Académique Documents
Professionnel Documents
Culture Documents
GRAMODAYA VISHWAVIDYALAYA
ON
“BUILDING CONSTRUCTION”
TAKEN AT
In Civil Engineering
Rajat Sharma(154829)
Rajeev Dwivedi(154830)
Rishabh Pandey(154831)
INTRODUCTION:- Construction of residential building is in process at
“Airport road”, Gwalior(M.P.) under Private company & contract of this
building is taken by “Shiv Narayan Construction Co., Gwalior(M.P.)
Surveyors are among good company, working closely with their peers in
the fields of engineering, architecture, geology & planning. Their role
underpins these industries. Surveyors are the first people on any
construction site, measuring & mapping the land. These primary
measurements are then used by architects to understand and make the
most of the unique landscape when designing & engineers to plan
structures accurately and safely, ensuring buildings not only fit with the
landscape but are able to be constructed.
INSPECTION OF SOIL:-
How to calculate safe bearing capacity of soil on site?
This simple and quick field test will give you a rough idea of bearing capacity
of soil.
PROCEDURE:-
Calculation:-
Calculate the ultimate resistance of soil (R) using the formula
given below.
R= (w*h)/d
Where,
R= Ultimate resistance of soil (in kg)
d= Average depth of impression (in cm)
w= Weight of the solid ball or square cube (in kg)
h= Height of fall f solid ball o cube (in cm)
If “A” is the cross sectional area of the solid steel ball or cube,
then resistance of soil per unit area is calculated using following
formula.
Resistance of soil per unit area (in kg/cm²)= R/A
Safe bearing capacity (in kg/cm ²)= R/(A*F.O.S.)
Where,
F.O.S.= Factor of safety
Notes To Remember:-
1. F.O.S. varies from 2 o 3 depending upon the type of the structure &
site condition.
2. In order to get reliable test result, perform this test on different types
of soil & then use your judgment to reach at any conclusion.
3. Instead of using solid steel ball or square cube, we can also use CBR
test plunger, or cone (used for cone penetration test).
Excavation Of Land
Excavation is the process of moving earth, rock or other materials with
tools, equipments or explosives. It includes earthwork, trenching, wall
shafts, tunneling & underground. Excavation has a number of
important applications including exploration, environmental
restoration, mining & construction. Among these, construction is one
of the most common applications for excavation. Excavation is used in
construction to create building foundations, reservoirs & roads. Some of
the different processes used in excavation include trenching, digging,
dredging & site development. Each of these process requires unique
techniques, tools & machinery to get the job done right. The processes
used upon the structure that will result from the construction process.
Before the excavation process can begin, the site must be carefully
examined to make sure the natural habitat & artifacts surrounding it are
preserved throughout excavation. Next, the plans for the size & depth of the
site are made & the excavation company makes drawings from them to
clearly mark the excavation site’s boundaries. Once these two important
steps have been taken, the excavation work can begin. The entire
excavation process includes:-
Remove all the loose earth from the pits. Do water sprinkling & ramming
the cleaned surface of pit by mechanical rammer. Do the shuttering by
planks & runners wherever if necessary. Mix the concrete with required
proportion & water cement ratio by mechanical mixer machine & place the
same in to pits. Poured surface to be rammed& finished smoothly.Then RCC
mat of size (4*4) sq.ft with 16 no. 10mm bars is laid.
Construction of Footing
Footings are an important part of foundation construction. They are
typically made of purpose of footings is to support the foundation &
prevent setting. Footings are especially important in areas with
troublesome soils.
The construction of footings is best left to the pros that can assess the soil
conditions & decide on the proper depth & width for the footings as well as
the proper placement. The dimensions of footings also depend on the size &
type of structure that will be built. Placement of footings is crucial to
provide the proper support for the foundation & ultimately the structure.
Concrete footings also may also be needed for projects such as deck,
pergola, retaining wall or other types of construction.Footing of cross
section(9*9) sq.inch is generally provided with 18 inch tapered and
concrete mix of 1:1.5:3 is used.
.
Types of Footing:-
There are different types of footings which are used on the basic of soil &
type of structure.
There are many different kinds of foundations, see our page on types of
foundations for more information.
