Harsh Bhadja - 9016282775

M.Tech - Structure

Quick Estimation

Sr. Item Rate Unit Unit Rate


No.
1 Project Cost (Including labour 1200 Rs./ft2 -
cost, material cost,including all
finishing work)
-
2 % of labour & Material -
Material Cost 65-70% of project cost - -
Labour Cost 30-35% of project cost - -
-
3 Sub-Structure Cost-Super -
Structure
Sub-Structure Cost 15-20% of project Cost - -
Super-Structure Cost 80-85% of project Cost - -
For upper Floors(above 10m) 10% increase in labour Lead -
cost for each floor
-
4 Tentative Steel Requirement -
Beam 100-150 Kg/m3 -
Column 250-350 Kg/m3 -
Slab 40-60 Kg/m3 -
Footing 40-60 Kg/m3 -
Raft 60-90 Kg/m3 -
Flat Slab 80-100 Kg/m3 -
-
5 For 1000 ft2 (93 mt2) -
Cement 350-400 Nos. Bags 280-320 Rs./bag
Steel 2-2.5 tonnes 40-45 Rs./kg
Bricks 30000-35000 Nos. 4.5-5 Rs./Nos
Kapachhi 9.35-9.91 mt3 750 Rs/tonne
Grit 5.1-5.66 mt3 650 Rs./tonne
Sand 34-35.42 mt3 450 Rs/tonne
-
6 Dumper Capacity -
Kapachhi (20 mm) 16 tonnes -
Grit (10 mm) 18 tonnes -
Sand 22-24 tonnes -
Steel 22-25 tonnes -
-
-
7 Plaster-20 mm (10 mt2) -
Cement 1.25 Bags -
Sand 0.28 mt3 -
Plaster-12 mm (10 mt2) -
Cement 1 Bags -
Sand 0.2 mt3 -