Académique Documents
Professionnel Documents
Culture Documents
Bureau : DPWH
Region : IX
District : Zamboanga del Norte 2nd DEO
INDIVIDUAL PROGRAM OF WORKS
(For All Types of Project)
Date :
GRAM OF WORKS
es of Project)
2,500,000.00
FY 2018(GAA)
By Contract
Calendar Days
Upon Approval
SED BUILDING
No.
1
1
1
1
1
1
3
4
F PROPOSED WORK
DIRECT COST
UNIT COST
Department of Public Works and Highways
Bureau : DPWH
Region : IX
District : Zamboanga del Norte 2nd DEO
Date :
PROJECT CATEGORY:
BUILDING
PROJECT DESCRIPTION:
Scope of Work : Construction One Unit 3 Classroom Building
803 Excavation of Footing and Wall Footing 1.51 Cu. M. 198.73 99,044.00
404 (a) Reinforcing Steel Column Footing 1.29 Kgs. 1,394.00 84,728.53
404(b) Reinforcing Steel for Wall Footing 0.13 Kgs. 127.92 8,637.20
404 (e) Reinforcing Steel for Slab on Fill 0.98 Kgs. 1,032.30 64,707.06
404 (f) Reinforcing Steel for Footing Tie Beam 4.30 Kgs. 4,878.07 282,609.89
404 (g) Reinforcing Steel for Stairs 0.69 Kgs. 780.68 45,449.72
404 (h) Reinforcing Steel for Suspended Slab 2.86 Kgs. 2,960.00 187,856.16
404 (i) Reinforcing Steel for Sunbreaker 0.23 Kgs. 236.80 14,985.36
1002-a Plumbing Works (Septic Vault & Area Drain) 1.67 L.S. 1.00 109,569.00
1010(a) Door & Window Frames Accessories 1.10 L.S. 1.00 72,127.20
1010(b) Doors 1.07 Sets 23.00 70,197.42
1032 (a-3) Steel & Roof Painting 0.53 Sq.M. 696.40 35,112.72
SPL-2 Steel for Fire Excape Stair 1.08 L.S 1.00 71,308.08
100.00 6,572,627.59
c Works and Highways
DPWH
IX
Zamboanga del Norte 2nd DEO
OGRAM OF WORKS
es of Project)
2,802,592.44
By Contract
Calendar Days
Upon Approval
LDING
498.38
118.10
794.88
938.29
5,150.52
5,665.61
7,251.01
5,741.44
5,301.24
5,367.50
7,560.96
6,910.57
10,160.29
87.73
60.78
67.52
56.37
55.83
62.68
57.93
58.22
63.46
63.28
874.26
30.41
65,416.00
109,569.00
206,284.80
1,309.87
72,127.20
3,052.06
845.26
150.17
696.44
1,547.78
141.42
138.46
36.88
61.00
50.42
36,409.00
99,842.48
9,503.96
72,731.60
3,939.07
71,308.08
3,573.27
49,183.08
7,500.00
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 198.73
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Unskilled Labor 4
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
D UNIT PRICE ANALYSIS (DUPA)
50 P 611.92 P 30,596.00
50 342.24 68,448.00
Sub-Total: P 99,044.00
Sub-Total: P -
I. Total Cost
P 99,044.00
498.38
6.61 % of D 6,543.95
8.00 % of D 7,923.52
(D+F+G+H) P 119,187.05
I/Qty P 599.74
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 169.67
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Unskilled Labor 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
D UNIT PRICE ANALYSIS (DUPA)
21 P 611.92 P 12,850.32
21 342.24 7,187.04
Sub-Total: P 20,037.36
Sub-Total: P -
I. Total Cost
P 20,037.36
118.10
6.61 % of D 1,323.89
8.00 % of D 1,602.99
(D+F+G+H) P 24,112.45
I/Qty P 142.11
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 31.25
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Unskilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
2 P 611.92 P 1,223.84
2 342.24 1,368.96
Sub-Total: P 2,592.80
Sub-Total: P -
I. Total Cost
P 24,840.80
794.88
6.61 % of D 1,641.26
8.00 % of D 1,987.26
(D+F+G+H) P 29,892.79
I/Qty P 956.54
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 31.25
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Labor 1
c. Unskilled Laborers 4
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Embackment
3 P 611.92 P 1,835.76
3 443.20 1,329.60
3 325.68 3,908.16
Sub-Total: P 7,073.52
Sub-Total: P -
I. Total Cost
P 29,321.52
938.29
6.61 % of D 1,937.31
8.00 % of D 2,345.72
(D+F+G+H) P 35,284.78
I/Qty P 1,129.11
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 22.82
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Labor 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Sand Cu.m.
c. Gravel Cu.m.
