Rev : 00
LAMPIRAN 9.1.
Date : Location :
Contract No. : Elevation : El. …………… m to El. ………….. m
Contractor Source of borrow area : ……………………….
Item no. : Weather : ( ) Clear, ( ) Cloudy, ( ) Rainy
2 Placing of material
a. Thickness of layer after spreading is within specified. (yes) (no)
b. Removal of all roots, mud etc. from fill material has been completed (yes) (no)
3 Compaction
a. Condition of compaction equipment (good) (bad)
b. Time of roller passing (as specified) (yes) (no)
c. Required tests have been done properly (as specified) (yes) (no)