Vous êtes sur la page 1sur 10

TECHNICAL ARTICLE

Recommended Contractual Methods For


Resolving Delay Events
Prospectively or Retrospectively
Patrick M. Kelly, PSP

Abstract: The reality of construction projects is that the oft-mandated methodol-


ogy for granting a contract time extension is ignored during the press of work. Having defined the nature and
This can result in a significant change in the risk allocation between the parties. cause of trends and the scope
The traditional risk allocation model requires performing a prospective time im- and cause of deviations and
pact analysis (TIA), with agreements on time and money prior to corrective work change requests, corrective
commencing. Yet, when the work is performed before negotiation, the risk allo- action alternatives are
cation has shifted significantly. This article makes recommendations for two con- developed and assessed using
tractual paths for resolution of changes with potential time impacts, to balance the forecasting process (Section
risk and responsibility for cost control. The first method, occurring prior to the 10.2). Forecasting applies the
start of corrective work, uses a prospective TIA to determine entitlement to time, methods of integrated project
and bilateral negotiation to manage costs. The second method occurs immedi-
planning (Chapter 7) in the
ately upon completion of corrective work, tracks costs through stringent time and
material cost accounting, and determines time through a contemporaneous pe- context of a project that is
riod analysis. Having two methods for resolution gives project managers additional progressing while demanding
tools to resolve time-related issues early and prior to contract completion, mini- quick and effective change
mizing potential disputes. This article was first presented as CDR.923 at the 2012 management decisions.
AACE International Annual Meeting in San Antonio, Texas. The change management
process may identify alternative
Key Words: Construction, contracts, cost, project management, and risk actions to implement changes
and to correct performance

T
he AACE Total Cost thereby closing the project trends (including process
Management Framework, control cycle loop. The process improvements). These are
Section 10.3, “Change includes the identification, generally simple action
Management,” states: definition, categorization, statements (e.g., “revise
recording, tracking, analyzing, schedule logic”). The forecasting
Change management refers to disposition (i.e., approval or process develops the proposed
the process of managing any disapproval for incorporation action statements into
change to the scope of work into approved or baseline actionable control plan
and/or any deviation, project control plans), and alternatives for further
performance trend, or change to reporting of deviations, trends, assessment (e.g., “complete
an approved or baseline project and changes [14]. activity B before activity A”).
control plan. The change Additional alternative actions
management process is used to Furthermore, regarding the analysis may be identified in this process
approve or disapprove changes of changes, “Section 10.3.2.5 “Assess [15].
in the scope and baseline plans, Impact” states:

COST ENGINEERING NOVEMBER/DECEMBER 2013 29


This article does not address the Furthermore, it is very important that the time effects of changes relates to
correction of performance trends owner be given the opportunity to whether the event and added work have
described in the TCM; however, understand the event and the impacted activities which define the
deviations and change requests resulting implications of the added work, prior to project’s critical path. In other words, if
in the need for analysis and possible that work taking place. It is possible that the event and added work do not impact
alternative actions requires a proactive the cost or time implications of the added a critical activity, then it is merely
change management plan within the work may cause the owner to alter his impacting the float of a non-critical
project controls process. plan for proceeding. The owner may, for activity and not the overall duration of
instance, delete scopes of work in order the project.
The Problem to account for the time and money When events such as these occur, the
While executing construction associated with the added work, or may contractor is typically required to submit
contracts, contractors often encounter use another contractor to perform the a request for time extension (RFTE) which
problems which were not foreseen by work. provides analysis and justification for a
either party, and which are not covered For some owners, whether or not to modification to contract time, resulting
by the contract. Additionally, the needs of proceed with the work may be contingent from a critical path delay. In most
owners occasionally evolve after the upon whether the owner has sufficient contracts, the mandated form of RFTE is
award of a contract, necessitating a funds to pay for the added work related the time impact analysis (TIA). However,
change to the contract. to the changes. And, if money is available given the stringent requirements that
These issues can be described as but on-time completion is a must, the exist for the correct performance of a
having the following three parts. owner may also need to decide whether prospective TIA, it is problematic to have
to pay for acceleration of future work in this as the sole contractual means for
• The discovery of an interference or order to meet the original contract resolution of a time-related dispute
changed condition, (hereafter completion date. during project performance.
referred to as the, “event”); All these options are denied to the Should there not be sufficient time to
• The time necessary to resolve the owner when the contractor moves perform a TIA in a prospective manner, it
contractual issues related to the forward with work prior to analysis and is helpful to have an alternate means for
change, (hereafter referred to as the, agreements. Failure to reach any sort of the determination of entitlement to a
“resolution time”); and, formal agreement prior to the start of the time extension. On occasions where it is
• The work necessary to overcome the added work therefore puts both parties impractical to perform a prospective TIA,
event and return to the original at risk. It is in the interests of both parties a contemporary period analysis (CPA) can
contract scope, (hereafter referred to to arrive at such an agreement as early as show entitlement to a time extension in
as the, “added work”). possible, but before the start of the the period immediately following the
added work. completion of the event, resolution time,
For example, the discovery of an and added work. (Note that while this
abandoned duct bank not shown on the article refers to AACE Recommended
plans would be the “event,” while the Practice 29R-03, Forensic Schedule
“added work” would involve the Analysis, it is intended that the CPA be
excavation and demolition of the duct conducted while the project is still in
bank. Once the added work is complete, progress; that is, prior to project
the event has been overcome, and completion. In fact, it is best if the CPA is
original contract work can resume. Figure 1—Elements of the conducted in the update period
In between the event and the added Fragnet immediately following the completion of
work lies a lag time, during which the the added work.) Closely linked to the
administrative processes designed to These three parts together make up analysis method that should be used to
establish a means for payment and to the essential elements of the determine or control the aspect of
determine the necessity of a time fragmentary network, or “fragnet,” which changes related to time is the selection of
extension take place. This is the represent the total impact that the the contract type that should be used to
“resolution time,” and minimizing this changed condition can have on the determine or control the aspect changes
time is a key way to reduce the overall project. As a result of many of these related to cost and risk.
impact of changed conditions. It is events, resolution time, and added work,
essential, however, to ensure that before the contractor’s ability to finish the scope Construction Contracting: The Balance
the added work begins, the contractual of work within the original contract between Cost Control and Risk
methods to compensate the contractor duration may be impacted. Construction is fraught with risks for
(for both time and money) are in place. Construction contracts need a both parties: risks to cost, time, and
The contractor should not wish to method to analyze the effects of events performance. Design of the construction
proceed until there is assurance that he and added work to the overall duration of contract is the process of building an
will be compensated for the time and the project. In a contract that requires agreement between the two competent
effort associated with the added work. CPM scheduling, the discussion of the parties—the owner and the contractor—

