Vous êtes sur la page 1sur 3

BANYU URIP PROJECT

INFRASTRUCTURE FACILITIES EPC - 5

WORK PERMIT SYSTEM


Doc No. REV.
Health Safety Environment Page 1 of 3
IDBC-RH-SPZZZ-C00008 0

Date/ Tanggal :
PERMIT TO WORK Facility / Fasilitas :South Area
Surat Izin Kerja No. of Work Permit :S/EPC5/CW/06-15/
 Hot Work  Cold Work  Energy  Excavation  Confined  Critical Lift
Pekerjaan Pekerjaan Isolation Penggalian Space Pengangkatan
Panas Dingin Isolasi Bekerja Kritis
Energi Diruang
Terbatas
1. Description/location of job / Uraian / LokasiPekerjaan

No. of Worker / 2. Validity of Work Permit / Masa berlaku


Jumlah Pekerja Izin kerja
Work Permit Applicant /
Date / Tanggal :
Pemohon
From 07.00 Hrs To 18.00 Hrs
Sign / Tanda tangan
Work Permit Holder /
Pemegang Izin Kerja
Authorized Person / PenanggungJawab
Check if applicable and explain below
3. Isolations / Isolasi  Electrical  Mechanical Jika ada mohon dijelaskan dibawah ini
………………………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………………………

Time and date isolated / Isolated by / Diisolasi Oleh: Position / Jabatan :


Jam danTanggal Isolasi:

………………………… ………………………………….. …………………………


4. Work Permit Requirement  JSA & Risk Assessment  Drawing Activity  Rigging Plan
/ Persyaratan Izin Kerja
 Work Method  As build Drawing  Underground Composite

(Check the hazards and the required precautions / Beri tanda pada bahaya dan
5. Hazards pencegahannya)

 Liquid/ gas under pressure / Cairan Gas  Confined spaces / Di dalam  Weather/ Cuaca  Fire / Kebakaran
bertekanan Ruang Terbatas  Electricity/  Toxins / Keracunan
 Explosion due to combustibles / Ledakan  Danger of falling / Bahaya Kelistrikan  Lifting Ops. /
dari material yang mudah terbakar Jatuh  Corrosives / Korosi Pengangkatan
 3rd party operations (explain below) /  Moving machinery /  Pinch points/  Scaffolding /
Aktifitas Kontraktor (Jelaskan dibawah) Peralatan / Mesin yang Terjepit Perancah
 Noise/ Kebisingan bergerak
 Flying particles or sparks/
Partikel terbang /Percikan
api
Other Hazards / BahayaLainnya
………………………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………………………

Precautions:  Airline (cascade)  Water flushing  Supervision  Grounding


 Fire Extinguishers /  Inert purging  Stand-by-man  Ventilation  PPE
APAR  H2S Monitoring  Safety harness  SCBA  Barriers
 Job Safety Analysis
(JSA)
BANYU URIP PROJECT
INFRASTRUCTURE FACILITIES EPC - 5

WORK PERMIT SYSTEM


Doc No. REV.
Health Safety Environment Page 2 of 3
IDBC-RH-SPZZZ-C00008 0

Other precautions / Pencegahan lainnya:


………………………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………………………………

6. Gas Testing / Pengetesan Gas


Oxygen / Oksigen H2S Flammable Gas / Gas mudah terbakar
Date Time Reading Date Time Reading Date Time Reading
Tanggal Jam Hasil Tanggal Jam Hasil Tanggal Jam Hasil

Gas Tester by / Pengetesan Gas dilakukan oleh :

Name / Nama : Sign / Tanda Tangan :

7. Work Permit Issued / Pengeluaran Surat Ijin Kerja 8. Authorization of Company (if required) / PenanggungJawab
The details of the permit have been discussed with the Permit Perusahaan (Jika diperlukan)
Holder and those involved / Surat ijin ini telah dibahas secara
rinci oleh Pemegang Ijin dan pihak -pihak yang terkait. Name / Nama :

Authorized Person / Penanggung Jawab _________________ Sign / Tanda tangan:

9. Issue and Acceptance / Pengeluaran dan Penerimaan Izin Kerja 10. Job Hand Over / Pengalihan Pekerjaan
I have checked the worksite and the required precautions have Permit Holder changed at /Perubahan Pemegang Izin pada
been taken and discussed with all involved / Saya telah
memeriksa area kerja dan pencegahan yang diperlukan dan telah …………………….…hours / jam ……………………….date / Tgl
dibahas oleh pihak-pihak terkait The in-coming Permit Holder and his workmen have been
satisfactorily briefed on all the hazards and precaution /
Pemegang ijin baru dan pekerjanya telah dijelaskan dengan rinci
tentang potensi Bahaya dan Pencegahannya

Outgoing Permit Holder / Pemegang Izin Lama :

-------------------------------------------------------------
Incoming Permit Holder / Pemegang Izin Baru :
Permit Holder / Pemegang Izin Kerja _________
---------------------------------------------------------------
11. De-Isolations /
Pelepasan Isolasi
 Electrical /  Mechanical / 12. Suspension of Permit / PenundaanpenggunaanSuratIzinKerja
Elektrik Mekanik I declare that the work for which this permit was issued has been
The electrical/mechanical isolations applicable to the Permit have temporarily suspended, all involved have withdrawn and the
now been removed / Isolasi Eektrik/Mekanik yang dipakai dalam izin area/ equipment has been left in a clean and safe state/ Saya
ini telah dihentikan menyatakan bahwa Surat Izin Kerja yang telah diterbitkan ini ditunda
BANYU URIP PROJECT
INFRASTRUCTURE FACILITIES EPC - 5

WORK PERMIT SYSTEM


Doc No. REV.
Health Safety Environment Page 3 of 3
IDBC-RH-SPZZZ-C00008 0

Electrician / Ahli Listrik ......................................................... pemakaiannya sementara waktu, semua pihak yang terkait ditarik,
semua peralatan dan area kerja ditinggalkan dalam kondisi bersih dan
aman
Mechanic / Ahli Mekanik ......................................................... Reason of suspension / Alasan Penundaan :

Isolator / Di isolasi oleh .........................................................


Authorization Person / Penanggung Jawab :

12. Work Completion / Penyelesaian pekerjaan 13. Permit Closure / Penutupan Izin Kerja
The above work has been completed. The worksite has been The work has been inspected and is complete. The Isolation have
left safe, clean, and tidy / Pekerjaan diatas dinyatakan selesai. been removed and the area is safe / Pekerjaan diatas telah diperiksa
Lokasi pekerjaan ditinggalkan dengan bersih, aman dan rapi dan selesai. Isolasi telah dihilangkan dan lokasi kerja dinyatakan
aman

………………………………..... …………………………
Authorized Person / Company (If Necessary) /
Permit Holder / Pemegang Izin Kerja ..................................... Penanggung Jawab Perusahaan jika perlu

Work Permit Extention Form / Form Perpanjangan Surat Izin Kerja


Sign
Date / Time / TandaTangan
No
Tanggal Jam Contactor Consortium General Client
Applicant HSE Superintendent Representative
07.00 –
1 18.00
07.00 –
2 18.00
07.00 –
3 18.00
07.00 –
4 18.00
07.00 –
5 18.00
07.00 –
6 18.00
07.00 –
7 18.00

Note :
Work Permit at any time may be revoked or reviewed if the performed does not
meet the requirements or provisions that safety required
Izin Kerja sewaktu-waktu dapat dicabut atau di tinjau ulang jika pekerjaan yang dilakukan
tidak memenuhi syarat atau ketentuan keselamatan yang disyaratkan