D UNIT PRICE ANALYSIS (DUPA)
26 P 611.92 P 15,909.92
26 443.20 11,523.20
26 342.24 8,898.24
Sub-Total: P 36,331.36
Sub-Total: P -
I. Total Cost
P 117,555.36
5,150.52
6.61 % of D 7,767.02
8.00 % of D 9,404.43
(D+F+G+H) P 141,463.15
I/Qty P 6,198.00
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 2.89
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Sand cu.m.
c. Gravel cu.m.
D UNIT PRICE ANALYSIS (DUPA)
RC wall Footing
Sub-Total: P 4,365.60
I. Total Cost
P 16,373.60
5,665.61
6.61 % of D 1,081.82
8.00 % of D 1,309.89
(D+F+G+H) P 19,703.58
I/Qty P 6,817.85
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 33.18
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Labor 3
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Sand cu.m.
c. Gravel cu.m.
Sub-Total: P 102,388.48
Sub-Total: P -
I. Total Cost
10 520.00 5,200.00
Sub-Total P 138,200.00
P 240,588.48
7,251.01
6.61 % of D 15,895.96
8.00 % of D 19,247.08
(D+F+G+H) P 289,518.10
I/Qty P 8,725.68
*DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 49.38
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Labor 3
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Sand cu.m.
c. Gravel cu.m.
D UNIT PRICE ANALYSIS (DUPA)
Sub-Total: P 84,907.52
I. Total Cost
5 80.00 400.00
10 520.00 5,200.00
Sub-Total P 198,605.00
P 283,512.52
5,741.44
6.61 % of D 18,732.01
8.00 % of D 22,681.00
(D+F+G+H) P 341,171.80
I/Qty P 6,909.11
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 31.54
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Laborers 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Sand cu.m.
c. Gravel cu.m.
D UNIT PRICE ANALYSIS (DUPA)
Sub-Total: P 41,571.84
Sub-Total: P -
I. Total Cost
P 167,179.84
5,301.24
6.61 % of D 11,045.77
8.00 % of D 13,374.39
(D+F+G+H) P 201,180.00
I/Qty P 6,379.38
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 23.36
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Laborers 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Sand cu.m.
c. Gravel cu.m.
D UNIT PRICE ANALYSIS (DUPA)
Sub-Total: P 31,178.88
Sub-Total: P -
I. Total Cost
P 125,384.88
5,367.50
6.61 % of D 8,284.33
8.00 % of D 10,030.79
(D+F+G+H) P 150,885.00
I/Qty P 6,459.12
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 4.49
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Laborers 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Sand cu.m.
c. Gravel cu.m.
Sub-Total: P 7,794.72
Sub-Total: P -
I. Total Cost
5 520.00 2,600.00
Sub-Total P 26,154.00
P 33,948.72
7,560.96
6.61 % of D 2,243.03
8.00 % of D 2,715.90
(D+F+G+H) P 40,853.03
I/Qty P 9,098.67
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 29.17
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Laborers 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Sand cu.m.
c. Gravel cu.m.
Sub-Total: P 51,964.80
Sub-Total: P -
I. Total Cost
33 520.00 17,160.00
Sub-Total P 149,582.00
P 201,546.80
6,910.57
6.61 % of D 13,316.43
8.00 % of D 16,123.74
(D+F+G+H) P 242,536.33
I/Qty P 8,316.01
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 2.33
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Laborers 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Sand cu.m.
c. Gravel cu.m.
R.C. Sunbreaker
Sub-Total: P 5,196.48
Sub-Total: P -
I. Total Cost
5 520.00 2,600.00
Sub-Total P 18,477.00
P 23,673.48
10,160.29
6.61 % of D 1,564.13
8.00 % of D 1,893.88
(D+F+G+H) P 28,488.07
I/Qty P 12,226.64
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 6,739.53
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
a. Welding Machine 2
C. Materials:
e. 1.5" x 1.5" x 3/16" x 500mm Angle Bar (Purlins Block) (7pcs) kgs.