30 COST ENGINEERING NOVEMBER/DECEMBER 2013


that clearly defines the scope of work and functional or detailed specification, when confidence. A T&M contract provides no
establishes a price for the work (which the owner can establish a fair and positive profit incentive to the contractor
contains a fair and reasonable profit). The reasonable price. A FFP contract usually for cost control or labor efficiency.
contract serves as a legally binding establishes a price based on the Therefore, it is essential that the owner
agreement, wherein the contractor contractor’s understanding of that provide surveillance of contractor
promises to perform the work described, developed scope of work, with respect performance in order to ensure that
and the owner agrees to pay. also paid to market conditions and the efficient methods and effective cost
likely prices of competitors also seeking controls are being used. Cost controls are
The Contract the contract. Given that the price is fixed, therefore typically provided by daily
The contract consists of the basic maximum incentive for cost control is submission of cost records, and proper
agreement, which forms the legally placed upon the contractor. It provides cost accounting methods which will
binding agreement described above. It maximum incentive for the contractor to allocate labor and equipment specific to
can also consist of supplemental control costs and perform effectively and the event and added work.
agreements (also called modifications), imposes a minimum administrative Generally speaking, the
when the basic agreement must be burden upon the contracting parties. reasonableness of a price is established in
altered for some reason. A supplemental CR contracts allow for payment of one of the following ways:
agreement will alter the contract in allowable incurred costs, to the extent
scope, quantity, or schedule. These prescribed in the contract. These • There is adequate price competition.
supplemental agreements can either be contracts establish an estimate of total • There are reasonable price
bilaterally negotiated and agreed upon, cost for the purpose of obligating funds comparisons with prior purchases of
or can be unilaterally issued by the and establishing a ceiling that the the same or similar supplies or
owner. contractor may not exceed (except at its services made on a competitive basis
Beyond this basic definition of a own risk) without the approval of the or supported by valid certified cost or
contract, however, there are many contracting officer. pricing data.
different types of contracts, which are A Cost-Plus-Incentive-Fee contract • Available cost or pricing information
appropriate to use depending on the (CPIF contract) is a specific type of cost- permits realistic estimates of the
circumstances of the project. The Federal reimbursement contract that provides for probable costs of performance. And,
Acquisition Regulations (FAR), Part 16, an initially negotiated fee to be adjusted • Performance uncertainties can be
Types of Contracts, provides a standard later by a formula based on the identified and reasonable estimates
taxonomy for the contract types. (Clearly, relationship of total allowable costs to of their cost impact can be made,
not all construction projects are total target costs [12]. Such contracts and the contractor is willing to
performed under the FAR; however, the should be used when circumstances do accept a firm fixed price representing
FAR definitions are a convenient method not allow the owner to define its assumption of the risks involved.
of describing the many contract types in requirements sufficiently to allow for a
use in the industry.) FAR, Part 16, lists the FFP contract, or uncertainties involved in Among the factors that FAR, Part 16,
following five major groups of contract contract performance do not permit costs recommends for consideration are the
types: to be estimated with sufficient accuracy following [9]:
to use any type of fixed-price contract.
• Fixed Price contracts [4]; Since CPIF contracts use a pre- • Price competition—The process of
• Cost Reimbursement (CR) contracts determined formula for judging the full and open competition for a
[5]; contractor’s time and cost performance, contract is generally accepted to
• Incentive contracts[6]; and that formula calculates the level of create a fair and reasonable price.
• Indefinite Delivery (IDIQ) contracts profit that the contractor earned. In this Multiple contractors bidding on a
[7]; and, way, the CPIF provides a method of common scope of work will typically
• Time and Materials (T&M) contracts incentivizing performance, though the result in a situation where the lowest
[8]. incentive is often not as great as the responsive bidder’s price represents
potential incentive in a FFP contract. the best price available for that
For the purposes of this article, the T&M Contracts allow for acquiring scope of work within that particular
three contract groups that are most supplies or services on the basis of direct market. This is typically how a
relevant to the performance of an labor hours at specified fixed hourly rates reasonable price for a base
individual construction project are firm that include wages, overhead, general agreement is reached, particularly in
fixed price (FFP), CR, and T&M contracts. and administrative expenses, and profit; FFP contracts.
FFP contracts establish a price that is and actual cost for materials [13]. A T&M • Price analysis, or, if necessary, cost
not subject to any adjustment on the contract may be used only when it is not analysis—If full and open
basis of the contractor’s cost experience possible at the time of placing the competition is not an option (for
in performing the contract [11]. The FFP contract to estimate accurately the extent instance, in the creation of
contract is suitable for acquiring services or duration of the work or to anticipate supplementary agreements) then it
on the basis of a reasonably definite costs with any reasonable degree of may become necessary for the

