TESTING ....................................................................................................................... 18
4. CONTRACTOR DOCUMENTS....................................................................................................................... 19
4.1 SUPPLY OF DOCUMENTS AND DRAWINGS ....................................................................................................... 19
4.2 UNITS OF MEASURE...................................................................................................................................................... 19
5. STANDARDS / SPECIFICATIONS ................................................................................................................. 20
6. APPENDIX A ................................................................................................................................................... 21
MODIFICATION RECORD
Revision Date Author Details
000 2015-10-05 David, Alston Issued for Enquiry
GE
Power Conversion
1. INTRODUCTION
This document specifies the minimum requirements for the Assembly and Works Testing of Brilliance
Power Stations to be delivered in terms of the:-
The Brilliance Power Station is a two part design comprising an Inverter Skid Unit and a Transformer
Inverter Skid Unit.
Location Outdoor
Altitude <1500m
Ambient air -16 to 40ºC
Design temperature 40ºC
Relative Humidity 10% Min 100% Max
Seismic Intensity Horizontal 0.4G
Table 1
1.2 DRAWINGS
Assembled Mass
The estimated assembled mass of the Brilliance Power Station is provided in Table 3.
The scope of this contract includes the off-loading, proper receiving, inspection and safe storage of Free
Issued equipment. The equipment to be Free Issued for each power station is listed in Table 4 below.
Brilliance Inverter
The Inverter will be supplied by GE Power Conversion complete and ready for fixing to the skid base. The
Inverter SHALL be affixed to the skid base using the fixing/ bolting listed in Table 5 below.
Re-combiner Panel
The Re-Combiner Panel will be supplied by GE complete and ready for fixing to the skid base. The Re-
combiner Panel SHALL be affixed to the skid base using the fixing/ bolting listed in Table 6 below.
Power Transformer
The Power Transformer will be supplied by GE Power Conversion complete and ready for fixing to the
skid base. The Transformer SHALL be affixed to the skid base using the fixing/ bolting listed in Table
7below.
The scope of this contract includes the supply, installation and testing of the electrical cabling between
the various items of equipment of the Brilliance Power Station.
The two base units, transformer and Inverter base skids are to be positioned together and loosely
connected prior to the installation of any cable/s.
L1
Figure 1
R S T
U1 V1 W1
POWER TRANSFORMER
Auxiliary Power Cable
3 x 4mm2 600/1000v PVC
Figure 2
Cable Installation
These cables SHALL be installed on the cable tray in trefoil groups and securely strapped to the cable
tray built into the skid as shown in Figure 3 are must be taken when handling these cables to ensure no
damage is done to the connectors if these are installed prior to installation of the cable.
GE
Power Conversion
Cable Tray
Figure 4
General Description Flexible interconnecting cable complete with Tin Plated Copper
Cable Lugs Fitted
Quantity (3 x 4 ) = 12 pieces
Cable Length L21 8.0 metre Refer Figure 4
Connector
Description Crimped Lug
Type UL Double Bolt 2 x ½” x 44.5
Bolt Size M12/ 1/2”
Crimps SHALL be hexagonal swage not pin crimp.
Connector Standard UL
Note 2 - The length stated is estimated. The actual cable length SHALL be determined by the
Contractor.
GE
Power Conversion
Cable Data
Description Single Core, EPR, PVC Sheathed, Unarmoured Cables
Design Standard UL or IEC
Conductor Size 373 kCM 185 mm2
Flexibility DLO – UL Class 5 IEC 60228
Rated Voltage 2.0 kV
Conductor Material Stranded Copper
Insulation Material Ethylene-propylene rubber
Sheath Material Black heavy duty, thermoset CPE ** Vendor to Advise
Sheath Colour *** Vendor to Advise
Armour Unarmoured Cable
Table 11
Cable installation
The cables SHALL be securely strapped to the cable tray provided on the skid installed in trefoil groups
as shown in Figure 6. Care must be taken when handling these cables to ensure no damage is done to
cable and that undue stress is not transferred to the cable termination.
