Vous êtes sur la page 1sur 12

SPE 87240

Technical Challenges Encountered During Coiled Tubing Underbalanced


Drilling In Oman
T Hoekstra, CEng; Chris Hopkins CEng, CPhys; Petroleum Development of Oman,
A Fleck, SPE; G Bell, CEng.; Baker Hughes INTEQ.

Copyright 2000, Society of Petroleum Engineers, Inc.


th
This paper was selected for presentation at the 9 Abu Dhabi International Petroleum
placement around a 2 7/8” liner run on coiled tubing.
Exhibition and Conference held in Abu Dhabi, U.A.E., 15-18 October 2000. • World Record for longest horizontal section drilled
This paper was selected for presentation by the ADIPEC Program Committee following with a coiled tubing (beaten twice - now at 1457m).
review of the information contained in an abstract submitted by the author(s). Contents of
the paper as presented have not been reviewed by the ADIPEC and are subject to • Underbalanced drilling technology applied safely and
correction by author(s). The material as presented does not necessarily reflect any
position of the ADIPEC or its members. Permission to copy is restricted to an abstract of successfully.
not more than 300 words. Illustrations may not be copied. The abstract should contain
conspicuous acknowledgement of where and by whom the paper was presented. Write
to ADIPEC Coordinator, GEC, P.O. Box 5546, Abu Dhabi, UAE. Fax 009712-4446135. Introduction
Petroleum Development Oman (PDO) operates over 90
fields in Oman. Total production is around 835,000
Abstract bbls/day, of which approximately 25% is produced from
This paper describes two of the major technical the Yibal field. This field lies in the northeastern part of
achievements during the first year of operation of a new, Oman. It is a water-driven carbonate reservoir. Reservoir
purpose built, underbalanced (UB) coiled tubing drilling pressure is supported by water injection and oil flows to
unit (CTDU). surface with the aid of gas lift.
The unit is designed to drill sidetracks and extensions Discovered in the early sixties, Yibal has a surface
to existing wells to improve reservoir drainage. The infrastructure of over 440 wells that branch out into a
package is fully self-contained, and uses native crude as multitude of well conduits subsurface. It is recognised in
the primary drilling fluid. Natural gas injection through Yibal that the number of existing vertical wells available
conventional gas lift mandrels is used to maintain for side-tracking will decline. In addition, the reservoir
underbalanced conditions. The unit was built during 1998 model shows that further development using conventional
and mobilised from the USA to Oman. Following final side-track technology will leave considerable volumes of
construction work and commissioning, it drilled its first unswept oil in small isolated pockets. The current phase in
well during February 1999. the Yibal field development is to utilise existing well bores
This paper focuses mainly on two technical areas. to target these small oil reserves, both by conventional
Firstly, the world-record-breaking extended reach wells, sidetracks and by sidetracks from previous side-tracks
including the challenges faced to achieve them. Secondly, using ultra-slim-hole (USH) technology.
the continuing project to minimise high water cut during
initial production following workover. Details of Unit Specifications. The drilling unit is a highly mobile
operations are included, with an overview of drilling hybrid coiled tubing drilling rig (Figure 1). It has the
performance for the wells drilled in the first year of capacity to pull completions, drill side-tracks and
operation. extensions using coiled tubing and run new completion
After 6 months of operation it was concluded that the tubulars. The package is mobilised on five heavy desert
production from slim hole wells drilled by the CTDU and trailers for Rig, CTD reel, Power Plant, Mud Pumps and
conventional rigs was not as expected (high water cut). Underbalanced Drilling Fluids Processing Unit. Additional
During this period a major review of the slim hole trailers carry CT work reels, maintenance workshops,
campaign took place, concentrating on cement placement office and living accommodation and storage tanks.
around the 2-7/8” liner and stimulation of the reservoir The drill floor incorporates a support frame for a
after perforating. This resulted in a major improvement of 100,000 lbs capacity CT injector. The main pipe storage
production and ultimately the continuation of the slim hole reel is a specialised 2-3/8” drum designed for use with an
project. unsupported CT loop instead of a conventional guide arch.
The operator has drilled 21 wells to date with the 4
The reel has capacity for 5000m of 2-3/8” e-line CT. Two
CTDU and 9 more wells are planned for the year 2000. further work reels for standard (no e-line) 2-3/8” and 1-¾”
Technical contributions include: CT are also provided.
• Improved procedures and techniques for cement For underbalanced drilling with crude oil, the process
2 TECHNICAL CHALLENGES ENCOUNTERED DURING COILED TUBING UNDERBALANCED DRILLING IN OMAN SPE 87240

