Name of the work : Construction of 2 No Rapid Exit Taxiway (RET) for the main runway

07/25 and Straightening of B-taxiway as Parallel Taxi track for code -E aircraft at Chennai
International Airport , Chennai (Civil works)
Client Airports Authority Of India
Name of Agency RDS Project Ltd
Agreement No ENGG/ED-SR/SM(E-C)/Chennai/B-Taxi/2017/02

INDIVIDUAL GRADATION FOR DENSE BITUMINOUS MACADAM

Sample No 1
Date of Sampling 24/8/2018
Source Kadapperi,Tambaram
Location
Date of Testing 25/8/2018
Type of material 20 mm
Total Weight of Sample (gms) :

Weight Retained Cumulative Cumulative %


I.S.Sieve (mm) Cumulative % Passing
(gms) Weight Retained Retained

37.50 0 0 0 100
26.50 0 0 0 100
19.00 1648 1648 20.6 79.4
13.20 5090 6738 84.23 15.77
4.75 1258 7996 99.95 0.05
2.36
0.300
0.075

Remarks:

Contractor JE (E-C) AM/M (E-C) AGM (E-C)


Name of the work : Construction of 2 No Rapid Exit Taxiway (RET) for the main runway
07/25 and Straightening of B-taxiway as Parallel Taxi track for code -E aircraft at Chennai
International Airport , Chennai (Civil works)
Client Airports Authority Of India
Name of Agency RDS Project Ltd
Agreement No ENGG/ED-SR/SM(E-C)/Chennai/B-Taxi/2017/02

INDIVIDUAL GRADATION FOR DENSE BITUMINOUS MACADAM

Sample No 1
Date of Sampling 24/8/2018
Source Kadapperi,Tambaram
Location
Date of Testing 25/8/2018
Type of material 13.2 mm
Total Weight of Sample (gms) :

Weight Retained Cumulative Cumulative %


I.S.Sieve (mm) Cumulative % Passing
(gms) Weight Retained Retained

37.50 0 0 0 100
26.50 0 0 0 100
19.00 0 0 0 100
13.20 290 290 5.8 94.2
4.75 4500 4790 95.8 4.2
2.36 56 4846 96.92 3.08
0.300 148 4994 99.88 0.12
0.075

Remarks:

Contractor JE (E-C) AM/M (E-C) AGM (E-C)


Name of the work : Construction of 2 No Rapid Exit Taxiway (RET) for the main runway
07/25 and Straightening of B-taxiway as Parallel Taxi track for code -E aircraft at Chennai
International Airport , Chennai (Civil works)
Client Airports Authority Of India
Name of Agency RDS Project Ltd
Agreement No ENGG/ED-SR/SM(E-C)/Chennai/B-Taxi/2017/02

INDIVIDUAL GRADATION FOR DENSE BITUMINOUS MACADAM

Sample No 1
Date of Sampling 24/8/2018
Source Kadapperi,Tambaram
Location
Date of Testing 25/8/2018
Type of material 6.7 mm
Total Weight of Sample (gms) :

Weight Retained Cumulative Cumulative %


I.S.Sieve (mm) Cumulative % Passing
(gms) Weight Retained Retained

37.50 0 0 0 100
26.50 0 0 0 100
19.00 0 0 0 100
13.20 0 0 0 100
4.75 1858 1858 61.93 38.07
2.36 866 2724 90.8 9.2
0.300 138 2862 95.4 4.6
0.075 55 2917 97.23 2.77

Remarks:

Contractor JE (E-C) AM/M (E-C) AGM (E-C)


Name of the work : Construction of 2 No Rapid Exit Taxiway (RET) for the main runway
07/25 and Straightening of B-taxiway as Parallel Taxi track for code -E aircraft at Chennai
International Airport , Chennai (Civil works)
Client Airports Authority Of India
Name of Agency RDS Project Ltd
Agreement No ENGG/ED-SR/SM(E-C)/Chennai/B-Taxi/2017/02

INDIVIDUAL GRADATION FOR DENSE BITUMINOUS MACADAM

Sample No 1
Date of Sampling 24/8/2018
Source Kadapperi,Tambaram
Location
Date of Testing 25/8/2018
Type of material 2.36 mm
Total Weight of Sample (gms) :

Weight Retained Cumulative Cumulative %


I.S.Sieve (mm) Cumulative % Passing
(gms) Weight Retained Retained

37.50 0 0 0 100
26.50 0 0 0 100
19.00 0 0 0 100
13.20 0 0 0 100
4.75 0 0 0 100
2.36 398 398 39.8 60.2
0.300 374 772 77.2 22.8
0.075 126 898 89.8 10.2

