KOEFISIE HARGA

SATUAN URAIAN JUMLAH


N SATUAN
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 45,700.00 57,125.00
2.5 Kg Portland Semen 11,312.50 28,281.25
1.2 Lbr Seng Gelombang 3" - 5" 64,850.00 77,820.00
0.005 m3 Pasir Pasang 135,000.00 675
0.009 m3 Koral Beton 271,250.00 2,441.25
0.072 m3 Kayu 5/7X4m Kayu Meranti 3,447,500.00 248,220.00
0.06 Kg Paku Biasa 2" - 5" 26,750.00 1,605.00
0.45 Kg Meni Besi 26,100.00 11,745.00

0.2 OH Tukang Kayu 52,500.00 10,500.00


0.4 OH Pekerja 40,000.00 16,000.00
0.02 OH Kepala Tukang 55,000.00 1,100.00
0.02 OH Mandor 50,000.00 1,000.00
456,512.50
1 Pengukuran dan Pemasangan Bouwplank

Tenaga Koefisien Satuan


Kayu 5/7 0,012 M3
Paku biasa 2" - 5" 0,020 Kg
Kayu papan 3/20 0,007 M3

Sebagai contoh, dengan harga masing masing bahan untuk tabel di atas adalah sebagai berikut:

2 Harga Bahan
Bahan Harga
Kayu 5/7 22.000,00
Paku biasa 2" - 5" 22.000,00
Kayu papan 3/20 17.600,00

Dari Pengalian tabel nomor 1 dan 2, maka diperoleh analisa untuk Pengukuran dan Pemasangan

3 Pengukuran dan Pemasangan Bouwplank

Tenaga Koefisien Satuan Jumla


h
Harga
Kayu 5/7 0,012 Btg 264,0
Paku biasa 2" - 5" 0,020 M³ 0
440,0
Kayu papan 3/20 0,007 Kg 0
123,2
Total 0
827,2
0
Langka
h 3:
Menghi
tung
Upah
Tenaga
Kerja

Untuk
standar
upah,
harus
mengikuti
standar
upah
tiap-tiap
daerah
yang
dikeluark
an oleh
dinas
pekerjaan
umum
dengan
cara
mengalik
an upah
standar
dengan
koefisien
yang
ditetapka
n. Seperti
tabel
dibawah
ini:

4 Satuan dan Koefisien Tenaga Pengukuran dan Pemasangan


Bouwplank

Tenaga Koefisien Satuan


Tukang kayu 0,1 Oh
Pekerja 0,1 Oh
Kepala tukang 0,01 Oh
Mandor 0,005 Oh
Untuk
Upah
tenaga
kerja
yang
diperluk
an
dalam 
Pembua
tan
Penguku
ran dan
Pemasa
ngan
Bouwpla
nk,
seperti
tabel
dibawah

5 Upah Tenaga Pengukuran dan Pemasangan


Bouwplank

Tenaga Koefisien
Tukang kayu 80.000,00
Pekerja 70.000,00
Kepala tukang 100.000,00
Mandor 90.000,00
Selanjut
nya
adalah
dengan
mengali
kan
tabel
nomor 4
dan
tabel
nomor
5,
sehingg
a
diperole
h
analisa
biaya
untuk
Penguku
ran dan
Pemasa
ngan
Bouwpla
nk,
seperti
tabel di
bawah
ini.

6 Satuan dan Koefisien Tenaga Pengukuran dan Pemasangan Bouwplank

Tenaga Koefisien Satuan Jumla


h
Harga
Tukang kayu 0,1 Oh 8.000,
00
Pekerja 0,1 Oh 7.000,
00
Kepala tukang 0,01 Oh 1.000,
00
Mandor 0,005 Oh 450,0
Total 0
16.45
0,000
h sebagai berikut:

ran dan Pemasangan Bouwplank adalah sebagi berikut.


No. URAIAN SATUAN

A-01 1 M' Pagar Sementara Dari Kayu Tinggi 2 m

Dolken Kayu Ø
- Btg
8-10 / 400 cm

Semen
- Kg
Portland
- Pasir beton M3
- Koral Beton 2/3 M3
Kayu balok
- M3
terentang
Paku Biasa 2" -
- Kg
5"
- Residu Kg
- Pekerja Oh
- Tukang Kayu Oh
- Kepala Tukang Oh
- Mandor Oh
Jumlah
Dibulatkan
A-02 1 M' Pagar Sementara Seng Gelombang Tinggi 2 m

Dolken Kayu Ø
- Btg
8-10 / 400 cm

Semen
- Kg
Portland
Seng
- Gelombang Lbr
BJLS-30
- Pasir beton M3
- Koral Beton 2/3 M3
Kayu balok
- M3
terentang
Paku Biasa 2" -
- Kg
5"
- Meni Besi Kg
- Pekerja Oh
- Tukang Kayu Oh
- Kepala Tukang Oh
- Mandor Oh
Jumlah
Dibulatkan

A-03 1 M' Pagar SementaraKawat Duri Tinggi 1,80 m

Dolken Kayu Ø
- Btg
8-10 / 400 cm

Semen
- Kg
Portland
- Kawat Duri Kg
- Pasir beton M3
- Koral Beton 2/3 M3
Paku Biasa 2" -
- Kg
5"
- Pekerja Oh
- Tukang Kayu Oh
- Kepala Tukang Oh
- Mandor Oh
Jumlah
Dibulatkan

A-04 1 M2 Pengukuran Dan Pasang Bouwplank

- Kayu kaso 5/7 M3


Paku Biasa 2" -
- Kg
5"
Kayu papan
- M3
albasia
- Pekerja Oh
- Tukang Kayu Oh
- Kepala Tukang Oh
- Mandor Oh
Jumlah
Dibulatkan
A-05 1 M2 Pembuatan Kantor Sementara dgn Lantai Diplester

Dolken Kayu Ø
- Btg
8-10 / 400 cm

Kayu Balok
- M3
terentang
- Paku Biasa Kg
- Besi Strip Kg
Semen
- Kg
Portland
- Pasir Pasang M3
- Pasir beton M3
- Koral Beton2/3 M3
- Bata Merah Bh
- Seng Plat m'
Kawat
- M2
harmonika
Kaca Polos
- M2
3mm
- Kunci Tanam Bh
Plywood 120 x
- Lbr
240 x 0,4 cm
- Pekerja Oh
- Tukang Kayu Oh
- Tukang Batu Oh
- Kepala Tukang Oh
- Mandor Oh
Jumlah
Dibulatkan

A-06 1 M2 Pembuatan Gudang Semen dan Alat-alat

Dolken Kayu Ø
- Btg
8-10 / 400 cm

Kayu balok
- M3
terentang
- Paku Biasa Kg
Semen
- Kg
Portland
- Pasir Beton M3
- Koral Beton 2/3 M3

Seng
- Gelombang Lbr
BJLS 30
- Pekerja Oh
- Tukang Kayu Oh
- Kepala Tukang Oh
- Mandor Oh
Jumlah
Dibulatkan
A-07 1 M2 Pembuatan Bedeng Buruh

Dolken Kayu Ø
- Btg
8-10 / 400 cm

Kayu balok
- M3
terentang
- Paku Biasa Kg
Semen
- Kg
Portland
- Pasir Beton M3
- Koral Beton 2/3 M3

Seng
- Gelombang Lbr
BJLS 30
- Pekerja Oh
- Tukang Kayu Oh
- Kepala Tukang Oh
- Mandor Oh
Jumlah
Dibulatkan
A-08 1 M2 Membersihkan Lapangan dan Perataan
- Pekerja Oh
- Mandor Oh
Jumlah
Dibulatkan
A-09 1M2 Pembuatan Jalan Sementara
Batu Belah
- M3
15/20
- Batu Pecah 5/7 M3
- Pasir Pasang M3
- Pekerja Oh
- Mandor Oh
Jumlah
Dibulatkan
A-10 1 M3 Bongkaran Beton Bertulang
- Pekerja Oh
- Mandor Oh
Jumlah
Dibulatkan
A-11 1 M3 Bongkaran Dinding Tembok Bata Merah
- Pekerja Oh
- Mandor Oh
Jumlah
Dibulatkan

A-12 1 M¹ Pagar beton Pracetak ( 5 x 50 x 213 ) cm

Panel Beton
- Lbr
Pracetak
Kolom Beton
- Btg
Pracetak
- Pasir Beton M3
- Koral 2/3 M3
Semen abu -
- Kg
abu
- Pekerja Oh
- Tukang Batu Oh
- Kepala Tukang Oh
- Mandor Oh
Jumlah
Dibulatkan
A-13 1 M¹ Pagar kawat ayam tiang besi L50.50.5, tinggi 1 m'
Kawat ram
- Lbr
ayam
Besi siku L
- Kg
50.50.5
Besi pelat (1,2
- Kg
x 3) mm
- Baut bh
Semen
- Kg
Portland
- Pasir beton M3
- Koral Beton 2/3 M3
- Pekerja Oh
- Tukang Batu Oh
- Kepala Tukang Oh
- Mandor Oh
Jumlah
Dibulatkan
A-14 1 M2 Pagar BRC lengkap dengan tiang
BRC lengkap
- Lbr
dengan tiang
Semen
- Kg
Portland
- Kawat Duri Kg
- Pasir beton M3
- Koral Beton 2/3 M3
- Pekerja Oh
- Tukang Batu Oh
- Kepala Tukang Oh
- Mandor Oh
Jumlah
Dibulatkan
A-15 1 M2 Steiger Werk / perancah dari Bambu
Bambu Ø 6 -
- btng
10 (600) cm
- Tali ijuk kg
- Pekerja org
- Tukang kayu org
- Kepala tukang org
- Mandor org
Jumlah
Dibulatkan
A-16 1 M' Cerucuk Bambu
Bambu Ø 7 -10
- btng
(400) cm
- Pekerja org
- Mandor org
Jumlah
Dibulatkan
HARGA
VOLUME HARGA
SATUAN
(Rp) (Rp)

1.25 28,000.00 35,000.00

2.5 1,406.00 3,515.00


0.005 255,400.00 1,277.00
0.009 211,100.00 1,899.90

0.072 2,640,000.00 190,080.00

0.06 23,400.00 1,404.00


0.4 8,100.00 3,240.00
0.4 42,000.00 16,800.00
0.2 65,000.00 13,000.00
0.02 75,000.00 1,500.00
0.02 80,000.00 1,600.00
269,315.90
269,316.00

1.25 28,000.00 35,000.00

2.5 1,406.00 3,515.00

1.2 62,900.00 75,480.00

0.005 255,400.00 1,277.00


0.009 211,100.00 1,899.90

0.072 2,640,000.00 190,080.00

0.06 23,400.00 1,404.00


0.45 30,400.00 13,680.00
0.4 42,000.00 16,800.00
0.2 65,000.00 13,000.00
0.02 75,000.00 1,500.00
0.02 80,000.00 1,600.00
355,235.90
355,236.00

1 28,000.00 28,000.00

2 1,406.00 2,812.00
2.5 63,500.00 158,750.00
0.005 255,400.00 1,277.00
0.009 211,100.00 1,899.90

0.06 23,400.00 1,404.00


0.3 42,000.00 12,600.00
0.2 65,000.00 13,000.00
0.02 75,000.00 1,500.00
0.02 80,000.00 1,600.00
222,842.90
222,843.00

0.012 1,870,500.00 22,446.00


0.02 23,400.00 468

0.007 2,071,700.00 14,501.90


0.1 42,000.00 4,200.00
0.1 65,000.00 6,500.00
0.01 75,000.00 750
0.005 80,000.00 400
49,265.90
49,266.00
1.25 28,000.00 35,000.00

0.18 2,640,000.00 475,200.00


0.85 23,400.00 19,890.00
1.1 26,800.00 29,480.00
35 1,406.00 49,210.00
0.15 233,400.00 35,010.00
0.1 255,400.00 25,540.00
0.15 211,100.00 31,665.00
30 775 23,250.00
0.25 15,815.00 3,953.75
2 35,900.00 71,800.00

0.08 87,400.00 6,992.00


0.15 94,500.00 14,175.00
0.06 140,000.00 8,400.00
2 42,000.00 84,000.00
2 65,000.00 130,000.00
1 65,000.00 65,000.00
0.3 75,000.00 22,500.00
0.05 80,000.00 4,000.00
1,135,065.75
1,135,066.00

1.7 28,000.00 47,600.00

0.21 2,640,000.00 554,400.00


0.3 23,400.00 7,020.00
10.5 1,406.00 14,763.00
0.03 255,400.00 7,662.00
0.05 211,100.00 10,555.00

1.5 62,900.00 94,350.00

1 42,000.00 42,000.00
2 65,000.00 130,000.00
0.2 75,000.00 15,000.00
0.05 80,000.00 4,000.00
927,350.00
927,350.00

1.25 28,000.00 35,000.00

0.186 2,640,000.00 491,040.00


0.3 23,400.00 7,020.00
18 1,406.00 25,308.00
0.03 255,400.00 7,662.00
0.05 211,100.00 10,555.00

1.5 62,900.00 94,350.00

1 42,000.00 42,000.00
2 65,000.00 130,000.00
0.2 75,000.00 15,000.00
0.05 80,000.00 4,000.00
861,935.00
861,935.00

0.1 42,000.00 4,200.00


0.05 80,000.00 4,000.00
8,200.00
8,200.00
0.15 205,500.00 30,825.00

0.09 196,000.00 17,640.00


0.01 233,400.00 2,334.00
1 42,000.00 42,000.00
0.05 80,000.00 4,000.00
96,799.00
96,799.00

6.667 42,000.00 280,014.00


0.333 80,000.00 26,640.00
306,654.00
306,654.00

6.667 42,000.00 280,014.00


0.033 80,000.00 2,640.00
282,654.00
282,654.00

0.986 199,200.00 196,411.20

0.525 264,000.00 138,600.00


0.074 255,400.00 18,899.60
0.146 211,100.00 30,820.60
45 1,406.00 63,270.00
0.375 42,000.00 15,750.00
0.125 65,000.00 8,125.00
0.012 75,000.00 900
0.019 80,000.00 1,520.00
474,296.40
474,296.00

0.434 14,900.00 6,466.60

6.786 18,300.00 124,183.80


0.0424 18,300.00 775.92
4 600 2,400.00
2.5 1,406.00 3,515.00
0.005 255,400.00 1,277.00
0.009 211,100.00 1,899.90
0.375 42,000.00 15,750.00
0.125 65,000.00 8,125.00
0.012 75,000.00 900
0.019 80,000.00 1,520.00
166,813.22
166,813.00

0.434 171,300.00 74,344.20

2 1,406.00 2,812.00
2.5 63,500.00 158,750.00
0.005 255,400.00 1,277.00
0.009 211,100.00 1,899.90
0.375 42,000.00 15,750.00
0.125 65,000.00 8,125.00
0.012 75,000.00 900
0.019 80,000.00 1,520.00
265,378.10
265,378.00

1 25,000.00 25,000.00
0.25 23,400.00 5,850.00
0.25 42,000.00 10,500.00
0.017 65,000.00 1,105.00
0.002 75,000.00 150
0.013 80,000.00 1,040.00
43,645.00
43,645.00
1.25 25,000.00 31,250.00
0.5 42,000.00 21,000.00
0.025 80,000.00 2,000.00
54,250.00
54,250.00
Analisa Harga Satu

No.

N-01 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama


-
-
-

Dibulatkan
N-02 1 M2 Mendempul Dan Menggosok Kayu
-
-

-
-
-

-
-

Dibulatkan
N-03 1 M2 Pengecatan Bidang Kayu Lama Setara Sieve
-
-

-
-

-
-

Dibulatkan
N-04 1 M2 Pengecatan Bidang Kayu Baru Setara Sieve

-
-
-

-
-

-
-

Dibulatkan
N-05 1 M2 Pelaburan Bidang Kayu dengan Politur
-
-
-
-

-
-

Dibulatkan
N-06 1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter
-
-
-

Dibulatkan
N-07 1 M2 Pengecatan Tembok Baru Setara ICI
-
-
-
-
-
-
-

Dibulatkan
N-08 1 M2 Pengecatan Tembok Lama Setara ICI
-

-
-

-
-

Dibulatkan
N-09 1 M2 Pengecatan Plafond ( 3x ) Setara ICI

-
-
-
-
-
-

-
-

Dibulatkan
N-10 1 M2 Pengecatan Plafond ( 3x ) Setara Vinilex

-
-
-
-
-
-

-
-

Dibulatkan
N-10-r' 1 M2 Pengecatan Plafond ( 2x ) Setara Vinilex

-
-
-
-
-
-

-
-

Dibulatkan
N-11 1 M2 Memasang Wallpaper
-

-
-
-

-
-

Dibulatkan
N-12 1 M2 Pengecatan Permukaan Baja dengan Meni Besi
-
-
-
-

-
-

Dibulatkan
N-13 1 M2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah

-
-

-
-

-
-

Dibulatkan
N-14 1 M2 Pengecatan Permukaan Baja Lapis seng (galbani) secara manual 1 lps cat 2 um

-
-

-
-

Dibulatkan
N-15 1 M2 Pengecatan Tembok Baru Setara Vinilex (2 x laburan)

-
-

-
-

-
-

Dibulatkan
N-15r' 1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x laburan)

-
-

-
-

Dibulatkan
N-16 1 M2 Pengecatan Tembok Lama Setara Vinilex
-

-
-

-
-

Dibulatkan
Analisa Harga Satuan Pekerjaan Pengecatan
Diposkan : 05 Juni 2014
Oleh :

VOLUM
URAIAN SAT HARGA SAT HARGA
E

Soda api Kg 0.05 35,600.00 1,780.00


Pekerja Oh 0.15 42,000.00 6,300.00
Mandor Oh 0.0025 80,000.00 200
Jumlah 8,280.00
8,280.00

Dempul Kg 0.08 35,800.00 2,864.00


Minyak cat Kg 0.02 38,400.00 768

Batu apung Kg 0.01 29,600.00 296


Pekerja Oh 0.04 42,000.00 1,680.00
Tukang cat Oh 0.04 65,000.00 2,600.00

Kepala tukang Oh 0.004 75,000.00 300


Mandor Oh 0.0025 80,000.00 200
Jumlah 8,708.00
8,708.00

Plamir Kg 0.15 25,000.00 3,750.00


Cat dasar Kg 0.17 30,000.00 5,100.00

Cat penutup setara sieve 2x Kg 0.17 41,700.00 7,089.00

Pekerja Oh 0.07 42,000.00 2,940.00


Tukang cat Oh 0.075 65,000.00 4,875.00

Kepala tukang Oh 0.0075 75,000.00 562.5


Mandor Oh 0.0025 80,000.00 200
Jumlah 24,516.50
24,517.00
Cat meni Kg 0.2 30,400.00 6,080.00
Plamir Kg 0.15 25,000.00 3,750.00
Cat dasar Kg 0.17 30,000.00 5,100.00

Cat penutup 3x setara sieve Kg 0.35 41,700.00 14,595.00

Pekerja Oh 0.07 42,000.00 2,940.00


Tukang cat Oh 0.105 65,000.00 6,825.00

Kepala tukang Oh 0.004 75,000.00 300


Mandor Oh 0.0025 80,000.00 200
Jumlah 39,790.00
39,790.00

Politur Ltr 0.15 48,000.00 7,200.00


Politur jadi Ltr 0.372 112,700.00 41,924.40
Ampelas Lbr 2 5,000.00 10,000.00
Tukang cat Oh 0.06 65,000.00 3,900.00

Kepala tukang Oh 0.016 75,000.00 1,200.00


Mandor Oh 0.0025 80,000.00 200
Jumlah 64,424.40
64,424.00

Residu atau ter Ltr 0.35 8,100.00 2,835.00


Pekerja Oh 0.1 42,000.00 4,200.00
Mandor Oh 0.006 80,000.00 480
Jumlah 7,515.00
7,515.00

Plamir tembok Kg 0.1 55,000.00 5,500.00


Cat dasar Kg 0.1 20,000.00 2,000.00
Cat penutup 2x setara ICI Kg 0.26 112,000.00 29,120.00
Pekerja Oh 0.02 110,000.00 2200
Tukang cat Oh 0.063 130,000.00 8,190.00
Kepala tukang Oh 0.0063 150,000.00 945
Mandor Oh 0.0025 170,000.00 425
Jumlah 30,607.50
30,608.00 370 11,324,960.00
198.79 9,939,500.00
Cat dasar Kg 0.12 30,000.00 3,600.00 21,264,460.00

Cat penutup 2 x Kg 0.18 75,000.00 13,500.00

Pekerja Oh 0.028 42,000.00 1,176.00


Tukang cat Oh 0.042 65,000.00 2,730.00

Kepala tukang Oh 0.0042 75,000.00 315


Mandor Oh 0.0025 80,000.00 200
Jumlah 21,521.00
21,521.00

Cat tembok setara ICI Kg 0.2 75,000.00 15,000.00

Plamir tembok Kg 0.16 25,000.00 4,000.00


Rol cat Bh 0.01 32,500.00 325
Steger werk Ls 1 1,000.00 1,000.00
Ampelas Lbr 0.5 5,000.00 2,500.00
Pekerja Oh 0.2 42,000.00 8,400.00
Tukang cat Oh 0.3 65,000.00 19,500.00

Kepala tukang Oh 0.03 75,000.00 2,250.00


Mandor Oh 0.01 80,000.00 800
Jumlah 53,775.00
53,775.00

Cat tembok setara Vinilex Kg 0.2 25,000.00 5,000.00

Plamir tembok Kg 0.16 25,000.00 4,000.00


Rol cat Bh 0.01 32,500.00 325
Steger werk Ls 1 1,000.00 1,000.00
Ampelas Lbr 0.5 5,000.00 2,500.00
Pekerja Oh 0.2 42,000.00 8,400.00
Tukang cat Oh 0.3 65,000.00 19,500.00

Kepala tukang Oh 0.03 75,000.00 2,250.00


Mandor Oh 0.01 80,000.00 800
Jumlah 43,775.00
43,775.00

Cat tembok setara Vinilex Kg 0.13 25,000.00 3,250.00

Plamir tembok Kg 0.11 25,000.00 2,750.00


Rol cat Bh 0.1 32,500.00 3,250.00
Steger werk Ls 0.67 1,000.00 670
Ampelas Lbr 0.33 5,000.00 1,650.00
Pekerja Oh 0.13 42,000.00 5,460.00
Tukang cat Oh 0.2 65,000.00 13,000.00

Kepala tukang Oh 0.02 75,000.00 1,500.00


Mandor Oh 0.01 80,000.00 800
Jumlah 32,330.00
32,330.00

Wallpaper m2 1.2 55,700.00 66,840.00

Lem Perekat Kg 0.25 35,700.00 8,925.00


Pekerja Oh 0.35 42,000.00 14,700.00
Tukang cat Oh 0.175 65,000.00 11,375.00

Kepala tukang Oh 0.017 75,000.00 1,275.00


Mandor Oh 0.0017 80,000.00 136
Jumlah 103,251.00
103,251.00

Meni besi Kg 0.1 30,400.00 3,040.00


Kuas 3" Bh 0.01 16,000.00 160
Pekerja Oh 0.02 42,000.00 840
Tukang cat Oh 0.2 65,000.00 13,000.00

Kepala tukang Oh 0.02 75,000.00 1,500.00


Mandor Oh 0.01 80,000.00 800
Jumlah 19,340.00
19,340.00
Perancah

Meni besi Kg 0.1 30,400.00 3,040.00


Kuas 3" Bh 0.01 16,000.00 160

Kayu perancah m3 0.002 2,069,800.00 4,139.60

Pekerja Oh 0.25 42,000.00 10,500.00


Tukang cat Oh 0.225 65,000.00 14,625.00

Kepala tukang Oh 0.0225 75,000.00 1,687.50


Mandor Oh 0.0075 80,000.00 600
Jumlah 34,752.10
34,752.00
ecara manual 1 lps cat 2 um

Cat besi setara ICI Kg 0.3 67,700.00 20,310.00

Pekerja Oh 0.006 42,000.00 252


Tukang cat Oh 0.06 65,000.00 3,900.00

Kepala tukang Oh 0.012 75,000.00 900


Mandor Oh 0.006 80,000.00 480
Jumlah 25,842.00
25,842.00
n)

Plamir tembok Kg 0.1 25,000.00 2,500.00

Cat dasar Kg 0.1 30,000.00 3,000.00


Cat penutup 2x setara
Kg 0.26 25,000.00 6,500.00
vinilex

Pekerja Oh 0.02 42,000.00 840


Tukang cat Oh 0.063 65,000.00 4,095.00

Kepala tukang Oh 0.0063 75,000.00 472.5


Mandor Oh 0.0025 80,000.00 200
Jumlah 17,607.50
17,608.00
n)

Plamir tembok Kg 0.1 25,000.00 2,500.00

Cat dasar Kg 0.1 30,000.00 3,000.00

Cat penutup 3x setara


Kg 0.39 25,000.00 9,750.00
vinilex

Pekerja Oh 0.03 42,000.00 1,260.00


Tukang cat Oh 0.0945 65,000.00 6,142.50

Kepala tukang Oh 0.0095 75,000.00 712.5


Mandor Oh 0.0038 80,000.00 304
Jumlah 23,669.00
23,669.00

Cat dasar Kg 0.12 30,000.00 3,600.00

Cat penutup 2 x Kg 0.18 25,000.00 4,500.00

Pekerja Oh 0.028 42,000.00 1,176.00


Tukang cat Oh 0.042 65,000.00 2,730.00

Kepala tukang Oh 0.0042 75,000.00 315


Mandor Oh 0.0025 80,000.00 200
Jumlah 12,521.00
12,521.00
370 56850 21,034,500.00 42,298,960.00

105 122805 12,894,525.00


55,193,485.00