Vous êtes sur la page 1sur 8

MONITORING

The cost of damages caused by bushing


failures and the lost opportunity to deliv-
er energy could be several hundred times
higher than the price of a bushing

ABSTRACT
Transformer bushings are one of the
Transformer
bushing
most critical components of a trans-
former. Up to 20 % of major failures
on high voltage transformers today
can be tracked back to bushings.

monitoring
Almost half of these failures result
in catastrophic failures like explo-
sions, fires or oil spillages. The cost
of these damages and the lost op-
portunity to deliver energy could be
several hundred times higher than Higher accuracy leads to better faults
the price of a bushing. Even a fail-
ing bushing which will not lead to a
detection
catastrophic failure can harm people
due to burst porcelain insulators and 1. Introduction within the lifetime of the bushings. One:
broken fragments that can be cata- when the bushings reach an age of 10 to 13
pulted through the air by the force of Today, the experience is that a transformer years, failure is possible due to production
the breakdown arc. will have two sets of bushings during its and quality related issues. The second
entire lifetime. Transformers are expected wave of bushing failures can happen
to last 50 years, while bushings have an between 20 to 30 years of age, which is
KEYWORDS expected lifetime of 25 years. Experience considered as the normal life time. It is
bushing, monitoring, accuracy
suggests there are two points of failure also true that bushings can fail younger

108
108 TRANSFORMERS MAGAZINE | Special Edition: Bushings, 2017
Advertorial

In order to have a reliable monitoring system,


the accuracy of the acquisition of the moni-
tored parameters needs to be very high

loss angle will only show a slight change at and cannot, once one fails, be exchanged
ambient temperature. Common bushing easily by a new one. Often transformer fail­
monitoring systems today are not able ures cause the inability to deliver energy,
to capture these slight, but important and have high potential to harm people in
changes. The bushings from different addition to causing environmental disas­
phases are being cross-referenced to ters. Due to these factors, a high financial
each other. The sister bushings are used impact is often connected to transformer
as a reference source to assess the relative failures.
condition of a bushing. Voltage and angle
differences between phases, as well as Old economies such as Europe, North
different temperatures and aging rates are America and Japan are facing aged key
not considered with these methods. network components. Continuous moni­
toring solutions were not used extensively
Newer approaches are using stable voltage in the past, due to n-1 availability of the
sources as reference signals, preferable main equipment. Furthermore, moni­
from the same phase as the monitored toring solutions were less reliable or not
bushing. The phase shift between the available 10 to 20 years ago. The condi­
leakage current signal from the bushing tion assessment in the utilities of the old
and the voltage from the voltage economies was typically carried out using
transformer will be measured, corrected comprehensive periodic measurements
by the phase shift offset, and the loss factor and maintenance programs. Nowadays
can be calculated directly. For example, these utilities are seeking more and more
by using a voltage transformer (VT) for solutions to operate their costly com­
as reference source, small, but relevant ponents until their real end of life. Fur­
changes can be detected. thermore, asset exchange programs will
have to be based on the condition of the
The two main health indicators for a equipment. Condition monitoring (CM)
bushing are the loss factor (tan δ / power and condition based maintenance (CBM)
than 10 years as is also true that there are factor) and the capacitance. While the loss are an important factor to achieve these
bushings installed on transformers with factor is sensitive to almost all bushing goals. Transformers and transformer bush­
an age of more than 50 years. faults, the capacitance is an important ings are important components to look at
factor to detect partial breakdowns in these regards.
Bushing monitoring is designed to detect between capacitive layers and to detect, in
incipient faults and give an early warning, combination with the loss factor, contact The CIGRE WG A2.37 released in 2012
as well as using the bushings until their problems inside the bushing such as bad an interim report [1] which shows the
real end of life. In order to have a reliable contacts inside the bushing taps. newest statistics on transformer failures,
monitoring system, the accuracy of the see Table 1.
acquisition of the monitored parameters
needs to be very high. For example,
2. Failure statistic It can be seen that over all voltage classes,
even if a relevant amount of moisture is Transformers are one of the most critical transformer failure rate is 0.44 %, which
impregnated into the bushing core, the components within the electrical network means, out of approximately 230