Remarks:

Contractor JE (E-C) AM/M (E-C) AGM (E-C)


T) for the main runway
e -E aircraft at Chennai
)

US MACADAM

018

018

8000

Cumulative % Passing

100
100
79.4
15.77
0.05

AGM (E-C)
T) for the main runway
e -E aircraft at Chennai
)

US MACADAM

018

018

5000

Cumulative % Passing

100
100
100
94.2
4.2
3.08
0.12

AGM (E-C)
T) for the main runway
e -E aircraft at Chennai
)

US MACADAM

018

018

3000

Cumulative % Passing

100
100
100
100
38.07
9.2
4.6
2.77

AGM (E-C)
T) for the main runway
e -E aircraft at Chennai
)

US MACADAM

018

018

1000

Cumulative % Passing

100
100
100
100
100
60.2
22.8
10.2

AGM (E-C)
Name of the work : Construction of 2 No Rapid Exit Taxiway (RET) for the main runway
07/25 and Straightening of B-taxiway as Parallel Taxi track for code -E aircraft at Chennai
International Airport , Chennai (Civil works)
Client Airports Authority Of India
Name of Agency RDS Project Ltd
Agreement No ENGG/ED-SR/SM(E-C)/Chennai/B-Taxi/2017/02

INDIVIDUAL GRADATION FOR DENSE BITUMINOUS MACADAM

Sample No 1
Date of Sampling 24/8/2018
Source Kadapperi,Tambaram
Location
Date of Testing 25/8/2018
Type of material 20 mm
Total Weight of Sample (gms) :

Weight Retained Cumulative Cumulative %


I.S.Sieve (mm) Cumulative % Passing
(gms) Weight Retained Retained

37.50 0 0 0 100
26.50 0 0 0 100
19.00 1360 1360 17 83
13.20 4880 6240 78 22
4.75 1757 7997 99.96 0.04
2.36
0.300
0.075

Remarks:

Contractor JE (E-C) AM/M (E-C) AGM (E-C)


Name of the work : Construction of 2 No Rapid Exit Taxiway (RET) for the main runway
07/25 and Straightening of B-taxiway as Parallel Taxi track for code -E aircraft at Chennai
International Airport , Chennai (Civil works)
Client Airports Authority Of India
Name of Agency RDS Project Ltd
Agreement No ENGG/ED-SR/SM(E-C)/Chennai/B-Taxi/2017/02

INDIVIDUAL GRADATION FOR DENSE BITUMINOUS MACADAM

Sample No 1
Date of Sampling 24/8/2018
Source Kadapperi,Tambaram
Location
Date of Testing 25/8/2018
Type of material 13.2 mm
Total Weight of Sample (gms) :

Weight Retained Cumulative Cumulative %


I.S.Sieve (mm) Cumulative % Passing
(gms) Weight Retained Retained

37.50 0 0 0 100
26.50 0 0 0 100
19.00 0 0 0 100
13.20 308 308 6.16 93.84
4.75 4560 4868 97.36 2.64
2.36 47 4915 98.3 1.7
0.300 74 4989 99.78 0.22
0.075

Remarks:

Contractor JE (E-C) AM/M (E-C) AGM (E-C)


Name of the work : Construction of 2 No Rapid Exit Taxiway (RET) for the main runway
07/25 and Straightening of B-taxiway as Parallel Taxi track for code -E aircraft at Chennai
International Airport , Chennai (Civil works)
Client Airports Authority Of India
Name of Agency RDS Project Ltd
Agreement No ENGG/ED-SR/SM(E-C)/Chennai/B-Taxi/2017/02

INDIVIDUAL GRADATION FOR DENSE BITUMINOUS MACADAM

Sample No 1
Date of Sampling 24/8/2018
Source Kadapperi,Tambaram
Location
Date of Testing 25/8/2018
Type of material 6.7 mm
Total Weight of Sample (gms) :

Weight Retained Cumulative Cumulative %


I.S.Sieve (mm) Cumulative % Passing
(gms) Weight Retained Retained

37.50 0 0 0 100
26.50 0 0 0 100
19.00 0 0 0 100
13.20 0 0 0 100
4.75 1695 1695 56.5 43.5
2.36 1022 2717 90.57 9.43
0.300 172 2889 96.3 3.7
0.075 42 2931 97.7 2.3

Remarks:

Contractor JE (E-C) AM/M (E-C) AGM (E-C)


Name of the work : Construction of 2 No Rapid Exit Taxiway (RET) for the main runway
07/25 and Straightening of B-taxiway as Parallel Taxi track for code -E aircraft at Chennai
International Airport , Chennai (Civil works)
Client Airports Authority Of India
Name of Agency RDS Project Ltd
Agreement No ENGG/ED-SR/SM(E-C)/Chennai/B-Taxi/2017/02

