Vous êtes sur la page 1sur 53

Construction of Diaphragm Wall

Presentation by:
Gagan Goswami
1
Content

 Introduction

 Application

 Category of Diaphragm Wall

 Construction Procedure

2
Introduction
Diaphragm Wall is generally reinforced
concrete wall constructed in the ground using
Underslurry technique which was developed in
Europe.
The technique involves excavating a narrow
trench that is kept full of an engineered fluid
of slurry.
Walls of thickness between 300 and 1200 mm
can be formed in this way up to a depths of 45
meters.

3
Conceptual sketch showing
the RCC Diaphragm Wall

4
Diaphragm wall-Application
 Commonly used in congested areas
-Can be Installed in close proximity to
existing structure
 Practically suited for deep basements
 Used in conjunction with “Top Down”
construction technique

5
Schematic section of Diaphragm
Wall showing typical use

6
Schematic section of Diaphragm
Wall showing typical use

7
Schematic section of Diaphragm
Wall showing typical use

8
Schematic section of Diaphragm
Wall showing typical use

9
Anchoring of Diaphragm Wall using
Anchor Slab

Anchor Slab

10
Anchoring of Diaphragm Wall using
Anchor Blocks

Diaphragm Wall

Anchor Bars

Anchor Blocks

11
Important Conditions
Dictate the use of Diaphragm Wall
 Very unstable soil profiles below the water
table
 Limited construction time
 Where deeper than normal cantilever support
may be required

12
Positive facades of Diaphragm
Wall
 Can be Installed to considerable depth
 Formation of walls with substantial thickness
 Flexible system in plan layout
 Easily incorporated into Permanent works
 Designable to carry vertical loads
 Construction time of Basement can be lowered
considerably.
 Economic and Positive solution for large deep
basement in saturated and unstable soil profiles.
 Can be used for seepage control in Dams.
 Noise levels limited to engine noise only.
 No vibration during installation.

13
Negative Facades of
Diaphragm Wall
 Not economical for small, shallow Basements

14
Category of Diaphragm wall

1) In Situ Cement Bentonite Vertical Wall


2) In Situ RCC Vertical Wall
3) Precast RCC Vertical Wall

15
In Situ Cement Bentonite
Vertical Wall
 Provides water tight barrier
 Used to prevent seepage/water loss from
Natural reservoir and Dams

16
In Situ RCC Vertical Wall

 Underground Structural element


 Used for Retention systems and Permanent
foundation walls
 Deep groundwater barriers

17
Procedure

Diaphragm Wall construction begins with


the trench being excavated in
discontinuous sections or “panels”.
Stop-ends are placed vertically at each end
of primary panel to form joints for
adjacent secondary panel or closing
panels. Panels are usually 4 to 6 meters
long. Stop-ends are used to form the joints
between adjacent panels and a water bar
can be incorporated across these joints.

18
Construction Method

Secondary Primary Secondary Secondary Secondary Closing Secondary

Construction Joint formed by


Construction Joint
Circular Stopend Pipe

Schematic Diagram Showing Construction Joint between Adjucent Panels

19
Construction Method

Secondary Primary Secondary Secondary Secondary Closing Secondary

Construction Joint formed by Construction Joint


Flat Stop end

Schematic Diagram Showing Construction Joint between Adjucent Panels

20
Different Shapes of Diaphragm
Wall Panel

T-Shape Panel L-Shape Panel


21
Different stages of construction
activities

22
Diaphragm Wall Construction Site

23
Construction Procedure

 Stage-1: Fixing of Alignment


 Stage-2: Guide wall Construction
 Stage-3: Trenching
 Stage-4: Trench Cleaning
 Stage-5: Stop ends fixing
 Stage-6: Reinforcement Cage lowering
 Stage-7: Placing of Concrete
 Stage-8: Withdrawal of Stop ends

24
Guide Wall Construction

Guide Wall
is constructed
to fix the
alignment of
Diaphragm Wall
in the field

25
Guide Wall Construction

26
Trenching Equipments

 Hydraulic Grab
 Kelly-mounted or Cable-hung cam buckets

27
Kelly-mounted Hydraulic Grab

28
Cable-hung cam bucket

29
Trenching Process

 Trenching usually carried out under


bentonite slurry
 Bentonite Slurry – Key component.
-This Slurry acts as shoring to prevent
collapse by hydraulic pressure and
thyrotrophic property.

