CALCULATION OF PILE BEARING CAPACITY – AXIAL COMPRESSION & TENSION

PROYEK LUBUK GAUNG PLANT


DB-2 & DB-5

elev. of ground floor : 1.20 m pile cap


elev. of soil surface : 0.00 m COL : 1.50 m
pile cap thickness : 1.50 m
pile cap COL : -1.50 m depth elev
pile head : 1.50 -1.50 m
pile tip : 53.50 -53.50 m
pile length: 52.00 m

Area borepile pile elev eff. pile Qa Ta


diameter depth pile tip length recomnd recomnd
m m m m ton ton

11.00 -11.00 9.50 10 4


11.50 -11.50 10.00 12 5
12.00 -12.00 10.50 14 7

13.00 -13.00 11.50 15 8


14.00 -14.00 12.50 16 10
15.00 -15.00 13.50 18 12
16.00 -16.00 14.50 21 14
17.00 -17.00 15.50 22 16
18.00 -18.00 16.50 23 15
19.00 -19.00 17.50 24 16
20.00 -20.00 18.50 26 18
0.50 21.00 -21.00 19.50 28 20
Tanki
22.00 -22.00 20.50 30 22
23.00 -23.00 21.50 32 24

24.50 -24.50 23.00 35 25


25.50 -25.50 24.00 35 27
26.50 -26.50 25.00 41 30
27.50 -27.50 26.00 44 32
28.00 -28.00 26.50 45 33

33.00 -33.00 31.50 60 40


33.50 -33.50 32.00 65 42
34.00 -34.00 32.50 67 45
34.50 -34.50 33.00 70 47