COST ENGINEERING NOVEMBER/DECEMBER 2013 31


owner to analyze the proposed price Therefore, the selection of a contract Note that this article does not refer
or costs in order to determine type must balance all these factors, with to AACE RP 29R-03, Forensic Schedule
reasonableness. Price or costs can be an understanding that the selection of a Analysis, in its definition of the TIA. The
compared to the price or costs for contract type has implications for the TIA described in RP 29R-03, Method
similar services within similar price to perform the work and for the Implementation Protocol (MIP) 3.7, is a
markets, or can be compared to data balance of risk and administrative retrospective TIA. This article is providing
in appropriate estimating guides. requirements placed on each party. In a prospective perspective, in as much as
• Type and complexity of the other words, and owner should not think the TIA is concerned. The inherently
requirement — Complex that his administrative burden will be the retrospective nature of the CPA (MIPs 3.3
requirements usually result in a same for a T&M contract as it is for a FFP and 3.4) will be addressed separately, in a
greater level of risk being borne by contract—at least not if the owner manner that is in keeping with the
the owner. This selection factor intends to get the work performed in the recommended contract type.
relates, at least in part, to the most efficient manner possible. A TIA compares two schedules with
owner’s ability to fully define the As the owner’s cost risk increases, the same data date—one schedule that
scope of work. the owner must be willing (and able) to does not represent the event, resolution
• Urgency of the requirement—If the provide the additional oversight time, or added work, and one schedule
owner has a requirement that is necessary to ensure that the costs are that does represent the event, resolution
urgent in nature, it is likely that the reasonable and fully documented. In the time, and added work through the
owner will be required to accept a event that a contract cannot be FFP in its addition of activities and logic. The first
contract type in which he accepts entirety, because of the particular schedule is the most recently accepted
more of the risk. circumstances of that project, then it is schedule with a data date prior to the
• Adequacy of the contractor’s possible (or even preferable) to combine event—the “unimpacted schedule.”
accounting system—If the owner is contract types [10]. In these cases, (Note that it is a good practice, if the
considering using a contract type specific portions of a project’s scope are unimpacted schedule does not
other than FFP, it is essential that theperformed under a sub-agreement that is adequately represent the status of
owner verify that the contractor’s a different contract type from the basic progress at the time of the event, that it
accounting system is sophisticated agreement. should be statused and updated to the
enough to support the additional There are many different ways to day just prior to the event.)
cost accounting that CPIF and T&M contract for construction services. And, The second schedule has the same
contracts require. Given that the there are many different ways to analyze data date, but also contains the fragnet—
owner must rely on the contractor’s the time-related effects of a change to those added activities and logic which
accounting system to provide the the scope of work. It is important, then, represent the event, resolution time, and
support for the reasonableness of to pair the schedule analysis technique added work. This is the impacted
the costs incurred, the owner will not with the proper contract type (to be used schedule. The comparison of the
want to issue a T&M or CPIF contract in issuing the supplemental agreement), completion dates of the two schedules
to a contractor who cannot support to achieve the proper balance of cost risk (before and after the fragnet) determines
that level of accounting. and profit incentive, while also whether there is entitlement to a time
accounting for the time in the best way extension.
The key factor, however, in selection possible. In figure 3, a fragnet has been
of a contract type is the balance of risk inserted in the impacted schedule,
within the contract. Each contract type Path #1: The TIA and the FFP affecting the start of Activity A. As a
has a different method of allocating risk Supplemental Agreement result, the predicted completion date was
between the two parties, and balancing AACE International’s Recommended delayed from July 12, 2012, to August 1,
that risk is the ability to define the Practice 52R-09, Time Impact Analysis – 2012. The difference between the two
contract scope. In general, as the owner’s As Applied in Construction, describes the schedules’ predicted completion date is
ability to fully define the scope of work TIA this way: the basis of the negotiations for a time
increases, so does the owner’s ability to extension.
design a contract vehicle which places The TIA is a ‘forward-looking,’
more cost risk on the contractor. prospective schedule analysis
Conversely, if the owner is unable to fully technique that adds a modeled delay With regards to entitlement,
define the scope, the owner will likely to an accepted contract schedule to however, the reviewer must remember
have to accept more of the cost risk. determine the possible impact of that the existence of a delay does not
Figure 2 shows the complex that delay to project completion. This necessarily equate to entitlement to a
relationship between the balance of cost practice is not recommended for a time extension. There are any number of
risk and the profit incentive, along with retrospective (hindsight or forensic) issues which can delay a project which
the level of scope definition that the view taken after a significant passage are not excusable (such as contractor-
owner can provide. of time since the delay event [1]. caused delay events), or which are
excusable but non-compensable:

