Appendix C.

26 d : Single Cell RCC Box Culvert of size 2 x 3 (U/S & D/S Pitching)

Sl.
No. Descriptions Unit No. Length Width Ht./Th. Area Quantity

1 Excavation
Box Portion cum 5.50 12.00 1.00 66.000
L=2.0+2x0.35+2x1.30+2x0.10 = 5.50 m
Width = 12 m
Depth = 1.0 m from natural ground level
For Key portion cum 2 5.50 0.43 4.675
L=2.0+2x0.35+2x1.30+2x0.10 = 5.50 m
Area = (0.30x0.67)+(0.50x0.67x0.67) = 0.425 sqm
No. = 2
Wing wall cum 4 6.70 3.68 1.50 147.936
Length of wing wall = 6.7 m
Depth of Foundation = 1.50 m
Width = (3.04+ 4.31)/2 = 3.68 m
(Refer MOST Dwq. No. SD/113 sheet 6 of 6)
No. = 4
For Return wall
Length of Return wall = 1.4 + 0.1 = 1.5m cum 4 1.50 2.05 1.50 18.450
Width = 2.05 m
Depth = 1.50 m
No. = 4
Total 237.061
2 Levelling course plain cement concrete grade M-15
in foundation.
Box Portion cum 5.50 12.00 0.15 9.900
L=2.0+2x0.35+2x1.30+2x0.10 = 5.50 m
Width = 12 m
Thick = 0.15 m
Wing wall cum 4 6.70 3.68 0.15 14.794
Length of wing wall = 6.7 m
Depth of PCC = 0.15 m
Width = (3.04+ 4.31)/2 = 3.68 m
(Refer MOST Dwq. No. SD/113 sheet 6 of 6)
No. = 4
For Return wall cum 4 1.50 2.05 0.15 1.845
Length of Return wall = 1.4 + 0.1 = 1.5m
Width = 2.05 m
Depth = 0.15 m
No. = 4
Total 26.539
3 Box Portion
RCC grade M-25 cum 77.000
(Refer MOST Dwg. No. SD/108 sheet 2 of 6)
4 Wing wall
PCC grade M-20 cum 96.000
(Refer MOST Dwg. No. SD/113 sheet 6 of 6)
Return Wall cum 4 1.40 1.75 9.800
Length = 1.4 m
Area =
(1.81x0.50)+(0.50x0.46x0.24)+(0.50x0.85x(0.85+0.
3)+(0.50x0.30)+(0.40x0.35) =
0.905+0.055+0.50+0.15+0.14 = 1.75 sqm

No. = 4
Total 105.800
5 Approach slab

Appendix C - 84
Appendix C.26 d : Single Cell RCC Box Culvert of size 2 x 3 (U/S & D/S Pitching)

Sl.
No. Descriptions Unit No. Length Width Ht./Th. Area Quantity

I. Levelling course M-15 concrete cum 2 3.50 12.00 0.15 12.600


L= 3.50 m
W = 12m
Thick = 0.15m
No. = 2
II. RCC M-30 grade concrete cum 2 3.50 12.00 0.30 25.200
L= 3.50 m
W = 12m
Thick = 0.3m
No. = 2
6 RCC M 40 Crash Barriers Lm 2 9.60 19.200
No. = 2
L = 2+2x0.3+2x3.5 = 9.60 m
7 Filling with Filter media (Both side)
a) For Box Portion cum 2 0.60 12.00 1.40 20.160
No. =2
L= 0.6m
W = 12m
Ht. = 1.4m
b) For wing wall cum 4 3.82 0.60 3.36 30.804
Length of wing wall = 6.7 m
Ave.Ht. = (4.57+2.15)/2 = 3.36 m
Width = 0.60 m
No. = 4
Total 50.964
8 Stone pitching for Floor Apron
a) 150 mm thick PCC M-15 cum 9.600
b) 300 mm thick concrete cum 19.200
c) 150 mm thick Flat Stone cum 9.600
(Refer MOST Dwg. No. SD/111 sheet 4 of 4) 38.400
9 Stone pitching for Flexible Apron
750 mm thick Stone cum 77.500
(Refer MOST Dwg. No. SD/111 sheet 4 of 4)
10 Curtain Wall
a) PCC under curtain wall cum 5.800
c) Concrete for D/S curtain wall cum 21.800
d) Concrete for U/S curtain wall cum 16.800
(Refer MOST Dwg. No. SD/111 sheet 4 of 4)
11 Tar Paper Bearing sqm 2 12.00 0.30 7.200
12 Backfilling behind Abutment, wing wall etc.
a) Behind Abutment cum 2 12.00 3.50 1.70 142.800
b) Behind Wing wall cum 4 6.70 3.50 1.50 140.700
Total 283.500
13 Expansion joint Mtr. 2 12.00 24.000
14 Drainage Spout No. 2.000
15 Weap holes No. 50.000
16 Reinforcement (As per MOST)
a) For Box Portion MT 5.650

Executive Engineer, PWD


Nagaon NH Division, Nagaon

Appendix C - 85
Appendix C.26 j : Single Cell RCC Box Culvert of size 4 x 4 (U/S & D/S Pitching)

