1. Windows is to have silicone applied on them once the office is cleaned thoroughly and is dust Ongoing
free.
2. Bushes to the doors need to be adjusted to give a softer closing operation. Completed
3. The porcelain tiles have (1) one year warranty on them and the snags (stepped and hollow Negligible and don’t need replacing
sounding tiles).
7. Filler will be applied in all spaces around any window and door that I had shown. Completed
8. Wall corner/edges will be sorted out By Mr. Daniel ~ 0716010512/ 0793892026 Completed
10. Socket installation in all office and open plan offices. Ongoing
Page 1 of 3
11. Labelling of sockets and Distribution board completed
12. Installing cables and socket boxes in the server room Ongoing
13. Installing cables for the water heater in the bath room completed
4. MD signage needs to have a flexi pipe installed for the Falcon signs
5. Cable tray has a bolt missing and needs one installed. Not Done
AOB
1. Nelson labelled the sockets of the hangar and proceeded upstairs to install the remaining sockets.
2. we already purchased 16 socket boxes and the electrification work has resumed
3. A stopper needs to be put at the 1st floor main entrance door at the joint of the 4 tiles
4. 1st floor toilets need 2flex pipes, 2 toilet lids and 2 angle valves.
5. 1st floor 2nd booth doors need to be straightened because they don’t close flat.
6. Second toilet booth door has a space that one can see the occupant inside.
Page 2 of 3
5. MSO decided that the Aluminum work , Electrical Work & Plumbing needs to be completed
6. Painting and filler finishes to be done at the end and concluded by cleaning
7. Accountant’s window rubber silicone needs to be straightened out and corners need to be cut.
8.