32 COST ENGINEERING NOVEMBER/DECEMBER 2013


Figure 2—Balance of Risk and Profit

(meaning time but no money, such as perform it, and a price. The contractor to accomplish and accept
force majeure events like weather then has control of his costs (and by contractually; eliminating the cost-
delays). Therefore, the reviewer must extension his profit), but also is driven considerations from both
determine whether the event is responsible for conforming to the time ‘creator’ and ‘approver’ of the TIA
excusable and compensable, in terms of for performance. The risk is appropriately [2].
the contract. balanced between the parties, since the
Given this understanding of the analysis method and the contracting As discussed above, the
technical process necessary to perform a method are aligned. Note that the TIA reasonableness of FFP contracts is most
proper prospective TIA, it is important to process itself does not directly address commonly determined through price
note that the creation of a fragnet— the cost aspect of changes. RP 52R-09 competition. In absence of price
before the performance of the added states: competition, FAR, Part 16, suggests price
work—that accurately represents or cost analysis. Therefore, if a delay is
everything the contractor will have to do This TIA practice concerns itself with shown to exist, the reviewer must then
in order to overcome the change and time aspects, not cost aspects of conduct the process of determining the
return to base contract work, is in fact projects. The time impact must be reasonableness of the costs requested by
directly related to the owner’s ability to quantified prior to determining any the contractor. The costs will, in this case,
define the scope of work. In this way, the cost implications. No practical include both direct costs (those costs
prerequisite for selection of this advantage is obtained by including related to the labor and materials
methodology is very similar to the cost factors into a time impact necessary to perform the work) and
prerequisite for using a FFP contract. And, analysis. Linking time and cost into indirect costs (the time-related costs
in fact, the bilateral supplemental one analysis implies that time associated with the extended contract
agreement that would be the result of impacts are a function of costs, duration).
this version of the change process is a which for the purposes of a On the other hand, if an event is
small FFP contract—the owner and prospective TIA is not true. shown to not have an effect on the critical
contractor are agreeing up front on a Separating time analysis from cost path, the reviewer must still determine
scope of work to be performed, a time to analysis makes TIA inherently easier whether that change had any cost

COST ENGINEERING NOVEMBER/DECEMBER 2013 33


supplemental agreement. Instead,
owners and contractors should use an
alternate path to resolution.