Sl. Descriptions Unit No. Length Width Ht./Th. Area Quantity


No.
1 Excavation
Box Portion cum 7.70 12.00 1.00 92.400
L=4.0+2x1.20+2x0.55+2x0.10 = 7.70 m
Width = 12 m
Depth = 1.0 m from natural ground level
For Key portion cum 2 7.70 0.28 4.235
L=4.0+2x1.20+2x0.55+2x0.10 = 7.70 m
Area = (0.30x0.50)+(0.50x0.50x0.50) = 0.275 sqm
No. = 2
Wing wall cum 4 9.84 6.69 1.50 ###
Length of wing wall = 9.841 m
Depth of Foundation = 1.50 m
Width = (5.54+ 7.84)/2 = 6.69 m
(Refer MOST Dwq. No. SD/113 sheet 6 of 6)
No. = 4
For Return wall
Length of Return wall = 1.4 + 0.1 = 1.5m cum 4 1.50 2.05 1.50 18.450
Width = 2.05 m
Depth = 1.50 m
No. = 4
Total ###
2 Levelling course plain cement concrete grade M-15 in
foundation.
Box Portion cum 7.70 12.00 0.15 13.860
L=4.0+2x1.20+2x0.55+2x0.10 = 7.70 m
Width = 12 m
Thick = 0.15 m
Wing wall cum 4 9.84 6.69 0.15 39.502
Length of wing wall = 9.841 m
Depth = 0.15 m
Width = (5.54+ 7.84)/2 = 6.69 m
(Refer MOST Dwq. No. SD/113 sheet 6 of 6)
No. = 4
For Return wall cum 4 1.50 2.05 0.15 1.845
Length of Return wall = 1.4 + 0.1 = 1.5m
Width = 2.05 m
Depth = 0.15 m
No. = 4
Total 55.207
3 RCC grade M-25
Box Portion cum ###
(Refer MOST Dwg. No. SD/108 sheet 3 of 6)
4 PCC grade M-20
Wing Wall cum ###
(Refer MOST Dwg. No. SD/113 sheet 6 of 6)
Return Wall cum 4 1.40 1.75 9.800
Length = 1.4 m
Area =
(1.81x0.50)+(0.50x0.46x0.24)+(0.50x0.85x(0.85+0.3)+(
0.50x0.30)+(0.40x0.35) = 0.905+0.055+0.50+0.15+0.14
= 1.75 sqm

No. = 4

Appendix C - 96
Appendix C.26 j : Single Cell RCC Box Culvert of size 4 x 4 (U/S & D/S Pitching)

Sl. Descriptions Unit No. Length Width Ht./Th. Area Quantity


No.
Total ###
5 Approach slab
I. Levelling course M-15 concrete cum 2 3.50 12.00 0.15 12.600
L= 3.50 m
W = 12m
Thick = 0.15m
No. = 4
II. RCC M-25 grade concrete cum 2 3.50 12.00 0.30 25.200
L= 3.50 m
W = 12m
Thick = 0.3m
No. = 4
6 Crash Barrier Lm 2 12.10 24.200
No. = 2
L = 12.10 m
7 Filling with Filter media (Both side)
a) For Box Portion cum 2 0.60 12.00 3.40 48.960
No. =2
L= 0.6m
W = 12m
Ht. = 3.4m
b) For wing wall cum 4 0.60 9.84 3.92 92.584
Length of wing wall = 9.841 m
Ave.Ht. = (5.68+2.15)/2 = 3.92 m
Width = 0.60 m
No. = 4
Total ###
8 Stone pitching for Floor Apron
a) 150 mm thick PCC M-15 cum 22.900
b) 300 mm thick concrete cum 45.800
c) 150 mm thick Flat Stone cum 22.900
(Refer MOST Dwg. No. SD/111 sheet 4 of 4) 91.600
9 Stone pitching for Flexible Apron
750 mm thick Stone cum ###
(Refer MOST Dwg. No. SD/111 sheet 4 of 4)
10 Curtain Wall
a) PCC under curtain wall cum 9.000
c) Concrete for D/S curtain wall cum 34.000
d) Concrete for U/S curtain wall cum 26.300
(Refer MOST Dwg. No. SD/111 sheet 4 of 4)
11 Tar Paper Bearing sqm 2 12.00 0.30 7.200
12 Backfilling behind Abutment, wing wall etc.
a) Behind Abutment cum 2 12.00 3.50 3.70 ###
b) Behind Wing wall cum 4 9.84 3.50 3.50 ###
Total ###
13 Expansion joint Mtr. 2 12.00 24.000
14 Drainage Spout No. 4.000
15 Weap holes 100 mm dia. No. ###
16 Reinforcement (As per MOST)
a) For Box Portion MT 9.200

Appendix C - 97
Appendix C.26 i : Single Cell RCC Box Culvert of size 4 x 3 (U/S & D/S Pitching)

