Académique Documents
Professionnel Documents
Culture Documents
First start-up
7. Fresh Feed-in
7.1 Switch to Normal Feedstock (at 100% design capacity)
7.2 Increase Throughput to Design
7.3. Stripper
7.4 Splitter
First Start-Up
1
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
The leak tests and vacuum tests have been successfully completed.
The reaction section & heaters have been dried out.
The reaction section is under a hydrogen pressure.
The amine section has been degreased, rinsed and is under an oxygen-free
gas positive pressure.
LP sections are under fuel gas or nitrogen pressure.
The other parts of the unit are under fuel gas or nitrogen positive pressure
and water has been drained as far as possible. Water may still be trapped on
certain column trays and in other equipment items.
All utilities are in service. Blinds in the headers have been removed, and
valves open to all users.
The catalysts are correctly loaded in the reactor.
All instrumentation has been checked.
All safety devices and emergency sequences have been tested.
Safety valves for all equipment items shall have been lined up, and these
actions recorded on a checklist.
The reaction section is isolated from upstream and downstream equipments.
(ie, From feed section & LP section)
The washing water drum has been filled with boiler feed water; the drum
level control and split range pressure control are in automatic operation.
Pumps and compressors (and their drivers) have been aligned and run-in.
Heat exchangers/ fin fan coolers have been checked and are ready for
operation.
Start-up gas oil is available (hydro treated gas oil) from tank No. 70046A/B.
H2 plant is running.
Lean amine is available.
Chemical injection systems have been prepared and chemical pumps
calibrated. The chemical injection lines have been filled up to the injection
points.
A start-up feedstock is available: usually a straight run gas-oil, with following
specifications:
o ASTM distillation close to the ASTM of design feed.
o Specific gravity as close as possible to the design feed.
Note: A start-up feedstock means a distillate essentially free of diolefins and olefins
with low sulphur and nitrogen contents.
2
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
During all these steps, care should be taken of all level indications. As density
of gas oil could be different from normal operating fluid, indications can be
erratic. Levels should be checked on site with the corresponding level glass.
2. Preparation
The chronology of the various start-up tasks is shown on the attached schedule.
The duration shown are those required to perform the tasks. The time gap between
two consecutive operations has not been taken into account.
3
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
4 Amine Section
Amine inventorying
Amine circulation
4
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
Verify that the LP amine absorber bottoms have a working level and unblock
the level control valve LV-333069. Verify that the level control is operating
correctly and relevant amine is being returned to the amine regeneration unit
through rich amine line.
The level of amine established in the HP amine absorber (DA-33301) will act as a
liquid seal during the hydrogen test of the reaction section. During sulphiding. the HP
Amine Absorber (DA-33301) by-pass line will be opened. The lean amine HP pump
(GA-33303 A /B) can remain in mini-flow operation (or stopped) until it is required.
These pumps can be switched to stand by from time to time so that both can be
thoroughly checked out.
During stripping and splitter sections drying out, ensure that the reaction
section is well isolated.
o configured as follows:
5
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
6
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
7
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
Note: This procedure assumes that the Amine Treatment System is ready for
receiving Stripper (DA-33302) off gases.
8
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
As levels begin to fall in feed surge drum, bring in additional start-up gasoil
inventory to the system.
Build-up Stripper Bottom Level steadily to approximately 60% of level
indicator range. Cross-check the LIC-333044 indication in the DCS with the
LG-333046 indication in the field. When a level of 60% is achieved, close the
start-up line FIC-333011 valve.
Do not loose stripper pressure. If pressure bleed-off is too rapid and stripper
pressure falls below about 5 kg/cm² g, restore the pressure via nitrogen
pressurization line.
Open the level / flow control valve (FV-333045) at the bottom of the stripper
(DA-33302) to fill the line towards the splitter (DA-33303).
The next step is to line-up the system in order to bring in fresh start-up gas oil feed
and to pump-out the contaminated gas oil to slop.
Open the block valve in the off-spec product to slops line.
Switch control of feed surge drum level controller (LIC-333006) to automatic.
9
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
Adjust the level / flow controller (LIC-333044 / FIC-333045) set point in the
stripper (DA-33302) to approximately 60% and start one of the feed pumps as
detailed earlier.
Open the start-up gasoil flow control valve (FV-333011) to approximately
10% via the flow controller (FIC-333011).