Path #2: The CPA and the T&M (or CPIF)


Supplemental Agreement
The second possible path for
resolution of changes involves using a
T&M contract type (or possibly a CPIF, if
the owner’s contracting organization is
sufficiently sophisticated to handle the
development and execution of the
formulas for calculating the incentive
fee). As discussed, the T&M contract type
is used when the owner cannot
sufficiently define the scope of work, or
when the urgency of the work is such that
the owner is willing to accept a greater
portion of risk in order to achieve faster
completion (i.e., minimizing the
resolution time to the maximum extent
possible).
In cases where the owner cannot
sufficiently define the scope, it is not
realistic to compel the contractor to
estimate, with any degree of accuracy,
the durations of activities for the added
work. However, with most contract
Figure 2—Balance of Risk and Profit specifications, the prospective TIA is the
only method available to the contractor
to justify an RFTE. The other option—to
impacts to the contractor. In this case, the price that the owner pays to ensure a
perform the work without a
there should only be direct costs, since finalized resolution of changes which are
supplemental agreement, and “take care
there are no time-related costs. The his responsibility. Should the owner
of it at the end of the project”—is
reviewer should also consider the choose to actively avoid spending
unacceptable because it can confuse the
possibility that the changes that have not resolution time on finalizing a
parties as to where the responsibility for
affected the critical path may have supplemental agreement, or passively
cost and time control lies. If both parties
caused disruption to the contractor’s avoid it by allowing the contractor to
think that the other is responsible for
work. The contractor is also possibly due proceed with added work prior to the
controlling costs and time, it is likely that
these costs related to disruption (to the supplemental agreement, the owner is
neither party will pay the appropriate
extent they can be quantified). Ignoring likely to find himself in a situation where
amount of attention to these factors. It is
the non-critical impacts of changes, he is either paying too much for a change,
here that the seeds of disputes and
however, will deprive the contractor of or is involved in a post-completion claim.
claims related to changes are planted,
money he is likely due, and increase the However, use of this combination of
and it is because of these incongruities
chances that the contractual relationship analysis technique and contract type is
that a second path is needed.
will become adversarial. This pushes the also predicated upon the urgency of the
According to AACE RP 29R-03,
contract closer to claim. work. It is possible that once the event
Forensic Schedule Analysis, Method
It is important to understand that the occurs, both parties can immediately
Implementation Protocols (MIP) 3.3 and
time between the occurrence of the agree (with a reasonable level of
3.4 are commonly called, “windows
event and the start of added work—the certainty) that the added work will affect
analysis or contemporary period analysis”
resolution time—must be minimized as the critical path. Furthermore, the owner
[16]. This will be the common term used
much as possible, but that the resolution may believe that time is more important
to describe these two methods, and the
time is necessary to ensure that the time than money, and that he would prefer the
method will be further described and
and cost of the added work is fair and contractor to immediately begin the
refined herein. The CPA “is retrospective
reasonable and that the contractor has an added work (thus minimizing or
technique that uses the project schedule
incentive to keep his costs and eliminating the resolution time).
updates to quantify the loss or gain of
performance period within reasonable In these cases, Path #1 (the TIA/FFP
time along a logic path and identify the
boundaries. The resolution time, then, is option) is not valid for reaching a
causes. Although this method is a

34 COST ENGINEERING NOVEMBER/DECEMBER 2013


retrospective technique, it relies on the this way, the scheduler can help This “post-impact revised schedule”
forward-looking calculations made at the document the responsibility for different can serve as the basis for additional
time the updates were prepared. That is, portions of the delay shown in the negotiation and compensation, which can
it primarily uses the information to the analysis. The fragnet will not, however, be definitized in either the second
right of the updates’ data date.” forward-project the effects of future supplementary agreement or in a
Furthermore, RP 29R-03 states: delays. No activities should be added to separate supplementary agreement,
the right of the data date, and the critical depending on the needs of the project.
“[The Contemporaneous Period path of the post-impact schedule will be However, it is very important to use
Analysis] is an observational driven by the progress information input separate schedules for the post-impact
technique since it does not involve into the original schedule activities, schedule and the post-impact revised
the insertion or deletion of delays, rather than by the effects of the fragnet. schedule, so that the effects of progress
but instead is based on observing the For a detailed discussion of documenting (i.e., the delay to the causal activity
behavior of the network from update delays in this manner, see reference [3]. caused by the actualized fragnet) can be
to update and measuring schedule In figure 4, the pre-impact schedule, clearly separated from the effects of
variances based on unaltered, calculated as of Feb. 4, 2012, shows a network revisions (i.e., revisions to future
existing logic models.” predicted completion date of July 12, activities, logic, or durations).
2012. The post-impact schedule has been Only by separating these two
Because the method uses schedule statused with progress information schedules can the reviewer clearly
updates whose logic may have changed through the next update’s data date, delineate responsibility for the gains or
from the previous updates, as well as March 4, 2012. Note that activities for the losses seen in the schedules, and provide
from the baseline, it is considered a event, resolution time, and added work justification to the contracting authorities
dynamic logic method. have been added to the post-impact for the size of the costs and time in each
It is labeled contemporaneous schedule, but that they are all actualized of the extensions. In figure 5, the
because the updates it relies on were at 100 percent complete and cannot remaining duration of Activity A, as well
prepared contemporaneously with the affect the CPM calculations. The progress as the original durations of Activities C
project execution…. [17]. information also shows that Activity A and D, were reduced in order to regain
A CPA compares two schedules with and Activity B started and progressed; the original predicted completion date of
successive data dates. The first schedule however, the start of Activity A was July 12, 2012.
is the most recently accepted schedule delayed to the point where the critical
with a data date prior to the event. For path was delayed overall. The fact that Note that the comparison of the pre-
the purposes of this article, this will be Activity A has delayed the critical path impact schedule to the post-impact
called the “pre-impact schedule.” (Note (regardless of cause or responsibility) schedule is a simple Contemporaneous
that it is a good practice, if the pre-impact makes Activity A the “causal activity.” Period Analysis, as described in MIP 3.3,
schedule does not adequately represent Because of the effects of the start delay whereas the comparison of the pre-
the status of progress at the time of the to the causal activity, the post-impact impact schedule to the post-impact
event, that it should be statused and schedule shows a later predicted schedule to the post-impact revised
updated to the day just prior to the completion date. The difference in schedule is a Bifurcated
event). predicted completion dates between Contemporaneous Period Analysis, as
The second schedule is the next these two schedules is the duration of the described in MIP 3.4. The difference lies
update schedule after the completion of time extension in the final supplemental in the existence of network revisions and
the added work. For the purposes of this agreement. in the quantification of responsibility for
article, this will be called the “post- It is possible that after the post- those revisions as they relate to changes
impact schedule.” This schedule will be impact schedule has been submitted, in predicted means and methods.
logically identical to the pre-impact that either or both of the parties may This more immediate
schedule. The only difference between decide that it is preferable to condense implementation of the CPA (i.e., using the
the two schedules should be the inclusion the remaining portion of the work in two updates encompassing the fragnet as
of status information—actual start and order to regain the original predicted soon as the added work is complete,
finish dates, percents complete, and completion date. In these cases, it is rather than waiting until the end of the
remaining durations—to represent the preferable to submit a third schedule, project an performing a full CPA across
progress of activities which were having the same data date of the post- the project) is the main way in which this
originally included in the schedule series, impact schedule but containing network implementation differs from the one
and a series of added activities for the revisions to the uncompleted schedule described in RP 29R-03. While the
fragnet. activities. These network revisions may methodology is the same, the
It is very important to note, however, represent compensable acceleration, or methodology described in RP 29R-03, is
that these fragnet activities will be added possibly the deletion of other future generally performed on the entire
to the left of the data date, so that they work, in order to regain the completion duration after project completion. This
do not affect the forward and backward date. article envisions the CPA as a part of the
pass calculations of the CPM algorithm. In in-stream project management process.

COST ENGINEERING NOVEMBER/DECEMBER 2013 35


In other words, while the analysis is
technically a retrospective analysis, it is
being performed contemporaneous with
project progress, and as soon after the
completion of the added work as
possible. This results in a basis for
approval of an RFTE as early as possible.
Schedule specifications can be
designed to create this second path, that
would establish a general scope of work
(detailed to the extent possible), a first
supplemental agreement that would
establish a basis of payment (most likely a
T&M contract that will cover direct costs
and profit), and an agreement that the
time effects of the change would be
judged using a CPA immediately following
the completion of the added work. The
CPA would result in an agreement on the
time impact of the event, resolution time,
and added work. This time impact would
then be included in a second
supplemental agreement which would
compensate the contractor for the time
and indirect costs associated with the
change.
The need for owner-provided
oversight to costs is essential in Path #2.
As described in FAR, Part 16, the Figure 4—Contemporaneous Period Analysis
contractor has little incentive to control
costs in a T&M contract, and in fact has a time as necessary to fully develop the
much smaller profit incentive than with a scope of the added work, such that Path Conclusion
FFP contract. It must be clear in the #1 becomes feasible. Furthermore, The goal of this project management
specification (and in the first by including language in the schedule method is to minimize the resolution
supplemental agreement establishing the specification describing a methodology time, while ensuring that the risks for cost
T&M) that the contractor is required to for use after an event has occurred, the and time control are well-defined and
provide detailed cost accounting records, owner has provided for a means to definitized in a supplemental agreement.
establishing a relationship between all analyze the schedule retrospectively. Note that in both paths, a supplemental
the labor, equipment, and materials that If no agreement can be reached agreement to the contract is in place prior
are used in the execution of added work. during the project on the time impacts, to the start of the added work. However,
This data should be submitted daily, the CPA becomes the method for in Path #2, the finalized agreement for
and the owner must have personnel on analyzing the project’s delays after the time is left until after the work is
staff that is capable of reviewing the fact. This averts any assertion that the TIA complete. But a T&M (or CPIF) agreement
information, establishing a correlation is the “contractual method for is already in place for the work. The
between the written records and the establishment of entitlement to a time contractor is not performing work
work observed in the field, and verifying extension.” without an agreement in either case.
the reasonableness of the costs through The use of a TIA after the fact would Performing work without an agreement is
detailed cost analysis. If the contractor mean performing a retrospective TIA. a good way to drive the project to claim.
cannot provide this level of cost While there are occasions when such an But it also the goal of this project
accounting, or the owner cannot provide analysis may be necessary, retrospective management method to ensure that the
this level of administrative support and TIAs are very difficult to perform, analysis methodology is linked with an
analysis, then Path #2 is not an commonly misrepresent delays and their appropriate contractual methodology, in
appropriate method for establishing a impacts, and tend to ignore the order to have similar levels of
cost and time basis for a supplemental contemporaneous understanding of responsibility and risk balance.
agreement. criticality [18]. For Path #1, the TIA is a method that
If that is the case, then the owner Recommended specification prospectively estimates the time
must accept that he cannot minimize the language describing this process is necessary to perform the added work and
resolution time, and must spend as much included as Attachment #1. whether that time will impact the critical

36 COST ENGINEERING NOVEMBER/DECEMBER 2013


time and cost before start of added work.
This may lengthen the resolution time,
but will benefit the owner in the long run
because the risk is placed on the
contractor, in a manner consistent with
the FFP nature of the basic agreement.
The contractor, however, should not fear
Path #1. Because of his experience with
construction, the contractor is likely in a
position of superior knowledge, and in a
FFP agreement his profit incentive is
maximized.
However, as discussed, Path #2 has
its benefits, most notably in that it
minimizes resolution time and limits the
need for full scope definition. These
benefits come with clear trade-offs for
the owner, who will bear significantly
more risk under this scenario. And both
parties will be under significant
administrative burden, for cost
accounting and delay analysis, using this
method.

Regardless of the method used,


however, it should be the goal of both
parties to reach agreement on the time
and cost impacts of changes as early as
Figure 5—Regaining Schedule Through Revisions possible. Having two paths will maximize
the opportunities for resolution of these
path. The FFP supplemental agreement is This is the proper balance of analysis changes, and as a result minimize the
a method that prospectively estimates methodology and contract method. If chances for disputes. ◆
the cost of performing that work. In both the parties mix these methods, it is likely
cases, the contractor is responsible for that a muddled contractual situation will REFERENCES
the estimation and is in the position to result. For instance, if the contractor 1. Calvey, Timothy T.; and Ronald M.
control the costs and the time, in order to receives a FFP supplemental agreement Winter. Overview, RP 52R-09, Time
come in under budget on both. As a for direct costs related to the added Impact Analysis – As Applied in
result, the contractor has the best work, but no agreement is reached Construction, AACE International, pg.
opportunity to maximize profits. between the parties as to how the time 1.
For Path #2, the CPA is a method that impacts will be judged and paid, the 2. Calvey, Timothy T.; and Ronald M.
retrospectively determines the time that contractor is essentially operating in an Winter Overview, RP 52R-09, Time
was taken to perform the added work informal T&M environment. Impact Analysis – As Applied in
and how much of that time impacted the The contractor is in a position where Construction, AACE International.
critical path. The T&M supplemental it may be to his benefit to perform the pg.1.
agreement is a method that work at a slower rate than possible in 3. Carson, Christopher W. “Claims
retrospectively tracks the costs expended order to maximize indirect costs and Analysis Nested in Schedule
in performing the work. In both cases, associated profits; however, the Updates,” AACE International
the contractor is operating without a contractor will be unsure of whether he Transactions (2006): PS.06.
clear upper boundary, and work is being will be given a supplemental agreement 4. Federal Acquisition Regulations
performed at the owner’s cost and time for these indirect costs. In that same through FAC 2005-55, Subpart 16.2,
risk (more or less). In this case, the owner case, since the contractual responsibility Fixed Price Contracts, effective
must provide significantly greater for performance is unclear, the owner will January 3, 2012.
oversight to ensure that costs and time be in a position where he may not notice 5. Federal Acquisition Regulations
are reasonable. As a result, the that the responsibility has, by default, through FAC 2005-55, Subpart 16.3,
contractor is in a position where his risk fallen to him to ensure performance. Cost Reimbursement Contracts,
of exceeding costs is less, but his profits The best method for the owner is effective January 3, 2012.
will likely be lower. likely Path #1, and to use it means that 6. Federal Acquisition Regulations
the owner must achieve agreement on through FAC 2005-55, Subpart 16.4,