Sl.
No. Descriptions Unit No. Length Width Ht./Th. Area Quantity
1 Excavation ###
Box Portion cum 6.00 12.00 1.50 108.00
L=4.0+2x0.5+2x0.40+2x0.10 = 6.00 m
Width = 12 m
Depth = 1.5 m from natural ground level
For Key portion cum 2 6.00 0.28 3.30
L=4.0+2x0.5+2x0.40+2x0.10 = 6.00 m
Area = (0.30x0.50)+(0.50x0.50x0.50) = 0.275 sqm
No. = 2
Wing wall cum 4 6.93 3.74 1.50 155.51
Length of wing wall = 6.93 m
Depth of Foundation = 1.50 m
Width = (3.095+ 4.392)/2 = 3.74 m
(Refer MOST Dwq. No. SD/113 sheet 6 of 6)
No. = 4
For Return wall
Length of Return wall = 1.4 + 0.1 = 1.5m cum 4 1.50 2.05 1.50 18.45
Width = 2.05 m
Depth = 1.50 m
No. = 4
Total 285.26
2 Levelling course plain cement concrete grade M-15 in ###
foundation.
Box Portion cum 6.00 12.00 0.15 10.80
L=4.0+2x0.5+2x0.40+2x0.10 = 6.00 m
Width = 12 m
Thick = 0.15 m
Wing wall cum 4 6.93 3.74 0.15 15.55
Length of wing wall = 6.93 m
Depth = 0.15 m
Width = (3.095+ 4.392)/2 = 3.74 m
(Refer MOST Dwq. No. SD/113 sheet 6 of 6)
No. = 4
For Return wall cum 4 1.50 2.05 0.15 1.85
Length of Return wall = 1.4 + 0.1 = 1.5m
Width = 2.05 m
Depth = 0.15 m
No. = 4
Total 28.20
3 RCC grade M-25
Box Portion cum 114.00
(Refer MOST Dwg. No. SD/108 sheet 3 of 6)
4 PCC grade M-20
Wing Wall cum 101.65
(Refer MOST Dwg. No. SD/113 sheet 6 of 6)
Return Wall cum 4 1.40 1.75 9.80
Length = 1.4 m
Area =
(1.81x0.50)+(0.50x0.46x0.24)+(0.50x0.85x(0.85+0.3)+(
0.50x0.30)+(0.40x0.35) = 0.905+0.055+0.50+0.15+0.14
= 1.75 sqm

No. = 4
Total 111.45
5 Approach slab cum 2 3.50 12.00 0.15 12.60

Appendix C - 94
Appendix C.26 i : Single Cell RCC Box Culvert of size 4 x 3 (U/S & D/S Pitching)

Sl.
No. Descriptions Unit No. Length Width Ht./Th. Area Quantity
I. Levelling course M-15 concrete
L= 3.50 m
W = 12m

Appendix C - 95
Appendix C.26 i : Single Cell RCC Box Culvert of size 4 x 3 (U/S & D/S Pitching)

Sl.
No. Descriptions Unit No. Length Width Ht./Th. Area Quantity
Thick = 0.15m
No. = 2
II. RCC M-25 grade concrete
L= 3.50 m cum 2 3.50 12.00 0.30 25.20
W = 12m
Thick = 0.3m
No. = 2
6 Crash Barrier Lm 2 12.10 24.20
No. = 2
L = 4+2x0.5+2x3.5 = 12.10 m
7 Filling with Filter media (Both side) ###
a) For Box Portion cum 2 0.60 12.00 3.40 48.96
No. =2
L= 0.6m
W = 12m
Ht. = 3.4m
b) For wing wall cum 4 0.60 6.93 3.40 56.55
Length of wing wall = 6.93 m
Ave.Ht. = (4.65+2.15)/2 = 3.40 m
Width = 0.60 m
No. = 4
Total 105.51
8 Stone pitching for Floor Apron
a) 150 mm thick PCC M-15 cum 13.100
b) 300 mm thick concrete cum 26.200
c) 150 mm thick Flat Stone cum 13.100
(Refer MOST Dwg. No. SD/111 sheet 4 of 4) 52.400
9 Stone pitching for Flexible Apron
750 mm thick Stone cum 93.100
(Refer MOST Dwg. No. SD/111 sheet 4 of 4) ###
10 Curtain Wall
a) PCC under curtain wall cum 6.900
c) Concrete for D/S curtain wall cum 20.300
d) Concrete for U/S curtain wall cum 26.200
(Refer MOST Dwg. No. SD/111 sheet 4 of 4)
11 Tar Paper Bearing sqm 2 12.00 0.30 7.20
12 Backfilling behind Abutment, wing wall etc.
a) Behind Abutment cum 2 12.00 3.50 2.50 210.00
b) Behind Wing wall cum 4 6.93 3.50 2.40 232.85
Total 442.85
13 Expansion joint Mtr. 2 12.00 24.00
14 Drainage Spout No. 4.00
15 Weap holes 100 mm dia. No. 145.00
16 Reinforcement (As per MOST) ###
a) For Box Portion MT 7.12

Executive Engineer, PWD


Nagaon NH Division, Nagaon

Appendix C - 96