INDIVIDUAL GRADATION FOR DENSE BITUMINOUS MACADAM

Sample No 1
Date of Sampling 24/8/2018
Source Kadapperi,Tambaram
Location
Date of Testing 25/8/2018
Type of material 2.36 mm
Total Weight of Sample (gms) :

Weight Retained Cumulative Cumulative %


I.S.Sieve (mm) Cumulative % Passing
(gms) Weight Retained Retained

37.50 0 0 0 100
26.50 0 0 0 100
19.00 0 0 0 100
13.20 0 0 0 100
4.75 0 0 0 100
2.36 372 372 37.2 62.8
0.300 362 734 73.4 26.6
0.075 138 872 87.2 12.8

Remarks:

Contractor JE (E-C) AM/M (E-C) AGM (E-C)


T) for the main runway
e -E aircraft at Chennai
)

US MACADAM

018

018

8000

Cumulative % Passing

100
100
83
22
0.04

AGM (E-C)
T) for the main runway
e -E aircraft at Chennai
)

US MACADAM

018

018

5000

Cumulative % Passing

100
100
100
93.84
2.64
1.7
0.22

AGM (E-C)
T) for the main runway
e -E aircraft at Chennai
)

US MACADAM

018

018

3000

Cumulative % Passing

100
100
100
100
43.5
9.43
3.7
2.3

AGM (E-C)
T) for the main runway
e -E aircraft at Chennai
)

US MACADAM

018

018

1000

Cumulative % Passing

100
100
100
100
100
62.8
26.6
12.8

AGM (E-C)
COMBINED PROPORTION OF DBM AGGREGATES :

Aggregate % to be mixed
20 mm 33%
13.2 mm 5%
6.7 mm 17%
2.36 mm 43%
Filler 2%
TOTAL 100%

20 mm 13.2 mm 6.7 mm 2.36 mm Filler DBM


Sieve
Avg % Avg % Avg % Avg % Avg % % to be Upper Lower
Size in Limits
passing passing passing passing passing mixed limit Limit
mm
37.5 100 100 100 100 100 100.00 100 100 100
26.5 100 100 100 100 100 100.00 90-100 100 90
19.0 81.2 100 100 100 100 93.80 71-95 95 71
13.2 18.89 94.02 100 100 100 72.93 56-80 80 56
4.75 0.05 3.42 40.79 100 100 52.12 38-54 54 38
2.36 0 2.39 9.32 61.5 100 30.15 28-42 42 28
0.300 0 0.17 4.15 24.7 100 13.34 7-21 21 7
0.075 0 0 2.54 11.5 6.5 5.51 2-8 8 2

120.00

100.00

80.00
% passing

60.00

40.00

20.00

0.00
0.01 0.1 1 10 100

Sieve Size
0.00
0.01 0.1 1 10 100

Sieve Size
ATES :

Middile
Limit

100
95
83
68
46
35
14
5

100
100
COMBINED PROPORTION OF DBM Gr-II AGGREGATES :
Ashoka Buildcon Ltd. Vax Consultants Pvt. Ltd.

Aggregate % to be mixed
20 mm 35.00%
13.2 mm 23.00%
6.7 mm 0.00%
2.36 mm 39.00%
Filler 3.00%
TOTAL 100.00%

20 mm 13.2 mm 6.7 mm 2.36 mm Filler DBM Gr-II


Sieve
Avg % Avg % Avg % Avg % Avg % % to be Upper Lower
Size in Limits
passing passing passing passing passing mixed limit Limit
mm
37.5 100 100 100 100 100 100.00 100 100 100
26.5 100 100 100 100 100 100.00 90-100 100 90
19.0 80.34 100 100 100 100 93.12 71-95 95 71
13.2 16.71 94.06 100 100 100 69.48 56-80 80 56
4.75 1.05 3.45 26.63 100 100 43.16 38-54 54 38
2.36 0 2.18 5.88 75.54 100 32.96 28-42 42 28
0.300 0 0 2.84 31.49 100 15.28 7-21 21 7
0.075 0 0 1.18 7.87 6.5 3.26 2-8 8 2
120.00

100.00

80.00
% Passing

60.00

40.00

20.00

0.00
0.01 0.1 1 10 100
Sieve Size in mm
EPC Contractor Concessionaires I.E Representative
TION OF DBM Gr-II AGGREGATES :
Vax Consultants Pvt. Ltd.

DBM Gr-II

Middile
Limit

100
95
83
68
46
35
14
5

1 10 100
Sieve Size in mm
I.E Representative