30
Bentonite Slurry

 Used as a support fluid


 The bentonite suspension used in bore holes
is basically a clay of montmorillonite group
having exchangeable sodium cations (Na+).
 The action of bentonite in stabilizing the
sides of bore holes is primarily due to the
thixotropic property of bentonite
suspension.
 The bentonite suspension when undisturbed
forms a jelly which when agitated becomes a
fluid again.
31
Functions of Bentonite

 In case of granular soils, the bentonite


suspension penetrates into the sides under
positive pressure and after a while forms a
jelly.
 The bentonite suspension gets deposited on
the sides of the hole resulting in the
formation of a filter cake in contact with
soil against which the fluid pressure acts.
 In case of impervious clay, the bentonite
does not penetrate into the soil, but
deposits only a thin film on the surface of
the hole.
32
Factors affecting stability
of Trench
 Level of the supporting fluid
-Level of the bentonite slurry should be
maintained preferably at least 1.5m above the
ground water level to avoid problem of
instability.
 Density and Viscosity of supporting fluid
 Loss of shear strength with time
 Suction effect during trenching

33
Specification of Bentonite
(as per IS:2911-Part1:Sec2)
 Liquid limit : 300 to 450 % (in accordance
with IS:2720-part V )
 Sand content : Less than 7 %
 Density: 1.12
 Marsh viscosity : About 37 second, tested by
Marsh cone
 Swelling index: Swelling index at least 2 times
of dry volume.
 pH value : Less than 11.5

34
Tests and compliance values for support fluid
prepared from bentonite
(as per IS9556-1980)
Property Test method As Before
supplied concret
to the ing
bore
Density Mud balance 1.04- <1.15g/
1.10g/m ml
l
Viscosity Marsh cone 30 - 90
seconds

Shear Shearometer / 1.4 to 10


strength Vane shear N/sq.m
apparatus

pH Digital pH 9.5-12
meter 35
Schematic Diagram of
Bentonite Setup
•Storage tanks

Settling Circulation Fresh

T3 T2 T1
Mixer
•Mud
Pump

Diaphragm Wall Construction area

36
Bentonite Setup

37
Preparation of Bentonite Slurry

Bentonite slurry made by passing dry powder


through water jet. A conical hopper is used
with bottom nozzle through which water is
pumped under pressure. The bentonite powder
is poured directly from top and when it falls
down the hopper, it gets agitated in the water.
After getting circulated, the mixed bentonite
thus falls in the tank.

38
Trench Cleaning

 Joints of adjacent panels to be cleaned to


obtain watertight bond
 Loose materials to be lifted by suitable air
lifting method

39
Fixing of Stop ends

 Stop ends to be fixed at the proper


position keeping it truly vertical
 Distance between two Stop ends to be
fixed as per prefixed Panel Layout

40
Reinforcement Cage

Excavation of panel is followed by placing of


steel reinforcement cage in center of the
panel.

41
Reinforcement Cage fabrication

42
Reinforcement Cage shifting

43
Lowering of reinforcement cage
in the excavated panel

44
Lowering of reinforcement cage
in the excavated panel

45
Resting of reinforcement cage
in the excavated panel

46
Different stages of construction

47
Placing of Concrete

 Placing of concrete having slump 150mm to


190mm by tremmie method
 Concrete to be placed through a top metal hopper
and into a rigid leak proof tremmie pipe (2 sets),
sufficiently large enough to permit free flow of
concrete.
 Initially there should be a suitable plug at the
bottom of metal hopper, which will not discharge
concrete until sufficient concrete accumulate in
the metal hopper.
 concrete displaces the slurry from bottom and
rises in such a manner that mixing of concrete
with slurry does not occurs

48
Placing Concrete

49
Placing of Concrete

 Pouring shall be continued till it


accumulates in vertical Tremmie pipe up
to top of funnel.
 Tremmie pipe shall be raised so as to
release the concrete in a single continuous
flow.
 Concrete to be discharged in the trench
without any lateral movement of Tremmie
pipe.

50
Placing of Concrete

 Caution - Bottom end of Tremmie pipe


must remains immersed in concrete.
 Operation to be continued till good
concrete reaches 300mm above the
cut-off level of Diaphragm Wall.
 This concrete above cut-off shall be
removed when green Chipping of concrete
is not to be permitted.
 Length of Tremmie pipe shall be reduced
by removal of Tremmie segment stage by
stage. 51
Withdrawal of Stop ends

 Withdrawal of Stop ends just after the


Initial setting of concrete.
 If retarders are not added, Stop End Pipes
shall be moved up & down not later than
45 minutes from the time of placing of
concrete.

52
Thank You
If any Query please mail me-
gagangoswami@yahoo.co.in
53

Vous aimerez peut-être aussi