Steel Trusses
39 P 611.92 P 23,864.88
39 443.20 69,139.20
39 342.24 26,694.72
Sub-Total: P 119,698.80
26 P 490.00 P 25,480.00
Sub-Total: P 25,480.00
I. Total Cost
Sub-Total P 422,295.12
P 567,473.92
84.20
6.61 % of D 37,493.67
8.00 % of D 45,397.91
(D+F+G+H) P 682,883.78
I/Qty P 101.33
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 6,739.53
No. of
Designation
Person
A. Labor:
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Steel Trusses
Sub-Total: P 0.00
Sub-Total: P -
Sub-Total (A + B): -
I. Total Cost
P 23,781.00
3.53
6.61 % of D 1,571.24
8.00 % of D 1,902.48
(D+F+G+H) P 28,617.45
I/Qty P 4.25
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1,394.00
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 19,478.16
Sub-Total: P -
I. Total Cost
Sub-Total P 65,250.37
P 84,728.53
60.78
6.61 % of D 5,598.11
8.00 % of D 6,778.28
(D+F+G+H) P 101,960.17
I/Qty P 73.14
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 127.92
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 2,996.64
Sub-Total: P -
I. Total Cost
P 8,637.20
67.52
6.61 % of D 570.67
8.00 % of D 690.98
(D+F+G+H) P 10,393.79
I/Qty P 81.25
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 14,964.96
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
89 P 611.92 P 54,460.88
89 443.20 118,334.40
Sub-Total: P 172,795.28
Sub-Total: P -
I. Total Cost
Sub-Total P 670,820.96
P 843,616.24
56.37
6.61 % of D 55,738.72
8.00 % of D 67,489.30
(D+F+G+H) P 1,015,186.47
I/Qty P 67.84
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 9,163.35
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 97,773.52
I. Total Cost
Sub-Total P 413,855.19
P 511,628.71
55.83
6.61 % of D 33,803.91
8.00 % of D 40,930.30
(D+F+G+H) P 615,681.06
I/Qty P 67.19
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1,032.30
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Steelman 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 19,478.16
Sub-Total: P -
I. Total Cost
P 64,707.06
62.68
6.61 % of D 4,275.27
8.00 % of D 5,176.56
(D+F+G+H) P 77,866.84
I/Qty P 75.43
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 4,878.07
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Steelman 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 65,926.08
Sub-Total: P -
I. Total Cost
Sub-Total P 216,683.81
P 282,609.89
57.93
6.61 % of D 18,672.37
8.00 % of D 22,608.79
(D+F+G+H) P 340,085.60
I/Qty P 69.72
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 780.68
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Steelman 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 10,488.24
Sub-Total: P -
I. Total Cost
Sub-Total P 34,961.48
P 45,449.72
58.22
6.61 % of D 3,002.92
8.00 % of D 3,635.98
(D+F+G+H) P 54,693.04
I/Qty P 70.06
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 2,960.00
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Steelman 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 56,936.16
Sub-Total: P -
I. Total Cost
P 187,856.16
63.46
6.61 % of D 12,411.88
8.00 % of D 15,028.49
(D+F+G+H) P 226,061.36
I/Qty P 76.37
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 236.80
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Steelman 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 4,494.96
Sub-Total: P -
I. Total Cost
P 14,985.36
63.28
6.61 % of D 990.10
8.00 % of D 1,198.83
(D+F+G+H) P 18,033.00
I/Qty P 76.15
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 597.00
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Mason 1
c. Unskilled Laborers 5
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Masonry Works(CHB)
Sub-Total: P 107,886.48
Sub-Total: P -
I. Total Cost
P 521,930.98
874.26
6.61 % of D 34,484.59
8.00 % of D 41,754.48
(D+F+G+H) P 628,078.55
I/Qty P 1,052.06
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 312.51
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
a. Unskilled Labor 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Soil Poisoning
Sub-Total: P 954.16
Sub-Total: P -
I. Total Cost
P 9,504.16
30.41
6.61 % of D 627.95
8.00 % of D 760.33
(D+F+G+H) P 11,437.07
I/Qty P 36.60
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Labor 3
c. Unskilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
a. Water Closet including Fittings & Accessories, American Std. or Equiv. nos.