package consists of settling/storage tanks, transfer pumps configuration (4 producers surrounding 1 injector). This
and high pressure pumps (Figure 2). On the return side, was later extended to include 4 additional producers (‘9-
the flow is first fed through de-sanding hydro-cyclones spot’ configuration). Subsequent infill drilling increased
before passing through a choke to a 3-phase separator. Gas the drainage around the injection wells and added injectors
from the separator is fed to a remote flare. Water is to selected areas. The current, 4th phase involves drilling
collected and fed to a holding tank for discharge to the horizontal sidetracks from existing wells. Conventional
production flow-line. Oil is transferred to the crude settling sidetracks involve drilling 8 ½” hole from the 9-5/8”
tank for processing and then returned to the HP pumps. casing, exiting in the shales overlying the pay zone.
Export pumps are provided to allow for transfer of excess With the build-up section lined, a 6-1/8” horizontal
produced oil to the production flow-line. section was drilled and lined with 4 ½” production liner.
The complete unit is operated from a central control This was later extended to include ultra slim holes (USH)
cabin mounted at the rig floor. This cabin is a pressurised exiting from existing horizontal 4 ½” liners. A typical well
unit, housing the main control computers and interfaces to schematic is shown in Figure 4. The majority of the USH
systems in hazardous areas. Control of the injector, reel sidetracks have been drilled with coiled tubing. Typically,
and mud pumps is via a control network with rotary ultra slim hole wells had been limited to a reach of
programmable logic controllers. Joystick and touch screen 850m.
man-machine interfaces are used with advanced graphical
process displays. Project Planning. The well density complicates further
development drilling. Using a directional drilling database
Drilling Bottom Hole Assembly. To compliment the covering over 440 wells, and a well-planning software
features of the surface equipment, an integrated, modular package, the initial well proposal is prepared. Sometimes,
CT drilling and evaluation bottom hole assembly (BHA) the identified targets could not be accessed from near-by
was selected. (Figure 3). This 3-1/8” assembly has a bi- wells due to current production requirements or problems
directional communication link using wireline telemetry. with candidate well completions or casing. Thus it was
The BHA consists of 9 main sections – CT connector, necessary to tap these reserves from remote wells. This
upper quick connector with casing collar locator, double increased the required reach to beyond the typical USH
ball valve deployment sub, resistivity tool, lower quick side-track length of approximately 1000m. To test the
connector, steering system, orienter, release tool and maximum extension achievable with the CTDU, a long
adjustable bent housing motor. The integrated sensor sidetrack was planned. Given the fact that the existing
package includes multiple propagation resistivity (MPR) (4 world record horizontal reach on coiled tubing was
compensated measurements for deep investigation), approximately 1000 meters, it was evident that thorough
gamma ray, annular pressure, internal tool pressure, up-front engineering was required to maximise the chances
weight on bit and temperature. of success. The following technical issues were looked at:
To control the well bore trajectory, the orienting tool is • Sliding friction is the main limiting factor for
used to turn the bent housing motor. Inclination, azimuth transferring weight to the bit in extended reach coil
and tool face setting data are transmitted to the graphical operations. It is of the utmost importance to optimise
displays in the control cabin. The Directional Driller can the well trajectory accordingly. Dogleg severities (DLS)
adjust the tool face while drilling via a computer interface. of less than 10 deg/30m are planned. The situation is
complicated by the existence of nearby wells and
Well Programme Outline. The unit was moved to the first collision risk analysis is essential. Often, as many as 5
well in February 1999 for final acceptance testing. The wells are identified as collision risks. Collision risks
first operational run into the well was completed on 25th with a separation factor of 2.0 or less are identified and
February 1999. detailed reports prepared identifying the predicted
The generic scope of work for the unit is based on 4 ½” location of minimum separation. Figure 5 shows a
through-tubing re-entries (Figure 4). A window is milled horizontal section for a typical sidetrack.
in the horizontal section of the 4 ½” liner at a TVD of • Drilling lubricants were used to reduce friction along
approximately 1400m. A 3 ¾” hole is drilled the well bore. Tests on previous wells showed that
underbalanced horizontally through the pay zone and a 2- down hole friction factors could be reduced by
7/8” liner is run and cemented. To access the target zones, approximately 0.04.
1-9/16” perforating guns are used and the perforations are • Simulations were carried out to model the forces
then acidised. involved in the drilling, liner running and liner clean
Prior to the unit moving onto location and entering the out phases of the programme.
well, a well pulling hoist establishes the integrity of the • The simulations showed, assuming that lower friction
completion and annuli. factors would be achieved, sidetracks of 1500m
horizontal length would just be achievable. The
Extended Reach Drilling limiting factor was usually cleaning out the liner with
Drilling in the Yibal field has developed in 4 distinct the 1 ¾” CT rather than the drilling operation.
phases. First, wells were drilled vertically in a ‘5-spot’ Addition of drill collars would be required in the (CT)
SPE 87240 HOEKSTRA, HOPKINS, FLECK, BELL 3