As the level increases in the stripper (DA-33302), open the downstream
block valve of the level /flow control valve (FV-333045) in the stripper to the
splitter feed line. When the stripper level reaches the set point of the level
indicator/controller the level control valve will open, routing start-up gasoil to
the splitter.
As the level increases in the splitter (DA-33303), open the downstream block
valve of the splitter level control valve (FV-333071) and the isolation valve
(UV-333026) located at the splitter bottom. When the splitter level reaches
the set point of the level indicator / controller the level control valve will
open, routing start-up gasoil to the slops (off spec) through diesel product
pumps.
Flow to slops will be set by the feed pumps rate from feed surge drum.
The different circulations are stopped from time to time until no more water is
found at all low points.
Continue to sample the start-up gasoil to slops at regular intervals. When the
oil appears to be cleared, compare the aspect of the initial sample to the
latest one. If quality appears satisfactory (when the gasoil is no longer cloudy)
continue to the next step.
Close the block isolation valves and blind on the gasoil to slops line and
simultaneously open the closed isolation valves in the start-up line to feed
surge drum.
Monitor the levels in the feed surge drum and stripper to see that they cope
with the change back to closed loop circulation.
Maintain start-up line flow at 60% of design throughput.
Remove water if any. This is mandatory to avoid blowing out the column
trays, while heating up the loop. When circulation is well established, and if no
significant problems arise, such as a pump suction strainer blocking,
instrumentation anomalies and so on, heat can be added to the stripper
section. Proceed as follows:
10
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
6. Catalyst Treatment
6.1 Hydrogen Circulation
The reaction section is under H2 atmosphere used for the leak test. Re-start the
recycle gas compressor in closed loop through the reaction section (following
circuit):
Schematic for the following shall be prepared
11
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
HP Separator (FA-33304)---
HP Amine Absorber KOD (FA-33305)---
HP Amine Absorber Is Bypassed---
Recycle Gas Compressor KOD (FA-33306) ---
Recycle gas compressor (GB-33301).
12
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
13
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
6.2 Pre-Wetting
The reaction section is under hydrogen pressure (normal operating figure
minus 10%ie,65.9ksc) with the reactor bed temperatures at 150°C, and with
no more free water found at the HP separator, FA-33304 (one will check that
this pressure is in accordance with reactor P /T Chart).
Slowly introduce the start-up gas oil into the reactor by opening the isolation
valve (UV-333003) and de-isolating the double block valves upstream
/downstream of the feed flow control valve (FV-333009), and commencing
flow via FIC-333009 in manual control from the DCS. The flow will be
steadily increased (normally) to 60% unit design throughput. Whilst the start-
up gas oil flows from storage to the Stripper (DA-33302) is reduced to 40%.
Note: Gas oil contact with catalyst under hydrogen atmosphere gives a small but
noticeable increase of temperature in the reactor (depending on the recycle flow
rate, the delta “T” may be around 20°C).
When the start-up gas oil is introduced into the reaction section the
operating level in the Feed Surge Drum (FA-33302) should be
maintained by allowing new start-up gas oil to the unit. Due to the
lowering of gas oil flow rate going directly to the stripping section,
take care that the liquid level in the stripper is not lost.
Start-up gas oil will eventually appear in the Cold MP Separator (FA-
33309). Open the Cold MP Separator liquid level isolation valve, when
the level in the separator is high enough to permit this action. Set LIC-
333023 to manual control mode and ensure zero % output (level control
valve fully closed). Open the upstream and downstream isolation valves
of the control valve (LV-333023).
When the gas oil level in the cold MP Separator (FA-33309) HC side reaches
approximately 60%, match the set point of its LIC-333024 to this value and
switch the loop to automatic control mode. Gas oil will now be routed to the
Stripper and then the Splitter (DA-33303). But the Power Recovery Turbine
will be under Bypass at this point.
Note that, as soon as liquid is shown in Cold MP Separator the once-through
circulation must be established to remove any fine particles of catalyst which
are carried over with the gas oil. Send gas oil to slops.
Raise the feed flow rate to the reaction section up to 100% design throughput
and isolate the start up line from feed surge drum to the stripper (FV - 11).
After 4 hours, take a sample of gas oil and make a visual check. If gas oil is
clear, open the recirculation line 8”P-3330230 via FV-333072 back to FSD
14
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
and isolate the slop connection, otherwise continue the once through
circulation until gas oil becomes clear.
As soon as flows and levels are stabilized in the reaction section, raise the
pressure to the normal operating figure, keeping reactor beds at 150°C.
Once recirculation is established, reduce if possible the recycle gas flow
down to 50% of the nominal flow. The purpose of this step is to ensure that
the whole catalytic beds and the pores of the catalyst have been in contact
with hydrocarbons prior to the sulphiding. This catalyst wetting has a
beneficial impact on the sulphiding achievement on the catalyst activity and on
the reactor hydrodynamics.
Maintain these operating conditions for 4 hours.
If catalyst activation cannot be performed after this step, temperature is kept
at 150°C and unit will be put in stand-by. Otherwise, temperature will
increase to 170°C.
7. Fresh Feed-in
7.1 Switch to Normal Feedstock (at a throughput of 100% design capacity)
Note: Target temperatures given in this procedure are only a guide as actual desired
target temperatures will depend on the composition of the feed.
15
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
Check the level of amine and pressure in the lean amine surge drum (FA-
33314). Start one of the Amine HP Pumps (GA-33303 A / B, if not already
started).
Start lean amine flow to the HP Amine Absorber (DA-33301) in the normal
fashion. Set the flow controller (FIC-333080) at mid scale (50%) and verify its
operation.
Verify that the HP Amine Absorber has a good working level and unblock the
level control valve, and verify that the level control is operating correctly and
that rich amine is being transferred from the HP to the LP amine absorber
(DA-33305) and then returned to the ARU.
2nd Step
16
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
necessary but will somewhat offset the lower tray efficiencies expected when
absorber hydrocarbon feed rates are below design.
The recommended sampling and analytical testing schedule should begin
immediately to determine if further plant adjustments are required.
3rd Step
Progressively increase stepwise (5% per hour) fresh feed flow rate to 50% of
the design gas oil flow rate, decrease the recirculating gas oil to the feed
surge drum to 50%.
Next, progressively raise the reactor inlet temperature so that an outlet
temperature of 300°C is achieved (5°C per hour). Check H 2S in the recycle
gas and reduce sulphiding agent injection (stop it if necessary).
At this time the Stripper and the Splitter should be brought up to conditions
as near to normal as possible. Excess stripped gas oil is sent to storage (then
will initially be turned out to slops (off-spec.), until design quality product is
achieved).
4th Step
Repeat this procedure by increasing the fresh feed up to 75% of design feed
rate, decreasing re-circulating gas oil flow to 25% of design feed rate. Adjust
the reactor temperatures and the different parameters in the same way as
previously, this time aiming for a reactor outlet temperature of 320°C.
5th Step
At this point, increase the fresh feed to 100% and block in the recirculation
flow to the feed surge drum, and adjust the reactor temperatures to get the
required specification in the hydro treated products.
Note:
This step-by-step fresh feed-in procedure allows a progressive plant
start-up without any shocks to the equipment, such as Feed Pump
Exchangers, Reactor, Stripper and Splitter.
Do not forget to check all hot equipments for proper unrestricted
thermal expansion.
Feed filter backwash frequency is to be closely monitored when raising
the fresh feed throughput.
To ensure a minimum duty for the heater during transient phase, the
feed bottom exchangers of the reaction section can be by-passed.
Hot bolting of the Reactor and heat exchangers is to be carried out as
a normal practice.
Adjust quench flow rate to obtain the reactor temperatures needed for
achieving the desired product specification.
17
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
After the unit operation has been stabilized for a few hours (unit running at
60% fresh feed), increase feed flow up to 100% design capacity, in increments
of 5%.
When it is necessary to change feed rate, feed type, hydrogen make-up quality or
anything, which will affect operating temperatures, anticipate the change by
adjusting reactor temperatures as follows:
7.3 Stripper
Note: The following operations on the stripper are normally carried out during
the sulphiding procedure when sufficient heat is available for the first time to
operate this item correctly.
The operations are written here as a reminder and can also be found in
the sulphiding procedure in the chapter-10 “Catalyst specification and
special procedures”.
18
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……….
Section-1-Chapter V – First start-up 20-6-2012
7.4 Splitter
The splitter bottom level control (LIC-333052 / FIC-333071) is in auto mode. The
Splitter Reflux Pumps (GA-33306 A / B) shall be already in operation. The Splitter
Reboiler (BA-33302) outlet temperature is slowly adjusted to reach the products
specifications and to obtain the design reflux flow rate.
19