TRANSFORMER
Cable Markers
( by Contractor )
2w-1
2w-2
2w-3
2w-4
2u-1
2u-2
2u-3
2u-4
2v-1
2v-2
2v-3
2v-4
L1
AC Cable
Skid Edge
L1-1
L1-2
L1-3
L1-4
L2-1
L2-2
L2-3
L2-4
L3-1
L3-2
L3-3
L3-4
INVERTER AC PANEL
Figure 5
GE
Power Conversion
Cable Tray
Figure 6
These cables are to be installed, tested and then disconnected at the transformer end when the two
skids are separated for transport.
Figure 7
General Description Flexible interconnecting cable complete with Tin Plated Copper
Cable Lugs Fitted
Quantity (2 x7 ) = 14 pieces
Cable Length L21 2.0 metre - Note 3 Refer Figure 7
Connector
Description Crimped Lug
Type UL Double Bolt 2 x ½” x 44.5
Bolt Size M12/ 1/2”
Crimps SHALL be hexagonal swage not pin crimp.
Connector Standard UL
Note 3 - The length stated is estimated. The actual cable length SHALL be determined by the
Contractor.
GE
Power Conversion
Cable Data
Description Single Core, EPR, PVC Sheathed, Unarmoured Cables
Design Standard UL or IEC
Conductor Size 373 kCM 185 mm2
Flexibility DLO – UL Class 5 IEC 60228
Rated Voltage 2.0 kV
Conductor Material Stranded Copper
Insulation Material Ethylene-propylene rubber
Sheath Material Black heavy duty, thermoset CPE ** Vendor to Advise
Sheath Colour *** Vendor to Advise
Armour Unarmoured Cable
Table 12
Similarly 185mm2 / 373 kCM cable MAY be substituted with 200mm2 / 400 kCM provided the bending
radius of the cable allows for the installation of the cables. The number of parallel conductors MAY be
reduced cable be used provided the continuous current capacity of 2400 Amperes DC is maintained.
Cable Installation
The DC Cable connections are shown in Figure 8 below.
INVERTER DC PANEL
N1-1
N1-2
N1-3
N1-4
N1-5
N1-6
N1-7
P1-1
P1-2
P1-3
P1-4
P1-5
P1-6
P1-7
Cable Markers
( by Contractor )
DC Cable
N1-1
N1-2
N1-3
N1-4
N1-5
N1-6
N1-7
P1-1
P1-2
P1-4
P1-5
P1-6
P1-7
P1-3
RE-COMBINER
These cables are to be installed, tested and are NOT required to be disconnected when the two skids are
separated for transport.
GE
Power Conversion
2.4.4 Auxiliary Power Cable
The scope of this contract includes the supply and installation of auxiliary cables complete with cable
glands, lugs and core / cable markers.
Cable Installation
The connection points of the Auxiliary Power Supply cables are shown in Figure 9 below.
Skid Edge
Auxiliary Supply
Auxiliary Supply
3 x 4.0 mm2
3 x 4.0 mm2
3 x 4.0 mm2
3 x 4.0 mm2
110V
110V
110V
480V
RE-COMBINER - AC PANEL
Figure 9
These cables are to be installed, tested and then disconnected at the transformer skid end when the two
skids are separated for transport.
Cable Installation
The control system cabling is shown in Figure 10 below:-
Cable are Disconnected this End for Transport
Transformer RMU
Protection Relay Protection Panel
Conduit Conduit
Skid Edge
12 x 1.5 mm2
Conduit
RJ45 RJ45
RE-COMBINER PANEL
Figure 10
These cables are to be installed, tested and then disconnected at the transformer skid end when the two
skids are separated for transport.
Conduit
The cable running to the Transformer Protection relay SHALL be installed in aluminium or galvanised
steel conduit up the side of the transformer and at the RMU where it is run parallel to the MV cables.
Standard BS6724
Voltage Rating/Class 250V
Cross Sectional Area 12 Cores 1.5 mm2
Conductor Material Copper ( Class 2 stranded )
Insulation XLPE /LSF
Armour Type Wire Armour or Braid
Outer Sheath PVC /LSF
Table 14
GE
Power Conversion
Ethernet Cable
The supply, complete with RJ45 Plugs is included in the scope of this contract. The Ethernet cable SHALL
be at least CAT 6 and equipped with moulded connectors.