liner running string to provide sufficient weight to get predicted surface weights in the region of 5,000 to 6,000
the liner to bottom. daN. At the end of the well, however, weight transfer to
the bit was extremely difficult, and the surface weight fell
Well 12. Well 12 was drilled in 1986 and developed with a below zero (snubbing). It was frequently necessary to pick
horizontal sidetrack in 1997. An USH sidetrack was up off bottom and ‘spud’ the assembly.
proposed to drain oil from an area identified by the Considerable changes were required in the gas injection
reservoir model as having significant quantities of rates (with a resulting change in wellhead pressure (WHP))
undeveloped oil. The sidetrack was planned to have a and the amount of lubricating fluid added to the drilling
horizontal length of 1200m, with the 4 ½” casing exit fluid. Gas injection rates varied from 9,000 m3/day to
planned for 1600mAHD and a TD of 2800mAHD. 22,000 m3/day and WHP fluctuated from as low as 500
kPa to as high as 1,600 kPa. It is interesting to note that
Well 12 – Drilling phase time breakdown. the dynamic bottom hole pressure (BHP) stayed
Operation Time (hrs) remarkably constant and unusually high, in the 15,800 to
Make up and RIH directional assy. 3.50 16,000 kPa range.
RIH The addition of lubricant to the fluid being pumped
Drill 1640 to 2609m. Commence 151.5 into the well improved drilling rates, but no direct
with water and gas lift, change to relationship can be drawn between the amounts and
crude oil with gas lift. concentration of lubricant used and penetration rates. It
POOH – add thruster 10.00 was, under the underbalanced conditions, impossible to
Drill 2609 to 2621m 8.75 predict just where in the well bore the lubricant was
POOH – remove thruster 8.75 actually being placed. Two types of lubricants were tried,
Drill 2621 to 2808m, change over to 78.00 one which was water-soluble and another which was not
overbalanced mode. Drill with water water-soluble. Due to unavailability of the water-soluble
and add lubricants. kind, the non-soluble friction reduction agent was
Drill 2808 to 2873m (TD) 9.00 dispersed into the water based mud. This unfortunately
POOH and lay down tools. 3.00 gave several surface problems in the tank system due to the
formation of emulsions.
TOTAL TIME 272.5hrs,
The final well TD was called at 2873 mAHD, a world
11.35days
record for CTD of 1233m horizontal section achieved
(Figure 6).
Drilling phase. Drilling this section took over 6 days
Completion operations. Running the liner was
longer than planned. Drilling progress was significantly
simulated with the modelling software to calculate the
slower than on previous wells with typical ROPs in the
required number and position of drill collars. Similarly, the
range 2 to 10 m/hr as opposed to 40 to 50 m/hr
model was used to check that the 1 ¾” CT could clean out
experienced on previous wells. The UB drilling system is
the liner without exceeding load and stress limits.
designed to re-circulate produced crude oil with an initial
A 1300m 2-7/8” liner was run into the drilled sidetrack
‘charge’ brought in by road tanker. During initial stages of
with 36 joints of 3 ½” PAC drill pipe and 37 joints of 3
this sidetrack, significant water production was
1/8” drill collars added to the running string. The liner was
encountered. This required import of further supplies of
run to depth without any significant hold-up and without
crude by road, and in the meantime drilling was continued
the addition of any lubricant.
with dehydration water (DHW), which contributed to a
Due to problems encountered during the cementing
lack of lubricity in the well bore. Also, in drilling close to
operations, the well was not perforated. A cement bond log
the interface between the production reservoir and the
showed poor zonal isolation over the target sections, and it
overlying shales, great care must be taken to identify the
was decided to suspended the well to await remedial
signs of shale penetration. These are usually reduced ROP,
intervention and perforation / acidisation. No subsequent
GR response and overpulls on picking up off bottom. With
production results are available for this well.
slow progress, the concern was that the well bore was
closer to the shales than planned.
On several occasions, significant overpulls were Well 16. Well 16 was drilled as a vertical well in 1981 and
experienced; indicating potential reservoir exits, although subsequently sidetracked in 1995. Again, an USH sidetrack
only one stuck pipe incident was recorded. The drilling was proposed to drain oil from a position where the
parameters used throughout drilling the well remained reservoir model identified significant undeveloped oil. The
fairly consistent: weight on bit ranged from 1.2 kdaN to as sidetrack was proposed with the 4 ½” casing exit at
low as 0.2 kdaN towards the end of the well; pump rates approximately 1550mAHD and a target depth of
were 350-400 l/min with internal string pressures in the 2914mAHD, giving a total drilled length of over 1360
25,000 to 30,000 kPa range. Tubing pick-up weights mAHD
remained fairly predictable, increasing from 7,650 daN to Drilling phase. The well was initially drilled with
11,000 daN at the end of the well bore. Slack-off weights crude oil and gas lift at approximately 30,000 m3/day.
also closely followed the load/stress model, which With restricted crude supplies and no produced oil early in
4 TECHNICAL CHALLENGES ENCOUNTERED DURING COILED TUBING UNDERBALANCED DRILLING IN OMAN SPE 87240

