Académique Documents
Professionnel Documents
Culture Documents
T
he AACE Total Cost thereby closing the project trends (including process
Management Framework, control cycle loop. The process improvements). These are
Section 10.3, “Change includes the identification, generally simple action
Management,” states: definition, categorization, statements (e.g., “revise
recording, tracking, analyzing, schedule logic”). The forecasting
Change management refers to disposition (i.e., approval or process develops the proposed
the process of managing any disapproval for incorporation action statements into
change to the scope of work into approved or baseline actionable control plan
and/or any deviation, project control plans), and alternatives for further
performance trend, or change to reporting of deviations, trends, assessment (e.g., “complete
an approved or baseline project and changes [14]. activity B before activity A”).
control plan. The change Additional alternative actions
management process is used to Furthermore, regarding the analysis may be identified in this process
approve or disapprove changes of changes, “Section 10.3.2.5 “Assess [15].
in the scope and baseline plans, Impact” states:
(meaning time but no money, such as perform it, and a price. The contractor to accomplish and accept
force majeure events like weather then has control of his costs (and by contractually; eliminating the cost-
delays). Therefore, the reviewer must extension his profit), but also is driven considerations from both
determine whether the event is responsible for conforming to the time ‘creator’ and ‘approver’ of the TIA
excusable and compensable, in terms of for performance. The risk is appropriately [2].
the contract. balanced between the parties, since the
Given this understanding of the analysis method and the contracting As discussed above, the
technical process necessary to perform a method are aligned. Note that the TIA reasonableness of FFP contracts is most
proper prospective TIA, it is important to process itself does not directly address commonly determined through price
note that the creation of a fragnet— the cost aspect of changes. RP 52R-09 competition. In absence of price
before the performance of the added states: competition, FAR, Part 16, suggests price
work—that accurately represents or cost analysis. Therefore, if a delay is
everything the contractor will have to do This TIA practice concerns itself with shown to exist, the reviewer must then
in order to overcome the change and time aspects, not cost aspects of conduct the process of determining the
return to base contract work, is in fact projects. The time impact must be reasonableness of the costs requested by
directly related to the owner’s ability to quantified prior to determining any the contractor. The costs will, in this case,
define the scope of work. In this way, the cost implications. No practical include both direct costs (those costs
prerequisite for selection of this advantage is obtained by including related to the labor and materials
methodology is very similar to the cost factors into a time impact necessary to perform the work) and
prerequisite for using a FFP contract. And, analysis. Linking time and cost into indirect costs (the time-related costs
in fact, the bilateral supplemental one analysis implies that time associated with the extended contract
agreement that would be the result of impacts are a function of costs, duration).
this version of the change process is a which for the purposes of a On the other hand, if an event is
small FFP contract—the owner and prospective TIA is not true. shown to not have an effect on the critical
contractor are agreeing up front on a Separating time analysis from cost path, the reviewer must still determine
scope of work to be performed, a time to analysis makes TIA inherently easier whether that change had any cost
P
• Monitor All Projects & Users
As an inspirational keynote speaker, Swee Chiow has ad-
• Coordinate Access
dressed more than 365 audiences. Swee Chiow draws from
his personal experiences of over 40 expeditions and translates
• Analyze Operations
those experiences into lessons relevant to the audience. He
speaks on topics such as vision, teamwork, leadership, deter-
mination, planning, risk assessment, handling failure, passion Schedule Analyzer EnterpriseTM
and courage.
The 2014 International Total Cost Management Confer-
ence will be held November 12-13 at the Millennium Hilton The affordable solution for your Baseline
Bangkok, Thailand. The conference will be a two-day meeting and Update Reviews guaranteed to
that will commence with the opening plenary session on No- reduce your review time to less than half!
vember 12 featuring a Swee Chiou as the keynote speaker. The
• Direct to Database
program then will divide into two tracks of peer-reviewed tech-
nical presentations over the balance of the two days.
Registration for the Bangkok conference is available at
www.aacei.org.
SA e
• Hundreds of Analyses
• Built-In Report Writer
Find out more at http://ScheduleAnalyzer.com