Since the weight of the building rests on the soil (or rock), engineers have
to study the properties of the soil very carefully to ensure that it can carry
the loads imposed by the building. It is common for engineers to determine
the safe bearing capacity of the soil after such study. As the name
suggests, this is the amount of weight per unit area the soil can bear. For
example, the safe bearing capacity (SBC) at a location could be 20T/m², or
tones per square meter. This figure is the maximum the soil can bear, so an
engineer will take pains to see that her design does not exceed this figure in
any part of the building.
This capacity also changes at different depths of soil. In general, the deeper
one digs, the greater the SBC, unless there are pockets of weak soil in the
earth. To properly support a building, the soil must be very firm & strong. It
is common for the soil near sink into the earth like a ship in water. Building
contractors will usually dig until they reach very firm, string, soil that
cannot be dug up easily before constructing a foundation.
Types of Foundations:-
Broadly speaking, all foundations are divided into two categories:-
‘Shallow Foundation’ & ‘Deep Foundation’. The words shallow & deep
foundation refer to the depth of soil in which the foundation is made.
Shallow foundations can be made in depth of as little as 3ft(1m), while deep
foundations can be made at depths of 60-200ft(20-65m). Shallow
foundations are used for small, light buildings, while deep foundations ones
are for large, heavy buildings.
1. Shallow Foundation:- Shallow foundations are also called spread
footings or open footings. The ‘open’ refers to the fact that the
foundations are made by first excavating all the earth till the bottom
of the footing, & then constructing the footing. During the early stages
of work, the entire footing is visible to the eye, & is therefore called
an open foundation. The idea is that each footing is visible to the eye,
& is therefore called an open foundation. The idea is that each footing
is takes the concentrated load of the column & spread it out over a
large area, so that the actual weight on the soil does not exceed the
SBC of the soil.
· Individual footing
· Strip footing
· Raft footing
In cold climates, shallow foundations must be protected from freezing.
This is because water in the soil around the foundation can freeze &
expand, thereby damaging the foundation. These foundations should be
built below the frost line, which is the level in the ground above which
freezing occurs. If they cannot be built below the frost line, they should
be protected by insulation: normally a little heat from the building will
permit to the soil & prevent freezing.
Individual footings are usually connected by a plinth beam, a horizontal
beam that is built at ground or below ground level.
Raft foundation:- It is also known as Mat footing, are most often used
when basement are to be constructed. In a raft, the entire basement floor
slab acts as the foundation, the weight of the building is spread evenly over
the entire footprint of the building. It is caled a raft because the building is
like a vessel that ‘floats’ in a sea of soil.
Mat foundations are used where the soil is week, & therefore building loads
have to be spread over a large area, or where columns are closely space,
which means that if individual footings were used, they would touch each
other.
· Backfilling of Soil:-The ground over which the filling has to be
done should be cleaned off all grass, loose stones, rubbish of all kinds
etc. If there is water in the area, it should be pumped or bailed out.
· If the plinth depth doesn’t exceed 45cm above ground level & if the
exposed ground is B.C. soil, then remove the B.C. soil completely to
avoid uneven settlement of the flooring.
· Select the refiling in the plinth & ijn pits. Judge the quantity of
material available.
· Place the order fornany further refilling material required.
· Engage laborers for refilling.
· Keep all tools for refilling & compaction ready.
Filling, consolidation & compaction:-
· The sides of concrete & masonry in foundation trenches or in the
column pits should be filled with suitable excavated material. Filling
should be done in layers, & compacted with steel rammer or wooden
logs.
· The approved excavated material, which has been stocked, shall be
cleaned of all rubbish, large size stone, vegetation etc.
· Filling should be layers each layer being of 15-20cm.
· Each layer is watered & compacted with heavy rammers of wooden
logs or steel.
· If the area of refilling is large then either electric operated or fuel
operated compactors are used to compact the filling material.
· The process of filling in plinth, watering & compaction shall be
carried out till the required level is reached so as to form a
thoroughly compacted base.
· While compacting due care is taken to protect the foundation
columns, pinth walls, etc., which are already constructed.
· If the depth of filling exceeds more than 1m then for economicy
purpose building rabbit may be allowed as a filling material for
further depth, the procedure being the same.
