Guidelines for FIRE NOC

1) Architect Completion Certificate.


2) ‘A’ Form from fire license agency.
3) List of fire fighting appliances installed by the agency.
4) Payments slip of Fire Cess Charges.
5) Work Completion letter from Developer / Builder.
6) Letter of installation of fire fighting appliances from fire
license agency.
7) Provisional fire NOC.
8) Provisional drawing sanctioned from fire department.
9) Fire resistance door installation certificate.
10) Challan of fire pumps (Xerox Copy)
11) Lift inspection certificate.
12) Challan of D.G. sets.
13) Commencement Certificate obtained from Building
Permission Section.
14) Photographs of fire fighting appliances.

Undertaking on 200 Rs. Stamp Paper that provision of Fire safety is


maintained as per approved plan
CIDCO FIRE SERVICE
Details of Fire Fighting System Check List

Name of Society :
……………………………………………………………………………………………………..........

Address :

Types of Building :
…………………………………………………………………………………………………………

Inspection Date :

Total Area :
…………………………………………………………………………………………………………

Name of Main Person : …………………………………………………………………


signature ……………………..

No. Type of installation Available Remark


Quantity
1 Dry /wet Riser
2 Landing Valve
3 Hose Box
4 Hose
5 Branch
6 Hose Reel with shut – up Cock Nozzle
7 Terrace tank
8 Underground Static water storage Tank
9 Courtyard Hydrant
10 Siamese Connection
11 Electric Main pump
12 Booster Pump
13 Stand by Electric Pump
14 Jockey Pump
15 Diesel Pump
16 D.G. Set
17 Automatic Fire Alarm System
18 Auto Sprinkler System
19 Fire Door
20 Fire Lift
21 Refuge Area
22 Control Room
23 Entrance & Exit Gate
24 Staircase
25 Electric Duct
26 Fire Duct
Portable Fire Equipments
I) D.C.P Type Fire Extinguisher
II) CO2 Type Fire Extinguisher
III) A.B.C. Type Fire Extinguisher
Iv) Fire Brand type Fire Bucket

NOTE:

Fire Service Fee Structure for Special Planning Authorities

Sr. Type of Building Occupancy Special Planning Authorities


No.
Fees in Subject to Minimum
Rs. Per of
Sq. Mt. Rs.

(1) (2) (1)


(2)
RESIDENTIAL BUILDING (A)
(a) Lodging & rooming House (A-1)
Less Than 15 m in Height
(i) Up to 15 Rooms 5.00 30,000.00
(ii) More than 15 and up to 30 7.00 35,000.00
Rooms
(iii) More than 30 Rooms 10.00 50,000.00
(b) Apartment House (A-4)
1 From 15 m to 24 m in Height 5.00 30,000.00
2 24 m and above but not 7.00 40,000.00
exceeding 35 m in height
3 Above 35 m but not exceeding 10.00 60,000.00
45 m in height
4 Above 45 m in height 15.00 1,00,000.00
(C) Hotel (A- 5)
1 Less than 15 m in height

(i) Covered area not exceeding 5.00 30,000.00


300 m2 on each floor
(ii) Covered area exceeding 7.00 35,000.00
300m2 but not more 1000m2 n
each floor
(iii) Covered area exceeding 10.00 50,000.00
1000m2 on each floor
(2) 15m and above but not 15.00 1,00,000.00
exceeding 30m
(3) Above 30m in height 20.00 1,50,000.00
(d) Hotels( starred) (A-6)
(1) Less than 15m in height
(i) 3 starred Hotels 15.00 1,00,000.00
(ii) 5 starred Hotels 20.00 1,50,000.00
(iii) 7 starred Deluxe Hotels 25.00 2,00,000.00
(2) 15m & above but not exceeding 30.00 3,00,000.00
30 m in height
(3) Above 30m in height 50.00 4,00,000.00

EDUCATIONAL BUILDINGS(B)
(1) Less than 15m in height
(i) Ground plus one storey 5.00 30,000.00
(ii) Ground plus two story 7.00 35,000.00
(2) 15m and above but not 10.00 50,000.00
exceeding 30m in height
INSTITUTIONAL
BUILDINGS ( C)
(a) Hospitals, Sanatoria and nursing
homes(C-1)
(1) Less than 15m in height
(i) Up to ground plus one story 5.00 30,000.00
with plot area less than
1000m2, with no beds
(ii) Up to ground plus one storey 7.00 35,000.00
with plot area greater than
1000m2 with beds
(iii) Above two storey, with no 8.00 40,000.00
beds
(iv) Above two storey, with 9.00 45,000.00
beds
(2) 15m and above but not 10.00 75,000.00
exceeding 24m in height
(3) Above 24m and not exceeding 15.00 1,00,000.00
30m in height
(b) Custodial (c-2) and Penal and
Plental (c-3)
(1) Less than 10 in height
(i) Up to 300 persons 5.00 30,000.00
(ii) More than 300 persons 6.00 35,000.00
(2) 10m and above but not 8.00 40,000.00
exceeding 15m in height
(3) 15m and above but not 10.00 50,000.00
exceeding 24m in height
(4) 24m and above but not 15.00 1,00,000.00
exceeding 30m in height
ASSEMBLY BUILDING (D)
(D-1 TO D-5)
(1) Less than 10m in height

(i) Upto 300 persons 5.00 30,000.00


(ii) More than 300 persons 6.00 35,000.00
(2) Above 10 m but not exceeding 8.00 40,000.00
15m in height
(3) Above 15 m and above but not 10.00 75,000.00
exceeding 24m in height
(4) Above 24 m not exceeding 30 m 15.00 1,00,000.00
in height
BUSINESS BUILDINGS(E)
(1) Less than 10 m in height 5.00 35,000.00
(2) Above 10m but not exceeding 7.00 50,000.00
15m in height
(3) Above 15 m and up to 24 m in 10.00 1,00,000.00
height
(4) Above 24 m in height 15.00 1,50,000.00

MERCANTILE BUILDING (F )
(a) F-1 and F-2
(1) Less than 15 m in height
(i) Ground plus one story, with 5.00 30,000.00
total covered area not
exceeding 500m2
(ii) Ground plus one story and 7.00 35,000.00
covered area exceeding
500m2
(iii) More than ground plus one 8.00 50,000.00
story
(2) Above 15 m but not exceeding 10.00 1,00,000.00
24m in height
(3) Above 24m but not exceeding 15.00 1,50,000.00
30 m in height
(b) Underground shopping complex -- ----
(F-3)
INDUSTRIAL BUILDINGS (G)
(a) Low Hazard (G-1)
(1) Up to 18m in height
(i) Covered area up to 50m2 5.00 30,000.00
(ii) Covered area above 50m2 7.00 40,000.00
and up to 100m2
(iii) Covered area above 100m2 10.00 75,000.00
and upto 200m2
(iv) Covered area above 200m2 15.00 1,00,000.00
and up to 400m2
(v) Covered area above 400m2 20.00 1,50,000.00
(b) Moderate Hazard (G-2)
(1) Up to 18m in height
Covered area up to 100m2 5.00 30,000.00
Covered area above 100m2 and 7.00 75,000.00
up to 250 m2
Covered area above 250m2 and 10.00 1,00,000.00
up to 500m2
Covered area above 500 m2 15.00 1,50,000.00
(c) High Hazard (G-3)
(1) (A) Up to 15m in height
(i) Covered area up to 50m2 5.00 35,000.00
(ii) Covered area above 50m2 7.00 40,000.00
and up to 150m2
(iii) Covered area above 150m2 10.00 60,000.00
and up to 300m2
(iv) Covered area above 300m2 15.00 1,00,000.00
and up to 500m2
(v) Covered area above 500m2 20.00 2,00,000.00
(B)Cross country Pipelines 20.00 per 2,00,000.00
carrying hazardous gases and mts.
petroleum products
STORAGE BUILDINGS (H)
(1) Up to 15m in height
(i) Single storey Building 10.00 30,000.00
(ii) Ground Plus one floor 15.00 40,000.00
(2) Above ground plus one floor 20.00 50,000.00

HAZARDOUS BUILDINGS (J)


(1) Up to 15m in height
(i) Single storey Building 15.00 35,000.00
(ii) More than one floor 20.00 50,000.00
building but not exceeding
15m

As Follows Consummation Paper forms for the Fire


Department PROPOSAL NOC.

Sr Documents Yes / No Remark


No.
1
Copy of Architect’s
registration with council
of Architecture
2
Copy of Agreement to
Lease
3
Copy of Possession
receipt
4
Copy of confirmed
demarcation plan
5
Copy of all registered
tripartite agreement
6
Final transfer order from
Estate section
7
Copy of power of
attorney (POA)
8
Necessary charges / fees
including Fire Cess
9
Amalgamation NOC
from Estate section
10
Approval of location &
size of Elect. Sub station
from MSEDC
11 NOC from society
12
Built up Area statement
for Fire Cess

Note : After 07 days the above paper consummation paper forms will be
given a letter noc.

FIRE OFFICER
CIDCO FIRE SERVICE
Example of Stamp paper for Fire NOC