the sidetrack, subsequent stages of the well were drilled independently of the various differing gas injection rates
using produced formation water. Where drilling was applied, which would once again imply that the well never
difficult, drilling lubricants were added to the drill water; achieved a stable multi-phase flow condition for any length
crude oil was pumped when available. of time. Drilling operations were alternated between
After 735m drilling, the overlying shale was underbalanced and overbalanced modes: no clear
penetrated. As well as the indications previously relationship could be established between the rates of
mentioned, some signs of shale were noted in the produced penetration achievable and the particular mode chosen.
cuttings. It was decided to abandon this section of the well The highest ROPs were recorded in underbalanced mode,
and an abandonment packer was run. The inflatable packer but so were the lowest.
became stuck in the well bore, however, and during In the last 300m of the well, significant quantities of
attempts to release it, the coiled tubing parted at +/- 100m lubricant were added in 2-3% concentrations, and an
below the injector. This was subsequently shown to be due underbalanced mode was maintained.
to a material defect. As discussed above, planning of these wells generally
The CTDU was switched to conventional pipe requires a detailed study of collision avoidance. It is
operations and the lost pipe and packer running tools interesting to note that during the drilling of both of the
recovered to surface. referenced wells, nearby well management became a
Drilling recommenced with produced water as the common occurrence. It was found that by opening or
drilling fluid. Progress was slow and frequent wiper trips closing adjacent producing wells, and by opening or
were made. Again, signs of shale were noted and the closing nearby injector wells, significant differences could
drilling assembly became stuck in the hole. Crude oil was be made to drilling performance. The process was not a
pumped and the tools worked free. Drilling continued simple one, however, as each well path passed close to or
slowly with intermittent additions of lubricant and crude to crossed a number of wells (both injectors and producers)
the fluid system. Gel sweeps and wiper trips every 50 to and predicting the effects that each well had on the
70m were used to assist in removal of cuttings. The final performance in the well being drilled was extremely
250m of the sidetrack from 2750 to 3001m MD took over difficult. Varying delays were noted between opening and
50 hours to complete. closing nearby wells and the pressure response and flow
characteristics of the current well.
Well 16 – Drilling phase time breakdown. The final well TD was called at 3001 mAHD, a further
Operation Time (hrs) extension of the world record for CTD from 1233m to
Make up and RIH directional assy. 9.00 1457m horizontal section achieved (Figure 7).
Drill 1546 to 1791m 7.75 Completion operations. During installation of the
Lost signal – POOH and c/o tools 6.50 liner, the string became stuck at 46m off bottom, and the
Drill 1791 to 2281m 18.75 decision was made to cement the liner in place. The
Enter shale. Sweep and log hole. 7.75 cementation was carried out without incident with
POOH predicted displacement volumes being attained. The coil
RIH abandonment packer – stuck, 18.25 string was changed out to 1 ¾” and a mud motor was run
attempt to work free. CT parted. in the hole to clean out the liner and to drill the shoetrack
Secure well. to within 14m of the shoe. The well was then perforated in
C/o to drawworks, fish CT on drill 36.00 two runs and selectively acidised.
pipe Subsequent production was above average with very
RIH directional assy. Pump LCM 22.50 encouraging base solids and water content.
pills.
Drill 1545 to 2750m 145.25 Learning Points Extended Reach CTD. On completion
POOH – motor disconnected. 3.50 of the 2 extended reach wells, the following learning points
were noted:
Fish motor. 25.00
• Extended reach USH wells are possible up to 1500
Drill 2751 to 3001m (TD) 52.5
mAHD on coiled tubing under certain conditions;
Pipe stuck, work free, backream, 12.5
• Drilling lubricants are effective but water soluble
monitor well, POOH to surface.
products are preferable due to the adverse effect on
TOTAL TIME 365.25 hrs, 15
surface systems of non-water-soluble products;
days
• The use of simulation software, once calibrated, is
critical to the success of extended reach CTD
The drilling parameters on this well also remained
operations;
fairly consistent. WOBs were if anything marginally
• The critical operation with respect to weight transfer is
higher (1 to 3 kdaN) than the previously referenced well,
cleaning out of the liner after cementation rather than
which would indicate greater success in transferring
drilling the hole;
weight downhole to the bit. This can be attributed to the
simpler well bore geometry (Figures 6 and 7). In • Underbalanced drilling does not always give the best
underbalanced mode, wellhead pressure fluctuated reach. The simulation software was not able to model
SPE 87240 HOEKSTRA, HOPKINS, FLECK, BELL 5

this correctly; diesel/oil/bentonite (DOB, also known as Gunk).


• Proper management of nearby production and injection Additionally, PDO formulated a thixotropic low
wells is essential for achieving extended reach in compressive strength cement to tackle medium losses. The
producing fields; primary objective for these materials was to isolate loss
• Operational time is reducing as experience is gained, zones, but it was also a requirement that the materials be
Figure 8. suitable for placement through the CTD string and BHA
(2-3/8” CT with e-line).
Minimising Initial Water Production Results to date have been varied and further work and
About half way through the 21-well campaign, production trials are ongoing to achieve a better understanding of the
analysis showed that the USH well net oil production rates behaviour of these products in low and medium loss zones.
were below expectation with high water cuts. A study team Displacement through the CTD string and tools was tested
was formed with the task of identifying possible reasons for and no particular problems encountered. To reduce the loss
the poor performance and implementation of remedial rate to a manageable level (~10m3/h), the procedure
actions. currently adopted is to use magnesium cement or
The Yibal field is highly fractured and faulted. thixotropic cement when the loss rate is between 10 and
Conventional drilling experience is that lost circulation up 20m3/h. Above 20m3/hr loss rate, DOB, which is not
to 40m3/hr is a major problem. However, with permanent, is used and subsequently sealed in with
Underbalanced Drilling, lost circulation zones are not magnesium or thixotropic cement.
easily identified during drilling operations. The production
liners were run in overbalanced mode, assuming any loss Improved Cementing Techniques. The absence of cement
problems were tackled after drilling and before running the was found to be due mainly to untreated loss zones and
liner. over displacement during the cement job. The mechanics
It was concluded that the disappointing production of the cement jobs were investigated and several
results from the ultra slim wells were mainly due either to recommendations were put in place to ensure that cement
lack of zonal isolation behind the 2-7/8” liner or to non- placement was executed as intended. The prime
selective stimulation of the perforations (over stimulation recommendations were:
of the lowest pressure zone). In order to evaluate all • In the past, the displacement philosophy was ‘pump to
parameters involved in the well’s completion process, a bump’ if a liner wiper plug shear was observed.
matrix was drawn up showing all liner running, However, it became clear that the dart can be by-passed
cementing, perforation, acidisation and initial production by displacement fluid hence the cement displacement
results. This matrix immediately illustrated that liners volume should never exceed the volume of the running
cemented with tubulars in the running string had worse string used (e.g., 2-3/8” work coil and/or drillpipe/drill
cement displacements than the wells where the liner was collar combination) plus the volume of the liner and
run on CT only. This problem was investigated and pump shoe track;
tests with various cement displacement darts were • Cementing is attempted only if the loss-rate can be
executed, ultimately resulting in the presently-used 4-fin reduced to less than 10m3/h. Experience has shown that
dart design (Figure 9). when losses are less than this a reasonable cement job
can be achieved;
Curing Lost Circulation. Lost circulation creates a • Over-displacement was reduced by accurately checking
situation where zonal isolation by cementation is very the volume of all the sections of the cementing string
difficult and the well cannot be subsequently stimulated (CT, drill collars, liner) and the introduction of a new,
effectively. The current conventional methodology is to specially designed 4 fin wiper dart. Improvements were
drill overbalanced to identify the loss zones accurately. made to the detail of the pumping procedure, including
Attempts are then made to cure losses before drilling the addition of a high viscosity spacer behind the 4-fin
ahead. In underbalanced drilling, there is no effective way dart;
to identify any loss zone. Attempts were made to identify • Additional losses were attributed to the high ECD
loss zones using pressure logs (an integral part of the created when cementing ultra-slim holes. To reduce the
BHA’s standard capabilities), but the results were not fully equivalent circulating density (ECD), a 3 ½” x 4 1/8”
conclusive. bi-centre bit and a reaming while drilling (RWD) bit
Following loss treatment and liner cementation, cement were used to drill a larger hole. The hole gauge was
bond logs were initiated to assess the effectiveness of the measured at slightly over 4 inches on 2 wells with
cement placement. It was found that significant areas of calliper logging tools. Figure 10 shows the results from
the liners were being left with little or no cement. This was a multi-finger calliper tool which measured the hole at
the case even with 300% excess cement volumes. It was slightly over 4 inches diameter;
concluded that two areas had to be studied to improve • The calculations suggested that fracturing was
zonal isolation – loss treatment and cement placement. occurring during cementation at rates in excess of 250
A number of LCM trials were conducted with l/min and pumping rates were limited to this value.
magnesium cement, cross-linking polymer gels and This results in plug flow rather than turbulent flow.
6 TECHNICAL CHALLENGES ENCOUNTERED DURING COILED TUBING UNDERBALANCED DRILLING IN OMAN SPE 87240