· Under no circumstances black cotton soil shall be used for filing in
plinth & footing pits.
Plinth of structure:-
The foundation & plinth are the primary elements to safe guard a
building.
Beam is placed over the foundation i.e. at plinth level. The beam is built
up at ground level. The condensed soil is used to fill the empty space
between the foundation & plinth level.Brick or stone masonry is
generally developed under the plinth beam.
Once the beam has been analysed for the envisaged loading conditon it is
designed following the guidlines of beam design. The general steps are
listed below:-
d= (factored moment)/(Rb)
Ast = fck/(2fy)*(1-1-4.598R/fck)bd
From the above equation we would get the area of tension steel.
NOTE: Providing Lshape joint in beam to reduce the stress produced at the
joint T of beam.
L shape bars
Mainly L shape bars are connected to resist the earthquake. In case of
Cantilever beam extra bars are provided on upper side because tension
acts on upper side.
In lower base 16mm extra bar is provided & on slab beam 16mm upper &
lower bars are provided.
Double rods are provided on upper side are provided on upper side
when point load act on beam & parallel balancing beams are provided on
lower side.
BEAMS:- Plinth beams are similar to roof beams except that in designing
the plinth beam only the wall load has to be considered as there is no other
live load acting over it. For roof 10 mm main bars are used in long direction
with spacing of 6 inch centre to centre and 10 mm distributed bars are
used in short direction with spacing of 8 inch.Main bars are kept bigger
than short wall of room and crank is formed on L/4 length.Cranks are
formed to distribute point load uniformly over large area.Beams of cross
section 9inch*9inch is used with a length of 10ft -12ft, 1ft*9inch is used
with a length of 12ft-16ft,15inch*9inch is used with a length of 18ft.
Construction of column:-
RCC is the acronym of Reinforced Cement Concrete which is known as
structural member of RCC framestructured building. Generally it is a
verticalmember that transmits load from slab& beamright away posterior
soil.
We all know that column is the main backbone of a building. If any kind of
column failure happens then the entire buiding collapses.
Basically this failure takes place not because of the design fault; actually it
happens owing to the inferior construction practice. That is why it is
mandatory to have the proper knowledge of the construction method of
RCC column.
RCC column construction process comprises of the four steps that are
described below briefly:
1. Column layout work: This is the very first step of the RCC column
construction method. The placements of thee columns are considered
substantially in the worksite. It is perfomed by laying rope in
accordance with grids as shown in the drawing & finally note the
location of the columns with respect to rope
2. Column Reinforcement work: After column location marking task,
then the next step that comes is the placement of reinforcement as
per the structural drawing.
· The drawing description is as follows:
C1- 12#16mmø & stirrup- 10mmø@4”c/c.
This indicates that column C1 will consists of 12 numbers of 16mm
diameter bar as vertical bar & 10mm diameter steel should be located
4inch center to center as stirrup.
with bottom one-fourth height of columns clear height will hold stirrups at
load is born by columns & the floor area/ internal space of building is freely
bars are used for less than 10 ft centre to centre distance.Above 10 ft centre
cover is provided.Middle bar and end bars spacing distance is 3.5 inch and
The cement concrete ratio & numbers of steel bars with their diameter are
available in structural drawings which are designed according to the
Construction of wall:-
walls protect the building interior from external environmental effects such
as heat & cold, sunlight, ultravoilet radiation, rain, snow & sound whie
time, such as a one hour wall. Walls often contain doors a& windows, which
Walls are designed to be strong enough to safely resist the horizontal &
vertical forces imposed upon them, as defined by building codes. Such loads
include wind forces, self-weight, possibly the weights of walls & floors from
& humidity variations as well as by certain impacts, & the wear & tear of
interior occupancy.
reinforced concrete, studs & sheating & composite types. The design loads
in bearing walls are the vertical loading from above, plus horizontal loads,
both perpendicular & parallel to the wall plane. Bearing walls must be
those used for bearing walls. These walls can also compromise assemblies
each laterally supported by light subfaming members. The curtain wall can
construction used in both bearing & curtain walls. They are designed in
Reinforced concrete walls are used for both strength & esthetic purposes.
Such walls may be cast in place or precast, & they may be bearing or curtain
walls. Some precast concrete walls. Some precast concrete walls are
are more commonly used for floor or roof deck construction. They are
Stud & sheating walls are a light type of wall construction, commonly used
bearing walls. They usually consist of wood sheat hing nailed to wood or
(5×15cm) & spaced at 16in. (40cm) or 24in. (60cm) on center all common
building module dimensions. The interior sides of the studs are usually
Prefabricated walls are commonly used for curtain wall construction & are
spaced severa feet apart. Prefab walls are often made of sandwich
effective sandwhich wal. These usually have tongue & groove vertical edges
to permit sealed joints whenthe units are erected at the building site by
Glass, metal or ceremic coated metal panel walls are a common type of
curtain wal used in high rise construction. They are typically assembled as
the outside, & some form of liner, including possibly masonry, on the
Tilt up walls are sometimes used for construction efficiency. Here, a wall of
Interio partitions are a lighter form of wall used to separated interior areas
of the standard wall types; & they are often designned for some resistance
to fire & sound. Retaining walls are used as exterior walls of basements to
resists out side soil pressure. They are usually of reinforced concrete;
however, where the basement depth or evterior soil height is low, the wall
MASONRY:-
Masonry is the building of structures from individual units, which are often
laid in & bound together by mortar; the term masonry can also refer to the
concrete block, glass block & adobe. Masonry is generally a highly durable
form of construction. However, the materias used, the quality of the mortar
& workmanship, & the pattern in which the units are asembled can
Masonry is commonly used for walls & buildings. Brick & concrete block
are the most common types of masonry in use in industriaised nations &
structures with light transverse loading when the cores remain unfilled.
Filling some or all of the cores with concrete or concrete with steel
strength to structures.For 9 inch wall cement plaster of mix 1:8 is used and
bricks). Each row of bricks is known as a course. The pattern of headers &
the flemish bond (with alternating stretcher & header bricks present on
every course). Bonds can differ in strength & in insulating ability. Vertically
typical. In the periosd since then this style was thought to be too sterile, so
attempts were made to emulate older, rougher work. Some brick surfaces
are made to look particularly rustic by including burnt bricks, which have a
darker color or an irregular shape. Others may use antique salvage bricks,
much larger than ordinary bricks & so are much larger than ordinary bricks
& so are much faster to lay for a wall of given size. Cinder & concrete blocks
typically have much lower water absorption rates than brick. They often
are used as the structural core for veneered brick masonry, or are used
alone for the walls of factories, garages & other industrial sttyle buildings
application & can impart extra strength to a block wall. Surface bonding
SLABS
(100 & 500mm) thick, are most often used to construct floors & ceilings,
while thinner slabs are also used for exterior paving. Sometimes these
thinner slabs, ranging from 2in. (51mm) to 6in. (150mm) thick, are called
mud slabs, particularly when used under the main floor slabs. In many
slabs. In high rise building & sky scrapper, thinner, precast concrete
slabs are slung between the steel frames to form the floors & ceilings on
each level.
Reinforcement design:
short direction because the moment along long axes is so small that it
directions. If the ratio of the lengths of long & short side is less than
steel tray. This improves strength & prevents the slab from bending
under its own weight. The corrugations run across the short
slabs are built in a factory & transported to the site, ready to be lowered
(in the factory), post-stressed (on site), or unstressed. It is vital that the
type of boxing into which the wet concrete is poured. If the slab is to be
reinforced, the rebars are positioned within the form work before the
concrete is poured in. Plastic tipped metal, or plastic bar chairs are used
to hold the rebar away from the bottom & sides of the form work, so that
ground slab, the form work may consist only of sidewalls pushed into
the ground. For a suspended slab, the forrm work is shaped like a tray,
The form work is commonly built from wooden planks & boards,
plastics, or steel. On commercial building sites today, plastic & steel are
more common as they save labour. On low budget sites, for intance
when laying a concrete garden path, wooden planks are very common.
After the concrete has set the wood may be removed, or left there
permanently.
Thermal performance:-
There are two main thermal considerations. The first is the question of
However, there are still uses for a slab that is not insulated, typically in
those cases, casting the slab directly onto a rocky substrate will
walls & floors, or wherever the concrete is used within the thermal
slab acts as a regulator, keeping the building cool by day & warm by
night.
trucks. To prepare the base, cut the ground level to the proper depth
perhaps 2feet deep. The rest of the slab is 4 or 6in. Thick. A 4 or 6in.
Layer of gravel lies beneath the sab. A 4mm sheet of plastic lies
Suspended slabs are above ground level slabs which are not
directly in contact with the earth. They are commonly used to create
floors for the upper storeys of houses, but can alo be sat on top
CURING
When the concrete is placed & compacted, bleeding of water occurs & rises
through the surface of concrete due to settlement of concrete. The rate &
concreteetc.
partially cured within a week (keep the cement free & clear of heavy
Methods:-
· Sprinkling of water
· Ponding method
· Steam curing
Sprinkling of water:-
efficient curing. It is mostly used for curing floor slabs. The concrete
sprinkling of water may be done by hand. Vertical & sloping surfaces can
Membrane Curing:-
The method of curing described above come under the category of moist
papers, wax emulsions, bitumen emulsions & plastic films are the
scratching tools, utility knives, lath nails, lime, sand hair, plaster of
washes.
LATHS:- Traditionally, plaster waslaid onto laths, rather than
five feet to suit the distance at which the timbers of a floor or partittion
are set. Laths are about an inch wide & are made in three thickness;
1 3 1
single ( 𝑡𝑜 𝑖𝑛𝑐ℎ 𝑡ℎ𝑖𝑐𝑘), lath & a half ( 𝑖𝑛𝑐ℎ 𝑡ℎ𝑖𝑐𝑘) & double
8 16 4
3 1
( 𝑡𝑜 𝑖𝑛𝑐ℎ 𝑡ℎ𝑖𝑐𝑘).
8 2
The thicker laths should be used in ceilings, to stand the extra strain
(somtimes they were doubled for extra strength) & the thinner variety
in vertical work such as rough usage, in which case thicker laths become
necessary. Laths are usually nailed with a space of about 3/8 of an inch
Laths were formerly all made by hand. Most are now made by
machinery & are known as sawn laths, those made by hand being called
rent or riven laths. Rent laths give the best results, as they split in a line
wth the grain of the wood & are stronger & not so liable to twist as
machine-made laths, some of the fibers of which are usually cut in the
process of sawing.
Lime plastering:- It is composed of lime, sand, hair & water in
lime mortar principally used for internal plastering is that calcined from
chalk, oyster shells or other nearly pure limestone, & is known as fat,
pure, chalk or rich lime. Hydraulic limes are also used by the plasterer,
but chiefly for external work. Perfect slaking of the calcined lime before
will “blow” when in position & blister the work. Lime should therefore
be run as soon as the building is begun, & at least three weeks should
elapse between the operation of running the lime & its use.
car. Hair functions in much the same way as the strands in fiberglass
resin, by controlling & containing any small cracks within the mortar
The chemical reactions between cement & water produces C-S-H gel
which bonds the ingredients of concrete, viz. Coarse & fine aggregates,
mineral admixtures etc. & converts these fragments into a rock solid
left to the decision & comfort of the unskilled laborer. Site engineers &
available at site. Just as anew born baby, when it comes into this world
needs the outmost care for its development & protection from this new
adopting good curing practices at site will help concrete to achieve the
Specimens:
Three numbers of whole bricks from sample collected should be taken. The
Sampling:
24hours. Remove the frog & all voids in the bed faces flush with
cement mortar (1 cement, 1 clean coarse sand of grade 3mm & down).
Store it under the damp jute bags for 24 hours filled by immersion in
clean water for 3 days. Remove & wipe out any traces of moisture.
CALCULATIONS
i.) A set of IS Sieve of size- 80mm, 63m, 50mm, 40mm, 31.5mm, 25mm,
20mm, 16mm, 12.5m, 10mm, 6.3mm, 4.75mm, 2.36mm, 1.18mm,
600µm, 300µm, 150µm & 75µm.
ii.) Balance or scale with an accuracy to measure 0.1% of the test
weight.
Procedure to determine particle size distribution of aggregates: