Académique Documents
Professionnel Documents
Culture Documents
Version: 2.0
Date: 27/06/2018
THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE
GENERIC METERING PANEL TEST FORM
The test form should be read in conjunction with the relevant schematic diagram. This test
form includes both metering and NPD VTs.
Import MPAN
Export MPAN
Substation Name
Substation Number
Metering Panel Serial No
Metering Panel Make
Metering Panel Type
System Configuration 3-PHASE 3-WIRE
CT L1 L2 L3
VT L1 L2 L3
VT Configuration Checks
Remove metering VT and NPD VT (if applicable) fuses and links L1, L2, L3 and N ()
Check the metering circuit breaker is open ()
Apply 240/110V ac from an injection test set to the primary (HV) winding, measure each of the
secondary (LV) winding voltages and compare to the values in the table below *
L1 L2 V V (nominal) V V
L2 L3 V V V (nominal) V
L3 L1 V V V V (nominal)
Remove metering VT and NPD VT fuses and links removed above ()
* These voltages are for an injection test set and if a mains supply is used the results may differ.
** The NPD voltage measured should be in the order of 0.5 to 2V.
Injected/
CT Ratio CT Ratio Calculated Measured
Measured Ratio
Primary Secondary Secondary Secondary
Primary Correct
Phase Current Current Current Current
Current*
[D = B / A *
[A] [B] [C] [E] [E = D]
C]
L1 50 / 100A A A A ()
L2 50 / 100A A A A ()
L3 50 / 100A A A A ()
On completion of test ensure correct CT ratio as specified by designer is selected ()
* Delete as applicable.
CT Relationship to VT Output
CT Burden
1The maximum CT burden is based on 20 metres of 12-core 2.5mm2 or 40 metres of 19-core 2.5mm2 copper cable
with a resistance of 0.0068 Ω/m at 20oC and a CT rated secondary current of 5A.
Final Checks
Test Equipment
Certification
A copy of the completed test form together with the CT/VT calibration certificates shall be placed
in a plastic wallet in the metering unit terminal box.
A copy of the completed test form and the CT/VT calibration certificates shall be sent to the
relevant ART mailbox (ART.EPN@ukpowernetworks.co.uk, ART.LPN@ukpowernetworks.co.uk,
ART.SPN@ukpowernetworks.co.uk).
A copy of the completed test form and the CT/VT calibration certificates shall also be attached
to the relevant operation on the work order or the relevant PO in the contractor portal.