CONTROL DE D

FECHA TURNO ANCHO ALTURA LONGITUD M3 TM N° TALADROS

6/2/2013 DIA 0.8 1.146 2 1.83 4.58 10


6/3/2013 DIA 0.8 1.146 3 2.75 6.87 15
6/4/2013 DIA 0.8 1.146 3 2.75 6.87 15
6/5/2013 DIA 0.8 1.146 3.6 3.30 8.25 18
6/6/2013 DIA 0.8 1.146 2.2 2.02 5.04 11
6/7/2013 DIA 0.8 1.146 3.2 2.93 7.33 16
6/8/2013 DIA 0.8 1.146 6.8 6.23 15.58 34
6/11/2013 DIA 0.8 1.146 2.8 2.57 6.42 14
6/12/2013 DIA 0.8 1.146 2.4 2.20 5.50 12
6/13/2013 DIA 0.8 1.146 2.8 2.57 6.42 14
6/15/2013 DIA 0.8 1.146 3.8 3.48 8.71 19
6/17/2013 DIA 0.8 1.146 3.8 3.48 8.71 19
6/18/2013 DIA 0.8 1.146 2.8 2.57 6.42 14
6/19/2013 DIA 0.8 1.146 2.4 2.20 5.50 12
6/20/2013 DIA 0.8 1.146 2.8 2.57 6.42 14
6/21/2013 DIA 0.8 1.146 2.4 2.20 5.50 12
6/23/2013 DIA 0.8 1.146 2.8 2.57 6.42 14
6/26/2013 DIA 0.8 1.146 3.4 3.12 7.79 17
PROMEDIO 0.80 1.15 3.11 2.85 7.13 15.56
MODA 0.80 1.15 2.80 2.57 6.42 14.00
CONTROL DE DATOS EN PRODUCCION DE MINERAL EN TJ-370 E - JUNIO 2013
EXPLOSIVO
DIN(Cart) ANFO(Gam) Kg (Din)/m3 Kg (Nit)/m3 Kg (Din)/TM
Kg (Dinamita) Kg (Nitrato)
20 30 1.62 4.08 0.884 2.226 0.354
30 34 2.43 4.624 0.884 1.682 0.354
30 30 2.43 4.08 0.884 1.484 0.354
36 40 2.916 5.44 0.884 1.649 0.354
22 20 1.782 2.72 0.884 1.349 0.354
32 40 2.592 5.44 0.884 1.855 0.354
68 40 5.508 5.44 0.884 0.873 0.354
28 32 2.268 4.352 0.884 1.696 0.354
24 28 1.944 3.808 0.884 1.731 0.354
28 28 2.268 3.808 0.884 1.484 0.354
38 38 3.078 5.168 0.884 1.484 0.354
38 40 3.078 5.44 0.884 1.562 0.354
42 0 3.402 0 1.326 0.000 0.530
24 30 1.944 4.08 0.884 1.855 0.354
28 30 2.268 4.08 0.884 1.590 0.354
24 30 1.944 4.08 0.884 1.855 0.354
28 30 2.268 4.08 0.884 1.590 0.354
34 40 2.754 5.44 0.884 1.746 0.354
31.89 31.11 2.58 4.23 0.91 1.54 0.36
28.00 30.00 2.27 4.08 0.88 1.48 0.35
Kg (Nit)/TM

0.890
0.673
0.594
0.659
0.540
0.742
0.349
0.678
0.692
0.594
0.594
0.625
0.000
0.742
0.636
0.742
0.636
0.698
0.62
0.74
Costo Vida Costo x
PARAMETROS DESCRIPCION Unid. Cant.
Unit. S/. Util Disp. S/.
Malla 0.40 m x 0.50 m. 1. Mano de Obra

Longitud de Perforacion 2.80 m. Perforista Tarea 1.33 70 93.1


Ancho de Perforacion 0.80 m. Ayud. Perforista Tarea 1.33 60 79.8
Long. Taladro 1.15 m. 2.66 172.9
Nro. Taladros 14 Taladros
Volumen/Disparo 2.85 m3
Costo/m3. Costo Unit. Costo x Costo/m3.
DESCRIPCION Unid. Cant. Vida Util
(S/./m3) S/. Disp. S/. (S/./m3)
2. Explosivos 2.85 m3

67.20
Dinamita 65% 7/8"x7" Unid. 28 2.40
Anfo Kg 4.76 2.40 11.42
60.67 Fulminante Unid. 14 1.20 16.80
Guia de Seguridad Mts. 17.3 1.20 20.76
116.18 40.77
Costo Costo x Costo/m3.
DESCRIPCION Unid. Cant. Vida Util
Unit. S/. Disp. S/. (S/./m3)
3. Maquina y acc. Perf.

DESCRIPCION Unid. Cant.


Barreno de 4 pies P.P. 56.00 350.00 1000.00 19.60
Perforadora YT-29 P.P. 56.00 3240.00 120000.00 1.51 4. Herramientas y otros
Manguera aire Mts. 20.00 11.00 150.00 1.47 Piedra Esmeril Afilad. 1.00
Manguera agua Mts. 20.00 4.50 150.00 0.60 Pico Minero Pza. 1.00
Aceite Perf. Lts. 0.50 1.425 79.26 0.01 Lampa Minera Pza. 1.00
Pintura, barretillas, accesorios Glob. 5.00 Comba de 6 lbs. Pza. 1.00
28.19 9.89 compa de 12 lbs. Pza. 1.00

Llave Stilson 14" Pza. 1.00


Llave Crescent 18" Pza. 1.00
Arco de Sierra Pza. 1.00
Hoja de Sierra Pza. 1.00
Band-it, empalmes, etc Glob.
2.8 30
2.8 8.03
2.8 7.14
2.8 15
2.8 28
2.8 26.8
2.8 48

2.8 4.67
2.8 2.33
Costo Costo x Costo/m3. Costo
Vida Util DESCRIPCION Unid. Cant. Vida Util
Unit. S/. Disp. S/. (S/./m3) Unit. S/.
5. Implementos de Seguridad
84.00 50.00 1.68 Tareas con ropa de agua Tar. 2.63 7.78
22.48 50.00 0.45 Tareas sin ropa de agua Tar. 2.50 6.27
19.99 50.00 0.40
42.00 150.00 0.28
78.40 150.00 0.52

75.04 200.00 0.38


134.40 150.00 0.90
13.08 40.00 0.33
6.52 2.00 3.26
1.50
9.69 3.40
Costo x Costo/m3. Costo Costo x Costo/m3.
DESCRIPCION Unid. Cant. Vida Util
Disp. S/. (S/./m3) Unit. S/. Disp. S/. (S/./m3)
6. Equipos
20.47 Carretillas Pza. 1.00 250.00 180.00 1.39
15.68 Carro Minero Z-20 Pza. 1.00 1000.00 360.00 2.78
36.15 12.68 4.17 1.46
Costos Fijos
Jefatura Mina 0.2 85
Geologia 0.2 60
Pract. Ing. Minas 0.2 35
Adm. Mina 0.2 45
Supervisor 0.2 45
Capataz 0.2 45
Cocina 0.2 35