Table 1. Transformer failure statistics [1]


Highest system voltage


FAILURES & POPULATION 69 kV <100 100 kV <200 200 kV <300 300 kV <500 700 kV All
INFORMATION

Failures 145 212 163 154 11 685


Transformer - Years 15220 48994 47473 41569 959 156186
FAILURE RATE / YEAR 0.95 % 0.43 % 0.34 % 0.37 % 1.15 % 0.44 %

w w w . t ra n sfo r m e r s - m a g a z i n e . co m 109
MONITORING

Figure 1. Failed component statistics [1]

Power factor and partial discharge meas­ure­ of a bushing can lead to catastrophic
failures and can be going along with
ments are the most powerful parameters environmental disasters or fatal accidents
of personnel. According to a transformer
which can uncover most of the incipient reliability study published in [2], the
bushing failures majority of transformer fires are caused
by bushing failures.

transformers, one will fail per year. transformer and its main components The causes of bushing failures are
Besides the preventions of failures or needs to be gathered. Besides other varying from normal aging, moisture,
early detection of upcoming faults, components and accessories, bushings quality issues during manufacturing,
the assessment of the remaining life are one of the main causes of transformer repeated thermal and mechanical cycling,
and the health of equipment is of failures. The contribution to transformer transients and external influences like
immense interest, especially for aged failures is around 20 % of the overall external flashovers. As result, a high
equipment. To assess the asset condition, transformer major failures, depending number of bushing failures develop from
a comprehensive set of data from the on the type of transformer, Fig. 1. Failing partial breakdowns, thermal instabilities

Table 2. Detectability of different bushing failures (plus – it can be detected, minus – it cannot be detected)

Defect Tan δ Capacitance Partial discharge

-/+
Insulation aging + - Detectable if discharges are the
cause of the degradation/ aging

Moisture + - -

(+)
Void / Delamination After a certain time once the - +
dielectric material starts to corrode
+/-
Surface contamination + - If the surface contaminations
are creating surface discharges

+/-
Surface discharges Surface discharges with a high intensity - +
can be seen by a unstable tan δ
+/-
Partial breakdowns If it is combined with erosion of + +/-
insulating material
+ +
Contact problems Shows up as an increased Shows up as decreased +
or unstable tan δ or unstable capacitance

110 TRANSFORMERS MAGAZINE | Special Edition: Bushings, 2017


Figure 2. Leakage current and power factor / dissipation factor

or degradations of longitudinal insulation 3.1 Power factor / dissipation factor between capacitive and resistive current,
interfaces. which are presenting in their summation
The power factor reflects, as property of the leakage current.
The average lifetime of bushings is esti­ the insulation material, the condition of
mated in general as half of the life of a the insulation itself. It represents the ratio The capacitive current is the result of the
transformer (25 years). In reality, there are
bushings still working properly which are
older than 40 years as well as there are bush­
ings which are failing after 10 to 12 years
The advantage of online power factor moni­
of operation. To improve the transformer toring is that the power factor of a bushing
reliability the demand of reliable bushing
monitoring is increasing throughout the can be seen at different temperatures
industry.

3. Bushing monitoring
parameters
The main bushing parameters used
today for bushing health assessment are
the power factor in the IEEE world or
dissipation factor in the IEC world, the
main bushing capacitance and the partial
discharge activity. Table 2 provides
reference to the different bushing
parameters and their ability to be used to
detect different failures in an early stage
of development.

It can be seen that power factor and Figure 3. Power factor behavior over temperature due to increased moisture
partial discharge measurements are the
most powerful parameters which can
uncover most of the incipient bushing
failures. The capacitance monitoring is
a good indicator for partial breakdowns
(breakdown between two or more layers
with the result of a short circuit between
them) and contact problems (capacitance
decreases or is fluctuating heavily). Each
parameter will be discussed further
regarding the best usage for online
assessment of the condition of capacitor
core bushings. Figure 4. Bushing series capacitances

w w w . t ra n sfo r m e r s - m a g a z i n e . co m 111
MONITORING

Figure 5. Challenges for online bushing PD monitoring

capacitive layer design and therewith


given by design. The resistive current is
Detection of bushing related partial dis-
caused by the resistivity of the insula­ charge under online conditions is facing
tion material and is a direct parameter of
the quality of the insulation system. Each major problems
healthy solid and liquid insulation mate­
rial has its typical relative resistive current
component. An increasing resistive cur­ detect the power factor difference at 20 °C 3.2 Capacitance
rent will indicate a degradation of the in­ for a “wet” and “dry” insulation. With the
sulation system and will increase the angle δ current online methods, this accuracy As described above, the capacitive
and decrease the angle φ and will result can hardly be achieved. The difference current resulted by the capacitance is a
in an increase in power factor, Fig. 2. The between a dry and a wet bushing could parameter which represents the design
power factor measurement under online be 0.2 % at 40 °C, which still needs a high of the capacitive layers of a bushing.
conditions requires a high accuracy in accuracy to detect moisture or insulation It will increase if two or more layers
order to detect already small changes and aging early enough. of the electrical field control foils are
to guarantee the detection of increasing electrically shorted, Fig. 4. If only two
moisture content in the insulation system, The advantage of online power factor moni­ layers are shorted, the capacitance will
which is difficult to achieve under online toring is that the power factor of a bushing increase by a percentage equivalent to
condition. External influences like low can be seen at different temperatures. the total number of layers. For example,
frequency magnetic fields, external noise Depending on the load of the transformer, if 2 out of total 50 foils (layers) will be
and harmonics as well as the lack of sta­ the temperature of the bushing will vary. short-circuited, the capacitance will
ble reference signal sources are the factors Figure 3 shows that the power factor increase by 2 %.
which influence these measurements. gradient of “wet” bushings is much higher
at higher temperatures than for “dry” Although pure capacitance monitoring
Figure 3 shows the behavior of an bush­ings at the same temperature. Offline is easy to apply for online purposes
insulation system with increased moisture measurements at ambient temperature by simply using a defined secondary
contamination. The accuracy of the power and low accuracy online monitoring are capacitor (C3), the number of detectable
factor monitoring needs to be very high to not able to detect this kind of defects. defects are limited, see Table 2.

112 TRANSFORMERS MAGAZINE | Special Edition: Bushings, 2017


Common methods, give limited information about the monitored for bushings specifically by
health of a bushing. Mainly the partial using different methods, which will be
e.g. balanced current discharge from a bushing will be hidden discussed in the next chapter more in
method, have limita- by ‘external’ discharges/disturbances. detail.
Furthermore, the sensitivity is limited
tions due to the influ- and it is difficult to allocate detected
4. Overview of today’s used
ences of the natural discharges to a certain component or
even to distinguish between internal and bushing monitoring methods
load imbalance external discharges. The newest method used today for bush­
ing monitoring is the reference signal
More promising is to use capacitance m­ethod, where the phase shift of the
3.3 Partial discharge and the power factor. They can be leakage current of a bushing and its stable

As per Table 2, a high number of different


bushing defects can be detected by partial
discharge monitoring but not moisture.
Therefore, partial discharge (PD) mea­
surements are very important for routine
and re-testing at factory or onsite. Never­
theless, the detection of the bushing re­
lated partial discharge under online con­
ditions is facing major problems.

The measuring principle for online PD


bushing monitoring used today is based on
the IEC 60270 method. The bushing capa­
citance will be used as coupling capacitor.
Mainly this PD monitoring principle is ap­
plied to monitor PD in transformers but in
some cases also to monitor the bushings.