Ethernet cable will be installed in PVC conduit between the Re-combiner and the Inverter Control panel.
Figure 11
GE
Power Conversion
Description Insulated Earth Lead compete with Tin Plated
Copper Cable Lug Fitted
Length L41 250 mm Refer Figure 11
Quantity 7
Hole Diameter d11 12mm / ½”
Cable
Conductor Size 70 mm2
Conductor Material Stranded Copper
Flexibility Class 3
Insulation PVC Insulated G/Y
Rated Voltage 600
Cable Lug
Design Standard DIN VDE 0295
Material Tin Plated Copper
Crimp Crimps SHALL be hexagonal swage
Table 15 Earth Lead
2.5 PACKAGING/LOADING
The scope of this contract includes the loading of the assembled Power Station Skids onto road
transport trucks for dispatch to the Customer Site.
a) The lifting Lugs are to be fitted to each skid for transport.
Similarly, the scope of this contract includes the off-loading of deliveries of free issued equipment.
Where these deliveries are containerised the Contractor may choose to retain the Container and to
utilise it as storage.
GE
Power Conversion
2.6 GENERAL REQUIREMENTS
Cable glands SHALL be CMP CW industrial cable glands or Equal / Equivalent and SHALL conform to BS
6121 and EN 50262,
Gland Plates
The scope of this contract includes the drilling of gland plates to suit the cable glands selected.
3.1 INSPECTION
The Contractor SHALL provide GE Power Conversion full access to the work and storage areas where the
skids are being assembled or components/ equipment relating to the project are stored at any
reasonable time during the contract execution.
The Contractor SHALL perform the following tests prior to the dispatch/shipment of the fully integrated
skid units:-
Electrical Installation
Testing of the electrical installation to the extent of the scope of work performed:-
Electrical Earth Continuity
Electrical circuit continuity
Insulation Testing in accordance with Japanese requirements
Tightness of terminations
Mechanical rigidity of cables installed
Mechanical Installation
Inspection of the equipment installation to the extent of the scope of work performed:-
Tightness of all equipment mounting bolting/fixings
Rigidity of all cable ways / conduits
Cable strapping
The Contractor SHALL provide GE Power Conversion with full and unrestricted access to each completed
skid in order for GE to perform such pre-dispatch / acceptance testing that may be required and to
allow pre-delivery customer inspection.
Utility Services
The Contractor SHALL make the following Utility Services available to GE
Single Phase AC power for test equipment and hand tools.
Sanitary facilities. Changing, Washing and toilet facilities
GE
Power Conversion
4. CONTRACTOR DOCUMENTS
The scope of this contract includes the provision / supply of documents and drawings as listed in Table
16. These documents SHALL be submitted within the schedule and in the form stated in Table 17 below:-
Submission Description
Q With Quotation
P+n n weeks after Contract Award
D-n n weeks before Delivery
Table 17 Document Submission Codes
Language
Electrical Test reports shall be provided in dual Language English / Japanese. All other Document SHALL
be submitted in English Language
Only Metric units of measurement, Système International d’unités, SHALL be included on drawings and
other documents. Material Mill Certificates MAY be provided in Imperial units of Measurement.
GE
Power Conversion
5. STANDARDS / SPECIFICATIONS
Material and techniques used shall comply with the standards listed in Table 18 below. Equivalent US,
ASME or JS specifications may be substituted for the BS ISO specifications listed.
6. APPENDIX A
Ethernet
CT/PT Signals
MODBUS
Hardwired Signals
MODBUS
MET STATION TO BE INSTALLED
BY THE CONTRACTOR
Server
EGD
EGD MET STATION
EGD
EGD
LV5-RXI
LV5-RXI
DC Combiner DC Combiner
Box Box
Note : All interconnected cables /Network Cables outside of SunIQ ,MetStation and DC
combiner Boxes are excluded