TOTAL 70
24.56
METROS CUBICOS DE MINERAL EN TAJO 370 E + LIMPIEZA Y ACARREO
S.M.R.L. DON RAFO 2
Malla 0.40 x 0.50 m. Long. Perf. 2.80 mts.
Nro. Taladros 14 tal. Ancho Perf. 0.80 mts.
Long. Taladro 1.15 mts.
Volumen/Disparo 2.85 m3
Costo Unit. Costo x Costo/m3.
DESCRIPCION Unid. Cant. Vida Util DESCRIPCION Unid.
S/. Disp. S/. (S/./m3)
1. Mano de Obra 7. Combustible
Perforista Tarea 1.33 70 93.1 Compresora Hrs.
Ayud. Perforista Tarea 1.33 60 79.8 Ventilacion Hrs.
2.66 172.9 60.67
2. Explosivos 2.85 m3
Dinamita 65% 7/8"x7" Unid. 28 2.40 67.20
Anfo Kg 4.76 2.40 11.42
Fulminante Unid. 14 1.20 16.80
Guia de Seguridad Mts. 17.3 1.20 20.76
116.18 40.77
3. Maquina y acc. Perf.
Barreno de 4 pies P.P. 56.00 350.00 1000.00 19.60
Perforadora YT-29 P.P. 56.00 3240.00 120000.00 1.51
Manguera aire Mts. 20.00 11.00 150.00 1.47
Manguera agua Mts. 20.00 4.50 150.00 0.60
Aceite Perf. Lts. 0.50 1.425 79.26 0.01
Pintura, barretillas, accesorios Glob. 5.00
28.19 9.89
4. Herramientas y otros
Piedra Esmeril Afilad. 1.00 84.00 50.00 1.68
Pico Minero Pza. 1.00 22.48 50.00 0.45
Lampa Minera Pza. 1.00 19.99 50.00 0.40
Comba de 6 lbs. Pza. 1.00 42.00 150.00 0.28
compa de 12 lbs. Pza. 1.00 78.40 150.00 0.52
Llave Stilson 14" Pza. 1.00 75.04 200.00 0.38
Llave Crescent 18" Pza. 1.00 134.40 150.00 0.90
Arco de Sierra Pza. 1.00 13.08 40.00 0.33
Hoja de Sierra Pza. 1.00 6.52 2.00 3.26
Band-it, empalmes, etc Glob. 1.50
9.69 3.40
5. Implementos de Seguridad
Tareas con ropa de agua Tar. 2.63 7.78 20.47
Tareas sin ropa de agua Tar. 2.50 6.27 15.68
36.15 12.68
6. Equipos
Carretillas Pza. 1.00 250.00 180.00 1.39
Carro Minero Z-20 Pza. 1.00 1000.00 360.00 2.78
4.17 1.46
7. Combustible
Compresora Hrs. 1.50 21.75 32.63
Ventilacion Hrs. 0.25 21.75 5.44
38.06 13.36
COSTOS DIRECTOS 142.23
COSTOS FIJOS 50
192.23
GASTOS GENERALES (del costo directo) 12% 17.07
Utilidad (del costo directo) 10% 14.22
COSTO TOTAL (s/. /m3) 223.52
Costo Unit. Costo x Costo/m3.
Cant. Vida Util
S/. Disp. S/. (S/./m3)

1.50 21.75 32.63


0.25 21.75 5.44
38.06 13.36
Dinamita
Anfo
Fulminantes
Guia de Seguridad
Precio Tota
Taladro 3 pies
Taladro 4 pies
Taladro 5 pies
Precio unitario

Taladro 4 pies
Precio unitario
DINAMITA
ZONA NIVEL VETA LABOR CLASE
(Kg)
Lomada 2025 Sta. Rosa Tj-370 Explotacion 252.556
Lomada 2025 Sta. Rosa Tj-482 Explotacion 83.6
Lomada 2025 Sta. Rosa Tj-400 Explotacion 39.52
Lomada 2025 Sta. Rosa Tj-245 Explotacion 18.16
Lomada 2025 Sta. Rosa SN-370 Preparacion 87.04
Lomada 2025 Sta. Rosa CX-815N Explotacion 39.12
Lomada 2025 Sta. Rosa GL-317 Desarrollo 28.4
Lomada 2025 Sta. Rosa PQ-370 Explotacion 12
Lomada 2025 Sta. Rosa PQ-511 Explotacion 10.24
Lomada 2025-1985 Sta. Rita Carretera Desarrollo 153.04
Principal Faldera Faldera Carretera Explotacion 80.32
Principal 2172 Fonseca Tj-095 Explotacion 147.28
Consumo total 951.276

Cantidad Medida P.U. P.T.


11891 unid S/ 2.40 S/ 28,538.40
1719.992 kg S/ 2.40 S/ 4,127.98
5833 unid S/ 1.00 S/ 5,833.00
8358.91 unid S/ 1.30 S/ 10,866.58
Precio Total S/ 49,365.96
Dinamita Fulminantes Guia de Seguridad
(unid) Anfo (kg) (unid) (m) Costo por Taladro
2 0.136 1 1 S/ 7.43
1 0.544 1 1.23 S/ 6.30
1 0.816 1 1.53 S/ 7.35
S/ 2.40 S/ 2.40 S/ 1.00 S/ 1.30

Dinamita Anfo (kg) Fulminantes Guia de Seguridad Costo por taladro


(unid) (unid) (m)
2 0.408 1 1.23 S/ 8.38
S/ 2.40 S/ 2.40 S/ 1.00 S/ 1.30
ANFO FULES GUIA
(kg) (unid.) (m)
465.664 1576 2305
161.568 534 759.6
80.784 254 362.7
38.352 119 170.6
158.848 517 751.3
52.768 208 286.1
55.08 167 219.4
8.296 111 138.41
2.72 64 69.1
293.76 946 1363.3
157.624 503 716.9
244.528 834 1216.5
1719.992 5833 8358.91