Plug flow did not appear to have an adverse effect on implementation of all recommendations) with wells 13 to
the cement bond; 21.
• The volume per joint of 2-7/8” liner is very small;
therefore, in order to create a safety margin against Results and Conclusions
over displacement, the shoe track was increased from 2 • Underbalanced, ultra slim wells have been drilled on
to 10 joints; coiled tubing up to a world-record horizontal length of
• A cement bond log is now run as standard to check the 1457 m. This is a great technical achievement which
cement placement and optimise the position of pushes the technological boundaries associated with
perforations. CTD back significantly.
• If extended reach is required, thorough planning
Improved Stimulation Techniques. Non-selective (engineering and modelling) is essential. This
stimulation had been shown to allow early water feasibility study should include not only the drilling
breakthrough as the most permeable zone is over phase but also the liner running and clean-out
stimulated. This allows the acid to interconnect the operations.
fractures and create very high permeability. Even if these • Drilling progress decreased - as expected -
fractures are not connected to a water-bearing zone, this dramatically towards the end of the well in extended
high permeability in the oil bearing zones could potentially reach operations. A clear economical justification
allow early water breakthrough as the oil will drain therefore is required for each incremental 100m length
rapidly. As the other zones have not been stimulated, the being planned for future wells. Figure 13 shows the
well will predominantly produce from the stimulated time verses depth curve for Well 16.
fractures. Previous problems with selective stimulation • CTD ultra-slim wells are targeted typically at relatively
tools in slim wells resulted in a move to ‘poor boy’ small pockets of residual oil and the success of the well
acidisation – bull heading the treatment from surface. It depends heavily on the accuracy of the reservoir model
was concluded that: and geological knowledge of the target zone.
• Stimulation should be carried out selectively. This was • The study to minimise water production has been
achieved initially with a wash cup tool, but it was later effective. Relative well performance is illustrated in
replaced with an inflatable straddle tool due to poor Figure 11. The results of both the cementing and the
reliability. (Tools failed to hold test pressure and stimulation sub-studies have been positive, considering
become stuck in hole. The rubber packer elements the changes were being progressively implemented
disintegrated downhole, possibly due to debris); from Well 13 to Well 21.
• A philosophy of acidising from top to bottom was • Over 18,000 meters of new hole were drilled on coiled
initiated due to concerns about the durability of the tubing in the first 21 wells.
bottom wash cups and straddle packers; • The full benefits of underbalanced drilling have been
• A better understanding of the stimulation technique found to be less clear cut as was thought. Definite
was required. Acid concentrations, volume, squeeze benefits are gained with the technique when the coil is
pressure, displacement volume and placement stuck - especially differentially stuck. There are
techniques were clarified. A thorough review of current benefits in rate of penetration improvement, but this is
stimulation procedures was conducted and revised often overshadowed by the time spent curing losses
guidelines were produced; before running the liner. It has also been found that lost
• Perforating intervals are now chosen to be no closer circulation material is often removed during
than 30 meters from fractures, faults or water features; underbalanced operations, negating any benefit gained.
• Drilling Supervisors received specialist training to In some parts of the Yibal field small increases in ROP
execute stimulation jobs. A Petroleum Technologist are observed underbalanced while in others the opposite
was assigned to the rig to supervise stimulation jobs is true. To fully realise the benefits of the
when new Drilling Supervisors were on site. underbalanced system, the wells should be lined and
The above findings will not guarantee the prevention of cemented without treating the loss zones.
early water breakthrough. Even with selective stimulation,
the fractures within the perforated interval may still be Acknowledgements
over stimulated which can lead to early water The authors are grateful to the Ministry of Oil and Gas of
breakthrough. However, using selective stimulation will Oman, Petroleum Development Oman and Baker Hughes
enhance the chance of maximising production from the INTEQ for supporting the publication of this paper. The
ultra slim wells. The importance of correct stimulation was authors also thank all other staff (operator and service
highlighted when production tests were performed on an companies) involved in the Coiled Tubing Project to date
open hole well (Well No 14), after perforating and then whose hard work and dedication have ensured a safe and
after stimulation. In the first case, 99% BS&W was successful operation.
observed, and the gross increased 20% between the last
two tests. The improvement in initial production can be References
seen in Figures 11 and 12, comparing wells 1 to 12 (before 1. Schoenmakers, J.M.: “Introduction of Game-changing
SPE 87240 HOEKSTRA, HOPKINS, FLECK, BELL 7

