1263 MW Punjab Power Plant, Jhang Preliminary review procedure

Issuer: CMEC Comment Sheet ID.: 33-F10611S-S5204-02 Issued on:


Contractor: mengyong@mail.cmec.com Completion Date:

Reviewer: Employer / Document Control NESPAK / Document Control Lahmeyer / Document Control
Contact: gmtechnical@punjabthermalthermal.com pm.nespak.jp@gmail.com piotr.sputo@de.lahmeyer.com

Drawing/Document ID: 33-F10611S-S5204-02 REV A


Drawing/Document Title: PLAN OF COOLING TOWER CIRCULATING COOLING WATER PUMP HOUSE

The Categories of Approval follow: 1 = Approved, no comments / Reviewed


contract title, Chapter xxx, page yy
2 = Approved, with comments / Reviewed as noted
Besides the information discussed in the following, it is assumed that
subjects and the document itself are at least in accordance with the
Contract Specification. Approval or comment will not relieve the
3 = Not approved, rejected / Returned for correction
4 = For information only
Cat: 3
Contractor from fulfilling his contractual obligations.

Comm Doc Revie Prede Employer/Engineer’s Comments Contractor’s Action


ID: Rev wer cessor (To be submitted together with the
revised/completed documents)
1. 0 NE NIL Refer to our comment on Drawing #33-F10611S-S5204-01 Ok.
2. 0 NE NIL These drawings shall be read in conjunction with approved architectural, Ok.
plumbing, equipment and all other relevant drawings before execution at site.
3. 0 NE NIL Refer to our comment on Document #33-F10611S-S5204-A6C-01 Ok.
4. 0 NE NIL Layout of CW pump house is subject to approved equipment arrangement Ok.
plan, Cable routing plan, piping plan and approved Electrical, Mechanical and
water supply drawings. Reference # of all related approved drawings shall be
incorporated in the drawing.
5. 0 NE NIL As regard to note # 4 puddle flange shall be incorporated instead of wall Rechecked by Water Supply, the
through bushing as approved in water supply drawing # 33-F10611S-S0204. wall bushing shall be adopted.
6. 0 NE NIL All embedded parts, ladder, handrail, chequered plates and anchor bolts shall All steel parts shall be hot dip
be hot dip galvanized. A suitable note / detail shall be added accordingly. galvanized(ASTM A123) or shall be
painted according to procedure
mentioned in clause 4.2 33-
F10611S-T0233-001. It shall be
approved by engineer at site prior to
construction.

Page 1 of 2
1263 MW Punjab Power Plant, Jhang Preliminary review procedure
7. 0 NE NIL The rubber sealant belt shall be of approved quality from approved source. Ok.
8. 0 NE NIL Water stops and construction joints details and locations shall be incorporated. Please refer to note no.7 in drawing
33-F10611S-S5204-01 of this
volume

9. 0 NE NIL Reference # of gate slot and filter tank installations drawings shall be Ok and the drawing is updated.
incorporated.
10. A NE 1-4 Noted. Ok.

11. A NE NIL Refer to our comment on Drawing # 33-F10611S-S5204-A6C-01 and revise Ok.
the drawing accordingly if needed.
12.
13.
14.
15.
NESPAK Comments answered:
Date:

Lead Engineer Name & Signature Contractor

Page 2 of 2