The PD magnitudes of incipient bush­


ing faults are between 5 pC up to 100
pC. Higher values are possible in case of
contact issues. Typical values are usu­
ally below 50 pC. Comparing that with
the allowed and possible PD activity on
overhead lines (some nC) and inside the
Figure 6. Principle overview of the balanced current method
transformer (typically 500 pC up to 1 nC
allowed – see Figure 5), most likely the
bushing PD will be hided due to the high­
er ‘external’ signals. Furthermore, due to
the high capacitance of the test object and
the typical onsite background noise, the
sensitivity of such a PD monitoring using
the bushing as coupling capacitor is quite
limited. Additional to that, if a PD signal
is detected, it is difficult or even in some
cases impossible to find the origin of the
detected PD without any additional mea­
surements, which might require an outage
of the transformer. It could come from the
overhead lines, line connectors, trans­for­m­
er, high current duct or maybe even the
bushing itself.

3.4 Proposed parameter for online


monitoring

It can be concluded that partial discharge


online monitoring for bushings will Figure 7. Principle of the reference signal method

w w w . t ra n sfo r m e r s - m a g a z i n e . co m 113
MONITORING

load happen mostly more gradually and


are not permanent.

Another challenge for that method is the


phase asymmetry regarding the phase
angle. If the phase angle unbalance is only
0.2 degree, it would result in a deviation of
the power factor of about 0.35 %, which
is more than 100 % assuming the power
factor of a healthy OIP (Oil-impregnated
Paper) bushing will be around 0.25 %! The
small power factor changes, caused by
moisture (compare Figure 4), cannot be
detected or being detected in a late stage
of degradation.

Modern systems are using self-learning


methods, which are recording the typi­
cal daily and seasonal behavior of the
bushings to predict the load conditions.
Nevertheless, the achievable accuracy re­
garding the measured power factor is lim­
ited and is mostly displayed as a relative
change to the sister bushings.

Using this method for single phase trans­


former is even more challenging.

4.2 Reference method

Today the biggest drawback to increase


the accuracy and stability in power factor
and capacitance monitoring is that bush­
ings will be compared across phases.
Figure 8. Example for effective noise elimination
The only approach to overcome this
drawback is to find a load independent
reference signal is measured. This method imbalanced load. Phase asymmetries re­ ref­erence signal source within the same
will be discussed further below in more garding voltage magnitude of 1 to 1.5 % phase of the monitored bushing.
detail, but first the most common method and 0.2 degree in phase angle variations
and its advantages and disadvantages will are very common for stable networks The installation of a standard capacitor
be described. known from the ‘old economies’. Much (gas filled) as used for offline measure­
higher asymmetries can be seen in more ment and during routine testing in high
4.1 Balanced current method unstable networks in other parts of the voltage laboratories is far too expensive.
world. Another possibility is the usage of a volt­
The balanced current method, also age transformer. A voltage transformer
known as sum of currents method, Fig. 6, The asymmetries are changing with the (VT) always has a stable load on its sec­
is today’s most used method for bushing load conditions in a daily, seasonal and ondary winding (not load depended).
monitoring. The assumption is that under unpredictable manner. Changes in capa­ Furthermore, the VTs are not changing
perfect circumstances the summation of citance of a bushing (partial breakdowns) their transfer behavior with varying load
the leakage currents of the three bushings can be detected more easily because the of the network. The principle of this meth­
of the different phases under considerati­ general fluctuations of the voltage mag­ od is to measure the phase shift between
on of its phase angles is zero. The perfect nitude across all the three phase is lower the bushing leakage current and reference
circumstances mean that for all phases, compared to the expected change because signal. While existing equipment can be
the magnitude of the voltage amplitudes of a critical partial breakdown. But still, the used, it reduces the needed hardware to
are absolutely the same, and the phase clear detection of a partial breakdown for a minimum. Figure 7 illustrates the prin­
shift between the phases is exactly 120 voltage levels 500 kV and above remains ciple of the reference signal method using
degrees. Further, the bushings are con­ a challenge, even if the voltage magnitude VTs (CVTs) from the same phase.
sidered to behave the same. asymmetry is only 1.5 %. Nevertheless, a
partial breakdown shows up rather as a The reference signal is taken from the
Real electrical networks are carrying an permanent step change, while changes in same phase which increases the achieve­

114 TRANSFORMERS MAGAZINE | Special Edition: Bushings, 2017


a­ble accuracy. It is then not depending on By using a reference signal from the same
phase asymmetries any more. After digiti­
zing both input signals, all signal proces­ phase, a higher accuracy and a better de-
sing will be done by software algorithms.
Existing phase constant shifts from VT,
tection of incipient faults can be achieved
cables, etc. must be compensated.

The major challenges are the elimination


or limitation of noise, and the availability
of a stable reference source. Especially the
second is not always given. Sometimes
there are no VTs/ CVTs at the high volt­
age side or they are far away in a separate
switchyard (especially in power plants)
or VTs/ CVTs existing only for one phase
(mostly the middle phase). A comparative
monitoring in these cases can be applied,
where another bushing from the same
phase but a different transformer can be
used as reference and vice versa. Other
alternative methods are under develop­
ment.
Figure 9. Raw data example from site
The elimination or limitation of noise is
one of the major requirements to achiev­e
the necessary accuracy in the phase interest by utilities and power producers. References
shift measurement of 0.0057 degree (or Common methods, e.g. those based on
0.1 mrad). Fig. 8 is showing a noisy signal bal­anced current principles, are having 1. A2.37, CIGRE WG, Transformer Reli-
before and after signal processing, which limitations due to the influences of the na­ ability Survey: Interim Report, No. 261,
can be described as follows: tural unbalance of the network load. ELECTRA. 2012

• Noise and harmonics need to be elimi­ By using a reference from the same phase, 2. H.-P. Berg and N. Fritze, Reliability
nated by advanced software algorithms a higher accuracy and a better detection of of main transformers, Bundesamt für
incipient faults can be achieved. Further, Strahlenschutz, Salzgitter, Germany,
• The accuracy of the phase measurement this method will deliver direct power 2011
is better than 0.1 mrad (0.0057 degree) factor readings instead of the percentage
read­ings being shown today.
• The accuracy enables to detect changes
Contact
in tan δ form, e.g. 0.325 % to 0.340 % Further developments will be done to Thomas Linn
provide a reliable reference voltage source Phone: +1 585 643 3625
• This enables to detect moisture increa­ more easily and lesser efforts in cabling. E-mail: tlinn@qualitrolcorp.com
se, insulation system aging and degrad­
ation early enough

• Temperature compensation will be Author


necessary to achieve this accuracy Thomas Linn graduated from the Technical University
of Dresden with a degree in Electrical Engineering,
Furthermore, Fig. 9 shows another ex­ specializing in High Voltage Techniques. In 1998 he joined
ample for recorded raw data. Due to the ABB in Switzerland and was responsible for high voltage
relatively high amplitude, the signal from onsite testing for GIS and cables, PD measurements onsite
the reference source (blue curve) is almost and PD monitoring of gas insulated switchgear. Afterwards
not disturbed, while the signal coming he worked for 10 years with high voltage transformer
from the bushing tap has a noise compo­ bushings and became a senior technical expert for high
nent of about 15 to 20 %. voltage techniques and equipment. In March 2013 Thomas joined Qualitrol as
Technical Application Specialist. As a TAS, Thomas is able to leverage 20+ years
of experience in high voltage equipment such as GIS, high voltage bushings,
Conclusions cables, transformers, high voltage testing, partial discharge measurement and
Bushings are critical parts on transform­ monitoring, and high voltage test equipment. Thomas is a member of CIGRE
ers and having the potential to lead to and IEC TC42 in Switzerland and is contributing as an expert to different
catas­
trophic transformer failures. The CIGRE Working Groups internationally.
bushing online monitoring is gaining high

w w w . t ra n sfo r m e r s - m a g a z i n e . co m 115

Vous aimerez peut-être aussi