COST ENGINEERING NOVEMBER/DECEMBER 2013 37


Incentive Contracts, effective January 12. Federal Acquisition Regulations 17. Hoshino, Kenji P. Section 3.4
3, 2012 through FAC 2005-55, Subpart Observational/Dynamic/Contempora
7. Federal Acquisition Regulations 16.304, Cost-Plus-Incentive-Fee neous Split (MIP 3.4) RP 29R-03,
through FAC 2005-55, Subpart 16.5, Contracts, effective January 3, 2012. Forensic Schedule Analysis, Pg. 51.
Indefinite-Delivery Contracts, 13. Federal Acquisition Regulations 18. Livengood, John. “Retrospective TIAs:
effective January 3, 2012. through FAC 2005-55, Subpart Time to Lay Them to Rest,” AACE
8. Federal Acquisition Regulations 16.601, Time-and-Materials International Transactions, (2007):
Through FAC 2005-55, Subpart 16.6, Contracts, effective January 3, 2012. CDR.08.
Time-and-Materials, Labor-Hour, and 14. Holloman, John K., ed. Section 10.3,
Letter Contracts, effective January 3, Change Management, Total Cost ABOUT THE AUTHOR
2012. Management Framework. First
9. Federal Acquisition Regulations Edition, AACE International, pg. 215.
through FAC 2005-55, Subpart 15. Holloman, John K., ed. Section
16.104, Factors in Selecting Contract 10.3.2.5, Access Impact, Total Cost
Types, effective January 3, 2012. Management Framework. First
10. Federal Acquisition Regulations Edition, AACE International, pg. 219. Patrick M. Kelly, PSP, is
through FAC 2005-55, Subpart 16. Hoshino, Kenji P. Section 3.3 with Arcadis. He can
16.104, Factors in Selecting Contract Observational/Dynamic/Contempora be contacted by
Types, effective January 3, 2012. neous As-Is (MIP 3.3) and Section 3.4 sending e-mail to:
11. Federal Acquisition Regulations Observational/Dynamic/ Patrick.kelly@arcadis-us.com
through FAC 2005-55, Subpart Contemporaneous Split (MIP 3.4). RP
16.202, Firm-Fixed-Price Contracts, 29R-03, Forensic Schedule Analysis,
effective January 3, 2012. Pgs. 43-55.

INTERNATIONAL ADVENTURER TO KEYNOTE


2014 INTERNATIONAL TOTAL COST MANAGEMENT
CONFERENCE IN BANGKOK, THAILAND
AACE International announces that Khoo Swee Chiow,
noted adventurer and inspirational speaker, will deliver the
keynote address at the November 12-13, 2014 International
Total Cost Management Conference (ITCMC) in Bangkok, Thai- Add-on Software for P6/EPPM
land. The theme of the 2014 ITCMC will be “Taking TCM to A
Higher Level.”
Swee Chiow has climbed Mt Everest three times, skied to Introducing PROJECT WATCH™
the South and North Pole, climbed the Seven Summits, cycled
from Singapore to Beijing, swam across the Malacca Strait, The only software program that shows
kayaked across the Philippines and holds two Guinness World
the P6 or EPPM System Administrator
Records. In 2012, after many years of preparations, Swee
Chiow finally climbed K2, considered to be the toughest and
everything that is happening in real-time.
most dangerous mountain in the world.

P
• Monitor All Projects & Users
As an inspirational keynote speaker, Swee Chiow has ad-
• Coordinate Access
dressed more than 365 audiences. Swee Chiow draws from
his personal experiences of over 40 expeditions and translates
• Analyze Operations
those experiences into lessons relevant to the audience. He
speaks on topics such as vision, teamwork, leadership, deter-
mination, planning, risk assessment, handling failure, passion Schedule Analyzer EnterpriseTM
and courage.
The 2014 International Total Cost Management Confer-
ence will be held November 12-13 at the Millennium Hilton The affordable solution for your Baseline
Bangkok, Thailand. The conference will be a two-day meeting and Update Reviews guaranteed to
that will commence with the opening plenary session on No- reduce your review time to less than half!
vember 12 featuring a Swee Chiou as the keynote speaker. The
• Direct to Database
program then will divide into two tracks of peer-reviewed tech-
nical presentations over the balance of the two days.
Registration for the Bangkok conference is available at
www.aacei.org.
SA e
• Hundreds of Analyses
• Built-In Report Writer
Find out more at http://ScheduleAnalyzer.com

38 COST ENGINEERING NOVEMBER/DECEMBER 2013

Vous aimerez peut-être aussi