Drilling Technology,” paper SPE/IADC 37635 4. Saville, P et al.: "Well Engineering Aspects of a 2
presented at the 1997 SPE/IADC Drilling Conference, 7/8in Ultraslim Lined Well Campaign", paper SPE
Amsterdam, Netherlands, (March 1997). 52849 prepared for the 1999 SPE/IADC Drilling
2. Surewaard, J, et al.: “One Year Experience With Conference, Amsterdam, The Netherlands, (March
Coiled Tubing Drilling,” paper SPE/IADC 39260 1999).
presented at the 1997 SPE/IADC Middle East Drilling 5. Van Venrooy, J. et al. : “Underbalanced Drilling with
Technology Conference, Bahrain, (November 1997). Coiled Tubing in Oman”, paper SPE 57571 prepared
3. Johnston, C.A. et al: “Coiled Tubing Parabolic Loop for the 1999 SPE/IADC Middle East Drilling
System - A New Approach to Tubing Handling”, Technology Conference, Abu Dhabi, UAE, (Nov
paper SPE 50584 presented at the 1998 SPE European 1999).
Petroleum Conference, The Hague, The Netherlands,
(October 1998).
8 TECHNICAL CHALLENGES ENCOUNTERED DURING COILED TUBING UNDERBALANCED DRILLING IN OMAN SPE 87240

Figure 1 Hybrid Coiled Tubing Drilling Rig with


parabolic loop system.

Figure 2 Underbalanced drilling fluids handling


package – from left, oil storage tanks and
centrifuge, 3-phase separator, hydro-cyclone solids
separators.

Figure 3 CTD BHA.


SPE 87240 HOEKSTRA, HOPKINS, FLECK, BELL 9

Figure 4 – General well schematic of USH sidetrack.

Figure 5 – Sample well plan and deviation


10 TECHNICAL CHALLENGES ENCOUNTERED DURING COILED TUBING UNDERBALANCED DRILLING IN OMAN SPE 87240

-100m -100m

1100m 1200m
N
or
th
(m
) 1500m
1500m East (m
)
13
70 00
0m m
-100m -10 -100m -1
0m 00
m

Figure 7 Well No 16 - KOP 1544m, TD


Figure 6 Well No 12 - KOP 1640m, TD 2873m, 3001m, 1457m sidetrack
1233m sidetrack.

50.00

DAYS
45.00
TOTAL W ELL TIM E

40.00

35.00

30.00

25.00

20.00

15.00

10.00

5.00

0.00
1 2 3 4 5 6 7 8 9 11 12 13 14 15 16 18 19 20 21

Figure 8 - Operational time for Ultra Slim Hole wells - note wells 10 and 17 excluded (workover not
completed)
SPE 87240 HOEKSTRA, HOPKINS, FLECK, BELL 11

Figure 9 – 4-fin dart used in current USH cementations

Figure 10 – Calliper log of hole drilled with


‘Reaming While Drilling’ bit.

Initial P r o d u c t i o n
( C T U l t r a S l i m H o l e)
11

12

13

14

15

16

18

19

20

21
1

Figure 11 Relative production of Ultra Slim Hole wells averaged over first month. Wells 1 to 11 – before
cementing and stimulation improvements and wells 13 to 21 after. (Data for wells 20 and 21 is initial
production, not average for first month)
12 TECHNICAL CHALLENGES ENCOUNTERED DURING COILED TUBING UNDERBALANCED DRILLING IN OMAN SPE 87240

Average Production Preformance

S lim - D o w n a v e Conventional ave U ltra Slim H o l e a v e

Figure 12 - initial production for Ultra Slim Hole wells compared to average initial production for
Conventional and Slimed Down wells

T im e v s D e p t h C u r v e W e ll 1 6
9

5
Days

0
1500 1700 1900 2100 2300 2500 2700 2900 3100
D e p th (m)

Figure 13 - Time versus depth curve for Well 16.

Vous aimerez peut-être aussi