Plumbing Works
5 P 611.92 P 3,059.60
5 443.20 6,648.00
5 342.24 3,422.40
Sub-Total: P 13,130.00
Sub-Total: P -
r. Solvent can
I. Total Cost
Sub-Total P 52,286.00
P 65,416.00
65,416.00
6.61 % of D 4,322.11
8.00 % of D 5,233.28
(D+F+G+H) P 78,719.96
I/Qty P 78,719.96
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Labor 3
c. Unskilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Sand cu.m.
c. Gravel cu.m.
Area Drain
D UNIT PRICE ANALYSIS (DUPA)
6 P 611.92 P 3,671.52
6 443.20 7,977.60
6 342.24 4,106.88
Sub-Total: P 15,756.00
P P 0.00
Sub-Total: P -
1.00
b. Sand cu.m.
c. Gravel cu.m.
I. Total Cost
Sub-Total P 93,813.00
P 109,569.00
109,569.00
6.61 % of D 7,239.35
8.00 % of D 8,765.52
(D+F+G+H) P 131,852.57
I/Qty P 131,852.57
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Laborers 3
c. Unskilled Laborers 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
1 Blackboards, 1.20mx2.40m
Carpentry
Sub-Total: P 42,418.80
Sub-Total: P -
I. Total Cost
Sub-Total P 127,946.00
P 170,364.80
170,364.80
6.61 % of D 11,256.20
8.00 % of D 13,629.18
(D+F+G+H) P 205,012.70
I/Qty P 205,012.70
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
No. of
Designation
Person
A. Labor:
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Carpentry
Sub-Total: P 0.00
Sub-Total: P -
Sub-Total (A + B): -
I. Total Cost
Sub-Total P 35,920.00
P 35,920.00
35,920.00
6.61 % of D 2,373.28
8.00 % of D 2,873.60
(D+F+G+H) P 43,225.22
I/Qty P 43,225.22
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 64.80
`
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 17,739.84
Sub-Total: P -
I. Total Cost
P 84,879.84
1,309.87
6.61 % of D 5,608.11
8.00 % of D 6,790.39
(D+F+G+H) P 102,142.25
I/Qty P 1,576.27
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
`
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 10,451.20
Sub-Total: P -
I. Total Cost
P 72,127.20
72,127.20
6.61 % of D 4,765.53
8.00 % of D 5,770.18
(D+F+G+H) P 86,796.05
I/Qty P 86,796.05
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 23.00
`
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Laborer 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. D-2 Hollow Core Flush Type Swing Door w/ Marine Plywood sets
c. D-3 Hollow Core Flush Type Swing Door w/ Marine Plywood sets
d. D-4 Hollow Core Flush Type Swing Door Size 2.10mx0.60m sets
D UNIT PRICE ANALYSIS (DUPA)
Doors
Sub-Total: P 12,743.92
Sub-Total: P -
I. Total Cost
Sub-Total P 57,453.50
P 70,197.42
3,052.06
6.61 % of D 4,638.03
8.00 % of D 5,615.79
(D+F+G+H) P 84,473.80
I/Qty P 3,672.77
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 405.76
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Laborer 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 29,448.96
Sub-Total: P -
I. Total Cost
Sub-Total P 313,522.00
P 342,970.96
845.26
6.61 % of D 22,660.49
8.00 % of D 27,437.68
(D+F+G+H) P 412,722.59
I/Qty P 1,017.16
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 353.03
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
No. of
Name and Capacity
Man-Days
B. Equipment:
C. Materials:
Roofing Insulation
Sub-Total: P 19,478.16
Sub-Total: P -
I. Total Cost
P 53,016.01
150.17
6.61 % of D 3,502.83
8.00 % of D 4,241.28
(D+F+G+H) P 63,798.13
I/Qty P 180.72
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 72.50
`
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
a. Tile Cutter 1
C. Materials:
200mmx200mmx6mm
Sub-Total: P 19,645.20
Sub-Total: P 4,500.00
I. Total Cost
Sub-Total P 26,347.00
P 50,492.20
696.44
6.61 % of D 3,336.08
8.00 % of D 4,039.38
(D+F+G+H) P 60,761.04
I/Qty P 838.08
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 22.00
`
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
a. Tile Cutter 1
C. Materials:
Flooring
Sub-Total: P 8,731.20
Sub-Total: P 2,000.00
I. Total Cost
Sub-Total P 23,320.00
P 34,051.20
1,547.78
6.61 % of D 2,249.80
8.00 % of D 2,724.10
(D+F+G+H) P 40,976.35
I/Qty P 1,862.56
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 613.66
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Laborer 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 37,107.60
Sub-Total: P -
I. Total Cost
P 86,785.60
141.42
6.61 % of D 5,734.03
8.00 % of D 6,942.85
(D+F+G+H) P 104,435.60
I/Qty P 170.18
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1,530.40
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Laborer 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 89,494.80
Sub-Total: P -
I. Total Cost
P 211,892.80
138.46
6.61 % of D 14,000.01
8.00 % of D 16,951.42
(D+F+G+H) P 254,986.44
I/Qty P 166.61
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 2,142.56
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Laborers/Painter 2
c. Unskilled Laborers 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Masonry Painting
Sub-Total: P 29,448.96
Sub-Total: P -
I. Total Cost
Sub-Total P 49,568.00
P 79,016.96
36.88
6.61 % of D 5,220.74
8.00 % of D 6,321.36
(D+F+G+H) P 95,087.01
I/Qty P 44.38
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 546.67
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Laborers/Painter 2
c. Unskilled Laborers 1
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Wooden Painting
Sub-Total: P 7,362.24
Sub-Total: P -
I. Total Cost
Sub-Total P 25,983.30
P 33,345.54
61.00
6.61 % of D 2,203.18
8.00 % of D 2,667.64
(D+F+G+H) P 40,127.18
I/Qty P 73.40
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 696.40
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Laborers 3
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 11,649.12
Sub-Total: P -
I. Total Cost
Sub-Total P 23,463.60
P 35,112.72
50.42
6.61 % of D 2,319.94
8.00 % of D 2,809.02
(D+F+G+H) P 42,253.76
I/Qty P 60.67
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Labor 2
c. Unskilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 10,914.00
Sub-Total: P -
I. Total Cost
P 36,409.00
36,409.00
6.61 % of D 2,405.59
8.00 % of D 2,912.72
(D+F+G+H) P 43,813.67
I/Qty P 43,813.67
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 20,976.48
P P 0.00
Sub-Total: P -
I. Total Cost
Sub-Total P 78,866.00
P 99,842.48
99,842.48
6.61 % of D 6,596.71
8.00 % of D 7,987.40
(D+F+G+H) P 120,147.92
I/Qty P 120,147.92
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Sub-Total: P 4,494.96
P P 0.00
Sub-Total: P -
1 1,627.00 P 1,627.00
1 682.00 682.00
6 375.00 2,250.00
1 450.00 450.00
D. Direct Cost (A+B+C)
I. Total Cost
P 9,503.96
9,503.96
6.61 % of D 627.94
8.00 % of D 760.32
(D+F+G+H) P 11,436.83
I/Qty P 11,436.83
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Skilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
Lightning Fixtures
Sub-Total: P 7,491.60
P P 0.00
Sub-Total: P -
I. Total Cost
P 72,731.60
72,731.60
6.61 % of D 4,805.46
8.00 % of D 5,818.53
(D+F+G+H) P 87,523.37
I/Qty P 87,523.37
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 34.00
`
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
a. Welding Machine 2
C. Materials:
Ramp Rail
Steel Railings
Sub-Total: P 19,645.20
9 P 490.00 P 8,820.00
Sub-Total: P 8,820.00
I. Total Cost
Sub-Total P 105,463.12
P 133,928.32
3,939.07
6.61 % of D 8,848.80
8.00 % of D 10,714.27
(D+F+G+H) P 161,165.96
I/Qty P 4,740.18
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
`
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
c. Unskilled Labor 2
No. of
Name and Capacity
Units
B. Equipment:
a. Welding Machine 2
C. Materials:
Sub-Total: P 13,096.80
6 P 490.00 P 5,880.00
Sub-Total: P 5,880.00
I. Total Cost
Sub-Total P 52,331.28
P 71,308.08
71,308.08
6.61 % of D 4,711.41
8.00 % of D 5,704.65
(D+F+G+H) P 85,810.34
I/Qty P 85,810.34
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 2.00
`
No. of
Designation
Person
A. Labor:
a. Construction Foreman 1
b. Unskilled Worker 2
No. of
Name and Capacity
Units
B. Equipment:
C. Materials:
b. Tarpaulin pc.
