Lowering the bill


FOR PLATFORM
INSTALLATION
The world depends for much of its energy supply on oil and gas extracted from
beneath the seabed. New technology from Trelleborg for installing production
platforms offshore provides a welcome reduction in costs.
TEXT: NICK TERDRE PHOTO & ILLUSTRATION: TRELLEBORG

t
relleborg’s products – onto the support structure or jacket transferring the load from the barge
leg mating units (lmus), by a floating crane. But the hire rates to the jacket. This must be done in a
deck support units, sway for such cranes are high, sometimes controlled manner without causing
and surge fenders – make a running into several hundred thou- damage to either structure, even
valuable contribution to the sand dollars a day. The float-over though waves, currents or winds are
float-over method of installing the process provides a much less costly causing the barge to move.
topsides of offshore oil and gas plat- solution. But the crucial challenge, “The lmus – steel structures
forms from a barge. according to J.P. Chia, Engineering incorporating rubber elements –
Traditionally the topsides are lifted Manager at Trelleborg Singapore, is make this possible by dampening the

6 T·TIME 3·2010

10TTI3_lmu_3014.indd 6 2010-11-10 09:33:20


Using LMUs during a float-over process, the loads can be
transferred from the barge to the base structure in a controlled
manner. LMUs consist of a steel structure incorporating rubber
elements to achieve a specified spring rate, depending on
the expected loads and movements.

Qatar. The company performed full


custom design, engineering, fabrica-
tion and testing. Each of the lmus
for the 13,000-ton bg topsides
weighed 24 tons, was 2 meters in
diameter and stood 3.7 meters high.

Trelleborg worked with technical


service provider gl Noble Denton.
“In this project, Trelleborg
supplied 12 lmus, which showed
good performance and reliability
during the topside float-over installa-
tion,” says gl Noble Denton Project
Engineering Manager Andy Wang.
forces created as the topside’s load is “This should be attributed to the
transferred to the jacket,” Chia sound engineering work and
explains. “Using data provided by comprehensive manufacturing and
the client, the rubber elements are testing procedures of Trelleborg,
engineered to have the correct spring which we have observed both during
stiffness for this task.” this project and in our visits to the
Trelleborg yard.”
The LMUs are placed inside steel One of the key benefits of the
cans known as transition pieces, float-over solution is that nearly all HOW IT WORKS
which are installed on top of the the work on the topsides can be done In float-over operations, the topsides of a production plat-
jacket legs. in the fabrication yard, where labor form, which may vary in size from less than 1,000 tons to
Meanwhile, surge and sway costs are much lower. more than 40,000 tons, are installed from a barge. The
fenders absorb the impact of the A floating crane would have had barge is towed to the field and positioned between the legs
barge on the jacket as it moves to make several lifts to install the bg of the supporting structure or jacket.
The barge is then ballasted down until the topsides make
forward or sideways during the topsides, after which extra work
contact with the jacket legs. When their entire weight has
mating operation. would have been required to hook up been transferred to the jacket, the barge is towed away.
Once the topsides have been safely and commission the various For further information:
transferred onto the jacket, the two modules. julian.wee @trelleborg.com
structures are welded together. “Following last year’s successful
Deck support units, or dsus, come projects, Trelleborg Singapore has
into play in the fabrication yard. received several invitations to tender
EASY SKIDDING
In addition to LMUs, DSUs and fenders, Trelleborg also
The topsides are transferred onto for further float-over operations,”
supplies Orkot® bearings to ease the skidding process of
the barge on a deck support frame. Chia says. the topside onto the transport barge.
dsus positioned on the deck support Chia explains that all the float- Runners beneath the deck frame fit into grooves along
frame absorb the weight of the over products have to be fully tested which the topside is pushed using very strong strand jacks.
topsides as they are placed on the before use. The load deformation The Orkot bearings are placed in the grooves. With their
frame. behavior of the lmu pads has to be high load capacity and low friction coefficient, they reduce
Trelleborg Singapore participated verified, for example. the force that has to be applied to move the topsides, which
may weigh tens of thousands of tons.
in two float-over projects last year, “We have invested in a high-
For further information:
including the installation of the capacity test press to meet the peter.bakker@trelleborg.com
be and bg topsides for Maersk Oil increased demand,” says Chia.

T·TIME 3·2010 7

10TTI3_lmu_3014.indd 7 2010-11-10 09:33:22