Project Billboard
Sub-Total: P 1,182.48
Sub-Total: P -
I. Total Cost
Sub-Total P 5,964.05
P 7,146.53
3,573.27
6.61 % of D 472.18
8.00 % of D 571.72
(D+F+G+H) P 8,599.95
I/Qty P 4,299.98
DETAILED UNIT PRICE ANALYSIS (DUPA)
Quantity : 1.00
`
No. of
Designation
Person
A. Labor:
b. First Aider 1
B. Equipment:
a. Helmet 3,535.38
b. Gloves 3,535.38
C. Materials:
Sub-Total: P 18,532.80
Sub-Total: P 29,150.28
I. Total Cost
P 49,183.08
49,183.08
% of D -
% of D -
(D+F+G+H) P 51,642.23
I/Qty P 51,642.23
PERSONAL PROTECTIVE EQUI
NO. OF MAN-DAYS
Item No. Safety Shoes Rubber Boots
803 250.00
804(a) 42.00
804(b) 6.00
804( c) 18.00
900(b) 10.00
900 ( c) 246.00
900(d) 49.38
404(b) 6.00
404( c) 356.00
404(d) 205.00
506(1) 273.00
1000a 2.00
1,002 30.00
1002-a 36.00
1,003 90.00
PERSONAL PROTECTIVE EQUIPMENT
NO. OF MAN-DAYS
Rubber Boots Helmet Working Gloves
250.00 250.00
42.00 42.00
6.00 6.00
18.00 18.00
273.00 273.00
39.00 39.00
6.00 6.00
356.00 356.00
205.00 205.00
52.00 52.00
176.00 176.00
28.00 28.00
152.00 152.00
12.00 12.00
273.00 273.00
90.00 90.00
1009(a) 24.00
1010(a) 20.00
1010(b) 21.00
1,013 64.00
1013.2.4 64.00
1013.2.4 39.00
1018(a) 45.00
1018(b) 20.00
1,021 85.00
1,027 205.00
1032(a-1) 64.00
1032(a-2) 16.00
1,100 25.00
1,102 9.00
1102(a) 15.00
SPL-1 45.00
SPL-3 3.00
20.00 20.00
21.00 21.00
64.00 64.00
64.00 64.00
25.00 25.00
9.00 9.00
15.00 15.00
45.00 45.00
3.00 3.00
Unit of Measurement : L. S.
Quantity : 1.00
`
No. of
Designation
Person
A. Labor:
No. of
Name and Capacity
Units
B. Equipment:
Demobilization
C. Materials:
D UNIT PRICE ANALYSIS (DUPA)
Mobilization/Demobilization
Sub-Total: P 0.00
P 7,500.00 P 7,500.00
Sub-Total: P 7,500.00
I. Total Cost
P 7,500.00
7,500.00
0.00 % of D -
0.00 % of D -
(D+F+G+H) P 7,875.00
I/Qty P 7,875.00
Department of Public Works and Highways (DPWH)
Contract ID :
Contract Name : Construction of a Multi-Purposed Building(Livelihood center)
BILL OF QUANTITIES
Part No. :
Part Description :
Pay
Unit Price
Item Description Quantity Unit
(Pesos)
No.
(1) (2) (3) (4) (5)
EARTHWORKS
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
In words: (Pesos)
Php:
Php:
Php:
Php:
Php:
(Pesos) In words: (Pesos)
Php:
Php:
Php:
Php:
Php:
Php:
Php:
Php:
(Pesos) In words: (Pesos)
Php:
Php:
Php:
Php:
Php:
Php:
Php:
Php:
(Pesos) In words: (Pesos)
Php:
Php:
Php:
Php:
Php:
Php:
Php:
Php:
(Pesos) In words: (Pesos)
Php:
Php:
Php:
Php:
Php:
Php:
Php:
Php:
(Pesos) In words: (Pesos)
Php:
Php:
Php:
Php:
Php:
Php:
Php:
Php: