CONSORCIO MONTE SINAI

FICHA TECNICA DE LA OBRA


1.00 L.P. N° : 001-2017-CS/MDRT

“MEJORAMIENTO DEL SISTEMA DE AGUA POTA


2.00 OBRA : EN LAS COMUNIDADES DE MONTE SINAI, ALTO
DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

3.00 UBICACIÓN

DEPARTAMENTO : JUNIN

PROVINCIA : SATIPO

DISTRITO : RIO TAMBO MONTE SINAI, ALTO UNIN

COMUNIDADES :

4.00 ENTIDAD CONTRATANTE : MUNICIPALIDAD DISTRITAL DE RIO TAMBO

5.00 CONTRATISTA : CONSORCIO MONTE SINAI

6.00 SUPERVISOR DE OBRA : ING. RAFAEL ALFONSO ZARATE AVILA

7.00 RESIDENTE DE OBRA : ING. JOSE GONZALES FERIA

8.00 JEFE DE SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA

9.00 CONSULTOR :

10.00 FUENTE DE FINANCIAMIENTO : RECURSOS DETERMINADOS


RECURSOS POR OPERACIONES DE CREDITO
11.00 VALOR REFERENCIAL : S/. 5,939,051.66 INC. IGV.

TOTAL
12.00 PRESUPUESTO CONTRATADO (PC) : S/. 5,939,051.66 INC. IGV

13.00 MODALIDAD : PRECIOS UNITARIOS

14.00 No. DE CONTRATO : 060-2017-MDRT/UL

15.00 FECHA DE FIRMA DE CONTRATO : 06/11/2017

16.00 FECHA DE ENTREGA DE TERRENO : 21/11/2017

17.00 ADELANTO DIRECTO SOLICITADO : S/. 593,905.00 INC. IGV

18.00 ADELANTO DE MATERIALES SOLICITADO : S/. 934,945.00 INC. IGV


FECHA DE INICIO DEL PLAZO
19.00 : 23/11/2017
CONTRACTUAL

20.00 PLAZO DE EJECUCION : 360 DIAS CALENDARIOS

21.00 FECHA DE TERMINO DE PLAZO CONTRACTUA: 17/11/2018


ONTE SINAI
A DE LA OBRA

DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL


ADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGRE Y PIRIARI,
TAMBO - SATIPO - JUNIN”

MONTE SINAI, ALTO UNINI, VISTA ALEGRE Y PIRIAR

DISTRITAL DE RIO TAMBO

ONSO ZARATE AVILA

ONSO ZARATE AVILA

OPERACIONES DE CREDITO

Mes Base : NOVIEMBRE - 2017

S/IGV IGV

S/. 5,033,094.63 + S/. 905,957.03


RESUMEN DE VALORIZACION DE OBRA N° 09
SETIEMBRE DEL 2018

“MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGR


OBRA : COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGRE Y PIRIARI, DISTR
TAMBO - SATIPO - JUNIN”
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISOR : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA : 30 DE SETIEMBRE DEL 2018
PRESUPUESTO OFERTADO SIN IGV S/. 5,033,094.63

Acumulado
ITEM CONCEPTO
Anterior

I. AVANCE CONTRACTUAL DEL PRESENTE MES


Total I FORMULAS 1, 2 y 3 2,672,469.29

Avance Fisico de la Obra 53.10%


Avance Programado 39.29%

II. REAJUSTES Y REINTEGROS


Reajuste del presente mes
Reintegro del mes anterior
Reintegro del penultimo mes
Total II 0.00

III. DEDUCCIONES
III.1 Deduccion del reajuste por adelanto directo
Del presente mes
Mes anterior 0.00
Penultimo mes
Total III.1 0.00

III.2 Deduccion del reajuste por adelanto de materiales


Del presente mes 0.00
Mes anterior 0.00
Penultimo mes 0.00
Total III.2 0.00

IV. MONTO BRUTO (I + II - III.1 - III.2) 2,672,469.29

V. AMORTIZACIONES
V.1 Amortizacion por adelanto directo 164,090.96
V.2 Amortizacion por adelanto de materiales 317,916.21
Total V 482,007.17

VI. MONTO LIQUIDO A PAGAR (IV - V) 2,190,462.12

VII. I.G.V. (18% (VI)) 394,283.18


VIII. MONTO A FACTURAR (VI + VII) 2,584,745.30
DE VALORIZACION DE OBRA N° 09
SETIEMBRE DEL 2018

NTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS


S DE MONTE SINAI, ALTO UNINI, VISTA ALEGRE Y PIRIARI, DISTRITO DE RIO
TAMBO - SATIPO - JUNIN”

Acumulado
Presente Mes
Actual

474,371.55 3,146,840.84

9.43% 62.51%
12.68% 51.97%

0.00 0.00

0.00

0.00 0.00

0.00
0.00
0.00
0.00 0.00

474,371.55 3,146,840.84

47,437.14
107,856.61
155,293.75 637,300.92

319,077.80 2,509,539.92

57,434.00 451,717.19
376,511.80 2,961,257.11
RESUMEN DE VALORIZACION MENSUAL N° 07
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGRE Y PIRIARI,
DISTRITO DE RIO TAMBO - SATIPO - JUNIN”
PROPIETARIO MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA CONSORCIO MONTE SINAI
SUPERVISION ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018
Valorización

Item Descripción Costo Directo


Anterior % Presente Mes % Acumulado %

01 OBRAS GENERALES 1,131,181.33 419,474.96 166,413.11 585,888.07


01.01 OBRAS PROVISIONALES 96,882.40 81,761.70 84.39% 288.00 0.30% 82,049.70 84.69%
01.02 SEÑALIZACION 911.78 821.47 90.10% 18.15 1.99% 839.62 92.09%
01.03 BOCATOMA (01 UND) 44,400.82 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.04 DESARENADOR (01 UND) 11,261.94 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05 LINEA DE CONDUCCION (14+240 KM) 623,099.68 243,948.52 39.15% 139,014.92 22.31% 382,963.44 61.46%
01.06 VALVULA DE AIRE (26 UND) 16,906.30 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.07 VALVULA DE PURGA (05 UND) 3,836.32 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.08 CAMARA ROMPE PRESION (01 UNID) 1,147.04 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.09 PASE AEREO L=15.00m (09 UNID) 43,661.08 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.10 ------------------------------------------ 0.00 0.00 0.00 0.00
01.11 ------------------------------------------ 0.00 0.00 0.00 0.00
01.12 PREFILTRO (02 UND) 125,496.56 0.00 0.00% 0.00 0.00% 0.00 0.00%
1.13 FILTRO LENTO (01 UND) 149,269.73 86,848.12 58.18% 27,092.04 18.15% 113,940.16 76.33%
01.14 CERCO PERIMETRICO (L=240.00 m) 7,753.58 0.00 0.00% 0.00 0.00% 0.00 0.00%
CAMARA DE DISTRIBUCION DE CAUDALES 03 SALIDAS (01 6,554.10 6,095.15 93.00% 0.00 0.00% 6,095.15 93.00%
01.15 UNID)
2.00 SERVICIO DE AGUA POTABLE ALTO UNINI 380,796.28 259,244.77 36,785.28 296,030.05
2.01 LINEA DE ADUCCION (3+671.22 KM) ALTO UNINI 134,747.45 59,761.69 44.35% 36,785.28 27.30% 96,546.97 71.65%
02.02 VALVULA DE AIRE (08 UND) 4,736.48 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.03 VALVULA DE PURGA (02 UND) 1,637.06 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.04 CAMARA ROMPE PRESION (02 UNID) 2,336.78 0.00 0.00% 0.00 0.00% 0.00 0.00%
2.05 RESERVORIO DE UNINI V=15M3 (01UNID) 13,456.59 9,971.86 74.10% 0.00 0.00% 9,971.86 74.10%
2.06 RED DE DISTRIBUCION UNINI (L=4+622.78m) 199,623.47 187,289.02 93.82% 0.00 0.00% 187,289.02 93.82%
2.07 CONEXIONES DOMICILIARIAS ALTO UNINI (63 UNID.) 24,258.45 2,222.20 9.16% 0.00 0.00% 2,222.20 9.16%
03 SERVICIO DE AGUA POTABLE MONTE SINAI 188,269.20 51,774.00 20,010.01 71,784.01
03.01 LINEA DE ADUCCION (1+473 KM) 50,939.28 34,399.73 67.53% 15,567.37 30.56% 49,967.10 98.09%
03.02 VALVULA DE AIRE (03 UND) 1,916.94 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.03 VALVULA DE PURGA (01 UND) 803.79 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.04 RESERVORIO MONTE SINAI V=25M3 (01UNID) 36,260.71 15,584.00 42.98% 0.00 0.00% 15,584.00 42.98%
3.05 RED DE DISTRIBUCION MONTE SINAI (L=1+681.00m) 67,820.73 1,790.27 2.64% 4,442.64 6.55% 6,232.91 9.19%
03.06 CONEXIONES DOMICILIARIAS MONTE SINAI (88 UND) 30,527.75 0.00 0.00% 0.00 0.00% 0.00 0.00%
4.00 SERVICIO AGUA POTABLE PIRIARI 229,414.03 133,289.69 76,553.64 209,843.33
04.01 LINEA DE ADUCCION (3+120.00 KM) 114,619.44 38,217.60 33.34% 74,373.84 64.89% 112,591.44 98.23%
04.02 CAMARA ROMPE PRESION (01 UNID) 1,162.83 0.00 0.00% 0.00 0.00% 0.00 0.00%
4.03 RESERVORIO DE PIRIARI V=10M3 (01UNID) 12,275.39 9,132.23 74.39% 0.00 0.00% 9,132.23 74.39%
CAMARA DE DISTRIBUCION DE CAUDALES 02 SALIDAS (01 90.56% 0.00% 90.56%
4.04 UNID) 6,804.09 6,161.80 0.00 6,161.80
4.05 RED DE DISTRIBUCION PIRIARI (L=2+120.00 m) 82,425.37 74,328.56 90.18% 0.00 0.00% 74,328.56 90.18%
4.06 CONEXIONES DOMICILIARIAS PIRIARI (35 UNID.) 12,126.91 5,449.50 44.94% 2,179.80 17.97% 7,629.30 62.91%
5.00 SERVICIO DE AGUA POTABLE VISTA ALEGRE 404,172.09 321,597.95 33,319.80 354,917.75
5.01 LINEA DE CONDUCCION (2+760KM) 101,490.72 99,669.12 98.21% 0.00 0.00% 99,669.12 98.21%
05.02 VALVULA DE AIRE (07 UND) 5,730.79 0.00 0.00% 0.00 0.00% 0.00 0.00%
05.03 VALVULA DE PURGA (06 UND) 6,102.71 0.00 0.00% 0.00 0.00% 0.00 0.00%
CAMARA DE DISTRIBUCION DE CAUDALES 02 SALIDAS (01 90.56% 0.00% 90.56%
5.04 UNID) 6,804.09 6,161.80 0.00 6,161.80
5.05 RESERVORIO DE VISTA ALEGRE V=8 M3 (01UNID) 12,257.97 9,132.23 74.50% 0.00 0.00% 9,132.23 74.50%
5.06 RED DE DISTRIBUCION VISTA ALEGRE (L=7+028.00 m) 255,122.64 196,171.76 76.89% 33,319.80 13.06% 229,491.56 89.95%
5.07 CONEXIONES DOMICILIARIAS VISTA ALEGRE (48 UNID.) 16,663.17 10,463.04 62.79% 0.00 0.00% 10,463.04 62.79%
06 SERVICIO DE AGUA POTABLE RAMAL PIRIARI VISTA ALEGRE 149,770.57 45,486.74 15,047.52 60,534.26
6.01 LINEA DE ADUCCION RAMAL (1+649 KM) 52,702.79 1,665.49 3.16% 15,047.52 28.55% 16,713.01 31.71%
06.02 VALVULA DE AIRE (02 UND) 1,593.08 0.00 0.00% 0.00 0.00% 0.00 0.00%
06.03 ------------------------------------------ 0.00 0.00 0.00 0.00
06.04 CAMARA ROMPE PRESION (01 UNID) 1,219.23 0.00 0.00% 0.00 0.00% 0.00 0.00%
06.05 RED DE DISTRIBUCION RAMAL (L=2+575 m) 90,693.31 43,821.25 48.32% 0.00 0.00% 43,821.25 48.32%
06.06 CONEXIONES DOMICILIARIAS RAMAL (10 UNID.) 3,562.16 0.00 0.00% 0.00 0.00% 0.00 0.00%
07 SERVICIO DE ALCANTARILLADO SANITARIO MONTE SINAI (88 UND) 338,348.71 246,745.55 3,060.01 249,805.56
07.01 OBRAS PROVISIONALES 86,745.59 79,571.03 91.73% 0.00 0.00% 79,571.03 91.73%
07.02 RED DE COLECTORES (L=1034.43 m) 56,431.40 54,944.56 97.37% 1,486.85 2.63% 56,431.41 100.00%
07.03 RED DE EMISORES (L=421.21 m) 26,619.88 26,619.88 100.00% 0.00 0.00% 26,619.88 100.00%
07.04 BUZONES TIPO 113,344.39 85,610.08 75.53% 0.00 0.00% 85,610.08 75.53%
7.05 INSTALACION DE CONEXION DOMICILIARIA (88 UNID.) 55,207.45 0.00 0.00% 1,573.16 2.85% 1,573.16 2.85%
08 SERVICIO DE SANEAMIENTO BASICO 1,222,637.29 674,544.25 47,813.43 722,357.68
08.01 UNIDAD BASICA UNINI (63 UND) 493,758.08 281,110.90 56.93% 24,162.36 4.89% 305,273.26 61.83%
08.02 UNIDAD BASICA PIRIARI (35 UND) 274,313.71 149,100.54 54.35% 21,986.63 8.02% 171,087.17 62.37%
08.03 UNIDAD BASICA VISTA ALEGRE (48 UND) 376,188.54 217,880.89 57.92% 0.00 0.00% 217,880.89 57.92%
08.04 UNIDAD BASICA RAMAL (10 UND) 78,376.96 26,451.92 33.75% 1,664.44 2.12% 28,116.36 35.87%
9.00 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES 162,771.12 79,846.10 0.00 79,846.10
9.01 CAMARA DE REJAS Y DESARENADOR (01 UND) 4,211.77 2,264.71 53.77% 0.00 0.00% 2,264.71 53.77%
09.02 CAMARA REPARTIDORA DE CAUDALES(01 UND) 3,038.82 652.58 21.47% 0.00 0.00% 652.58 21.47%
09.03 TANQUE SEPTICO 30,850.36 29,741.38 96.41% 0.00 0.00% 29,741.38 96.41%
09.04 LECHO DE SECADO 16,949.15 0.00 0.00% 0.00 0.00% 0.00 0.00%
09.05 CAMARA DISTRIBUIDORA DE CAUDALES (03) 7,344.86 869.81 11.84% 0.00 0.00% 869.81 11.84%
09.06 POZO DE PERCOLACION (06) 82,208.80 45,024.63 54.77% 0.00 0.00% 45,024.63 54.77%
09.07 INSTALACION DE TUBERIAS (180m) 15,515.86 1,292.99 8.33% 0.00 0.00% 1,292.99 8.33%
09.08 CERCO PERIMETRICO (L=120.00 m) 2,651.50 0.00 0.00% 0.00 0.00% 0.00 0.00%
10 CAPACITACION Y EDUCACION 30,000.00 13,500.00 0.00 13,500.00
DESAROLLO DE LAS CAPACITACIONES Y/O TALLERES
10.01 ENSIBILIZACION, EDUCACION Y PARTICIPACION CIUDADANA 30,000.00 13,500.00 45.00% 0.00 0.00% 13,500.00 45.00%
DE APOYO A LA GESTION DE AP Y AS
11 MITIGACION DEL IMPACTO AMBIENTAL 64,429.67 38,657.81 6,442.97 45,100.77
11.01 MITIGACION DEL IMPACTO AMBIENTAL 64,429.67 38,657.80 60.00% 6,442.97 10.00% 45,100.77 70.00%

A TOTAL COSTO DIRECTO S/. 4,301,790.29 2,284,161.82 405,445.77 2,689,607.58


GASTOS GENERALES 12.00% 516,214.83 274,099.40 48,653.49 322,752.89
UTILIDADES 5.00% 215,089.51 114,208.08 20,272.29 134,480.37
B SUB TOTAL S/. 5,033,094.63 2,672,469.30 474,371.55 3,146,840.84
C TOTAL VALORIZADO SIN IGV 5,033,094.63 2,672,469.30 474,371.55 3,146,840.84
IGV 18.00% 905,957.03 481,044.47 85,386.88 566,431.35
D TOTAL VALORIZADO CON IGV 5,939,051.66 3,153,513.77 559,758.43 3,713,272.19

E PORCENTAJE DE AVANCE 100.00% 53.10% 9.43% 62.52%


RIZACION MENSUAL N° 07
O INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGRE Y PIRIARI,

Valorización

Saldo %

545,293.30
14,832.71 15.31%
72.18 7.92%
44,400.82 100.00%
11,261.94 100.00%
240,136.24 38.54%
16,906.30 100.00%
3,836.32 100.00%
1,147.04 100.00%
43,661.08 100.00%
0.00
0.00
125,496.56 100.00%
35,329.57 23.67%
7,753.58 100.00%

458.96 7.00%

84,766.23
38,200.48 28.35%
4,736.48 100.00%
1,637.06 100.00%
2,336.78 100.00%
3,484.73 25.90%
12,334.45 6.18%
22,036.25 90.84%
116,485.19
972.18 1.91%
1,916.94 100.00%
803.79 100.00%
20,676.71 57.02%
61,587.82 90.81%
30,527.75 100.00%
19,570.70
2,028.00 1.77%
1,162.83 100.00%
3,143.16 25.61%

9.44%
642.29
8,096.81 9.82%
4,497.61 37.09%
49,254.35
1,821.60 1.79%
5,730.79 100.00%
6,102.71 100.00%

9.44%
642.29
3,125.74 25.50%
25,631.09 10.05%
6,200.13 37.21%
89,236.30
35,989.78 68.29%
1,593.08 100.00%
0.00
1,219.23 100.00%
46,872.05 51.68%
3,562.16 100.00%
88,543.23
7,174.56 8.27%
0.00 0.00%
0.00 0.00%
27,734.38 24.47%
53,634.29 97.15%
500,279.97
188,484.93 38.17%
103,226.72 37.63%
158,307.74 42.08%
50,260.58 64.13%
82,925.05
1,947.06 46.23%
2,386.24 78.53%
1,108.99 3.59%
16,949.15 100.00%
6,475.05 88.16%
37,184.19 45.23%
14,222.87 91.67%
2,651.50 100.00%
16,500.00

16,500.00 55.00%

19,328.90
19,328.90 30.00%

1,612,183.15
193,462.00
80,609.16
1,886,254.31
1,886,254.31
339,525.78
2,225,780.09

37.48%
CURVA DE AVANCE DE OB
OBRA :
“MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALE

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO


CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
RESIDENTE : ING. JOSE GONZALES FERIA
FECHA : 30 DE SETIEMBRE DEL 2018

100%

90%

80%

70%
AVANCE ACUMULADO

60%

50%

40%

30%

20%

10%

0%
23 Nov 2017 30 Nov 2017 31 Dic 2017 31 Ene 2018 30 Abr 2018 31 May 2018 30 Jun 2018 31 Jul 2018 31 Ago 2018 30 Set 2018 31
23 Nov 2017 30 Nov 2017 31 Dic 2017 31 Ene 2018 30 Abr 2018 31 May 2018 30 Jun 2018
0.00% 1.70% 2.84% 7.77% 6.09% 8.93% 11.96%
PROGRAMADO 0.00% 1.70% 4.54% 12.31% 18.40% 27.33% 39.29%
0.00% 1.70% 2.84% 7.77% 5.45% 4.67% 9.26%
EJECUTADO 0.00% 1.70% 4.54% 12.31% 17.76% 22.43% 31.69%
ANCE DE OBRA
SINAI, ALTO UNINI, VISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

LEYENDA

PROGRAMADO

EJECUTADO

1 Ago 2018 30 Set 2018 31 Oct 2018 30 Nov 2018 31 Dic 2018 16 Ene 2019
Cronograma Mensual
31 Jul 2018 31 Ago 2018 30 Set 2018 31 Oct 2018 30 Nov 2018 31 Dic 2018 16 Ene 2019
12.68% 14.01% 11.73% 6.07% 5.13% 8.40% 2.69%
51.97% 65.98% 77.71% 83.78% 88.91% 97.31% 100.00%
10.17% 11.23% 9.43%
41.86% 53.09% 62.51%
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01 OBRAS GENERALES 1,131,181.33
01.01 OBRAS PROVISIONALES 96,882.40
01.01.01 ALMACEN, OFICINA Y CASETA DE GUARDIANIA glb 1.00 3,600.00 3,600.00 0.65
01.01.02 CARTEL DE IDENTIFICACION DE OBRA DE 5.40x3.60 m. und 1.00 1,986.12 1,986.12 1.00
01.01.03 TRANSPORTE DE MATERIALES Y EQUIPOS glb 1.00 71,745.59 71,745.59 0.89
01.01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO (AGUA) glb 1.00 16,220.45 16,220.45 0.82
01.01.05 ZANJAS DE CORONACION BOCATOMA, DE DRENAJE EN m3 96.00 34.69 3,330.24 -
ZONAS DE PTAR PTAP
01.02 SEÑALIZACION 911.78 -
01.02.01 MALLA PLASTICA SEÑALIZACION C/LIMITES SEGURIDAD DE m 2.00 120.97 241.94 1.25
OBRA
01.02.02 CARTEL DE SEÑALIZACION PREVENTIVA und 2.00 334.92 669.84 2.00
01.03 BOCATOMA (01 UND) 44,400.82 -
01.03.01 TRABAJOS PRELIMINARES 113.28 -
01.03.01.01 LIMPIEZA MANUAL DE TERRENO m2 92.85 0.53 49.21 -
01.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA m2 92.85 0.69 64.07 -
01.03.02 MOVIMIENTO DE TIERRAS 5,553.56 -
01.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL C/ PRESENCIA m3 118.98 34.69 4,127.42 -
DE AGUA
01.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 11.44 1.04 11.90 -
01.03.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 29.74 15.72 467.51 -
ZARANDEADO
01.03.02.04 ELIMINACION MATERIAL EXCEDENTE m3 89.23 10.61 946.73 -
01.03.03 OBRAS DE CONCRETO SIMPLE 17,643.29 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.03.03.01 CONCRETO CICLOPEO f'c=175KG/CM2 +30% P.M. m3 71.64 211.19 15,129.65 -
01.03.03.02 CONCRETO f'c=100 kg/cm2 m3 11.54 217.82 2,513.64 -
01.03.04 OBRAS DE CONCRETO ARMADO 12,342.25 -
01.03.04.01 CONCRETO f'c=210KG/CM2 m3 14.86 366.40 5,444.70 -
01.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 125.46 21.45 2,691.12 -
01.03.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 1,043.78 4.03 4,206.43 -
01.03.05 CURADO DE CONCRETO 92.87 -
01.03.05.01 CURADO CON PRODUCTO QUIMICO m2 103.19 0.90 92.87 -
01.03.06 REVOQUES Y ENLUCIDOS 2,765.92 -
01.03.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 109.69 20.68 2,268.39 -
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
01.03.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 26.38 18.86 497.53 -
ACABADO PULIDO
01.03.07 CARPINTERIA METALICA 1,509.64 -
01.03.07.01 MARCO Y COMPUERTA VOLANTE DE TIPO-1 (0.80x0.90M) und 1.00 1,149.82 1,149.82 -
01.03.07.02 REJILLA METALICA PREFABRICADA (0.90x1.30M) und 1.00 359.82 359.82 -
01.03.08 PINTURA 3,430.69 -
01.03.08.01 PINTURA LATEX SATINADO A DOS MANOS m2 136.07 10.13 1,378.39 -
01.03.08.02 PINTURA ANTICORROCIVA A DOS MANOS m2 109.69 18.71 2,052.30 -
01.03.09 VALVULAS, ACCESORIOS Y TUBERIAS 949.32 -
01.03.09.01 SALIDA DE CAPTACION DE DN 110MM und 1.00 949.32 949.32 -
01.04 DESARENADOR (01 UND) 11,261.94 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.04.01 TRABAJOS PRELIMINARES 21.92 -
01.04.01.01 LIMPIEZA MANUAL DE TERRENO m2 17.82 0.54 9.62 -
01.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 17.82 0.69 12.30 -
01.04.02 MOVIMIENTO DE TIERRAS 729.06 -
01.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 15.26 34.69 529.37 -
COMPACTADO
01.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 16.62 1.06 17.62 -
01.04.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 3.81 15.93 60.69 -
ZARANDEADO
01.04.02.04 ELIMINACION MATERIAL EXCEDENTE m3 11.44 10.61 121.38 -
01.04.03 OBRAS DE CONCRETO SIMPLE 361.58 -
01.04.03.01 CONCRETO f'c=100 kg/cm2 m3 1.66 217.82 361.58 -
01.04.04 OBRAS DE CONCRETO ARMADO 6,327.70 -
01.04.04.01 CONCRETO f'c=210KG/CM2 m3 7.45 351 2,614.95 -
01.04.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 775.96 4.05 3,142.64 -
01.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 26.20 21.76 570.11 -
01.04.05 CURADO DE CONCRETO 23.92 -
01.04.05.01 CURADO CON PRODUCTO QUIMICO m2 26.58 0.90 23.92 -
01.04.06 REVOQUES Y ENLUCIDOS 0 0.00 512.16 -
01.04.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 27.58 18.57 512.16 -
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
01.04.07 CARPINTERIA METALICA 0 0.00 2,683.92 -
01.04.07.01 MARCO Y COMPUERTA VOLANTE DE TIPO-1 (0.30x0.30m) und 2.00 542.14 1,084.28 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.04.07.02 MARCO Y COMPUERTA TIPO BAFLE und 2.00 799.82 1,599.64 -
01.04.08 PINTURA 196.83 -
01.04.08.01 PINTURA LATEX SATINADO A DOS MANOS m2 19.43 10.13 196.83 -
01.04.09 VALVULAS, ACCESORIOS Y TUBERIAS 404.85 -
01.04.09.01 ACCESORIO Y TUBERIA und 1.00 404.85 404.85 -
01.05 LINEA DE CONDUCCION (14+240 KM) 623,099.68 -
01.05.01 TRABAJOS PRELIMINARES 14,311.20 -
01.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 7,120.00 0.53 3,773.60 7,120.00
01.05.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 7,120.00 1.48 10,537.60 7,120.00
01.05.02 MOVIMIENTO DE TIERRAS 333,956.48 -
01.05.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA m3 5,696.00 26.52 151,057.92 1,800.00
01.05.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 14,240.00 1.06 15,094.40 5,990.00
MATERIAL COMPACTADO
01.05.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 14,240.00 4.70 66,928.00 5,990.00
01.05.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 14,240.00 2.71 38,590.40 5,990.00
(0.60 x 0.20 m)
01.05.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 4,272.00 14.58 62,285.76 1,289.00
ZARANDEADO
01.05.03 INSTALACION DE TUBERIA 267,142.40 -
01.05.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 110 MM C/ANILLO m 14,240.00 18.76 267,142.40 5,990.00
01.05.04 PRUEBA DE CALIDAD 7,689.60 -
01.05.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA m 14,240.00 0.54 7,689.60 -
DE AGUA
01.06 VALVULA DE AIRE (26 UND) 16,906.30 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.06.01 TRABAJOS PRELIMINARES 26.11 -
01.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 21.06 0.54 11.37 -
01.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 21.06 0.70 14.74 -
01.06.02 MOVIMIENTO DE TIERRAS 491.64 -
01.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 12.64 26.52 335.21 -
COMPACTADO
01.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 21.06 1.06 22.32 -
01.06.02.03 ELIMINACION MATERAIL EXCEDENTE m3 12.64 10.61 134.11 -
01.06.03 OBRAS DE CONCRETO SIMPLE 7,274.93 -
01.06.03.01 CONCRETO f'c=175 kg/cm2 m3 13.10 335.08 4,389.55 -
01.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 132.60 21.76 2,885.38 -
01.06.04 CURADO DE CONCRETO 119.34 -
01.06.04.01 CURADO CON PRODUCTO QUIMICO m2 132.60 0.90 119.34 -
01.06.05 REVOQUES Y ENLUCIDOS 1,714.23 -
01.06.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 110.24 15.55 1,714.23 -
C/IMPERMEABILIZANTES
01.06.06 CARPINTERIA METALICA 1,894.36 -
01.06.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 26.00 72.86 1,894.36 -
01.06.07 PINTURA 1,190.59 -
01.06.07.01 PINTURA ANTICORROCIVA A DOS MANOS m2 110.24 10.80 1,190.59 -
01.06.08 ACCESORIOS 4,195.10 -
01.06.08.01 ACCESORIOS VALVULA DE AIRE D=110MM und 26.00 161.35 4,195.10 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.07 VALVULA DE PURGA (05 UND) 3,836.32 -
01.07.01 TRABAJOS PRELIMINARES 7.14 -
01.07.01.01 LIMPIEZA MANUAL DE TERRENO m2 5.75 0.54 3.11 -
01.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 5.75 0.70 4.03 -
01.07.02 MOVIMIENTO DE TIERRAS 176.68 -
01.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 4.68 26.52 124.11 -
COMPACTADO
01.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 5.75 1.06 6.10 -
01.07.02.03 ELIMINACION MATERAIL EXCEDENTE m3 4.38 10.61 46.47 -
01.07.03 OBRAS DE CONCRETO SIMPLE 190.13 -
01.07.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" m3 0.23 28.93 6.65 -
COMPACTADO Y APISONADO E=0.10m
01.07.03.02 CONCRETO f'c = 140 kg/cm2 m3 0.63 291.24 183.48 -
01.07.04 OBRAS DE CONCRETO ESTRUCTURA 1,643.95 -
01.07.04.01 CONCRETO f'c=175 kg/cm2 m3 2.63 335.08 881.26 -
01.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 35.05 21.76 762.69 -
01.07.05 CARPINTERIA METALICA 364.30 -
01.07.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 5.00 72.86 364.30 -
01.07.06 PINTURA 85.17 -
01.07.06.01 PINTURA LATEX SATINADO A DOS MANOS m2 10.20 8.35 85.17 -
01.07.07 ACCESORIOS 1,368.95 -
01.07.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM und 5.00 273.79 1,368.95 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.08 CAMARA ROMPE PRESION (01 UNID) 1,147.04 -
01.08.01 TRABAJOS PRELIMINARES 2.30 -
01.08.01.01 LIMPIEZA MANUAL DE TERRENO m2 1.85 0.54 1.00 -
01.08.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 1.85 0.70 1.30 -
01.08.02 MOVIMIENTO DE TIERRAS 72.19 -
01.08.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.90 26.52 50.39 -
COMPACTADO
01.08.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 1.55 1.06 1.64 -
01.08.02.03 ELIMINACION MATERAIL EXCEDENTE m3 1.90 10.61 20.16 -
01.08.03 OBRAS DE CONCRETO SIMPLE 182.05 -
01.08.03.01 ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX m2 2.56 54.70 140.03 -
6", E=20m
01.08.03.02 CONCRETO f'c=100 kg/cm2 m3 0.07 217.82 15.25 -
01.08.03.03 CONCRETO f'c=140 kg/cm2 m3 0.04 261.29 10.45 -
01.08.03.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.75 21.76 16.32 -
01.08.04 OBRAS DE CONCRETO ARMADO 650.25 -
01.08.04.01 CONCRETO f'c=210KG/CM2 m3 0.91 351.00 319.41 -
01.08.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 10.16 21.76 221.08 -
01.08.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 27.10 4.05 109.76 -
01.08.05 CURADO DE CONCRETO 0.82 -
01.08.05.01 CURADO CON PRODUCTO QUIMICO m2 0.91 0.90 0.82 -
01.08.06 REVOQUES Y ENLUCIDOS 55.98 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.08.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 3.60 15.55 55.98 -
C/IMPERMEABILIZANTES
01.08.07 CARPINTERIA METALICA 72.86 -
01.08.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 1.00 72.86 72.86 -
01.08.08 PINTURA 21.60 -
01.08.08.01 PINTURA ANTICORROCIVA A DOS MANOS m2 2.00 10.80 21.60 -
01.08.09 ACCESORIOS 88.99 -
01.08.09.01 ACCESORIO DE CAMARA ROMPE PRESION und 1.00 88.99 88.99 -
01.09 PASE AEREO L=15.00m (09 UNID) 43,661.08 -
01.09.01 TRABAJOS PRELIMINARES 486.58 -
01.09.01.01 LIMPIEZA MANUAL DE TERRENO m2 392.40 0.54 211.90 -
01.09.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 392.40 0.70 274.68 -
01.09.02 MOVIMIENTO DE TIERRAS 2,038.44 -
01.09.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 54.90 26.52 1,455.95 -
COMPACTADO
01.09.02.02 ELIMINACION MATERAIL EXCEDENTE m3 54.90 10.61 582.49 -
01.09.03 OBRAS DE CONCRETO SIMPLE 196.04 -
01.09.03.01 CONCRETO f'c=100 kg/cm2 m3 0.90 217.82 196.04 -
01.09.04 OBRAS DE CONCRETO ARMADO 20,712.52 -
01.09.04.01 CONCRETO f'c=210KG/CM2 m3 18.52 351.00 6,500.52 -
01.09.04.02 CONCRETO EN DADO f'c=175 kg/cm2 m3 28.80 335.08 9,650.30 -
01.09.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.96 21.76 1,457.05 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.09.04.04 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 766.58 4.05 3,104.65 -
01.09.05 REVOQUES Y ENLUCIDOS 1,041.23 -
01.09.05.01 TARRAJEO EN COLUMNAS m2 66.96 15.55 1,041.23 -
01.09.06 ACCESORIOS PASE AEREO 19,186.27 -
01.09.06.01 CABLE DE ACERO TIPO BOA DE 3/8" m 150.30 37.74 5,672.32 -
01.09.06.02 PENDOLAS DE CABLE DE ACERO LISO DE 1/4" und 99.00 53.82 5,328.18 -
01.09.06.03 GRAPA TIPO CROSBY DE A°G° PARA CABLE DE 25 mm2. und 117.00 14.62 1,710.54 -
01.09.06.04 TUBERIA HDPE SDR7 DE 110MM m 126.00 22.91 2,886.66 -
01.09.06.05 LANZAMIENTO Y FIJACION glb 9.00 312.80 2,815.20 -
01.09.06.06 SUMINISTRO und 9.00 85.93 773.37 -
01.10 ------------------------------------------ -
01.11 ------------------------------------------ -
01.12 PREFILTRO (02 UND) 125,496.56 -
01.12.01 TRABAJOS PRELIMINARES 178.56 -
01.12.01.01 LIMPIEZA MANUAL DE TERRENO m2 144.00 0.54 77.76 -
01.12.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 144.00 0.70 100.80 -
01.12.02 MOVIMIENTO DE TIERRAS 13,238.34 -
01.12.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 453.10 26.52 12,016.21 -
COMPACTADO
01.12.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 144.00 1.06 152.64 -
01.12.02.03 ELIMINACION MATERAIL EXCEDENTE m3 100.80 10.61 1,069.49 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.12.03 OBRAS DE CONCRETO SIMPLE 1,568.30 -
01.12.03.01 CONCRETO f'c=100 kg/cm2 m3 7.20 217.82 1,568.30 -
01.12.04 OBRAS DE CONCRETO ARMADO 65,668.81 -
01.12.04.01 CONCRETO f'c=210KG/CM2 m3 79.98 351.00 28,072.98 -
01.12.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 5,228.36 4.05 21,174.86 -
01.12.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 754.64 21.76 16,420.97 -
01.12.05 CURADO DE CONCRETO 244.89 -
01.12.05.01 CURADO CON PRODUCTO QUIMICO m2 272.10 0.90 244.89 -
01.12.06 REVOQUES Y ENLUCIDOS 11,816.12 -
01.12.06.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 174.40 18.12 3,160.13 -
ACABADO FROTACHADO
01.12.06.02 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 458.96 18.86 8,655.99 -
C/IMPERMEABILIZANTES
01.12.07 PINTURA 8,418.66 -
01.12.07.01 PINTURA LATEX SATINADO A DOS MANOS m2 174.40 8.35 1,456.24 -
01.12.07.02 PINTURA ANTICORROCIVA A DOS MANOS m2 458.96 15.17 6,962.42 -
01.12.08 SUMINISTRO E INST. DE COMPONENTES DEL LECHO 22,285.20 -
FILTRANTE
01.12.08.01 FILTRO DE GRAVA 15mm m3 18.90 125.31 2,368.36 -
01.12.08.02 FILTRO DE GRAVA 10mm m3 37.80 119.31 4,509.92 -
01.12.08.03 FILTRO DE GRAVA 5mm m3 75.60 125.31 9,473.44 -
01.12.08.04 FILTRO DE GRAVA 1/2" m3 31.08 190.91 5,933.48 -
01.12.09 SUMINISTRO E INSTALACION DE ACCESORIOS 2,077.68 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.12.09.01 ACCESORIO DEL PREFILTRO glb 2.00 1,038.84 2,077.68 -
1.13 FILTRO LENTO (01 UND) 149,269.73 -
01.13.01 TRABAJOS PRELIMINARES 150.25 -
01.13.01.01 LIMPIEZA MANUAL DE TERRENO m2 121.17 0.54 65.43 121.17
01.13.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 121.17 0.70 84.82 121.17
01.13.02 MOVIMIENTO DE TIERRAS 17,611.04 -
01.13.02.01 CORTE C/MAQUINARIA EN TERRENO DE MATERIAL m3 204.89 74.64 15,292.99 204.89
COMPACTO
01.13.02.02 REFINE Y NIVELACION DE PLATAFORMA m2 49.38 1.06 52.34 49.38
01.13.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 17.97 15.72 282.49 -
ZARANDEADO
01.13.02.04 ELIMINACION MATERAIL EXCEDENTE m3 186.92 10.61 1,983.22 -
01.13.03 OBRAS DE CONCRETO SIMPLE 26,906.02 -
01.13.03.01 ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX m2 8.90 100.20 891.78 -
4", E=10m
01.13.03.02 CONCRETO f'c=100 kg/cm2 m3 119.43 217.82 26,014.24 119.43
01.13.04 OBRAS DE CONCRETO ARMADO 74,404.63 -
01.13.04.01 CONCRETO f'c=210KG/CM2 m3 96.56 351.00 33,892.56 36.96
01.13.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 7,736.61 4.05 31,333.27 7,736.61
01.13.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 421.82 21.76 9,178.80 -
01.13.05 CURADO DE CONCRETO 86.90 -
01.13.05.01 CURADO CON PRODUCTO QUIMICO m2 96.56 0.90 86.90 36.96
01.13.06 JUNTAS 998.81 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.13.06.01 JUNTAS WATERSTOP DE PVC DE 6" m 53.10 18.81 998.81 53.10
01.13.07 REVOQUES Y ENLUCIDOS 6,704.58 -
01.13.07.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 312.75 12.11 3,787.40 -
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
01.13.07.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 183.10 12.11 2,217.34 -
ACABADO PULIDO
01.13.07.03 MORTERO CON PENDIENTE EN FONDO C.A. 1:3, m2 57.79 12.11 699.84 -
C/IMPERMEABILIZANTES
01.13.08 CARPINTERIA METALICA 1,550.87 -
01.13.08.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 1.00 72.86 72.86 -
01.13.08.02 MARCO Y VERTEDERO METALICO PREFABRICADO E=1/4", und 1.00 200.82 200.82 -
(0.50x0.70M.)
01.13.08.03 MARCO Y VERTEDERO METALICO PREFABRICADO E=1/4", und 3.00 180.82 542.46 -
(0.40x0.70M.)
01.13.08.04 ESCALERA METALICA PREFABRICADA DE TUB F°G° DE 11/2", und 3.00 244.91 734.73 -
H=3.20M
01.13.09 FILTROS 18,724.20 -
01.13.09.01 FILTRO DE GRAVA DE 19 - 50 MM m3 10.00 184.91 1,849.10 -
01.13.09.02 FILTRO DE GRAVA DE 9.5 - 19 MM m3 5.00 190.91 954.55 -
01.13.09.03 FILTRO DE GRAVA DE 3 - 9.5 MM m3 5.00 190.91 954.55 -
01.13.09.04 FILTRO DE GRAVA DE ARENA GRUESA m3 100.00 149.66 14,966.00 -
01.13.10 PINTURA 1,552.71 -
01.13.10.01 PINTURA LATEX SATINADO A DOS MANOS m2 183.10 8.35 1,528.89 -
01.13.10.02 PINTURA ANTICORROCIVA A DOS MANOS m2 1.57 15.17 23.82 -
01.13.11 VALVULAS, ACCESORIOS Y TUBERIA 579.72 -
01.13.11.01 ACCESORIOS PARA INGRESO DE PRE FILTRO DN 160MM und 1.00 579.72 579.72 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.14 CERCO PERIMETRICO (L=240.00 m) 7,753.58 -
01.14.01 TRABAJOS PRELIMINARES 147.60 -
01.14.01.01 LIMPIEZA MANUAL DE TERRENO m2 120.00 0.54 64.80 -
01.14.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 120.00 0.69 82.80 -
01.14.02 MOVIMIENTO DE TIERRAS 599.69 -
01.14.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 14.11 26.02 367.14 -
COMPACTADO
01.14.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 35.28 1.04 36.69 -
01.14.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 3.53 15.72 55.49 -
ZARANDEADO
01.14.02.04 ELIMINACION MATERAIL EXCEDENTE m3 13.23 10.61 140.37 -
01.14.03 OBRAS DE CONCRETO SIMPLE 3,694.64 -
01.14.03.01 CONCRETO f'c=140 kg/cm2 m3 14.14 261.29 3,694.64 -
01.14.04 CERCO PERIMETRICO CON MALLA OLIMPICA GALVANIZADA 3,311.65 -
01.14.04.01 CERCO PERIMETRICO DE ALAMBRE DE PUAS m 240.00 12.57 3,016.80 -
01.14.04.02 PUERTA DE MADERA CON MARCO O SOPORTES und 1.00 95.75 95.75 -
01.14.04.03 PINTURA ESMALTE EN PUERTAS Y VENTANAS A DOS MANOS m2 10.00 19.91 199.10 -
01.15 CAMARA DE DISTRIBUCION DE CAUDALES 03 SALIDAS (01 6,554.10 -
UNID)
01.15.01 TRABAJOS PRELIMINARES 9.69 -
01.15.01.01 LIMPIEZA MANUAL DE TERRENO m2 7.81 0.54 4.22 7.81
01.15.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 7.81 0.7 5.47 7.81
01.15.02 MOVIMIENTO DE TIERRAS 548.35 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
01.15.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 16.46 26.52 436.52 16.46
COMPACTADO
01.15.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 7.81 1.06 8.28 7.81
01.15.02.03 ELIMINACION MATERAIL EXCEDENTE m3 9.76 10.61 103.55 9.76
01.15.03 OBRAS DE CONCRETO SIMPLE 6.53 -
01.15.03.01 CONCRETO f'c=100 kg/cm2 m3 0.03 217.82 6.53 0.03
01.15.04 OBRAS DE CONCRETO ARMADO 4,474.06 -
01.15.04.01 CONCRETO f'c=210KG/CM2 m3 7.17 351 2,516.67 7.17
01.15.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 73.75 21.76 1,604.80 73.75
01.15.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 87.06 4.05 352.59 87.06
01.15.05 CURADO DE CONCRETO 275.83 -
01.15.05.01 CURADO CON PRODUCTO QUIMICO m2 73.75 3.74 275.83 73.75
01.15.06 REVOQUES Y ENLUCIDOS 707.82 -
01.15.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 37.53 18.86 707.82 37.53
C/IMPERMEABILIZANTES
01.15.07 CARPINTERIA METALICA 72.86 -
01.15.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 1.00 72.86 72.86 1.00
01.15.08 PINTURA 185.17 -
01.15.08.01 PINTURA ANTICORROCIVA A DOS MANOS m2 21.81 8.49 185.17 -
01.15.09 ACCESORIOS 273.79 -
01.15.09.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM und 1.00 273.79 273.79 -
2 SERVICIO DE AGUA POTABLE ALTO UNINI 380,796.28 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
2.01 LINEA DE ADUCCION (3+671.22 KM) ALTO UNINI 134,747.45 -
02.01.01 TRABAJOS PRELIMINARES 3,707.93 -
02.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 1,835.61 0.54 991.23 1,835.61
02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 1,835.61 1.48 2,716.70 1,835.61
02.01.02 MOVIMIENTO DE TIERRAS 93,886.48 -
02.01.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA m3 1,762.19 26.52 46,733.28 768.00
02.01.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 3,671.22 1.06 3,891.49 1,600.00
MATERIAL COMPACTADO
02.01.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 3,671.22 4.7 17,254.73 1,600.00
02.01.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 3,671.22 2.71 9,949.01 1,600.00
(0.60 x 0.20 m)
02.01.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 1,101.37 14.58 16,057.97 480.00
ZARANDEADO
02.01.03 INSTALACION DE TUBERIA 34,730.03 -
02.01.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO m 3,671.25 9.46 34,730.03 1,600.00
02.01.04 PRUEBA DE CALIDAD 2,423.01 -
02.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA m 3,671.22 0.66 2,423.01 -
DE AGUA
02.02 VALVULA DE AIRE (08 UND) 4,736.48 -
02.02.01 TRABAJOS PRELIMINARES 8.04 -
02.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 6.48 0.54 3.50 -
02.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 6.48 0.70 4.54 -
02.02.02 MOVIMIENTO DE TIERRAS 151.30 -
02.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 3.89 26.52 103.16 -
COMPACTADO
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
02.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 6.48 1.06 6.87 -
02.02.02.03 ELIMINACION MATERAIL EXCEDENTE m3 3.89 10.61 41.27 -
02.02.03 OBRAS DE CONCRETO SIMPLE 2,277.80 -
02.02.03.01 CONCRETO f'c=175 kg/cm2 m3 4.03 344.91 1,389.99 -
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 40.80 21.76 887.81 -
02.02.04 CURADO DE CONCRETO 36.34 -
02.02.04.01 CURADO CON PRODUCTO QUIMICO m2 40.38 0.90 36.34 -
02.02.05 REVOQUES Y ENLUCIDOS 527.46 -
02.02.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 33.92 15.55 527.46 -
C/IMPERMEABILIZANTES
02.02.06 CARPINTERIA METALICA 582.88 -
02.02.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 8.00 72.86 582.88 -
02.02.07 PINTURA 366.34 -
02.02.07.01 PINTURA ANTICORROCIVA A DOS MANOS m2 33.92 10.80 366.34 -
02.02.08 ACCESORIOS 786.32 -
02.02.08.01 ABRAZADERA PVC SP CON REDUCCION DN 63 MM A Ø 1" und 8.00 98.29 786.32 -
02.03 VALVULA DE PURGA (02 UND) 1,637.06 -
02.03.01 TRABAJOS PRELIMINARES 2.85 -
02.03.01.01 LIMPIEZA MANUAL DE TERRENO m2 2.30 0.54 1.24 -
02.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 2.30 0.70 1.61 -
02.03.02 MOVIMIENTO DE TIERRAS 70.60 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
02.03.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.87 26.52 49.59 -
COMPACTADO
02.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 2.30 1.06 2.44 -
02.03.02.03 ELIMINACION MATERAIL EXCEDENTE m3 1.75 10.61 18.57 -
02.03.03 OBRAS DE CONCRETO SIMPLE 73.00 -
02.03.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" m3 0.09 28.93 2.60 -
COMPACTADO Y APISONADO E=0.10m
02.03.03.02 CONCRETO f'c = 140 kg/cm2 m3 0.25 281.59 70.40 -
02.03.04 OBRAS DE CONCRETO ESTRUCTURA 667.24 -
02.03.04.01 CONCRETO f'c=175 kg/cm2 m3 1.05 344.91 362.16 -
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 14.02 21.76 305.08 -
02.03.05 CARPINTERIA METALICA 145.72 -
02.03.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 2.00 72.86 145.72 -
02.03.06 PINTURA 34.07 -
02.03.06.01 PINTURA LATEX SATINADO A DOS MANOS m2 4.08 8.35 34.07 -
02.03.07 ACCESORIOS 643.58 -
02.03.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM und 2.00 321.79 643.58 -
02.04 CAMARA ROMPE PRESION (02 UNID) 2,336.78 -
02.04.01 TRABAJOS PRELIMINARES 4.57 -
02.04.01.01 LIMPIEZA MANUAL DE TERRENO m2 3.69 0.54 1.99 -
02.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 3.69 0.70 2.58 -
02.04.02 MOVIMIENTO DE TIERRAS 144.01 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
02.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 3.79 26.52 100.51 -
COMPACTADO
02.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 3.10 1.06 3.29 -
02.04.02.03 ELIMINACION MATERAIL EXCEDENTE m3 3.79 10.61 40.21 -
02.04.03 OBRAS DE CONCRETO SIMPLE 378.67 -
02.04.03.01 ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX m2 5.12 54.70 280.06 -
6", E=20m
02.04.03.02 CONCRETO f'c=100 kg/cm2 m3 0.14 217.82 30.49 -
02.04.03.03 CONCRETO f'c=140 kg/cm2 m3 0.14 253.43 35.48 -
02.04.03.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.50 21.76 32.64 -
02.04.04 OBRAS DE CONCRETO ARMADO 1,329.04 -
02.04.04.01 CONCRETO f'c=210KG/CM2 m3 1.81 368.69 667.33 -
02.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 20.32 21.76 442.16 -
02.04.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 54.21 4.05 219.55 -
02.04.05 CURADO DE CONCRETO 1.63 -
02.04.05.01 CURADO CON PRODUCTO QUIMICO m2 1.81 0.90 1.63 -
02.04.06 REVOQUES Y ENLUCIDOS 111.96 -
02.04.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 7.20 15.55 111.96 -
C/IMPERMEABILIZANTES
02.04.07 CARPINTERIA METALICA 145.72 -
02.04.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 2.00 72.86 145.72 -
02.04.08 PINTURA 43.20 -
02.04.08.01 PINTURA ANTICORROCIVA A DOS MANOS m2 4.00 10.8 43.20 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
02.04.09 ACCESORIOS 177.98 -
02.04.09.01 ACCESORIO DE CAMARA ROMPE PRESION und 2.00 88.99 177.98 -
2.05 RESERVORIO DE UNINI V=15M3 (01UNID) 13,456.59 -
02.05.01 TRABAJOS PRELIMINARES 36.16 -
02.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 29.16 0.54 15.75 29.16
02.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 29.16 0.70 20.41 29.16
02.05.02 MOVIMIENTO DE TIERRAS 208.08 -
02.05.02.01 CORTE C/MAQUINARIA EN TERRENO DE MATERIAL m3 7.22 15.55 112.27 7.22
COMPACTO
02.05.02.02 ELIMINACION MATERAIL EXCEDENTE m3 9.03 10.61 95.81 9.03
02.05.03 OBRAS DE CONCRETO SIMPLE 810.29 -
02.05.03.01 CONCRETO f'c=100 kg/cm2 m3 3.72 217.82 810.29 3.72
02.05.04 OBRAS DE CONCRETO ARMADO 6,438.62 -
02.05.04.01 CONCRETO f'c=210KG/CM2 m3 10.10 368.69 3,723.77 10.10
02.05.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 324.86 4.05 1,315.68 324.86
02.05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 64.30 21.76 1,399.17 64.30
02.05.05 CURADO DE CONCRETO 240.48 -
02.05.05.01 CURADO CON PRODUCTO QUIMICO m2 64.30 3.74 240.48 64.30
02.05.06 REVOQUES Y ENLUCIDOS 1,675.20 -
02.05.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 32.55 18.12 589.81 32.55
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
02.05.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 59.90 18.12 1,085.39 59.90
ACABADO PULIDO
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
02.05.07 CARPINTERIA METALICA 867.41 -
02.05.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 1.00 72.86 72.86 1.00
02.05.07.02 ESCALERA INTERIOR METALICA PREFABRICADA DE TUB und 1.00 169.91 169.91 -
F°G° DE 11/2"
02.05.07.03 ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB und 1.00 294.82 294.82 -
F°G° DE 11/2"
02.05.07.04 VENTILACION DE F°G° DE DN=75MM und 2.00 164.91 329.82 1.00
02.05.08 PINTURA 1,583.58 -
02.05.08.01 PINTURA LATEX SATINADO A DOS MANOS m2 38.72 17.42 674.50 -
02.05.08.02 PINTURA ANTICORROCIVA A DOS MANOS m2 33.62 27.04 909.08 -
02.05.09 VALVULAS, ACCESORIOS Y TUBERIA 964.35 -
02.05.09.01 ACCESORIO P/INGRESO DE RESERVORIO DN 63MM und 1.00 208.62 208.62 -
02.05.09.02 ACCESORIO P/SALIDA DE RESERVORIO und 1.00 366.59 366.59 -
02.05.09.03 ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA und 1.00 389.14 389.14 -
02.05.10 CASETA DE CLORACION (01 UND) 632.42 -
02.05.10.01 TRABAJOS PRELIMINARES -
02.05.10.01.01 LIMPIEZA MANUAL DE TERRENO m2 0.36 0.54 0.19 0.36
02.05.10.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 0.36 0.70 0.25 0.36
02.05.10.02 MOVIMIENTO DE TIERRAS -
02.05.10.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 0.22 26.52 5.83 0.22
COMPACTADO
02.05.10.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 0.36 1.06 0.38 0.36
02.05.10.02.03 ELIMINACION MATERAIL EXCEDENTE m3 0.36 10.61 3.82 0.36
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
02.05.10.03 OBRAS DE CONCRETO ARMADO -
02.05.10.03.01 CONCRETO f'c=210KG/CM2 m3 0.48 368.69 176.97 0.48
02.05.10.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 18.83 4.05 76.26 18.83
02.05.10.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.00 21.76 21.76 1.00
02.05.10.04 CURADO DE CONCRETO -
02.05.10.04.01 CURADO CON PRODUCTO QUIMICO m2 2.00 3.74 7.48 2.00
02.05.10.05 REVOQUES Y ENLUCIDOS -
02.05.10.05.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 2.00 16.16 32.32 2.00
ACABADO FROTACHADO
02.05.10.06 SUMINISTRO E INSTALACION DE ACCESORIOS -
02.05.10.06.01 SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE glb 1.00 307.16 307.16 -
CLORACION
2.06 RED DE DISTRIBUCION UNINI (L=4+622.78m) 199,623.47 -
02.06.01 TRABAJOS PRELIMINARES 4,923.26 -
02.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 2,311.39 0.54 1,248.15 2,311.39
02.06.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 2,311.39 1.59 3,675.11 2,311.39
02.06.02 MOVIMIENTO DE TIERRAS 154,373.06 -
02.06.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL m3 2,311.39 26.52 61,298.06 2,311.39
COMPACTADO
02.06.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 4,622.78 1.06 4,900.15 4,622.78
MATERIAL COMPACTADO
02.06.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 4,622.78 4.70 21,727.07 4,622.78
02.06.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 4,622.78 2.71 12,527.73 4,622.78
(0.60 x 0.20 m)
02.06.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 3,698.22 14.58 53,920.05 3,698.22
ZARANDEADO
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
02.06.03 INSTALACION DE TUBERIA 27,992.70 -
02.06.03.01 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2" m 2,428.78 8.00 19,430.24 2,428.78
02.06.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4" m 299.00 4.49 1,342.51 299.00
02.06.03.03 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2" m 1,895.00 3.81 7,219.95 1,895.00
02.06.04 PRUEBA DE CALIDAD 4,021.82 -
02.06.04.01 DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA m 4,622.78 0.87 4,021.82 -
DE AGUA
02.06.05 VALVULA DE AIRE DISTR (03 UND) 2,323.14 -
02.06.05.01 TRABAJOS PRELIMINARES -
02.06.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 2.43 0.54 1.31 -
02.06.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 2.43 0.7 1.70 -
02.06.05.02 MOVIMIENTO DE TIERRAS -
02.06.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.46 26.52 38.72 -
COMPACTADO
02.06.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 2.43 1.06 2.58 -
02.06.05.02.03 ELIMINACION MATERAIL EXCEDENTE m3 1.46 10.61 15.49 -
02.06.05.03 OBRAS DE CONCRETO SIMPLE -
02.06.05.03.01 CONCRETO f'c=175 kg/cm2 m3 1.51 344.91 520.81 -
02.06.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 28.35 21.76 616.90 -
02.06.05.04 CURADO DE CONCRETO -
02.06.05.04.01 CURADO CON PRODUCTO QUIMICO m2 28.35 0.9 25.52 -
02.06.05.05 REVOQUES Y ENLUCIDOS -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
02.06.05.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 12.72 15.55 197.80 -
C/IMPERMEABILIZANTES
02.06.05.06 CARPINTERIA METALICA -
02.06.05.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 3.00 72.86 218.58 -
02.06.05.07 PINTURA -
02.06.05.07.01 PINTURA ANTICORROCIVA A DOS MANOS m2 22.95 10.8 247.86 -
02.06.05.08 ACCESORIOS -
02.06.05.08.01 ABRAZADERA PVC SP CON REDUCCION DN 50 MM A Ø 1" und 3.00 145.29 435.87 -
02.06.06 VALVULA DE PURGA DISTR (04 UND) 2,986.07 -
02.06.06.01 TRABAJOS PRELIMINARES -
02.06.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 8.64 0.54 4.67 -
02.06.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 8.64 0.70 6.05 -
02.06.06.02 MOVIMIENTO DE TIERRAS -
02.06.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 4.92 26.52 130.48 -
COMPACTADO
02.06.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 4.60 1.06 4.88 -
02.06.06.02.03 ELIMINACION MATERAIL EXCEDENTE m3 4.68 10.61 49.65 -
02.06.06.03 OBRAS DE CONCRETO SIMPLE -
02.06.06.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" m3 0.20 28.93 5.79 -
COMPACTADO Y APISONADO E=0.10m
02.06.06.03.02 CONCRETO f'c = 140 kg/cm2 m3 0.52 281.59 146.43 -
02.06.06.04 OBRAS DE CONCRETO ESTRUCTURA -
02.06.06.04.01 CONCRETO f'c=175 kg/cm2 m3 2.28 335.08 763.98 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
02.06.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 12.84 21.76 279.40 -
02.06.06.05 CARPINTERIA METALICA -
02.06.06.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 4.00 72.86 291.44 -
02.06.06.06 PINTURA 0 -
02.06.06.06.01 PINTURA LATEX SATINADO A DOS MANOS m2 8.16 8.35 68.14 -
02.06.06.07 ACCESORIOS -
02.06.06.08 ACCESORIOS P/VALVULA DE PURGA DE DN 50MM und 4.00 308.79 1,235.16 -
02.06.07 VALVULA DE CONTROL (03 UND) 3,003.42 -
02.06.07.01 TRABAJOS PRELIMINARES -
02.06.07.01.01 LIMPIEZA MANUAL DE TERRENO m2 3.24 0.54 1.75 -
02.06.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 3.24 0.70 2.27 -
02.06.07.02 MOVIMIENTO DE TIERRAS -
02.06.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 2.91 26.52 77.17 -
COMPACTADO
02.06.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 3.24 1.06 3.43 -
02.06.07.02.03 ELIMINACION MATERAIL EXCEDENTE m3 3.48 10.61 36.92 -
02.06.07.03 OBRAS DE CONCRETO SIMPLE -
02.06.07.03.01 CONCRETO f'c=175 kg/cm2 m3 3.06 317.40 971.24 -
02.06.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 9.72 21.76 211.51 -
02.06.07.04 CARPINTERIA METALICA -
02.06.07.04.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 3.00 57.79 173.37 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
02.06.07.05 PINTURA -
02.06.07.05.01 PINTURA LATEX SATINADO A DOS MANOS m2 11.76 8.35 98.20 -
02.06.07.06 ACCESORIOS -
02.06.07.06.01 ACCESORIOS V. CONTROL 1" und 4.00 136.56 546.24 -
02.06.07.06.02 ACCESORIOS V. CONTROL 3/4" und 11.00 80.12 881.32 -
2.07 CONEXIONES DOMICILIARIAS ALTO UNINI (63 UNID.) 24,258.45 -
02.07.01 TRABAJOS PRELIMINARES 234.36 -
02.07.01.01 LIMPIEZA MANUAL DE TERRENO m2 189.00 0.54 102.06 -
02.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 189.00 0.70 132.30 -
02.07.02 MOVIMIENTO DE TIERRAS 7,920.15 -
02.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 189.00 26.52 5,012.28 -
COMPACTADO
02.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 204.00 1.06 216.24 -
02.07.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 70.20 15.49 1,087.40 -
ZARANDEADO
02.07.02.04 ELIMINACION MATERAIL EXCEDENTE m3 151.20 10.61 1,604.23 -
02.07.03 OBRAS DE CONCRETO SIMPLE 2,104.08 -
02.07.03.01 CONCRETO f'c=175 kg/cm2 m3 6.05 320.59 1,939.57 -
02.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.56 21.76 164.51 -
02.07.04 CONEXIONES DOMICILIARIA (63 UNID) 13,999.86 -
02.07.04.01 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN und 63.00 222.22 13,999.86 10.00
CONEXIONES DOMICIALIARIAS
03 SERVICIO DE AGUA POTABLE MONTE SINAI 188,269.20 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.01 LINEA DE ADUCCION (1+473 KM) 50,939.28 -
03.01.01 TRABAJOS PRELIMINARES 1,487.73 -
03.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 736.50 0.54 397.71 736.50
03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 736.50 1.48 1,090.02 736.50
03.01.02 MOVIMIENTO DE TIERRAS 34,544.79 -
03.01.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA m3 589.20 26.52 15,625.58 400.00
03.01.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 1,473.00 1.06 1,561.38 1,000.00
MATERIAL COMPACTADO
03.01.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 1,473.00 4.70 6,923.10 1,000.00
03.01.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 1,473.00 2.71 3,991.83 1,000.00
(0.60 x 0.20 m)
03.01.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 441.90 14.58 6,442.90 300.00
ZARANDEADO
03.01.03 INSTALACION DE TUBERIA 13,934.58 -
03.01.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO m 1,473.00 9.46 13,934.58 1,000.00
03.01.04 PRUEBA DE CALIDAD 972.18 -
03.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA m 1,473.00 0.66 972.18 -
DE AGUA
03.02 VALVULA DE AIRE (03 UND) 1,916.94 -
03.02.01 TRABAJOS PRELIMINARES 3.01 -
03.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 2.43 0.54 1.31 -
03.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 2.43 0.70 1.70 -
03.02.02 MOVIMIENTO DE TIERRAS 56.79 -
03.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.46 26.52 38.72 -
COMPACTADO
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 2.43 1.06 2.58 -
03.02.02.03 ELIMINACION MATERAIL EXCEDENTE m3 1.46 10.61 15.49 -
03.02.03 OBRAS DE CONCRETO SIMPLE 853.74 -
03.02.03.01 CONCRETO f'c=175 kg/cm2 m3 1.51 344.91 520.81 -
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 15.30 21.76 332.93 -
03.02.04 CURADO DE CONCRETO 13.77 -
03.02.04.01 CURADO CON PRODUCTO QUIMICO m2 15.30 0.90 13.77 -
03.02.05 REVOQUES Y ENLUCIDOS 197.80 -
03.02.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 12.72 15.55 197.80 -
C/IMPERMEABILIZANTES
03.02.06 CARPINTERIA METALICA 218.58 -
03.02.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 3.00 72.86 218.58 -
03.02.07 PINTURA 137.38 -
03.02.07.01 PINTURA ANTICORROCIVA A DOS MANOS m2 12.72 10.80 137.38 -
03.02.08 ACCESORIOS 435.87 -
03.02.08.01 ABRAZADERA PVC SP CON REDUCCION DN 63 MM A Ø 1" und 3.00 145.29 435.87 -
03.03 VALVULA DE PURGA (01 UND) 803.79 -
03.03.01 TRABAJOS PRELIMINARES 1.43 -
03.03.01.01 LIMPIEZA MANUAL DE TERRENO m2 1.15 0.54 0.62 -
03.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 1.15 0.70 0.81 -
03.03.02 MOVIMIENTO DE TIERRAS 35.49 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.03.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 0.94 26.52 24.93 -
COMPACTADO
03.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 1.15 1.06 1.22 -
03.03.02.03 ELIMINACION MATERAIL EXCEDENTE m3 0.88 10.61 9.34 -
03.03.03 OBRAS DE CONCRETO SIMPLE 38.06 -
03.03.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" m3 0.05 28.93 1.45 -
COMPACTADO Y APISONADO E=0.10m
03.03.03.02 CONCRETO f'c = 140 kg/cm2 m3 0.13 281.59 36.61 -
03.03.04 OBRAS DE CONCRETO ESTRUCTURA 330.13 -
03.03.04.01 CONCRETO f'c=175 kg/cm2 m3 0.53 335.08 177.59 -
03.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.01 21.76 152.54 -
03.03.05 CARPINTERIA METALICA 72.86 -
03.03.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 1.00 72.86 72.86 -
03.03.06 PINTURA 17.03 -
03.03.06.01 PINTURA LATEX SATINADO A DOS MANOS m2 2.04 8.35 17.03 -
03.03.07 ACCESORIOS 308.79 -
03.03.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM und 1.00 308.79 308.79 -
03.04 RESERVORIO MONTE SINAI V=25M3 (01UNID) 36,260.71 -
03.04.01 TRABAJOS PRELIMINARES 57.74 -
03.04.01.01 LIMPIEZA MANUAL DE TERRENO m2 46.94 0.54 25.35 46.94
03.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 46.94 0.69 32.39 46.94
03.04.02 MOVIMIENTO DE TIERRAS 1,221.61 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.04.02.01 CORTE C/MAQUINARIA EN TERRENO DE MATERIAL m3 41.75 15.54 648.80 41.75
COMPACTO
03.04.02.02 REFINE Y NIVELACION DE PLATAFORMA m2 21.50 1.04 22.36 21.50
03.04.02.03 ELIMINACION MATERAIL EXCEDENTE m3 51.88 10.61 550.45 51.88
03.04.03 OBRAS DE CONCRETO SIMPLE 1,044.40 -
03.04.03.01 CONCRETO f'c=100 kg/cm2 m3 4.66 224.12 1,044.40 4.66
03.04.04 OBRAS DE CONCRETO ARMADO 11,002.13 -
03.04.04.01 CONCRETO f'c=210KG/CM2 m3 15.69 368.69 5,784.75 15.69
03.04.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 785.99 4.05 3,183.26 785.99
03.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 93.48 21.76 2,034.12 93.48
03.04.05 CURADO DE CONCRETO 349.62 -
03.04.05.01 CURADO CON PRODUCTO QUIMICO m2 93.48 3.74 349.62 93.48
03.04.06 REVOQUES Y ENLUCIDOS 1,345.47 -
03.04.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 38.72 18.86 730.26 38.72
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
03.04.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 32.62 18.86 615.21 32.62
ACABADO PULIDO
03.04.07 CARPINTERIA METALICA 867.41 -
03.04.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 1.00 72.86 72.86 1.00
03.04.07.02 ESCALERA INTERIOR METALICA PREFABRICADA DE TUB und 1.00 169.91 169.91 -
F°G° DE 11/2"
03.04.07.03 ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB und 1.00 294.82 294.82 -
F°G° DE 11/2"
03.04.07.04 VENTILACION DE F°G° DE DN=75MM und 2.00 164.91 329.82 1.00
03.04.08 PINTURA 1,583.58 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.04.08.01 PINTURA LATEX SATINADO A DOS MANOS m2 38.72 17.42 674.50 -
03.04.08.02 PINTURA ANTICORROCIVA A DOS MANOS m2 33.62 27.04 909.08 -
03.04.09 VALVULAS, ACCESORIOS Y TUBERIA 964.35 -
03.04.09.01 ACCESORIO P/INGRESO DE RESERVORIO DN 63MM und 1.00 208.62 208.62 -
03.04.09.02 ACCESORIO P/SALIDA DE RESERVORIO und 1.00 366.59 366.59 -
03.04.09.03 ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA und 1.00 389.14 389.14 -
03.04.10 CASETA DE CLORACION (01 UND) 632.42 -
03.04.10.01 TRABAJOS PRELIMINARES -
03.04.10.01.01 LIMPIEZA MANUAL DE TERRENO m2 0.36 0.54 0.19 0.36
03.04.10.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 0.36 0.70 0.25 0.36
03.04.10.02 MOVIMIENTO DE TIERRAS -
03.04.10.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 0.22 26.52 5.83 0.22
COMPACTADO
03.04.10.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 0.36 1.06 0.38 0.36
03.04.10.02.03 ELIMINACION MATERAIL EXCEDENTE m3 0.36 10.61 3.82 0.36
03.04.10.03 OBRAS DE CONCRETO ARMADO -
03.04.10.03.01 CONCRETO f'c=210KG/CM2 m3 0.48 368.69 176.97 0.48
03.04.10.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 18.83 4.05 76.26 18.83
03.04.10.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.00 21.76 21.76 1.00
03.04.10.04 CURADO DE CONCRETO -
03.04.10.04.01 CURADO CON PRODUCTO QUIMICO m2 2.00 3.74 7.48 2.00
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.04.10.05 REVOQUES Y ENLUCIDOS -
03.04.10.05.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 2.00 16.16 32.32 2.00
ACABADO FROTACHADO
03.04.10.06 SUMINISTRO E INSTALACION DE ACCESORIOS -
03.04.10.06.01 SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE glb 1.00 307.16 307.16 -
CLORACION
03.04.11 CERCO PERIMETRICO (L=220.00 m) 17,191.98 -
03.04.11.01 TRABAJOS PRELIMINARES -
03.04.11.01.01 LIMPIEZA MANUAL DE TERRENO m2 220.00 0.54 118.80 -
03.04.11.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 220.00 0.70 154.00 -
03.04.11.02 MOVIMIENTO DE TIERRAS -
03.04.11.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 18.00 26.52 477.36 -
COMPACTADO
03.04.11.02.02 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 4.50 15.93 71.69 -
ZARANDEADO
03.04.11.02.03 REFINE Y NIVELACION DE FONDO DE TERRENO m2 45.00 1.06 47.70 -
03.04.11.02.04 ELIMINACION MATERAIL EXCEDENTE m3 16.88 10.61 179.10 -
03.04.11.03 OBRAS DE CONCRETO SIMPLE -
03.04.11.03.01 CONCRETO f'c=140 kg/cm2 m3 18.03 261.29 4,711.06 -
03.04.11.04 CERCO PERIMETRICO CON MALLA OLIMPICA GALVANIZADA -
03.04.11.04.01 MALLA OLIMPICA GALVANIZADA 2"X2" #12 DE h=1.43m CON m 220.00 12.55 2,761.00 -
MARCO ANGULAR 1 1/2"x1 1/2"x1/8"
03.04.11.04.02 PUERTA C/MALLA DE TUBO F°G° Ø=1 1/2", DE und 1.00 287.95 287.95 -
4.0x1.80M.TIPO II
03.04.11.04.03 PINTURA ESMALTE EN PUERTAS Y VENTANAS A DOS m2 396.00 21.17 8,383.32 -
MANOS
3.05 RED DE DISTRIBUCION MONTE SINAI (L=1+681.00m) 67,820.73 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.05.01 TRABAJOS PRELIMINARES 1,790.27 -
03.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 840.50 0.54 453.87 840.50
03.05.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 840.50 1.59 1,336.40 840.50
03.05.02 MOVIMIENTO DE TIERRAS 46,331.72 -
03.05.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL m3 840.50 26.52 22,290.06 -
COMPACTADO
03.05.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 1,681.00 1.06 1,781.86 -
MATERIAL COMPACTADO
03.05.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 1,681.00 4.70 7,900.70 -
03.05.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 1,681.00 2.71 4,555.51 -
(0.60 x 0.20 m)
03.05.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 672.40 14.58 9,803.59 -
ZARANDEADO
03.05.03 INSTALACION DE TUBERIA 10,392.55 -
03.05.03.01 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2" m 356.00 3.81 1,356.36 -
03.05.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4" m 275.00 4.49 1,234.75 -
03.05.03.03 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1" m 744.00 6.96 5,178.24 -
03.05.03.04 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2" m 186.00 8.00 1,488.00 -
03.05.03.05 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO m 120.00 9.46 1,135.20 -
03.05.04 PRUEBA DE CALIDAD 1,462.47 -
03.05.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA m 1,681.00 0.87 1,462.47 -
DE AGUA
03.05.05 VALVULA DE AIRE (03 UND) 2,323.14 -
03.05.05.01 TRABAJOS PRELIMINARES -
03.05.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 2.43 0.54 1.31 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.05.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 2.43 0.70 1.70 -
03.05.05.02 MOVIMIENTO DE TIERRAS -
03.05.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.46 26.52 38.72 -
COMPACTADO
03.05.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 2.43 1.06 2.58 -
03.05.05.02.03 ELIMINACION MATERAIL EXCEDENTE m3 1.46 10.61 15.49 -
03.05.05.03 OBRAS DE CONCRETO -
03.05.05.03.01 CONCRETO f'c=175 kg/cm2 m3 1.51 344.91 520.81 -
03.05.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 28.35 21.76 616.90 -
03.05.05.04 CURADO DE CONCRETO -
03.05.05.04.01 CURADO CON PRODUCTO QUIMICO m2 28.35 0.90 25.52 -
03.05.05.05 REVOQUES Y ENLUCIDOS -
03.05.05.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 12.72 15.55 197.80 -
C/IMPERMEABILIZANTES
03.05.05.06 CARPINTERIA METALICA -
03.05.05.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 3.00 72.86 218.58 -
03.05.05.07 PINTURA -
03.05.05.07.01 PINTURA ANTICORROCIVA A DOS MANOS m2 22.95 10.80 247.86 -
03.05.05.08 ACCESORIOS -
03.05.05.08.01 ABRAZADERA PVC SP CON REDUCCION DN 50 MM A Ø 1" und 3.00 145.29 435.87 -
03.05.06 VALVULA DE PURGA DISTR (04 UND) 2,986.07 -
03.05.06.01 TRABAJOS PRELIMINARES -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.05.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 8.64 0.54 4.67 -
03.05.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 8.64 0.70 6.05 -
03.05.06.02 MOVIMIENTO DE TIERRAS -
03.05.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 4.92 26.52 130.48 -
COMPACTADO
03.05.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 4.60 1.06 4.88 -
03.05.06.02.03 ELIMINACION MATERAIL EXCEDENTE m3 4.68 10.61 49.65 -
03.05.06.03 OBRAS DE CONCRETO SIMPLE -
03.05.06.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" m3 0.20 28.93 5.79 -
COMPACTADO Y APISONADO E=0.10m
03.05.06.03.02 CONCRETO f'c = 140 kg/cm2 m3 0.52 281.59 146.43 -
03.05.06.04 OBRAS DE CONCRETO ESTRUCTURA -
03.05.06.04.01 CONCRETO f'c=175 kg/cm2 m3 2.28 335.08 763.98 -
03.05.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 12.84 21.76 279.40 -
03.05.06.05 CARPINTERIA METALICA -
03.05.06.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 4.00 72.86 291.44 -
03.05.06.06 PINTURA -
03.05.06.06.01 PINTURA LATEX SATINADO A DOS MANOS m2 8.16 8.35 68.14 -
03.05.06.07 ACCESORIOS -
03.05.06.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 50MM und 4.00 308.79 1,235.16 -
03.05.07 VALVULA DE CONTROL (04 UND) 2,534.51 -
03.05.07.01 TRABAJOS PRELIMINARES -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.05.07.01.01 LIMPIEZA MANUAL DE TERRENO m2 4.32 0.54 2.33 -
03.05.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 4.32 0.70 3.02 -
03.05.07.02 MOVIMIENTO DE TIERRAS -
03.05.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 3.88 26.52 102.90 -
COMPACTADO
03.05.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 4.32 1.06 4.58 -
03.05.07.02.03 ELIMINACION MATERAIL EXCEDENTE m3 4.64 10.61 49.23 -
03.05.07.03 OBRAS DE CONCRETO SIMPLE -
03.05.07.03.01 CONCRETO f'c=175 kg/cm2 m3 4.08 317.40 1,294.99 -
03.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 12.96 21.76 282.01 -
03.05.07.04 CARPINTERIA METALICA -
03.05.07.04.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 4.00 57.79 231.16 -
03.05.07.05 PINTURA -
03.05.07.05.01 PINTURA LATEX SATINADO A DOS MANOS m2 15.68 8.35 130.93 -
03.05.07.06 ACCESORIOS -
03.05.07.06.01 ACCESORIOS V. CONTROL 1" und 2.00 136.56 273.12 -
03.05.07.06.02 ACCESORIOS V. CONTROL 3/4" und 2.00 80.12 160.24 -
03.06 CONEXIONES DOMICILIARIAS MONTE SINAI (88 UND) 30,527.75 -
03.06.01 TRABAJOS PRELIMINARES 392.83 -
03.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 316.80 0.54 171.07 -
03.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 316.80 0.70 221.76 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
03.06.02 MOVIMIENTO DE TIERRAS 0 0.00 8,013.90 -
03.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 168.96 26.52 4,480.82 -
COMPACTADO
03.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 211.20 1.06 223.87 -
03.06.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 95.20 15.93 1,516.54 -
ZARANDEADO
03.06.02.04 ELIMINACION MATERAIL EXCEDENTE m3 168.96 10.61 1,792.67 -
03.06.03 OBRAS DE CONCRETO SIMPLE 2,938.78 -
03.06.03.01 CONCRETO f'c=175 kg/cm2 m3 8.45 320.59 2,708.99 -
03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 10.56 21.76 229.79 -
03.06.04 CONEXIONES DOMICILIARIA (88 UNID) 19,182.24 -
03.06.04.01 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN und 88.00 217.98 19,182.24 -
CONEXIONES DOMICIALIARIAS
4 SERVICIO AGUA POTABLE PIRIARI 229,414.03 -
04.01 LINEA DE ADUCCION (3+120.00 KM) 114,619.44 -
04.01.01 TRABAJOS PRELIMINARES 3,135.60 -
04.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 1,560.00 0.53 826.80 1,560.00
04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 1,560.00 1.48 2,308.80 1,560.00
04.01.02 MOVIMIENTO DE TIERRAS 72,483.84 -
04.01.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA m3 1,248.00 26.02 32,472.96 400.00
04.01.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 3,120.00 1.04 3,244.80 1,000.00
MATERIAL COMPACTADO
04.01.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 3,120.00 4.70 14,664.00 1,000.00
04.01.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 3,120.00 2.71 8,455.20 1,000.00
(0.60 x 0.20 m)
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
04.01.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 936.00 14.58 13,646.88 300.00
ZARANDEADO
04.01.03 INSTALACION DE TUBERIA 36,972.00 -
04.01.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 75MM C/ANILLO m 3,120.00 11.85 36,972.00 1,000.00
04.01.04 PRUEBA DE CALIDAD 2,028.00 -
04.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA m 3,120.00 0.65 2,028.00 -
DE AGUA
04.02 CAMARA ROMPE PRESION (01 UNID) 1,162.83 -
04.02.01 TRABAJOS PRELIMINARES 2.30 -
04.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 1.85 0.54 1.00 -
04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 1.85 0.7 1.30 -
04.02.02 MOVIMIENTO DE TIERRAS 72.19 -
04.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.90 26.52 50.39 -
COMPACTADO
04.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 1.55 1.06 1.64 -
04.02.02.03 ELIMINACION MATERAIL EXCEDENTE m3 1.90 10.61 20.16 -
04.02.03 OBRAS DE CONCRETO SIMPLE 181.74 -
04.02.03.01 ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX m2 2.56 54.70 140.03 -
6", E=20m
04.02.03.02 CONCRETO f'c=100 kg/cm2 m3 0.07 217.82 15.25 -
04.02.03.03 CONCRETO f'c=140 kg/cm2 m3 0.04 253.43 10.14 -
04.02.03.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.75 21.76 16.32 -
04.02.04 OBRAS DE CONCRETO ARMADO 666.35 -
04.02.04.01 CONCRETO f'c=210KG/CM2 m3 0.91 368.69 335.51 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
04.02.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 10.16 21.76 221.08 -
04.02.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 27.10 4.05 109.76 -
04.02.05 CURADO DE CONCRETO 0.82 -
04.02.05.01 CURADO CON PRODUCTO QUIMICO m2 0.91 0.90 0.82 -
04.02.06 REVOQUES Y ENLUCIDOS 55.98 -
04.02.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 3.60 15.55 55.98 -
C/IMPERMEABILIZANTES
04.02.07 CARPINTERIA METALICA 72.86 -
04.02.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 1.00 72.86 72.86 -
04.02.08 PINTURA 21.60 -
04.02.08.01 PINTURA ANTICORROCIVA A DOS MANOS m2 2.00 10.80 21.60 -
04.02.09 ACCESORIOS 88.99 -
04.02.09.01 ACCESORIO DE CAMARA ROMPE PRESION und 1.00 88.99 88.99 -
4.03 RESERVORIO DE PIRIARI V=10M3 (01UNID) 12,275.39 -
04.03.01 TRABAJOS PRELIMINARES 28.57 -
04.03.01.01 LIMPIEZA MANUAL DE TERRENO m2 23.04 0.54 12.44 23.04
04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 23.04 0.70 16.13 23.04
04.03.02 MOVIMIENTO DE TIERRAS 158.37 -
04.03.02.01 CORTE C/MAQUINARIA EN TERRENO DE MATERIAL m3 5.12 15.55 79.62 5.12
COMPACTO
04.03.02.02 REFINE Y NIVELACION DE PLATAFORMA m2 10.24 1.06 10.85 10.24
04.03.02.03 ELIMINACION MATERAIL EXCEDENTE m3 6.40 10.61 67.90 6.40
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
04.03.03 OBRAS DE CONCRETO SIMPLE 228.60 -
04.03.03.01 CONCRETO f'c=100 kg/cm2 m3 1.02 224.12 228.60 1.02
04.03.04 OBRAS DE CONCRETO ARMADO 6,678.05 -
04.03.04.01 CONCRETO f'c=210KG/CM2 m3 12.02 368.69 4,431.65 12.02
04.03.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 280.76 4.05 1,137.08 280.76
04.03.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 50.98 21.76 1,109.32 50.98
04.03.05 CURADO DE CONCRETO 190.67 -
04.03.05.01 CURADO CON PRODUCTO QUIMICO m2 50.98 3.74 190.67 50.98
04.03.06 REVOQUES Y ENLUCIDOS 1,284.94 -
04.03.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 24.75 18.86 466.79 24.75
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
04.03.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 43.38 18.86 818.15 43.38
ACABADO PULIDO
04.03.07 CARPINTERIA METALICA 867.41 -
04.03.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 1.00 72.86 72.86 1.00
04.03.07.02 ESCALERA INTERIOR METALICA PREFABRICADA DE TUB und 1.00 169.91 169.91 -
F°G° DE 11/2"
04.03.07.03 ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB und 1.00 294.82 294.82 -
F°G° DE 11/2"
04.03.07.04 VENTILACION DE F°G° DE DN=75MM und 2.00 164.91 329.82 1.00
04.03.08 PINTURA 1,242.01 -
04.03.08.01 PINTURA LATEX SATINADO A DOS MANOS m2 33.92 17.42 590.89 -
04.03.08.02 PINTURA ANTICORROCIVA A DOS MANOS m2 24.08 27.04 651.12 -
04.03.09 VALVULAS, ACCESORIOS Y TUBERIA 964.35 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
04.03.09.01 ACCESORIO P/INGRESO DE RESERVORIO DN 63MM und 1.00 208.62 208.62 -
04.03.09.02 ACCESORIO P/SALIDA DE RESERVORIO und 1.00 366.59 366.59 -
04.03.09.03 ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA und 1.00 389.14 389.14 -
04.03.10 CASETA DE CLORACION (01 UND) 632.42 -
04.03.10.01 TRABAJOS PRELIMINARES -
04.03.10.01.01 LIMPIEZA MANUAL DE TERRENO m2 0.36 0.54 0.19 0.36
04.03.10.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 0.36 0.70 0.25 0.36
04.03.10.02 MOVIMIENTO DE TIERRAS -
04.03.10.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 0.22 26.52 5.83 0.22
COMPACTADO
04.03.10.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 0.36 1.06 0.38 0.36
04.03.10.02.03 ELIMINACION MATERAIL EXCEDENTE m3 0.36 10.61 3.82 0.36
04.03.10.03 OBRAS DE CONCRETO ARMADO -
04.03.10.03.01 CONCRETO f'c=210KG/CM2 m3 0.48 368.69 176.97 0.48
04.03.10.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 18.83 4.05 76.26 18.83
04.03.10.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.00 21.76 21.76 1.00
04.03.10.04 CURADO DE CONCRETO -
04.03.10.04.01 CURADO CON PRODUCTO QUIMICO m2 2.00 3.74 7.48 2.00
04.03.10.05 REVOQUES Y ENLUCIDOS -
04.03.10.05.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 2.00 16.16 32.32 2.00
ACABADO FROTACHADO
04.03.10.06 SUMINISTRO E INSTALACION DE ACCESORIOS -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
04.03.10.06.01 SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE glb 1.00 307.16 307.16 -
CLORACION
4.04 CAMARA DE DISTRIBUCION DE CAUDALES 02 SALIDAS (01 6,804.09 -
UNID)
04.04.01 TRABAJOS PRELIMINARES 9.69 -
04.04.01.01 LIMPIEZA MANUAL DE TERRENO m2 7.81 0.54 4.22 7.81
04.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 7.81 0.70 5.47 7.81
04.04.02 MOVIMIENTO DE TIERRAS 560.84 -
04.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 16.46 26.52 436.52 16.46
COMPACTADO
04.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 7.81 2.66 20.77 7.81
04.04.02.03 ELIMINACION MATERAIL EXCEDENTE m3 9.76 10.61 103.55 9.76
04.04.03 OBRAS DE CONCRETO SIMPLE 6.72 -
04.04.03.01 CONCRETO f'c=100 kg/cm2 m3 0.03 224.12 6.72 0.03
04.04.04 OBRAS DE CONCRETO ARMADO 4,600.90 -
04.04.04.01 CONCRETO f'c=210KG/CM2 m3 7.17 368.69 2,643.51 7.17
04.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 73.75 21.76 1,604.80 73.75
04.04.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 87.06 4.05 352.59 87.06
04.04.05 CURADO DE CONCRETO 275.83 -
04.04.05.01 CURADO CON PRODUCTO QUIMICO m2 73.75 3.74 275.83 73.75
04.04.06 REVOQUES Y ENLUCIDOS 707.82 -
04.04.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 37.53 18.86 707.82 37.53
C/IMPERMEABILIZANTES
04.04.07 CARPINTERIA METALICA 145.72 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
04.04.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 2.00 72.86 145.72 -
04.04.08 PINTURA 187.78 -
04.04.08.01 PINTURA ANTICORROCIVA A DOS MANOS m2 21.81 8.61 187.78 -
04.04.09 ACCESORIOS 308.79 -
04.04.09.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM und 1.00 308.79 308.79 -
4.05 RED DE DISTRIBUCION PIRIARI (L=2+120.00 m) 82,425.37 -
04.05.01 TRABAJOS PRELIMINARES 2,215.40 -
04.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 1,060.00 0.53 561.80 1,060.00
04.05.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 1,060.00 1.56 1,653.60 1,060.00
04.05.02 MOVIMIENTO DE TIERRAS 57,859.04 -
04.05.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL m3 1,060.00 26.02 27,581.20 1,060.00
COMPACTADO
04.05.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 2,120.00 1.04 2,204.80 2,120.00
MATERIAL COMPACTADO
04.05.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 2,120.00 4.7 9,964.00 2,120.00
04.05.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 2,120.00 2.71 5,745.20 2,120.00
(0.60 x 0.20 m)
04.05.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 848.00 14.58 12,363.84 848.00
ZARANDEADO
04.05.03 INSTALACION DE TUBERIA 14,254.12 -
04.05.03.01 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2" m 314.00 3.81 1,196.34 314.00
04.05.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4" m 282.00 4.49 1,266.18 282.00
04.05.03.03 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1" m 385.00 6.96 2,679.60 385.00
04.05.03.04 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2" m 1,139.00 8.00 9,112.00 1,139.00
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
04.05.04 PRUEBA DE CALIDAD 1,844.40 -
04.05.04.01 DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA m 2,120.00 0.87 1,844.40 -
DE AGUA
04.05.05 VALVULA DE AIRE (03 UND) 2,323.14 -
04.05.05.01 TRABAJOS PRELIMINARES -
04.05.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 2.43 0.54 1.31 -
04.05.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 2.43 0.70 1.70 -
04.05.05.02 MOVIMIENTO DE TIERRAS -
04.05.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.46 26.52 38.72 -
COMPACTADO
04.05.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 2.43 1.06 2.58 -
04.05.05.02.03 ELIMINACION MATERAIL EXCEDENTE m3 1.46 10.61 15.49 -
04.05.05.03 OBRAS DE CONCRETO SIMPLE -
04.05.05.03.01 CONCRETO f'c=175 kg/cm2 m3 1.51 344.91 520.81 -
04.05.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 28.35 21.76 616.90 -
04.05.05.04 CURADO DE CONCRETO -
04.05.05.04.01 CURADO CON PRODUCTO QUIMICO m2 28.35 0.9 25.52 -
04.05.05.05 REVOQUES Y ENLUCIDOS -
04.05.05.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 12.72 15.55 197.80 -
C/IMPERMEABILIZANTES
04.05.05.06 CARPINTERIA METALICA -
04.05.05.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 3.00 72.86 218.58 -
04.05.05.07 PINTURA -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
04.05.05.07.01 PINTURA ANTICORROCIVA A DOS MANOS m2 22.95 10.80 247.86 -
04.05.05.08 ACCESORIOS -
04.05.05.08.01 ABRAZADERA PVC SP CON REDUCCION DN 50 MM A Ø 1" und 3.00 145.29 435.87 -
04.05.06 VALVULA DE PURGA (02 UND) 1,451.20 -
04.05.06.01 TRABAJOS PRELIMINARES -
04.05.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 4.32 0.54 2.33 -
04.05.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 4.32 0.7 3.02 -
04.05.06.02 MOVIMIENTO DE TIERRAS -
04.05.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.96 26.52 51.98 -
COMPACTADO
04.05.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 2.30 1.06 2.44 -
04.05.06.02.03 ELIMINACION MATERAIL EXCEDENTE m3 1.84 10.61 19.52 -
04.05.06.03 OBRAS DE CONCRETO SIMPLE -
04.05.06.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" m3 0.09 28.93 2.60 -
COMPACTADO Y APISONADO E=0.10m
04.05.06.03.02 CONCRETO f'c = 140 kg/cm2 m3 0.25 281.59 70.40 -
04.05.06.04 OBRAS DE CONCRETO ESTRUCTURA -
04.05.06.04.01 CONCRETO f'c=175 kg/cm2 m3 1.14 317.4 361.84 -
04.05.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 6.42 21.76 139.70 -
04.05.06.05 CARPINTERIA METALICA -
04.05.06.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 2.00 72.86 145.72 -
04.05.06.06 PINTURA -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
04.05.06.06.01 PINTURA LATEX SATINADO A DOS MANOS m2 4.08 8.35 34.07 -
04.05.06.07 ACCESORIOS -
04.05.06.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 32 MM und 2.00 308.79 617.58 -
04.05.07 VALVULA DE CONTROL (04 UND) 2,478.07 -
04.05.07.01 TRABAJOS PRELIMINARES -
04.05.07.01.01 LIMPIEZA MANUAL DE TERRENO m2 4.32 0.54 2.33 -
04.05.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 4.32 0.70 3.02 -
04.05.07.02 MOVIMIENTO DE TIERRAS -
04.05.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 3.88 26.52 102.90 -
COMPACTADO
04.05.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 4.32 1.06 4.58 -
04.05.07.02.03 ELIMINACION MATERAIL EXCEDENTE m3 4.64 10.61 49.23 -
04.05.07.03 OBRAS DE CONCRETO SIMPLE -
04.05.07.03.01 CONCRETO f'c=175 kg/cm2 m3 4.08 317.40 1,294.99 -
04.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 12.96 21.76 282.01 -
04.05.07.04 CARPINTERIA METALICA -
04.05.07.04.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 4.00 57.79 231.16 -
04.05.07.05 PINTURA -
04.05.07.05.01 PINTURA LATEX SATINADO A DOS MANOS m2 15.68 8.35 130.93 -
04.05.07.06 ACCESORIOS -
04.05.07.06.01 ACCESORIOS V. CONTROL 1" und 1.00 136.56 136.56 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
04.05.07.06.02 ACCESORIOS V. CONTROL 3/4" und 3.00 80.12 240.36 -
4.06 CONEXIONES DOMICILIARIAS PIRIARI (35 UNID.) 12,126.91 -
04.06.01 TRABAJOS PRELIMINARES 153.72 -
04.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 126.00 0.53 66.78 -
04.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 126.00 0.69 86.94 -
04.06.02 MOVIMIENTO DE TIERRAS 3,212.27 -
04.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 67.20 26.02 1,748.54 -
COMPACTADO
04.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 84.00 1.04 87.36 -
04.06.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 42.20 15.72 663.38 -
ZARANDEADO
04.06.02.04 ELIMINACION MATERAIL EXCEDENTE m3 67.20 10.61 712.99 -
04.06.03 OBRAS DE CONCRETO SIMPLE 1,131.62 -
04.06.03.01 CONCRETO f'c=175 kg/cm2 m3 3.36 309.98 1,041.53 -
04.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 4.20 21.45 90.09 -
04.06.04 CONEXIONES DOMICILIARIA (35 UNID) 7,629.30 -
04.06.04.01 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN und 35.00 217.98 7,629.30 25.00
CONEXIONES DOMICIALIARIAS
5 SERVICIO DE AGUA POTABLE VISTA ALEGRE 404,172.09 -
5.01 LINEA DE CONDUCCION (2+760KM) 101,490.72 -
05.01.01 TRABAJOS PRELIMINARES 2,787.60 -
05.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 1,380.00 0.54 745.20 1,380.00
05.01.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 1,380.00 1.48 2,042.40 1,380.00
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.01.02 MOVIMIENTO DE TIERRAS 64,175.52 -
05.01.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA m3 1,104.00 26.02 28,726.08 1,104.00
05.01.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 2,760.00 1.06 2,925.60 2,760.00
MATERIAL COMPACTADO
05.01.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 2,760.00 4.70 12,972.00 2,760.00
05.01.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 2,760.00 2.71 7,479.60 2,760.00
(0.60 x 0.20 m)
05.01.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 828.00 14.58 12,072.24 828.00
ZARANDEADO
05.01.03 INSTALACION DE TUBERIA 32,706.00 -
05.01.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 75MM C/ANILLO m 2,760.00 11.85 32,706.00 2,760.00
05.01.04 PRUEBA DE CALIDAD 1,821.60 -
05.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA m 2,760.00 0.66 1,821.60 -
DE AGUA
05.02 VALVULA DE AIRE (07 UND) 5,730.79 -
05.02.01 TRABAJOS PRELIMINARES 7.03 -
05.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 5.67 0.54 3.06 -
05.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 5.67 0.7 3.97 -
05.02.02 MOVIMIENTO DE TIERRAS 132.25 -
05.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 3.40 26.52 90.17 -
COMPACTADO
05.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 5.67 1.06 6.01 -
05.02.02.03 ELIMINACION MATERAIL EXCEDENTE m3 3.40 10.61 36.07 -
05.02.03 OBRAS DE CONCRETO SIMPLE 2,656.95 -
05.02.03.01 CONCRETO f'c=175 kg/cm2 m3 3.53 344.91 1,217.53 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.15 21.76 1,439.42 -
05.02.04 CURADO DE CONCRETO 59.54 -
05.02.04.01 CURADO CON PRODUCTO QUIMICO m2 66.15 0.9 59.54 -
05.02.05 REVOQUES Y ENLUCIDOS 1,028.63 -
05.02.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 66.15 15.55 1,028.63 -
C/IMPERMEABILIZANTES
05.02.06 CARPINTERIA METALICA 510.02 -
05.02.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 7.00 72.86 510.02 -
05.02.07 PINTURA 578.34 -
05.02.07.01 PINTURA ANTICORROCIVA A DOS MANOS m2 53.55 10.80 578.34 -
05.02.08 ACCESORIOS 758.03 -
05.02.08.01 ABRAZADERA PVC SP CON REDUCCION DN 63 MM A Ø 1" und 7.00 108.29 758.03 -
05.03 VALVULA DE PURGA (06 UND) 6,102.71 -
05.03.01 TRABAJOS PRELIMINARES 8.49 -
05.03.01.01 LIMPIEZA MANUAL DE TERRENO m2 6.90 0.54 3.73 -
05.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 6.90 0.69 4.76 -
05.03.02 MOVIMIENTO DE TIERRAS 209.09 -
05.03.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 5.61 26.02 145.97 -
COMPACTADO
05.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 6.90 1.06 7.31 -
05.03.02.03 ELIMINACION MATERAIL EXCEDENTE m3 5.26 10.61 55.81 -
05.03.03 OBRAS DE CONCRETO SIMPLE 219.00 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.03.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" m3 0.27 28.93 7.81 -
COMPACTADO Y APISONADO E=0.10m
05.03.03.02 CONCRETO f'c = 140 kg/cm2 m3 0.75 281.59 211.19 -
05.03.04 OBRAS DE CONCRETO ARMADO 1,970.73 -
05.03.04.01 CONCRETO f'c=175 kg/cm2 m3 3.15 335.08 1,055.50 -
05.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 42.06 21.76 915.23 -
05.03.05 CARPINTERIA METALICA 437.16 -
05.03.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 6.00 72.86 437.16 -
05.03.06 PINTURA 170.34 -
05.03.06.01 PINTURA LATEX SATINADO A DOS MANOS m2 20.40 8.35 170.34 -
05.03.07 ACCESORIOS 3,087.90 -
05.03.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM und 10.00 308.79 3,087.90 -
5.04 CAMARA DE DISTRIBUCION DE CAUDALES 02 SALIDAS (01 6,804.09 -
UNID)
05.04.01 TRABAJOS PRELIMINARES 9.69 -
05.04.01.01 LIMPIEZA MANUAL DE TERRENO m2 7.81 0.54 4.22 7.81
05.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 7.81 0.7 5.47 7.81
05.04.02 MOVIMIENTO DE TIERRAS 560.84 -
05.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 16.46 26.52 436.52 16.46
COMPACTADO
05.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 7.81 2.66 20.77 7.81
05.04.02.03 ELIMINACION MATERAIL EXCEDENTE m3 9.76 10.61 103.55 9.76
05.04.03 OBRAS DE CONCRETO SIMPLE 6.72 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.04.03.01 CONCRETO f'c=100 kg/cm2 m3 0.03 224.12 6.72 0.03
05.04.04 OBRAS DE CONCRETO ARMADO 4,600.90 -
05.04.04.01 CONCRETO f'c=210KG/CM2 m3 7.17 368.69 2,643.51 7.17
05.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 73.75 21.76 1,604.80 73.75
05.04.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 87.06 4.05 352.59 87.06
05.04.05 CURADO DE CONCRETO 275.83 -
05.04.05.01 CURADO CON PRODUCTO QUIMICO m2 73.75 3.74 275.83 73.75
05.04.06 REVOQUES Y ENLUCIDOS 707.82 -
05.04.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 37.53 18.86 707.82 37.53
C/IMPERMEABILIZANTES
05.04.07 CARPINTERIA METALICA 145.72 -
05.04.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 2.00 72.86 145.72 -
05.04.08 PINTURA 187.78 -
05.04.08.01 PINTURA ANTICORROCIVA A DOS MANOS m2 21.81 8.61 187.78 -
05.04.09 ACCESORIOS 308.79 -
05.04.09.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM und 1.00 308.79 308.79 -
5.05 RESERVORIO DE VISTA ALEGRE V=8 M3 (01UNID) 12,257.97 -
05.05.01 TRABAJOS PRELIMINARES 28.57 -
05.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 23.04 0.54 12.44 23.04
05.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 23.04 0.70 16.13 23.04
05.05.02 MOVIMIENTO DE TIERRAS 158.37 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.05.02.01 CORTE C/MAQUINARIA EN TERRENO DE MATERIAL m3 5.12 15.55 79.62 5.12
COMPACTO
05.05.02.02 REFINE Y NIVELACION DE PLATAFORMA m2 10.24 1.06 10.85 10.24
05.05.02.03 ELIMINACION MATERAIL EXCEDENTE m3 6.40 10.61 67.90 6.40
05.05.03 OBRAS DE CONCRETO SIMPLE 228.60 -
05.05.03.01 CONCRETO f'c=100 kg/cm2 m3 1.02 224.12 228.60 1.02
05.05.04 OBRAS DE CONCRETO ARMADO 6,678.05 -
05.05.04.01 CONCRETO f'c=210KG/CM2 m3 12.02 368.69 4,431.65 12.02
05.05.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 280.76 4.05 1,137.08 280.76
05.05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 50.98 21.76 1,109.32 50.98
05.05.05 CURADO DE CONCRETO 190.67 -
05.05.05.01 CURADO CON PRODUCTO QUIMICO m2 50.98 3.74 190.67 50.98
05.05.06 REVOQUES Y ENLUCIDOS 1,284.94 -
05.05.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 24.75 18.86 466.79 24.75
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
05.05.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 43.38 18.86 818.15 43.38
ACABADO PULIDO
05.05.07 CARPINTERIA METALICA 867.41 -
05.05.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 1.00 72.86 72.86 1.00
05.05.07.02 ESCALERA INTERIOR METALICA PREFABRICADA DE TUB und 1.00 169.91 169.91 -
F°G° DE 11/2"
05.05.07.03 ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB und 1.00 294.82 294.82 -
F°G° DE 11/2"
05.05.07.04 VENTILACION DE F°G° DE DN=75MM und 2.00 164.91 329.82 1.00
05.05.08 PINTURA 1,224.59 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.05.08.01 PINTURA LATEX SATINADO A DOS MANOS m2 32.92 17.42 573.47 -
05.05.08.02 PINTURA ANTICORROCIVA A DOS MANOS m2 24.08 27.04 651.12 -
05.05.09 VALVULAS, ACCESORIOS Y TUBERIA 964.35 -
05.05.09.01 ACCESORIO P/INGRESO DE RESERVORIO DN 63MM und 1.00 208.62 208.62 -
05.05.09.02 ACCESORIO P/SALIDA DE RESERVORIO und 1.00 366.59 366.59 -
05.05.09.03 ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA und 1.00 389.14 389.14 -
05.05.10 CASETA DE CLORACION (01 UND) 632.42 -
05.05.10.01 TRABAJOS PRELIMINARES -
05.05.10.01.01 LIMPIEZA MANUAL DE TERRENO m2 0.36 0.54 0.19 0.36
05.05.10.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 0.36 0.70 0.25 0.36
05.05.10.02 MOVIMIENTO DE TIERRAS -
05.05.10.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 0.22 26.52 5.83 0.22
COMPACTADO
05.05.10.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 0.36 1.06 0.38 0.36
05.05.10.02.03 ELIMINACION MATERAIL EXCEDENTE m3 0.36 10.61 3.82 0.36
05.05.10.03 OBRAS DE CONCRETO ARMADO -
05.05.10.03.01 CONCRETO f'c=210KG/CM2 m3 0.48 368.69 176.97 0.48
05.05.10.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 18.83 4.05 76.26 18.83
05.05.10.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.00 21.76 21.76 1.00
05.05.10.04 CURADO DE CONCRETO -
05.05.10.04.01 CURADO CON PRODUCTO QUIMICO m2 2.00 3.74 7.48 2.00
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.05.10.05 REVOQUES Y ENLUCIDOS -
05.05.10.05.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 2.00 16.16 32.32 2.00
ACABADO FROTACHADO
05.05.10.06 SUMINISTRO E INSTALACION DE ACCESORIOS -
05.05.10.06.01 SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE glb 1.00 307.16 307.16 -
CLORACION
5.06 RED DE DISTRIBUCION VISTA ALEGRE (L=7+028.00 m) 255,122.64 -
05.06.01 TRABAJOS PRELIMINARES 7,484.82 -
05.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 3,514.00 0.54 1,897.56 3,514.00
05.06.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 3,514.00 1.59 5,587.26 3,514.00
05.06.02 MOVIMIENTO DE TIERRAS 193,705.74 -
05.06.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL m3 3,514.00 26.52 93,191.28 2,814.00
COMPACTADO
05.06.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 7,028.00 1.06 7,449.68 5,628.00
MATERIAL COMPACTADO
05.06.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 7,028.00 4.70 33,031.60 5,628.00
05.06.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 7,028.00 2.71 19,045.88 5,628.00
(0.60 x 0.20 m)
05.06.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 2,811.20 14.58 40,987.30 2,251.20
ZARANDEADO
05.06.03 INSTALACION DE TUBERIA 42,900.78 -
05.06.03.01 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2" m 1,027.00 3.81 3,912.87 527.00
05.06.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4" m 2,687.00 4.49 12,064.63 2,687.00
05.06.03.03 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1" m 868.00 6.96 6,041.28 868.00
05.06.03.04 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2" m 1,546.00 8.00 12,368.00 1,546.00
05.06.03.05 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO m 900.00 9.46 8,514.00 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.06.04 PRUEBA DE CALIDAD 6,114.36 -
05.06.04.01 DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA m 7,028.00 0.87 6,114.36 -
DE AGUA
05.06.05 VALVULA DE AIRE (02 UND) 1,593.08 -
05.06.05.01 TRABAJOS PRELIMINARES -
05.06.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 1.62 0.54 0.87 -
05.06.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 1.62 0.70 1.13 -
05.06.05.02 MOVIMIENTO DE TIERRAS -
05.06.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 0.97 26.52 25.72 -
COMPACTADO
05.06.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 1.62 1.06 1.72 -
05.06.05.02.03 ELIMINACION MATERAIL EXCEDENTE m3 0.97 10.61 10.29 -
05.06.05.03 OBRAS DE CONCRETO ARMADO -
05.06.05.03.01 CONCRETO f'c=175 kg/cm2 m3 1.01 344.91 348.36 -
05.06.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 18.90 21.76 411.26 -
05.06.05.04 CURADO DE CONCRETO -
05.06.05.04.01 CURADO CON PRODUCTO QUIMICO m2 18.90 0.90 17.01 -
05.06.05.05 REVOQUES Y ENLUCIDOS -
05.06.05.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 8.48 15.55 131.86 -
C/IMPERMEABILIZANTES
05.06.05.06 CARPINTERIA METALICA -
05.06.05.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 2.00 72.86 145.72 -
05.06.05.07 PINTURA -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.06.05.07.01 PINTURA ANTICORROCIVA A DOS MANOS m2 15.30 10.80 165.24 -
05.06.05.08 ACCESORIOS -
05.06.05.08.01 ACCESORIOS VALVULA DE AIRE D=110MM und 2.00 166.95 333.90 -
05.06.06 VALVULA DE PURGA (02 UND) 1,451.20 -
05.06.06.01 TRABAJOS PRELIMINARES -
05.06.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 4.32 0.54 2.33 -
05.06.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 4.32 0.70 3.02 -
05.06.06.02 MOVIMIENTO DE TIERRAS -
05.06.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.96 26.52 51.98 -
COMPACTADO
05.06.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 2.30 1.06 2.44 -
05.06.06.02.03 ELIMINACION MATERAIL EXCEDENTE m3 1.84 10.61 19.52 -
05.06.06.03 OBRAS DE CONCRETO SIMPLE -
05.06.06.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" m3 0.09 28.93 2.60 -
COMPACTADO Y APISONADO E=0.10m
05.06.06.03.02 CONCRETO f'c = 140 kg/cm2 m3 0.25 281.59 70.40 -
05.06.06.04 OBRAS DE CONCRETO ESTRUCTURA -
05.06.06.04.01 CONCRETO f'c=175 kg/cm2 m3 1.14 317.4 361.84 -
05.06.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 6.42 21.76 139.70 -
05.06.06.05 CARPINTERIA METALICA -
05.06.06.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 2.00 72.86 145.72 -
05.06.06.06 PINTURA -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.06.06.06.01 PINTURA LATEX SATINADO A DOS MANOS m2 4.08 8.35 34.07 -
05.06.06.07 ACCESORIOS -
05.06.06.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM und 2.00 308.79 617.58 -
05.06.07 VALVULA DE CONTROL (03 UND) 1,872.66 -
05.06.07.01 TRABAJOS PRELIMINARES -
05.06.07.01.01 LIMPIEZA MANUAL DE TERRENO m2 3.24 0.54 1.75 2.16
05.06.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 3.24 0.70 2.27 2.16
05.06.07.02 MOVIMIENTO DE TIERRAS -
05.06.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 2.91 26.52 77.17 1.94
COMPACTADO
05.06.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 3.24 1.06 3.43 2.16
05.06.07.02.03 ELIMINACION MATERAIL EXCEDENTE m3 3.48 10.61 36.92 2.32
05.06.07.03 OBRAS DE CONCRETO SIMPLE -
05.06.07.03.01 CONCRETO f'c=175 kg/cm2 m3 3.06 317.40 971.24 2.04
05.06.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 9.72 21.76 211.51 6.48
05.06.07.04 CARPINTERIA METALICA -
05.06.07.04.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 3.00 57.79 173.37 -
05.06.07.05 PINTURA -
05.06.07.05.01 PINTURA LATEX SATINADO A DOS MANOS m2 11.76 8.35 98.20 -
05.06.07.06 ACCESORIOS -
05.06.07.06.01 ACCESORIOS V. CONTROL 1" und 1.00 136.56 136.56 1.00
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
05.06.07.06.02 ACCESORIOS V. CONTROL 3/4" und 2.00 80.12 160.24 1.00
5.07 CONEXIONES DOMICILIARIAS VISTA ALEGRE (48 UNID.) 16,663.17 -
05.07.01 TRABAJOS PRELIMINARES 214.27 -
05.07.01.01 LIMPIEZA MANUAL DE TERRENO m2 172.80 0.54 93.31 -
05.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 172.80 0.70 120.96 -
05.07.02 MOVIMIENTO DE TIERRAS 4,423.35 -
05.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 92.16 26.52 2,444.08 -
COMPACTADO
05.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 115.20 1.06 122.11 -
05.07.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 55.20 15.93 879.34 -
ZARANDEADO
05.07.02.04 ELIMINACION MATERAIL EXCEDENTE m3 92.16 10.61 977.82 -
05.07.03 OBRAS DE CONCRETO SIMPLE 1,562.51 -
05.07.03.01 CONCRETO f'c=175 kg/cm2 m3 4.61 311.75 1,437.17 -
05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 5.76 21.76 125.34 -
05.07.04 CONEXIONES DOMICILIARIA (48 UNID) 10,463.04 -
05.07.04.01 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN und 48.00 217.98 10,463.04 48.00
CONEXIONES DOMICIALIARIAS
06 SERVICIO DE AGUA POTABLE RAMAL PIRIARI VISTA ALEGRE 149,770.57 -
6.01 LINEA DE ADUCCION RAMAL (1+649 KM) 52,702.79 -
06.01.01 TRABAJOS PRELIMINARES 1,665.49 -
06.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 824.50 0.54 445.23 824.50
06.01.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 824.50 1.48 1,220.26 824.50
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
06.01.02 MOVIMIENTO DE TIERRAS 38,342.55 -
06.01.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA m3 659.60 26.02 17,162.79 -
06.01.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 1,649.00 1.06 1,747.94 -
MATERIAL COMPACTADO
06.01.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 1,649.00 4.70 7,750.30 -
06.01.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 1,649.00 2.71 4,468.79 -
(0.60 x 0.20 m)
06.01.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 494.70 14.58 7,212.73 -
ZARANDEADO
06.01.03 INSTALACION DE TUBERIA 11,606.41 -
06.01.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO m 460.00 9.46 4,351.60 -
06.01.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2" m 180.00 8.00 1,440.00 -
06.01.03.03 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1" m 520.00 6.96 3,619.20 -
06.01.03.04 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4" m 489.00 4.49 2,195.61 -
06.01.04 PRUEBA DE CALIDAD 1,088.34 -
06.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA m 1,649.00 0.66 1,088.34 -
DE AGUA
06.02 VALVULA DE AIRE (02 UND) 1,593.08 -
06.02.01 TRABAJOS PRELIMINARES 2.00 -
06.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 1.62 0.54 0.87 -
06.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 1.62 0.70 1.13 -
06.02.02 MOVIMIENTO DE TIERRAS 37.73 -
06.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 0.97 26.52 25.72 -
COMPACTADO
06.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 1.62 1.06 1.72 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
06.02.02.03 ELIMINACION MATERAIL EXCEDENTE m3 0.97 10.61 10.29 -
06.02.03 OBRAS DE CONCRETO SIMPLE 759.62 -
06.02.03.01 CONCRETO f'c=175 kg/cm2 m3 1.01 344.91 348.36 -
06.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 18.90 21.76 411.26 -
06.02.04 CURADO DE CONCRETO 17.01 -
06.02.04.01 CURADO CON PRODUCTO QUIMICO m2 18.90 0.90 17.01 -
06.02.05 REVOQUES Y ENLUCIDOS 131.86 -
06.02.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 8.48 15.55 131.86 -
C/IMPERMEABILIZANTES
06.02.06 CARPINTERIA METALICA 145.72 -
06.02.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 2.00 72.86 145.72 -
06.02.07 PINTURA 165.24 -
06.02.07.01 PINTURA ANTICORROCIVA A DOS MANOS m2 15.30 10.80 165.24 -
06.02.08 ACCESORIOS 0 0.00 333.90 -
06.02.08.01 ACCESORIOS VALVULA DE AIRE D=63 MM und 2.00 166.95 333.90 -
06.03 ------------------------------------------ -
06.04 CAMARA ROMPE PRESION (01 UNID) 1,219.23 -
06.04.01 TRABAJOS PRELIMINARES 2.30 -
06.04.01.01 LIMPIEZA MANUAL DE TERRENO m2 1.85 0.54 1.00 -
06.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 1.85 0.70 1.30 -
06.04.02 MOVIMIENTO DE TIERRAS 77.18 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
06.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.90 26.52 50.39 -
COMPACTADO
06.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 1.55 1.06 1.64 -
06.04.02.03 ELIMINACION MATERAIL EXCEDENTE m3 2.37 10.61 25.15 -
06.04.03 OBRAS DE CONCRETO SIMPLE 182.65 -
06.04.03.01 ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX m2 2.56 54.70 140.03 -
6", E=20m
06.04.03.02 CONCRETO f'c=100 kg/cm2 m3 0.07 224.12 15.69 -
06.04.03.03 CONCRETO f'c=140 kg/cm2 m3 0.04 265.13 10.61 -
06.04.03.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.75 21.76 16.32 -
06.04.04 OBRAS DE CONCRETO ARMADO 635.66 -
06.04.04.01 CONCRETO f'c=210KG/CM2 m3 0.87 351.00 305.37 -
06.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 10.16 21.76 221.08 -
06.04.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 27.10 4.03 109.21 -
06.04.05 CURADO DE CONCRETO 0.78 -
06.04.05.01 CURADO CON PRODUCTO QUIMICO m2 0.87 0.90 0.78 -
06.04.06 REVOQUES Y ENLUCIDOS 97.03 -
06.04.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 6.24 15.55 97.03 -
C/IMPERMEABILIZANTES
06.04.07 CARPINTERIA METALICA 72.86 -
06.04.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 1.00 72.86 72.86 -
06.04.08 PINTURA 61.78 -
06.04.08.01 PINTURA ANTICORROCIVA A DOS MANOS m2 5.72 10.8 61.78 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
06.04.09 ACCESORIOS 88.99 -
06.04.09.01 ACCESORIO DE CAMARA ROMPE PRESION und 1.00 88.99 88.99 -
06.05 RED DE DISTRIBUCION RAMAL (L=2+575 m) 90,693.31 -
06.05.01 TRABAJOS PRELIMINARES 2,704.53 -
06.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 1,287.87 0.54 695.45 1,287.87
06.05.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 1,287.87 1.56 2,009.08 1,287.87
06.05.02 MOVIMIENTO DE TIERRAS 70,296.93 -
06.05.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL m3 1,287.87 26.02 33,510.38 659.15
COMPACTADO
06.05.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 2,575.73 1.04 2,678.76 1,318.29
MATERIAL COMPACTADO
06.05.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 2,575.73 4.70 12,105.93 1,318.29
06.05.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 2,575.73 2.71 6,980.23 1,318.29
(0.60 x 0.20 m)
06.05.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 1,030.29 14.58 15,021.63 527.32
ZARANDEADO
06.05.03 INSTALACION DE TUBERIA 9,928.61 -
06.05.03.01 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2" m 2,406.50 3.81 9,168.77 1,149.06
06.05.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4" m 169.23 4.49 759.84 169.23
06.05.04 PRUEBA DE CALIDAD 2,240.89 -
06.05.04.01 DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA m 2,575.73 0.87 2,240.89 -
DE AGUA
06.05.05 VALVULA DE AIRE (02 UND) 1,593.08 -
06.05.05.01 TRABAJOS PRELIMINARES -
06.05.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 1.62 0.54 0.87 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
06.05.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 1.62 0.70 1.13 -
06.05.05.02 MOVIMIENTO DE TIERRAS -
06.05.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 0.97 26.52 25.72 -
COMPACTADO
06.05.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 1.62 1.06 1.72 -
06.05.05.02.03 ELIMINACION MATERAIL EXCEDENTE m3 0.97 10.61 10.29 -
06.05.05.03 OBRAS DE CONCRETO SIMPLE -
06.05.05.03.01 CONCRETO f'c=175 kg/cm2 m3 1.01 344.91 348.36 -
06.05.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 18.90 21.76 411.26 -
06.05.05.04 CURADO DE CONCRETO -
06.05.05.04.01 CURADO CON PRODUCTO QUIMICO m2 18.90 0.90 17.01 -
06.05.05.05 REVOQUES Y ENLUCIDOS 0.00 -
06.05.05.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 8.48 15.55 131.86 -
C/IMPERMEABILIZANTES
06.05.05.06 CARPINTERIA METALICA -
06.05.05.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 2.00 72.86 145.72 -
06.05.05.07 PINTURA -
06.05.05.07.01 PINTURA ANTICORROCIVA A DOS MANOS m2 15.30 10.80 165.24 -
06.05.05.08 ACCESORIOS -
06.05.05.08.01 ACCESORIOS VALVULA DE AIRE D=63MM und 2.00 166.95 333.90 -
06.05.06 VALVULA DE PURGA (02 UND) 1,451.20 -
06.05.06.01 TRABAJOS PRELIMINARES -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
06.05.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 4.32 0.54 2.33 -
06.05.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 4.32 0.7 3.02 -
06.05.06.02 MOVIMIENTO DE TIERRAS -
06.05.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.96 26.52 51.98 -
COMPACTADO
06.05.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 2.30 1.06 2.44 -
06.05.06.02.03 ELIMINACION MATERAIL EXCEDENTE m3 1.84 10.61 19.52 -
06.05.06.03 OBRAS DE CONCRETO SIMPLE -
06.05.06.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" m3 0.09 28.93 2.60 -
COMPACTADO Y APISONADO E=0.10m
06.05.06.03.02 CONCRETO f'c = 140 kg/cm2 m3 0.25 281.59 70.40 -
06.05.06.04 OBRAS DE CONCRETO ESTRUCTURA -
06.05.06.04.01 CONCRETO f'c=175 kg/cm2 m3 1.14 317.40 361.84 -
06.05.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 6.42 21.76 139.70 -
06.05.06.05 CARPINTERIA METALICA -
06.05.06.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 2.00 72.86 145.72 -
06.05.06.06 PINTURA -
06.05.06.06.01 PINTURA LATEX SATINADO A DOS MANOS m2 4.08 8.35 34.07 -
06.05.06.07 ACCESORIOS -
06.05.06.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM und 2.00 308.79 617.58 -
06.05.07 VALVULA DE CONTROL (04 UND) 2,478.07 -
06.05.07.01 TRABAJOS PRELIMINARES -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
06.05.07.01.01 LIMPIEZA MANUAL DE TERRENO m2 4.32 0.54 2.33 -
06.05.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 4.32 0.70 3.02 -
06.05.07.02 MOVIMIENTO DE TIERRAS -
06.05.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 3.88 26.52 102.90 -
COMPACTADO
06.05.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 4.32 1.06 4.58 -
06.05.07.02.03 ELIMINACION MATERAIL EXCEDENTE m3 4.64 10.61 49.23 -
06.05.07.03 OBRAS DE CONCRETO SIMPLE -
06.05.07.03.01 CONCRETO f'c=175 kg/cm2 m3 4.08 317.4 1,294.99 -
06.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 12.96 21.76 282.01 -
06.05.07.04 CARPINTERIA METALICA -
06.05.07.04.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4" und 4.00 57.79 231.16 -
06.05.07.05 PINTURA -
06.05.07.05.01 PINTURA LATEX SATINADO A DOS MANOS m2 15.68 8.35 130.93 -
06.05.07.06 ACCESORIOS -
06.05.07.06.01 ACCESORIOS V. CONTROL 1" und 1.00 136.56 136.56 -
06.05.07.06.02 ACCESORIOS V. CONTROL 3/4" und 3.00 80.12 240.36 -
06.06 CONEXIONES DOMICILIARIAS RAMAL (10 UNID.) 3,562.16 -
06.06.01 TRABAJOS PRELIMINARES 44.64 -
06.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 36.00 0.54 19.44 -
06.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 36.00 0.7 25.20 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
06.06.02 MOVIMIENTO DE TIERRAS 1,012.33 -
06.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 19.20 26.52 509.18 -
COMPACTADO
06.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 24.00 1.06 25.44 -
06.06.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 17.20 15.93 274.00 -
ZARANDEADO
06.06.02.04 ELIMINACION MATERAIL EXCEDENTE m3 19.20 10.61 203.71 -
06.06.03 OBRAS DE CONCRETO SIMPLE 325.39 -
06.06.03.01 CONCRETO f'c=175 kg/cm2 m3 0.96 311.75 299.28 -
06.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 21.76 26.11 -
06.06.04 CONEXIONES DOMICILIARIA (10 UNID) 2,179.80 -
06.06.04.01 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN und 10.00 217.98 2,179.80 -
CONEXIONES DOMICIALIARIAS
07 SERVICIO DE ALCANTARILLADO SANITARIO MONTE SINAI (88 338,348.71 -
UND)
07.01 OBRAS PROVISIONALES 86,745.59 -
07.01.01 TRANSPORTE DE MATERIALES (ALCANTARILLADO) glb 1.00 15,000.00 15,000.00 1.00
07.01.02 MOVILIZACION FLETE DE MATERIALES (ALCANTARILLADO) glb 1.00 71,745.59 71,745.59 0.90
07.02 RED DE COLECTORES (L=1034.43 m) 56,431.40 -
07.02.01 TRABAJOS PRELIMINARES 1,044.79 -
07.02.01.01 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 517.22 1.48 765.49 517.22
07.02.01.02 LIMPIEZA MANUAL DE TERRENO m2 517.22 0.54 279.30 517.22
07.02.02 MOVIMIENTO DE TIERRAS 27,756.99 -
07.02.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL m3 517.22 26.52 13,716.67 513.61
COMPACTADO
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
07.02.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 1,034.43 1.06 1,096.50 994.90
MATERIAL COMPACTADO
07.02.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 1,034.43 4.70 4,861.82 994.90
07.02.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 1,034.43 2.71 2,803.31 994.90
(0.60 x 0.20 m)
07.02.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 362.05 14.58 5,278.69 362.02
ZARANDEADO
07.02.03 SUMINISTRO E INSTALACION DE TUBERIAS 26,946.90 -
07.02.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC S-20 NTP ISO m 1,034.43 26.05 26,946.90 994.90
4435 DN 160MM C/ANILLO
07.02.04 PRUEBA DE CALIDAD 682.72 -
07.02.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA m 1,034.43 0.66 682.72 994.90
DE AGUA
07.03 RED DE EMISORES (L=421.21 m) 26,619.88 -
07.03.01 TRABAJOS PRELIMINARES 2,531.53 -
07.03.01.01 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 210.61 1.48 311.70 210.61
07.03.01.02 LIMPIEZA MANUAL DE TERRENO m2 210.61 0.54 113.73 210.61
07.03.01.03 SEÑALIZACION PARA LIMITES DE SEGURIDAD VIAL m 210.61 10.00 2,106.10 210.61
07.03.02 MOVIMIENTO DE TIERRAS 12,837.83 -
07.03.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL m3 210.61 26.52 5,585.38 210.61
COMPACTADO
07.03.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 421.21 1.06 446.48 421.21
MATERIAL COMPACTADO
07.03.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m) m 421.21 4.70 1,979.69 421.21
07.03.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 421.21 2.71 1,141.48 421.21
(0.60 x 0.20 m)
07.03.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 252.73 14.58 3,684.80 252.73
ZARANDEADO
07.03.03 SUMINISTRO E INSTALACION DE TUBERIAS 10,972.52 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
07.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC S-20 NTP ISO m 421.21 26.05 10,972.52 421.21
4435 DN 160MM C/ANILLO
07.03.04 PRUEBA DE CALIDAD 278.00 -
07.03.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA m 421.21 0.66 278.00 421.21
DE AGUA
07.04 BUZONES TIPO 113,344.39 -
07.04.01 BUZON DE ALCANTARILLADO TIPO I Øint=1.20, H=0.80 - 1.50m 41,532.92 -
(14 und)
07.04.01.01 TRABAJOS PRELIMINARES 0.00 -
07.04.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 28.15 0.54 15.20 28.15
07.04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA m2 28.15 0.70 19.71 28.15
07.04.01.02 MOVIMIENTO DE TIERRAS -
07.04.01.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 32.37 35.36 1,144.60 32.37
COMPACTADO
07.04.01.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 28.15 1.06 29.84 28.15
07.04.01.02.03 PERFILADO MANUAL DE LAS PAREDES DE BUZONES m2 80.93 26.52 2,146.26 80.93
07.04.01.02.04 ELIMINACION MATERAIL EXCEDENTE m3 40.46 10.61 429.28 40.46
07.04.01.03 OBRAS DE CONCRETO SIMPLE -
07.04.01.03.01 CONCRETO f'c=100 kg/cm2 m3 3.27 225.68 737.97 3.27
07.04.01.03.02 CONCRETO f'c=140 kg/cm2, m3 1.27 149.93 190.41 1.15
07.04.01.03.03 CONCRETO f'c=175 kg/cm2 m3 19.79 334.83 6,626.29 19.79
07.04.01.03.04 ENCOFRADO Y DESENCOFRADO NORMAL m3 80.93 21.76 1,761.04 80.93
07.04.01.04 OBRAS DE CONCRETO ARMADO -
07.04.01.04.01 CONCRETO f'c=210KG/CM2 m3 28.15 368.69 10,378.62 28.15
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
07.04.01.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 540.85 21.76 11,768.90 540.85
07.04.01.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 34.75 4.05 140.74 34.75
07.04.01.04.04 MARCO DE FIERRO FUNDIDO Y PLATINA DE DE BORDE und 14.00 268 3,752.00 14.00
TAPA (segun diseño)
07.04.01.05 REVOQUES -
07.04.01.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 115.67 20.68 2,392.06 115.67
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
07.04.02 BUZON DE ALCANTARILLADO TIPO II Øint=1.20 H=1.50m - 47,090.48
3.00m (05 und)
-
07.04.02.01 TRABAJOS PRELIMINARES 0.00 -
07.04.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 30.16 0.54 16.29 28.15
07.04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA m2 30.16 0.70 21.11 28.15
07.04.02.02 MOVIMIENTO DE TIERRAS -
07.04.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 67.86 35.36 2,399.53 64.54
COMPACTADO
07.04.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 30.16 1.06 31.97 28.15
07.04.02.02.03 PERFILADO MANUAL DE LAS PAREDES DE BUZONES m2 169.65 26.52 4,499.12 161.35
07.04.02.02.04 ELIMINACION MATERAIL EXCEDENTE m3 84.82 10.61 899.94 79.17
07.04.02.03 OBRAS DE CONCRETO SIMPLE -
07.04.02.03.01 CONCRETO f'c=100 kg/cm2 m3 3.51 225.68 792.14 3.37
07.04.02.03.02 CONCRETO f'c=140 kg/cm2, m3 1.36 149.93 203.90 1.27
07.04.02.03.03 CONCRETO f'c=175 kg/cm2 m3 35.72 334.83 11,960.13 33.34
07.04.02.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 169.65 21.76 3,691.58 158.34
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
07.04.02.05 OBRAS DE CONCRETO ARMADO -
07.04.02.05.01 CONCRETO f'c=210KG/CM2 m3 30.16 368.69 11,119.69 28.15
07.04.02.05.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 37.23 21.76 810.12 34.75
07.04.02.05.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 579.48 4.05 2,346.89 540.85
07.04.02.05.04 MARCO DE FIERRO FUNDIDO Y PLATINA DE DE BORDE und 15.00 268.00 4,020.00 14.00
TAPA (segun diseño)
07.04.02.06 REVOQUES -
07.04.02.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 206.87 20.68 4,278.07 193.08
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
07.04.03 BUZON DE ALCANTARILLADO TIPO III Øint=1.20m H=MAYORES 24,720.99 -
A 5.0m (06 und)
07.04.03.01 TRABAJOS PRELIMINARES -
07.04.03.01.01 LIMPIEZA MANUAL DE TERRENO m2 8.04 0.54 4.34 -
07.04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA m2 8.04 0.7 5.63 -
07.04.03.02 MOVIMIENTO DE TIERRAS -
07.04.03.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 44.23 35.36 1,563.97 -
COMPACTADO
07.04.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 8.04 1.06 8.52 -
07.04.03.02.03 PERFILADO MANUAL DE LAS PAREDES DE BUZONES m2 110.58 26.52 2,932.58 -
07.04.03.02.04 ELIMINACION MATERAIL EXCEDENTE m3 55.29 10.61 586.63 -
07.04.03.03 OBRAS DE CONCRETO SIMPLE -
07.04.03.03.01 CONCRETO f'c=100 kg/cm2 m3 0.93 225.68 209.88 -
07.04.03.03.02 CONCRETO f'c=140 kg/cm2, m3 0.36 149.93 53.97 -
07.04.03.03.03 CONCRETO f'c=175 kg/cm2 m3 20.96 334.83 7,018.04 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
07.04.03.03.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 110.58 21.76 2,406.22 -
07.04.03.04 OBRAS DE CONCRETO ARMADO -
07.04.03.04.01 CONCRETO f'c=210KG/CM2 m3 8.04 368.69 2,964.27 -
07.04.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 154.53 21.76 3,362.57 -
07.04.03.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 9.93 4.05 40.22 -
07.04.03.04.04 MARCO DE FIERRO FUNDIDO Y PLATINA DE DE BORDE und 4.00 268 1,072.00 -
TAPA (segun diseño)
07.04.03.05 REVOQUES -
07.04.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 120.51 20.68 2,492.15 -
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
7.05 INSTALACION DE CONEXION DOMICILIARIA (88 UNID.) 55,207.45 -
07.05.01 TRABAJOS PRELIMINARES 1,354.32 -
07.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 237.60 4.24 1,007.42 -
07.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 237.60 1.46 346.90 -
07.05.02 MOVIMIENTO DE TIERRAS 21,718.75 -
07.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 237.60 26.52 6,301.15 -
COMPACTADO
07.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 528.00 2.66 1,404.48 -
07.05.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 528.00 15.93 8,411.04 -
ZARANDEADO
07.05.02.04 ELIMINACION MATERAIL EXCEDENTE m3 528.00 10.61 5,602.08 -
07.05.03 OBRAS DE CONCRETO SIMPLE 2,892.86 -
07.05.03.01 CONCRETO f'c=175 kg/cm2 m3 8.45 320.59 2,708.99 -
07.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.45 21.76 183.87 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
07.05.04 CONEXIONES DOMICILIARIA (88 UNID) 29,241.52 -
07.05.04.01 CONEXION DE DESAGUE D= 160 MM TERRENO SEMIROC. und 88.00 332.29 29,241.52 -
HASTA 4.00M
08 SERVICIO DE SANEAMIENTO BASICO 1,222,637.29 -
08.01 UNIDAD BASICA UNINI (63 UND) 493,758.08 -
08.01.01 CASETA 290,104.48 -
08.01.01.01 TRABAJOS PRELIMINARES -
08.01.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 328.86 0.54 177.58 328.86
08.01.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 328.86 0.70 230.20 328.86
08.01.01.02 CIMIENTO CORRIDO -
08.01.01.02.01 MOVIMIENTO DE TIERRAS -
08.01.01.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 81.40 26.52 2,158.73 81.40
08.01.01.02.01.02 ELIMINACION MATERAIL EXCEDENTE m3 101.59 10.61 1,077.87 101.59
08.01.01.02.02 OBRAS DE CONCRETO SIMPLE -
08.01.01.02.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO m3 71.69 217.86 15,618.38 71.69
CORRIDO
08.01.01.02.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO m2 198.07 28.85 5,714.32 198.07
08.01.01.02.02.03 CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE m3 12.38 293.49 3,633.41 12.38
CIMIENTO
08.01.01.02.02.04 ENCOFRADO Y DESENCOFRADO NORMAL m3 37.80 23.40 884.52 35.40
08.01.01.02.02.05 SARDINEL DE DUCHA h=0.20 m m 94.50 20.77 1,962.77 -
08.01.01.03 LOSA PISO -
08.01.01.03.01 MOVIMIENTO DE TIERRAS -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.01.01.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 113.95 26.52 3,021.95 -
08.01.01.03.01.02 ELIMINACION MATERAIL EXCEDENTE m3 142.44 10.61 1,511.29 -
08.01.01.03.01.03 REFINE Y NIVELACION PARA LOSA m2 137.34 0.88 120.86 -
08.01.01.03.02 OBRAS DE CONCRETO ARMADO -
08.01.01.03.02.01 ENCOFRADO Y DESENCOFRADO NORMAL m3 207.14 23.40 4,847.08 -
08.01.01.03.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 974.50 4.05 3,946.73 -
08.01.01.03.02.03 CONCRETO f'c=210KG/CM2 m3 33.79 349.03 11,793.72 -
08.01.01.04 MUROS Y COLUMNAS -
08.01.01.04.01 OBRAS DE CONCRETO ARMADO -
08.01.01.04.01.01 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS m2 98.91 21.17 2,093.92 92.63
08.01.01.04.01.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 644.87 4.05 2,611.72 644.87
08.01.01.04.01.03 CONCRETO f'c=210KG/CM2 PARA COLUMNETAS m3 15.67 349.03 5,469.30 14.68
08.01.01.04.02 MUROS Y TABIQUERIA -
08.01.01.04.02.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA m2 688.21 49.31 33,935.64 666.36
K.K.0.23x0.12x0.08M
08.01.01.04.03 REVOQUES ENLUCIDOS Y MOLDURAS -
08.01.01.04.03.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 m2 295.63 17.98 5,315.43 -
cm, ACABADO FROTACHADO
08.01.01.04.03.02 TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm m2 120.02 27.97 3,356.96 -
ACABADO PULIDO
08.01.01.04.04 PISOS Y PAVIMENTO -
08.01.01.04.04.01 CONTRAPISO ACABADO PULIDO DE 2" m2 97.97 23.39 2,291.52 -
08.01.01.05 COBERTURAS -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.01.01.05.01 ESTRUCTURA DE MADERA -
08.01.01.05.01.01 CORREAS DE MADERA TORNILLO DE 2"x2" m 22.47 12.3 276.38 -
08.01.01.05.01.02 CORREAS DE MADERA TORNILLO DE 2"x3" m 53.03 35.65 1,890.52 -
08.01.01.05.02 COBERTURAS LIVIANA DE CALAMINA -
08.01.01.05.02.01 COBERTURA CON CALAMINA GALVANIZADA m2 283.12 32.89 9,311.82 -
08.01.01.06 PUERTAS Y VENTANAS -
08.01.01.06.01 CARPINTERIA DE MADERA -
08.01.01.06.01.01 MARCO Y PUERTA DE MADERA C/ CALAMINA m2 98.28 147.52 14,498.27 -
GALVANIZADA
08.01.01.06.01.02 VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 m2 47.38 41.80 1,980.48 -
X 0.80)
08.01.01.06.02 CERRAJERIA -
08.01.01.06.02.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2" und 189.00 15.98 3,020.22 -
08.01.01.06.02.02 CERRADURA TIPO PERILLA ALUMINIO 60mm und 63.00 31.20 1,965.60 -
08.01.01.07 LAVADERO DOMICIARIO -
08.01.01.07.01 MOVIMIENTO DE TIERRAS -
08.01.01.07.01.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.80 26.52 47.74 -
COMPACTADO
08.01.01.07.01.02 ELIMINACION MATERAIL EXCEDENTE m3 2.36 10.61 25.04 -
08.01.01.07.02 OBRAS DE CONCRETO SIMPLE -
08.01.01.07.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO m3 1.80 217.86 392.15 -
LAVADERO
08.01.01.07.02.02 CONTRAPISO e=4 cm.ACABADO TIPO VEREDA m2 260.13 24.90 6,477.24 -
08.01.01.07.03 OBRAS DE CONCRETO ARMADO -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.01.01.07.03.01 CONCRETO f'c=175 kg/cm2 m3 4.94 311.75 1,540.05 -
08.01.01.07.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 345.40 4.05 1,398.87 -
08.01.01.07.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 130.35 21.17 2,759.51 -
08.01.01.07.04 MUROS Y TABIQUERIA -
08.01.01.07.04.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA m2 39.50 49.31 1,947.75 -
K.K.0.23x0.12x0.08M
08.01.01.07.05 REVOQUES ENLUCIDOS Y MOLDURAS -
08.01.01.07.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 m2 116.20 17.98 2,089.28 -
cm, ACABADO FROTACHADO
08.01.01.08 INSTALACIONES SANITARIAS AGUA -
08.01.01.08.01 APARATOS Y ACCESORIOS SANITARIO -
08.01.01.08.01.01 INODORO TANQUE BAJO INC./COLOCACION und 63.00 226.19 14,249.97 -
08.01.01.08.01.02 LAVADERO DE PARED und 63.00 170.09 10,715.67 -
08.01.01.08.01.03 DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE und 63.00 43.22 2,722.86 -
MEZCLADORA
08.01.01.08.01.04 CODO PVC SAL 2"x90º und 378.00 17.80 6,728.40 366.00
08.01.01.08.01.05 CODO PVC SAL 2"x45º und 378.00 17.8 6,728.40 366.00
08.01.01.08.01.06 TEE PVC SAL 2" und 63.00 10.40 655.20 61.00
08.01.01.08.01.07 YEE PVC SAL 2" und 252.00 17.80 4,485.60 244.00
08.01.01.08.01.08 SALIDA DE PVC SAL DE VENTILACION DE 2" pto 63.00 109.61 6,905.43 61.00
08.01.01.08.01.09 SUMIDERO DE BRONCE ROSCADO 2" und 126.00 106.57 13,427.82 -
08.01.01.08.01.10 REGISTRO DE BRONCE 2" und 189.00 40.82 7,714.98 -
08.01.01.08.02 ACCESORIO DE AGUA -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.01.01.08.02.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2" pto 252.00 88.44 22,286.88 -
08.01.01.08.02.02 RED DE DISTRIBUCION INTERNA CON TUBERIA DE m 420.84 21.03 8,850.27 267.20
PVC C-10 DE 1/2"
08.01.01.08.02.03 TEE PVC SP 1/2" und 189.00 9.26 1,750.14 120.00
08.01.01.08.02.04 CODO PVC SP 1/2"x90º und 252.00 9.26 2,333.52 160.00
08.01.01.08.02.05 UNION UNIVERSAL PVC 1/2" und 126.00 7.54 950.04 80.00
08.01.01.08.02.06 NIPLE C/ROSCA DE F°G° 1/2", L=1" und 126.00 10.47 1,319.22 80.00
08.01.01.08.02.07 ADAPTADOR C/ROSCA PVC 1/2" und 126.00 8.79 1,107.54 80.00
08.01.01.08.02.08 VALVULA COMPUERTA DE BRONCE 1/2" und 63.00 62.61 3,944.43 -
08.01.01.08.02.09 VALVULA ESFERICA DE 1/2" und 63.00 59.11 3,723.93 40.00
08.01.01.08.02.10 GRIFO BRONCE DE 1/2" und 126.00 64.36 8,109.36 -
08.01.02 EVACUACION DE AGUAS RESIDUALES 203,653.60 -
08.01.02.01 TRABAJOS PRELIMINARES -
08.01.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 1,523.34 0.54 822.60 1,474.98
08.01.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 1,523.34 0.70 1,066.34 1,474.98
08.01.02.02 SISTEMA DE AGUAS GRISES -
08.01.02.02.01 TRAMPA DE NATAS Y SOLIDOS -
08.01.02.02.01.01 MOVIMIENTO DE TIERRAS -
08.01.02.02.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 35.91 26.52 952.33 34.77
08.01.02.02.01.01.02 REFINE Y NIVELACION PARA LOSA m2 37.80 0.88 33.26 36.60
08.01.02.02.01.01.03 ELIMINACION MATERAIL EXCEDENTE m3 44.89 10.61 476.28 43.47
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.01.02.02.01.02 OBRAS DE CONCRETO ARMADO -
08.01.02.02.01.02.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m2 143.64 23.40 3,361.18 139.08
08.01.02.02.01.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 87.32 4.05 353.65 84.55
08.01.02.02.01.02.03 CONCRETO f'c=210KG/CM2 m3 18.77 349.03 6,551.29 18.18
08.01.02.02.01.03 CURADO DE CONCRETO -
08.01.02.02.01.03.01 CURADO CON PRODUCTO QUIMICO m2 167.58 0.90 150.82 162.26
08.01.02.02.01.04 REVOQUES Y ENLUCIDOS -
08.01.02.02.01.04.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 167.58 20.68 3,465.55 162.26
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.01.02.02.01.05 PINTURA -
08.01.02.02.01.05.01 PINTURA ANTICORROCIVA A DOS MANOS m2 57.96 18.71 1,084.43 -
08.01.02.02.01.06 ACCESORIOS -
08.01.02.02.01.06.01 TEE PVC SAL 2" und 126.00 10.40 1,310.40 122.00
08.01.02.02.02 RED DE DESAGÜE 2" -
08.01.02.02.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 89.11 26.52 2,363.20 86.28
08.01.02.02.02.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO m3 44.55 50.30 2,240.87 43.13
08.01.02.02.02.03 SUMINISTRO Y COLOCACION TUBERIA PVC DE 2" m 278.46 5.88 1,637.34 269.62
08.01.02.03 SISTEMA DE AGUAS NEGRAS -
08.01.02.03.01 CAJA DE REGISTRO -
08.01.02.03.01.01 MOVIMIENTO DE TIERRAS -
08.01.02.03.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 6.62 26.52 175.56 6.41
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.01.02.03.01.01.02 REFINE Y NIVELACION PARA LOSA m2 13.23 0.88 11.64 12.81
08.01.02.03.01.01.03 ELIMINACION MATERAIL EXCEDENTE m3 8.27 10.61 87.74 8.01
08.01.02.03.01.02 OBRAS DE CONCRETO SIMPLE -
08.01.02.03.01.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 3.34 293.49 980.26 3.24
08.01.02.03.01.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 47.25 23.40 1,105.65 45.75
08.01.02.03.01.03 OBRAS DE CONCRETO ARMADO -
08.01.02.03.01.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 19.22 23.40 449.75 18.61
08.01.02.03.01.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 44.32 4.05 179.50 42.91
08.01.02.03.01.03.03 CONCRETO f'c=210KG/CM2 m3 0.66 349.03 230.36 0.64
08.01.02.03.01.04 CURADO DE CONCRETO -
08.01.02.03.01.04.01 CURADO CON PRODUCTO QUIMICO m2 42.53 0.90 38.28 41.18
08.01.02.03.01.05 REVOQUES Y ENLUCIDOS -
08.01.02.03.01.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 42.53 20.68 879.52 41.18
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.01.02.03.01.06 PINTURA -
08.01.02.03.01.06.01 PINTURA ANTICORROCIVA A DOS MANOS m2 19.22 18.71 359.61 -
08.01.02.03.02 SUMINISTRO E INSTALACION BIODIGESTOR -
08.01.02.03.02.01 MOVIMIENTO DE TIERRAS -
08.01.02.03.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 230.20 26.52 6,104.90 222.89
08.01.02.03.02.01.02 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 37.80 12.63 477.41 36.60
ZARANDEADO
08.01.02.03.02.01.03 ELIMINACION MATERAIL EXCEDENTE m3 287.75 10.61 3,053.03 278.61
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.01.02.03.02.02 OBRAS DE CONCRETO SIMPLE -
08.01.02.03.02.02.01 SOLADO e=4", CONCRETO C:H, 1:10 m2 132.30 23.33 3,086.56 128.10
08.01.02.03.02.03 ACCESORIOS -
08.01.02.03.02.03.01 BIODIGESTOR AUTOLIMPIABLE V=750 lts und 63.00 1,507.99 95,003.37 63.00
08.01.02.03.03 REGISTRO DE LODOS -
08.01.02.03.03.01 MOVIMIENTO DE TIERRAS -
08.01.02.03.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 28.35 26.52 751.84 27.45
08.01.02.03.03.01.02 REFINE Y NIVELACION PARA LOSA m2 35.44 0.88 31.19 34.32
08.01.02.03.03.01.03 ELIMINACION MATERAIL EXCEDENTE m3 35.44 10.61 376.02 34.32
08.01.02.03.03.02 OBRAS DE CONCRETO SIMPLE -
08.01.02.03.03.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 13.24 293.49 3,885.81 12.82
08.01.02.03.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 114.66 23.40 2,683.04 111.02
08.01.02.03.03.03 OBRAS DE CONCRETO ARMADO -
08.01.02.03.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 23.47 23.40 549.20 22.73
08.01.02.03.03.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 58.34 4.05 236.28 56.49
08.01.02.03.03.03.03 CONCRETO f'c=210KG/CM2 m3 1.77 349.03 617.78 1.72
08.01.02.03.03.04 CURADO DE CONCRETO -
08.01.02.03.03.04.01 CURADO CON PRODUCTO QUIMICO m2 114.66 0.90 103.19 111.02
08.01.02.03.03.05 REVOQUES Y ENLUCIDOS -
08.01.02.03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 114.66 20.68 2,371.17 111.02
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.01.02.03.03.06 ACCESORIOS -
08.01.02.03.03.06.01 ADAPTADOR C/ROSCA PVC 2" und 126.00 17.75 2,236.50 122.00
08.01.02.03.03.06.02 UNION UNIVERSAL DE PVC SP 2" und 126.00 18.08 2,278.08 122.00
08.01.02.03.03.06.03 VALVULA COMPUERTA DE BRONCE 2" und 63.00 88.58 5,580.54 61.00
08.01.02.03.04 RED DE DESAGÚE 4" -
08.01.02.03.04.01 EXCAVACION A MANO EN TERRENO NORMAL m3 114.51 26.52 3,036.81 110.88
08.01.02.03.04.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO m3 57.25 50.30 2,879.68 55.43
08.01.02.03.04.03 SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4" m 357.84 13.74 4,916.72 346.48
08.01.02.03.05 CAJA DISTRIBUIDORA DE CAUDALES -
08.01.02.03.05.01 MOVIMIENTO DE TIERRAS -
08.01.02.03.05.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 9.45 26.52 250.61 9.15
08.01.02.03.05.01.02 REFINE Y NIVELACION PARA LOSA m2 18.90 0.88 16.63 18.30
08.01.02.03.05.01.03 ELIMINACION MATERAIL EXCEDENTE m3 17.48 10.61 185.46 16.92
08.01.02.03.05.02 OBRAS DE CONCRETO SIMPLE -
08.01.02.03.05.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 3.78 293.49 1,109.39 3.66
08.01.02.03.05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 51.03 23.40 1,194.10 49.41
08.01.02.03.05.03 OBRAS DE CONCRETO ARMADO -
08.01.02.03.05.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 25.83 23.40 604.42 25.01
08.01.02.03.05.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 58.34 4.05 236.28 56.49
08.01.02.03.05.03.03 CONCRETO f'c=210KG/CM2 m3 0.95 349.03 331.58 0.92
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.01.02.03.05.04 CURADO DE CONCRETO -
08.01.02.03.05.04.01 CURADO CON PRODUCTO QUIMICO m2 51.03 0.90 45.93 49.41
08.01.02.03.05.05 REVOQUES Y ENLUCIDOS -
08.01.02.03.05.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 51.03 20.68 1,055.30 49.41
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.01.02.03.05.06 PINTURA -
08.01.02.03.05.06.01 PINTURA ANTICORROCIVA A DOS MANOS m2 24.57 18.71 459.70 -
08.01.02.04 ZANJAS DE INFILTRACION -
08.01.02.04.01 MOVIMIENTO DE TIERRAS -
08.01.02.04.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 142.13 26.52 3,769.29 -
08.01.02.04.01.02 REFINE Y NIVELACION FONDO ZANJA m2 177.66 0.88 156.34 -
08.01.02.04.01.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 71.06 12.63 897.49 -
ZARANDEADO
08.01.02.04.01.04 ELIMINACION MATERAIL EXCEDENTE m3 124.36 10.61 1,319.46 -
08.01.02.04.02 RELLENO CON MATERIAL SELECCIONADO -
08.01.02.04.02.01 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - m3 26.65 108.81 2,899.79 -
2"
08.01.02.04.02.02 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 m3 26.65 108.81 2,899.79 -
1/2" - 2"
08.01.02.04.02.03 RELLENO CON MATERIAL PROPIO m3 40.08 11.70 468.94 -
08.01.02.04.03 ACCESORIOS -
08.01.02.04.03.01 MATERIAL INFILTRANTE EN ZANJAS m2 177.66 17.06 3,030.88 -
08.01.02.04.03.02 TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO m 296.10 40.85 12,095.69 -
08.02 UNIDAD BASICA PIRIARI (35 UND) 274,313.71 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.02.01 CASETA 161,170.22 -
08.02.01.01 TRABAJOS PRELIMINARES -
08.02.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 182.70 0.54 98.66 172.26
08.02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 182.70 0.70 127.89 172.26
08.02.01.02 CIMIENTO CORRIDO -
08.02.01.02.01 MOVIMIENTO DE TIERRAS -
08.02.01.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 45.22 26.52 1,199.23 42.63
08.02.01.02.01.02 ELIMINACION MATERAIL EXCEDENTE m3 56.44 10.61 598.83 53.21
08.02.01.02.02 OBRAS DE CONCRETO SIMPLE -
08.02.01.02.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO m3 39.83 217.86 8,677.36 37.56
CORRIDO
08.02.01.02.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO m2 110.04 28.85 3,174.65 103.76
08.02.01.02.02.03 CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE m3 6.88 293.49 2,019.21 6.49
CIMIENTO
08.02.01.02.02.04 ENCOFRADO Y DESENCOFRADO NORMAL m3 21.00 23.40 491.40 13.20
08.02.01.02.02.05 SARDINEL DE DUCHA h=0.20 m m 52.50 20.77 1,090.43 33.00
08.02.01.03 LOSA PISO -
08.02.01.03.01 MOVIMIENTO DE TIERRAS -
08.02.01.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 63.31 26.52 1,678.98 -
08.02.01.03.01.02 ELIMINACION MATERAIL EXCEDENTE m3 79.14 10.61 839.68 -
08.02.01.03.01.03 REFINE Y NIVELACION PARA LOSA m2 76.30 0.88 67.14 -
08.02.01.03.02 OBRAS DE CONCRETO ARMADO -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.02.01.03.02.01 ENCOFRADO Y DESENCOFRADO NORMAL m3 115.08 23.40 2,692.87 -
08.02.01.03.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 541.39 4.05 2,192.63 -
08.02.01.03.02.03 CONCRETO f'c=210KG/CM2 m3 18.77 349.03 6,551.29 -
08.02.01.04 MUROS Y COLUMNAS -
08.02.01.04.01 OBRAS DE CONCRETO ARMADO -
08.02.01.04.01.01 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS m2 54.95 21.17 1,163.29 51.81
08.02.01.04.01.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 358.26 4.05 1,450.95 337.78
08.02.01.04.01.03 CONCRETO f'c=210KG/CM2 PARA COLUMNETAS m3 8.71 349.03 3,040.05 8.21
08.02.01.04.02 MUROS Y TABIQUERIA -
08.02.01.04.02.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA m2 382.34 49.31 18,853.19 360.50
K.K.0.23x0.12x0.08M
08.02.01.04.03 REVOQUES ENLUCIDOS Y MOLDURAS -
08.02.01.04.03.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 m2 164.24 17.98 2,953.04 -
cm, ACABADO FROTACHADO
08.02.01.04.03.02 TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm m2 66.68 27.97 1,865.04 -
ACABADO PULIDO
08.02.01.04.04 PISOS Y PAVIMENTO -
08.02.01.04.04.01 CONTRAPISO ACABADO PULIDO DE 2" m2 54.43 23.39 1,273.12 -
08.02.01.05 COBERTURAS -
08.02.01.05.01 ESTRUCTURA DE MADERA -
08.02.01.05.01.01 CORREAS DE MADERA TORNILLO DE 2"x2" m 12.48 12.30 153.50 -
08.02.01.05.01.02 CORREAS DE MADERA TORNILLO DE 2"x3" m 29.46 35.65 1,050.25 -
08.02.01.05.02 COBERTURAS LIVIANA DE CALAMINA -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.02.01.05.02.01 COBERTURA CON CALAMINA GALVANIZADA m2 157.29 32.89 5,173.27 -
08.02.01.06 PUERTAS Y VENTANAS -
08.02.01.06.01 CARPINTERIA DE MADERA -
08.02.01.06.01.01 MARCO Y PUERTA DE MADERA C/ CALAMINA m2 54.60 147.52 8,054.59 -
GALVANIZADA
08.02.01.06.01.02 VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 m2 26.32 41.80 1,100.18 -
X 0.80)
08.02.01.06.02 CERRAJERIA -
08.02.01.06.02.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2" und 105.00 15.98 1,677.90 -
08.02.01.06.02.02 CERRADURA TIPO PERILLA ALUMINIO 60mm und 35.00 31.20 1,092.00 -
08.02.01.07 LAVADERO DOMICIARIO -
08.02.01.07.01 MOVIMIENTO DE TIERRAS -
08.02.01.07.01.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.00 26.52 26.52 -
COMPACTADO
08.02.01.07.01.02 ELIMINACION MATERAIL EXCEDENTE m3 1.31 10.61 13.90 -
08.02.01.07.02 OBRAS DE CONCRETO SIMPLE -
08.02.01.07.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO m3 1.00 217.86 217.86 -
LAVADERO
08.02.01.07.02.02 CONTRAPISO e=4 cm.ACABADO TIPO VEREDA m2 144.52 24.90 3,598.55 -
08.02.01.07.03 OBRAS DE CONCRETO ARMADO -
08.02.01.07.03.01 CONCRETO f'c=175 kg/cm2 m3 2.74 311.75 854.20 -
08.02.01.07.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 191.89 4.05 777.15 -
08.02.01.07.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 72.41 21.17 1,532.92 -
08.02.01.07.04 MUROS Y TABIQUERIA -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.02.01.07.04.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA m2 21.95 49.31 1,082.35 -
K.K.0.23x0.12x0.08M
08.02.01.07.05 REVOQUES ENLUCIDOS Y MOLDURAS -
08.02.01.07.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 m2 64.56 17.98 1,160.79 -
cm, ACABADO FROTACHADO
08.02.01.08 INSTALACIONES SANITARIAS AGUA -
08.02.01.08.01 APARATOS Y ACCESORIOS SANITARIO -
08.02.01.08.01.01 INODORO TANQUE BAJO INC./COLOCACION und 35.00 226.19 7,916.65 -
08.02.01.08.01.02 LAVADERO DE PARED und 35.00 170.09 5,953.15 -
08.02.01.08.01.03 DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE und 35.00 43.22 1,512.70 -
MEZCLADORA
08.02.01.08.01.04 CODO PVC SAL 2"x90º und 210.00 17.80 3,738.00 198.00
08.02.01.08.01.05 CODO PVC SAL 2"x45º und 210.00 17.80 3,738.00 198.00
08.02.01.08.01.06 TEE PVC SAL 2" und 35.00 10.40 364.00 33.00
08.02.01.08.01.07 YEE PVC SAL 2" und 140.00 17.80 2,492.00 132.00
08.02.01.08.01.08 SALIDA DE PVC SAL DE VENTILACION DE 2" pto 35.00 109.61 3,836.35 33.00
08.02.01.08.01.09 SUMIDERO DE BRONCE ROSCADO 2" und 70.00 106.57 7,459.90 -
08.02.01.08.01.10 REGISTRO DE BRONCE 2" und 105.00 40.82 4,286.10 -
08.02.01.08.02 ACCESORIO DE AGUA -
08.02.01.08.02.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2" pto 140.00 88.44 12,381.60 -
08.02.01.08.02.02 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC m 233.80 21.03 4,916.81 146.96
C-10 DE 1/2"
08.02.01.08.02.03 TEE PVC SP 1/2" und 105.00 9.26 972.30 66.00
08.02.01.08.02.04 CODO PVC SP 1/2"x90º und 140.00 9.26 1,296.40 88.00
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.02.01.08.02.05 UNION UNIVERSAL PVC 1/2" und 70.00 7.54 527.80 44.00
08.02.01.08.02.06 NIPLE C/ROSCA DE F°G° 1/2", L=1" und 70.00 10.47 732.90 44.00
08.02.01.08.02.07 ADAPTADOR C/ROSCA PVC 1/2" und 70.00 8.79 615.30 44.00
08.02.01.08.02.08 VALVULA COMPUERTA DE BRONCE 1/2" und 35.00 62.61 2,191.35 -
08.02.01.08.02.09 VALVULA ESFERICA DE 1/2" und 35.00 59.11 2,068.85 22.00
08.02.01.08.02.10 GRIFO BRONCE DE 1/2" und 70.00 64.36 4,505.20 -
08.02.02 EVACUACION DE AGUAS RESIDUALES 113,143.49 -
08.02.02.01 TRABAJOS PRELIMINARES -
08.02.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 846.30 0.54 457.00 797.94
08.02.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 846.30 0.70 592.41 797.94
08.02.02.02 SISTEMA DE AGUAS GRISES -
08.02.02.02.01 TRAMPA DE NATAS Y SOLIDOS -
08.02.02.02.01.01 MOVIMIENTO DE TIERRAS -
08.02.02.02.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 19.95 26.52 529.07 18.81
08.02.02.02.01.01.02 REFINE Y NIVELACION PARA LOSA m2 21.00 0.88 18.48 19.80
08.02.02.02.01.01.03 ELIMINACION MATERAIL EXCEDENTE m3 24.94 10.61 264.61 23.51
08.02.02.02.01.02 OBRAS DE CONCRETO ARMADO -
08.02.02.02.01.02.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 79.80 23.40 1,867.32 75.24
08.02.02.02.01.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 48.51 4.05 196.47 45.73
08.02.02.02.01.02.03 CONCRETO f'c=210KG/CM2 m3 10.43 349.03 3,640.38 9.83
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.02.02.02.01.03 CURADO DE CONCRETO -
08.02.02.02.01.03.01 CURADO CON PRODUCTO QUIMICO m2 93.10 0.90 83.79 87.78
08.02.02.02.01.04 REVOQUES Y ENLUCIDOS -
08.02.02.02.01.04.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 93.10 20.68 1,925.31 87.78
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.02.02.02.01.05 PINTURA -
08.02.02.02.01.05.01 PINTURA ANTICORROCIVA A DOS MANOS m2 32.20 18.71 602.46 -
08.02.02.02.01.06 ACCESORIOS -
08.02.02.02.01.06.01 TEE PVC SAL 2" und 70.00 10.40 728.00 66.00
08.02.02.02.02 RED DE DESAGÜE 2" -
08.02.02.02.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 49.50 26.52 1,312.74 46.67
08.02.02.02.02.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO m3 24.75 50.30 1,244.93 23.33
08.02.02.02.02.03 SUMINISTRO Y COLOCACION TUBERIA PVC DE 2" m 154.70 5.88 909.64 145.86
08.02.02.03 SISTEMA DE AGUAS NEGRAS -
08.02.02.03.01 CAJA DE REGISTRO -
08.02.02.03.01.01 MOVIMIENTO DE TIERRAS -
08.02.02.03.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 3.68 26.52 97.59 3.47
08.02.02.03.01.01.02 REFINE Y NIVELACION PARA LOSA m2 7.35 0.88 6.47 6.93
08.02.02.03.01.01.03 ELIMINACION MATERAIL EXCEDENTE m3 4.59 10.61 48.70 4.33
08.02.02.03.01.02 OBRAS DE CONCRETO SIMPLE -
08.02.02.03.01.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 1.86 293.49 545.89 1.76
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.02.02.03.01.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 26.25 23.40 614.25 24.75
08.02.02.03.01.03 OBRAS DE CONCRETO ARMADO -
08.02.02.03.01.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 10.68 23.40 249.91 10.07
08.02.02.03.01.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 24.62 4.05 99.71 23.21
08.02.02.03.01.03.03 CONCRETO f'c=210KG/CM2 m3 0.37 349.03 129.14 0.35
08.02.02.03.01.04 CURADO DE CONCRETO -
08.02.02.03.01.04.01 CURADO CON PRODUCTO QUIMICO m2 23.63 0.90 21.27 22.28
08.02.02.03.01.05 REVOQUES Y ENLUCIDOS -
08.02.02.03.01.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 23.63 20.68 488.67 22.28
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.02.02.03.01.06 PINTURA -
08.02.02.03.01.06.01 PINTURA ANTICORROCIVA A DOS MANOS m2 10.68 18.71 199.82 -
08.02.02.03.02 SUMINISTRO E INSTALACION BIODIGESTOR -
08.02.02.03.02.01 MOVIMIENTO DE TIERRAS -
08.02.02.03.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 127.89 26.52 3,391.64 120.58
08.02.02.03.02.01.02 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 21.00 12.63 265.23 19.80
ZARANDEADO
08.02.02.03.02.01.03 ELIMINACION MATERAIL EXCEDENTE m3 159.86 10.61 1,696.11 -
08.02.02.03.02.02 OBRAS DE CONCRETO SIMPLE -
08.02.02.03.02.02.01 SOLADO e=4", CONCRETO C:H, 1:10 m2 73.50 23.33 1,714.76 69.30
08.02.02.03.02.03 ACCESORIOS -
08.02.02.03.02.03.01 BIODIGESTOR AUTOLIMPIABLE V=750 lts und 35.00 1,507.99 52,779.65 33.00
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.02.02.03.03 REGISTRO DE LODOS -
08.02.02.03.03.01 MOVIMIENTO DE TIERRAS -
08.02.02.03.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 15.75 26.52 417.69 14.85
08.02.02.03.03.01.02 REFINE Y NIVELACION PARA LOSA m2 19.69 0.88 17.33 18.56
08.02.02.03.03.01.03 ELIMINACION MATERAIL EXCEDENTE m3 19.69 10.61 208.91 18.56
08.02.02.03.03.02 OBRAS DE CONCRETO SIMPLE -
08.02.02.03.03.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 7.35 293.49 2,157.15 6.93
08.02.02.03.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 63.70 23.40 1,490.58 60.06
08.02.02.03.03.03 OBRAS DE CONCRETO ARMADO -
08.02.02.03.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m3 13.04 23.40 305.14 12.29
08.02.02.03.03.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 32.41 4.05 131.26 30.55
08.02.02.03.03.03.03 CONCRETO f'c=210KG/CM2 m3 0.98 349.03 342.05 0.92
08.02.02.03.03.04 CURADO DE CONCRETO -
08.02.02.03.03.04.01 CURADO CON PRODUCTO QUIMICO m2 63.70 0.90 57.33 60.06
08.02.02.03.03.05 REVOQUES Y ENLUCIDOS -
08.02.02.03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 63.70 20.68 1,317.32 60.06
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.02.02.03.03.06 ACCESORIOS -
08.02.02.03.03.06.01 ADAPTADOR C/ROSCA PVC 2" und 70.00 17.75 1,242.50 66.00
08.02.02.03.03.06.02 UNION UNIVERSAL DE PVC SP 2" und 70.00 18.08 1,265.60 66.00
08.02.02.03.03.06.03 VALVULA COMPUERTA DE BRONCE 2" und 35.00 88.58 3,100.30 33.00
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.02.02.03.04 RED DE DESAGÚE 4" -
08.02.02.03.04.01 EXCAVACION A MANO EN TERRENO NORMAL m3 63.62 26.52 1,687.20 59.99
08.02.02.03.04.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO m3 31.81 50.30 1,600.04 29.99
08.02.02.03.04.03 SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4" m 198.80 13.74 2,731.51 187.44
08.02.02.03.05 CAJA DISTRIBUIDORA DE CAUDALES -
08.02.02.03.05.01 MOVIMIENTO DE TIERRAS -
08.02.02.03.05.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 5.25 26.52 139.23 4.95
08.02.02.03.05.01.02 REFINE Y NIVELACION PARA LOSA m2 10.50 0.88 9.24 9.90
08.02.02.03.05.01.03 ELIMINACION MATERAIL EXCEDENTE m3 9.71 10.61 103.02 9.16
08.02.02.03.05.02 OBRAS DE CONCRETO SIMPLE -
08.02.02.03.05.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 2.10 293.49 616.33 1.98
08.02.02.03.05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 28.35 23.40 663.39 26.73
08.02.02.03.05.03 OBRAS DE CONCRETO ARMADO -
08.02.02.03.05.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 14.35 23.40 335.79 13.53
08.02.02.03.05.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 32.41 4.05 131.26 30.55
08.02.02.03.05.03.03 CONCRETO f'c=210KG/CM2 m3 0.53 349.03 184.99 0.50
08.02.02.03.05.04 CURADO DE CONCRETO -
08.02.02.03.05.04.01 CURADO CON PRODUCTO QUIMICO m2 28.35 0.90 25.52 26.73
08.02.02.03.05.05 REVOQUES Y ENLUCIDOS -
08.02.02.03.05.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 28.35 20.68 586.28 26.73
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.02.02.03.05.06 PINTURA -
08.02.02.03.05.06.01 PINTURA ANTICORROCIVA A DOS MANOS m2 13.65 18.71 255.39 -
08.02.02.04 ZANJAS DE INFILTRACION -
08.02.02.04.01 MOVIMIENTO DE TIERRAS -
08.02.02.04.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 78.96 26.52 2,094.02 -
08.02.02.04.01.02 REFINE Y NIVELACION FONDO ZANJA m2 98.70 0.88 86.86 -
08.02.02.04.01.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 39.48 12.63 498.63 -
ZARANDEADO
08.02.02.04.01.04 ELIMINACION MATERAIL EXCEDENTE m3 69.09 10.61 733.04 -
08.02.02.04.02 RELLENO CON MATERIAL SELECCIONADO -
08.02.02.04.02.01 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - m3 14.81 108.81 1,611.48 -
2"
08.02.02.04.02.02 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 m3 14.81 108.81 1,611.48 -
1/2" - 2"
08.02.02.04.02.03 RELLENO CON MATERIAL PROPIO m3 22.27 11.70 260.56 -
08.02.02.04.03 ACCESORIOS -
08.02.02.04.03.01 MATERIAL INFILTRANTE EN ZANJAS m2 98.70 17.06 1,683.82 -
08.02.02.04.03.02 TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO m 164.50 40.85 6,719.83 -
08.03 UNIDAD BASICA VISTA ALEGRE (48 UND) 376,188.54 -
08.03.01 CASETA 221,028.04 -
08.03.01.01 TRABAJOS PRELIMINARES -
08.03.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 250.56 0.54 135.30 245.34
08.03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 250.56 0.70 175.39 245.34
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.03.01.02 CIMIENTO CORRIDO -
08.03.01.02.01 MOVIMIENTO DE TIERRAS -
08.03.01.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 62.02 26.52 1,644.77 60.72
08.03.01.02.01.02 ELIMINACION MATERAIL EXCEDENTE m3 77.40 10.61 821.21 75.79
08.03.01.02.02 OBRAS DE CONCRETO SIMPLE -
08.03.01.02.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO m3 54.62 217.86 11,899.51 53.49
CORRIDO
08.03.01.02.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO m2 150.91 28.85 4,353.75 147.77
08.03.01.02.02.03 CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE m3 9.43 293.49 2,767.61 9.23
CIMIENTO
08.03.01.02.02.04 ENCOFRADO Y DESENCOFRADO NORMAL m3 28.80 23.40 673.92 24.00
08.03.01.02.02.05 SARDINEL DE DUCHA h=0.20 m m 72.00 20.77 1,495.44 -
08.03.01.03 LOSA PISO -
08.03.01.03.01 MOVIMIENTO DE TIERRAS -
08.03.01.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 86.82 26.52 2,302.47 -
08.03.01.03.01.02 ELIMINACION MATERAIL EXCEDENTE m3 108.53 10.61 1,151.50 -
08.03.01.03.01.03 REFINE Y NIVELACION PARA LOSA m2 104.64 0.88 92.08 -
08.03.01.03.02 OBRAS DE CONCRETO ARMADO -
08.03.01.03.02.01 ENCOFRADO Y DESENCOFRADO NORMAL m3 157.82 23.40 3,692.99 -
08.03.01.03.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 742.48 4.05 3,007.04 -
08.03.01.03.02.03 CONCRETO f'c=210KG/CM2 m3 25.74 349.03 8,984.03 -
08.03.01.04 MUROS Y COLUMNAS -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.03.01.04.01 OBRAS DE CONCRETO ARMADO -
08.03.01.04.01.01 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS m2 75.36 21.17 1,595.37 73.79
08.03.01.04.01.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 491.33 4.05 1,989.89 481.09
08.03.01.04.01.03 CONCRETO f'c=210KG/CM2 PARA COLUMNETAS m3 11.94 349.03 4,167.42 9.20
08.03.01.04.02 MUROS Y TABIQUERIA -
08.03.01.04.02.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA m2 524.35 49.31 25,855.70 513.43
K.K.0.23x0.12x0.08M
08.03.01.04.03 REVOQUES ENLUCIDOS Y MOLDURAS -
08.03.01.04.03.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 m2 225.24 17.98 4,049.82 -
cm, ACABADO FROTACHADO
08.03.01.04.03.02 TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm m2 91.44 27.97 2,557.58 -
ACABADO PULIDO
08.03.01.04.04 PISOS Y PAVIMENTO -
08.03.01.04.04.01 CONTRAPISO ACABADO PULIDO DE 2" m2 74.64 23.39 1,745.83 -
08.03.01.05 COBERTURAS -
08.03.01.05.01 ESTRUCTURA DE MADERA -
08.03.01.05.01.01 CORREAS DE MADERA TORNILLO DE 2"x2" m 17.12 12.30 210.58 -
08.03.01.05.01.02 CORREAS DE MADERA TORNILLO DE 2"x3" m 40.40 35.65 1,440.26 -
08.03.01.05.02 COBERTURAS LIVIANA DE CALAMINA -
08.03.01.05.02.01 COBERTURA CON CALAMINA GALVANIZADA m2 215.71 32.89 7,094.70 -
08.03.01.06 PUERTAS Y VENTANAS -
08.03.01.06.01 CARPINTERIA DE MADERA -
08.03.01.06.01.01 MARCO Y PUERTA DE MADERA C/ CALAMINA m2 74.88 147.52 11,046.30 -
GALVANIZADA
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.03.01.06.01.02 VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 m2 36.10 41.80 1,508.98 -
X 0.80)
08.03.01.06.02 CERRAJERIA -
08.03.01.06.02.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2" und 144.00 15.98 2,301.12 -
08.03.01.06.02.02 CERRADURA TIPO PERILLA ALUMINIO 60mm und 48.00 31.20 1,497.60 -
08.03.01.07 LAVADERO DOMICIARIO -
08.03.01.07.01 MOVIMIENTO DE TIERRAS -
08.03.01.07.01.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.37 26.52 36.33 -
COMPACTADO
08.03.01.07.01.02 ELIMINACION MATERAIL EXCEDENTE m3 1.80 10.61 19.10 -
08.03.01.07.02 OBRAS DE CONCRETO SIMPLE -
08.03.01.07.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO m3 1.37 217.86 298.47 -
LAVADERO
08.03.01.07.02.02 CONTRAPISO e=4 cm.ACABADO TIPO VEREDA m2 198.19 24.90 4,934.93 -
08.03.01.07.03 OBRAS DE CONCRETO ARMADO -
08.03.01.07.03.01 CONCRETO f'c=175 kg/cm2 m3 3.76 311.75 1,172.18 -
08.03.01.07.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 263.16 4.05 1,065.80 -
08.03.01.07.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 99.31 21.17 2,102.39 -
08.03.01.07.04 MUROS Y TABIQUERIA -
08.03.01.07.04.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA m2 30.10 49.31 1,484.23 -
K.K.0.23x0.12x0.08M
08.03.01.07.05 REVOQUES ENLUCIDOS Y MOLDURAS -
08.03.01.07.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 m2 88.54 17.98 1,591.95 -
cm, ACABADO FROTACHADO
08.03.01.08 INSTALACIONES SANITARIAS AGUA -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.03.01.08.01 APARATOS Y ACCESORIOS SANITARIO -
08.03.01.08.01.01 INODORO TANQUE BAJO INC./COLOCACION und 48.00 226.19 10,857.12 -
08.03.01.08.01.02 LAVADERO DE PARED und 48.00 170.09 8,164.32 -
08.03.01.08.01.03 DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE und 48.00 43.22 2,074.56 -
MEZCLADORA
08.03.01.08.01.04 CODO PVC SAL 2"x90º und 288.00 17.80 5,126.40 282.00
08.03.01.08.01.05 CODO PVC SAL 2"x45º und 288.00 17.80 5,126.40 282.00
08.03.01.08.01.06 TEE PVC SAL 2" und 48.00 10.40 499.20 47.00
08.03.01.08.01.07 YEE PVC SAL 2" und 192.00 17.80 3,417.60 188.00
08.03.01.08.01.08 SALIDA DE PVC SAL DE VENTILACION DE 2" pto 48.00 109.61 5,261.28 47.00
08.03.01.08.01.09 SUMIDERO DE BRONCE ROSCADO 2" und 96.00 106.57 10,230.72 -
08.03.01.08.01.10 REGISTRO DE BRONCE 2" und 144.00 40.82 5,878.08 -
08.03.01.08.02 ACCESORIO DE AGUA -
08.03.01.08.02.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2" pto 192.00 88.44 16,980.48 -
08.03.01.08.02.02 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC m 320.64 21.03 6,743.06 313.96
C-10 DE 1/2"
08.03.01.08.02.03 TEE PVC SP 1/2" und 144.00 9.26 1,333.44 141.00
08.03.01.08.02.04 CODO PVC SP 1/2"x90º und 192.00 9.26 1,777.92 188.00
08.03.01.08.02.05 UNION UNIVERSAL PVC 1/2" und 96.00 7.54 723.84 94.00
08.03.01.08.02.06 NIPLE C/ROSCA DE F°G° 1/2", L=1" und 96.00 10.47 1,005.12 94.00
08.03.01.08.02.07 ADAPTADOR C/ROSCA PVC 1/2" und 96.00 8.79 843.84 94.00
08.03.01.08.02.08 VALVULA COMPUERTA DE BRONCE 1/2" und 48.00 62.61 3,005.28 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.03.01.08.02.09 VALVULA ESFERICA DE 1/2" und 48.00 59.11 2,837.28 47.00
08.03.01.08.02.10 GRIFO BRONCE DE 1/2" und 96.00 64.36 6,178.56 -
08.03.02 EVACUACION DE AGUAS RESIDUALES 155,160.50 -
08.03.02.01 TRABAJOS PRELIMINARES -
08.03.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 1,160.64 0.54 626.75 1,136.46
08.03.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 1,160.64 0.70 812.45 1,136.46
08.03.02.02 SISTEMA DE AGUAS GRISES -
08.03.02.02.01 TRAMPA DE NATAS Y SOLIDOS -
08.03.02.02.01.01 MOVIMIENTO DE TIERRAS -
08.03.02.02.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 27.36 26.52 725.59 26.79
08.03.02.02.01.01.02 REFINE Y NIVELACION PARA LOSA m2 28.80 0.88 25.34 28.20
08.03.02.02.01.01.03 ELIMINACION MATERAIL EXCEDENTE m3 34.20 10.61 362.86 33.49
08.03.02.02.01.02 OBRAS DE CONCRETO ARMADO -
08.03.02.02.01.02.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 109.44 23.40 2,560.90 107.16
08.03.02.02.01.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 66.53 4.05 269.45 65.14
08.03.02.02.01.02.03 CONCRETO f'c=210KG/CM2 m3 14.30 349.03 4,991.13 14.00
08.03.02.02.01.03 CURADO DE CONCRETO -
08.03.02.02.01.03.01 CURADO CON PRODUCTO QUIMICO m2 127.68 0.90 114.91 125.02
08.03.02.02.01.04 REVOQUES Y ENLUCIDOS -
08.03.02.02.01.04.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 127.68 20.68 2,640.42 125.02
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.03.02.02.01.05 PINTURA -
08.03.02.02.01.05.01 PINTURA ANTICORROCIVA A DOS MANOS m2 44.16 18.71 826.23 -
08.03.02.02.01.06 ACCESORIOS -
08.03.02.02.01.06.01 TEE PVC SAL 2" und 96.00 10.40 998.40 94.00
08.03.02.02.02 RED DE DESAGÜE 2" -
08.03.02.02.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 67.89 26.52 1,800.44 66.48
08.03.02.02.02.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO m3 33.95 50.30 1,707.69 33.24
08.03.02.02.02.03 SUMINISTRO Y COLOCACION TUBERIA PVC DE 2" m 212.16 5.88 1,247.50 207.74
08.03.02.03 SISTEMA DE AGUAS NEGRAS -
08.03.02.03.01 CAJA DE REGISTRO -
08.03.02.03.01.01 MOVIMIENTO DE TIERRAS -
08.03.02.03.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 5.04 26.52 133.66 4.94
08.03.02.03.01.01.02 REFINE Y NIVELACION PARA LOSA m2 10.08 0.88 8.87 9.87
08.03.02.03.01.01.03 ELIMINACION MATERAIL EXCEDENTE m3 6.30 10.61 66.84 6.17
08.03.02.03.01.02 OBRAS DE CONCRETO SIMPLE -
08.03.02.03.01.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 2.54 293.49 745.46 2.48
08.03.02.03.01.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 36.00 23.40 842.40 35.25
08.03.02.03.01.03 OBRAS DE CONCRETO ARMADO -
08.03.02.03.01.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 14.64 23.40 342.58 14.34
08.03.02.03.01.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 33.77 4.05 136.77 33.07
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.03.02.03.01.03.03 CONCRETO f'c=210KG/CM2 m3 0.50 349.03 174.52 0.49
08.03.02.03.01.04 CURADO DE CONCRETO -
08.03.02.03.01.04.01 CURADO CON PRODUCTO QUIMICO m2 32.40 0.90 29.16 31.73
08.03.02.03.01.05 REVOQUES Y ENLUCIDOS -
08.03.02.03.01.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 32.40 20.68 670.03 31.73
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.03.02.03.01.06 PINTURA -
08.03.02.03.01.06.01 PINTURA ANTICORROCIVA A DOS MANOS m2 14.64 18.71 273.91 -
08.03.02.03.02 SUMINISTRO E INSTALACION BIODIGESTOR -
08.03.02.03.02.01 MOVIMIENTO DE TIERRAS -
08.03.02.03.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 175.39 26.52 4,651.34 171.74
08.03.02.03.02.01.02 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 28.80 12.63 363.74 28.20
ZARANDEADO
08.03.02.03.02.01.03 ELIMINACION MATERAIL EXCEDENTE m3 219.24 10.61 2,326.14 214.67
08.03.02.03.02.02 OBRAS DE CONCRETO SIMPLE -
08.03.02.03.02.02.01 SOLADO e=4", CONCRETO C:H, 1:10 m2 100.80 23.33 2,351.66 98.70
08.03.02.03.02.03 ACCESORIOS -
08.03.02.03.02.03.01 BIODIGESTOR AUTOLIMPIABLE V=750 lts und 48.00 1,507.99 72,383.52 47.00
08.03.02.03.03 REGISTRO DE LODOS -
08.03.02.03.03.01 MOVIMIENTO DE TIERRAS -
08.03.02.03.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 21.60 26.52 572.83 21.15
08.03.02.03.03.01.02 REFINE Y NIVELACION PARA LOSA m2 27.00 0.88 23.76 26.44
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.03.02.03.03.01.03 ELIMINACION MATERAIL EXCEDENTE m3 27.00 10.61 286.47 26.44
08.03.02.03.03.02 OBRAS DE CONCRETO SIMPLE -
08.03.02.03.03.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 10.09 293.49 2,961.31 9.88
08.03.02.03.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 87.36 23.40 2,044.22 85.54
08.03.02.03.03.03 OBRAS DE CONCRETO ARMADO -
08.03.02.03.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m3 17.88 23.40 418.39 17.51
08.03.02.03.03.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 44.45 4.05 180.02 43.52
08.03.02.03.03.03.03 CONCRETO f'c=210KG/CM2 m3 1.35 349.03 471.19 1.32
08.03.02.03.03.04 CURADO DE CONCRETO -
08.03.02.03.03.04.01 CURADO CON PRODUCTO QUIMICO m2 87.36 0.90 78.62 85.54
08.03.02.03.03.05 REVOQUES Y ENLUCIDOS -
08.03.02.03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 87.36 20.68 1,806.60 85.54
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.03.02.03.03.06 ACCESORIOS -
08.03.02.03.03.06.01 ADAPTADOR C/ROSCA PVC 2" und 96.00 17.75 1,704.00 94.00
08.03.02.03.03.06.02 UNION UNIVERSAL DE PVC SP 2" und 96.00 18.08 1,735.68 94.00
08.03.02.03.03.06.03 VALVULA COMPUERTA DE BRONCE 2" und 48.00 88.58 4,251.84 47.00
08.03.02.03.04 RED DE DESAGÚE 4" -
08.03.02.03.04.01 EXCAVACION A MANO EN TERRENO NORMAL m3 87.24 26.52 2,313.60 85.42
08.03.02.03.04.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO m3 43.62 50.30 2,194.09 42.71
08.03.02.03.04.03 SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4" m 272.64 13.74 3,746.07 266.96
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.03.02.03.05 CAJA DISTRIBUIDORA DE CAUDALES -
08.03.02.03.05.01 MOVIMIENTO DE TIERRAS -
08.03.02.03.05.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 7.20 26.52 190.94 7.05
08.03.02.03.05.01.02 REFINE Y NIVELACION PARA LOSA m2 14.40 0.88 12.67 14.10
08.03.02.03.05.01.03 ELIMINACION MATERAIL EXCEDENTE m3 13.32 10.61 141.33 13.05
08.03.02.03.05.02 OBRAS DE CONCRETO SIMPLE -
08.03.02.03.05.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 2.88 293.49 845.25 2.82
08.03.02.03.05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 38.88 23.40 909.79 38.07
08.03.02.03.05.03 OBRAS DE CONCRETO ARMADO -
08.03.02.03.05.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 19.68 23.40 460.51 19.27
08.03.02.03.05.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 44.45 4.05 180.02 43.52
08.03.02.03.05.03.03 CONCRETO f'c=210KG/CM2 m3 0.72 349.03 251.30 0.71
08.03.02.03.05.04 CURADO DE CONCRETO -
08.03.02.03.05.04.01 CURADO CON PRODUCTO QUIMICO m2 38.88 0.90 34.99 38.07
08.03.02.03.05.05 REVOQUES Y ENLUCIDOS -
08.03.02.03.05.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 38.88 20.68 804.04 38.07
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.03.02.03.05.06 PINTURA -
08.03.02.03.05.06.01 PINTURA ANTICORROCIVA A DOS MANOS m2 18.72 18.71 350.25 -
08.03.02.04 ZANJAS DE INFILTRACION -
08.03.02.04.01 MOVIMIENTO DE TIERRAS -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.03.02.04.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 108.29 26.52 2,871.85 -
08.03.02.04.01.02 REFINE Y NIVELACION FONDO ZANJA m2 135.36 0.88 119.12 -
08.03.02.04.01.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 54.14 12.63 683.79 -
ZARANDEADO
08.03.02.04.01.04 ELIMINACION MATERAIL EXCEDENTE m3 94.75 10.61 1,005.30 -
08.03.02.04.02 RELLENO CON MATERIAL SELECCIONADO -
08.03.02.04.02.01 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - m3 20.30 108.81 2,208.84 -
2"
08.03.02.04.02.02 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 m3 20.30 108.81 2,208.84 -
1/2" - 2"
08.03.02.04.02.03 RELLENO CON MATERIAL PROPIO m3 30.54 11.70 357.32 -
08.03.02.04.03 ACCESORIOS -
08.03.02.04.03.01 MATERIAL INFILTRANTE EN ZANJAS m2 135.36 17.06 2,309.24 -
08.03.02.04.03.02 TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO m 225.60 40.85 9,215.76 -
08.04 UNIDAD BASICA RAMAL (10 UND) 78,376.96 -
08.04.01 CASETA 46,049.83 -
08.04.01.01 TRABAJOS PRELIMINARES -
08.04.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 52.20 0.54 28.19 36.54
08.04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 52.20 0.70 36.54 36.54
08.04.01.02 CIMIENTO CORRIDO -
08.04.01.02.01 MOVIMIENTO DE TIERRAS -
08.04.01.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 12.92 26.52 342.64 9.04
08.04.01.02.01.02 ELIMINACION MATERAIL EXCEDENTE m3 16.13 10.61 171.14 11.29
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.04.01.02.02 OBRAS DE CONCRETO SIMPLE -
08.04.01.02.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO m3 11.38 217.86 2,479.25 7.97
CORRIDO
08.04.01.02.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO m2 31.44 28.85 907.04 22.00
08.04.01.02.02.03 CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE m3 1.97 293.49 578.18 1.38
CIMIENTO
08.04.01.02.02.04 ENCOFRADO Y DESENCOFRADO NORMAL m3 6.00 23.40 140.40 -
08.04.01.02.02.05 SARDINEL DE DUCHA h=0.20 m m 15.00 20.77 311.55 -
08.04.01.03 LOSA PISO -
08.04.01.03.01 MOVIMIENTO DE TIERRAS -
08.04.01.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 18.09 26.52 479.75 -
08.04.01.03.01.02 ELIMINACION MATERAIL EXCEDENTE m3 22.61 10.61 239.89 -
08.04.01.03.01.03 REFINE Y NIVELACION PARA LOSA m2 21.80 0.88 19.18 -
08.04.01.03.02 OBRAS DE CONCRETO ARMADO -
08.04.01.03.02.01 ENCOFRADO Y DESENCOFRADO NORMAL m3 32.88 23.40 769.39 -
08.04.01.03.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 154.68 4.05 626.45 -
08.04.01.03.02.03 CONCRETO f'c=210KG/CM2 m3 5.36 349.03 1,870.80 -
08.04.01.04 MUROS Y COLUMNAS -
08.04.01.04.01 OBRAS DE CONCRETO ARMADO -
08.04.01.04.01.01 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS m2 15.70 21.17 332.37 9.42
08.04.01.04.01.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 102.36 4.05 414.56 71.66
08.04.01.04.01.03 CONCRETO f'c=210KG/CM2 PARA COLUMNETAS m3 2.49 349.03 869.08 1.49
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.04.01.04.02 MUROS Y TABIQUERIA -
08.04.01.04.02.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA m2 109.24 49.31 5,386.62 65.54
K.K.0.23x0.12x0.08M
08.04.01.04.03 REVOQUES ENLUCIDOS Y MOLDURAS -
08.04.01.04.03.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 m2 46.93 17.98 843.80 -
cm, ACABADO FROTACHADO
08.04.01.04.03.02 TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm m2 19.05 27.97 532.83 -
ACABADO PULIDO
08.04.01.04.04 PISOS Y PAVIMENTO -
08.04.01.04.04.01 CONTRAPISO ACABADO PULIDO DE 2" m2 15.55 23.39 363.71 -
08.04.01.05 COBERTURAS -
08.04.01.05.01 ESTRUCTURA DE MADERA -
08.04.01.05.01.01 CORREAS DE MADERA TORNILLO DE 2"x2" m 3.57 12.30 43.91 -
08.04.01.05.01.02 CORREAS DE MADERA TORNILLO DE 2"x3" m 8.42 35.65 300.17 -
08.04.01.05.02 COBERTURAS LIVIANA DE CALAMINA -
08.04.01.05.02.01 COBERTURA CON CALAMINA GALVANIZADA m2 44.94 32.89 1,478.08 -
08.04.01.06 PUERTAS Y VENTANAS -
08.04.01.06.01 CARPINTERIA DE MADERA -
08.04.01.06.01.01 MARCO Y PUERTA DE MADERA C/ CALAMINA m2 15.60 147.52 2,301.31 -
GALVANIZADA
08.04.01.06.01.02 VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 m2 7.52 41.80 314.34 -
X 0.80)
08.04.01.06.02 CERRAJERIA -
08.04.01.06.02.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2" und 30.00 15.98 479.40 -
08.04.01.06.02.02 CERRADURA TIPO PERILLA ALUMINIO 60mm und 10.00 31.20 312.00 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.04.01.07 LAVADERO DOMICIARIO -
08.04.01.07.01 MOVIMIENTO DE TIERRAS -
08.04.01.07.01.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 0.29 26.52 7.69 -
COMPACTADO
08.04.01.07.01.02 ELIMINACION MATERAIL EXCEDENTE m3 0.38 10.61 4.03 -
08.04.01.07.02 OBRAS DE CONCRETO SIMPLE -
08.04.01.07.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO m3 0.29 217.86 63.18 -
LAVADERO
08.04.01.07.02.02 CONTRAPISO e=4 cm.ACABADO TIPO VEREDA m2 41.29 24.90 1,028.12 -
08.04.01.07.03 OBRAS DE CONCRETO ARMADO -
08.04.01.07.03.01 CONCRETO f'c=175 kg/cm2 m3 0.78 311.75 243.17 -
08.04.01.07.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 54.83 4.05 222.06 -
08.04.01.07.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 20.69 21.17 438.01 -
08.04.01.07.04 MUROS Y TABIQUERIA -
08.04.01.07.04.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA m2 6.27 49.31 309.17 -
K.K.0.23x0.12x0.08M
08.04.01.07.05 REVOQUES ENLUCIDOS Y MOLDURAS -
08.04.01.07.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 m2 18.45 17.98 331.73 -
cm, ACABADO FROTACHADO
08.04.01.08 INSTALACIONES SANITARIAS AGUA -
08.04.01.08.01 APARATOS Y ACCESORIOS SANITARIO -
08.04.01.08.01.01 INODORO TANQUE BAJO INC./COLOCACION und 10.00 226.19 2,261.90 -
08.04.01.08.01.02 LAVADERO DE PARED und 10.00 170.09 1,700.90 -
08.04.01.08.01.03 DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE und 10.00 43.22 432.20 -
MEZCLADORA
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.04.01.08.01.04 CODO PVC SAL 2"x90º und 60.00 17.80 1,068.00 36.00
08.04.01.08.01.05 CODO PVC SAL 2"x45º und 60.00 17.80 1,068.00 36.00
08.04.01.08.01.06 TEE PVC SAL 2" und 10.00 10.40 104.00 6.00
08.04.01.08.01.07 YEE PVC SAL 2" und 40.00 17.80 712.00 24.00
08.04.01.08.01.08 SALIDA DE PVC SAL DE VENTILACION DE 2" pto 10.00 109.61 1,096.10 6.00
08.04.01.08.01.09 SUMIDERO DE BRONCE ROSCADO 2" und 20.00 106.57 2,131.40 -
08.04.01.08.01.10 REGISTRO DE BRONCE 2" und 30.00 40.82 1,224.60 -
08.04.01.08.02 ACCESORIO DE AGUA -
08.04.01.08.02.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2" pto 40.00 88.44 3,537.60 -
08.04.01.08.02.02 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC m 66.80 21.03 1,404.80 -
C-10 DE 1/2"
08.04.01.08.02.03 TEE PVC SP 1/2" und 30.00 9.26 277.80 -
08.04.01.08.02.04 CODO PVC SP 1/2"x90º und 40.00 9.26 370.40 -
08.04.01.08.02.05 UNION UNIVERSAL PVC 1/2" und 20.00 7.54 150.80 -
08.04.01.08.02.06 NIPLE C/ROSCA DE F°G° 1/2", L=1" und 20.00 10.47 209.40 -
08.04.01.08.02.07 ADAPTADOR C/ROSCA PVC 1/2" und 20.00 8.79 175.80 -
08.04.01.08.02.08 VALVULA COMPUERTA DE BRONCE 1/2" und 10.00 62.61 626.10 -
08.04.01.08.02.09 VALVULA ESFERICA DE 1/2" und 10.00 59.11 591.10 -
08.04.01.08.02.10 GRIFO BRONCE DE 1/2" und 20.00 64.36 1,287.20 -
08.04.02 EVACUACION DE AGUAS RESIDUALES 32,327.13 -
08.04.02.01 TRABAJOS PRELIMINARES -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.04.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 241.80 0.54 130.57 145.08
08.04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 241.80 0.70 169.26 145.08
08.04.02.02 SISTEMA DE AGUAS GRISES -
08.04.02.02.01 TRAMPA DE NATAS Y SOLIDOS -
08.04.02.02.01.01 MOVIMIENTO DE TIERRAS -
08.04.02.02.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 5.70 26.52 151.16 3.42
08.04.02.02.01.01.02 REFINE Y NIVELACION PARA LOSA m2 6.00 0.88 5.28 3.60
08.04.02.02.01.01.03 ELIMINACION MATERAIL EXCEDENTE m3 7.13 10.61 75.65 4.28
08.04.02.02.01.02 OBRAS DE CONCRETO ARMADO -
08.04.02.02.01.02.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 22.80 23.40 533.52 13.68
08.04.02.02.01.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 13.86 4.05 56.13 8.32
08.04.02.02.01.02.03 CONCRETO f'c=210KG/CM2 m3 2.98 349.03 1,040.11 1.79
08.04.02.02.01.03 CURADO DE CONCRETO -
08.04.02.02.01.03.01 CURADO CON PRODUCTO QUIMICO m2 26.60 0.90 23.94 15.96
08.04.02.02.01.04 REVOQUES Y ENLUCIDOS -
08.04.02.02.01.04.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 26.60 20.68 550.09 15.96
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.04.02.02.01.05 PINTURA -
08.04.02.02.01.05.01 PINTURA ANTICORROCIVA A DOS MANOS m2 9.20 18.71 172.13 -
08.04.02.02.01.06 ACCESORIOS -
08.04.02.02.01.06.01 TEE PVC SAL 2" und 20.00 10.40 208.00 12.00
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.04.02.02.02 RED DE DESAGÜE 2" -
08.04.02.02.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 14.14 26.52 374.99 8.48
08.04.02.02.02.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO m3 7.07 50.30 355.62 4.25
08.04.02.02.02.03 SUMINISTRO Y COLOCACION TUBERIA PVC DE 2" m 44.20 5.88 259.90 26.52
08.04.02.03 SISTEMA DE AGUAS NEGRAS -
08.04.02.03.01 CAJA DE REGISTRO -
08.04.02.03.01.01 MOVIMIENTO DE TIERRAS -
08.04.02.03.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 1.05 26.52 27.85 0.64
08.04.02.03.01.01.02 REFINE Y NIVELACION PARA LOSA m2 2.10 0.88 1.85 1.26
08.04.02.03.01.01.03 ELIMINACION MATERAIL EXCEDENTE m3 1.31 10.61 13.90 0.79
08.04.02.03.01.02 OBRAS DE CONCRETO SIMPLE -
08.04.02.03.01.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 0.53 293.49 155.55 0.32
08.04.02.03.01.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 7.50 23.40 175.50 4.50
08.04.02.03.01.03 OBRAS DE CONCRETO ARMADO -
08.04.02.03.01.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 3.05 23.40 71.37 1.84
08.04.02.03.01.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 7.04 4.05 28.51 4.22
08.04.02.03.01.03.03 CONCRETO f'c=210KG/CM2 m3 0.11 349.03 38.39 0.07
08.04.02.03.01.04 CURADO DE CONCRETO -
08.04.02.03.01.04.01 CURADO CON PRODUCTO QUIMICO m2 6.75 0.90 6.08 4.06
08.04.02.03.01.05 REVOQUES Y ENLUCIDOS -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.04.02.03.01.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 6.75 20.68 139.59 4.06
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.04.02.03.01.06 PINTURA -
08.04.02.03.01.06.01 PINTURA ANTICORROCIVA A DOS MANOS m2 3.05 18.71 57.07 -
08.04.02.03.02 SUMINISTRO E INSTALACION BIODIGESTOR -
08.04.02.03.02.01 MOVIMIENTO DE TIERRAS -
08.04.02.03.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 36.54 26.52 969.04 21.92
08.04.02.03.02.01.02 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 6.00 12.63 75.78 3.60
ZARANDEADO
08.04.02.03.02.01.03 ELIMINACION MATERAIL EXCEDENTE m3 45.68 10.61 484.66 27.41
08.04.02.03.02.02 OBRAS DE CONCRETO SIMPLE -
08.04.02.03.02.02.01 SOLADO e=4", CONCRETO C:H, 1:10 m2 21.00 23.33 489.93 12.60
08.04.02.03.02.03 ACCESORIOS -
08.04.02.03.02.03.01 BIODIGESTOR AUTOLIMPIABLE V=750 lts und 10.00 1,507.99 15,079.90 6.00
08.04.02.03.03 REGISTRO DE LODOS -
08.04.02.03.03.01 MOVIMIENTO DE TIERRAS -
08.04.02.03.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 4.50 26.52 119.34 2.70
08.04.02.03.03.01.02 REFINE Y NIVELACION PARA LOSA m2 5.63 0.88 4.95 3.38
08.04.02.03.03.01.03 ELIMINACION MATERAIL EXCEDENTE m3 5.63 10.61 59.73 3.38
08.04.02.03.03.02 OBRAS DE CONCRETO SIMPLE -
08.04.02.03.03.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 2.10 293.49 616.33 1.26
08.04.02.03.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 18.20 23.40 425.88 10.92
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.04.02.03.03.03 OBRAS DE CONCRETO ARMADO -
08.04.02.03.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m3 3.73 23.40 87.28 2.24
08.04.02.03.03.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 9.26 4.05 37.50 5.56
08.04.02.03.03.03.03 CONCRETO f'c=210KG/CM2 m3 0.28 349.03 97.73 0.17
08.04.02.03.03.04 CURADO DE CONCRETO -
08.04.02.03.03.04.01 CURADO CON PRODUCTO QUIMICO m2 18.20 0.90 16.38 10.92
08.04.02.03.03.05 REVOQUES Y ENLUCIDOS -
08.04.02.03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 18.20 20.68 376.38 10.92
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.04.02.03.03.06 ACCESORIOS -
08.04.02.03.03.06.01 ADAPTADOR C/ROSCA PVC 2" und 20.00 17.75 355.00 12.00
08.04.02.03.03.06.02 UNION UNIVERSAL DE PVC SP 2" und 20.00 18.08 361.60 12.00
08.04.02.03.03.06.03 VALVULA COMPUERTA DE BRONCE 2" und 10.00 88.58 885.80 6.00
08.04.02.03.04 RED DE DESAGÚE 4" -
08.04.02.03.04.01 EXCAVACION A MANO EN TERRENO NORMAL m3 18.18 26.52 482.13 10.91
08.04.02.03.04.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO m3 9.09 50.30 457.23 5.46
08.04.02.03.04.03 SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4" m 56.80 13.74 780.43 34.08
08.04.02.03.05 CAJA DISTRIBUIDORA DE CAUDALES -
08.04.02.03.05.01 MOVIMIENTO DE TIERRAS -
08.04.02.03.05.01.01 EXCAVACION A MANO EN TERRENO NORMAL m3 1.50 26.52 39.78 0.90
08.04.02.03.05.01.02 REFINE Y NIVELACION PARA LOSA m2 3.00 0.88 2.64 1.80
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.04.02.03.05.01.03 ELIMINACION MATERAIL EXCEDENTE m3 2.78 10.61 29.50 1.67
08.04.02.03.05.02 OBRAS DE CONCRETO SIMPLE -
08.04.02.03.05.02.01 CONCRETO f'c=140kg/cm2+25%P.M. m3 0.60 293.49 176.09 0.36
08.04.02.03.05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m3 8.10 23.40 189.54 4.86
08.04.02.03.05.03 OBRAS DE CONCRETO ARMADO -
08.04.02.03.05.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL m3 4.10 23.40 95.94 2.46
08.04.02.03.05.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 9.26 4.05 37.50 5.56
08.04.02.03.05.03.03 CONCRETO f'c=210KG/CM2 m3 0.15 349.03 52.35 0.10
08.04.02.03.05.04 CURADO DE CONCRETO -
08.04.02.03.05.04.01 CURADO CON PRODUCTO QUIMICO m2 8.10 0.90 7.29 4.86
08.04.02.03.05.05 REVOQUES Y ENLUCIDOS -
08.04.02.03.05.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, m2 8.10 20.68 167.51 4.86
DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
08.04.02.03.05.06 PINTURA -
08.04.02.03.05.06.01 PINTURA ANTICORROCIVA A DOS MANOS m2 3.90 18.71 72.97 -
08.04.02.04 ZANJAS DE INFILTRACION -
08.04.02.04.01 MOVIMIENTO DE TIERRAS -
08.04.02.04.01.01 REFINE Y NIVELACION FONDO ZANJA m2 28.20 0.88 24.82 -
08.04.02.04.01.02 EXCAVACION A MANO EN TERRENO NORMAL m3 22.56 26.52 598.29 -
08.04.02.04.01.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 11.28 12.63 142.47 -
ZARANDEADO
08.04.02.04.01.04 ELIMINACION MATERAIL EXCEDENTE m3 19.74 10.61 209.44 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
08.04.02.04.02 RELLENO CON MATERIAL SELECCIONADO -
08.04.02.04.02.01 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - m3 4.23 108.81 460.27 -
2"
08.04.02.04.02.02 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 m3 4.23 108.81 460.27 -
1/2" - 2"
08.04.02.04.02.03 RELLENO CON MATERIAL PROPIO m3 6.36 11.70 74.41 -
08.04.02.04.03 ACCESORIOS -
08.04.02.04.03.01 MATERIAL INFILTRANTE EN ZANJAS m2 28.20 17.06 481.09 -
08.04.02.04.03.02 TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO m 47.00 40.85 1,919.95 -
9 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES 162,771.12 -
9.01 CAMARA DE REJAS Y DESARENADOR (01 UND) 4,211.77 -
09.01.01 TRABAJOS PRELIMINARES 6.61 -
09.01.01.01 LIMPIEZA MANUAL DE TERRENO m2 5.33 0.54 2.88 5.33
09.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 5.33 0.70 3.73 5.33
09.01.02 MOVIMIENTO DE TIERRAS 132.67 -
09.01.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 2.72 35.36 96.18 2.72
COMPACTADO
09.01.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 4.54 1.06 4.81 4.54
09.01.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 0.53 15.93 8.44 0.53
ZARANDEADO
09.01.02.04 ELIMINACION MATERIAL EXCEDENTE m3 2.19 10.61 23.24 -
09.01.03 OBRAS DE CONCRETO SIMPLE 106.07 -
09.01.03.01 CONCRETO f'c=100 kg/cm2 m3 0.47 225.68 106.07 0.47
09.01.04 OBRAS DE CONCRETO ARMADO 1,634.21 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
09.01.04.01 CONCRETO f'c=210KG/CM2 m3 2.21 359.85 795.27 2.21
09.01.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 95.82 4.05 388.07 95.82
09.01.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 20.72 21.76 450.87 20.72
09.01.05 CURADO DE CONCRETO 41.00 -
09.01.05.01 CURADO CON PRODUCTO QUIMICO m2 45.56 0.90 41.00 45.56
09.01.06 REVOQUES Y ENLUCIDOS 367.39 -
09.01.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 9.12 18.86 172.00 9.12
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
09.01.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 10.36 18.86 195.39 10.36
ACABADO FROTACHADO
09.01.07 CARPINTERIA METALICA 1,923.82 -
09.01.07.01 REJA S NORMA RNC 30MM (e=15 t=30mm abertura 25mm) und 1.00 499.82 499.82 -
09.01.07.02 COMPUERTAS und 2.00 712.00 1,424.00 -
09.02 CAMARA REPARTIDORA DE CAUDALES(01 UND) 3,038.82 -
09.02.01 TRABAJOS PRELIMINARES 1.44 -
09.02.01.01 LIMPIEZA MANUAL DE TERRENO m2 1.16 0.54 0.63 1.16
09.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 1.16 0.70 0.81 1.16
09.02.02 MOVIMIENTO DE TIERRAS 58.41 -
09.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 1.17 35.36 41.37 1.17
COMPACTADO
09.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 1.16 1.06 1.23 1.16
09.02.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 0.10 15.93 1.59 0.10
ZARANDEADO
09.02.02.04 ELIMINACION MATERIAL EXCEDENTE m3 1.34 10.61 14.22 1.34
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
09.02.03 OBRAS DE CONCRETO SIMPLE 106.07 -
09.02.03.01 CONCRETO f'c=100 kg/cm2 m3 0.47 225.68 106.07 0.47
09.02.04 OBRAS DE CONCRETO ARMADO 655.79 -
09.02.04.01 CONCRETO f'c=210KG/CM2 m3 0.47 359.85 169.13 -
09.02.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 92.60 4.05 375.03 92.60
09.02.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 5.13 21.76 111.63 5.13
09.02.05 CURADO DE CONCRETO 4.62 -
09.02.05.01 CURADO CON PRODUCTO QUIMICO m2 5.13 0.90 4.62 -
09.02.06 REVOQUES Y ENLUCIDOS 48.85 -
09.02.06.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, m2 2.59 18.86 48.85 -
ACABADO FROTACHADO
09.02.07 CARPINTERIA METALICA 2,163.64 -
09.02.07.01 TAPA Y MARCO FFD PESADO und 2.00 369.82 739.64 -
09.02.07.02 COMPUERTAS und 2.00 712.00 1,424.00 -
09.03 TANQUE SEPTICO 30,850.36 -
09.03.01 TRABAJOS PRELIMINARES 45.14 -
09.03.01.01 LIMPIEZA MANUAL DE TERRENO m2 36.40 0.54 19.66 36.40
09.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 36.40 0.70 25.48 36.40
09.03.02 MOVIMIENTO DE TIERRAS 4,554.25 -
09.03.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 96.46 35.36 3,410.83 96.46
COMPACTADO
09.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 36.40 1.06 38.58 36.40
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
09.03.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 15.30 15.93 243.73 15.30
ZARANDEADO
09.03.02.04 ELIMINACION MATERIAL EXCEDENTE m3 81.16 10.61 861.11 81.16
09.03.03 OBRAS DE CONCRETO SIMPLE 929.36 -
09.03.03.01 SOLADO e=3" MEZCLA 1:2 CEMENTO HORMIGON m2 36.40 23.36 850.30 36.40
09.03.03.02 DADO DE CONCRETO PARA ANCLAJE TUBERIA - CAMARA und 2.00 39.53 79.06 2.00
09.03.04 OBRAS DE CONCRETO ARMADO 21,821.93 -
09.03.04.01 CONCRETO f'c=210KG/CM2 P/LOSA DE FONDO - PISO m3 29.50 359.85 10,615.58 29.50
09.03.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 1,566.28 4.05 6,343.43 1,566.28
09.03.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 223.48 21.76 4,862.92 223.48
09.03.05 REVOQUES Y ENLUCIDOS 2,390.69 -
09.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 126.76 18.86 2,390.69 126.76
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
09.03.06 ACCESORIOS 1,108.99 -
09.03.06.01 SUMINISTRO E INSTALACION DE TUBERIA PVC S-25 NTP ISO m 5.00 36.55 182.75 -
4435 DN 200MM C/ANILLO
09.03.06.02 SUMINISTRO E INSTALACION DE TUBERIA PVC S-20 NTP ISO m 5.00 26.05 130.25 -
4435 DN 160MM C/ANILLO
09.03.06.03 SUMINISTRO INST. VALVULA DE COMPUERTA DE HDF PARA und 1.00 101.29 101.29 -
TUB. PVC UF DN 200
09.03.06.04 SUMINISTRO E INSTALACION DE TEE SANITARIA DN=200mm und 1.00 86.86 86.86 -
09.03.06.05 SUMINISTRO E INSTALACION DE TEE SANITARIA DN=160mm und 3.00 54.86 164.58 -
09.03.06.06 VENTILACION DE F°G° DE DN=75MM und 2.00 221.63 443.26 -
09.04 LECHO DE SECADO 16,949.15 -
09.04.01 TRABAJOS PRELIMINARES 53.05 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
09.04.01.01 LIMPIEZA MANUAL DE TERRENO m2 42.78 0.54 23.10 -
09.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 42.78 0.70 29.95 -
09.04.02 MOVIMIENTO DE TIERRAS 6,889.32 -
09.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 115.71 35.36 4,091.51 -
COMPACTADO
09.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 44.85 1.06 47.54 -
09.04.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 23.76 15.93 378.50 -
ZARANDEADO
09.04.02.04 RELLENO C/AFIRMADO m3 23.76 56.36 1,339.11 -
09.04.02.05 RELLENO C/AGREGADO ARENA GRUESA E=0.35M m3 9.15 62.68 573.52 -
09.04.02.06 RELLENO CON GRAVA SUELTO DE 1/2" m3 1.83 64.93 118.82 -
09.04.02.07 RELLENO CON GRAVA SUELTO DE 3/4" m3 3.97 64.93 257.77 -
09.04.02.08 ELIMINACION MATERIAL EXCEDENTE m3 7.78 10.61 82.55 -
09.04.03 OBRAS DE CONCRETO ARMADO 5,931.87 -
09.04.03.01 CONCRETO f'c=210KG/CM2 P/LOSA DE FONDO - PISO m3 8.10 359.85 2,914.79 -
09.04.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 500.17 4.05 2,025.69 -
09.04.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 45.56 21.76 991.39 -
09.04.04 REVOQUES Y ENLUCIDOS 208.40 -
09.04.04.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, m2 12.60 12.14 152.96 -
C/IMPERMEABILIZANTES
09.04.04.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:3, m2 2.93 18.92 55.44 -
C/IMPERMEABILIZANTES
09.04.05 MUROS Y TABIQUERIA 2,657.98 -
09.04.05.01 MURO DE LADRILLO K.K. APAREJO DE SOGA E=0.12m (ESP. m2 58.43 45.49 2,657.98 -
HORIZONTAL E=0.10m)
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
09.04.06 COBERTURA 1,208.53 -
09.04.06.01 VIGA DE MADERA TORNILLO 3"x6" m 12.78 51.67 660.34 -
09.04.06.02 CORREAS DE MADERA TORNILLO DE 2"x2" m 7.20 16.20 116.64 -
09.04.06.03 PLANCHA DE CALAMINA TIPO TEJA ANDINA 0.72x1.14M m2 35.00 12.33 431.55 -
09.05 CAMARA DISTRIBUIDORA DE CAUDALES (03) 7,344.86 -
09.05.01 TRABAJOS PRELIMINARES 4.16 -
09.05.01.01 LIMPIEZA MANUAL DE TERRENO m2 3.36 0.54 1.81 3.36
09.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 3.36 0.70 2.35 3.36
09.05.02 MOVIMIENTO DE TIERRAS 194.38 -
09.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 3.32 35.36 117.40 3.32
COMPACTADO
09.05.02.02 REFINE Y NIVELACION PARA LOSA m2 3.36 1.06 3.56 3.36
09.05.02.03 ELIMINACION MATERAIL EXCEDENTE m3 6.92 10.61 73.42 6.92
09.05.03 OBRAS DE CONCRETO ARMADO 1,118.62 -
09.05.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 12.66 23.40 296.24 12.66
09.05.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 92.60 4.05 375.03 92.60
09.05.03.03 CONCRETO f'c=210KG/CM2 m3 1.25 357.88 447.35 -
09.05.04 CURADO DE CONCRETO 11.39 -
09.05.04.01 CURADO CON PRODUCTO QUIMICO m2 12.66 0.90 11.39 -
09.05.05 REVOQUES Y ENLUCIDOS 170.40 -
09.05.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION m2 8.24 20.68 170.40 -
IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
09.05.06 CARPINTERIA METALICA 5,381.46 -
09.05.06.01 TAPA Y MARCO FFD PESADO und 3.00 369.82 1,109.46 -
09.05.06.02 COMPUERTAS und 6.00 712.00 4,272.00 -
09.05.07 ACCESORIOS 464.45 -
09.05.07.01 TUBERIA PVC SAL DE 4" m 35.00 13.27 464.45 -
09.06 POZO DE PERCOLACION (06) 82,208.80 -
09.06.01 TRABAJOS PRELIMINARES 100.53 -
09.06.01.01 LIMPIEZA MANUAL DE TERRENO m2 137.41 0.54 74.20 137.41
09.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 37.61 0.70 26.33 37.61
09.06.02 MOVIMIENTO DE TIERRAS 30,545.92 -
09.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 625.23 35.36 22,108.13 625.23
COMPACTADO
09.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 137.41 1.06 145.65 137.41
09.06.02.03 ELIMINACION MATERIAL EXCEDENTE m3 781.54 10.61 8,292.14 781.54
09.06.03 CONCRETO SIMPLE 3,534.25 -
09.06.03.01 CONCRETO CILOPEO PARA CIMIENTACION 1:10 + 30% P.G. m3 20.94 168.78 3,534.25 6.98
09.06.04 CONCRETO ARMADO 15,619.23 -
09.06.04.01 CONCRETO f'c=175 kg/cm2 m3 20.94 320.59 6,713.15 6.98
09.06.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60 kg 1,378.44 4.05 5,582.68 459.48
09.06.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 152.73 21.76 3,323.40 50.92
09.06.05 TABIQUERIA EN FORMA CIRCULAR 16,984.54 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
09.06.05.01 MURO LADRILLO K.K. DE ARCILLA 18 H. (0.09x0.13x0.24) m2 333.75 50.89 16,984.54 111.26
AMARRE DE CANTO MORTERO 1:1:5
09.06.06 RELLENO CON GRAVA 13,992.97 -
09.06.06.01 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" m3 128.60 108.81 13,992.97 21.43
09.06.07 ACCESORIOS 1,431.36 -
09.06.07.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 160MM m 36.00 36.82 1,325.52 -
09.06.07.02 TUBERIA PVC SAL DE 2" m 18.00 5.88 105.84 -
09.07 INSTALACION DE TUBERIAS (180m) 15,515.86 -
09.07.01 TRABAJOS PRELIMINARES 218.16 -
09.07.01.01 LIMPIEZA MANUAL DE TERRENO m2 108.00 0.54 58.32 9.00
09.07.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO m2 108.00 1.48 159.84 9.00
09.07.02 MOVIMIENTO DE TIERRAS 8,670.10 -
09.07.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA m3 216.00 26.52 5,728.32 18.00
09.07.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO m 180.00 1.06 190.80 15.00
MATERIAL COMPACTADO
09.07.02.03 CAMA DE APOYO PARA TUBERIA (0.60x0.10m) m 180.00 4.70 846.00 15.00
09.07.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m 180.00 2.71 487.80 15.00
(0.60 x 0.20 m)
09.07.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 97.20 14.58 1,417.18 8.10
ZARANDEADO
09.07.03 TENDIDO DE TUBERIA 6,627.60 -
09.07.03.01 SUMINISTRO Y COLOCACION DE TUBERIA DE PVC C-7.5 NTP m 180.00 36.82 6,627.60 15.00
1452 DN 200MM
09.08 CERCO PERIMETRICO (L=120.00 m) 2,651.50 -
09.08.01 TRABAJOS PRELIMINARES 74.40 -
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
09.08.01.01 LIMPIEZA MANUAL DE TERRENO m2 60.00 0.54 32.40 -
09.08.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA m2 60.00 0.70 42.00 -
09.08.02 MOVIMIENTO DE TIERRAS 108.52 -
09.08.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL m3 2.98 26.52 79.03 -
COMPACTADO
09.08.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO m2 15.80 1.06 16.75 -
09.08.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO m3 0.60 15.93 9.56 -
ZARANDEADO
09.08.02.04 ELIMINACION MATERAIL EXCEDENTE m3 0.30 10.61 3.18 -
09.08.03 OBRAS DE CONCRETO SIMPLE 794.74 -
09.08.03.01 CONCRETO f'c=140 kg/cm2 m3 2.98 266.69 794.74 -
09.08.04 CERCO PERIMETRICO CON MALLA OLIMPICA GALVANIZADA 1,673.84 -
09.08.04.01 CERCO PERIMETRICO DE ALAMBRE DE PUAS m 120.00 12.57 1,508.40 -
09.08.04.02 PUERTA DE MADERA CON MARCO O SOPORTES und 1.00 95.75 95.75 -
09.08.04.03 PINTURA ESMALTE EN PUERTAS Y VENTANAS A DOS MANOS m2 3.50 19.91 69.69 -
10 CAPACITACION Y EDUCACION 30,000.00 -
10.01 DESAROLLO DE LAS CAPACITACIONES Y/O TALLERES glb 1.00 30,000.00 30,000.00 0.45
11 ENSIBILIZACION, EDUCACION
MITIGACION DEL IMPACTO Y PARTICIPACION CIUDADANA DE
AMBIENTAL 64,429.67
APOYO A LA GESTION DE AP Y AS -
11.01 MITIGACION DEL IMPACTO AMBIENTAL glb 1.00 64,429.67 64,429.67 0.60

1 COSTO DIRECTO 4,301,790.29


2 GASTOS GENERALES 12.00% 516,214.83
VALORIZACION MENSU
OBRA “MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGR
FORMULA : AGUA POTABLE Y ALCANTARILLADO Y PTAR
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
CONTRATISTA : CONSORCIO MONTE SINAI
SUPERVISION : ING. RAFAEL ALFONSO ZARATE AVILA
FECHA 30 DE SETIEMBRE DEL 2018

PRESUPUESTO CONTRACTUAL AVANCE A


ITEM DESCRIPCION
UND. METRADO P.U. PARCIAL METRADO
3 UTILIDADES 5.00% 215,089.51
4 TOTAL PRESUPUESTO 5,033,094.63
5 SUB TOTAL VALORIZADO SIN IGV 5,033,094.63
6 IGV 18.00% 905,957.03
7 TOTAL VALORIZADO CON IGV 5,939,051.66
8 PORCENTAJE DE AVANCE 100%

% DE AVANCE MENSUAL A EJECUTADO 9.43%


% DE AVANCE ACUMULADO 62.51%
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


419,474.96 166,413.11 585,888.07 545,293.30
81,761.70 288.00 82,049.70 14,832.71

2,328.00 64.67% 0.08 288.00 8.00% 0.73 2,616.00 72.67% 0.27 984.00
1,986.12 100.00% - 0.00% 1.00 1,986.12 100.00% - 0.00
64,092.73 89.33% - - 0.00% 0.89 64,092.73 89.33% 0.11 7,652.86
13,354.85 82.33% - - 0.00% 0.82 13,354.85 82.33% 0.18 2,865.61
- 0.00% - 0.00% - - 0.00% 96.00 3,330.24
821.47 18.15 - 839.62 72.18

151.63 62.67% 0.15 18.15 7.50% 1.40 169.78 70.17% 0.60 72.18
669.84 100.00% - 0.00% 2.00 669.84 100.00% - 0.00
0.00 0.00 - 0.00 44,400.82

- - - - 0.00% 113.28
- 0.00% - - 0.00% - - 0.00% 92.85 49.21
- 0.00% - - 0.00% - - 0.00% 92.85 64.07
- - - - - 5,553.56
- 0.00% - 0.00% - - 0.00% 118.98 4,127.42
- 0.00% - 0.00% - - 0.00% 11.44 11.90
- 0.00% - 0.00% - - 0.00% 29.74 467.51
- 0.00% - 0.00% - - 0.00% 89.23 946.73
- - - - - 17,643.29
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 71.64 15,129.65
- 0.00% - 0.00% - - 0.00% 11.54 2,513.64
- - - - - 12,342.25
- 0.00% - 0.00% - - 0.00% 14.86 5,444.70
- 0.00% - 0.00% - - 0.00% 125.46 2,691.12
- 0.00% - 0.00% - - 0.00% 1,043.78 4,206.43
- - - - - 92.87
- 0.00% - 0.00% - - 0.00% 103.19 92.87
- - - - - 2,765.92
- 0.00% - 0.00% - - 0.00% 109.69 2,268.39
- 0.00% - 0.00% - - 0.00% 26.38 497.53
- - - - - 1,509.64
- 0.00% - 0.00% - - 0.00% 1.00 1,149.82
- 0.00% - 0.00% - - 0.00% 1.00 359.82
- - - - - 3,430.69
- 0.00% - 0.00% - - 0.00% 136.07 1,378.39
- 0.00% - 0.00% - - 0.00% 109.69 2,052.30
- - - - 0.00% - 949.32
- 0.00% - 0.00% - - 0.00% 1.00 949.32
0.00 0.00 - 0.00 - 11,261.94
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 21.92
- 0.00% - 0.00% - - 0.00% 17.82 9.62
- 0.00% - 0.00% - - 0.00% 17.82 12.30
- - - - - 729.06
- 0.00% - 0.00% - - 0.00% 15.26 529.37
- 0.00% - 0.00% - - 0.00% 16.62 17.62
- 0.00% - 0.00% - - 0.00% 3.81 60.69
- 0.00% - 0.00% - - 0.00% 11.44 121.38
0.00 - - - - 361.58
- 0.00% - 0.00% - - 0.00% 1.66 361.58
- - - - - 6,327.70
- 0.00% - 0.00% - - 0.00% 7.45 2,614.95
- 0.00% - 0.00% - - 0.00% 775.96 3,142.64
- 0.00% - 0.00% - - 0.00% 26.20 570.11
- - - - - 23.92
- 0.00% - 0.00% - - 0.00% 26.58 23.92
- - - - - 512.16
- 0.00% - 0.00% - - 0.00% 27.58 512.16
- - - - - 2,683.92
- 0.00% - 0.00% - - 0.00% 2.00 1,084.28
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 2.00 1,599.64
- - - - - 196.83
- 0.00% - 0.00% - - 0.00% 19.43 196.83
- - - - - 404.85
- 0.00% - 0.00% - - 0.00% 1.00 404.85
243,948.52 139,014.92 - 382,963.44 - 240,136.24

14,311.20 - - 14,311.20 - -
3,773.60 100.00% - 0.00% 7,120.00 3,773.60 100.00% - 0.00
10,537.60 100.00% - 0.00% 7,120.00 10,537.60 100.00% - 0.00
117,264.92 69,602.92 - 186,867.84 - 147,088.64
47,736.00 31.60% 1,036.00 27,474.72 18.19% 2,836.00 75,210.72 49.79% 2,860.00 75,847.20
6,349.40 42.06% 3,700.00 3,922.00 25.98% 9,690.00 10,271.40 68.05% 4,550.00 4,823.00
28,153.00 42.06% 3,700.00 17,390.00 25.98% 9,690.00 45,543.00 68.05% 4,550.00 21,385.00
16,232.90 42.06% 3,700.00 10,027.00 25.98% 9,690.00 26,259.90 68.05% 4,550.00 12,330.50
18,793.62 30.17% 740.00 10,789.20 17.32% 2,029.00 29,582.82 47.50% 2,243.00 32,702.94
112,372.40 69,412.00 - 181,784.40 - 85,358.00
112,372.40 42.06% 3,700.00 69,412.00 25.98% 9,690.00 181,784.40 68.05% 4,550.00 85,358.00
- - - - - 7,689.60
- 0.00% - 0.00% - - 0.00% 14,240.00 7,689.60
0.00 0.00 - 0.00 - 16,906.30
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - 0.00% - 26.11
- 0.00% - 0.00% - - 0.00% 21.06 11.37
- 0.00% - 0.00% - - 0.00% 21.06 14.74
- - - - - 491.64
- 0.00% - 0.00% - - 0.00% 12.64 335.21
- 0.00% - 0.00% - - 0.00% 21.06 22.32
- 0.00% - 0.00% - - 0.00% 12.64 134.11
- - - - - 7,274.93
- 0.00% - 0.00% - - 0.00% 13.10 4,389.55
- 0.00% - 0.00% - - 0.00% 132.60 2,885.38
- - - - - 119.34
- 0.00% - 0.00% - - 0.00% 132.60 119.34
- - - - - 1,714.23
- 0.00% - 0.00% - - 0.00% 110.24 1,714.23
- - - - - 1,894.36
- 0.00% - 0.00% - - 0.00% 26.00 1,894.36
- - - - - 1,190.59
- 0.00% - 0.00% - - 0.00% 110.24 1,190.59
- - - - - 4,195.10
- 0.00% - 0.00% - - 0.00% 26.00 4,195.10
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


0.00 0.00 - 0.00 - 3,836.32

- - - - - 7.14
- 0.00% - 0.00% - - 0.00% 5.75 3.11
- 0.00% - 0.00% - - 0.00% 5.75 4.03
- - - - - 176.68
- 0.00% - 0.00% - - 0.00% 4.68 124.11
- 0.00% - 0.00% - - 0.00% 5.75 6.10
- 0.00% - 0.00% - - 0.00% 4.38 46.47
- - - - - 190.13
- 0.00% - 0.00% - - 0.00% 0.23 6.65
- 0.00% - 0.00% - - 0.00% 0.63 183.48
- - - - - 1,643.95
- 0.00% - 0.00% - - 0.00% 2.63 881.26
- 0.00% - 0.00% - - 0.00% 35.05 762.69
- - - - - 364.30
- 0.00% - 0.00% - - 0.00% 5.00 364.30
- - - - - 85.17
- 0.00% - 0.00% - - 0.00% 10.20 85.17
- - - - - 1,368.95
- 0.00% - 0.00% - - 0.00% 5.00 1,368.95
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


0.00 0.00 - 0.00 0.00% - 1,147.04

- - - - - 2.30
- 0.00% - 0.00% - - 0.00% 1.85 1.00
- 0.00% - 0.00% - - 0.00% 1.85 1.30
- - - - - 72.19
- 0.00% - 0.00% - - 0.00% 1.90 50.39
- 0.00% - 0.00% - - 0.00% 1.55 1.64
- 0.00% - 0.00% - - 0.00% 1.90 20.16
- - - - - 182.05
- 0.00% - 0.00% - - 0.00% 2.56 140.03
- 0.00% - 0.00% - - 0.00% 0.07 15.25
- 0.00% - 0.00% - - 0.00% 0.04 10.45
- 0.00% - 0.00% - - 0.00% 0.75 16.32
- - - - - 650.25
- 0.00% - 0.00% - - 0.00% 0.91 319.41
- 0.00% - 0.00% - - 0.00% 10.16 221.08
- 0.00% - 0.00% - - 0.00% 27.10 109.76
- - - - - 0.82
- 0.00% - 0.00% - - 0.00% 0.91 0.82
- - - - - 55.98
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 3.60 55.98
- - - - - 72.86
- 0.00% - 0.00% - - 0.00% 1.00 72.86
- - - - - 21.60
- 0.00% - 0.00% - - 0.00% 2.00 21.60
- - - - - 88.99
- 0.00% - 0.00% - - 0.00% 1.00 88.99
0.00 0.00 - 0.00 - 43,661.08

- - - - - 486.58
- 0.00% - 0.00% - - 0.00% 392.40 211.90
- 0.00% - 0.00% - - 0.00% 392.40 274.68
- - - - - 2,038.44
- 0.00% - 0.00% - - 0.00% 54.90 1,455.95
- 0.00% - 0.00% - - 0.00% 54.90 582.49
- - - - - 196.04
- 0.00% - 0.00% - - 0.00% 0.90 196.04
- - - - - 20,712.52
- 0.00% - 0.00% - - 0.00% 18.52 6,500.52
- 0.00% - 0.00% - - 0.00% 28.80 9,650.30
- 0.00% - 0.00% - - 0.00% 66.96 1,457.05
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 766.58 3,104.65
- - - - - 1,041.23
- 0.00% - 0.00% - - 0.00% 66.96 1,041.23
- - - - - 19,186.27
- 0.00% - 0.00% - - 0.00% 150.30 5,672.32
- 0.00% - 0.00% - - 0.00% 99.00 5,328.18
- 0.00% - 0.00% - - 0.00% 117.00 1,710.54
- 0.00% - 0.00% - - 0.00% 126.00 2,886.66
- 0.00% - 0.00% - - 0.00% 9.00 2,815.20
- 0.00% - 0.00% - - 0.00% 9.00 773.37
- - - - -
- - - - -
0.00 0.00 - 0.00 - 125,496.56

- - - - - 178.56
- 0.00% - 0.00% - - 0.00% 144.00 77.76
- 0.00% - 0.00% - - 0.00% 144.00 100.80
- - - - - 13,238.34
- 0.00% - 0.00% - - 0.00% 453.10 12,016.21
- 0.00% - 0.00% - - 0.00% 144.00 152.64
- 0.00% - 0.00% - - 0.00% 100.80 1,069.49
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 1,568.30
- 0.00% - 0.00% - - 0.00% 7.20 1,568.30
- - - - - 65,668.81
- 0.00% - 0.00% - - 0.00% 79.98 28,072.98
- 0.00% - 0.00% - - 0.00% 5,228.36 21,174.86
- 0.00% - 0.00% - - 0.00% 754.64 16,420.97
- - - - - 244.89
- 0.00% - 0.00% - - 0.00% 272.10 244.89
- - - - - 11,816.12
- 0.00% - 0.00% - - 0.00% 174.40 3,160.13
- 0.00% - 0.00% - - 0.00% 458.96 8,655.99
- - - - - 8,418.66
- 0.00% - 0.00% - - 0.00% 174.40 1,456.24
- 0.00% - 0.00% - - 0.00% 458.96 6,962.42
- - - - - 22,285.20
- 0.00% - 0.00% - - 0.00% 18.90 2,368.36
- 0.00% - 0.00% - - 0.00% 37.80 4,509.92
- 0.00% - 0.00% - - 0.00% 75.60 9,473.44
- 0.00% - 0.00% - - 0.00% 31.08 5,933.48
- - - - - 2,077.68
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 2.00 2,077.68
86,848.12 27,092.04 - 113,940.16 - 35,329.57

150.25 - - 150.25 - -
65.43 100.00% - - 0.00% 121.17 65.43 100.00% - 0.00
84.82 100.00% - - 0.00% 121.17 84.82 100.00% - 0.00
15,345.33 186.75 - 15,532.08 - 2,078.95
15,292.99 100.00% - - 0.00% 204.89 15,292.99 100.00% - 0.00
52.34 100.00% - - 0.00% 49.38 52.34 100.00% - 0.00
- 0.00% 11.88 186.75 66.11% 11.88 186.75 66.11% 6.09 95.73
- 0.00% - 0.00% - - 0.00% 186.92 1,983.22
26,014.24 - - 26,014.24 - 891.78
- 0.00% - 0.00% - - 0.00% 8.90 891.78
26,014.24 100.00% - - 0.00% 119.43 26,014.24 100.00% - 0.00
44,306.23 26,855.56 - 71,161.79 - 3,242.84
12,972.96 38.28% 55.25 19,392.75 57.22% 92.21 32,365.71 95.50% 4.35 1,526.85
31,333.27 100.00% - - 0.00% 7,736.61 31,333.27 100.00% - 0.00
- 0.00% 342.96 7,462.81 81.30% 342.96 7,462.81 81.30% 78.86 1,715.99
33.26 49.73 - 82.99 - 3.92
33.26 38.28% 55.25 49.73 57.22% 92.21 82.99 95.50% 4.35 3.92
998.81 - - 998.81 - -
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


998.81 100.00% - - 0.00% 53.10 998.81 100.00% - 0.00
- - - - - 6,704.58
- 0.00% - 0.00% - - 0.00% 312.75 3,787.40
- 0.00% - 0.00% - - 0.00% 183.10 2,217.34
- 0.00% - 0.00% - - 0.00% 57.79 699.84
- - - - - 1,550.87
- 0.00% - 0.00% - - 0.00% 1.00 72.86
- 0.00% - 0.00% - - 0.00% 1.00 200.82
- 0.00% - 0.00% - - 0.00% 3.00 542.46
- 0.00% - 0.00% - - 0.00% 3.00 734.73
- - - - - 18,724.20
- 0.00% - 0.00% - - 0.00% 10.00 1,849.10
- 0.00% - 0.00% - - 0.00% 5.00 954.55
- 0.00% - 0.00% - - 0.00% 5.00 954.55
- 0.00% - 0.00% - - 0.00% 100.00 14,966.00
- - - - - 1,552.71
- 0.00% - 0.00% - - 0.00% 183.10 1,528.89
- 0.00% - 0.00% - - 0.00% 1.57 23.82
- - - - - 579.72
- 0.00% - 0.00% - - 0.00% 1.00 579.72
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


0.00 0.00 - 0.00 - 7,753.58

- - - - - 147.60
- 0.00% - 0.00% - - 0.00% 120.00 64.80
- 0.00% - 0.00% - - 0.00% 120.00 82.80
- - - - - 599.69
- 0.00% - 0.00% - - 0.00% 14.11 367.14
- 0.00% - 0.00% - - 0.00% 35.28 36.69
- 0.00% - 0.00% - - 0.00% 3.53 55.49
- 0.00% - 0.00% - - 0.00% 13.23 140.37
- - - - - 3,694.64
- 0.00% - 0.00% - - 0.00% 14.14 3,694.64
- - - - - 3,311.65
- 0.00% - 0.00% - - 0.00% 240.00 3,016.80
- 0.00% - 0.00% - - 0.00% 1.00 95.75
- 0.00% - 0.00% - - 0.00% 10.00 199.10
6,095.15 0.00 - 6,095.15 - 458.96

9.69 - - 9.69 - -
4.22 100.00% - 0.00% 7.81 4.22 100.00% - 0.00
5.47 100.00% - 0.00% 7.81 5.47 100.00% - 0.00
548.35 - - 548.35 - -
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


436.52 100.00% - 0.00% 16.46 436.52 100.00% - 0.00
8.28 100.00% - 0.00% 7.81 8.28 100.00% - 0.00
103.55 100.00% - 0.00% 9.76 103.55 100.00% - 0.00
6.53 - - 6.53 - -
6.53 100.00% - 0.00% 0.03 6.53 100.00% - 0.00
4,474.07 - - 4,474.07 - -
2,516.67 100.00% - 0.00% 7.17 2,516.67 100.00% - 0.00
1,604.80 100.00% - 0.00% 73.75 1,604.80 100.00% - 0.00
352.60 100.00% - 0.00% 87.06 352.60 100.00% - 0.00
275.83 - - 275.83 - -
275.83 100.00% - 0.00% 73.75 275.83 100.00% - 0.00
707.82 - - 707.82 - -
707.82 100.00% - 0.00% 37.53 707.82 100.00% - 0.00
72.86 - - 72.86 - -
72.86 100.00% - 0.00% 1.00 72.86 100.00% - 0.00
- - - - - 185.17
- 0.00% - 0.00% - - 0.00% 21.81 185.17
- - - - - 273.79
- 0.00% - 0.00% - - 0.00% 1.00 273.79
259,244.77 36,785.28 - 296,030.05 - 84,766.23
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


59,761.69 36,785.28 - 96,546.97 - 38,200.48

3,707.93 - - 3,707.93 - -
991.23 100.00% - 0.00% 1,835.61 991.23 100.00% - 0.00
2,716.70 100.00% - 0.00% 1,835.61 2,716.70 100.00% - 0.00
40,917.76 26,852.28 - 67,770.04 - 26,116.44
20,367.36 43.58% 504.00 13,366.08 28.60% 1,272.00 33,733.44 72.18% 490.19 12,999.84
1,696.00 43.58% 1,050.00 1,113.00 28.60% 2,650.00 2,809.00 72.18% 1,021.22 1,082.49
7,520.00 43.58% 1,050.00 4,935.00 28.60% 2,650.00 12,455.00 72.18% 1,021.22 4,799.73
4,336.00 43.58% 1,050.00 2,845.50 28.60% 2,650.00 7,181.50 72.18% 1,021.22 2,767.51
6,998.40 43.58% 315.00 4,592.70 28.60% 795.00 11,591.10 72.18% 306.37 4,466.87
15,136.00 9,933.00 - 25,069.00 - 9,661.03
15,136.00 43.58% 1,050.00 9,933.00 28.60% 2,650.00 25,069.00 72.18% 1,021.25 9,661.03
- - - - - 2,423.01
- 0.00% - 0.00% - - 0.00% 3,671.22 2,423.01
0.00 0.00 - 0.00 - 4,736.48

- - - - - 8.04
- 0.00% - 0.00% - - 0.00% 6.48 3.50
- 0.00% - 0.00% - - 0.00% 6.48 4.54
- - - - - 151.30
- 0.00% - 0.00% - - 0.00% 3.89 103.16
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 6.48 6.87
- 0.00% - 0.00% - - 0.00% 3.89 41.27
- - - - - 2,277.80
- 0.00% - 0.00% - - 0.00% 4.03 1,389.99
- 0.00% - 0.00% - - 0.00% 40.80 887.81
- - - - - 36.34
- 0.00% - 0.00% - - 0.00% 40.38 36.34
- - - - - 527.46
- 0.00% - 0.00% - - 0.00% 33.92 527.46
- - - - - 582.88
- 0.00% - 0.00% - - 0.00% 8.00 582.88
- - - - - 366.34
- 0.00% - 0.00% - - 0.00% 33.92 366.34
- - - - - 786.32
- 0.00% - 0.00% - - 0.00% 8.00 786.32
0.00 0.00 - 0.00 - 1,637.06

- - - - - 2.85
- 0.00% - 0.00% - - 0.00% 2.30 1.24
- 0.00% - 0.00% - - 0.00% 2.30 1.61
- - - - - 70.60
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 1.87 49.59
- 0.00% - 0.00% - - 0.00% 2.30 2.44
- 0.00% - 0.00% - - 0.00% 1.75 18.57
- - - - - 73.00
- 0.00% - 0.00% - - 0.00% 0.09 2.60
- 0.00% - 0.00% - - 0.00% 0.25 70.40
- - - - - 667.24
- 0.00% - 0.00% - - 0.00% 1.05 362.16
- 0.00% - 0.00% - - 0.00% 14.02 305.08
- - - - - 145.72
- 0.00% - 0.00% - - 0.00% 2.00 145.72
- - - - - 34.07
- 0.00% - 0.00% - - 0.00% 4.08 34.07
- - - - - 643.58
- 0.00% - 0.00% - - 0.00% 2.00 643.58
0.00 0.00 - 0.00 - 2,336.78

- - - - - 4.57
- 0.00% - 0.00% - - 0.00% 3.69 1.99
- 0.00% - 0.00% - - 0.00% 3.69 2.58
- - - - - 144.01
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 3.79 100.51
- 0.00% - 0.00% - - 0.00% 3.10 3.29
- 0.00% - 0.00% - - 0.00% 3.79 40.21
- - - - - 378.67
- 0.00% - 0.00% - - 0.00% 5.12 280.06
- 0.00% - 0.00% - - 0.00% 0.14 30.49
- 0.00% - 0.00% - - 0.00% 0.14 35.48
- 0.00% - 0.00% - - 0.00% 1.50 32.64
- - - - - 1,329.04
- 0.00% - 0.00% - - 0.00% 1.81 667.33
- 0.00% - 0.00% - - 0.00% 20.32 442.16
- 0.00% - 0.00% - - 0.00% 54.21 219.55
- - - - - 1.63
- 0.00% - 0.00% - - 0.00% 1.81 1.63
- - - - - 111.96
- 0.00% - 0.00% - - 0.00% 7.20 111.96
- - - - - 145.72
- 0.00% - 0.00% - - 0.00% 2.00 145.72
- - - - - 43.20
- 0.00% - 0.00% - - 0.00% 4.00 43.20
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 177.98
- 0.00% - 0.00% - - 0.00% 2.00 177.98
9,971.86 0.00 - 9,971.86 - 3,484.73

36.16 - - 36.16 - -
15.75 100.00% - - 0.00% 29.16 15.75 100.00% - 0.00
20.41 100.00% - - 0.00% 29.16 20.41 100.00% - 0.00
208.08 - - 208.08 - -
112.27 100.00% - - 0.00% 7.22 112.27 100.00% - 0.00
95.81 100.00% - - 0.00% 9.03 95.81 100.00% - 0.00
810.29 - - 810.29 - -
810.29 100.00% - - 0.00% 3.72 810.29 100.00% - 0.00
6,438.62 - - 6,438.62 - -
3,723.77 100.00% - - 0.00% 10.10 3,723.77 100.00% - 0.00
1,315.68 100.00% - - 0.00% 324.86 1,315.68 100.00% - 0.00
1,399.17 100.00% - - 0.00% 64.30 1,399.17 100.00% - 0.00
240.48 - - 240.48 - -
240.48 100.00% - - 0.00% 64.30 240.48 100.00% - 0.00
1,675.20 - - 1,675.20 - -
589.81 100.00% - - 0.00% 32.55 589.81 100.00% - 0.00
1,085.39 100.00% - - 0.00% 59.90 1,085.39 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


237.77 - - 237.77 - 629.64
72.86 100.00% - - 0.00% 1.00 72.86 100.00% - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 169.91
- 0.00% - 0.00% - - 0.00% 1.00 294.82
164.91 50.00% - - 0.00% 1.00 164.91 50.00% 1.00 164.91
- - - - - 1,583.58
- 0.00% - 0.00% - - 0.00% 38.72 674.50
- 0.00% - 0.00% - - 0.00% 33.62 909.08
- - - - - 964.35
- 0.00% - 0.00% - - 0.00% 1.00 208.62
- 0.00% - 0.00% - - 0.00% 1.00 366.59
- 0.00% - 0.00% - - 0.00% 1.00 389.14
325.26 - - 325.26 - 307.16
- - - - -
0.19 100.00% - - 0.00% 0.36 0.19 100.00% - 0.00
0.25 100.00% - - 0.00% 0.36 0.25 100.00% - 0.00
- - - - - 0.00
5.83 100.00% - - 0.00% 0.22 5.83 100.00% - 0.00
0.38 100.00% - - 0.00% 0.36 0.38 100.00% - 0.00
3.82 100.00% - - 0.00% 0.36 3.82 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
176.97 100.00% - - 0.00% 0.48 176.97 100.00% - 0.00
76.26 100.00% - - 0.00% 18.83 76.26 100.00% - 0.00
21.76 100.00% - - 0.00% 1.00 21.76 100.00% - 0.00
- - - - - 0.00
7.48 100.00% - - 0.00% 2.00 7.48 100.00% - 0.00
- - - - - 0.00
32.32 100.00% - - 0.00% 2.00 32.32 100.00% - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 307.16
187,289.02 0.00 - 187,289.02 - 12,334.45

4,923.26 - - 4,923.26 - -
1,248.15 100.00% - 0.00% 2,311.39 1,248.15 100.00% - 0.00
3,675.11 100.00% - 0.00% 2,311.39 3,675.11 100.00% - 0.00
154,373.06 - - 154,373.06 - -
61,298.06 100.00% - - 0.00% 2,311.39 61,298.06 100.00% - 0.00
4,900.15 100.00% - - 0.00% 4,622.78 4,900.15 100.00% - 0.00
21,727.07 100.00% - - 0.00% 4,622.78 21,727.07 100.00% - 0.00
12,527.73 100.00% - - 0.00% 4,622.78 12,527.73 100.00% - 0.00
53,920.05 100.00% - - 0.00% 3,698.22 53,920.05 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


27,992.70 - - 27,992.70 - -
19,430.24 100.00% - - 0.00% 2,428.78 19,430.24 100.00% - 0.00
1,342.51 100.00% - - 0.00% 299.00 1,342.51 100.00% - 0.00
7,219.95 100.00% - - 0.00% 1,895.00 7,219.95 100.00% - 0.00
- - - - - 4,021.82
- 0.00% - 0.00% - - 0.00% 4,622.78 4,021.82
- - - - - 2,323.14
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.43 1.31
- 0.00% - 0.00% - - 0.00% 2.43 1.70
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.46 38.72
- 0.00% - 0.00% - - 0.00% 2.43 2.58
- 0.00% - 0.00% - - 0.00% 1.46 15.49
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.51 520.81
- 0.00% - 0.00% - - 0.00% 28.35 616.90
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 28.35 25.52
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 12.72 197.80
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.00 218.58
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 22.95 247.86
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.00 435.87
- - - - - 2,986.07
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 8.64 4.67
- 0.00% - 0.00% - - 0.00% 8.64 6.05
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.92 130.48
- 0.00% - 0.00% - - 0.00% 4.60 4.88
- 0.00% - 0.00% - - 0.00% 4.68 49.65
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.20 5.79
- 0.00% - 0.00% - - 0.00% 0.52 146.43
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.28 763.98
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 12.84 279.40
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.00 291.44
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 8.16 68.14
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.00 1,235.16
- - - - - 3,003.42
- - - - 0.00% - 0.00
- 0.00% - 0.00% - - 0.00% 3.24 1.75
- 0.00% - 0.00% - - 0.00% 3.24 2.27
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.91 77.17
- 0.00% - 0.00% - - 0.00% 3.24 3.43
- 0.00% - 0.00% - - 0.00% 3.48 36.92
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.06 971.24
- 0.00% - 0.00% - - 0.00% 9.72 211.51
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.00 173.37
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 11.76 98.20
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.00 546.24
- 0.00% - 0.00% - - 0.00% 11.00 881.32
2,222.20 0.00 - 2,222.20 - 22,036.25

- - - - - 234.36
- 0.00% - 0.00% - - 0.00% 189.00 102.06
- 0.00% - 0.00% - - 0.00% 189.00 132.30
- - - - - 7,920.15
- 0.00% - 0.00% - - 0.00% 189.00 5,012.28
- 0.00% - 0.00% - - 0.00% 204.00 216.24
- 0.00% - 0.00% - - 0.00% 70.20 1,087.40
- 0.00% - 0.00% - - 0.00% 151.20 1,604.23
- - - - - 2,104.08
- 0.00% - 0.00% - - 0.00% 6.05 1,939.57
- 0.00% - 0.00% - - 0.00% 7.56 164.51
2,222.20 - - 2,222.20 - 11,777.66
2,222.20 15.87% - - 0.00% 10.00 2,222.20 15.87% 53.00 11,777.66
51,774.00 20,010.01 - 71,784.01 - 116,485.19
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


34,399.73 15,567.37 - 49,967.10 - 972.18

1,487.73 - - 1,487.73 - -
397.71 100.00% - 0.00% 736.50 397.71 100.00% - 0.00
1,090.02 100.00% - 0.00% 736.50 1,090.02 100.00% - 0.00
23,452.00 11,092.79 - 34,544.79 - -
10,608.00 67.89% 189.20 5,017.58 32.11% 589.20 15,625.58 100.00% - 0.00
1,060.00 67.89% 473.00 501.38 32.11% 1,473.00 1,561.38 100.00% - 0.00
4,700.00 67.89% 473.00 2,223.10 32.11% 1,473.00 6,923.10 100.00% - 0.00
2,710.00 67.89% 473.00 1,281.83 32.11% 1,473.00 3,991.83 100.00% - 0.00
4,374.00 67.89% 141.90 2,068.90 32.11% 441.90 6,442.90 100.00% - 0.00
9,460.00 4,474.58 - 13,934.58 - -
9,460.00 67.89% 473.00 4,474.58 32.11% 1,473.00 13,934.58 100.00% - 0.00
- - - - - 972.18
- 0.00% - 0.00% - - 0.00% 1,473.00 972.18
0.00 0.00 - 0.00 - 1,916.94

- - - - - 3.01
- 0.00% - 0.00% - - 0.00% 2.43 1.31
- 0.00% - 0.00% - - 0.00% 2.43 1.70
- - - - - 56.79
- 0.00% - 0.00% - - 0.00% 1.46 38.72
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 2.43 2.58
- 0.00% - 0.00% - - 0.00% 1.46 15.49
- - - - - 853.74
- 0.00% - 0.00% - - 0.00% 1.51 520.81
- 0.00% - 0.00% - - 0.00% 15.30 332.93
- - - - - 13.77
- 0.00% - 0.00% - - 0.00% 15.30 13.77
- - - - - 197.80
- 0.00% - 0.00% - - 0.00% 12.72 197.80
- - - - - 218.58
- 0.00% - 0.00% - - 0.00% 3.00 218.58
- - - - - 137.38
- 0.00% - 0.00% - - 0.00% 12.72 137.38
- - - - - 435.87
- 0.00% - 0.00% - - 0.00% 3.00 435.87
0.00 0.00 - 0.00 - 803.79

- - - - - 1.43
- 0.00% - 0.00% - - 0.00% 1.15 0.62
- 0.00% - 0.00% - - 0.00% 1.15 0.81
- - - - - 35.49
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 0.94 24.93
- 0.00% - 0.00% - - 0.00% 1.15 1.22
- 0.00% - 0.00% - - 0.00% 0.88 9.34
- - - - - 38.06
- 0.00% - 0.00% - - 0.00% 0.05 1.45
- 0.00% - 0.00% - - 0.00% 0.13 36.61
- - - - - 330.13
- 0.00% - 0.00% - - 0.00% 0.53 177.59
- 0.00% - 0.00% - - 0.00% 7.01 152.54
- - - - - 72.86
- 0.00% - 0.00% - - 0.00% 1.00 72.86
- - - - - 17.03
- 0.00% - 0.00% - - 0.00% 2.04 17.03
- - - - - 308.79
- 0.00% - 0.00% - - 0.00% 1.00 308.79
15,584.00 0.00 - 15,584.00 - 20,676.71

57.74 - - 57.74 - -
25.35 100.00% - - 0.00% 46.94 25.35 100.00% - 0.00
32.39 100.00% - - 0.00% 46.94 32.39 100.00% - 0.00
1,221.61 - - - 1,221.61 - -
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


648.80 100.00% - - 0.00% 41.75 648.80 100.00% - 0.00
22.36 100.00% - - 0.00% 21.50 22.36 100.00% - 0.00
550.45 100.00% - - 0.00% 51.88 550.45 100.00% - 0.00
1,044.40 - - - 1,044.40 - -
1,044.40 100.00% - - 0.00% 4.66 1,044.40 100.00% - 0.00
11,002.13 - - - 11,002.13 - -
5,784.75 100.00% - - 0.00% 15.69 5,784.75 100.00% - 0.00
3,183.26 100.00% - - 0.00% 785.99 3,183.26 100.00% - 0.00
2,034.12 100.00% - - 0.00% 93.48 2,034.12 100.00% - 0.00
349.62 - - - 349.62 - -
349.62 100.00% - - 0.00% 93.48 349.62 100.00% - 0.00
1,345.47 - - 1,345.47 - -
730.26 100.00% - - 0.00% 38.72 730.26 100.00% - 0.00
615.21 100.00% - - 0.00% 32.62 615.21 100.00% - 0.00
237.77 - - 237.77 - 629.64
72.86 100.00% - - 0.00% 1.00 72.86 100.00% - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 169.91
- 0.00% - 0.00% - - 0.00% 1.00 294.82
164.91 50.00% - - 0.00% 1.00 164.91 50.00% 1.00 164.91
- - - - - 1,583.58
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 38.72 674.50
- 0.00% - 0.00% - - 0.00% 33.62 909.08
- - - - - 964.35
- 0.00% - 0.00% - - 0.00% 1.00 208.62
- 0.00% - 0.00% - - 0.00% 1.00 366.59
- 0.00% - 0.00% - - 0.00% 1.00 389.14
325.26 - - 325.26 - 307.16
- - - - - 0.00
0.19 100.00% - - 0.00% 0.36 0.19 100.00% - 0.00
0.25 100.00% - - 0.00% 0.36 0.25 100.00% - 0.00
- - - - - 0.00
5.83 100.00% - - 0.00% 0.22 5.83 100.00% - 0.00
0.38 100.00% - - 0.00% 0.36 0.38 100.00% - 0.00
3.82 100.00% - - 0.00% 0.36 3.82 100.00% - 0.00
- - - - - 0.00
176.97 100.00% - - 0.00% 0.48 176.97 100.00% - 0.00
76.26 100.00% - - 0.00% 18.83 76.26 100.00% - 0.00
21.76 100.00% - - 0.00% 1.00 21.76 100.00% - 0.00
- - - - - 0.00
7.48 100.00% - - 0.00% 2.00 7.48 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
32.32 100.00% - - 0.00% 2.00 32.32 100.00% - 0.00
- - - - 0.00% - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 307.16
- - - - - 17,191.98
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 220.00 118.80
- 0.00% - 0.00% - - 0.00% 220.00 154.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 18.00 477.36
- 0.00% - 0.00% - - 0.00% 4.50 71.69
- 0.00% - 0.00% - - 0.00% 45.00 47.70
- 0.00% - 0.00% - - 0.00% 16.88 179.10
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 18.03 4,711.06
- - - - 0.00% - 0.00
- 0.00% - 0.00% - - 0.00% 220.00 2,761.00
- 0.00% - 0.00% - - 0.00% 1.00 287.95
- 0.00% - 0.00% - - 0.00% 396.00 8,383.32
1,790.27 4,442.64 - 6,232.91 - 61,587.82
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


1,790.27 - - 1,790.27 - -
453.87 100.00% - 0.00% 840.50 453.87 100.00% - 0.00
1,336.40 100.00% - 0.00% 840.50 1,336.40 100.00% - 0.00
- 3,307.44 - 3,307.44 - 43,024.28
- 0.00% 60.00 1,591.20 7.14% 60.00 1,591.20 7.14% 780.50 20,698.86
- 0.00% 120.00 127.20 7.14% 120.00 127.20 7.14% 1,561.00 1,654.66
- 0.00% 120.00 564.00 7.14% 120.00 564.00 7.14% 1,561.00 7,336.70
- 0.00% 120.00 325.20 7.14% 120.00 325.20 7.14% 1,561.00 4,230.31
- 0.00% 48.00 699.84 7.14% 48.00 699.84 7.14% 624.40 9,103.75
- 1,135.20 - 1,135.20 - 9,257.35
- 0.00% - 0.00% - - 0.00% 356.00 1,356.36
- 0.00% - 0.00% - - 0.00% 275.00 1,234.75
- 0.00% - 0.00% - - 0.00% 744.00 5,178.24
- 0.00% - 0.00% - - 0.00% 186.00 1,488.00
- 0.00% 120.00 1,135.20 100.00% 120.00 1,135.20 100.00% - 0.00
- - - - - 1,462.47
- 0.00% - 0.00% - - 0.00% 1,681.00 1,462.47
- - - - - 2,323.14
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.43 1.31
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 2.43 1.70
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.46 38.72
- 0.00% - 0.00% - - 0.00% 2.43 2.58
- 0.00% - 0.00% - - 0.00% 1.46 15.49
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.51 520.81
- 0.00% - 0.00% - - 0.00% 28.35 616.90
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 28.35 25.52
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 12.72 197.80
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.00 218.58
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 22.95 247.86
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.00 435.87
- - - - - 2,986.07
- - - - 0.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 8.64 4.67
- 0.00% - 0.00% - - 0.00% 8.64 6.05
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.92 130.48
- 0.00% - 0.00% - - 0.00% 4.60 4.88
- 0.00% - 0.00% - - 0.00% 4.68 49.65
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.20 5.79
- 0.00% - 0.00% - - 0.00% 0.52 146.43
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.28 763.98
- 0.00% - 0.00% - - 0.00% 12.84 279.40
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.00 291.44
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 8.16 68.14
- - - - 0.00% - 0.00
- 0.00% - 0.00% - - 0.00% 4.00 1,235.16
- - - - 0.00% - 2,534.51
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 4.32 2.33
- 0.00% - 0.00% - - 0.00% 4.32 3.02
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.88 102.90
- 0.00% - 0.00% - - 0.00% 4.32 4.58
- 0.00% - 0.00% - - 0.00% 4.64 49.23
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.08 1,294.99
- 0.00% - 0.00% - - 0.00% 12.96 282.01
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.00 231.16
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 15.68 130.93
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 273.12
- 0.00% - 0.00% - - 0.00% 2.00 160.24
0.00 0.00 - 0.00 - 30,527.75

- - - - - 392.83
- 0.00% - 0.00% - - 0.00% 316.80 171.07
- 0.00% - 0.00% - - 0.00% 316.80 221.76
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 8,013.90
- 0.00% - 0.00% - - 0.00% 168.96 4,480.82
- 0.00% - 0.00% - - 0.00% 211.20 223.87
- 0.00% - 0.00% - - 0.00% 95.20 1,516.54
- 0.00% - 0.00% - - 0.00% 168.96 1,792.67
- - - - - 2,938.78
- 0.00% - 0.00% - - 0.00% 8.45 2,708.99
- 0.00% - 0.00% - - 0.00% 10.56 229.79
- - - - - 19,182.24
- 0.00% - 0.00% - - 0.00% 88.00 19,182.24
133,289.69 76,553.64 - 209,843.33 - 19,570.70
38,217.60 74,373.84 - 112,591.44 - 2,028.00

3,135.60 - - 3,135.60 - -
826.80 100.00% - 0.00% 1,560.00 826.80 100.00% - 0.00
2,308.80 100.00% - 0.00% 1,560.00 2,308.80 100.00% - 0.00
23,232.00 49,251.84 - 72,483.84 - -
10,408.00 32.05% 848.00 22,064.96 67.95% 1,248.00 32,472.96 100.00% - 0.00
1,040.00 32.05% 2,120.00 2,204.80 67.95% 3,120.00 3,244.80 100.00% - 0.00
4,700.00 32.05% 2,120.00 9,964.00 67.95% 3,120.00 14,664.00 100.00% - 0.00
2,710.00 32.05% 2,120.00 5,745.20 67.95% 3,120.00 8,455.20 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


4,374.00 32.05% 636.00 9,272.88 67.95% 936.00 13,646.88 100.00% - 0.00
11,850.00 25,122.00 - 36,972.00 - -
11,850.00 32.05% 2,120.00 25,122.00 67.95% 3,120.00 36,972.00 100.00% - 0.00
- - - - 0.00% - 2,028.00
- 0.00% - 0.00% - - 0.00% 3,120.00 2,028.00
0.00 0.00 - 0.00 0.00% - 1,162.83

- - - - - 2.30
- 0.00% - 0.00% - - 0.00% 1.85 1.00
- 0.00% - 0.00% - - 0.00% 1.85 1.30
- - - - - 72.19
- 0.00% - 0.00% - - 0.00% 1.90 50.39
- 0.00% - 0.00% - - 0.00% 1.55 1.64
- 0.00% - 0.00% - - 0.00% 1.90 20.16
- - - - - 181.74
- 0.00% - 0.00% - - 0.00% 2.56 140.03
- 0.00% - 0.00% - - 0.00% 0.07 15.25
- 0.00% - 0.00% - - 0.00% 0.04 10.14
- 0.00% - 0.00% - - 0.00% 0.75 16.32
- - - - - 666.35
- 0.00% - 0.00% - - 0.00% 0.91 335.51
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 10.16 221.08
- 0.00% - 0.00% - - 0.00% 27.10 109.76
- - - - - 0.82
- 0.00% - 0.00% - - 0.00% 0.91 0.82
- - - - - 55.98
- 0.00% - 0.00% - - 0.00% 3.60 55.98
- - - - - 72.86
- 0.00% - 0.00% - - 0.00% 1.00 72.86
- - - - - 21.60
- 0.00% - 0.00% - - 0.00% 2.00 21.60
- - - - - 88.99
- 0.00% - 0.00% - - 0.00% 1.00 88.99
9,132.23 0.00 - 9,132.23 - 3,143.16

28.57 - - 28.57 - -
12.44 100.00% - - 0.00% 23.04 12.44 100.00% - 0.00
16.13 100.00% - - 0.00% 23.04 16.13 100.00% - 0.00
158.37 - - 158.37 - -
79.62 100.00% - - 0.00% 5.12 79.62 100.00% - 0.00
10.85 100.00% - - 0.00% 10.24 10.85 100.00% - 0.00
67.90 100.00% - - 0.00% 6.40 67.90 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


228.60 - - 228.60 - -
228.60 100.00% - - 0.00% 1.02 228.60 100.00% - 0.00
6,678.05 - - 6,678.05 - -
4,431.65 100.00% - - 0.00% 12.02 4,431.65 100.00% - 0.00
1,137.08 100.00% - - 0.00% 280.76 1,137.08 100.00% - 0.00
1,109.32 100.00% - - 0.00% 50.98 1,109.32 100.00% - 0.00
190.67 - - 190.67 - -
190.67 100.00% - - 0.00% 50.98 190.67 100.00% - 0.00
1,284.94 - - 1,284.94 - -
466.79 100.00% - - 0.00% 24.75 466.79 100.00% - 0.00
818.15 100.00% - - 0.00% 43.38 818.15 100.00% - 0.00
237.77 - - 237.77 - 629.64
72.86 100.00% - - 0.00% 1.00 72.86 100.00% - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 169.91
- 0.00% - 0.00% - - 0.00% 1.00 294.82
164.91 50.00% - - 0.00% 1.00 164.91 50.00% 1.00 164.91
- - - - - 1,242.01
- 0.00% - 0.00% - - 0.00% 33.92 590.89
- 0.00% - 0.00% - - 0.00% 24.08 651.12
- - - - - 964.35
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 1.00 208.62
- 0.00% - 0.00% - - 0.00% 1.00 366.59
- 0.00% - 0.00% - - 0.00% 1.00 389.14
325.26 - - 325.26 - 307.16
- - - - - 0.00
0.19 100.00% - - 0.00% 0.36 0.19 100.00% - 0.00
0.25 100.00% - - 0.00% 0.36 0.25 100.00% - 0.00
- - - - - 0.00
5.83 100.00% - - 0.00% 0.22 5.83 100.00% - 0.00
0.38 100.00% - - 0.00% 0.36 0.38 100.00% - 0.00
3.82 100.00% - - 0.00% 0.36 3.82 100.00% - 0.00
- - - - - 0.00
176.97 100.00% - - 0.00% 0.48 176.97 100.00% - 0.00
76.26 100.00% - - 0.00% 18.83 76.26 100.00% - 0.00
21.76 100.00% - - 0.00% 1.00 21.76 100.00% - 0.00
- - - - - 0.00
7.48 100.00% - - 0.00% 2.00 7.48 100.00% - 0.00
- - - - - 0.00
32.32 100.00% - - 0.00% 2.00 32.32 100.00% - 0.00
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 1.00 307.16
6,161.80 0.00 - 6,161.80 - 642.29

9.69 - - 9.69 - -
4.22 100.00% - - 0.00% 7.81 4.22 100.00% - 0.00
5.47 100.00% - - 0.00% 7.81 5.47 100.00% - 0.00
560.84 - - 560.84 - -
436.52 100.00% - - 0.00% 16.46 436.52 100.00% - 0.00
20.77 100.00% - - 0.00% 7.81 20.77 100.00% - 0.00
103.55 100.00% - - 0.00% 9.76 103.55 100.00% - 0.00
6.72 - - 6.72 - -
6.72 100.00% - - 0.00% 0.03 6.72 100.00% - 0.00
4,600.90 - - 4,600.90 - -
2,643.51 100.00% - - 0.00% 7.17 2,643.51 100.00% - 0.00
1,604.80 100.00% - - 0.00% 73.75 1,604.80 100.00% - 0.00
352.59 100.00% - - 0.00% 87.06 352.59 100.00% - 0.00
275.83 - - 275.83 - -
275.83 100.00% - - 0.00% 73.75 275.83 100.00% - 0.00
707.82 - - 707.82 - -
707.82 100.00% - - 0.00% 37.53 707.82 100.00% - 0.00
- - - - - 145.72
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 2.00 145.72
- - - - - 187.78
- 0.00% - 0.00% - - 0.00% 21.81 187.78
- - - - - 308.79
- 0.00% - 0.00% - - 0.00% 1.00 308.79
74,328.56 0.00 - 74,328.56 - 8,096.81

2,215.40 - - 2,215.40 - -
561.80 100.00% - 0.00% 1,060.00 561.80 100.00% - 0.00
1,653.60 100.00% - 0.00% 1,060.00 1,653.60 100.00% - 0.00
57,859.04 - - 57,859.04 - -
27,581.20 100.00% - - 0.00% 1,060.00 27,581.20 100.00% - 0.00
2,204.80 100.00% - - 0.00% 2,120.00 2,204.80 100.00% - 0.00
9,964.00 100.00% - - 0.00% 2,120.00 9,964.00 100.00% - 0.00
5,745.20 100.00% - - 0.00% 2,120.00 5,745.20 100.00% - 0.00
12,363.84 100.00% - - 0.00% 848.00 12,363.84 100.00% - 0.00
14,254.12 - - 14,254.12 - -
1,196.34 100.00% - - 0.00% 314.00 1,196.34 100.00% - 0.00
1,266.18 100.00% - - 0.00% 282.00 1,266.18 100.00% - 0.00
2,679.60 100.00% - - 0.00% 385.00 2,679.60 100.00% - 0.00
9,112.00 100.00% - - 0.00% 1,139.00 9,112.00 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 1,844.40
- 0.00% - 0.00% - - 0.00% 2,120.00 1,844.40
- - - - - 2,323.14
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.43 1.31
- 0.00% - 0.00% - - 0.00% 2.43 1.70
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.46 38.72
- 0.00% - 0.00% - - 0.00% 2.43 2.58
- 0.00% - 0.00% - - 0.00% 1.46 15.49
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.51 520.81
- 0.00% - 0.00% - - 0.00% 28.35 616.90
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 28.35 25.52
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 12.72 197.80
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.00 218.58
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 22.95 247.86
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.00 435.87
- - - - - 1,451.20
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.32 2.33
- 0.00% - 0.00% - - 0.00% 4.32 3.02
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.96 51.98
- 0.00% - 0.00% - - 0.00% 2.30 2.44
- 0.00% - 0.00% - - 0.00% 1.84 19.52
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.09 2.60
- 0.00% - 0.00% - - 0.00% 0.25 70.40
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.14 361.84
- 0.00% - 0.00% - - 0.00% 6.42 139.70
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 145.72
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 4.08 34.07
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 617.58
- - - - - 2,478.07
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.32 2.33
- 0.00% - 0.00% - - 0.00% 4.32 3.02
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.88 102.90
- 0.00% - 0.00% - - 0.00% 4.32 4.58
- 0.00% - 0.00% - - 0.00% 4.64 49.23
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.08 1,294.99
- 0.00% - 0.00% - - 0.00% 12.96 282.01
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.00 231.16
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 15.68 130.93
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 136.56
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 3.00 240.36
5,449.50 2,179.80 - 7,629.30 - 4,497.61

- - - - - 153.72
- 0.00% - 0.00% - - 0.00% 126.00 66.78
- 0.00% - 0.00% - - 0.00% 126.00 86.94
- - - - - 3,212.27
- 0.00% - 0.00% - - 0.00% 67.20 1,748.54
- 0.00% - 0.00% - - 0.00% 84.00 87.36
- 0.00% - 0.00% - - 0.00% 42.20 663.38
- 0.00% - 0.00% - - 0.00% 67.20 712.99
- - - - - 1,131.62
- 0.00% - 0.00% - - 0.00% 3.36 1,041.53
- 0.00% - 0.00% - - 0.00% 4.20 90.09
5,449.50 2,179.80 - 7,629.30 - -
5,449.50 71.43% 10.00 2,179.80 28.57% 35.00 7,629.30 100.00% - 0.00
321,597.95 33,319.80 - 354,917.75 - 49,254.35
99,669.12 0.00 - 99,669.12 - 1,821.60

2,787.60 - - 2,787.60 - -
745.20 100.00% - 0.00% 1,380.00 745.20 100.00% - 0.00
2,042.40 100.00% - 0.00% 1,380.00 2,042.40 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


64,175.52 - - 64,175.52 - -
28,726.08 100.00% - - 0.00% 1,104.00 28,726.08 100.00% - 0.00
2,925.60 100.00% - - 0.00% 2,760.00 2,925.60 100.00% - 0.00
12,972.00 100.00% - - 0.00% 2,760.00 12,972.00 100.00% - 0.00
7,479.60 100.00% - - 0.00% 2,760.00 7,479.60 100.00% - 0.00
12,072.24 100.00% - - 0.00% 828.00 12,072.24 100.00% - 0.00
32,706.00 - - 32,706.00 - -
32,706.00 100.00% - - 0.00% 2,760.00 32,706.00 100.00% - 0.00
- - - - - 1,821.60
- 0.00% - 0.00% - - 0.00% 2,760.00 1,821.60
0.00 0.00 - 0.00 - 5,730.79

- - - - - 7.03
- 0.00% - 0.00% - - 0.00% 5.67 3.06
- 0.00% - 0.00% - - 0.00% 5.67 3.97
- - - - - 132.25
- 0.00% - 0.00% - - 0.00% 3.40 90.17
- 0.00% - 0.00% - - 0.00% 5.67 6.01
- 0.00% - 0.00% - - 0.00% 3.40 36.07
- - - - - 2,656.95
- 0.00% - 0.00% - - 0.00% 3.53 1,217.53
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 66.15 1,439.42
- - - - - 59.54
- 0.00% - 0.00% - - 0.00% 66.15 59.54
- - - - - 1,028.63
- 0.00% - 0.00% - - 0.00% 66.15 1,028.63
- - - - - 510.02
- 0.00% - 0.00% - - 0.00% 7.00 510.02
- - - - - 578.34
- 0.00% - 0.00% - - 0.00% 53.55 578.34
- - - - - 758.03
- 0.00% - 0.00% - - 0.00% 7.00 758.03
0.00 0.00 - 0.00 - 6,102.71

- - - - - 8.49
- 0.00% - 0.00% - - 0.00% 6.90 3.73
- 0.00% - 0.00% - - 0.00% 6.90 4.76
- - - - - 209.09
- 0.00% - 0.00% - - 0.00% 5.61 145.97
- 0.00% - 0.00% - - 0.00% 6.90 7.31
- 0.00% - 0.00% - - 0.00% 5.26 55.81
- - - - - 219.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 0.27 7.81
- 0.00% - 0.00% - - 0.00% 0.75 211.19
- - - - - 1,970.73
- 0.00% - 0.00% - - 0.00% 3.15 1,055.50
- 0.00% - 0.00% - - 0.00% 42.06 915.23
- - - - - 437.16
- 0.00% - 0.00% - - 0.00% 6.00 437.16
- - - - - 170.34
- 0.00% - 0.00% - - 0.00% 20.40 170.34
- - - - - 3,087.90
- 0.00% - 0.00% - - 0.00% 10.00 3,087.90
6,161.80 0.00 - 6,161.80 - 642.29

9.69 - - 9.69 - -
4.22 100.00% - - 0.00% 7.81 4.22 100.00% - 0.00
5.47 100.00% - - 0.00% 7.81 5.47 100.00% - 0.00
560.84 - - 560.84 - -
436.52 100.00% - - 0.00% 16.46 436.52 100.00% - 0.00
20.77 100.00% - - 0.00% 7.81 20.77 100.00% - 0.00
103.55 100.00% - - 0.00% 9.76 103.55 100.00% - 0.00
6.72 - - 6.72 - -
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


6.72 100.00% - - 0.00% 0.03 6.72 100.00% - 0.00
4,600.90 - - 4,600.90 - -
2,643.51 100.00% - - 0.00% 7.17 2,643.51 100.00% - 0.00
1,604.80 100.00% - - 0.00% 73.75 1,604.80 100.00% - 0.00
352.59 100.00% - - 0.00% 87.06 352.59 100.00% - 0.00
275.83 - - 275.83 - -
275.83 100.00% - - 0.00% 73.75 275.83 100.00% - 0.00
707.82 - - 707.82 - -
707.82 100.00% - - 0.00% 37.53 707.82 100.00% - 0.00
- - - - - 145.72
- 0.00% - 0.00% - - 0.00% 2.00 145.72
- - - - - 187.78
- 0.00% - 0.00% - - 0.00% 21.81 187.78
- - - - - 308.79
- 0.00% - 0.00% - - 0.00% 1.00 308.79
9,132.23 0.00 - 9,132.23 - 3,125.74

28.57 - - 28.57 - -
12.44 100.00% - - 0.00% 23.04 12.44 100.00% - 0.00
16.13 100.00% - - 0.00% 23.04 16.13 100.00% - 0.00
158.37 - - 158.37 - -
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


79.62 100.00% - - 0.00% 5.12 79.62 100.00% - 0.00
10.85 100.00% - - 0.00% 10.24 10.85 100.00% - 0.00
67.90 100.00% - - 0.00% 6.40 67.90 100.00% - 0.00
228.60 - - 228.60 - -
228.60 100.00% - - 0.00% 1.02 228.60 100.00% - 0.00
6,678.05 - - 6,678.05 - -
4,431.65 100.00% - - 0.00% 12.02 4,431.65 100.00% - 0.00
1,137.08 100.00% - - 0.00% 280.76 1,137.08 100.00% - 0.00
1,109.32 100.00% - - 0.00% 50.98 1,109.32 100.00% - 0.00
190.67 - - 190.67 - -
190.67 100.00% - - 0.00% 50.98 190.67 100.00% - 0.00
1,284.94 - - 1,284.94 - -
466.79 100.00% - - 0.00% 24.75 466.79 100.00% - 0.00
818.15 100.00% - - 0.00% 43.38 818.15 100.00% - 0.00
237.77 - - 237.77 - 629.64
72.86 100.00% - - 0.00% 1.00 72.86 100.00% - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 169.91
- 0.00% - 0.00% - - 0.00% 1.00 294.82
164.91 50.00% - - 0.00% 1.00 164.91 50.00% 1.00 164.91
- - - - - 1,224.59
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 32.92 573.47
- 0.00% - 0.00% - - 0.00% 24.08 651.12
- - - - - 964.35
- 0.00% - 0.00% - - 0.00% 1.00 208.62
- 0.00% - 0.00% - - 0.00% 1.00 366.59
- 0.00% - 0.00% - - 0.00% 1.00 389.14
325.26 - - 325.26 - 307.16
- - - - - 0.00
0.19 100.00% - - 0.00% 0.36 0.19 100.00% - 0.00
0.25 100.00% - - 0.00% 0.36 0.25 100.00% - 0.00
- - - - - 0.00
5.83 100.00% - - 0.00% 0.22 5.83 100.00% - 0.00
0.38 100.00% - - 0.00% 0.36 0.38 100.00% - 0.00
3.82 100.00% - - 0.00% 0.36 3.82 100.00% - 0.00
- - - - - 0.00
176.97 100.00% - - 0.00% 0.48 176.97 100.00% - 0.00
76.26 100.00% - - 0.00% 18.83 76.26 100.00% - 0.00
21.76 100.00% - - 0.00% 1.00 21.76 100.00% - 0.00
- - - - - 0.00
7.48 100.00% - - 0.00% 2.00 7.48 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
32.32 100.00% - - 0.00% 2.00 32.32 100.00% - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 307.16
196,171.76 33,319.80 - 229,491.56 - 25,631.09

7,484.82 - - 7,484.82 - -
1,897.56 100.00% - 0.00% 3,514.00 1,897.56 100.00% - 0.00
5,587.26 100.00% - 0.00% 3,514.00 5,587.26 100.00% - 0.00
155,118.94 24,805.80 - 179,924.74 - 13,781.00
74,627.28 80.08% 450.00 11,934.00 12.81% 3,264.00 86,561.28 92.89% 250.00 6,630.00
5,965.68 80.08% 900.00 954.00 12.81% 6,528.00 6,919.68 92.89% 500.00 530.00
26,451.60 80.08% 900.00 4,230.00 12.81% 6,528.00 30,681.60 92.89% 500.00 2,350.00
15,251.88 80.08% 900.00 2,439.00 12.81% 6,528.00 17,690.88 92.89% 500.00 1,355.00
32,822.50 80.08% 360.00 5,248.80 12.81% 2,611.20 38,071.30 92.89% 200.00 2,916.00
32,481.78 8,514.00 - 40,995.78 - 1,905.00
2,007.87 51.31% - - 0.00% 527.00 2,007.87 51.31% 500.00 1,905.00
12,064.63 100.00% - - 0.00% 2,687.00 12,064.63 100.00% - 0.00
6,041.28 100.00% - - 0.00% 868.00 6,041.28 100.00% - 0.00
12,368.00 100.00% - - 0.00% 1,546.00 12,368.00 100.00% - 0.00
- 0.00% 900.00 8,514.00 100.00% 900.00 8,514.00 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 6,114.36
- 0.00% - 0.00% - - 0.00% 7,028.00 6,114.36
- - - - - 1,593.08
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.62 0.87
- 0.00% - 0.00% - - 0.00% 1.62 1.13
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.97 25.72
- 0.00% - 0.00% - - 0.00% 1.62 1.72
- 0.00% - 0.00% - - 0.00% 0.97 10.29
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.01 348.36
- 0.00% - 0.00% - - 0.00% 18.90 411.26
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 18.90 17.01
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 8.48 131.86
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 145.72
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 15.30 165.24
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 333.90
- - - - - 1,451.20
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.32 2.33
- 0.00% - 0.00% - - 0.00% 4.32 3.02
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.96 51.98
- 0.00% - 0.00% - - 0.00% 2.30 2.44
- 0.00% - 0.00% - - 0.00% 1.84 19.52
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.09 2.60
- 0.00% - 0.00% - - 0.00% 0.25 70.40
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.14 361.84
- 0.00% - 0.00% - - 0.00% 6.42 139.70
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 145.72
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 4.08 34.07
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 617.58
1,086.22 - - 1,086.22 - 786.45
- - - - - 0.00
1.17 66.67% - - 0.00% 2.16 1.17 66.67% 1.08 0.58
1.51 66.67% - - 0.00% 2.16 1.51 66.67% 1.08 0.76
- - - - - 0.00
51.45 66.67% - - 0.00% 1.94 51.45 66.67% 0.97 25.72
2.29 66.67% - - 0.00% 2.16 2.29 66.67% 1.08 1.14
24.62 66.67% - - 0.00% 2.32 24.62 66.67% 1.16 12.31
- - - - - 0.00
647.50 66.67% - - 0.00% 2.04 647.50 66.67% 1.02 323.75
141.00 66.67% - - 0.00% 6.48 141.00 66.67% 3.24 70.50
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.00 173.37
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 11.76 98.20
- - - - - 0.00
136.56 100.00% - - 0.00% 1.00 136.56 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


80.12 50.00% - - 0.00% 1.00 80.12 50.00% 1.00 80.12
10,463.04 0.00 - 10,463.04 - 6,200.13

- - - - - 214.27
- 0.00% - 0.00% - - 0.00% 172.80 93.31
- 0.00% - 0.00% - - 0.00% 172.80 120.96
- - - - - 4,423.35
- 0.00% - 0.00% - - 0.00% 92.16 2,444.08
- 0.00% - 0.00% - - 0.00% 115.20 122.11
- 0.00% - 0.00% - - 0.00% 55.20 879.34
- 0.00% - 0.00% - - 0.00% 92.16 977.82
- - - - - 1,562.51
- 0.00% - 0.00% - - 0.00% 4.61 1,437.17
- 0.00% - 0.00% - - 0.00% 5.76 125.34
10,463.04 - - 10,463.04 - -
10,463.04 100.00% - - 0.00% 48.00 10,463.04 100.00% - 0.00
45,486.74 15,047.52 - 60,534.26 - 89,236.30
1,665.49 15,047.52 - 16,713.01 - 35,989.78

1,665.49 - - 1,665.49 - -
445.23 100.00% - 0.00% 824.50 445.23 100.00% - 0.00
1,220.26 100.00% - 0.00% 824.50 1,220.26 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 10,695.92 - 10,695.92 - 27,646.63
- 0.00% 184.00 4,787.68 27.90% 184.00 4,787.68 27.90% 475.60 12,375.11
- 0.00% 460.00 487.60 27.90% 460.00 487.60 27.90% 1,189.00 1,260.34
- 0.00% 460.00 2,162.00 27.90% 460.00 2,162.00 27.90% 1,189.00 5,588.30
- 0.00% 460.00 1,246.60 27.90% 460.00 1,246.60 27.90% 1,189.00 3,222.19
- 0.00% 138.00 2,012.04 27.90% 138.00 2,012.04 27.90% 356.70 5,200.69
- 4,351.60 - 4,351.60 - 7,254.81
- 0.00% 460.00 4,351.60 100.00% 460.00 4,351.60 100.00% - 0.00
- 0.00% - 0.00% - - 0.00% 180.00 1,440.00
- 0.00% - 0.00% - - 0.00% 520.00 3,619.20
- 0.00% - 0.00% - - 0.00% 489.00 2,195.61
- - - - - 1,088.34
- 0.00% - 0.00% - - 0.00% 1,649.00 1,088.34
0.00 0.00 - 0.00 - 1,593.08

- - - - - 2.00
- 0.00% - 0.00% - - 0.00% 1.62 0.87
- 0.00% - 0.00% - - 0.00% 1.62 1.13
- - - - - 37.73
- 0.00% - 0.00% - - 0.00% 0.97 25.72
- 0.00% - 0.00% - - 0.00% 1.62 1.72
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 0.97 10.29
- - - - - 759.62
- 0.00% - 0.00% - - 0.00% 1.01 348.36
- 0.00% - 0.00% - - 0.00% 18.90 411.26
- - - - - 17.01
- 0.00% - 0.00% - - 0.00% 18.90 17.01
- - - - - 131.86
- 0.00% - 0.00% - - 0.00% 8.48 131.86
- - - - - 145.72
- 0.00% - 0.00% - - 0.00% 2.00 145.72
- - - - - 165.24
- 0.00% - 0.00% - - 0.00% 15.30 165.24
- - - - - 333.90
- 0.00% - 0.00% - - 0.00% 2.00 333.90
- - - - - 0.00
0.00 0.00 - 0.00 - 1,219.23

- - - - - 2.30
- 0.00% - 0.00% - - 0.00% 1.85 1.00
- 0.00% - 0.00% - - 0.00% 1.85 1.30
- - - - - 77.18
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 1.90 50.39
- 0.00% - 0.00% - - 0.00% 1.55 1.64
- 0.00% - 0.00% - - 0.00% 2.37 25.15
- - - - - 182.65
- 0.00% - 0.00% - - 0.00% 2.56 140.03
- 0.00% - 0.00% - - 0.00% 0.07 15.69
- 0.00% - 0.00% - - 0.00% 0.04 10.61
- 0.00% - 0.00% - - 0.00% 0.75 16.32
- - - - - 635.66
- 0.00% - 0.00% - - 0.00% 0.87 305.37
- 0.00% - 0.00% - - 0.00% 10.16 221.08
- 0.00% - 0.00% - - 0.00% 27.10 109.21
- - - - - 0.78
- 0.00% - 0.00% - - 0.00% 0.87 0.78
- - - - - 97.03
- 0.00% - 0.00% - - 0.00% 6.24 97.03
- - - - - 72.86
- 0.00% - 0.00% - - 0.00% 1.00 72.86
- - - - - 61.78
- 0.00% - 0.00% - - 0.00% 5.72 61.78
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 88.99
- 0.00% - 0.00% - - 0.00% 1.00 88.99
43,821.25 0.00 - 43,821.25 - 46,872.05

2,704.53 - - 2,704.53 - -
695.45 100.00% - 0.00% 1,287.87 695.45 100.00% - 0.00
2,009.08 100.00% - 0.00% 1,287.87 2,009.08 100.00% - 0.00
35,978.96 - - 35,978.96 - 34,317.96
17,151.08 51.18% - - 0.00% 659.15 17,151.08 51.18% 628.72 16,359.29
1,371.02 51.18% - - 0.00% 1,318.29 1,371.02 51.18% 1,257.44 1,307.74
6,195.96 51.18% - - 0.00% 1,318.29 6,195.96 51.18% 1,257.44 5,909.97
3,572.57 51.18% - - 0.00% 1,318.29 3,572.57 51.18% 1,257.44 3,407.66
7,688.33 51.18% - - 0.00% 527.32 7,688.33 51.18% 502.97 7,333.30
5,137.76 - - 5,137.76 - 4,790.85
4,377.92 47.75% - - 0.00% 1,149.06 4,377.92 47.75% 1,257.44 4,790.85
759.84 100.00% - - 0.00% 169.23 759.84 100.00% - 0.00
- - - - - 2,240.89
- 0.00% - 0.00% - - 0.00% 2,575.73 2,240.89
- - - - - 1,593.08
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.62 0.87
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 1.62 1.13
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.97 25.72
- 0.00% - 0.00% - - 0.00% 1.62 1.72
- 0.00% - 0.00% - - 0.00% 0.97 10.29
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.01 348.36
- 0.00% - 0.00% - - 0.00% 18.90 411.26
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 18.90 17.01
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 8.48 131.86
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 145.72
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 15.30 165.24
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 333.90
- - - - - 1,451.20
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 4.32 2.33
- 0.00% - 0.00% - - 0.00% 4.32 3.02
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.96 51.98
- 0.00% - 0.00% - - 0.00% 2.30 2.44
- 0.00% - 0.00% - - 0.00% 1.84 19.52
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.09 2.60
- 0.00% - 0.00% - - 0.00% 0.25 70.40
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.14 361.84
- 0.00% - 0.00% - - 0.00% 6.42 139.70
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 145.72
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.08 34.07
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.00 617.58
- - - - - 2,478.07
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 4.32 2.33
- 0.00% - 0.00% - - 0.00% 4.32 3.02
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.88 102.90
- 0.00% - 0.00% - - 0.00% 4.32 4.58
- 0.00% - 0.00% - - 0.00% 4.64 49.23
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.08 1,294.99
- 0.00% - 0.00% - - 0.00% 12.96 282.01
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.00 231.16
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 15.68 130.93
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 136.56
- 0.00% - 0.00% - - 0.00% 3.00 240.36
0.00 0.00 - 0.00 - 3,562.16

- - - - - 44.64
- 0.00% - 0.00% - - 0.00% 36.00 19.44
- 0.00% - 0.00% - - 0.00% 36.00 25.20
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 1,012.33
- 0.00% - 0.00% - - 0.00% 19.20 509.18
- 0.00% - 0.00% - - 0.00% 24.00 25.44
- 0.00% - 0.00% - - 0.00% 17.20 274.00
- 0.00% - 0.00% - - 0.00% 19.20 203.71
- - - - - 325.39
- 0.00% - 0.00% - - 0.00% 0.96 299.28
- 0.00% - 0.00% - - 0.00% 1.20 26.11
- - - - - 2,179.80
- 0.00% - 0.00% - - 0.00% 10.00 2,179.80
246,745.55 3,060.01 - 249,805.56 - 88,543.23
79,571.03 0.00 - 79,571.03 - 7,174.56

15,000.00 100.00% - 0.00% 1.00 15,000.00 100.00% - 0.00


64,571.03 90.00% - - 0.00% 0.90 64,571.03 90.00% 0.10 7,174.56
54,944.56 1,486.85 - 56,431.41 0.00% - 0.00

1,044.79 - - 1,044.79 0.00% - -


765.49 100.00% - 0.00% 517.22 765.49 100.00% - 0.00
279.30 100.00% - 0.00% 517.22 279.30 100.00% - 0.00
27,325.99 431.00 - 27,756.99 - -
13,620.94 99.30% 3.61 95.74 0.70% 517.22 13,716.68 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


1,054.59 96.18% 39.53 41.90 3.82% 1,034.43 1,096.49 100.00% - 0.00
4,676.03 96.18% 39.53 185.79 3.82% 1,034.43 4,861.82 100.00% - 0.00
2,696.18 96.18% 39.53 107.13 3.82% 1,034.43 2,803.31 100.00% - 0.00
5,278.25 99.99% 0.03 0.44 0.01% 362.05 5,278.69 100.00% - 0.00
25,917.15 1,029.76 - 26,946.91 - -
25,917.15 96.18% 39.53 1,029.76 3.82% 1,034.43 26,946.91 100.00% - 0.00
656.63 26.09 - 682.72 - -
656.63 96.18% 39.53 26.09 3.82% 1,034.43 682.72 100.00% - 0.00
26,619.88 0.00 - 26,619.88 - 0.00

2,531.53 - - 2,531.53 - -
311.70 100.00% - 0.00% 210.61 311.70 100.00% - 0.00
113.73 100.00% - 0.00% 210.61 113.73 100.00% - 0.00
2,106.10 100.00% - 0.00% 210.61 2,106.10 100.00% - 0.00
12,837.83 - - 12,837.83 - -
5,585.38 100.00% - - 0.00% 210.61 5,585.38 100.00% - 0.00
446.48 100.00% - - 0.00% 421.21 446.48 100.00% - 0.00
1,979.69 100.00% - - 0.00% 421.21 1,979.69 100.00% - 0.00
1,141.48 100.00% - - 0.00% 421.21 1,141.48 100.00% - 0.00
3,684.80 100.00% - - 0.00% 252.73 3,684.80 100.00% - 0.00
10,972.52 - - 10,972.52 - -
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


10,972.52 100.00% - - 0.00% 421.21 10,972.52 100.00% - 0.00
278.00 - - 278.00 - -
278.00 100.00% - - 0.00% 421.21 278.00 100.00% - 0.00
85,610.08 0.00 - 85,610.08 - 27,734.38

41,514.40 - - 41,514.40 - 18.53


- - - - - 0.00
15.20 100.00% - 0.00% 28.15 15.20 100.00% - 0.00
19.71 100.00% - 0.00% 28.15 19.71 100.00% - 0.00
- - - - - 0.00
1,144.60 100.00% - 0.00% 32.37 1,144.60 100.00% - 0.00
29.84 100.00% - 0.00% 28.15 29.84 100.00% - 0.00
2,146.26 100.00% - 0.00% 80.93 2,146.26 100.00% - 0.00
429.28 100.00% - - 0.00% 40.46 429.28 100.00% - 0.00
- - - - - 0.00
737.97 100.00% - 0.00% 3.27 737.97 100.00% - 0.00
171.88 90.27% - - 0.00% 1.15 171.88 90.27% 0.12 18.53
6,626.29 100.00% - 0.00% 19.79 6,626.29 100.00% - 0.00
1,761.04 100.00% - 0.00% 80.93 1,761.04 100.00% - 0.00
- - - - - 0.00
10,378.63 100.00% - - 0.00% 28.15 10,378.63 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


11,768.90 100.00% - - 0.00% 540.85 11,768.90 100.00% - 0.00
140.74 100.00% - - 0.00% 34.75 140.74 100.00% - 0.00
3,752.00 100.00% - - 0.00% 14.00 3,752.00 100.00% - 0.00
- - - - - 0.00
2,392.06 100.00% - 0.00% 115.67 2,392.06 100.00% - 0.00
44,095.68

- - 44,095.68 - 2,994.86
- - - - - 0.00
15.21 93.34% - - 0.00% 28.15 15.21 93.34% 2.01 1.09
19.71 93.34% - - 0.00% 28.15 19.71 93.34% 2.01 1.41
- - - - - 0.00
2,282.13 95.11% - 0.00% 64.54 2,282.13 95.11% 3.32 117.40
29.84 93.34% - - 0.00% 28.15 29.84 93.34% 2.01 2.13
4,279.00 95.11% - - 0.00% 161.35 4,279.00 95.11% 8.30 220.12
839.99 93.34% - - 0.00% 79.17 839.99 93.34% 5.65 59.95
- - - - - 0.00
760.54 96.01% - 0.00% 3.37 760.54 96.01% 0.14 31.60
190.41 93.38% - - 0.00% 1.27 190.41 93.38% 0.09 13.49
11,163.24 93.34% - - 0.00% 33.34 11,163.24 93.34% 2.38 796.90
3,445.48 93.33% - - 0.00% 158.34 3,445.48 93.33% 11.31 246.11
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
10,378.63 93.34% - - 0.00% 28.15 10,378.63 93.34% 2.01 741.07
756.16 93.34% - - 0.00% 34.75 756.16 93.34% 2.48 53.96
2,190.44 93.33% - - 0.00% 540.85 2,190.44 93.33% 38.63 156.45
3,752.00 93.33% - - 0.00% 14.00 3,752.00 93.33% 1.00 268.00
- - - - - 0.00
3,992.90 93.33% - - 0.00% 193.08 3,992.90 93.33% 13.79 285.18
- - - - - 24,720.99
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 8.04 4.34
- 0.00% - 0.00% - - 0.00% 8.04 5.63
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 44.23 1,563.97
- 0.00% - 0.00% - - 0.00% 8.04 8.52
- 0.00% - 0.00% - - 0.00% 110.58 2,932.58
- 0.00% - 0.00% - - 0.00% 55.29 586.63
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.93 209.88
- 0.00% - 0.00% - - 0.00% 0.36 53.97
- 0.00% - 0.00% - - 0.00% 20.96 7,018.04
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 110.58 2,406.22
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 8.04 2,964.27
- 0.00% - 0.00% - - 0.00% 154.53 3,362.57
- 0.00% - 0.00% - - 0.00% 9.93 40.22
- 0.00% - 0.00% - - 0.00% 4.00 1,072.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 120.51 2,492.15
0.00 1,573.16 - 1,573.16 - 53,634.29

- 92.34 - 92.34 - 1,261.98


- 0.00% 16.20 68.69 6.82% 16.20 68.69 6.82% 221.40 938.74
- 0.00% 16.20 23.65 6.82% 16.20 23.65 6.82% 221.40 323.24
- 1,480.82 - 1,480.82 - 20,237.93
- 0.00% 16.20 429.62 6.82% 16.20 429.62 6.82% 221.40 5,871.53
- 0.00% 36.00 95.76 6.82% 36.00 95.76 6.82% 492.00 1,308.72
- 0.00% 36.00 573.48 6.82% 36.00 573.48 6.82% 492.00 7,837.56
- 0.00% 36.00 381.96 6.82% 36.00 381.96 6.82% 492.00 5,220.12
- - - - - 2,892.86
- 0.00% - 0.00% - - 0.00% 8.45 2,708.99
- 0.00% - 0.00% - - 0.00% 8.45 183.87
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 29,241.52
- 0.00% - 0.00% - - 0.00% 88.00 29,241.52
674,544.25 47,813.43 - 722,357.68 - 500,279.97
281,110.90 24,162.36 - 305,273.26 - 188,484.93

109,406.99 6,678.22 - 116,085.21 - 174,019.32


- - - - - 0.00
177.59 100.00% - - 0.00% 328.86 177.59 100.00% - 0.00
230.21 100.00% - - 0.00% 328.86 230.21 100.00% - 0.00
- - - - - 0.00
- - - - - 0.00
2,158.66 100.00% - - 0.00% 81.40 2,158.66 100.00% 0.00 0.07
1,077.87 100.00% - - 0.00% 101.59 1,077.87 100.00% - 0.00
- - - - - 0.00
15,618.97 100.00% - - 0.00% 71.69 15,618.97 100.00% -0.00 -0.59
5,714.22 100.00% - - 0.00% 198.07 5,714.22 100.00% 0.00 0.11
3,632.95 99.99% - - 0.00% 12.38 3,632.95 99.99% 0.00 0.47
828.36 93.65% - - 0.00% 35.40 828.36 93.65% 2.40 56.16
- 0.00% - 0.00% - - 0.00% 94.50 1,962.77
- - - - - 0.00
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 113.95 3,021.95
- 0.00% - 0.00% - - 0.00% 142.44 1,511.29
- 0.00% - 0.00% - - 0.00% 137.34 120.86
- - - - 0.00% - 0.00
- 0.00% - 0.00% - - 0.00% 207.14 4,847.08
- 0.00% - 0.00% - - 0.00% 974.50 3,946.73
- 0.00% - 0.00% - - 0.00% 33.79 11,793.72
- - - - - 0.00
- - - - - 0.00
1,960.98 93.65% - - 0.00% 92.63 1,960.98 93.65% 6.28 132.95
2,611.72 100.00% - 0.00% 644.87 2,611.72 100.00% - 0.00
5,123.19 93.67% - - 0.00% 14.68 5,123.19 93.67% 0.99 346.11
- - - - - 0.00
32,858.44 96.83% - - 0.00% 666.36 32,858.44 96.83% 21.85 1,077.20
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 295.63 5,315.43
- 0.00% - 0.00% - - 0.00% 120.02 3,356.96
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 97.97 2,291.52
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 22.47 276.38
- 0.00% - 0.00% - - 0.00% 53.03 1,890.52
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 283.12 9,311.82
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 98.28 14,498.27
- 0.00% - 0.00% - - 0.00% 47.38 1,980.48
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 189.00 3,020.22
- 0.00% - 0.00% - - 0.00% 63.00 1,965.60
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.80 47.74
- 0.00% - 0.00% - - 0.00% 2.36 25.04
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.80 392.15
- 0.00% - 0.00% - - 0.00% 260.13 6,477.24
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 4.94 1,540.05
- 0.00% - 0.00% - - 0.00% 345.40 1,398.87
- 0.00% - 0.00% - - 0.00% 130.35 2,759.51
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 39.50 1,947.75
- - - - 0.00% - 0.00
- 0.00% - 0.00% - - 0.00% 116.20 2,089.28
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 63.00 14,249.97
- 0.00% - 0.00% - - 0.00% 63.00 10,715.67
- 0.00% - 0.00% - - 0.00% 63.00 2,722.86
6,514.80 96.83% - - 0.00% 366.00 6,514.80 96.83% 12.00 213.60
6,514.80 96.83% - - 0.00% 366.00 6,514.80 96.83% 12.00 213.60
634.40 96.83% - - 0.00% 61.00 634.40 96.83% 2.00 20.80
4,343.20 96.83% - - 0.00% 244.00 4,343.20 96.83% 8.00 142.40
6,686.21 96.83% - - 0.00% 61.00 6,686.21 96.83% 2.00 219.22
- 0.00% - 0.00% - - 0.00% 126.00 13,427.82
- 0.00% - 0.00% - - 0.00% 189.00 7,714.98
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 252.00 22,286.88
5,619.22 63.49% 140.28 2,950.09 33.33% 407.48 8,569.31 96.83% 13.36 280.96
1,111.20 63.49% 63.00 583.38 33.33% 183.00 1,694.58 96.83% 6.00 55.56
1,481.60 63.49% 84.00 777.84 33.33% 244.00 2,259.44 96.83% 8.00 74.08
603.20 63.49% 42.00 316.68 33.33% 122.00 919.88 96.83% 4.00 30.16
837.60 63.49% 42.00 439.74 33.33% 122.00 1,277.34 96.83% 4.00 41.88
703.20 63.49% 42.00 369.18 33.33% 122.00 1,072.38 96.83% 4.00 35.16
- 0.00% - - 0.00% - - 0.00% 63.00 3,944.43
2,364.40 63.49% 21.00 1,241.31 33.33% 61.00 3,605.71 96.83% 2.00 118.22
- 0.00% - 0.00% - - 0.00% 126.00 8,109.36
171,703.91 17,484.14 - 189,188.05 - 14,465.61
- - - - - 0.00
796.49 96.83% - - 0.00% 1,474.98 796.49 96.83% 48.36 26.11
1,032.49 96.83% - - 0.00% 1,474.98 1,032.49 96.83% 48.36 33.85
- - - - - 0.00
- - - - - 0.00
- - - - - 0.00
922.10 96.83% - - 0.00% 34.77 922.10 96.83% 1.14 30.23
32.21 96.83% - - 0.00% 36.60 32.21 96.83% 1.20 1.06
461.22 96.84% - - 0.00% 43.47 461.22 96.84% 1.42 15.07
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
3,254.47 96.83% - - 0.00% 139.08 3,254.47 96.83% 4.56 106.70
342.43 96.83% - - 0.00% 84.55 342.43 96.83% 2.77 11.22
6,345.37 96.86% - - 0.00% 18.18 6,345.37 96.86% 0.59 205.93
- - - - - 0.00
146.03 96.83% - - 0.00% 162.26 146.03 96.83% 5.32 4.79
- - - - - 0.00
3,355.54 96.83% - - 0.00% 162.26 3,355.54 96.83% 5.32 110.02
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 57.96 1,084.43
- - - - - 0.00
1,268.80 96.83% - - 0.00% 122.00 1,268.80 96.83% 4.00 41.60
- - - - - 0.00
2,288.15 96.82% - - 0.00% 86.28 2,288.15 96.82% 2.83 75.05
2,169.44 96.81% - - 0.00% 43.13 2,169.44 96.81% 1.42 71.43
1,585.37 96.83% - - 0.00% 269.62 1,585.37 96.83% 8.84 51.98
- - - - - 0.00
- - - - - 0.00
- - - - - 0.00
169.99 96.83% - - 0.00% 6.41 169.99 96.83% 0.21 5.57
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


11.27 96.83% - - 0.00% 12.81 11.27 96.83% 0.42 0.37
84.99 96.86% - - 0.00% 8.01 84.99 96.86% 0.26 2.76
- - - - - 0.00
950.91 97.01% - - 0.00% 3.24 950.91 97.01% 0.10 29.35
1,070.55 96.83% - - 0.00% 45.75 1,070.55 96.83% 1.50 35.10
- - - - - 0.00
435.47 96.83% - - 0.00% 18.61 435.47 96.83% 0.61 14.27
173.79 96.82% - - 0.00% 42.91 173.79 96.82% 1.41 5.71
223.38 96.97% - - 0.00% 0.64 223.38 96.97% 0.02 6.98
- - - - - 0.00
37.06 96.83% - - 0.00% 41.18 37.06 96.83% 1.35 1.22
- - - - - 0.00
851.60 96.83% - - 0.00% 41.18 851.60 96.83% 1.35 27.92
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 19.22 359.61
- - - - - 0.00
- - - - - 0.00
5,911.04 96.82% - - 0.00% 222.89 5,911.04 96.82% 7.31 193.86
462.26 96.83% - - 0.00% 36.60 462.26 96.83% 1.20 15.16
2,956.05 96.82% - - 0.00% 278.61 2,956.05 96.82% 9.14 96.98
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
2,988.57 96.83% - - 0.00% 128.10 2,988.57 96.83% 4.20 97.99
- - - - - 0.00
95,003.37 100.00% - - 0.00% 63.00 95,003.37 100.00% - 0.00
- - - - - 0.00
- - - - - 0.00
727.97 96.83% - - 0.00% 27.45 727.97 96.83% 0.90 23.87
30.20 96.84% - - 0.00% 34.32 30.20 96.84% 1.12 0.99
364.14 96.84% - - 0.00% 34.32 364.14 96.84% 1.12 11.88
- - - - - 0.00
3,762.54 96.83% - - 0.00% 12.82 3,762.54 96.83% 0.42 123.27
2,597.87 96.83% - - 0.00% 111.02 2,597.87 96.83% 3.64 85.18
- - - - 0.00% - 0.00
531.88 96.85% - - 0.00% 22.73 531.88 96.85% 0.74 17.32
228.78 96.83% - - 0.00% 56.49 228.78 96.83% 1.85 7.49
600.33 97.18% - - 0.00% 1.72 600.33 97.18% 0.05 17.45
- - - - - 0.00
99.92 96.83% - - 0.00% 111.02 99.92 96.83% 3.64 3.28
- - - - - 0.00
2,295.89 96.83% - - 0.00% 111.02 2,295.89 96.83% 3.64 75.28
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
2,165.50 96.83% - - 0.00% 122.00 2,165.50 96.83% 4.00 71.00
2,205.76 96.83% - - 0.00% 122.00 2,205.76 96.83% 4.00 72.32
5,403.38 96.83% - - 0.00% 61.00 5,403.38 96.83% 2.00 177.16
- - - - - 0.00
2,940.54 96.83% - - 0.00% 110.88 2,940.54 96.83% 3.63 96.27
2,788.13 96.82% - - 0.00% 55.43 2,788.13 96.82% 1.82 91.55
4,760.64 96.83% - - 0.00% 346.48 4,760.64 96.83% 11.36 156.09
- - - - - 0.00
- - - - - 0.00
242.66 96.83% - - 0.00% 9.15 242.66 96.83% 0.30 7.96
16.10 96.83% - - 0.00% 18.30 16.10 96.83% 0.60 0.53
179.52 96.80% - - 0.00% 16.92 179.52 96.80% 0.56 5.94
- - - - - 0.00
1,074.17 96.83% - - 0.00% 3.66 1,074.17 96.83% 0.12 35.22
1,156.19 96.83% - - 0.00% 49.41 1,156.19 96.83% 1.62 37.91
- - - - - 0.00
585.23 96.83% - - 0.00% 25.01 585.23 96.83% 0.82 19.19
228.78 96.83% - - 0.00% 56.49 228.78 96.83% 1.85 7.49
321.11 96.84% - - 0.00% 0.92 321.11 96.84% 0.03 10.47
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
44.47 96.83% - - 0.00% 49.41 44.47 96.83% 1.62 1.46
- - - - - 0.00
1,021.80 96.83% - - 0.00% 49.41 1,021.80 96.83% 1.62 33.50
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 24.57 459.70
- - - - - 0.00
- - - - - 0.00
- 0.00% 90.24 2,393.16 63.49% 90.24 2,393.16 63.49% 51.89 1,376.12
- 0.00% 112.80 99.26 63.49% 112.80 99.26 63.49% 64.86 57.08
- 0.00% 45.12 569.87 63.50% 45.12 569.87 63.50% 25.94 327.62
- 0.00% 78.96 837.77 63.49% 78.96 837.77 63.49% 45.40 481.69
- - - - - 0.00
- 0.00% 16.92 1,841.07 63.49% 16.92 1,841.07 63.49% 9.73 1,058.72
- 0.00% 16.92 1,841.07 63.49% 16.92 1,841.07 63.49% 9.73 1,058.72
- 0.00% 25.45 297.77 63.50% 25.45 297.77 63.50% 14.63 171.17
- - - - - 0.00
- 0.00% 112.80 1,924.37 63.49% 112.80 1,924.37 63.49% 64.86 1,106.51
- 0.00% 188.00 7,679.80 63.49% 188.00 7,679.80 63.49% 108.10 4,415.89
149,100.54 21,986.63 - 171,087.17 - 103,226.72
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


59,445.24 11,057.91 - 70,503.15 - 90,667.14
- - - - - 0.00
93.02 94.29% 10.44 5.64 5.71% 182.70 98.66 100.00% - 0.00
120.59 94.29% 10.44 7.31 5.71% 182.70 127.90 100.00% - 0.00
- - - - 0.00% - 0.00
- - - - 0.00% - 0.00
1,130.55 94.27% 2.59 68.69 5.73% 45.22 1,199.24 100.00% - 0.00
564.56 94.28% 3.23 34.27 5.72% 56.44 598.83 100.00% - 0.00
- - - - - 0.00
8,182.82 94.30% 2.27 494.54 5.70% 39.83 8,677.36 100.00% - 0.00
2,993.49 94.29% 6.28 181.18 5.71% 110.04 3,174.67 100.00% - 0.00
1,904.34 94.31% 0.39 114.46 5.67% 6.88 2,018.80 99.98% 0.00 0.42
308.88 62.86% - - 0.00% 13.20 308.88 62.86% 7.80 182.52
685.41 62.86% - - 0.00% 33.00 685.41 62.86% 19.50 405.02
- - - - - 0.00
- - - - - 0.00
- 0.00% 1.81 48.00 2.86% 1.81 48.00 2.86% 61.50 1,630.98
- 0.00% 2.26 23.98 2.86% 2.26 23.98 2.86% 76.88 815.70
- 0.00% 2.18 1.92 2.86% 2.18 1.92 2.86% 74.12 65.23
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% 3.29 76.99 2.86% 3.29 76.99 2.86% 111.79 2,615.89
- 0.00% 15.47 62.65 2.86% 15.47 62.65 2.86% 525.92 2,129.98
- 0.00% 0.54 188.48 2.88% 0.54 188.48 2.88% 18.23 6,362.82
- - - - - 0.00
- - - - - 0.00
1,096.81 94.29% - - 0.00% 51.81 1,096.81 94.29% 3.14 66.47
1,368.01 94.28% 20.48 82.94 5.72% 358.26 1,450.95 100.00% - 0.00
2,865.54 94.26% - - 0.00% 8.21 2,865.54 94.26% 0.50 174.52
- - - - - 0.00
17,776.26 94.29% - - 0.00% 360.50 17,776.26 94.29% 21.84 1,076.93
- - - - - 0.00
- 0.00% 148.26 2,665.71 90.27% 148.26 2,665.71 90.27% 15.98 287.32
- 0.00% 49.94 1,396.82 74.90% 49.94 1,396.82 74.90% 16.74 468.22
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 54.43 1,273.12
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 12.48 153.50
- 0.00% - 0.00% - - 0.00% 29.46 1,050.25
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 157.29 5,173.27
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 54.60 8,054.59
- 0.00% - 0.00% - - 0.00% 26.32 1,100.18
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 105.00 1,677.90
- 0.00% - 0.00% - - 0.00% 35.00 1,092.00
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 26.52
- 0.00% - 0.00% - - 0.00% 1.31 13.90
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.00 217.86
- 0.00% - 0.00% - - 0.00% 144.52 3,598.55
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 2.74 854.20
- 0.00% - 0.00% - - 0.00% 191.89 777.15
- 0.00% - 0.00% - - 0.00% 72.41 1,532.92
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 21.95 1,082.35
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 64.56 1,160.79
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 35.00 7,916.65
- 0.00% - 0.00% - - 0.00% 35.00 5,953.15
- 0.00% 30.00 1,296.60 85.71% 30.00 1,296.60 85.71% 5.00 216.10
3,524.40 94.29% 12.00 213.60 5.71% 210.00 3,738.00 100.00% - 0.00
3,524.40 94.29% 12.00 213.60 5.71% 210.00 3,738.00 100.00% - 0.00
343.20 94.29% 2.00 20.80 5.71% 35.00 364.00 100.00% - 0.00
2,349.60 94.29% 8.00 142.40 5.71% 140.00 2,492.00 100.00% - 0.00
3,617.13 94.29% 2.00 219.22 5.71% 35.00 3,836.35 100.00% - 0.00
- 0.00% - 0.00% - - 0.00% 70.00 7,459.90
- 0.00% - 0.00% - - 0.00% 105.00 4,286.10
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 140.00 12,381.60
3,090.57 62.86% 73.48 1,545.28 31.43% 220.44 4,635.85 94.29% 13.36 280.96
611.16 62.86% 33.00 305.58 31.43% 99.00 916.74 94.29% 6.00 55.56
814.88 62.86% 44.00 407.44 31.43% 132.00 1,222.32 94.29% 8.00 74.08
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


331.76 62.86% 22.00 165.88 31.43% 66.00 497.64 94.29% 4.00 30.16
460.68 62.86% 22.00 230.34 31.43% 66.00 691.02 94.29% 4.00 41.88
386.76 62.86% 22.00 193.38 31.43% 66.00 580.14 94.29% 4.00 35.16
- 0.00% - 0.00% - - 0.00% 35.00 2,191.35
1,300.42 62.86% 11.00 650.21 31.43% 33.00 1,950.63 94.29% 2.00 118.22
- 0.00% - 0.00% - - 0.00% 70.00 4,505.20
89,655.30 10,928.72 - 100,584.02 - 12,559.58
- - - - - 0.00
430.88 94.29% - - 0.00% 797.94 430.88 94.29% 48.36 26.11
558.55 94.29% - - 0.00% 797.94 558.55 94.29% 48.36 33.85
- - - - - 0.00
- - - - - 0.00
- - - - - 0.00
498.85 94.29% - - 0.00% 18.81 498.85 94.29% 1.14 30.23
17.43 94.29% - - 0.00% 19.80 17.43 94.29% 1.20 1.06
249.44 94.27% - - 0.00% 23.51 249.44 94.27% 1.43 15.17
- - - - - 0.00
1,760.61 94.29% - - 0.00% 75.24 1,760.61 94.29% 4.56 106.70
185.20 94.27% - - 0.00% 45.73 185.20 94.27% 2.78 11.26
3,430.97 94.25% - - 0.00% 9.83 3,430.97 94.25% 0.60 209.42
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
79.01 94.29% - - 0.00% 87.78 79.01 94.29% 5.32 4.79
- - - - - 0.00
1,815.29 94.29% - - 0.00% 87.78 1,815.29 94.29% 5.32 110.02
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 32.20 602.46
- - - - - 0.00
686.40 94.29% - - 0.00% 66.00 686.40 94.29% 4.00 41.60
- - - - - 0.00
1,237.69 94.28% - - 0.00% 46.67 1,237.69 94.28% 2.83 75.05
1,173.50 94.26% - - 0.00% 23.33 1,173.50 94.26% 1.42 71.43
857.66 94.29% - - 0.00% 145.86 857.66 94.29% 8.84 51.98
- - - - - 0.00
- - - - - 0.00
- - - - - 0.00
92.02 94.29% - - 0.00% 3.47 92.02 94.29% 0.21 5.57
6.10 94.29% - - 0.00% 6.93 6.10 94.29% 0.42 0.37
45.94 94.34% - - 0.00% 4.33 45.94 94.34% 0.26 2.76
- - - - - 0.00
516.54 94.62% - - 0.00% 1.76 516.54 94.62% 0.10 29.35
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


579.15 94.29% - - 0.00% 24.75 579.15 94.29% 1.50 35.10
- - - - - 0.00
235.63 94.29% - - 0.00% 10.07 235.63 94.29% 0.61 14.27
94.00 94.27% - - 0.00% 23.21 94.00 94.27% 1.41 5.71
122.16 94.59% - - 0.00% 0.35 122.16 94.59% 0.02 6.98
- - - - - 0.00
20.06 94.29% - - 0.00% 22.28 20.06 94.29% 1.35 1.22
- - - - - 0.00
460.75 94.29% - - 0.00% 22.28 460.75 94.29% 1.35 27.92
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 10.68 199.82
- - - - - 0.00
- - - - - 0.00
3,197.78 94.28% - - 0.00% 120.58 3,197.78 94.28% 7.31 193.86
250.07 94.29% - - 0.00% 19.80 250.07 94.29% 1.20 15.16
- 0.00% - 0.00% - - 0.00% 159.86 1,696.11
- - - - - 0.00
1,616.77 94.29% - - 0.00% 69.30 1,616.77 94.29% 4.20 97.99
- - - - - 0.00
49,763.67 94.29% - - 0.00% 33.00 49,763.67 94.29% 2.00 3,015.98
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
- - - - - 0.00
393.83 94.29% - - 0.00% 14.85 393.83 94.29% 0.90 23.87
16.33 94.26% - - 0.00% 18.56 16.33 94.26% 1.13 0.99
196.92 94.26% - - 0.00% 18.56 196.92 94.26% 1.13 11.99
- - - - - 0.00
2,033.89 94.29% - - 0.00% 6.93 2,033.89 94.29% 0.42 123.27
1,405.41 94.29% - - 0.00% 60.06 1,405.41 94.29% 3.64 85.18
- - - - - 0.00
287.59 94.25% - - 0.00% 12.29 287.59 94.25% 0.75 17.55
123.73 94.26% - - 0.00% 30.55 123.73 94.26% 1.86 7.53
321.11 93.88% - - 0.00% 0.92 321.11 93.88% 0.06 20.94
- - - - - 0.00
54.06 94.29% - - 0.00% 60.06 54.06 94.29% 3.64 3.28
- - - - - 0.00
1,242.05 94.29% - - 0.00% 60.06 1,242.05 94.29% 3.64 75.28
- - - - - 0.00
1,171.50 94.29% - - 0.00% 66.00 1,171.50 94.29% 4.00 71.00
1,193.28 94.29% - - 0.00% 66.00 1,193.28 94.29% 4.00 72.32
2,923.14 94.29% - - 0.00% 33.00 2,923.14 94.29% 2.00 177.16
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
1,590.94 94.29% - - 0.00% 59.99 1,590.94 94.29% 3.63 96.27
1,508.49 94.28% - - 0.00% 29.99 1,508.49 94.28% 1.82 91.55
2,575.43 94.29% - - 0.00% 187.44 2,575.43 94.29% 11.36 156.09
- - - - - 0.00
- - - - - 0.00
131.28 94.29% - - 0.00% 4.95 131.28 94.29% 0.30 7.96
8.72 94.29% - - 0.00% 9.90 8.72 94.29% 0.60 0.53
97.19 94.34% - - 0.00% 9.16 97.19 94.34% 0.55 5.84
- - - - - 0.00
581.11 94.29% - - 0.00% 1.98 581.11 94.29% 0.12 35.22
625.49 94.29% - - 0.00% 26.73 625.49 94.29% 1.62 37.91
- - - - - 0.00
316.61 94.29% - - 0.00% 13.53 316.61 94.29% 0.82 19.19
123.73 94.26% - - 0.00% 30.55 123.73 94.26% 1.86 7.53
174.51 94.34% - - 0.00% 0.50 174.51 94.34% 0.03 10.47
- - - - - 0.00
24.06 94.29% - - 0.00% 26.73 24.06 94.29% 1.62 1.46
- - - - - 0.00
552.78 94.29% - - 0.00% 26.73 552.78 94.29% 1.62 33.50
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 13.65 255.39
- - - - - 0.00
- - - - - 0.00
- 0.00% 56.40 1,495.73 71.43% 56.40 1,495.73 71.43% 22.56 598.29
- 0.00% 70.50 62.04 71.43% 70.50 62.04 71.43% 28.20 24.82
- 0.00% 28.20 356.17 71.43% 28.20 356.17 71.43% 11.28 142.47
- 0.00% 49.35 523.60 71.43% 49.35 523.60 71.43% 19.74 209.44
- - - - - 0.00
- 0.00% 10.58 1,151.21 71.44% 10.58 1,151.21 71.44% 4.23 460.27
- 0.00% 10.58 1,151.21 71.44% 10.58 1,151.21 71.44% 4.23 460.27
- 0.00% 15.91 186.15 71.44% 15.91 186.15 71.44% 6.36 74.41
- - - - - 0.00
- 0.00% 70.50 1,202.73 71.43% 70.50 1,202.73 71.43% 28.20 481.09
- 0.00% 117.50 4,799.88 71.43% 117.50 4,799.88 71.43% 47.00 1,919.95
217,880.89 0.00 - 217,880.89 - 158,307.74

87,917.06 - - 87,917.06 - 133,111.01


- - - - - 0.00
132.48 97.92% - - 0.00% 245.34 132.48 97.92% 5.22 2.82
171.74 97.92% - - 0.00% 245.34 171.74 97.92% 5.22 3.65
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
- - - - - 0.00
1,610.35 97.91% - - 0.00% 60.72 1,610.35 97.91% 1.30 34.42
804.17 97.92% - - 0.00% 75.79 804.17 97.92% 1.61 17.06
- - - - - 0.00
11,652.87 97.93% - - 0.00% 53.49 11,652.87 97.93% 1.13 246.64
4,263.14 97.92% - - 0.00% 147.77 4,263.14 97.92% 3.14 90.62
2,709.34 97.89% - - 0.00% 9.23 2,709.34 97.89% 0.20 58.27
561.60 83.33% - - 0.00% 24.00 561.60 83.33% 4.80 112.32
- 0.00% - 0.00% - - 0.00% 72.00 1,495.44
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 86.82 2,302.47
- 0.00% - 0.00% - - 0.00% 108.53 1,151.50
- 0.00% - 0.00% - - 0.00% 104.64 92.08
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 157.82 3,692.99
- 0.00% - 0.00% - - 0.00% 742.48 3,007.04
- 0.00% - 0.00% - - 0.00% 25.74 8,984.03
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
1,562.13 97.92% - - 0.00% 73.79 1,562.13 97.92% 1.57 33.24
1,948.42 97.92% - - 0.00% 481.09 1,948.42 97.92% 10.24 41.47
3,211.08 77.05% - - 0.00% 9.20 3,211.08 77.05% 2.74 956.34
- - - - - 0.00
25,317.18 97.92% - - 0.00% 513.43 25,317.18 97.92% 10.92 538.52
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 225.24 4,049.82
- 0.00% - 0.00% - - 0.00% 91.44 2,557.58
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 74.64 1,745.83
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 17.12 210.58
- 0.00% - 0.00% - - 0.00% 40.40 1,440.26
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 215.71 7,094.70
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 74.88 11,046.30
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 36.10 1,508.98
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 144.00 2,301.12
- 0.00% - 0.00% - - 0.00% 48.00 1,497.60
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.37 36.33
- 0.00% - 0.00% - - 0.00% 1.80 19.10
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 1.37 298.47
- 0.00% - 0.00% - - 0.00% 198.19 4,934.93
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.76 1,172.18
- 0.00% - 0.00% - - 0.00% 263.16 1,065.80
- 0.00% - 0.00% - - 0.00% 99.31 2,102.39
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 30.10 1,484.23
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 88.54 1,591.95
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 48.00 10,857.12
- 0.00% - 0.00% - - 0.00% 48.00 8,164.32
- 0.00% - 0.00% - - 0.00% 48.00 2,074.56
5,019.60 97.92% - - 0.00% 282.00 5,019.60 97.92% 6.00 106.80
5,019.60 97.92% - - 0.00% 282.00 5,019.60 97.92% 6.00 106.80
488.80 97.92% - - 0.00% 47.00 488.80 97.92% 1.00 10.40
3,346.40 97.92% - - 0.00% 188.00 3,346.40 97.92% 4.00 71.20
5,151.67 97.92% - - 0.00% 47.00 5,151.67 97.92% 1.00 109.61
- 0.00% - 0.00% - - 0.00% 96.00 10,230.72
- 0.00% - 0.00% - - 0.00% 144.00 5,878.08
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 192.00 16,980.48
6,602.58 97.92% - - 0.00% 313.96 6,602.58 97.92% 6.68 140.48
1,305.66 97.92% - - 0.00% 141.00 1,305.66 97.92% 3.00 27.78
1,740.88 97.92% - - 0.00% 188.00 1,740.88 97.92% 4.00 37.04
708.76 97.92% - - 0.00% 94.00 708.76 97.92% 2.00 15.08
984.18 97.92% - - 0.00% 94.00 984.18 97.92% 2.00 20.94
826.26 97.92% - - 0.00% 94.00 826.26 97.92% 2.00 17.58
- 0.00% - - 0.00% - - 0.00% 48.00 3,005.28
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


2,778.17 97.92% - - 0.00% 47.00 2,778.17 97.92% 1.00 59.11
- 0.00% - - 0.00% - - 0.00% 96.00 6,178.56
129,963.83 - - 129,963.83 - 25,196.73
- - - - - 0.00
613.69 97.92% - - 0.00% 1,136.46 613.69 97.92% 24.18 13.06
795.52 97.92% - - 0.00% 1,136.46 795.52 97.92% 24.18 16.93
- - - - - 0.00
- - - - - 0.00
- - - - - 0.00
710.47 97.92% - - 0.00% 26.79 710.47 97.92% 0.57 15.12
24.82 97.92% - - 0.00% 28.20 24.82 97.92% 0.60 0.53
355.32 97.92% - - 0.00% 33.49 355.32 97.92% 0.71 7.53
- - - - - 0.00
2,507.54 97.92% - - 0.00% 107.16 2,507.54 97.92% 2.28 53.35
263.82 97.91% - - 0.00% 65.14 263.82 97.91% 1.39 5.63
4,886.42 97.90% - - 0.00% 14.00 4,886.42 97.90% 0.30 104.71
- - - - - 0.00
112.52 97.92% - - 0.00% 125.02 112.52 97.92% 2.66 2.39
- - - - - 0.00
2,585.41 97.92% - - 0.00% 125.02 2,585.41 97.92% 2.66 55.01
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 44.16 826.23
- - - - - 0.00
977.60 97.92% - - 0.00% 94.00 977.60 97.92% 2.00 20.80
- - - - - 0.00
1,763.05 97.92% - - 0.00% 66.48 1,763.05 97.92% 1.41 37.39
1,671.97 97.91% - - 0.00% 33.24 1,671.97 97.91% 0.71 35.71
1,221.51 97.92% - - 0.00% 207.74 1,221.51 97.92% 4.42 25.99
- - - - - 0.00
- - - - - 0.00
- - - - - 0.00
131.01 98.02% - - 0.00% 4.94 131.01 98.02% 0.10 2.65
8.69 97.92% - - 0.00% 9.87 8.69 97.92% 0.21 0.18
65.46 97.94% - - 0.00% 6.17 65.46 97.94% 0.13 1.38
- - - - - 0.00
727.86 97.64% - - 0.00% 2.48 727.86 97.64% 0.06 17.61
824.85 97.92% - - 0.00% 35.25 824.85 97.92% 0.75 17.55
- - - - - 0.00
335.56 97.95% - - 0.00% 14.34 335.56 97.95% 0.30 7.02
133.93 97.93% - - 0.00% 33.07 133.93 97.93% 0.70 2.84
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


171.02 98.00% - - 0.00% 0.49 171.02 98.00% 0.01 3.49
- - - - - 0.00
28.56 97.93% - - 0.00% 31.73 28.56 97.93% 0.67 0.60
- - - - - 0.00
656.18 97.93% - - 0.00% 31.73 656.18 97.93% 0.67 13.86
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 14.64 273.91
- - - - - 0.00
- - - - - 0.00
4,554.52 97.92% - - 0.00% 171.74 4,554.52 97.92% 3.65 96.83
356.17 97.92% - - 0.00% 28.20 356.17 97.92% 0.60 7.58
2,277.65 97.92% - - 0.00% 214.67 2,277.65 97.92% 4.57 48.49
- - - - - 0.00
2,302.67 97.92% - - 0.00% 98.70 2,302.67 97.92% 2.10 48.99
- - - - - 0.00
70,875.53 97.92% - - 0.00% 47.00 70,875.53 97.92% 1.00 1,507.99
- - - - - 0.00
- - - - - 0.00
560.90 97.92% - - 0.00% 21.15 560.90 97.92% 0.45 11.93
23.27 97.93% - - 0.00% 26.44 23.27 97.93% 0.56 0.49
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


280.53 97.93% - - 0.00% 26.44 280.53 97.93% 0.56 5.94
- - - - - 0.00
2,899.68 97.92% - - 0.00% 9.88 2,899.68 97.92% 0.21 61.63
2,001.64 97.92% - - 0.00% 85.54 2,001.64 97.92% 1.82 42.59
- - - - - 0.00
409.73 97.93% - - 0.00% 17.51 409.73 97.93% 0.37 8.66
176.26 97.91% - - 0.00% 43.52 176.26 97.91% 0.93 3.77
460.72 97.78% - - 0.00% 1.32 460.72 97.78% 0.03 10.47
- - - - - 0.00
76.99 97.92% - - 0.00% 85.54 76.99 97.92% 1.82 1.64
- - - - - 0.00
1,768.97 97.92% - - 0.00% 85.54 1,768.97 97.92% 1.82 37.64
- - - - - 0.00
1,668.50 97.92% - - 0.00% 94.00 1,668.50 97.92% 2.00 35.50
1,699.52 97.92% - - 0.00% 94.00 1,699.52 97.92% 2.00 36.16
4,163.26 97.92% - - 0.00% 47.00 4,163.26 97.92% 1.00 88.58
- - - - - 0.00
2,265.34 97.91% - - 0.00% 85.42 2,265.34 97.91% 1.82 48.27
2,148.31 97.91% - - 0.00% 42.71 2,148.31 97.91% 0.91 45.77
3,668.03 97.92% - - 0.00% 266.96 3,668.03 97.92% 5.68 78.04
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
- - - - - 0.00
186.97 97.92% - - 0.00% 7.05 186.97 97.92% 0.15 3.98
12.41 97.92% - - 0.00% 14.10 12.41 97.92% 0.30 0.26
138.46 97.97% - - 0.00% 13.05 138.46 97.97% 0.27 2.86
- - - - - 0.00
827.64 97.92% - - 0.00% 2.82 827.64 97.92% 0.06 17.61
890.84 97.92% - - 0.00% 38.07 890.84 97.92% 0.81 18.95
- - - - - 0.00
450.92 97.92% - - 0.00% 19.27 450.92 97.92% 0.41 9.59
176.26 97.91% - - 0.00% 43.52 176.26 97.91% 0.93 3.77
247.81 98.61% - - 0.00% 0.71 247.81 98.61% 0.01 3.49
- - - - - 0.00
34.26 97.92% - - 0.00% 38.07 34.26 97.92% 0.81 0.73
- - - - - 0.00
787.29 97.92% - - 0.00% 38.07 787.29 97.92% 0.81 16.75
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 18.72 350.25
- - - - - 0.00
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 108.29 2,871.85
- 0.00% - 0.00% - - 0.00% 135.36 119.12
- 0.00% - 0.00% - - 0.00% 54.14 683.79
- 0.00% - 0.00% - - 0.00% 94.75 1,005.30
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 20.30 2,208.84
- 0.00% - 0.00% - - 0.00% 20.30 2,208.84
- 0.00% - 0.00% - - 0.00% 30.54 357.32
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 135.36 2,309.24
- 0.00% - 0.00% - - 0.00% 225.60 9,215.76
26,451.92 1,664.44 - 28,116.36 - 50,260.58

9,851.21 404.81 - 10,256.02 - 35,793.79


- - - - - 0.00
19.73 70.00% - - 0.00% 36.54 19.73 70.00% 15.66 8.46
25.57 70.00% - - 0.00% 36.54 25.57 70.00% 15.66 10.96
- - - - - 0.00
- - - - - 0.00
239.74 69.97% - - 0.00% 9.04 239.74 69.97% 3.88 102.90
119.78 69.99% - - 0.00% 11.29 119.78 69.99% 4.84 51.35
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
1,736.34 70.04% - - 0.00% 7.97 1,736.34 70.04% 3.41 742.90
634.70 69.97% - - 0.00% 22.00 634.70 69.97% 9.44 272.34
405.02 70.05% - - 0.00% 1.38 405.02 70.05% 0.59 173.16
- 0.00% - 0.00% - - 0.00% 6.00 140.40
- 0.00% - 0.00% - - 0.00% 15.00 311.55
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 18.09 479.75
- 0.00% - 0.00% - - 0.00% 22.61 239.89
- 0.00% - 0.00% - - 0.00% 21.80 19.18
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 32.88 769.39
- 0.00% - 0.00% - - 0.00% 154.68 626.45
- 0.00% - 0.00% - - 0.00% 5.36 1,870.80
- - - - - 0.00
- - - - - 0.00
199.42 60.00% - - 0.00% 9.42 199.42 60.00% 6.28 132.95
290.22 70.01% - - 0.00% 71.66 290.22 70.01% 30.70 124.34
520.05 59.84% - - 0.00% 1.49 520.05 59.84% 1.00 349.03
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
3,231.78 60.00% - - 0.00% 65.54 3,231.78 60.00% 43.70 2,154.85
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 46.93 843.80
- 0.00% - 0.00% - - 0.00% 19.05 532.83
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 15.55 363.71
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.57 43.91
- 0.00% - 0.00% - - 0.00% 8.42 300.17
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 44.94 1,478.08
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 15.60 2,301.31
- 0.00% - 0.00% - - 0.00% 7.52 314.34
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 30.00 479.40
- 0.00% - 0.00% - - 0.00% 10.00 312.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.29 7.69
- 0.00% - 0.00% - - 0.00% 0.38 4.03
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.29 63.18
- 0.00% - 0.00% - - 0.00% 41.29 1,028.12
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 0.78 243.17
- 0.00% - 0.00% - - 0.00% 54.83 222.06
- 0.00% - 0.00% - - 0.00% 20.69 438.01
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 6.27 309.17
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 18.45 331.73
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 10.00 2,261.90
- 0.00% - 0.00% - - 0.00% 10.00 1,700.90
- 0.00% - 0.00% - - 0.00% 10.00 432.20
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


640.80 60.00% 6.00 106.80 10.00% 42.00 747.60 70.00% 18.00 320.40
640.80 60.00% 6.00 106.80 10.00% 42.00 747.60 70.00% 18.00 320.40
62.40 60.00% 1.00 10.40 10.00% 7.00 72.80 70.00% 3.00 31.20
427.20 60.00% 4.00 71.20 10.00% 28.00 498.40 70.00% 12.00 213.60
657.66 60.00% 1.00 109.61 10.00% 7.00 767.27 70.00% 3.00 328.83
- 0.00% - 0.00% - - 0.00% 20.00 2,131.40
- 0.00% - 0.00% - - 0.00% 30.00 1,224.60
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 40.00 3,537.60
- 0.00% - 0.00% - - 0.00% 66.80 1,404.80
- 0.00% - 0.00% - - 0.00% 30.00 277.80
- 0.00% - 0.00% - - 0.00% 40.00 370.40
- 0.00% - 0.00% - - 0.00% 20.00 150.80
- 0.00% - 0.00% - - 0.00% 20.00 209.40
- 0.00% - 0.00% - - 0.00% 20.00 175.80
- 0.00% - 0.00% - - 0.00% 10.00 626.10
- 0.00% - 0.00% - - 0.00% 10.00 591.10
- 0.00% - 0.00% - - 0.00% 20.00 1,287.20
16,600.71 1,259.63 - 17,860.34 - 14,466.79
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


78.35 60.00% 24.18 13.06 10.00% 169.26 91.41 70.00% 72.54 39.17
101.56 60.00% 24.18 16.93 10.00% 169.26 118.49 70.00% 72.54 50.78
- - - - - 0.00
- - - - - 0.00
- - - - - 0.00
90.70 60.00% 0.57 15.12 10.00% 3.99 105.82 70.00% 1.71 45.35
3.17 60.00% 0.60 0.53 10.00% 4.20 3.70 70.00% 1.80 1.58
45.41 60.03% 0.71 7.53 9.96% 4.99 52.94 69.99% 2.14 22.71
- - - - - 0.00
320.11 60.00% 2.28 53.35 10.00% 15.96 373.46 70.00% 6.84 160.06
33.70 60.03% 1.39 5.63 10.03% 9.71 39.33 70.06% 4.15 16.81
624.76 60.07% 0.30 104.71 10.07% 2.09 729.47 70.13% 0.89 310.64
- - - - - 0.00
14.36 60.00% 2.66 2.39 10.00% 18.62 16.75 70.00% 7.98 7.18
- - - - - 0.00
330.05 60.00% 2.66 55.01 10.00% 18.62 385.06 70.00% 7.98 165.03
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 9.20 172.13
- - - - - 0.00
124.80 60.00% 2.00 20.80 10.00% 14.00 145.60 70.00% 6.00 62.40
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
224.89 59.97% 1.41 37.39 9.97% 9.89 262.28 69.94% 4.25 112.71
213.77 60.11% 0.71 35.71 10.04% 4.96 249.48 70.16% 2.11 106.13
155.94 60.00% 4.42 25.99 10.00% 30.94 181.93 70.00% 13.26 77.97
- - - - -
- - - - -
- - - - -
16.98 60.95% 0.11 2.92 10.48% 0.75 19.90 71.43% 0.30 7.96
1.10 60.00% 0.21 0.18 10.00% 1.47 1.28 70.00% 0.63 0.55
8.38 60.31% 0.13 1.38 9.92% 0.92 9.76 70.23% 0.39 4.14
- - - - - 0.00
93.91 60.38% 0.05 14.67 9.43% 0.37 108.58 69.81% 0.16 46.96
105.30 60.00% 0.75 17.55 10.00% 5.25 122.85 70.00% 2.25 52.65
- - - - - 0.00
43.05 60.33% 0.31 7.25 10.16% 2.15 50.30 70.49% 0.90 21.06
17.10 59.94% 0.70 2.84 9.94% 4.92 19.94 69.89% 2.12 8.59
24.43 63.64% 0.01 3.49 9.09% 0.08 27.92 72.73% 0.03 10.47
- - - - - 0.00
3.65 60.15% 0.68 0.61 10.07% 4.74 4.26 70.22% 2.01 1.81
- - - - - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


83.96 60.15% 0.68 14.06 10.07% 4.74 98.02 70.22% 2.01 41.57
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.05 57.07
- - - - - 0.00
- - - - - 0.00
581.32 59.99% 3.65 96.80 9.99% 25.57 678.12 69.98% 10.97 290.92
45.47 60.00% 0.60 7.58 10.00% 4.20 53.05 70.00% 1.80 22.73
290.82 60.00% 4.57 48.49 10.00% 31.98 339.31 70.01% 13.70 145.36
- - - - - 0.00
293.96 60.00% 2.10 48.99 10.00% 14.70 342.95 70.00% 6.30 146.98
- - - - - 0.00
9,047.94 60.00% - - 0.00% 6.00 9,047.94 60.00% 4.00 6,031.96
- - - - - 0.00
- - - - - 0.00
71.60 60.00% 0.45 11.93 10.00% 3.15 83.53 70.00% 1.35 35.80
2.97 60.04% 0.56 0.49 9.95% 3.94 3.46 69.98% 1.69 1.49
35.86 60.04% 0.56 5.94 9.95% 3.94 41.80 69.98% 1.69 17.93
- - - - - 0.00
369.79 60.00% 0.21 61.63 10.00% 1.47 431.42 70.00% 0.63 184.90
255.53 60.00% 1.82 42.59 10.00% 12.74 298.12 70.00% 5.46 127.76
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
52.42 60.05% 0.37 8.66 9.92% 2.61 61.08 69.97% 1.12 26.21
22.52 60.04% 0.93 3.77 10.04% 6.49 26.29 70.09% 2.77 11.22
59.33 60.71% 0.03 10.47 10.71% 0.20 69.80 71.43% 0.08 27.92
- - - - - 0.00
9.83 60.00% 1.82 1.64 10.00% 12.74 11.47 70.00% 5.46 4.91
- - - - - 0.00
225.83 60.00% 1.82 37.64 10.00% 12.74 263.47 70.00% 5.46 112.91
- - - - - 0.00
213.00 60.00% 2.00 35.50 10.00% 14.00 248.50 70.00% 6.00 106.50
216.96 60.00% 2.00 36.16 10.00% 14.00 253.12 70.00% 6.00 108.48
531.48 60.00% 1.00 88.58 10.00% 7.00 620.06 70.00% 3.00 265.74
- - - - - 0.00
289.34 60.01% 1.82 48.27 10.01% 12.73 337.61 70.02% 5.45 144.53
274.64 60.07% 0.91 45.77 10.01% 6.37 320.41 70.08% 2.72 136.82
468.26 60.00% 5.68 78.04 10.00% 39.76 546.30 70.00% 17.04 234.13
- - - - - 0.00
- - - - - 0.00
23.87 60.00% 0.15 3.98 10.00% 1.05 27.85 70.00% 0.45 11.93
1.58 60.00% 0.30 0.26 10.00% 2.10 1.84 70.00% 0.90 0.79
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


17.72 60.07% 0.28 2.97 10.07% 1.95 20.69 70.14% 0.83 8.81
- - - - - 0.00
105.66 60.00% 0.06 17.61 10.00% 0.42 123.27 70.00% 0.18 52.83
113.72 60.00% 0.81 18.95 10.00% 5.67 132.67 70.00% 2.43 56.86
- - - - - 0.00
57.56 60.00% 0.41 9.59 10.00% 2.87 67.15 70.00% 1.23 28.78
22.52 60.04% 0.93 3.77 10.04% 6.49 26.29 70.09% 2.77 11.22
34.90 66.67% 0.02 6.98 13.33% 0.12 41.88 80.00% 0.03 10.47
- - - - - 0.00
4.38 60.00% 0.81 0.73 10.00% 5.67 5.11 70.00% 2.43 2.19
- - - - - 0.00
100.50 60.00% 0.81 16.75 10.00% 5.67 117.25 70.00% 2.43 50.25
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 3.90 72.97
- - - - - 0.00
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 28.20 24.82
- 0.00% - 0.00% - - 0.00% 22.56 598.29
- 0.00% - 0.00% - - 0.00% 11.28 142.47
- 0.00% - 0.00% - - 0.00% 19.74 209.44
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 4.23 460.27
- 0.00% - 0.00% - - 0.00% 4.23 460.27
- 0.00% - 0.00% - - 0.00% 6.36 74.41
- - - - - 0.00
- 0.00% - 0.00% - - 0.00% 28.20 481.09
- 0.00% - 0.00% - - 0.00% 47.00 1,919.95
79,846.10 - - 79,846.10 - 82,925.05
2,264.71 0.00 - 2,264.71 - 1,947.06

6.61 - - 6.61 - -
2.88 100.00% - 0.00% 5.33 2.88 100.00% - 0.00
3.73 100.00% - 0.00% 5.33 3.73 100.00% - 0.00
109.43 - - 109.43 - 23.24
96.18 100.00% - - 0.00% 2.72 96.18 100.00% - 0.00
4.81 100.00% - - 0.00% 4.54 4.81 100.00% - 0.00
8.44 100.00% - - 0.00% 0.53 8.44 100.00% - 0.00
- 0.00% - 0.00% - - 0.00% 2.19 23.24
106.07 - - 106.07 - -
106.07 100.00% - - 0.00% 0.47 106.07 100.00% - 0.00
1,634.21 - - 1,634.21 - -
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


795.27 100.00% - - 0.00% 2.21 795.27 100.00% - 0.00
388.07 100.00% - - 0.00% 95.82 388.07 100.00% - 0.00
450.87 100.00% - - 0.00% 20.72 450.87 100.00% - 0.00
41.00 - - 41.00 - -
41.00 100.00% - - 0.00% 45.56 41.00 100.00% - 0.00
367.39 - - 367.39 - -
172.00 100.00% - - 0.00% 9.12 172.00 100.00% - 0.00
195.39 100.00% - - 0.00% 10.36 195.39 100.00% - 0.00
- - - - - 1,923.82
- 0.00% - 0.00% - - 0.00% 1.00 499.82
- 0.00% - 0.00% - - 0.00% 2.00 1,424.00
652.58 0.00 - 652.58 - 2,386.24

1.44 - - 1.44 - -
0.63 100.00% - 0.00% 1.16 0.63 100.00% - 0.00
0.81 100.00% - 0.00% 1.16 0.81 100.00% - 0.00
58.41 - - 58.41 - -
41.37 100.00% - - 0.00% 1.17 41.37 100.00% - 0.00
1.23 100.00% - - 0.00% 1.16 1.23 100.00% - 0.00
1.59 100.00% - - 0.00% 0.10 1.59 100.00% - 0.00
14.22 100.00% - - 0.00% 1.34 14.22 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


106.07 - - 106.07 - -
106.07 100.00% - - 0.00% 0.47 106.07 100.00% - 0.00
486.66 - - 486.66 - 169.13
- 0.00% - 0.00% - - 0.00% 0.47 169.13
375.03 100.00% - - 0.00% 92.60 375.03 100.00% - 0.00
111.63 100.00% - - 0.00% 5.13 111.63 100.00% - 0.00
- - - - - 4.62
- 0.00% - 0.00% - - 0.00% 5.13 4.62
- - - - - 48.85
- 0.00% - 0.00% - - 0.00% 2.59 48.85
- - - - - 2,163.64
- 0.00% - 0.00% - - 0.00% 2.00 739.64
- 0.00% - 0.00% - - 0.00% 2.00 1,424.00
29,741.38 0.00 - 29,741.38 - 1,108.99

45.14 - - 45.14 - -
19.66 100.00% - 0.00% 36.40 19.66 100.00% - 0.00
25.48 100.00% - 0.00% 36.40 25.48 100.00% - 0.00
4,554.25 - - 4,554.25 - -
3,410.83 100.00% - 0.00% 96.46 3,410.83 100.00% - 0.00
38.58 100.00% - 0.00% 36.40 38.58 100.00% - 0.00
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


243.73 100.00% - 0.00% 15.30 243.73 100.00% - 0.00
861.11 100.00% - 0.00% 81.16 861.11 100.00% - 0.00
929.36 - - 929.36 - -
850.30 100.00% - 0.00% 36.40 850.30 100.00% - 0.00
79.06 100.00% - - 0.00% 2.00 79.06 100.00% - 0.00
21,821.94 - - 21,821.94 - -
10,615.58 100.00% - - 0.00% 29.50 10,615.58 100.00% - 0.00
6,343.44 100.00% - - 0.00% 1,566.28 6,343.44 100.00% - 0.00
4,862.92 100.00% - - 0.00% 223.48 4,862.92 100.00% - 0.00
2,390.69 - - 2,390.69 - -
2,390.69 100.00% - 0.00% 126.76 2,390.69 100.00% - 0.00
- - - - - 1,108.99
- 0.00% - 0.00% - - 0.00% 5.00 182.75
- 0.00% - 0.00% - - 0.00% 5.00 130.25
- 0.00% - 0.00% - - 0.00% 1.00 101.29
- 0.00% - 0.00% - - 0.00% 1.00 86.86
- 0.00% - 0.00% - - 0.00% 3.00 164.58
- 0.00% - 0.00% - - 0.00% 2.00 443.26
0.00 0.00 - 0.00 - 16,949.15

- - - - - 53.05
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 42.78 23.10
- 0.00% - 0.00% - - 0.00% 42.78 29.95
- - - - - 6,889.32
- 0.00% - 0.00% - - 0.00% 115.71 4,091.51
- 0.00% - 0.00% - - 0.00% 44.85 47.54
- 0.00% - 0.00% - - 0.00% 23.76 378.50
- 0.00% - 0.00% - - 0.00% 23.76 1,339.11
- 0.00% - 0.00% - - 0.00% 9.15 573.52
- 0.00% - 0.00% - - 0.00% 1.83 118.82
- 0.00% - 0.00% - - 0.00% 3.97 257.77
- 0.00% - 0.00% - - 0.00% 7.78 82.55
- - - - - 5,931.87
- 0.00% - 0.00% - - 0.00% 8.10 2,914.79
- 0.00% - 0.00% - - 0.00% 500.17 2,025.69
- 0.00% - 0.00% - - 0.00% 45.56 991.39
- - - - - 208.40
- 0.00% - 0.00% - - 0.00% 12.60 152.96
- 0.00% - 0.00% - - 0.00% 2.93 55.44
- - - - - 2,657.98
- 0.00% - 0.00% - - 0.00% 58.43 2,657.98
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 1,208.53
- 0.00% - 0.00% - - 0.00% 12.78 660.34
- 0.00% - 0.00% - - 0.00% 7.20 116.64
- 0.00% - 0.00% - - 0.00% 35.00 431.55
869.81 0.00 - 869.81 - 6,475.05

4.16 - - 4.16 - -
1.81 100.00% - 0.00% 3.36 1.81 100.00% - 0.00
2.35 100.00% - 0.00% 3.36 2.35 100.00% - 0.00
194.38 - - 194.38 - -
117.40 100.00% - - 0.00% 3.32 117.40 100.00% - 0.00
3.56 100.00% - - 0.00% 3.36 3.56 100.00% - 0.00
73.42 100.00% - - 0.00% 6.92 73.42 100.00% - 0.00
671.27 - - 671.27 - 447.35
296.24 100.00% - - 0.00% 12.66 296.24 100.00% - 0.00
375.03 100.00% - - 0.00% 92.60 375.03 100.00% - 0.00
- 0.00% - 0.00% - - 0.00% 1.25 447.35
- - - - - 11.39
- 0.00% - 0.00% - - 0.00% 12.66 11.39
- - - - - 170.40
- 0.00% - 0.00% - - 0.00% 8.24 170.40
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- - - - - 5,381.46
- 0.00% - 0.00% - - 0.00% 3.00 1,109.46
- 0.00% - 0.00% - - 0.00% 6.00 4,272.00
- - - - - 464.45
- 0.00% - 0.00% - - 0.00% 35.00 464.45
45,024.63 0.00 - 45,024.63 - 37,184.19

100.53 - - 100.53 - -
74.20 100.00% - 0.00% 137.41 74.20 100.00% - 0.00
26.33 100.00% - 0.00% 37.61 26.33 100.00% - 0.00
30,545.92 - - 30,545.92 - -
22,108.13 100.00% - 0.00% 625.23 22,108.13 100.00% - 0.00
145.65 100.00% - 0.00% 137.41 145.65 100.00% - 0.00
8,292.14 100.00% - 0.00% 781.54 8,292.14 100.00% - 0.00
1,178.08 - - 1,178.08 - 2,356.17
1,178.08 33.33% - - 0.00% 6.98 1,178.08 33.33% 13.96 2,356.17
5,206.53 - - 5,206.53 - 10,412.72
2,237.72 33.33% - - 0.00% 6.98 2,237.72 33.33% 13.96 4,475.44
1,860.90 33.33% - - 0.00% 459.48 1,860.90 33.33% 918.96 3,721.79
1,107.91 33.34% - - 0.00% 50.92 1,107.91 33.34% 101.82 2,215.49
5,661.77 - - 5,661.77 - 11,322.77
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


5,661.77 33.33% - - 0.00% 111.26 5,661.77 33.33% 222.50 11,322.77
2,331.80 - - 2,331.80 - 11,661.17
2,331.80 16.66% - 0.00% 21.43 2,331.80 16.66% 107.17 11,661.17
- - - - - 1,431.36
- 0.00% - 0.00% - - 0.00% 36.00 1,325.52
- 0.00% - 0.00% - - 0.00% 18.00 105.84
1,292.99 0.00 - 1,292.99 - 14,222.87

18.18 - - 18.18 - 199.98


4.86 8.33% - - 0.00% 9.00 4.86 8.33% 99.00 53.46
13.32 8.33% - - 0.00% 9.00 13.32 8.33% 99.00 146.52
722.51 - - 722.51 - 7,947.59
477.36 8.33% - - 0.00% 18.00 477.36 8.33% 198.00 5,250.96
15.90 8.33% - - 0.00% 15.00 15.90 8.33% 165.00 174.90
70.50 8.33% - - 0.00% 15.00 70.50 8.33% 165.00 775.50
40.65 8.33% - - 0.00% 15.00 40.65 8.33% 165.00 447.15
118.10 8.33% - - 0.00% 8.10 118.10 8.33% 89.10 1,299.08
552.30 - - 552.30 - 6,075.30
552.30 8.33% - - 0.00% 15.00 552.30 8.33% 165.00 6,075.30
0.00 0.00 - 0.00 - 2,651.50

- - - - - 74.40
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


- 0.00% - 0.00% - - 0.00% 60.00 32.40
- 0.00% - 0.00% - - 0.00% 60.00 42.00
- - - - - 108.52
- 0.00% - 0.00% - - 0.00% 2.98 79.03
- 0.00% - 0.00% - - 0.00% 15.80 16.75
- 0.00% - 0.00% - - 0.00% 0.60 9.56
- 0.00% - 0.00% - - 0.00% 0.30 3.18
- - - - - 794.74
- 0.00% - 0.00% - - 0.00% 2.98 794.74
- - - - - 1,673.84
- 0.00% - 0.00% - - 0.00% 120.00 1,508.40
- 0.00% - 0.00% - - 0.00% 1.00 95.75
- 0.00% - 0.00% - - 0.00% 3.50 69.69
13,500.00 - - 13,500.00 - 16,500.00
13,500.00 45.00% - - 0.00% 0.45 13,500.00 45.00% 0.55 16,500.00
38,657.81 6,442.97 - 45,100.77 - 19,328.90
38,657.80 60.00% 0.10 6,442.97 10.00% 0.70 45,100.77 70.00% 0.30 19,328.90

2,284,161.83 405,445.770 2,689,607.60 1,612,182.69


274,099.40 48,653.49 322,752.89 193,461.94
MENSUAL DE OBRA N° 09
ISTA ALEGRE Y PIRIARI, DISTRITO DE RIO TAMBO - SATIPO - JUNIN”

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO


114,208.06 20,272.29 134,480.35 80,609.16
2,672,469.29 474,371.55 3,146,840.84 1,886,253.79
2,672,469.29 474,371.55 3,146,840.84 1,886,253.79
481,044.48 85,386.88 566,431.36 339,525.67
3,153,513.77 559,758.43 3,713,272.20 2,225,779.46
53.09% 9.43% 62.51% 37.49%
CUTAR

27.33%
0.00%
10.67%
17.67%
100.00%

29.83%
0.00%

100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
CUTAR

100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%

100.00%
100.00%
100.00%

100.00%

100.00%

100.00%
CUTAR

%
100.00%

100.00%

100.00%

0.00%
0.00%

50.21%
31.95%
31.95%
31.95%
52.50%

31.95%

100.00%
CUTAR

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%

100.00%

100.00%
CUTAR

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%
CUTAR

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
CUTAR

%
100.00%

100.00%

100.00%

100.00%

100.00%
100.00%

100.00%
100.00%

100.00%

100.00%
100.00%
100.00%
CUTAR

%
100.00%

100.00%

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
100.00%
100.00%
CUTAR

100.00%

100.00%
100.00%
100.00%

100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
CUTAR

%
100.00%

0.00%
0.00%

0.00%
0.00%
33.89%
100.00%

100.00%
0.00%

4.50%
0.00%
18.70%

4.50%
CUTAR

%
0.00%

100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
CUTAR

100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%

100.00%
100.00%
100.00%

0.00%
0.00%
CUTAR

%
0.00%
0.00%
0.00%

0.00%

0.00%
0.00%
0.00%

0.00%

0.00%

0.00%

100.00%

100.00%
CUTAR

0.00%
0.00%

27.82%
27.82%
27.82%
27.82%
27.82%

27.82%

100.00%

100.00%
100.00%

100.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%
100.00%
CUTAR

%
100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%

100.00%
100.00%
CUTAR

%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%

100.00%

100.00%

100.00%
CUTAR

100.00%

0.00%
0.00%

0.00%
0.00%

0.00%

0.00%
0.00%
0.00%

0.00%

0.00%
0.00%
CUTAR

0.00%
100.00%
100.00%
50.00%

100.00%
100.00%

100.00%
100.00%
100.00%

0.00%
0.00%

0.00%
0.00%
0.00%
CUTAR

0.00%
0.00%
0.00%

0.00%

0.00%

100.00%

0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
CUTAR

0.00%
0.00%
0.00%

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
CUTAR

%
100.00%

100.00%

100.00%

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
CUTAR

%
100.00%

100.00%

100.00%

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
CUTAR

100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%

84.13%
CUTAR

0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%

0.00%

100.00%

100.00%
100.00%

100.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%
100.00%
CUTAR

%
100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%

0.00%
0.00%
CUTAR

%
0.00%
0.00%
0.00%

0.00%

0.00%
0.00%
0.00%

0.00%

0.00%
0.00%

0.00%
100.00%
100.00%
50.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%
100.00%

0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
CUTAR

0.00%

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%

100.00%
100.00%
100.00%
CUTAR

0.00%
0.00%

92.86%
92.86%
92.86%
92.86%
92.86%

100.00%
100.00%
100.00%
100.00%
0.00%

100.00%

100.00%
CUTAR

%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%

100.00%

100.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%
100.00%

100.00%
100.00%
CUTAR

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%

100.00%

0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
CUTAR

%
0.00%

0.00%

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%
CUTAR

%
100.00%
100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

0.00%
0.00%

0.00%
0.00%
0.00%
CUTAR

0.00%

0.00%
0.00%
0.00%

0.00%

0.00%
0.00%

0.00%
100.00%
100.00%
50.00%

100.00%
100.00%
CUTAR

%
100.00%
100.00%
100.00%

0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

0.00%

0.00%
CUTAR

%
100.00%

0.00%
0.00%

0.00%
0.00%
0.00%

0.00%

0.00%
0.00%
0.00%

0.00%

0.00%
CUTAR

%
100.00%

100.00%

100.00%

0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
CUTAR

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%
CUTAR

%
100.00%

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
CUTAR

%
100.00%

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%
CUTAR

%
100.00%

100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%

0.00%

0.00%
0.00%
CUTAR

0.00%
0.00%
0.00%
0.00%
0.00%

0.00%

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
CUTAR

%
100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%

0.00%
0.00%

0.00%
0.00%
0.00%
CUTAR

%
0.00%

0.00%
0.00%
0.00%

0.00%

0.00%

100.00%

100.00%

100.00%

0.00%
0.00%
CUTAR

%
0.00%
0.00%
0.00%

0.00%

0.00%
0.00%
0.00%

0.00%

0.00%
0.00%

0.00%
100.00%
100.00%
50.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%
100.00%

0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
CUTAR

0.00%

100.00%

0.00%
0.00%

7.11%
7.11%
7.11%
7.11%
7.11%

48.69%
0.00%
0.00%
0.00%
0.00%
CUTAR

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%
CUTAR

%
100.00%

100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
CUTAR

%
100.00%

100.00%

33.33%
33.33%

33.33%
33.33%
33.33%

33.33%
33.33%

100.00%

100.00%

0.00%
CUTAR

%
50.00%

100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%

0.00%

0.00%
0.00%
CUTAR

72.10%
72.10%
72.10%
72.10%
72.10%

0.00%
100.00%
100.00%
100.00%

100.00%

100.00%
100.00%

100.00%
100.00%
CUTAR

%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%
100.00%
CUTAR

%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%

100.00%

100.00%

100.00%
CUTAR

100.00%

0.00%
0.00%

48.82%
48.82%
48.82%
48.82%
48.82%

52.25%
0.00%

100.00%

100.00%
CUTAR

%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%

100.00%

100.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%

100.00%

100.00%
100.00%

100.00%
100.00%
CUTAR

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%

100.00%

0.00%
10.00%

0.00%
0.00%

0.00%
CUTAR

%
0.00%
0.00%
0.00%
0.00%

0.00%

0.00%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
CUTAR

%
0.00%

0.00%

0.00%
0.00%

0.00%
0.00%
0.00%
0.00%

0.00%
9.73%
0.00%
0.00%

0.00%
CUTAR

%
0.00%
0.00%
0.00%

0.00%

6.66%
6.66%

4.89%
6.66%
4.89%
6.66%

3.99%
6.62%
6.66%
6.67%
CUTAR

6.66%
6.66%
6.67%
6.67%

6.67%

100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
CUTAR

%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%

93.18%
93.18%

93.18%
93.18%
93.18%
93.18%

100.00%
100.00%
CUTAR

100.00%

0.00%
0.00%

0.00%
0.00%

0.00%
0.00%
0.01%
6.35%
100.00%
CUTAR

%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%

6.35%
0.00%
6.33%

3.17%

100.00%
100.00%

100.00%
CUTAR

100.00%
100.00%

100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%
CUTAR

%
100.00%
100.00%
100.00%

100.00%

100.00%

100.00%
100.00%
100.00%
3.17%
3.17%
3.17%
3.17%
3.17%
100.00%
100.00%
CUTAR

%
100.00%
3.17%
3.17%
3.17%
3.17%
3.17%
3.17%
100.00%
3.17%
100.00%

3.17%
3.17%

3.17%
3.17%
3.16%
CUTAR

3.17%
3.17%
3.14%

3.17%

3.17%

100.00%

3.17%

3.18%
3.19%
3.17%

3.17%
CUTAR

%
3.17%
3.14%

2.99%
3.17%

3.17%
3.18%
3.03%

3.17%

3.17%

100.00%

3.18%
3.17%
3.18%
CUTAR

3.17%

0.00%

3.17%
3.16%
3.16%

3.17%
3.17%

3.15%
3.17%
2.82%

3.17%

3.17%
CUTAR

3.17%
3.17%
3.17%

3.17%
3.18%
3.17%

3.17%
3.17%
3.20%

3.17%
3.17%

3.17%
3.17%
3.16%
CUTAR

3.17%

3.17%

100.00%

36.51%
36.51%
36.50%
36.51%

36.51%
36.51%
36.50%

36.51%
36.51%
CUTAR

0.00%
0.00%

0.00%
0.00%

0.00%
0.00%
0.02%
37.14%
37.14%

97.14%
97.14%
97.14%
CUTAR

%
97.14%
97.14%
97.12%

5.71%
0.00%
5.74%

5.71%

9.73%
25.10%

100.00%

100.00%
100.00%
CUTAR

%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%
100.00%
CUTAR

%
100.00%

100.00%

100.00%
100.00%
14.29%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
100.00%

100.00%
5.71%
5.71%
5.71%
CUTAR

%
5.71%
5.71%
5.71%
100.00%
5.71%
100.00%

5.71%
5.71%

5.71%
5.71%
5.73%

5.71%
5.73%
5.75%
CUTAR

5.71%

5.71%

100.00%

5.71%

5.72%
5.74%
5.71%

5.71%
5.71%
5.66%

5.38%
CUTAR

%
5.71%

5.71%
5.73%
5.41%

5.71%

5.71%

100.00%

5.72%
5.71%
100.00%

5.71%

5.71%
CUTAR

5.71%
5.74%
5.74%

5.71%
5.71%

5.75%
5.74%
6.12%

5.71%

5.71%

5.71%
5.71%
5.71%
CUTAR

5.71%
5.72%
5.71%

5.71%
5.71%
5.66%

5.71%
5.71%

5.71%
5.74%
5.66%

5.71%

5.71%
CUTAR

100.00%

28.57%
28.57%
28.57%
28.57%

28.56%
28.56%
28.56%

28.57%
28.57%

2.08%
2.08%
CUTAR

2.09%
2.08%

2.07%
2.08%
2.11%
16.67%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
CUTAR

2.08%
2.08%
22.95%

2.08%

100.00%
100.00%

100.00%

100.00%
100.00%

100.00%

100.00%
CUTAR

%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%

100.00%
CUTAR

100.00%
100.00%
100.00%
2.08%
2.08%
2.08%
2.08%
2.08%
100.00%
100.00%

100.00%
2.08%
2.08%
2.08%
2.08%
2.08%
2.08%
100.00%
CUTAR

%
2.08%
100.00%

2.08%
2.08%

2.08%
2.08%
2.08%

2.08%
2.09%
2.10%

2.08%

2.08%
CUTAR

100.00%

2.08%

2.08%
2.09%
2.08%

1.98%
2.08%
2.06%

2.36%
2.08%

2.05%
2.07%
CUTAR

%
2.00%

2.07%

2.07%

100.00%

2.08%
2.08%
2.08%

2.08%

2.08%

2.08%
2.07%
CUTAR

%
2.07%

2.08%
2.08%

2.07%
2.09%
2.22%

2.08%

2.08%

2.08%
2.08%
2.08%

2.09%
2.09%
2.08%
CUTAR

2.08%
2.08%
2.03%

2.08%
2.08%

2.08%
2.09%
1.39%

2.08%

2.08%

100.00%
CUTAR

%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

30.00%
30.00%

30.03%
30.01%
CUTAR

29.96%
30.03%
29.95%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%
100.00%

40.00%
29.99%
40.16%
CUTAR

40.00%

100.00%
100.00%

100.00%

100.00%
100.00%

100.00%

100.00%
100.00%

100.00%
100.00%
CUTAR

100.00%
100.00%

100.00%
100.00%

100.00%
100.00%
100.00%

100.00%

100.00%

100.00%
100.00%
100.00%
CUTAR

%
30.00%
30.00%
30.00%
30.00%
30.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
CUTAR

%
30.00%
30.00%

30.00%
30.00%
30.01%

30.00%
29.94%
29.87%

30.00%

30.00%

100.00%

30.00%
CUTAR

30.06%
29.84%
30.00%

28.57%
30.00%
29.77%

30.19%
30.00%

29.51%
30.11%
27.27%

29.78%
CUTAR

%
29.78%

100.00%

30.02%
30.00%
29.99%

30.00%

40.00%

30.00%
30.02%
30.02%

30.00%
30.00%
CUTAR

30.03%
29.91%
28.57%

30.00%

30.00%

30.00%
30.00%
30.00%

29.98%
29.92%
30.00%

30.00%
30.00%
CUTAR

%
29.86%

30.00%
30.00%

30.00%
29.91%
20.00%

30.00%

30.00%

100.00%

100.00%
100.00%
100.00%
100.00%
CUTAR

100.00%
100.00%
100.00%

100.00%
100.00%

0.00%
0.00%

0.00%
0.00%
0.00%
100.00%

0.00%
CUTAR

%
0.00%
0.00%
0.00%

0.00%

0.00%
0.00%

100.00%
100.00%

0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
CUTAR

0.00%

100.00%
0.00%
0.00%

100.00%

100.00%

100.00%
100.00%

0.00%
0.00%

0.00%
0.00%
CUTAR

%
0.00%
0.00%

0.00%
0.00%

0.00%
0.00%
0.00%

0.00%

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
CUTAR

%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

100.00%
CUTAR

100.00%
100.00%
100.00%

0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
0.00%
100.00%

100.00%

100.00%
CUTAR

100.00%
100.00%

100.00%

0.00%
0.00%

0.00%
0.00%
0.00%

66.67%

66.67%
66.67%
66.66%
CUTAR

%
66.67%

83.34%

100.00%
100.00%

91.67%
91.67%

91.67%
91.67%
91.67%
91.67%
91.67%

91.67%
CUTAR

%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%

100.00%

100.00%
100.00%
100.00%

55.00%

30.00%
CUTAR

%
METRADOS EJECUTADOS MENS
Del 01 al 30 de Setiembre del 2018

“MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO INTEGRAL EN LAS


OBRA :
Y PIRIARI, DISTRITO DE RIO TAMBO - SA

CONTRATISTA : CONSORCIO MONTE SINAI


MODALIDAD : PRECIOS UNITARIOS
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE RIO TAMBO
RESIDENTE : ING. JOSE GONZALES FERIA
SUPERVISOR : ING. RAFAEL ALFONSO ZARATE AVILA


PART.
01 OBRAS GENERALES
01.01 OBRAS PROVISIONALES
01.01.01 ALMACEN, OFICINA Y CASETA DE GUARDIANIA
01.01.02 CARTEL DE IDENTIFICACION DE OBRA DE 5.40x3.60 m.
01.01.03 TRANSPORTE DE MATERIALES Y EQUIPOS
01.01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO (AGUA)
01.01.05 ZANJAS DE CORONACION BOCATOMA, DE DRENAJE EN ZONAS DE PTAR PTAP
01.02 SEÑALIZACION
01.02.01 MALLA PLASTICA SEÑALIZACION C/LIMITES SEGURIDAD DE OBRA
01.02.02 CARTEL DE SEÑALIZACION PREVENTIVA
01.03 BOCATOMA (01 UND)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA MANUAL DE TERRENO
01.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL C/ PRESENCIA DE AGUA
01.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
01.03.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
01.03.02.04 ELIMINACION MATERIAL EXCEDENTE
01.03.03 OBRAS DE CONCRETO SIMPLE
01.03.03.01 CONCRETO CICLOPEO f'c=175KG/CM2 +30% P.M.
01.03.03.02 CONCRETO f'c=100 kg/cm2
01.03.04 OBRAS DE CONCRETO ARMADO
01.03.04.01 CONCRETO f'c=210KG/CM2
01.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
01.03.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
01.03.05 CURADO DE CONCRETO
01.03.05.01 CURADO CON PRODUCTO QUIMICO
01.03.06 REVOQUES Y ENLUCIDOS
01.03.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
01.03.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
01.03.07 CARPINTERIA METALICA
01.03.07.01 MARCO Y COMPUERTA VOLANTE DE TIPO-1 (0.80x0.90M)
01.03.07.02 REJILLA METALICA PREFABRICADA (0.90x1.30M)
01.03.08 PINTURA
01.03.08.01 PINTURA LATEX SATINADO A DOS MANOS
01.03.08.02 PINTURA ANTICORROCIVA A DOS MANOS
01.03.09 VALVULAS, ACCESORIOS Y TUBERIAS
01.03.09.01 SALIDA DE CAPTACION DE DN 110MM
01.04 DESARENADOR (01 UND)
01.04.01 TRABAJOS PRELIMINARES
01.04.01.01 LIMPIEZA MANUAL DE TERRENO
01.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
01.04.02 MOVIMIENTO DE TIERRAS
01.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
01.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
01.04.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
01.04.02.04 ELIMINACION MATERIAL EXCEDENTE
01.04.03 OBRAS DE CONCRETO SIMPLE
01.04.03.01 CONCRETO f'c=100 kg/cm2
01.04.04 OBRAS DE CONCRETO ARMADO
01.04.04.01 CONCRETO f'c=210KG/CM2
01.04.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
01.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
01.04.05 CURADO DE CONCRETO
01.04.05.01 CURADO CON PRODUCTO QUIMICO
01.04.06 REVOQUES Y ENLUCIDOS
01.04.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
01.04.07 CARPINTERIA METALICA
01.04.07.01 MARCO Y COMPUERTA VOLANTE DE TIPO-1 (0.30x0.30m)
01.04.07.02 MARCO Y COMPUERTA TIPO BAFLE
01.04.08 PINTURA
01.04.08.01 PINTURA LATEX SATINADO A DOS MANOS
01.04.09 VALVULAS, ACCESORIOS Y TUBERIAS
01.04.09.01 ACCESORIO Y TUBERIA
01.05 LINEA DE CONDUCCION (14+240 KM)
01.05.01 TRABAJOS PRELIMINARES
01.05.01.01 LIMPIEZA MANUAL DE TERRENO
01.05.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
01.05.02 MOVIMIENTO DE TIERRAS
01.05.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
01.05.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
01.05.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
01.05.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
01.05.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
01.05.03 INSTALACION DE TUBERIA
01.05.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 110 MM C/ANILLO
01.05.04 PRUEBA DE CALIDAD
01.05.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
01.06 VALVULA DE AIRE (26 UND)
01.06.01 TRABAJOS PRELIMINARES
01.06.01.01 LIMPIEZA MANUAL DE TERRENO
01.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
01.06.02 MOVIMIENTO DE TIERRAS
01.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
01.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
01.06.02.03 ELIMINACION MATERAIL EXCEDENTE
01.06.03 OBRAS DE CONCRETO SIMPLE
01.06.03.01 CONCRETO f'c=175 kg/cm2
01.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
01.06.04 CURADO DE CONCRETO
01.06.04.01 CURADO CON PRODUCTO QUIMICO
01.06.05 REVOQUES Y ENLUCIDOS
01.06.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
01.06.06 CARPINTERIA METALICA
01.06.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
01.06.07 PINTURA
01.06.07.01 PINTURA ANTICORROCIVA A DOS MANOS
01.06.08 ACCESORIOS
01.06.08.01 ACCESORIOS VALVULA DE AIRE D=110MM
01.07 VALVULA DE PURGA (05 UND)
01.07.01 TRABAJOS PRELIMINARES
01.07.01.01 LIMPIEZA MANUAL DE TERRENO
01.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
01.07.02 MOVIMIENTO DE TIERRAS
01.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
01.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
01.07.02.03 ELIMINACION MATERAIL EXCEDENTE
01.07.03 OBRAS DE CONCRETO SIMPLE
01.07.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO
E=0.10m
01.07.03.02 CONCRETO f'c = 140 kg/cm2
01.07.04 OBRAS DE CONCRETO ESTRUCTURA
01.07.04.01 CONCRETO f'c=175 kg/cm2
01.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
01.07.05 CARPINTERIA METALICA
01.07.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
01.07.06 PINTURA
01.07.06.01 PINTURA LATEX SATINADO A DOS MANOS
01.07.07 ACCESORIOS
01.07.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
01.08 CAMARA ROMPE PRESION (01 UNID)
01.08.01 TRABAJOS PRELIMINARES
01.08.01.01 LIMPIEZA MANUAL DE TERRENO
01.08.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
01.08.02 MOVIMIENTO DE TIERRAS
01.08.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
01.08.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
01.08.02.03 ELIMINACION MATERAIL EXCEDENTE
01.08.03 OBRAS DE CONCRETO SIMPLE
01.08.03.01 ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX 6", E=20m
01.08.03.02 CONCRETO f'c=100 kg/cm2
01.08.03.03 CONCRETO f'c=140 kg/cm2
01.08.03.04 ENCOFRADO Y DESENCOFRADO NORMAL
01.08.04 OBRAS DE CONCRETO ARMADO
01.08.04.01 CONCRETO f'c=210KG/CM2
01.08.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
01.08.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
01.08.05 CURADO DE CONCRETO
01.08.05.01 CURADO CON PRODUCTO QUIMICO
01.08.06 REVOQUES Y ENLUCIDOS
01.08.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
01.08.07 CARPINTERIA METALICA
01.08.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
01.08.08 PINTURA
01.08.08.01 PINTURA ANTICORROCIVA A DOS MANOS
01.08.09 ACCESORIOS
01.08.09.01 ACCESORIO DE CAMARA ROMPE PRESION
01.09 PASE AEREO L=15.00m (09 UNID)
01.09.01 TRABAJOS PRELIMINARES
01.09.01.01 LIMPIEZA MANUAL DE TERRENO
01.09.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
01.09.02 MOVIMIENTO DE TIERRAS
01.09.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
01.09.02.02 ELIMINACION MATERAIL EXCEDENTE
01.09.03 OBRAS DE CONCRETO SIMPLE
01.09.03.01 CONCRETO f'c=100 kg/cm2
01.09.04 OBRAS DE CONCRETO ARMADO
01.09.04.01 CONCRETO f'c=210KG/CM2
01.09.04.02 CONCRETO EN DADO f'c=175 kg/cm2
01.09.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
01.09.04.04 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
01.09.05 REVOQUES Y ENLUCIDOS
01.09.05.01 TARRAJEO EN COLUMNAS
01.09.06 ACCESORIOS PASE AEREO
01.09.06.01 CABLE DE ACERO TIPO BOA DE 3/8"
01.09.06.02 PENDOLAS DE CABLE DE ACERO LISO DE 1/4"
01.09.06.03 GRAPA TIPO CROSBY DE A°G° PARA CABLE DE 25 mm2.
01.09.06.04 TUBERIA HDPE SDR7 DE 110MM
01.09.06.05 LANZAMIENTO Y FIJACION
01.09.06.06 SUMINISTRO
01.10 ------------------------------------------
01.11 ------------------------------------------
01.12 PREFILTRO (02 UND)
01.12.01 TRABAJOS PRELIMINARES
01.12.01.01 LIMPIEZA MANUAL DE TERRENO
01.12.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
01.12.02 MOVIMIENTO DE TIERRAS
01.12.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
01.12.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
01.12.02.03 ELIMINACION MATERAIL EXCEDENTE
01.12.03 OBRAS DE CONCRETO SIMPLE
01.12.03.01 CONCRETO f'c=100 kg/cm2
01.12.04 OBRAS DE CONCRETO ARMADO
01.12.04.01 CONCRETO f'c=210KG/CM2
01.12.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
01.12.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
01.12.05 CURADO DE CONCRETO
01.12.05.01 CURADO CON PRODUCTO QUIMICO
01.12.06 REVOQUES Y ENLUCIDOS
01.12.06.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
01.12.06.02 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
01.12.07 PINTURA
01.12.07.01 PINTURA LATEX SATINADO A DOS MANOS
01.12.07.02 PINTURA ANTICORROCIVA A DOS MANOS
01.12.08 SUMINISTRO E INST. DE COMPONENTES DEL LECHO FILTRANTE
01.12.08.01 FILTRO DE GRAVA 15mm
01.12.08.02 FILTRO DE GRAVA 10mm
01.12.08.03 FILTRO DE GRAVA 5mm
01.12.08.04 FILTRO DE GRAVA 1/2"
01.12.09 SUMINISTRO E INSTALACION DE ACCESORIOS
01.12.09.01 ACCESORIO DEL PREFILTRO
1.13 FILTRO LENTO (01 UND)
01.13.01 TRABAJOS PRELIMINARES
01.13.01.01 LIMPIEZA MANUAL DE TERRENO
01.13.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
01.13.02 MOVIMIENTO DE TIERRAS
01.13.02.01 CORTE C/MAQUINARIA EN TERRENO DE MATERIAL COMPACTO
01.13.02.02 REFINE Y NIVELACION DE PLATAFORMA
01.13.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
01.13.02.04 ELIMINACION MATERAIL EXCEDENTE
01.13.03 OBRAS DE CONCRETO SIMPLE
01.13.03.01 ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX 4", E=10m
01.13.03.02 CONCRETO f'c=100 kg/cm2
01.13.04 OBRAS DE CONCRETO ARMADO
01.13.04.01 CONCRETO f'c=210KG/CM2
01.13.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
01.13.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
01.13.05 CURADO DE CONCRETO
01.13.05.01 CURADO CON PRODUCTO QUIMICO
01.13.06 JUNTAS
01.13.06.01 JUNTAS WATERSTOP DE PVC DE 6"
01.13.07 REVOQUES Y ENLUCIDOS
01.13.07.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
01.13.07.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
01.13.07.03 MORTERO CON PENDIENTE EN FONDO C.A. 1:3, C/IMPERMEABILIZANTES
01.13.08 CARPINTERIA METALICA
01.13.08.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
01.13.08.02 MARCO Y VERTEDERO METALICO PREFABRICADO E=1/4",(0.50x0.70M.)
01.13.08.03 MARCO Y VERTEDERO METALICO PREFABRICADO E=1/4",(0.40x0.70M.)
01.13.08.04 ESCALERA METALICA PREFABRICADA DE TUB F°G° DE 11/2", H=3.20M
01.13.09 FILTROS
01.13.09.01 FILTRO DE GRAVA DE 19 - 50 MM
01.13.09.02 FILTRO DE GRAVA DE 9.5 - 19 MM
01.13.09.03 FILTRO DE GRAVA DE 3 - 9.5 MM
01.13.09.04 FILTRO DE GRAVA DE ARENA GRUESA
01.13.10 PINTURA
01.13.10.01 PINTURA LATEX SATINADO A DOS MANOS
01.13.10.02 PINTURA ANTICORROCIVA A DOS MANOS
01.13.11 VALVULAS, ACCESORIOS Y TUBERIA
01.13.11.01 ACCESORIOS PARA INGRESO DE PRE FILTRO DN 160MM
01.14 CERCO PERIMETRICO (L=240.00 m)
01.14.01 TRABAJOS PRELIMINARES
01.14.01.01 LIMPIEZA MANUAL DE TERRENO
01.14.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
01.14.02 MOVIMIENTO DE TIERRAS
01.14.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
01.14.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
01.14.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
01.14.02.04 ELIMINACION MATERAIL EXCEDENTE
01.14.03 OBRAS DE CONCRETO SIMPLE
01.14.03.01 CONCRETO f'c=140 kg/cm2
01.14.04 CERCO PERIMETRICO CON MALLA OLIMPICA GALVANIZADA
01.14.04.01 CERCO PERIMETRICO DE ALAMBRE DE PUAS
01.14.04.02 PUERTA DE MADERA CON MARCO O SOPORTES
01.14.04.03 PINTURA ESMALTE EN PUERTAS Y VENTANAS A DOS MANOS
01.15 CAMARA DE DISTRIBUCION DE CAUDALES 03 SALIDAS (01 UNID)
01.15.01 TRABAJOS PRELIMINARES
01.15.01.01 LIMPIEZA MANUAL DE TERRENO
01.15.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
01.15.02 MOVIMIENTO DE TIERRAS
01.15.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
01.15.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
01.15.02.03 ELIMINACION MATERAIL EXCEDENTE
01.15.03 OBRAS DE CONCRETO SIMPLE
01.15.03.01 CONCRETO f'c=100 kg/cm2
01.15.04 OBRAS DE CONCRETO ARMADO
01.15.04.01 CONCRETO f'c=210KG/CM2
01.15.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
01.15.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
01.15.05 CURADO DE CONCRETO
01.15.05.01 CURADO CON PRODUCTO QUIMICO
01.15.06 REVOQUES Y ENLUCIDOS
01.15.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
01.15.07 CARPINTERIA METALICA
01.15.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
01.15.08 PINTURA
01.15.08.01 PINTURA ANTICORROCIVA A DOS MANOS
01.15.09 ACCESORIOS
01.15.09.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
2 SERVICIO DE AGUA POTABLE ALTO UNINI
2.01 LINEA DE ADUCCION (3+671.22 KM) ALTO UNINI
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 LIMPIEZA MANUAL DE TERRENO
02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
02.01.02 MOVIMIENTO DE TIERRAS
02.01.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
02.01.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
02.01.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
02.01.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
02.01.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
02.01.03 INSTALACION DE TUBERIA
02.01.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO
02.01.04 PRUEBA DE CALIDAD
02.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
02.02 VALVULA DE AIRE (08 UND)
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 LIMPIEZA MANUAL DE TERRENO
02.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
02.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
02.02.02.03 ELIMINACION MATERAIL EXCEDENTE
02.02.03 OBRAS DE CONCRETO SIMPLE
02.02.03.01 CONCRETO f'c=175 kg/cm2
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
02.02.04 CURADO DE CONCRETO
02.02.04.01 CURADO CON PRODUCTO QUIMICO
02.02.05 REVOQUES Y ENLUCIDOS
02.02.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
02.02.06 CARPINTERIA METALICA
02.02.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
02.02.07 PINTURA
02.02.07.01 PINTURA ANTICORROCIVA A DOS MANOS
02.02.08 ACCESORIOS
02.02.08.01 ABRAZADERA PVC SP CON REDUCCION DN 63 MM A Ø 1"
02.03 VALVULA DE PURGA (02 UND)
02.03.01 TRABAJOS PRELIMINARES
02.03.01.01 LIMPIEZA MANUAL DE TERRENO
02.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
02.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
02.03.02.03 ELIMINACION MATERAIL EXCEDENTE
02.03.03 OBRAS DE CONCRETO SIMPLE
02.03.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO
E=0.10m
02.03.03.02 CONCRETO f'c = 140 kg/cm2
02.03.04 OBRAS DE CONCRETO ESTRUCTURA
02.03.04.01 CONCRETO f'c=175 kg/cm2
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
02.03.05 CARPINTERIA METALICA
02.03.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
02.03.06 PINTURA
02.03.06.01 PINTURA LATEX SATINADO A DOS MANOS
02.03.07 ACCESORIOS
02.03.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
02.04 CAMARA ROMPE PRESION (02 UNID)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA MANUAL DE TERRENO
02.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
02.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
02.04.02.03 ELIMINACION MATERAIL EXCEDENTE
02.04.03 OBRAS DE CONCRETO SIMPLE
02.04.03.01 ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX 6", E=20m
02.04.03.02 CONCRETO f'c=100 kg/cm2
02.04.03.03 CONCRETO f'c=140 kg/cm2
02.04.03.04 ENCOFRADO Y DESENCOFRADO NORMAL
02.04.04 OBRAS DE CONCRETO ARMADO
02.04.04.01 CONCRETO f'c=210KG/CM2
02.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
02.04.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
02.04.05 CURADO DE CONCRETO
02.04.05.01 CURADO CON PRODUCTO QUIMICO
02.04.06 REVOQUES Y ENLUCIDOS
02.04.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
02.04.07 CARPINTERIA METALICA
02.04.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
02.04.08 PINTURA
02.04.08.01 PINTURA ANTICORROCIVA A DOS MANOS
02.04.09 ACCESORIOS
02.04.09.01 ACCESORIO DE CAMARA ROMPE PRESION
2.05 RESERVORIO DE UNINI V=15M3 (01UNID)
02.05.01 TRABAJOS PRELIMINARES
02.05.01.01 LIMPIEZA MANUAL DE TERRENO
02.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 CORTE C/MAQUINARIA EN TERRENO DE MATERIAL COMPACTO
02.05.02.02 ELIMINACION MATERAIL EXCEDENTE
02.05.03 OBRAS DE CONCRETO SIMPLE
02.05.03.01 CONCRETO f'c=100 kg/cm2
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 CONCRETO f'c=210KG/CM2
02.05.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
02.05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
02.05.05 CURADO DE CONCRETO
02.05.05.01 CURADO CON PRODUCTO QUIMICO
02.05.06 REVOQUES Y ENLUCIDOS
02.05.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
02.05.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
02.05.07 CARPINTERIA METALICA
02.05.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
02.05.07.02 ESCALERA INTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
02.05.07.03 ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
02.05.07.04 VENTILACION DE F°G° DE DN=75MM
02.05.08 PINTURA
02.05.08.01 PINTURA LATEX SATINADO A DOS MANOS
02.05.08.02 PINTURA ANTICORROCIVA A DOS MANOS
02.05.09 VALVULAS, ACCESORIOS Y TUBERIA
02.05.09.01 ACCESORIO P/INGRESO DE RESERVORIO DN 63MM
02.05.09.02 ACCESORIO P/SALIDA DE RESERVORIO
02.05.09.03 ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA
02.05.10 CASETA DE CLORACION (01 UND)
02.05.10.01 TRABAJOS PRELIMINARES
02.05.10.01.01 LIMPIEZA MANUAL DE TERRENO
02.05.10.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
02.05.10.02 MOVIMIENTO DE TIERRAS
02.05.10.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
02.05.10.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
02.05.10.02.03 ELIMINACION MATERAIL EXCEDENTE
02.05.10.03 OBRAS DE CONCRETO ARMADO
02.05.10.03.01 CONCRETO f'c=210KG/CM2
02.05.10.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
02.05.10.03.03 ENCOFRADO Y DESENCOFRADO NORMAL
02.05.10.04 CURADO DE CONCRETO
02.05.10.04.01 CURADO CON PRODUCTO QUIMICO
02.05.10.05 REVOQUES Y ENLUCIDOS
02.05.10.05.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
02.05.10.06 SUMINISTRO E INSTALACION DE ACCESORIOS
02.05.10.06.01 SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE CLORACION
2.06 RED DE DISTRIBUCION UNINI (L=4+622.78m)
02.06.01 TRABAJOS PRELIMINARES
02.06.01.01 LIMPIEZA MANUAL DE TERRENO
02.06.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
02.06.02 MOVIMIENTO DE TIERRAS
02.06.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
02.06.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
02.06.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
02.06.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
02.06.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
02.06.03 INSTALACION DE TUBERIA
02.06.03.01 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2"
02.06.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
02.06.03.03 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2"
02.06.04 PRUEBA DE CALIDAD
02.06.04.01 DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA DE AGUA
02.06.05 VALVULA DE AIRE DISTR (03 UND)
02.06.05.01 TRABAJOS PRELIMINARES
02.06.05.01.01 LIMPIEZA MANUAL DE TERRENO
02.06.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
02.06.05.02 MOVIMIENTO DE TIERRAS
02.06.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
02.06.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
02.06.05.02.03 ELIMINACION MATERAIL EXCEDENTE
02.06.05.03 OBRAS DE CONCRETO SIMPLE
02.06.05.03.01 CONCRETO f'c=175 kg/cm2
02.06.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
02.06.05.04 CURADO DE CONCRETO
02.06.05.04.01 CURADO CON PRODUCTO QUIMICO
02.06.05.05 REVOQUES Y ENLUCIDOS
02.06.05.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
02.06.05.06 CARPINTERIA METALICA
02.06.05.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
02.06.05.07 PINTURA
02.06.05.07.01 PINTURA ANTICORROCIVA A DOS MANOS
02.06.05.08 ACCESORIOS
02.06.05.08.01 ABRAZADERA PVC SP CON REDUCCION DN 50 MM A Ø 1"
02.06.06 VALVULA DE PURGA DISTR (04 UND)
02.06.06.01 TRABAJOS PRELIMINARES
02.06.06.01.01 LIMPIEZA MANUAL DE TERRENO
02.06.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
02.06.06.02 MOVIMIENTO DE TIERRAS
02.06.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
02.06.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
02.06.06.02.03 ELIMINACION MATERAIL EXCEDENTE
02.06.06.03 OBRAS DE CONCRETO SIMPLE
02.06.06.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y
APISONADO E=0.10m
02.06.06.03.02 CONCRETO f'c = 140 kg/cm2
02.06.06.04 OBRAS DE CONCRETO ESTRUCTURA
02.06.06.04.01 CONCRETO f'c=175 kg/cm2
02.06.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
02.06.06.05 CARPINTERIA METALICA
02.06.06.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
02.06.06.06 PINTURA
02.06.06.06.01 PINTURA LATEX SATINADO A DOS MANOS
02.06.06.07 ACCESORIOS
02.06.06.08 ACCESORIOS P/VALVULA DE PURGA DE DN 50MM
02.06.07 VALVULA DE CONTROL (03 UND)
02.06.07.01 TRABAJOS PRELIMINARES
02.06.07.01.01 LIMPIEZA MANUAL DE TERRENO
02.06.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
02.06.07.02 MOVIMIENTO DE TIERRAS
02.06.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
02.06.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
02.06.07.02.03 ELIMINACION MATERAIL EXCEDENTE
02.06.07.03 OBRAS DE CONCRETO SIMPLE
02.06.07.03.01 CONCRETO f'c=175 kg/cm2
02.06.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
02.06.07.04 CARPINTERIA METALICA
02.06.07.04.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
02.06.07.05 PINTURA
02.06.07.05.01 PINTURA LATEX SATINADO A DOS MANOS
02.06.07.06 ACCESORIOS
02.06.07.06.01 ACCESORIOS V. CONTROL 1"
02.06.07.06.02 ACCESORIOS V. CONTROL 3/4"
2.07 CONEXIONES DOMICILIARIAS ALTO UNINI (63 UNID.)
02.07.01 TRABAJOS PRELIMINARES
02.07.01.01 LIMPIEZA MANUAL DE TERRENO
02.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
02.07.02 MOVIMIENTO DE TIERRAS
02.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
02.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
02.07.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
02.07.02.04 ELIMINACION MATERAIL EXCEDENTE
02.07.03 OBRAS DE CONCRETO SIMPLE
02.07.03.01 CONCRETO f'c=175 kg/cm2
02.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
02.07.04 CONEXIONES DOMICILIARIA (63 UNID)
02.07.04.01 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN CONEXIONES
DOMICIALIARIAS
03 SERVICIO DE AGUA POTABLE MONTE SINAI
03.01 LINEA DE ADUCCION (1+473 KM)
03.01.01 TRABAJOS PRELIMINARES
03.01.01.01 LIMPIEZA MANUAL DE TERRENO
03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
03.01.02 MOVIMIENTO DE TIERRAS
03.01.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
03.01.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
03.01.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
03.01.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
03.01.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
03.01.03 INSTALACION DE TUBERIA
03.01.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO
03.01.04 PRUEBA DE CALIDAD
03.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
03.02 VALVULA DE AIRE (03 UND)
03.02.01 TRABAJOS PRELIMINARES
03.02.01.01 LIMPIEZA MANUAL DE TERRENO
03.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
03.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
03.02.02.03 ELIMINACION MATERAIL EXCEDENTE
03.02.03 OBRAS DE CONCRETO SIMPLE
03.02.03.01 CONCRETO f'c=175 kg/cm2
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
03.02.04 CURADO DE CONCRETO
03.02.04.01 CURADO CON PRODUCTO QUIMICO
03.02.05 REVOQUES Y ENLUCIDOS
03.02.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
03.02.06 CARPINTERIA METALICA
03.02.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
03.02.07 PINTURA
03.02.07.01 PINTURA ANTICORROCIVA A DOS MANOS
03.02.08 ACCESORIOS
03.02.08.01 ABRAZADERA PVC SP CON REDUCCION DN 63 MM A Ø 1"
03.03 VALVULA DE PURGA (01 UND)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA MANUAL DE TERRENO
03.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
03.03.02 MOVIMIENTO DE TIERRAS
03.03.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
03.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
03.03.02.03 ELIMINACION MATERAIL EXCEDENTE
03.03.03 OBRAS DE CONCRETO SIMPLE
03.03.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO
E=0.10m
03.03.03.02 CONCRETO f'c = 140 kg/cm2
03.03.04 OBRAS DE CONCRETO ESTRUCTURA
03.03.04.01 CONCRETO f'c=175 kg/cm2
03.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
03.03.05 CARPINTERIA METALICA
03.03.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
03.03.06 PINTURA
03.03.06.01 PINTURA LATEX SATINADO A DOS MANOS
03.03.07 ACCESORIOS
03.03.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
03.04 RESERVORIO MONTE SINAI V=25M3 (01UNID)
03.04.01 TRABAJOS PRELIMINARES
03.04.01.01 LIMPIEZA MANUAL DE TERRENO
03.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 CORTE C/MAQUINARIA EN TERRENO DE MATERIAL COMPACTO
03.04.02.02 REFINE Y NIVELACION DE PLATAFORMA
03.04.02.03 ELIMINACION MATERAIL EXCEDENTE
03.04.03 OBRAS DE CONCRETO SIMPLE
03.04.03.01 CONCRETO f'c=100 kg/cm2
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 CONCRETO f'c=210KG/CM2
03.04.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
03.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
03.04.05 CURADO DE CONCRETO
03.04.05.01 CURADO CON PRODUCTO QUIMICO
03.04.06 REVOQUES Y ENLUCIDOS
03.04.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
03.04.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
03.04.07 CARPINTERIA METALICA
03.04.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
03.04.07.02 ESCALERA INTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
03.04.07.03 ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
03.04.07.04 VENTILACION DE F°G° DE DN=75MM
03.04.08 PINTURA
03.04.08.01 PINTURA LATEX SATINADO A DOS MANOS
03.04.08.02 PINTURA ANTICORROCIVA A DOS MANOS
03.04.09 VALVULAS, ACCESORIOS Y TUBERIA
03.04.09.01 ACCESORIO P/INGRESO DE RESERVORIO DN 63MM
03.04.09.02 ACCESORIO P/SALIDA DE RESERVORIO
03.04.09.03 ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA
03.04.10 CASETA DE CLORACION (01 UND)
03.04.10.01 TRABAJOS PRELIMINARES
03.04.10.01.01 LIMPIEZA MANUAL DE TERRENO
03.04.10.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
03.04.10.02 MOVIMIENTO DE TIERRAS
03.04.10.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
03.04.10.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
03.04.10.02.03 ELIMINACION MATERAIL EXCEDENTE
03.04.10.03 OBRAS DE CONCRETO ARMADO
03.04.10.03.01 CONCRETO f'c=210KG/CM2
03.04.10.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
03.04.10.03.03 ENCOFRADO Y DESENCOFRADO NORMAL
03.04.10.04 CURADO DE CONCRETO
03.04.10.04.01 CURADO CON PRODUCTO QUIMICO
03.04.10.05 REVOQUES Y ENLUCIDOS
03.04.10.05.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
03.04.10.06 SUMINISTRO E INSTALACION DE ACCESORIOS
03.04.10.06.01 SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE CLORACION
03.04.11 CERCO PERIMETRICO (L=220.00 m)
03.04.11.01 TRABAJOS PRELIMINARES
03.04.11.01.01 LIMPIEZA MANUAL DE TERRENO
03.04.11.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
03.04.11.02 MOVIMIENTO DE TIERRAS
03.04.11.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
03.04.11.02.02 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
03.04.11.02.03 REFINE Y NIVELACION DE FONDO DE TERRENO
03.04.11.02.04 ELIMINACION MATERAIL EXCEDENTE
03.04.11.03 OBRAS DE CONCRETO SIMPLE
03.04.11.03.01 CONCRETO f'c=140 kg/cm2
03.04.11.04 CERCO PERIMETRICO CON MALLA OLIMPICA GALVANIZADA
03.04.11.04.01 MALLA OLIMPICA GALVANIZADA 2"X2" #12 DE h=1.43m CON MARCO ANGULAR
1 1/2"x1 1/2"x1/8"
03.04.11.04.02 PUERTA C/MALLA DE TUBO F°G° Ø=1 1/2", DE 4.0x1.80M.TIPO II
03.04.11.04.03 PINTURA ESMALTE EN PUERTAS Y VENTANAS A DOS MANOS
3.05 RED DE DISTRIBUCION MONTE SINAI (L=1+681.00m)
03.05.01 TRABAJOS PRELIMINARES
03.05.01.01 LIMPIEZA MANUAL DE TERRENO
03.05.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
03.05.02 MOVIMIENTO DE TIERRAS
03.05.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
03.05.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
03.05.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
03.05.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
03.05.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
03.05.03 INSTALACION DE TUBERIA
03.05.03.01 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2"
03.05.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
03.05.03.03 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1"
03.05.03.04 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2"
03.05.03.05 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO
03.05.04 PRUEBA DE CALIDAD
03.05.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
03.05.05 VALVULA DE AIRE (03 UND)
03.05.05.01 TRABAJOS PRELIMINARES
03.05.05.01.01 LIMPIEZA MANUAL DE TERRENO
03.05.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
03.05.05.02 MOVIMIENTO DE TIERRAS
03.05.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
03.05.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
03.05.05.02.03 ELIMINACION MATERAIL EXCEDENTE
03.05.05.03 OBRAS DE CONCRETO
03.05.05.03.01 CONCRETO f'c=175 kg/cm2
03.05.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
03.05.05.04 CURADO DE CONCRETO
03.05.05.04.01 CURADO CON PRODUCTO QUIMICO
03.05.05.05 REVOQUES Y ENLUCIDOS
03.05.05.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
03.05.05.06 CARPINTERIA METALICA
03.05.05.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
03.05.05.07 PINTURA
03.05.05.07.01 PINTURA ANTICORROCIVA A DOS MANOS
03.05.05.08 ACCESORIOS
03.05.05.08.01 ABRAZADERA PVC SP CON REDUCCION DN 50 MM A Ø 1"
03.05.06 VALVULA DE PURGA DISTR (04 UND)
03.05.06.01 TRABAJOS PRELIMINARES
03.05.06.01.01 LIMPIEZA MANUAL DE TERRENO
03.05.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
03.05.06.02 MOVIMIENTO DE TIERRAS
03.05.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
03.05.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
03.05.06.02.03 ELIMINACION MATERAIL EXCEDENTE
03.05.06.03 OBRAS DE CONCRETO SIMPLE
03.05.06.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO
E=0.10m
03.05.06.03.02 CONCRETO f'c = 140 kg/cm2
03.05.06.04 OBRAS DE CONCRETO ESTRUCTURA
03.05.06.04.01 CONCRETO f'c=175 kg/cm2
03.05.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
03.05.06.05 CARPINTERIA METALICA
03.05.06.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
03.05.06.06 PINTURA
03.05.06.06.01 PINTURA LATEX SATINADO A DOS MANOS
03.05.06.07 ACCESORIOS
03.05.06.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 50MM
03.05.07 VALVULA DE CONTROL (04 UND)
03.05.07.01 TRABAJOS PRELIMINARES
03.05.07.01.01 LIMPIEZA MANUAL DE TERRENO
03.05.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
03.05.07.02 MOVIMIENTO DE TIERRAS
03.05.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
03.05.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
03.05.07.02.03 ELIMINACION MATERAIL EXCEDENTE
03.05.07.03 OBRAS DE CONCRETO SIMPLE
03.05.07.03.01 CONCRETO f'c=175 kg/cm2
03.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
03.05.07.04 CARPINTERIA METALICA
03.05.07.04.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
03.05.07.05 PINTURA
03.05.07.05.01 PINTURA LATEX SATINADO A DOS MANOS
03.05.07.06 ACCESORIOS
03.05.07.06.01 ACCESORIOS V. CONTROL 1"
03.05.07.06.02 ACCESORIOS V. CONTROL 3/4"
03.06 CONEXIONES DOMICILIARIAS MONTE SINAI (88 UND)
03.06.01 TRABAJOS PRELIMINARES
03.06.01.01 LIMPIEZA MANUAL DE TERRENO
03.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
03.06.02 MOVIMIENTO DE TIERRAS
03.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
03.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
03.06.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
03.06.02.04 ELIMINACION MATERAIL EXCEDENTE
03.06.03 OBRAS DE CONCRETO SIMPLE
03.06.03.01 CONCRETO f'c=175 kg/cm2
03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
03.06.04 CONEXIONES DOMICILIARIA (88 UNID)
03.06.04.01 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN CONEXIONES
DOMICIALIARIAS
4 SERVICIO AGUA POTABLE PIRIARI
04.01 LINEA DE ADUCCION (3+120.00 KM)
04.01.01 TRABAJOS PRELIMINARES
04.01.01.01 LIMPIEZA MANUAL DE TERRENO
04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
04.01.02 MOVIMIENTO DE TIERRAS
04.01.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
04.01.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
04.01.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
04.01.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
04.01.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
04.01.03 INSTALACION DE TUBERIA
04.01.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 75MM C/ANILLO
04.01.04 PRUEBA DE CALIDAD
04.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
04.02 CAMARA ROMPE PRESION (01 UNID)
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA MANUAL DE TERRENO
04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
04.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
04.02.02.03 ELIMINACION MATERAIL EXCEDENTE
04.02.03 OBRAS DE CONCRETO SIMPLE
04.02.03.01 ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX 6", E=20m
04.02.03.02 CONCRETO f'c=100 kg/cm2
04.02.03.03 CONCRETO f'c=140 kg/cm2
04.02.03.04 ENCOFRADO Y DESENCOFRADO NORMAL
04.02.04 OBRAS DE CONCRETO ARMADO
04.02.04.01 CONCRETO f'c=210KG/CM2
04.02.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
04.02.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
04.02.05 CURADO DE CONCRETO
04.02.05.01 CURADO CON PRODUCTO QUIMICO
04.02.06 REVOQUES Y ENLUCIDOS
04.02.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
04.02.07 CARPINTERIA METALICA
04.02.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
04.02.08 PINTURA
04.02.08.01 PINTURA ANTICORROCIVA A DOS MANOS
04.02.09 ACCESORIOS
04.02.09.01 ACCESORIO DE CAMARA ROMPE PRESION
4.03 RESERVORIO DE PIRIARI V=10M3 (01UNID)
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA MANUAL DE TERRENO
04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 CORTE C/MAQUINARIA EN TERRENO DE MATERIAL COMPACTO
04.03.02.02 REFINE Y NIVELACION DE PLATAFORMA
04.03.02.03 ELIMINACION MATERAIL EXCEDENTE
04.03.03 OBRAS DE CONCRETO SIMPLE
04.03.03.01 CONCRETO f'c=100 kg/cm2
04.03.04 OBRAS DE CONCRETO ARMADO
04.03.04.01 CONCRETO f'c=210KG/CM2
04.03.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
04.03.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
04.03.05 CURADO DE CONCRETO
04.03.05.01 CURADO CON PRODUCTO QUIMICO
04.03.06 REVOQUES Y ENLUCIDOS
04.03.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
04.03.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
04.03.07 CARPINTERIA METALICA
04.03.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
04.03.07.02 ESCALERA INTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
04.03.07.03 ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
04.03.07.04 VENTILACION DE F°G° DE DN=75MM
04.03.08 PINTURA
04.03.08.01 PINTURA LATEX SATINADO A DOS MANOS
04.03.08.02 PINTURA ANTICORROCIVA A DOS MANOS
04.03.09 VALVULAS, ACCESORIOS Y TUBERIA
04.03.09.01 ACCESORIO P/INGRESO DE RESERVORIO DN 63MM
04.03.09.02 ACCESORIO P/SALIDA DE RESERVORIO
04.03.09.03 ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA
04.03.10 CASETA DE CLORACION (01 UND)
04.03.10.01 TRABAJOS PRELIMINARES
04.03.10.01.01 LIMPIEZA MANUAL DE TERRENO
04.03.10.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
04.03.10.02 MOVIMIENTO DE TIERRAS
04.03.10.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
04.03.10.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
04.03.10.02.03 ELIMINACION MATERAIL EXCEDENTE
04.03.10.03 OBRAS DE CONCRETO ARMADO
04.03.10.03.01 CONCRETO f'c=210KG/CM2
04.03.10.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
04.03.10.03.03 ENCOFRADO Y DESENCOFRADO NORMAL
04.03.10.04 CURADO DE CONCRETO
04.03.10.04.01 CURADO CON PRODUCTO QUIMICO
04.03.10.05 REVOQUES Y ENLUCIDOS
04.03.10.05.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
04.03.10.06 SUMINISTRO E INSTALACION DE ACCESORIOS
04.03.10.06.01 SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE CLORACION
4.04 CAMARA DE DISTRIBUCION DE CAUDALES 02 SALIDAS (01 UNID)
04.04.01 TRABAJOS PRELIMINARES
04.04.01.01 LIMPIEZA MANUAL DE TERRENO
04.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
04.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
04.04.02.03 ELIMINACION MATERAIL EXCEDENTE
04.04.03 OBRAS DE CONCRETO SIMPLE
04.04.03.01 CONCRETO f'c=100 kg/cm2
04.04.04 OBRAS DE CONCRETO ARMADO
04.04.04.01 CONCRETO f'c=210KG/CM2
04.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
04.04.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
04.04.05 CURADO DE CONCRETO
04.04.05.01 CURADO CON PRODUCTO QUIMICO
04.04.06 REVOQUES Y ENLUCIDOS
04.04.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
04.04.07 CARPINTERIA METALICA
04.04.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
04.04.08 PINTURA
04.04.08.01 PINTURA ANTICORROCIVA A DOS MANOS
04.04.09 ACCESORIOS
04.04.09.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
4.05 RED DE DISTRIBUCION PIRIARI (L=2+120.00 m)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA MANUAL DE TERRENO
04.05.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
04.05.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
04.05.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
04.05.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
04.05.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
04.05.03 INSTALACION DE TUBERIA
04.05.03.01 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2"
04.05.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
04.05.03.03 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1"
04.05.03.04 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2"
04.05.04 PRUEBA DE CALIDAD
04.05.04.01 DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA DE AGUA
04.05.05 VALVULA DE AIRE (03 UND)
04.05.05.01 TRABAJOS PRELIMINARES
04.05.05.01.01 LIMPIEZA MANUAL DE TERRENO
04.05.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
04.05.05.02 MOVIMIENTO DE TIERRAS
04.05.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
04.05.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
04.05.05.02.03 ELIMINACION MATERAIL EXCEDENTE
04.05.05.03 OBRAS DE CONCRETO SIMPLE
04.05.05.03.01 CONCRETO f'c=175 kg/cm2
04.05.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
04.05.05.04 CURADO DE CONCRETO
04.05.05.04.01 CURADO CON PRODUCTO QUIMICO
04.05.05.05 REVOQUES Y ENLUCIDOS
04.05.05.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
04.05.05.06 CARPINTERIA METALICA
04.05.05.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
04.05.05.07 PINTURA
04.05.05.07.01 PINTURA ANTICORROCIVA A DOS MANOS
04.05.05.08 ACCESORIOS
04.05.05.08.01 ABRAZADERA PVC SP CON REDUCCION DN 50 MM A Ø 1"
04.05.06 VALVULA DE PURGA (02 UND)
04.05.06.01 TRABAJOS PRELIMINARES
04.05.06.01.01 LIMPIEZA MANUAL DE TERRENO
04.05.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
04.05.06.02 MOVIMIENTO DE TIERRAS
04.05.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
04.05.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
04.05.06.02.03 ELIMINACION MATERAIL EXCEDENTE
04.05.06.03 OBRAS DE CONCRETO SIMPLE
04.05.06.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO
E=0.10m
04.05.06.03.02 CONCRETO f'c = 140 kg/cm2
04.05.06.04 OBRAS DE CONCRETO ESTRUCTURA
04.05.06.04.01 CONCRETO f'c=175 kg/cm2
04.05.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
04.05.06.05 CARPINTERIA METALICA
04.05.06.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
04.05.06.06 PINTURA
04.05.06.06.01 PINTURA LATEX SATINADO A DOS MANOS
04.05.06.07 ACCESORIOS
04.05.06.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 32 MM
04.05.07 VALVULA DE CONTROL (04 UND)
04.05.07.01 TRABAJOS PRELIMINARES
04.05.07.01.01 LIMPIEZA MANUAL DE TERRENO
04.05.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
04.05.07.02 MOVIMIENTO DE TIERRAS
04.05.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
04.05.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
04.05.07.02.03 ELIMINACION MATERAIL EXCEDENTE
04.05.07.03 OBRAS DE CONCRETO SIMPLE
04.05.07.03.01 CONCRETO f'c=175 kg/cm2
04.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
04.05.07.04 CARPINTERIA METALICA
04.05.07.04.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
04.05.07.05 PINTURA
04.05.07.05.01 PINTURA LATEX SATINADO A DOS MANOS
04.05.07.06 ACCESORIOS
04.05.07.06.01 ACCESORIOS V. CONTROL 1"
04.05.07.06.02 ACCESORIOS V. CONTROL 3/4"
4.06 CONEXIONES DOMICILIARIAS PIRIARI (35 UNID.)
04.06.01 TRABAJOS PRELIMINARES
04.06.01.01 LIMPIEZA MANUAL DE TERRENO
04.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
04.06.02 MOVIMIENTO DE TIERRAS
04.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
04.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
04.06.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
04.06.02.04 ELIMINACION MATERAIL EXCEDENTE
04.06.03 OBRAS DE CONCRETO SIMPLE
04.06.03.01 CONCRETO f'c=175 kg/cm2
04.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
04.06.04 CONEXIONES DOMICILIARIA (35 UNID)
04.06.04.01 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN CONEXIONES
DOMICIALIARIAS
5 SERVICIO DE AGUA POTABLE VISTA ALEGRE
5.01 LINEA DE CONDUCCION (2+760KM)
05.01.01 TRABAJOS PRELIMINARES
05.01.01.01 LIMPIEZA MANUAL DE TERRENO
05.01.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
05.01.02 MOVIMIENTO DE TIERRAS
05.01.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
05.01.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
05.01.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
05.01.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
05.01.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
05.01.03 INSTALACION DE TUBERIA
05.01.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 75MM C/ANILLO
05.01.04 PRUEBA DE CALIDAD
05.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
05.02 VALVULA DE AIRE (07 UND)
05.02.01 TRABAJOS PRELIMINARES
05.02.01.01 LIMPIEZA MANUAL DE TERRENO
05.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
05.02.02 MOVIMIENTO DE TIERRAS
05.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
05.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
05.02.02.03 ELIMINACION MATERAIL EXCEDENTE
05.02.03 OBRAS DE CONCRETO SIMPLE
05.02.03.01 CONCRETO f'c=175 kg/cm2
05.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
05.02.04 CURADO DE CONCRETO
05.02.04.01 CURADO CON PRODUCTO QUIMICO
05.02.05 REVOQUES Y ENLUCIDOS
05.02.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
05.02.06 CARPINTERIA METALICA
05.02.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
05.02.07 PINTURA
05.02.07.01 PINTURA ANTICORROCIVA A DOS MANOS
05.02.08 ACCESORIOS
05.02.08.01 ABRAZADERA PVC SP CON REDUCCION DN 63 MM A Ø 1"
05.03 VALVULA DE PURGA (06 UND)
05.03.01 TRABAJOS PRELIMINARES
05.03.01.01 LIMPIEZA MANUAL DE TERRENO
05.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
05.03.02 MOVIMIENTO DE TIERRAS
05.03.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
05.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
05.03.02.03 ELIMINACION MATERAIL EXCEDENTE
05.03.03 OBRAS DE CONCRETO SIMPLE
05.03.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO
E=0.10m
05.03.03.02 CONCRETO f'c = 140 kg/cm2
05.03.04 OBRAS DE CONCRETO ARMADO
05.03.04.01 CONCRETO f'c=175 kg/cm2
05.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
05.03.05 CARPINTERIA METALICA
05.03.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
05.03.06 PINTURA
05.03.06.01 PINTURA LATEX SATINADO A DOS MANOS
05.03.07 ACCESORIOS
05.03.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
5.04 CAMARA DE DISTRIBUCION DE CAUDALES 02 SALIDAS (01 UNID)
05.04.01 TRABAJOS PRELIMINARES
05.04.01.01 LIMPIEZA MANUAL DE TERRENO
05.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
05.04.02 MOVIMIENTO DE TIERRAS
05.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
05.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
05.04.02.03 ELIMINACION MATERAIL EXCEDENTE
05.04.03 OBRAS DE CONCRETO SIMPLE
05.04.03.01 CONCRETO f'c=100 kg/cm2
05.04.04 OBRAS DE CONCRETO ARMADO
05.04.04.01 CONCRETO f'c=210KG/CM2
05.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
05.04.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
05.04.05 CURADO DE CONCRETO
05.04.05.01 CURADO CON PRODUCTO QUIMICO
05.04.06 REVOQUES Y ENLUCIDOS
05.04.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
05.04.07 CARPINTERIA METALICA
05.04.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
05.04.08 PINTURA
05.04.08.01 PINTURA ANTICORROCIVA A DOS MANOS
05.04.09 ACCESORIOS
05.04.09.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
5.05 RESERVORIO DE VISTA ALEGRE V=8 M3 (01UNID)
05.05.01 TRABAJOS PRELIMINARES
05.05.01.01 LIMPIEZA MANUAL DE TERRENO
05.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
05.05.02 MOVIMIENTO DE TIERRAS
05.05.02.01 CORTE C/MAQUINARIA EN TERRENO DE MATERIAL COMPACTO
05.05.02.02 REFINE Y NIVELACION DE PLATAFORMA
05.05.02.03 ELIMINACION MATERAIL EXCEDENTE
05.05.03 OBRAS DE CONCRETO SIMPLE
05.05.03.01 CONCRETO f'c=100 kg/cm2
05.05.04 OBRAS DE CONCRETO ARMADO
05.05.04.01 CONCRETO f'c=210KG/CM2
05.05.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
05.05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
05.05.05 CURADO DE CONCRETO
05.05.05.01 CURADO CON PRODUCTO QUIMICO
05.05.06 REVOQUES Y ENLUCIDOS
05.05.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
05.05.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
05.05.07 CARPINTERIA METALICA
05.05.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
05.05.07.02 ESCALERA INTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
05.05.07.03 ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
05.05.07.04 VENTILACION DE F°G° DE DN=75MM
05.05.08 PINTURA
05.05.08.01 PINTURA LATEX SATINADO A DOS MANOS
05.05.08.02 PINTURA ANTICORROCIVA A DOS MANOS
05.05.09 VALVULAS, ACCESORIOS Y TUBERIA
05.05.09.01 ACCESORIO P/INGRESO DE RESERVORIO DN 63MM
05.05.09.02 ACCESORIO P/SALIDA DE RESERVORIO
05.05.09.03 ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA
05.05.10 CASETA DE CLORACION (01 UND)
05.05.10.01 TRABAJOS PRELIMINARES
05.05.10.01.01 LIMPIEZA MANUAL DE TERRENO
05.05.10.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
05.05.10.02 MOVIMIENTO DE TIERRAS
05.05.10.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
05.05.10.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
05.05.10.02.03 ELIMINACION MATERAIL EXCEDENTE
05.05.10.03 OBRAS DE CONCRETO ARMADO
05.05.10.03.01 CONCRETO f'c=210KG/CM2
05.05.10.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
05.05.10.03.03 ENCOFRADO Y DESENCOFRADO NORMAL
05.05.10.04 CURADO DE CONCRETO
05.05.10.04.01 CURADO CON PRODUCTO QUIMICO
05.05.10.05 REVOQUES Y ENLUCIDOS
05.05.10.05.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
05.05.10.06 SUMINISTRO E INSTALACION DE ACCESORIOS
05.05.10.06.01 SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE CLORACION
5.06 RED DE DISTRIBUCION VISTA ALEGRE (L=7+028.00 m)
05.06.01 TRABAJOS PRELIMINARES
05.06.01.01 LIMPIEZA MANUAL DE TERRENO
05.06.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
05.06.02 MOVIMIENTO DE TIERRAS
05.06.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
05.06.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
05.06.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
05.06.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
05.06.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
05.06.03 INSTALACION DE TUBERIA
05.06.03.01 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2"
05.06.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
05.06.03.03 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1"
05.06.03.04 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2"
05.06.03.05 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO
05.06.04 PRUEBA DE CALIDAD
05.06.04.01 DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA DE AGUA
05.06.05 VALVULA DE AIRE (02 UND)
05.06.05.01 TRABAJOS PRELIMINARES
05.06.05.01.01 LIMPIEZA MANUAL DE TERRENO
05.06.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
05.06.05.02 MOVIMIENTO DE TIERRAS
05.06.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
05.06.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
05.06.05.02.03 ELIMINACION MATERAIL EXCEDENTE
05.06.05.03 OBRAS DE CONCRETO ARMADO
05.06.05.03.01 CONCRETO f'c=175 kg/cm2
05.06.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
05.06.05.04 CURADO DE CONCRETO
05.06.05.04.01 CURADO CON PRODUCTO QUIMICO
05.06.05.05 REVOQUES Y ENLUCIDOS
05.06.05.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
05.06.05.06 CARPINTERIA METALICA
05.06.05.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
05.06.05.07 PINTURA
05.06.05.07.01 PINTURA ANTICORROCIVA A DOS MANOS
05.06.05.08 ACCESORIOS
05.06.05.08.01 ACCESORIOS VALVULA DE AIRE D=110MM
05.06.06 VALVULA DE PURGA (02 UND)
05.06.06.01 TRABAJOS PRELIMINARES
05.06.06.01.01 LIMPIEZA MANUAL DE TERRENO
05.06.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
05.06.06.02 MOVIMIENTO DE TIERRAS
05.06.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
05.06.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
05.06.06.02.03 ELIMINACION MATERAIL EXCEDENTE
05.06.06.03 OBRAS DE CONCRETO SIMPLE
05.06.06.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y
APISONADO E=0.10m
05.06.06.03.02 CONCRETO f'c = 140 kg/cm2
05.06.06.04 OBRAS DE CONCRETO ESTRUCTURA
05.06.06.04.01 CONCRETO f'c=175 kg/cm2
05.06.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
05.06.06.05 CARPINTERIA METALICA
05.06.06.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
05.06.06.06 PINTURA
05.06.06.06.01 PINTURA LATEX SATINADO A DOS MANOS
05.06.06.07 ACCESORIOS
05.06.06.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
05.06.07 VALVULA DE CONTROL (03 UND)
05.06.07.01 TRABAJOS PRELIMINARES
05.06.07.01.01 LIMPIEZA MANUAL DE TERRENO
05.06.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
05.06.07.02 MOVIMIENTO DE TIERRAS
05.06.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
05.06.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
05.06.07.02.03 ELIMINACION MATERAIL EXCEDENTE
05.06.07.03 OBRAS DE CONCRETO SIMPLE
05.06.07.03.01 CONCRETO f'c=175 kg/cm2
05.06.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
05.06.07.04 CARPINTERIA METALICA
05.06.07.04.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
05.06.07.05 PINTURA
05.06.07.05.01 PINTURA LATEX SATINADO A DOS MANOS
05.06.07.06 ACCESORIOS
05.06.07.06.01 ACCESORIOS V. CONTROL 1"
05.06.07.06.02 ACCESORIOS V. CONTROL 3/4"
5.07 CONEXIONES DOMICILIARIAS VISTA ALEGRE (48 UNID.)
05.07.01 TRABAJOS PRELIMINARES
05.07.01.01 LIMPIEZA MANUAL DE TERRENO
05.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
05.07.02 MOVIMIENTO DE TIERRAS
05.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
05.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
05.07.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
05.07.02.04 ELIMINACION MATERAIL EXCEDENTE
05.07.03 OBRAS DE CONCRETO SIMPLE
05.07.03.01 CONCRETO f'c=175 kg/cm2
05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
05.07.04 CONEXIONES DOMICILIARIA (48 UNID)
05.07.04.01 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN CONEXIONES
DOMICIALIARIAS
06 SERVICIO DE AGUA POTABLE RAMAL PIRIARI VISTA ALEGRE
6.01 LINEA DE ADUCCION RAMAL (1+649 KM)
06.01.01 TRABAJOS PRELIMINARES
06.01.01.01 LIMPIEZA MANUAL DE TERRENO
06.01.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
06.01.02 MOVIMIENTO DE TIERRAS
06.01.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
06.01.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
06.01.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
06.01.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
06.01.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
06.01.03 INSTALACION DE TUBERIA
06.01.03.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO
06.01.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2"
06.01.03.03 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1"
06.01.03.04 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
06.01.04 PRUEBA DE CALIDAD
06.01.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
06.02 VALVULA DE AIRE (02 UND)
06.02.01 TRABAJOS PRELIMINARES
06.02.01.01 LIMPIEZA MANUAL DE TERRENO
06.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
06.02.02 MOVIMIENTO DE TIERRAS
06.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
06.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
06.02.02.03 ELIMINACION MATERAIL EXCEDENTE
06.02.03 OBRAS DE CONCRETO SIMPLE
06.02.03.01 CONCRETO f'c=175 kg/cm2
06.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
06.02.04 CURADO DE CONCRETO
06.02.04.01 CURADO CON PRODUCTO QUIMICO
06.02.05 REVOQUES Y ENLUCIDOS
06.02.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
06.02.06 CARPINTERIA METALICA
06.02.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
06.02.07 PINTURA
06.02.07.01 PINTURA ANTICORROCIVA A DOS MANOS
06.02.08 ACCESORIOS
06.02.08.01 ACCESORIOS VALVULA DE AIRE D=63 MM
06.03 ------------------------------------------
06.04 CAMARA ROMPE PRESION (01 UNID)
06.04.01 TRABAJOS PRELIMINARES
06.04.01.01 LIMPIEZA MANUAL DE TERRENO
06.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
06.04.02 MOVIMIENTO DE TIERRAS
06.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
06.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
06.04.02.03 ELIMINACION MATERAIL EXCEDENTE
06.04.03 OBRAS DE CONCRETO SIMPLE
06.04.03.01 ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX 6", E=20m
06.04.03.02 CONCRETO f'c=100 kg/cm2
06.04.03.03 CONCRETO f'c=140 kg/cm2
06.04.03.04 ENCOFRADO Y DESENCOFRADO NORMAL
06.04.04 OBRAS DE CONCRETO ARMADO
06.04.04.01 CONCRETO f'c=210KG/CM2
06.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
06.04.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
06.04.05 CURADO DE CONCRETO
06.04.05.01 CURADO CON PRODUCTO QUIMICO
06.04.06 REVOQUES Y ENLUCIDOS
06.04.06.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
06.04.07 CARPINTERIA METALICA
06.04.07.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
06.04.08 PINTURA
06.04.08.01 PINTURA ANTICORROCIVA A DOS MANOS
06.04.09 ACCESORIOS
06.04.09.01 ACCESORIO DE CAMARA ROMPE PRESION
06.05 RED DE DISTRIBUCION RAMAL (L=2+575 m)
06.05.01 TRABAJOS PRELIMINARES
06.05.01.01 LIMPIEZA MANUAL DE TERRENO
06.05.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
06.05.02 MOVIMIENTO DE TIERRAS
06.05.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
06.05.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
06.05.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
06.05.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
06.05.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
06.05.03 INSTALACION DE TUBERIA
06.05.03.01 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2"
06.05.03.02 TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
06.05.04 PRUEBA DE CALIDAD
06.05.04.01 DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA DE AGUA
06.05.05 VALVULA DE AIRE (02 UND)
06.05.05.01 TRABAJOS PRELIMINARES
06.05.05.01.01 LIMPIEZA MANUAL DE TERRENO
06.05.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
06.05.05.02 MOVIMIENTO DE TIERRAS
06.05.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
06.05.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
06.05.05.02.03 ELIMINACION MATERAIL EXCEDENTE
06.05.05.03 OBRAS DE CONCRETO SIMPLE
06.05.05.03.01 CONCRETO f'c=175 kg/cm2
06.05.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
06.05.05.04 CURADO DE CONCRETO
06.05.05.04.01 CURADO CON PRODUCTO QUIMICO
06.05.05.05 REVOQUES Y ENLUCIDOS
06.05.05.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
06.05.05.06 CARPINTERIA METALICA
06.05.05.06.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
06.05.05.07 PINTURA
06.05.05.07.01 PINTURA ANTICORROCIVA A DOS MANOS
06.05.05.08 ACCESORIOS
06.05.05.08.01 ACCESORIOS VALVULA DE AIRE D=63MM
06.05.06 VALVULA DE PURGA (02 UND)
06.05.06.01 TRABAJOS PRELIMINARES
06.05.06.01.01 LIMPIEZA MANUAL DE TERRENO
06.05.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
06.05.06.02 MOVIMIENTO DE TIERRAS
06.05.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
06.05.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
06.05.06.02.03 ELIMINACION MATERAIL EXCEDENTE
06.05.06.03 OBRAS DE CONCRETO SIMPLE
06.05.06.03.01 ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO
E=0.10m
06.05.06.03.02 CONCRETO f'c = 140 kg/cm2
06.05.06.04 OBRAS DE CONCRETO ESTRUCTURA
06.05.06.04.01 CONCRETO f'c=175 kg/cm2
06.05.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
06.05.06.05 CARPINTERIA METALICA
06.05.06.05.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
06.05.06.06 PINTURA
06.05.06.06.01 PINTURA LATEX SATINADO A DOS MANOS
06.05.06.07 ACCESORIOS
06.05.06.07.01 ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
06.05.07 VALVULA DE CONTROL (04 UND)
06.05.07.01 TRABAJOS PRELIMINARES
06.05.07.01.01 LIMPIEZA MANUAL DE TERRENO
06.05.07.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
06.05.07.02 MOVIMIENTO DE TIERRAS
06.05.07.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
06.05.07.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
06.05.07.02.03 ELIMINACION MATERAIL EXCEDENTE
06.05.07.03 OBRAS DE CONCRETO SIMPLE
06.05.07.03.01 CONCRETO f'c=175 kg/cm2
06.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
06.05.07.04 CARPINTERIA METALICA
06.05.07.04.01 MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
06.05.07.05 PINTURA
06.05.07.05.01 PINTURA LATEX SATINADO A DOS MANOS
06.05.07.06 ACCESORIOS
06.05.07.06.01 ACCESORIOS V. CONTROL 1"
06.05.07.06.02 ACCESORIOS V. CONTROL 3/4"
06.06 CONEXIONES DOMICILIARIAS RAMAL (10 UNID.)
06.06.01 TRABAJOS PRELIMINARES
06.06.01.01 LIMPIEZA MANUAL DE TERRENO
06.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
06.06.02 MOVIMIENTO DE TIERRAS
06.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
06.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
06.06.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
06.06.02.04 ELIMINACION MATERAIL EXCEDENTE
06.06.03 OBRAS DE CONCRETO SIMPLE
06.06.03.01 CONCRETO f'c=175 kg/cm2
06.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
06.06.04 CONEXIONES DOMICILIARIA (10 UNID)
06.06.04.01 SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN CONEXIONES
DOMICIALIARIAS
07 SERVICIO DE ALCANTARILLADO SANITARIO MONTE SINAI (88 UND)
07.01 OBRAS PROVISIONALES
07.01.01 TRANSPORTE DE MATERIALES (ALCANTARILLADO)
07.01.02 MOVILIZACION FLETE DE MATERIALES (ALCANTARILLADO)
07.02 RED DE COLECTORES (L=1034.43 m)
07.02.01 TRABAJOS PRELIMINARES
07.02.01.01 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
07.02.01.02 LIMPIEZA MANUAL DE TERRENO
07.02.02 MOVIMIENTO DE TIERRAS
07.02.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
07.02.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
07.02.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
07.02.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
07.02.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
07.02.03 SUMINISTRO E INSTALACION DE TUBERIAS
07.02.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC S-20 NTP ISO 4435 DN 160MM
C/ANILLO
07.02.04 PRUEBA DE CALIDAD
07.02.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
07.03 RED DE EMISORES (L=421.21 m)
07.03.01 TRABAJOS PRELIMINARES
07.03.01.01 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
07.03.01.02 LIMPIEZA MANUAL DE TERRENO
07.03.01.03 SEÑALIZACION PARA LIMITES DE SEGURIDAD VIAL
07.03.02 MOVIMIENTO DE TIERRAS
07.03.02.01 EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
07.03.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
07.03.02.03 CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
07.03.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
07.03.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
07.03.03 SUMINISTRO E INSTALACION DE TUBERIAS
07.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC S-20 NTP ISO 4435 DN 160MM
C/ANILLO
07.03.04 PRUEBA DE CALIDAD
07.03.04.01 DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
07.04 BUZONES TIPO
07.04.01 BUZON DE ALCANTARILLADO TIPO I Øint=1.20, H=0.80 - 1.50m (14 und)
07.04.01.01 TRABAJOS PRELIMINARES
07.04.01.01.01 LIMPIEZA MANUAL DE TERRENO
07.04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA
07.04.01.02 MOVIMIENTO DE TIERRAS
07.04.01.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
07.04.01.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
07.04.01.02.03 PERFILADO MANUAL DE LAS PAREDES DE BUZONES
07.04.01.02.04 ELIMINACION MATERAIL EXCEDENTE
07.04.01.03 OBRAS DE CONCRETO SIMPLE
07.04.01.03.01 CONCRETO f'c=100 kg/cm2
07.04.01.03.02 CONCRETO f'c=140 kg/cm2,
07.04.01.03.03 CONCRETO f'c=175 kg/cm2
07.04.01.03.04 ENCOFRADO Y DESENCOFRADO NORMAL
07.04.01.04 OBRAS DE CONCRETO ARMADO
07.04.01.04.01 CONCRETO f'c=210KG/CM2
07.04.01.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
07.04.01.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
07.04.01.04.04 MARCO DE FIERRO FUNDIDO Y PLATINA DE DE BORDE TAPA (segun diseño)
07.04.01.05 REVOQUES
07.04.01.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
07.04.02 BUZON DE ALCANTARILLADO TIPO II Øint=1.20 H=1.50m - 3.00m (05 und)
07.04.02.01 TRABAJOS PRELIMINARES
07.04.02.01.01 LIMPIEZA MANUAL DE TERRENO
07.04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA
07.04.02.02 MOVIMIENTO DE TIERRAS
07.04.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
07.04.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
07.04.02.02.03 PERFILADO MANUAL DE LAS PAREDES DE BUZONES
07.04.02.02.04 ELIMINACION MATERAIL EXCEDENTE
07.04.02.03 OBRAS DE CONCRETO SIMPLE
07.04.02.03.01 CONCRETO f'c=100 kg/cm2
07.04.02.03.02 CONCRETO f'c=140 kg/cm2,
07.04.02.03.03 CONCRETO f'c=175 kg/cm2
07.04.02.04 ENCOFRADO Y DESENCOFRADO NORMAL
07.04.02.05 OBRAS DE CONCRETO ARMADO
07.04.02.05.01 CONCRETO f'c=210KG/CM2
07.04.02.05.02 ENCOFRADO Y DESENCOFRADO NORMAL
07.04.02.05.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
07.04.02.05.04 MARCO DE FIERRO FUNDIDO Y PLATINA DE DE BORDE TAPA (segun diseño)
07.04.02.06 REVOQUES
07.04.02.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
07.04.03 BUZON DE ALCANTARILLADO TIPO III Øint=1.20m H=MAYORES A 5.0m (06 und)
07.04.03.01 TRABAJOS PRELIMINARES
07.04.03.01.01 LIMPIEZA MANUAL DE TERRENO
07.04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA
07.04.03.02 MOVIMIENTO DE TIERRAS
07.04.03.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
07.04.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
07.04.03.02.03 PERFILADO MANUAL DE LAS PAREDES DE BUZONES
07.04.03.02.04 ELIMINACION MATERAIL EXCEDENTE
07.04.03.03 OBRAS DE CONCRETO SIMPLE
07.04.03.03.01 CONCRETO f'c=100 kg/cm2
07.04.03.03.02 CONCRETO f'c=140 kg/cm2,
07.04.03.03.03 CONCRETO f'c=175 kg/cm2
07.04.03.03.04 ENCOFRADO Y DESENCOFRADO NORMAL
07.04.03.04 OBRAS DE CONCRETO ARMADO
07.04.03.04.01 CONCRETO f'c=210KG/CM2
07.04.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL
07.04.03.04.03 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
07.04.03.04.04 MARCO DE FIERRO FUNDIDO Y PLATINA DE DE BORDE TAPA (segun diseño)
07.04.03.05 REVOQUES
07.04.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
7.05 INSTALACION DE CONEXION DOMICILIARIA (88 UNID.)
07.05.01 TRABAJOS PRELIMINARES
07.05.01.01 LIMPIEZA MANUAL DE TERRENO
07.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
07.05.02 MOVIMIENTO DE TIERRAS
07.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
07.05.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
07.05.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
07.05.02.04 ELIMINACION MATERAIL EXCEDENTE
07.05.03 OBRAS DE CONCRETO SIMPLE
07.05.03.01 CONCRETO f'c=175 kg/cm2
07.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL
07.05.04 CONEXIONES DOMICILIARIA (88 UNID)
07.05.04.01 CONEXION DE DESAGUE D= 160 MM TERRENO SEMIROC. HASTA 4.00M
08 SERVICIO DE SANEAMIENTO BASICO
08.01 UNIDAD BASICA UNINI (63 UND)
08.01.01 CASETA
08.01.01.01 TRABAJOS PRELIMINARES
08.01.01.01.01 LIMPIEZA MANUAL DE TERRENO
08.01.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
08.01.01.02 CIMIENTO CORRIDO
08.01.01.02.01 MOVIMIENTO DE TIERRAS
08.01.01.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.01.01.02.01.02 ELIMINACION MATERAIL EXCEDENTE
08.01.01.02.02 OBRAS DE CONCRETO SIMPLE
08.01.01.02.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO CORRIDO
08.01.01.02.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO
08.01.01.02.02.03 CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE CIMIENTO
08.01.01.02.02.04 ENCOFRADO Y DESENCOFRADO NORMAL
08.01.01.02.02.05 SARDINEL DE DUCHA h=0.20 m
08.01.01.03 LOSA PISO
08.01.01.03.01 MOVIMIENTO DE TIERRAS
08.01.01.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.01.01.03.01.02 ELIMINACION MATERAIL EXCEDENTE
08.01.01.03.01.03 REFINE Y NIVELACION PARA LOSA
08.01.01.03.02 OBRAS DE CONCRETO ARMADO
08.01.01.03.02.01 ENCOFRADO Y DESENCOFRADO NORMAL
08.01.01.03.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.01.01.03.02.03 CONCRETO f'c=210KG/CM2
08.01.01.04 MUROS Y COLUMNAS
08.01.01.04.01 OBRAS DE CONCRETO ARMADO
08.01.01.04.01.01 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS
08.01.01.04.01.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.01.01.04.01.03 CONCRETO f'c=210KG/CM2 PARA COLUMNETAS
08.01.01.04.02 MUROS Y TABIQUERIA
08.01.01.04.02.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
08.01.01.04.03 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.01.04.03.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
08.01.01.04.03.02 TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm ACABADO PULIDO
08.01.01.04.04 PISOS Y PAVIMENTO
08.01.01.04.04.01 CONTRAPISO ACABADO PULIDO DE 2"
08.01.01.05 COBERTURAS
08.01.01.05.01 ESTRUCTURA DE MADERA
08.01.01.05.01.01 CORREAS DE MADERA TORNILLO DE 2"x2"
08.01.01.05.01.02 CORREAS DE MADERA TORNILLO DE 2"x3"
08.01.01.05.02 COBERTURAS LIVIANA DE CALAMINA
08.01.01.05.02.01 COBERTURA CON CALAMINA GALVANIZADA
08.01.01.06 PUERTAS Y VENTANAS
08.01.01.06.01 CARPINTERIA DE MADERA
08.01.01.06.01.01 MARCO Y PUERTA DE MADERA C/ CALAMINA GALVANIZADA
08.01.01.06.01.02 VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 X 0.80)
08.01.01.06.02 CERRAJERIA
08.01.01.06.02.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2"
08.01.01.06.02.02 CERRADURA TIPO PERILLA ALUMINIO 60mm
08.01.01.07 LAVADERO DOMICIARIO
08.01.01.07.01 MOVIMIENTO DE TIERRAS
08.01.01.07.01.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
08.01.01.07.01.02 ELIMINACION MATERAIL EXCEDENTE
08.01.01.07.02 OBRAS DE CONCRETO SIMPLE
08.01.01.07.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO LAVADERO
08.01.01.07.02.02 CONTRAPISO e=4 cm.ACABADO TIPO VEREDA
08.01.01.07.03 OBRAS DE CONCRETO ARMADO
08.01.01.07.03.01 CONCRETO f'c=175 kg/cm2
08.01.01.07.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.01.01.07.03.03 ENCOFRADO Y DESENCOFRADO NORMAL
08.01.01.07.04 MUROS Y TABIQUERIA
08.01.01.07.04.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
08.01.01.07.05 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.01.07.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
08.01.01.08 INSTALACIONES SANITARIAS AGUA
08.01.01.08.01 APARATOS Y ACCESORIOS SANITARIO
08.01.01.08.01.01 INODORO TANQUE BAJO INC./COLOCACION
08.01.01.08.01.02 LAVADERO DE PARED
08.01.01.08.01.03 DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE MEZCLADORA
08.01.01.08.01.04 CODO PVC SAL 2"x90º
08.01.01.08.01.05 CODO PVC SAL 2"x45º
08.01.01.08.01.06 TEE PVC SAL 2"
08.01.01.08.01.07 YEE PVC SAL 2"
08.01.01.08.01.08 SALIDA DE PVC SAL DE VENTILACION DE 2"
08.01.01.08.01.09 SUMIDERO DE BRONCE ROSCADO 2"
08.01.01.08.01.10 REGISTRO DE BRONCE 2"
08.01.01.08.02 ACCESORIO DE AGUA
08.01.01.08.02.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2"
08.01.01.08.02.02 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2"
08.01.01.08.02.03 TEE PVC SP 1/2"
08.01.01.08.02.04 CODO PVC SP 1/2"x90º
08.01.01.08.02.05 UNION UNIVERSAL PVC 1/2"
08.01.01.08.02.06 NIPLE C/ROSCA DE F°G° 1/2", L=1"
08.01.01.08.02.07 ADAPTADOR C/ROSCA PVC 1/2"
08.01.01.08.02.08 VALVULA COMPUERTA DE BRONCE 1/2"
08.01.01.08.02.09 VALVULA ESFERICA DE 1/2"
08.01.01.08.02.10 GRIFO BRONCE DE 1/2"
08.01.02 EVACUACION DE AGUAS RESIDUALES
08.01.02.01 TRABAJOS PRELIMINARES
08.01.02.01.01 LIMPIEZA MANUAL DE TERRENO
08.01.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
08.01.02.02 SISTEMA DE AGUAS GRISES
08.01.02.02.01 TRAMPA DE NATAS Y SOLIDOS
08.01.02.02.01.01 MOVIMIENTO DE TIERRAS
08.01.02.02.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.01.02.02.01.01.02 REFINE Y NIVELACION PARA LOSA
08.01.02.02.01.01.03 ELIMINACION MATERAIL EXCEDENTE
08.01.02.02.01.02 OBRAS DE CONCRETO ARMADO
08.01.02.02.01.02.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.01.02.02.01.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.01.02.02.01.02.03 CONCRETO f'c=210KG/CM2
08.01.02.02.01.03 CURADO DE CONCRETO
08.01.02.02.01.03.01 CURADO CON PRODUCTO QUIMICO
08.01.02.02.01.04 REVOQUES Y ENLUCIDOS
08.01.02.02.01.04.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.01.02.02.01.05 PINTURA
08.01.02.02.01.05.01 PINTURA ANTICORROCIVA A DOS MANOS
08.01.02.02.01.06 ACCESORIOS
08.01.02.02.01.06.01 TEE PVC SAL 2"
08.01.02.02.02 RED DE DESAGÜE 2"
08.01.02.02.02.01 EXCAVACION A MANO EN TERRENO NORMAL
08.01.02.02.02.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO
08.01.02.02.02.03 SUMINISTRO Y COLOCACION TUBERIA PVC DE 2"
08.01.02.03 SISTEMA DE AGUAS NEGRAS
08.01.02.03.01 CAJA DE REGISTRO
08.01.02.03.01.01 MOVIMIENTO DE TIERRAS
08.01.02.03.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.01.02.03.01.01.02 REFINE Y NIVELACION PARA LOSA
08.01.02.03.01.01.03 ELIMINACION MATERAIL EXCEDENTE
08.01.02.03.01.02 OBRAS DE CONCRETO SIMPLE
08.01.02.03.01.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.01.02.03.01.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.01.02.03.01.03 OBRAS DE CONCRETO ARMADO
08.01.02.03.01.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.01.02.03.01.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.01.02.03.01.03.03 CONCRETO f'c=210KG/CM2
08.01.02.03.01.04 CURADO DE CONCRETO
08.01.02.03.01.04.01 CURADO CON PRODUCTO QUIMICO
08.01.02.03.01.05 REVOQUES Y ENLUCIDOS
08.01.02.03.01.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.01.02.03.01.06 PINTURA
08.01.02.03.01.06.01 PINTURA ANTICORROCIVA A DOS MANOS
08.01.02.03.02 SUMINISTRO E INSTALACION BIODIGESTOR
08.01.02.03.02.01 MOVIMIENTO DE TIERRAS
08.01.02.03.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.01.02.03.02.01.02 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
08.01.02.03.02.01.03 ELIMINACION MATERAIL EXCEDENTE
08.01.02.03.02.02 OBRAS DE CONCRETO SIMPLE
08.01.02.03.02.02.01 SOLADO e=4", CONCRETO C:H, 1:10
08.01.02.03.02.03 ACCESORIOS
08.01.02.03.02.03.01 BIODIGESTOR AUTOLIMPIABLE V=750 lts
08.01.02.03.03 REGISTRO DE LODOS
08.01.02.03.03.01 MOVIMIENTO DE TIERRAS
08.01.02.03.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.01.02.03.03.01.02 REFINE Y NIVELACION PARA LOSA
08.01.02.03.03.01.03 ELIMINACION MATERAIL EXCEDENTE
08.01.02.03.03.02 OBRAS DE CONCRETO SIMPLE
08.01.02.03.03.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.01.02.03.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.01.02.03.03.03 OBRAS DE CONCRETO ARMADO
08.01.02.03.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL
08.01.02.03.03.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.01.02.03.03.03.03 CONCRETO f'c=210KG/CM2
08.01.02.03.03.04 CURADO DE CONCRETO
08.01.02.03.03.04.01 CURADO CON PRODUCTO QUIMICO
08.01.02.03.03.05 REVOQUES Y ENLUCIDOS
08.01.02.03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.01.02.03.03.06 ACCESORIOS
08.01.02.03.03.06.01 ADAPTADOR C/ROSCA PVC 2"
08.01.02.03.03.06.02 UNION UNIVERSAL DE PVC SP 2"
08.01.02.03.03.06.03 VALVULA COMPUERTA DE BRONCE 2"
08.01.02.03.04 RED DE DESAGÚE 4"
08.01.02.03.04.01 EXCAVACION A MANO EN TERRENO NORMAL
08.01.02.03.04.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO
08.01.02.03.04.03 SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4"
08.01.02.03.05 CAJA DISTRIBUIDORA DE CAUDALES
08.01.02.03.05.01 MOVIMIENTO DE TIERRAS
08.01.02.03.05.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.01.02.03.05.01.02 REFINE Y NIVELACION PARA LOSA
08.01.02.03.05.01.03 ELIMINACION MATERAIL EXCEDENTE
08.01.02.03.05.02 OBRAS DE CONCRETO SIMPLE
08.01.02.03.05.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.01.02.03.05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.01.02.03.05.03 OBRAS DE CONCRETO ARMADO
08.01.02.03.05.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.01.02.03.05.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.01.02.03.05.03.03 CONCRETO f'c=210KG/CM2
08.01.02.03.05.04 CURADO DE CONCRETO
08.01.02.03.05.04.01 CURADO CON PRODUCTO QUIMICO
08.01.02.03.05.05 REVOQUES Y ENLUCIDOS
08.01.02.03.05.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.01.02.03.05.06 PINTURA
08.01.02.03.05.06.01 PINTURA ANTICORROCIVA A DOS MANOS
08.01.02.04 ZANJAS DE INFILTRACION
08.01.02.04.01 MOVIMIENTO DE TIERRAS
08.01.02.04.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.01.02.04.01.02 REFINE Y NIVELACION FONDO ZANJA
08.01.02.04.01.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
08.01.02.04.01.04 ELIMINACION MATERAIL EXCEDENTE
08.01.02.04.02 RELLENO CON MATERIAL SELECCIONADO
08.01.02.04.02.01 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - 2"
08.01.02.04.02.02 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 1/2" - 2"
08.01.02.04.02.03 RELLENO CON MATERIAL PROPIO
08.01.02.04.03 ACCESORIOS
08.01.02.04.03.01 MATERIAL INFILTRANTE EN ZANJAS
08.01.02.04.03.02 TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO
08.02 UNIDAD BASICA PIRIARI (35 UND)
08.02.01 CASETA
08.02.01.01 TRABAJOS PRELIMINARES
08.02.01.01.01 LIMPIEZA MANUAL DE TERRENO
08.02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
08.02.01.02 CIMIENTO CORRIDO
08.02.01.02.01 MOVIMIENTO DE TIERRAS
08.02.01.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.02.01.02.01.02 ELIMINACION MATERAIL EXCEDENTE
08.02.01.02.02 OBRAS DE CONCRETO SIMPLE
08.02.01.02.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO CORRIDO
08.02.01.02.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO
08.02.01.02.02.03 CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE CIMIENTO
08.02.01.02.02.04 ENCOFRADO Y DESENCOFRADO NORMAL
08.02.01.02.02.05 SARDINEL DE DUCHA h=0.20 m
08.02.01.03 LOSA PISO
08.02.01.03.01 MOVIMIENTO DE TIERRAS
08.02.01.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.02.01.03.01.02 ELIMINACION MATERAIL EXCEDENTE
08.02.01.03.01.03 REFINE Y NIVELACION PARA LOSA
08.02.01.03.02 OBRAS DE CONCRETO ARMADO
08.02.01.03.02.01 ENCOFRADO Y DESENCOFRADO NORMAL
08.02.01.03.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.02.01.03.02.03 CONCRETO f'c=210KG/CM2
08.02.01.04 MUROS Y COLUMNAS
08.02.01.04.01 OBRAS DE CONCRETO ARMADO
08.02.01.04.01.01 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS
08.02.01.04.01.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.02.01.04.01.03 CONCRETO f'c=210KG/CM2 PARA COLUMNETAS
08.02.01.04.02 MUROS Y TABIQUERIA
08.02.01.04.02.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
08.02.01.04.03 REVOQUES ENLUCIDOS Y MOLDURAS
08.02.01.04.03.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
08.02.01.04.03.02 TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm ACABADO PULIDO
08.02.01.04.04 PISOS Y PAVIMENTO
08.02.01.04.04.01 CONTRAPISO ACABADO PULIDO DE 2"
08.02.01.05 COBERTURAS
08.02.01.05.01 ESTRUCTURA DE MADERA
08.02.01.05.01.01 CORREAS DE MADERA TORNILLO DE 2"x2"
08.02.01.05.01.02 CORREAS DE MADERA TORNILLO DE 2"x3"
08.02.01.05.02 COBERTURAS LIVIANA DE CALAMINA
08.02.01.05.02.01 COBERTURA CON CALAMINA GALVANIZADA
08.02.01.06 PUERTAS Y VENTANAS
08.02.01.06.01 CARPINTERIA DE MADERA
08.02.01.06.01.01 MARCO Y PUERTA DE MADERA C/ CALAMINA GALVANIZADA
08.02.01.06.01.02 VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 X 0.80)
08.02.01.06.02 CERRAJERIA
08.02.01.06.02.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2"
08.02.01.06.02.02 CERRADURA TIPO PERILLA ALUMINIO 60mm
08.02.01.07 LAVADERO DOMICIARIO
08.02.01.07.01 MOVIMIENTO DE TIERRAS
08.02.01.07.01.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
08.02.01.07.01.02 ELIMINACION MATERAIL EXCEDENTE
08.02.01.07.02 OBRAS DE CONCRETO SIMPLE
08.02.01.07.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO LAVADERO
08.02.01.07.02.02 CONTRAPISO e=4 cm.ACABADO TIPO VEREDA
08.02.01.07.03 OBRAS DE CONCRETO ARMADO
08.02.01.07.03.01 CONCRETO f'c=175 kg/cm2
08.02.01.07.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.02.01.07.03.03 ENCOFRADO Y DESENCOFRADO NORMAL
08.02.01.07.04 MUROS Y TABIQUERIA
08.02.01.07.04.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
08.02.01.07.05 REVOQUES ENLUCIDOS Y MOLDURAS
08.02.01.07.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
08.02.01.08 INSTALACIONES SANITARIAS AGUA
08.02.01.08.01 APARATOS Y ACCESORIOS SANITARIO
08.02.01.08.01.01 INODORO TANQUE BAJO INC./COLOCACION
08.02.01.08.01.02 LAVADERO DE PARED
08.02.01.08.01.03 DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE MEZCLADORA
08.02.01.08.01.04 CODO PVC SAL 2"x90º
08.02.01.08.01.05 CODO PVC SAL 2"x45º
08.02.01.08.01.06 TEE PVC SAL 2"
08.02.01.08.01.07 YEE PVC SAL 2"
08.02.01.08.01.08 SALIDA DE PVC SAL DE VENTILACION DE 2"
08.02.01.08.01.09 SUMIDERO DE BRONCE ROSCADO 2"
08.02.01.08.01.10 REGISTRO DE BRONCE 2"
08.02.01.08.02 ACCESORIO DE AGUA
08.02.01.08.02.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2"
08.02.01.08.02.02 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2"
08.02.01.08.02.03 TEE PVC SP 1/2"
08.02.01.08.02.04 CODO PVC SP 1/2"x90º
08.02.01.08.02.05 UNION UNIVERSAL PVC 1/2"
08.02.01.08.02.06 NIPLE C/ROSCA DE F°G° 1/2", L=1"
08.02.01.08.02.07 ADAPTADOR C/ROSCA PVC 1/2"
08.02.01.08.02.08 VALVULA COMPUERTA DE BRONCE 1/2"
08.02.01.08.02.09 VALVULA ESFERICA DE 1/2"
08.02.01.08.02.10 GRIFO BRONCE DE 1/2"
08.02.02 EVACUACION DE AGUAS RESIDUALES
08.02.02.01 TRABAJOS PRELIMINARES
08.02.02.01.01 LIMPIEZA MANUAL DE TERRENO
08.02.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
08.02.02.02 SISTEMA DE AGUAS GRISES
08.02.02.02.01 TRAMPA DE NATAS Y SOLIDOS
08.02.02.02.01.01 MOVIMIENTO DE TIERRAS
08.02.02.02.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.02.02.02.01.01.02 REFINE Y NIVELACION PARA LOSA
08.02.02.02.01.01.03 ELIMINACION MATERAIL EXCEDENTE
08.02.02.02.01.02 OBRAS DE CONCRETO ARMADO
08.02.02.02.01.02.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.02.02.02.01.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.02.02.02.01.02.03 CONCRETO f'c=210KG/CM2
08.02.02.02.01.03 CURADO DE CONCRETO
08.02.02.02.01.03.01 CURADO CON PRODUCTO QUIMICO
08.02.02.02.01.04 REVOQUES Y ENLUCIDOS
08.02.02.02.01.04.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.02.02.02.01.05 PINTURA
08.02.02.02.01.05.01 PINTURA ANTICORROCIVA A DOS MANOS
08.02.02.02.01.06 ACCESORIOS
08.02.02.02.01.06.01 TEE PVC SAL 2"
08.02.02.02.02 RED DE DESAGÜE 2"
08.02.02.02.02.01 EXCAVACION A MANO EN TERRENO NORMAL
08.02.02.02.02.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO
08.02.02.02.02.03 SUMINISTRO Y COLOCACION TUBERIA PVC DE 2"
08.02.02.03 SISTEMA DE AGUAS NEGRAS
08.02.02.03.01 CAJA DE REGISTRO
08.02.02.03.01.01 MOVIMIENTO DE TIERRAS
08.02.02.03.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.02.02.03.01.01.02 REFINE Y NIVELACION PARA LOSA
08.02.02.03.01.01.03 ELIMINACION MATERAIL EXCEDENTE
08.02.02.03.01.02 OBRAS DE CONCRETO SIMPLE
08.02.02.03.01.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.02.02.03.01.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.02.02.03.01.03 OBRAS DE CONCRETO ARMADO
08.02.02.03.01.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.02.02.03.01.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.02.02.03.01.03.03 CONCRETO f'c=210KG/CM2
08.02.02.03.01.04 CURADO DE CONCRETO
08.02.02.03.01.04.01 CURADO CON PRODUCTO QUIMICO
08.02.02.03.01.05 REVOQUES Y ENLUCIDOS
08.02.02.03.01.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.02.02.03.01.06 PINTURA
08.02.02.03.01.06.01 PINTURA ANTICORROCIVA A DOS MANOS
08.02.02.03.02 SUMINISTRO E INSTALACION BIODIGESTOR
08.02.02.03.02.01 MOVIMIENTO DE TIERRAS
08.02.02.03.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.02.02.03.02.01.02 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
08.02.02.03.02.01.03 ELIMINACION MATERAIL EXCEDENTE
08.02.02.03.02.02 OBRAS DE CONCRETO SIMPLE
08.02.02.03.02.02.01 SOLADO e=4", CONCRETO C:H, 1:10
08.02.02.03.02.03 ACCESORIOS
08.02.02.03.02.03.01 BIODIGESTOR AUTOLIMPIABLE V=750 lts
08.02.02.03.03 REGISTRO DE LODOS
08.02.02.03.03.01 MOVIMIENTO DE TIERRAS
08.02.02.03.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.02.02.03.03.01.02 REFINE Y NIVELACION PARA LOSA
08.02.02.03.03.01.03 ELIMINACION MATERAIL EXCEDENTE
08.02.02.03.03.02 OBRAS DE CONCRETO SIMPLE
08.02.02.03.03.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.02.02.03.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.02.02.03.03.03 OBRAS DE CONCRETO ARMADO
08.02.02.03.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL
08.02.02.03.03.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.02.02.03.03.03.03 CONCRETO f'c=210KG/CM2
08.02.02.03.03.04 CURADO DE CONCRETO
08.02.02.03.03.04.01 CURADO CON PRODUCTO QUIMICO
08.02.02.03.03.05 REVOQUES Y ENLUCIDOS
08.02.02.03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.02.02.03.03.06 ACCESORIOS
08.02.02.03.03.06.01 ADAPTADOR C/ROSCA PVC 2"
08.02.02.03.03.06.02 UNION UNIVERSAL DE PVC SP 2"
08.02.02.03.03.06.03 VALVULA COMPUERTA DE BRONCE 2"
08.02.02.03.04 RED DE DESAGÚE 4"
08.02.02.03.04.01 EXCAVACION A MANO EN TERRENO NORMAL
08.02.02.03.04.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO
08.02.02.03.04.03 SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4"
08.02.02.03.05 CAJA DISTRIBUIDORA DE CAUDALES
08.02.02.03.05.01 MOVIMIENTO DE TIERRAS
08.02.02.03.05.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.02.02.03.05.01.02 REFINE Y NIVELACION PARA LOSA
08.02.02.03.05.01.03 ELIMINACION MATERAIL EXCEDENTE
08.02.02.03.05.02 OBRAS DE CONCRETO SIMPLE
08.02.02.03.05.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.02.02.03.05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.02.02.03.05.03 OBRAS DE CONCRETO ARMADO
08.02.02.03.05.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.02.02.03.05.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.02.02.03.05.03.03 CONCRETO f'c=210KG/CM2
08.02.02.03.05.04 CURADO DE CONCRETO
08.02.02.03.05.04.01 CURADO CON PRODUCTO QUIMICO
08.02.02.03.05.05 REVOQUES Y ENLUCIDOS
08.02.02.03.05.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.02.02.03.05.06 PINTURA
08.02.02.03.05.06.01 PINTURA ANTICORROCIVA A DOS MANOS
08.02.02.04 ZANJAS DE INFILTRACION
08.02.02.04.01 MOVIMIENTO DE TIERRAS
08.02.02.04.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.02.02.04.01.02 REFINE Y NIVELACION FONDO ZANJA
08.02.02.04.01.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
08.02.02.04.01.04 ELIMINACION MATERAIL EXCEDENTE
08.02.02.04.02 RELLENO CON MATERIAL SELECCIONADO
08.02.02.04.02.01 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - 2"
08.02.02.04.02.02 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 1/2" - 2"
08.02.02.04.02.03 RELLENO CON MATERIAL PROPIO
08.02.02.04.03 ACCESORIOS
08.02.02.04.03.01 MATERIAL INFILTRANTE EN ZANJAS
08.02.02.04.03.02 TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO
08.03 UNIDAD BASICA VISTA ALEGRE (48 UND)
08.03.01 CASETA
08.03.01.01 TRABAJOS PRELIMINARES
08.03.01.01.01 LIMPIEZA MANUAL DE TERRENO
08.03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
08.03.01.02 CIMIENTO CORRIDO
08.03.01.02.01 MOVIMIENTO DE TIERRAS
08.03.01.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.03.01.02.01.02 ELIMINACION MATERAIL EXCEDENTE
08.03.01.02.02 OBRAS DE CONCRETO SIMPLE
08.03.01.02.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO CORRIDO
08.03.01.02.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO
08.03.01.02.02.03 CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE CIMIENTO
08.03.01.02.02.04 ENCOFRADO Y DESENCOFRADO NORMAL
08.03.01.02.02.05 SARDINEL DE DUCHA h=0.20 m
08.03.01.03 LOSA PISO
08.03.01.03.01 MOVIMIENTO DE TIERRAS
08.03.01.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.03.01.03.01.02 ELIMINACION MATERAIL EXCEDENTE
08.03.01.03.01.03 REFINE Y NIVELACION PARA LOSA
08.03.01.03.02 OBRAS DE CONCRETO ARMADO
08.03.01.03.02.01 ENCOFRADO Y DESENCOFRADO NORMAL
08.03.01.03.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.03.01.03.02.03 CONCRETO f'c=210KG/CM2
08.03.01.04 MUROS Y COLUMNAS
08.03.01.04.01 OBRAS DE CONCRETO ARMADO
08.03.01.04.01.01 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS
08.03.01.04.01.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.03.01.04.01.03 CONCRETO f'c=210KG/CM2 PARA COLUMNETAS
08.03.01.04.02 MUROS Y TABIQUERIA
08.03.01.04.02.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
08.03.01.04.03 REVOQUES ENLUCIDOS Y MOLDURAS
08.03.01.04.03.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
08.03.01.04.03.02 TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm ACABADO PULIDO
08.03.01.04.04 PISOS Y PAVIMENTO
08.03.01.04.04.01 CONTRAPISO ACABADO PULIDO DE 2"
08.03.01.05 COBERTURAS
08.03.01.05.01 ESTRUCTURA DE MADERA
08.03.01.05.01.01 CORREAS DE MADERA TORNILLO DE 2"x2"
08.03.01.05.01.02 CORREAS DE MADERA TORNILLO DE 2"x3"
08.03.01.05.02 COBERTURAS LIVIANA DE CALAMINA
08.03.01.05.02.01 COBERTURA CON CALAMINA GALVANIZADA
08.03.01.06 PUERTAS Y VENTANAS
08.03.01.06.01 CARPINTERIA DE MADERA
08.03.01.06.01.01 MARCO Y PUERTA DE MADERA C/ CALAMINA GALVANIZADA
08.03.01.06.01.02 VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 X 0.80)
08.03.01.06.02 CERRAJERIA
08.03.01.06.02.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2"
08.03.01.06.02.02 CERRADURA TIPO PERILLA ALUMINIO 60mm
08.03.01.07 LAVADERO DOMICIARIO
08.03.01.07.01 MOVIMIENTO DE TIERRAS
08.03.01.07.01.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
08.03.01.07.01.02 ELIMINACION MATERAIL EXCEDENTE
08.03.01.07.02 OBRAS DE CONCRETO SIMPLE
08.03.01.07.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO LAVADERO
08.03.01.07.02.02 CONTRAPISO e=4 cm.ACABADO TIPO VEREDA
08.03.01.07.03 OBRAS DE CONCRETO ARMADO
08.03.01.07.03.01 CONCRETO f'c=175 kg/cm2
08.03.01.07.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.03.01.07.03.03 ENCOFRADO Y DESENCOFRADO NORMAL
08.03.01.07.04 MUROS Y TABIQUERIA
08.03.01.07.04.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
08.03.01.07.05 REVOQUES ENLUCIDOS Y MOLDURAS
08.03.01.07.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
08.03.01.08 INSTALACIONES SANITARIAS AGUA
08.03.01.08.01 APARATOS Y ACCESORIOS SANITARIO
08.03.01.08.01.01 INODORO TANQUE BAJO INC./COLOCACION
08.03.01.08.01.02 LAVADERO DE PARED
08.03.01.08.01.03 DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE MEZCLADORA
08.03.01.08.01.04 CODO PVC SAL 2"x90º
08.03.01.08.01.05 CODO PVC SAL 2"x45º
08.03.01.08.01.06 TEE PVC SAL 2"
08.03.01.08.01.07 YEE PVC SAL 2"
08.03.01.08.01.08 SALIDA DE PVC SAL DE VENTILACION DE 2"
08.03.01.08.01.09 SUMIDERO DE BRONCE ROSCADO 2"
08.03.01.08.01.10 REGISTRO DE BRONCE 2"
08.03.01.08.02 ACCESORIO DE AGUA
08.03.01.08.02.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2"
08.03.01.08.02.02 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2"
08.03.01.08.02.03 TEE PVC SP 1/2"
08.03.01.08.02.04 CODO PVC SP 1/2"x90º
08.03.01.08.02.05 UNION UNIVERSAL PVC 1/2"
08.03.01.08.02.06 NIPLE C/ROSCA DE F°G° 1/2", L=1"
08.03.01.08.02.07 ADAPTADOR C/ROSCA PVC 1/2"
08.03.01.08.02.08 VALVULA COMPUERTA DE BRONCE 1/2"
08.03.01.08.02.09 VALVULA ESFERICA DE 1/2"
08.03.01.08.02.10 GRIFO BRONCE DE 1/2"
08.03.02 EVACUACION DE AGUAS RESIDUALES
08.03.02.01 TRABAJOS PRELIMINARES
08.03.02.01.01 LIMPIEZA MANUAL DE TERRENO
08.03.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
08.03.02.02 SISTEMA DE AGUAS GRISES
08.03.02.02.01 TRAMPA DE NATAS Y SOLIDOS
08.03.02.02.01.01 MOVIMIENTO DE TIERRAS
08.03.02.02.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.03.02.02.01.01.02 REFINE Y NIVELACION PARA LOSA
08.03.02.02.01.01.03 ELIMINACION MATERAIL EXCEDENTE
08.03.02.02.01.02 OBRAS DE CONCRETO ARMADO
08.03.02.02.01.02.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.03.02.02.01.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.03.02.02.01.02.03 CONCRETO f'c=210KG/CM2
08.03.02.02.01.03 CURADO DE CONCRETO
08.03.02.02.01.03.01 CURADO CON PRODUCTO QUIMICO
08.03.02.02.01.04 REVOQUES Y ENLUCIDOS
08.03.02.02.01.04.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.03.02.02.01.05 PINTURA
08.03.02.02.01.05.01 PINTURA ANTICORROCIVA A DOS MANOS
08.03.02.02.01.06 ACCESORIOS
08.03.02.02.01.06.01 TEE PVC SAL 2"
08.03.02.02.02 RED DE DESAGÜE 2"
08.03.02.02.02.01 EXCAVACION A MANO EN TERRENO NORMAL
08.03.02.02.02.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO
08.03.02.02.02.03 SUMINISTRO Y COLOCACION TUBERIA PVC DE 2"
08.03.02.03 SISTEMA DE AGUAS NEGRAS
08.03.02.03.01 CAJA DE REGISTRO
08.03.02.03.01.01 MOVIMIENTO DE TIERRAS
08.03.02.03.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.03.02.03.01.01.02 REFINE Y NIVELACION PARA LOSA
08.03.02.03.01.01.03 ELIMINACION MATERAIL EXCEDENTE
08.03.02.03.01.02 OBRAS DE CONCRETO SIMPLE
08.03.02.03.01.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.03.02.03.01.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.03.02.03.01.03 OBRAS DE CONCRETO ARMADO
08.03.02.03.01.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.03.02.03.01.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.03.02.03.01.03.03 CONCRETO f'c=210KG/CM2
08.03.02.03.01.04 CURADO DE CONCRETO
08.03.02.03.01.04.01 CURADO CON PRODUCTO QUIMICO
08.03.02.03.01.05 REVOQUES Y ENLUCIDOS
08.03.02.03.01.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.03.02.03.01.06 PINTURA
08.03.02.03.01.06.01 PINTURA ANTICORROCIVA A DOS MANOS
08.03.02.03.02 SUMINISTRO E INSTALACION BIODIGESTOR
08.03.02.03.02.01 MOVIMIENTO DE TIERRAS
08.03.02.03.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.03.02.03.02.01.02 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
08.03.02.03.02.01.03 ELIMINACION MATERAIL EXCEDENTE
08.03.02.03.02.02 OBRAS DE CONCRETO SIMPLE
08.03.02.03.02.02.01 SOLADO e=4", CONCRETO C:H, 1:10
08.03.02.03.02.03 ACCESORIOS
08.03.02.03.02.03.01 BIODIGESTOR AUTOLIMPIABLE V=750 lts
08.03.02.03.03 REGISTRO DE LODOS
08.03.02.03.03.01 MOVIMIENTO DE TIERRAS
08.03.02.03.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.03.02.03.03.01.02 REFINE Y NIVELACION PARA LOSA
08.03.02.03.03.01.03 ELIMINACION MATERAIL EXCEDENTE
08.03.02.03.03.02 OBRAS DE CONCRETO SIMPLE
08.03.02.03.03.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.03.02.03.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.03.02.03.03.03 OBRAS DE CONCRETO ARMADO
08.03.02.03.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL
08.03.02.03.03.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.03.02.03.03.03.03 CONCRETO f'c=210KG/CM2
08.03.02.03.03.04 CURADO DE CONCRETO
08.03.02.03.03.04.01 CURADO CON PRODUCTO QUIMICO
08.03.02.03.03.05 REVOQUES Y ENLUCIDOS
08.03.02.03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.03.02.03.03.06 ACCESORIOS
08.03.02.03.03.06.01 ADAPTADOR C/ROSCA PVC 2"
08.03.02.03.03.06.02 UNION UNIVERSAL DE PVC SP 2"
08.03.02.03.03.06.03 VALVULA COMPUERTA DE BRONCE 2"
08.03.02.03.04 RED DE DESAGÚE 4"
08.03.02.03.04.01 EXCAVACION A MANO EN TERRENO NORMAL
08.03.02.03.04.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO
08.03.02.03.04.03 SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4"
08.03.02.03.05 CAJA DISTRIBUIDORA DE CAUDALES
08.03.02.03.05.01 MOVIMIENTO DE TIERRAS
08.03.02.03.05.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.03.02.03.05.01.02 REFINE Y NIVELACION PARA LOSA
08.03.02.03.05.01.03 ELIMINACION MATERAIL EXCEDENTE
08.03.02.03.05.02 OBRAS DE CONCRETO SIMPLE
08.03.02.03.05.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.03.02.03.05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.03.02.03.05.03 OBRAS DE CONCRETO ARMADO
08.03.02.03.05.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.03.02.03.05.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.03.02.03.05.03.03 CONCRETO f'c=210KG/CM2
08.03.02.03.05.04 CURADO DE CONCRETO
08.03.02.03.05.04.01 CURADO CON PRODUCTO QUIMICO
08.03.02.03.05.05 REVOQUES Y ENLUCIDOS
08.03.02.03.05.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.03.02.03.05.06 PINTURA
08.03.02.03.05.06.01 PINTURA ANTICORROCIVA A DOS MANOS
08.03.02.04 ZANJAS DE INFILTRACION
08.03.02.04.01 MOVIMIENTO DE TIERRAS
08.03.02.04.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.03.02.04.01.02 REFINE Y NIVELACION FONDO ZANJA
08.03.02.04.01.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
08.03.02.04.01.04 ELIMINACION MATERAIL EXCEDENTE
08.03.02.04.02 RELLENO CON MATERIAL SELECCIONADO
08.03.02.04.02.01 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - 2"
08.03.02.04.02.02 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 1/2" - 2"
08.03.02.04.02.03 RELLENO CON MATERIAL PROPIO
08.03.02.04.03 ACCESORIOS
08.03.02.04.03.01 MATERIAL INFILTRANTE EN ZANJAS
08.03.02.04.03.02 TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO
08.04 UNIDAD BASICA RAMAL (10 UND)
08.04.01 CASETA
08.04.01.01 TRABAJOS PRELIMINARES
08.04.01.01.01 LIMPIEZA MANUAL DE TERRENO
08.04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
08.04.01.02 CIMIENTO CORRIDO
08.04.01.02.01 MOVIMIENTO DE TIERRAS
08.04.01.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.04.01.02.01.02 ELIMINACION MATERAIL EXCEDENTE
08.04.01.02.02 OBRAS DE CONCRETO SIMPLE
08.04.01.02.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO CORRIDO
08.04.01.02.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO
08.04.01.02.02.03 CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE CIMIENTO
08.04.01.02.02.04 ENCOFRADO Y DESENCOFRADO NORMAL
08.04.01.02.02.05 SARDINEL DE DUCHA h=0.20 m
08.04.01.03 LOSA PISO
08.04.01.03.01 MOVIMIENTO DE TIERRAS
08.04.01.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.04.01.03.01.02 ELIMINACION MATERAIL EXCEDENTE
08.04.01.03.01.03 REFINE Y NIVELACION PARA LOSA
08.04.01.03.02 OBRAS DE CONCRETO ARMADO
08.04.01.03.02.01 ENCOFRADO Y DESENCOFRADO NORMAL
08.04.01.03.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.04.01.03.02.03 CONCRETO f'c=210KG/CM2
08.04.01.04 MUROS Y COLUMNAS
08.04.01.04.01 OBRAS DE CONCRETO ARMADO
08.04.01.04.01.01 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS
08.04.01.04.01.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.04.01.04.01.03 CONCRETO f'c=210KG/CM2 PARA COLUMNETAS
08.04.01.04.02 MUROS Y TABIQUERIA
08.04.01.04.02.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
08.04.01.04.03 REVOQUES ENLUCIDOS Y MOLDURAS
08.04.01.04.03.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
08.04.01.04.03.02 TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm ACABADO PULIDO
08.04.01.04.04 PISOS Y PAVIMENTO
08.04.01.04.04.01 CONTRAPISO ACABADO PULIDO DE 2"
08.04.01.05 COBERTURAS
08.04.01.05.01 ESTRUCTURA DE MADERA
08.04.01.05.01.01 CORREAS DE MADERA TORNILLO DE 2"x2"
08.04.01.05.01.02 CORREAS DE MADERA TORNILLO DE 2"x3"
08.04.01.05.02 COBERTURAS LIVIANA DE CALAMINA
08.04.01.05.02.01 COBERTURA CON CALAMINA GALVANIZADA
08.04.01.06 PUERTAS Y VENTANAS
08.04.01.06.01 CARPINTERIA DE MADERA
08.04.01.06.01.01 MARCO Y PUERTA DE MADERA C/ CALAMINA GALVANIZADA
08.04.01.06.01.02 VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 X 0.80)
08.04.01.06.02 CERRAJERIA
08.04.01.06.02.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2"
08.04.01.06.02.02 CERRADURA TIPO PERILLA ALUMINIO 60mm
08.04.01.07 LAVADERO DOMICIARIO
08.04.01.07.01 MOVIMIENTO DE TIERRAS
08.04.01.07.01.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
08.04.01.07.01.02 ELIMINACION MATERAIL EXCEDENTE
08.04.01.07.02 OBRAS DE CONCRETO SIMPLE
08.04.01.07.02.01 CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO LAVADERO
08.04.01.07.02.02 CONTRAPISO e=4 cm.ACABADO TIPO VEREDA
08.04.01.07.03 OBRAS DE CONCRETO ARMADO
08.04.01.07.03.01 CONCRETO f'c=175 kg/cm2
08.04.01.07.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.04.01.07.03.03 ENCOFRADO Y DESENCOFRADO NORMAL
08.04.01.07.04 MUROS Y TABIQUERIA
08.04.01.07.04.01 MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
08.04.01.07.05 REVOQUES ENLUCIDOS Y MOLDURAS
08.04.01.07.05.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
08.04.01.08 INSTALACIONES SANITARIAS AGUA
08.04.01.08.01 APARATOS Y ACCESORIOS SANITARIO
08.04.01.08.01.01 INODORO TANQUE BAJO INC./COLOCACION
08.04.01.08.01.02 LAVADERO DE PARED
08.04.01.08.01.03 DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE MEZCLADORA
08.04.01.08.01.04 CODO PVC SAL 2"x90º
08.04.01.08.01.05 CODO PVC SAL 2"x45º
08.04.01.08.01.06 TEE PVC SAL 2"
08.04.01.08.01.07 YEE PVC SAL 2"
08.04.01.08.01.08 SALIDA DE PVC SAL DE VENTILACION DE 2"
08.04.01.08.01.09 SUMIDERO DE BRONCE ROSCADO 2"
08.04.01.08.01.10 REGISTRO DE BRONCE 2"
08.04.01.08.02 ACCESORIO DE AGUA
08.04.01.08.02.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2"
08.04.01.08.02.02 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2"
08.04.01.08.02.03 TEE PVC SP 1/2"
08.04.01.08.02.04 CODO PVC SP 1/2"x90º
08.04.01.08.02.05 UNION UNIVERSAL PVC 1/2"
08.04.01.08.02.06 NIPLE C/ROSCA DE F°G° 1/2", L=1"
08.04.01.08.02.07 ADAPTADOR C/ROSCA PVC 1/2"
08.04.01.08.02.08 VALVULA COMPUERTA DE BRONCE 1/2"
08.04.01.08.02.09 VALVULA ESFERICA DE 1/2"
08.04.01.08.02.10 GRIFO BRONCE DE 1/2"
08.04.02 EVACUACION DE AGUAS RESIDUALES
08.04.02.01 TRABAJOS PRELIMINARES
08.04.02.01.01 LIMPIEZA MANUAL DE TERRENO
08.04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
08.04.02.02 SISTEMA DE AGUAS GRISES
08.04.02.02.01 TRAMPA DE NATAS Y SOLIDOS
08.04.02.02.01.01 MOVIMIENTO DE TIERRAS
08.04.02.02.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.04.02.02.01.01.02 REFINE Y NIVELACION PARA LOSA
08.04.02.02.01.01.03 ELIMINACION MATERAIL EXCEDENTE
08.04.02.02.01.02 OBRAS DE CONCRETO ARMADO
08.04.02.02.01.02.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.04.02.02.01.02.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.04.02.02.01.02.03 CONCRETO f'c=210KG/CM2
08.04.02.02.01.03 CURADO DE CONCRETO
08.04.02.02.01.03.01 CURADO CON PRODUCTO QUIMICO
08.04.02.02.01.04 REVOQUES Y ENLUCIDOS
08.04.02.02.01.04.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.04.02.02.01.05 PINTURA
08.04.02.02.01.05.01 PINTURA ANTICORROCIVA A DOS MANOS
08.04.02.02.01.06 ACCESORIOS
08.04.02.02.01.06.01 TEE PVC SAL 2"
08.04.02.02.02 RED DE DESAGÜE 2"
08.04.02.02.02.01 EXCAVACION A MANO EN TERRENO NORMAL
08.04.02.02.02.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO
08.04.02.02.02.03 SUMINISTRO Y COLOCACION TUBERIA PVC DE 2"
08.04.02.03 SISTEMA DE AGUAS NEGRAS
08.04.02.03.01 CAJA DE REGISTRO
08.04.02.03.01.01 MOVIMIENTO DE TIERRAS
08.04.02.03.01.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.04.02.03.01.01.02 REFINE Y NIVELACION PARA LOSA
08.04.02.03.01.01.03 ELIMINACION MATERAIL EXCEDENTE
08.04.02.03.01.02 OBRAS DE CONCRETO SIMPLE
08.04.02.03.01.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.04.02.03.01.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.04.02.03.01.03 OBRAS DE CONCRETO ARMADO
08.04.02.03.01.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.04.02.03.01.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.04.02.03.01.03.03 CONCRETO f'c=210KG/CM2
08.04.02.03.01.04 CURADO DE CONCRETO
08.04.02.03.01.04.01 CURADO CON PRODUCTO QUIMICO
08.04.02.03.01.05 REVOQUES Y ENLUCIDOS
08.04.02.03.01.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.04.02.03.01.06 PINTURA
08.04.02.03.01.06.01 PINTURA ANTICORROCIVA A DOS MANOS
08.04.02.03.02 SUMINISTRO E INSTALACION BIODIGESTOR
08.04.02.03.02.01 MOVIMIENTO DE TIERRAS
08.04.02.03.02.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.04.02.03.02.01.02 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
08.04.02.03.02.01.03 ELIMINACION MATERAIL EXCEDENTE
08.04.02.03.02.02 OBRAS DE CONCRETO SIMPLE
08.04.02.03.02.02.01 SOLADO e=4", CONCRETO C:H, 1:10
08.04.02.03.02.03 ACCESORIOS
08.04.02.03.02.03.01 BIODIGESTOR AUTOLIMPIABLE V=750 lts
08.04.02.03.03 REGISTRO DE LODOS
08.04.02.03.03.01 MOVIMIENTO DE TIERRAS
08.04.02.03.03.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.04.02.03.03.01.02 REFINE Y NIVELACION PARA LOSA
08.04.02.03.03.01.03 ELIMINACION MATERAIL EXCEDENTE
08.04.02.03.03.02 OBRAS DE CONCRETO SIMPLE
08.04.02.03.03.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.04.02.03.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.04.02.03.03.03 OBRAS DE CONCRETO ARMADO
08.04.02.03.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL
08.04.02.03.03.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.04.02.03.03.03.03 CONCRETO f'c=210KG/CM2
08.04.02.03.03.04 CURADO DE CONCRETO
08.04.02.03.03.04.01 CURADO CON PRODUCTO QUIMICO
08.04.02.03.03.05 REVOQUES Y ENLUCIDOS
08.04.02.03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.04.02.03.03.06 ACCESORIOS
08.04.02.03.03.06.01 ADAPTADOR C/ROSCA PVC 2"
08.04.02.03.03.06.02 UNION UNIVERSAL DE PVC SP 2"
08.04.02.03.03.06.03 VALVULA COMPUERTA DE BRONCE 2"
08.04.02.03.04 RED DE DESAGÚE 4"
08.04.02.03.04.01 EXCAVACION A MANO EN TERRENO NORMAL
08.04.02.03.04.02 CAMA DE APOYO C/MATERIAL DE PRESTAMO
08.04.02.03.04.03 SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4"
08.04.02.03.05 CAJA DISTRIBUIDORA DE CAUDALES
08.04.02.03.05.01 MOVIMIENTO DE TIERRAS
08.04.02.03.05.01.01 EXCAVACION A MANO EN TERRENO NORMAL
08.04.02.03.05.01.02 REFINE Y NIVELACION PARA LOSA
08.04.02.03.05.01.03 ELIMINACION MATERAIL EXCEDENTE
08.04.02.03.05.02 OBRAS DE CONCRETO SIMPLE
08.04.02.03.05.02.01 CONCRETO f'c=140kg/cm2+25%P.M.
08.04.02.03.05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL
08.04.02.03.05.03 OBRAS DE CONCRETO ARMADO
08.04.02.03.05.03.01 ENCOFRADO Y DESENCOFRADO PARA SARDINEL
08.04.02.03.05.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
08.04.02.03.05.03.03 CONCRETO f'c=210KG/CM2
08.04.02.03.05.04 CURADO DE CONCRETO
08.04.02.03.05.04.01 CURADO CON PRODUCTO QUIMICO
08.04.02.03.05.05 REVOQUES Y ENLUCIDOS
08.04.02.03.05.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA
1:10; E=1.5 cm, ACABADO PULIDO
08.04.02.03.05.06 PINTURA
08.04.02.03.05.06.01 PINTURA ANTICORROCIVA A DOS MANOS
08.04.02.04 ZANJAS DE INFILTRACION
08.04.02.04.01 MOVIMIENTO DE TIERRAS
08.04.02.04.01.01 REFINE Y NIVELACION FONDO ZANJA
08.04.02.04.01.02 EXCAVACION A MANO EN TERRENO NORMAL
08.04.02.04.01.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
08.04.02.04.01.04 ELIMINACION MATERAIL EXCEDENTE
08.04.02.04.02 RELLENO CON MATERIAL SELECCIONADO
08.04.02.04.02.01 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - 2"
08.04.02.04.02.02 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 1/2" - 2"
08.04.02.04.02.03 RELLENO CON MATERIAL PROPIO
08.04.02.04.03 ACCESORIOS
08.04.02.04.03.01 MATERIAL INFILTRANTE EN ZANJAS
08.04.02.04.03.02 TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO
9 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES
9.01 CAMARA DE REJAS Y DESARENADOR (01 UND)
09.01.01 TRABAJOS PRELIMINARES
09.01.01.01 LIMPIEZA MANUAL DE TERRENO
09.01.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
09.01.02 MOVIMIENTO DE TIERRAS
09.01.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
09.01.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
09.01.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
09.01.02.04 ELIMINACION MATERIAL EXCEDENTE
09.01.03 OBRAS DE CONCRETO SIMPLE
09.01.03.01 CONCRETO f'c=100 kg/cm2
09.01.04 OBRAS DE CONCRETO ARMADO
09.01.04.01 CONCRETO f'c=210KG/CM2
09.01.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
09.01.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
09.01.05 CURADO DE CONCRETO
09.01.05.01 CURADO CON PRODUCTO QUIMICO
09.01.06 REVOQUES Y ENLUCIDOS
09.01.06.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
09.01.06.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
09.01.07 CARPINTERIA METALICA
09.01.07.01 REJA S NORMA RNC 30MM (e=15 t=30mm abertura 25mm)
09.01.07.02 COMPUERTAS
09.02 CAMARA REPARTIDORA DE CAUDALES(01 UND)
09.02.01 TRABAJOS PRELIMINARES
09.02.01.01 LIMPIEZA MANUAL DE TERRENO
09.02.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
09.02.02 MOVIMIENTO DE TIERRAS
09.02.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
09.02.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
09.02.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
09.02.02.04 ELIMINACION MATERIAL EXCEDENTE
09.02.03 OBRAS DE CONCRETO SIMPLE
09.02.03.01 CONCRETO f'c=100 kg/cm2
09.02.04 OBRAS DE CONCRETO ARMADO
09.02.04.01 CONCRETO f'c=210KG/CM2
09.02.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
09.02.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
09.02.05 CURADO DE CONCRETO
09.02.05.01 CURADO CON PRODUCTO QUIMICO
09.02.06 REVOQUES Y ENLUCIDOS
09.02.06.01 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO
FROTACHADO
09.02.07 CARPINTERIA METALICA
09.02.07.01 TAPA Y MARCO FFD PESADO
09.02.07.02 COMPUERTAS
09.03 TANQUE SEPTICO
09.03.01 TRABAJOS PRELIMINARES
09.03.01.01 LIMPIEZA MANUAL DE TERRENO
09.03.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
09.03.02 MOVIMIENTO DE TIERRAS
09.03.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
09.03.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
09.03.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
09.03.02.04 ELIMINACION MATERIAL EXCEDENTE
09.03.03 OBRAS DE CONCRETO SIMPLE
09.03.03.01 SOLADO e=3" MEZCLA 1:2 CEMENTO HORMIGON
09.03.03.02 DADO DE CONCRETO PARA ANCLAJE TUBERIA - CAMARA
09.03.04 OBRAS DE CONCRETO ARMADO
09.03.04.01 CONCRETO f'c=210KG/CM2 P/LOSA DE FONDO - PISO
09.03.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
09.03.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
09.03.05 REVOQUES Y ENLUCIDOS
09.03.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
09.03.06 ACCESORIOS
09.03.06.01 SUMINISTRO E INSTALACION DE TUBERIA PVC S-25 NTP ISO 4435 DN 200MM
C/ANILLO
09.03.06.02 SUMINISTRO E INSTALACION DE TUBERIA PVC S-20 NTP ISO 4435 DN 160MM
C/ANILLO
09.03.06.03 SUMINISTRO INST. VALVULA DE COMPUERTA DE HDF PARA TUB. PVC UF DN
200
09.03.06.04 SUMINISTRO E INSTALACION DE TEE SANITARIA DN=200mm
09.03.06.05 SUMINISTRO E INSTALACION DE TEE SANITARIA DN=160mm
09.03.06.06 VENTILACION DE F°G° DE DN=75MM
09.04 LECHO DE SECADO
09.04.01 TRABAJOS PRELIMINARES
09.04.01.01 LIMPIEZA MANUAL DE TERRENO
09.04.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
09.04.02 MOVIMIENTO DE TIERRAS
09.04.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
09.04.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
09.04.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
09.04.02.04 RELLENO C/AFIRMADO
09.04.02.05 RELLENO C/AGREGADO ARENA GRUESA E=0.35M
09.04.02.06 RELLENO CON GRAVA SUELTO DE 1/2"
09.04.02.07 RELLENO CON GRAVA SUELTO DE 3/4"
09.04.02.08 ELIMINACION MATERIAL EXCEDENTE
09.04.03 OBRAS DE CONCRETO ARMADO
09.04.03.01 CONCRETO f'c=210KG/CM2 P/LOSA DE FONDO - PISO
09.04.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
09.04.03.03 ENCOFRADO Y DESENCOFRADO NORMAL
09.04.04 REVOQUES Y ENLUCIDOS
09.04.04.01 TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
09.04.04.02 TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
09.04.05 MUROS Y TABIQUERIA
09.04.05.01 MURO DE LADRILLO K.K. APAREJO DE SOGA E=0.12m (ESP. HORIZONTAL
E=0.10m)
09.04.06 COBERTURA
09.04.06.01 VIGA DE MADERA TORNILLO 3"x6"
09.04.06.02 CORREAS DE MADERA TORNILLO DE 2"x2"
09.04.06.03 PLANCHA DE CALAMINA TIPO TEJA ANDINA 0.72x1.14M
09.05 CAMARA DISTRIBUIDORA DE CAUDALES (03)
09.05.01 TRABAJOS PRELIMINARES
09.05.01.01 LIMPIEZA MANUAL DE TERRENO
09.05.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
09.05.02 MOVIMIENTO DE TIERRAS
09.05.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
09.05.02.02 REFINE Y NIVELACION PARA LOSA
09.05.02.03 ELIMINACION MATERAIL EXCEDENTE
09.05.03 OBRAS DE CONCRETO ARMADO
09.05.03.01 ENCOFRADO Y DESENCOFRADO NORMAL
09.05.03.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
09.05.03.03 CONCRETO f'c=210KG/CM2
09.05.04 CURADO DE CONCRETO
09.05.04.01 CURADO CON PRODUCTO QUIMICO
09.05.05 REVOQUES Y ENLUCIDOS
09.05.05.01 TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10;
E=1.5 cm, ACABADO PULIDO
09.05.06 CARPINTERIA METALICA
09.05.06.01 TAPA Y MARCO FFD PESADO
09.05.06.02 COMPUERTAS
09.05.07 ACCESORIOS
09.05.07.01 TUBERIA PVC SAL DE 4"
09.06 POZO DE PERCOLACION (06)
09.06.01 TRABAJOS PRELIMINARES
09.06.01.01 LIMPIEZA MANUAL DE TERRENO
09.06.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
09.06.02 MOVIMIENTO DE TIERRAS
09.06.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
09.06.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
09.06.02.03 ELIMINACION MATERIAL EXCEDENTE
09.06.03 CONCRETO SIMPLE
09.06.03.01 CONCRETO CILOPEO PARA CIMIENTACION 1:10 + 30% P.G.
09.06.04 CONCRETO ARMADO
09.06.04.01 CONCRETO f'c=175 kg/cm2
09.06.04.02 ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
09.06.04.03 ENCOFRADO Y DESENCOFRADO NORMAL
09.06.05 TABIQUERIA EN FORMA CIRCULAR
09.06.05.01 MURO LADRILLO K.K. DE ARCILLA 18 H. (0.09x0.13x0.24) AMARRE DE CANTO
MORTERO 1:1:5
09.06.06 RELLENO CON GRAVA
09.06.06.01 RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1"
09.06.07 ACCESORIOS
09.06.07.01 TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 160MM
09.06.07.02 TUBERIA PVC SAL DE 2"
09.07 INSTALACION DE TUBERIAS (180m)
09.07.01 TRABAJOS PRELIMINARES
09.07.01.01 LIMPIEZA MANUAL DE TERRENO
09.07.01.02 TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
09.07.02 MOVIMIENTO DE TIERRAS
09.07.02.01 EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
09.07.02.02 REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL
COMPACTADO
09.07.02.03 CAMA DE APOYO PARA TUBERIA (0.60x0.10m)
09.07.02.04 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
09.07.02.05 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
09.07.03 TENDIDO DE TUBERIA
09.07.03.01 SUMINISTRO Y COLOCACION DE TUBERIA DE PVC C-7.5 NTP 1452 DN 200MM
09.08 CERCO PERIMETRICO (L=120.00 m)
09.08.01 TRABAJOS PRELIMINARES
09.08.01.01 LIMPIEZA MANUAL DE TERRENO
09.08.01.02 TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
09.08.02 MOVIMIENTO DE TIERRAS
09.08.02.01 EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
09.08.02.02 REFINE Y NIVELACION DE FONDO DE TERRENO
09.08.02.03 RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
09.08.02.04 ELIMINACION MATERAIL EXCEDENTE
09.08.03 OBRAS DE CONCRETO SIMPLE
09.08.03.01 CONCRETO f'c=140 kg/cm2
09.08.04 CERCO PERIMETRICO CON MALLA OLIMPICA GALVANIZADA
09.08.04.01 CERCO PERIMETRICO DE ALAMBRE DE PUAS
09.08.04.02 PUERTA DE MADERA CON MARCO O SOPORTES
09.08.04.03 PINTURA ESMALTE EN PUERTAS Y VENTANAS A DOS MANOS
10 CAPACITACION Y EDUCACION
10.01 DESAROLLO DE LAS CAPACITACIONES Y/O TALLERES ENSIBILIZACION,
EDUCACION Y PARTICIPACION CIUDADANA DE APOYO A LA GESTION DE AP Y AS
11 MITIGACION DEL IMPACTO AMBIENTAL
11.01 MITIGACION DEL IMPACTO AMBIENTAL
UTADOS MENSUAL
Setiembre del 2018

IENTO INTEGRAL EN LAS COMUNIDADES DE MONTE SINAI, ALTO UNINI, VISTA ALEGRE
RITO DE RIO TAMBO - SATIPO - JUNIN”

MES SETIEMBRE
PERIODO 01 de Setiembre 2018 al 30 de Setiembre 2018
DIAS ACUMULADOS 30 días calendarios
FECHA DE VALORIZACIÓN 30 DE SETIEMBRE DEL 2018

METRADO METRADOS EJECUTADOS SALDO DE


UND
PRESUP. ANTERIOR ACTUAL ACUM. OBRA

glb 1.00 0.65 0.08 0.73 0.27


und 1.00 1.00 - 1.00 -
glb 1.00 0.89 0.89 0.11
glb 1.00 0.82 0.82 0.18
m3 96.00 - - - 96.00
- - - -
m 2 1.25 0.15 1.40 0.60
und 2 2.00 - 2.00 -
- - - -
- - - -
m2 92.85 - - - 92.85
m2 92.85 - - - 92.85
- - - -
m3 118.98 - - - 118.98
m2 11.44 - - - 11.44
m3 29.74 - - - 29.74
m3 89.23 - - - 89.23
- - - -
m3 71.64 - - - 71.64
m3 11.54 - - - 11.54
- - - -
m3 14.86 - - - 14.86
m2 125.46 - - - 125.46
kg 1043.78 - - - 1,043.78
- - - -
m2 103.19 - - - 103.19
- - - -
m2 109.69 - - - 109.69
m2 26.38 - - - 26.38
- - - -
und 1.00 - - - 1.00
und 1.00 - - - 1.00
- - - -
m2 136.07 - - - 136.07
m2 109.69 - - - 109.69
- - - -
und 1.00 - - - 1.00
- - - -
- - - -
m2 17.82 - - - 17.82
m2 17.82 - - - 17.82
- - - -
m3 15.26 - - - 15.26
m2 16.62 - - - 16.62
m3 3.81 - - - 3.81
m3 11.44 - - - 11.44
- - - -
m3 1.66 - - - 1.66
- - - -
m3 7.45 - - - 7.45
kg 775.96 - - - 775.96
m2 26.20 - - - 26.20
- - - -
m2 26.58 - - - 26.58
- - - -
m2 27.58 - - - 27.58
- - - -
und 2.00 - - - 2.00
und 2.00 - - - 2.00
- - - -
m2 19.43 - - - 19.43
- - - -
und 1.00 - - - 1.00
- - - -
- - - -
m2 7,120.00 7,120.00 - 7,120.00 -
m2 7,120.00 7,120.00 - 7,120.00 -
- - - -
m3 5,696.00 1,800.00 1,036.00 2,836.00 2,860.00
m 14,240.00 5,990.00 3,700.00 9,690.00 4,550.00
m 14,240.00 5,990.00 3,700.00 9,690.00 4,550.00
m 14,240.00 5,990.00 3,700.00 9,690.00 4,550.00
m3 4272 1,289.00 740.00 2,029.00 2,243.00
- - -
m 14,240.00 5,990.00 3,700.00 9,690.00 4,550.00
- - - -
m 14,240.00 - - - 14,240.00
- - - -
- - - -
m2 21.06 - - - 21.06
m2 21.06 - - - 21.06
- - - -
m3 12.64 - - - 12.64
m2 21.06 - - - 21.06
m3 12.64 - - - 12.64
- - - -
m3 13.10 - - - 13.10
m2 132.60 - - - 132.60
- - - -
m2 132.60 - - - 132.60
- - - -
m2 110.24 - - - 110.24
- - - -
und 26.00 - - - 26.00
- - - -
m2 110.24 - - - 110.24
- - - -
und 26 - - - 26.00
- - - -
- - - -
m2 5.75 - - - 5.75
m2 5.75 - - - 5.75
- - - -
m3 4.68 - - - 4.68
m2 5.75 - - - 5.75
m3 4.38 - - - 4.38
- - - -
m3 0.23 - - - 0.23
m3 0.63 - - - 0.63
- - - -
m3 2.63 - - - 2.63
m2 35.05 - - - 35.05
- - - -
und 5.00 - - - 5.00
- - - -
m2 10.20 - - - 10.20
- - - -
und 5 - - - 5.00
- - - -
- - - -
m2 1.85 - - - 1.85
m2 1.85 - - - 1.85
- - - -
m3 1.90 - - - 1.90
m2 1.55 - - - 1.55
m3 1.90 - - - 1.90
- - - -
m2 2.56 - - - 2.56
m3 0.07 - - - 0.07
m3 0.04 - - - 0.04
m2 0.75 - - - 0.75
- - - -
m3 0.91 - - - 0.91
m2 10.16 - - - 10.16
kg 27.10 - - - 27.10
- - - -
m2 0.91 - - - 0.91
- - - -
m2 3.60 - - - 3.60
- - - -
und 1.00 - - - 1.00
- - - -
m2 2.00 - - - 2.00
- - - -
und 1.00 - - - 1.00
- - - -
- - - -
m2 392.4 - - - 392.40
m2 392.40 - - - 392.40
- - - -
m3 54.90 - - - 54.90
m3 54.90 - - - 54.90
- - - -
m3 0.90 - - - 0.90
- - - -
m3 18.52 - - - 18.52
m3 28.8 - - - 28.80
m2 66.96 - - - 66.96
kg 766.58 - - - 766.58
- - - -
m2 66.96 - - - 66.96
- - - -
m 150.30 - - - 150.30
und 99.00 - - - 99.00
und 117 - - - 117.00
m 126.00 - - - 126.00
glb 9.00 - - - 9.00
und 9.00 - - - 9.00
- - - -
- - - -
- - - -
- - - -
m2 144.00 - - - 144.00
m2 144.00 - - - 144.00
- - - -
m3 453.1 - - - 453.10
m2 144 - - - 144.00
m3 100.8 - - - 100.80
- - - -
m3 7.20 - - - 7.20
- - - -
m3 79.98 - - - 79.98
kg 5,228.36 - - - 5,228.36
m2 754.64 - - - 754.64
- - - -
m2 272.10 - - - 272.10
- - - -
m2 174.40 - - - 174.40
m2 458.96 - - - 458.96
- - - -
m2 174.40 - - - 174.40
m2 458.96 - - - 458.96
- - - -
m3 18.90 - - - 18.90
m3 37.8 - - - 37.80
m3 75.60 - - - 75.60
m3 31.08 - - - 31.08
- - - -
glb 2.00 - - - 2.00
- - - -
- - - -
m2 121.17 121.17 121.17 -
m2 121.17 121.17 121.17 -
- - - -
m3 204.89 204.89 204.89 -
m2 49.38 49.38 49.38 -
m3 17.97 - 11.88 11.88 6.09
m3 186.92 - - - 186.92
- - - -
m2 8.90 - - - 8.90
m3 119.43 119.43 119.43 -
- - - -
m3 96.56 36.96 55.25 92.21 4.35
kg 7,736.61 7,736.61 - 7,736.61 -
m2 421.82 - 342.96 342.96 78.86
- - - -
m2 96.56 36.96 55.25 92.21 4.35
- - - -
m 53.10 53.10 53.10 -
- - - -
m2 312.75 - - - 312.75
m2 183.1 - - - 183.10
m2 57.79 - - - 57.79
- - - -
und 1.00 - - - 1.00
und 1 - - - 1.00
und 3 - - - 3.00
und 3 - - - 3.00
- - - -
m3 10.00 - - - 10.00
m3 5 - - - 5.00
m3 5.00 - - - 5.00
m3 100.00 - - - 100.00
- - - -
m2 183.1 - - - 183.10
m2 1.57 - - - 1.57
- - - -
und 1 - - - 1.00
- - - -
- - - -
m2 120.00 - - - 120.00
m2 120.00 - - - 120.00
- - - -
m3 14.11 - - - 14.11
m2 35.28 - - - 35.28
m3 3.53 - - - 3.53
m3 13.23 - - - 13.23
- - - -
m3 14.14 - - - 14.14
- - - -
m 240.00 - - - 240.00
und 1.00 - - - 1.00
m2 10 - - - 10.00
- - - -
- - - -
m2 7.81 7.81 7.81 -
m2 7.81 7.81 7.81 -
- - - -
m3 16.46 16.46 16.46 -
m2 7.81 7.81 7.81 -
m3 9.76 9.76 9.76 -
- - - -
m3 0.03 0.03 0.03 -
- - - -
m3 7.17 7.17 7.17 -
m2 73.75 73.75 73.75 -
kg 87.06 87.06 87.06 -
- - -
m2 73.75 73.75 73.75 -
- - -
m2 37.53 37.53 37.53 -
- - - -
und 1.00 1.00 1.00 -
- - - -
m2 21.81 - - - 21.81
- - - -
und 1.00 - - - 1.00
- - - -
- - - -
- - - -
m2 1,835.61 1,835.61 - 1,835.61 -
m2 1835.61 1,835.61 - 1,835.61 -
- - - -
m3 1,762.19 768.00 504.00 1,272.00 490.19
m 3,671.22 1,600.00 1,050.00 2,650.00 1,021.22
m 3671.22 1,600.00 1,050.00 2,650.00 1,021.22
m 3,671.22 1,600.00 1,050.00 2,650.00 1,021.22
m3 1,101.37 480.00 315.00 795.00 306.37
- - -
m 3,671.25 1,600.00 1,050.00 2,650.00 1,021.25
- - - -
m 3,671.22 - - - 3,671.22
- - - -
- - - -
m2 6.48 - - - 6.48
m2 6.48 - - - 6.48
- - - -
m3 3.89 - - - 3.89
m2 6.48 - - - 6.48
m3 3.89 - - - 3.89
- - - -
m3 4.03 - - - 4.03
m2 40.80 - - - 40.80
- - - -
m2 40.38 - - - 40.38
- - - -
m2 33.92 - - - 33.92
- - - -
und 8 - - - 8.00
- - - -
m2 33.92 - - - 33.92
- - - -
und 8.00 - - - 8.00
- - - -
- - - -
m2 2.3 - - - 2.30
m2 2.30 - - - 2.30
- - - -
m3 1.87 - - - 1.87
m2 2.30 - - - 2.30
m3 1.75 - - - 1.75
- - - -
m3 0.09 - - - 0.09
m3 0.25 - - - 0.25
- - - -
m3 1.05 - - - 1.05
m2 14.02 - - - 14.02
- - - -
und 2.00 - - - 2.00
- - - -
m2 4.08 - - - 4.08
- - - -
und 2.00 - - - 2.00
- - - -
- - - -
m2 3.69 - - - 3.69
m2 3.69 - - - 3.69
- - - -
m3 3.79 - - - 3.79
m2 3.10 - - - 3.10
m3 3.79 - - - 3.79
- - - -
m2 5.12 - - - 5.12
m3 0.14 - - - 0.14
m3 0.14 - - - 0.14
m2 1.50 - - - 1.50
- - - -
m3 1.81 - - - 1.81
m2 20.32 - - - 20.32
kg 54.21 - - - 54.21
- - - -
m2 1.81 - - - 1.81
- - - -
m2 7.2 - - - 7.20
- - - -
und 2.00 - - - 2.00
- - - -
m2 4 - - - 4.00
- - - -
und 2.00 - - - 2.00
- - - -
- - - -
m2 29.16 29.16 29.16 -
m2 29.16 29.16 29.16 -
- - -
m3 7.22 7.22 7.22 -
m3 9.03 9.03 9.03 -
- - -
m3 3.72 3.72 3.72 -
- - -
m3 10.1 10.10 10.10 -
kg 324.86 324.86 324.86 -
m2 64.30 64.30 64.30 -
- - -
m2 64.3 64.30 64.30 -
- - -
m2 32.55 32.55 32.55 -
m2 59.90 59.90 59.90 -
- - -
und 1.00 1.00 1.00 -
und 1.00 - - 1.00
und 1.00 - - 1.00
und 2.00 1.00 1.00 1.00
- - -
m2 38.72 - - 38.72
m2 33.62 - - - 33.62
- - - -
und 1.00 - - - 1.00
und 1 - - - 1.00
und 1.00 - - - 1.00
- - - -
- - - -
m2 0.36 0.36 0.36 -
m2 0.36 0.36 0.36 -
- - -
m3 0.22 0.22 0.22 -
m2 0.36 0.36 0.36 -
m3 0.36 0.36 0.36 -
- - -
m3 0.48 0.48 0.48 -
kg 18.83 18.83 18.83 -
m2 1 1.00 1.00 -
- - -
m2 2.00 2.00 2.00 -
- - -
m2 2 2.00 2.00 -
- - - -
glb 1.00 - - - 1.00
- - - -
- - - -
m2 2311.39 2,311.39 - 2,311.39 -
m2 2,311.39 2,311.39 - 2,311.39 -
- - - -
m3 2,311.39 2,311.39 2,311.39 -
m 4,622.78 4,622.78 4,622.78 -
m 4,622.78 4,622.78 4,622.78 -
m 4622.78 4,622.78 4,622.78 -
m3 3,698.22 3,698.22 3,698.22 -
- - -
m 2,428.78 2,428.78 2,428.78 -
m 299 299.00 299.00 -
m 1,895.00 1,895.00 1,895.00 -
- - - -
m 4,622.78 - - - 4,622.78
- - - -
- - - -
m2 2.43 - - - 2.43
m2 2.43 - - - 2.43
- - - -
m3 1.46 - - - 1.46
m2 2.43 - - - 2.43
m3 1.46 - - - 1.46
- - - -
m3 1.51 - - - 1.51
m2 28.35 - - - 28.35
- - - -
m2 28.35 - - - 28.35
- - - -
m2 12.72 - - - 12.72
- - - -
und 3 - - - 3.00
- - - -
m2 22.95 - - - 22.95
- - - -
und 3.00 - - - 3.00
- - - -
- - - -
m2 8.64 - - - 8.64
m2 8.64 - - - 8.64
- - - -
m3 4.92 - - - 4.92
m2 4.60 - - - 4.60
m3 4.68 - - - 4.68
- - - -
m3 0.2 - - - 0.20
m3 0.52 - - - 0.52
- - - -
m3 2.28 - - - 2.28
m2 12.84 - - - 12.84
- - - -
und 4.00 - - - 4.00
- - - -
m2 8.16 - - - 8.16
- - - -
und 4.00 - - - 4.00
- - - -
- - - -
m2 3.24 - - - 3.24
m2 3.24 - - - 3.24
- - - -
m3 2.91 - - - 2.91
m2 3.24 - - - 3.24
m3 3.48 - - - 3.48
- - - -
m3 3.06 - - - 3.06
m2 9.72 - - - 9.72
- - - -
und 3 - - - 3.00
- - - -
m2 11.76 - - - 11.76
- - - -
und 4.00 - - - 4.00
und 11.00 - - - 11.00
- - - -
- - - -
m2 189 - - - 189.00
m2 189.00 - - - 189.00
- - - -
m3 189.00 - - - 189.00
m2 204.00 - - - 204.00
m3 70.20 - - - 70.20
m3 151.20 - - - 151.20
- - - -
m3 6.05 - - - 6.05
m2 7.56 - - - 7.56
- - - -
und 63 10.00 10.00 53.00
- - - -
- - - -
- - - -
m2 736.50 736.50 - 736.50 -
m2 736.50 736.50 - 736.50 -
- - - -
m3 589.20 400.00 189.20 589.20 -
m 1473.00 1,000.00 473.00 1,473.00 -
m 1,473.00 1,000.00 473.00 1,473.00 -
m 1,473.00 1,000.00 473.00 1,473.00 -
m3 441.90 300.00 141.90 441.90 -
- - -
m 1,473.00 1,000.00 473.00 1,473.00 -
- - -
m 1473 - - - 1,473.00
- - - -
- - - -
m2 2.43 - - - 2.43
m2 2.43 - - - 2.43
- - - -
m3 1.46 - - - 1.46
m2 2.43 - - - 2.43
m3 1.46 - - - 1.46
- - - -
m3 1.51 - - - 1.51
m2 15.30 - - - 15.30
- - - -
m2 15.30 - - - 15.30
- - - -
m2 12.72 - - - 12.72
- - - -
und 3 - - - 3.00
- - - -
m2 12.72 - - - 12.72
- - - -
und 3.00 - - - 3.00
- - - -
- - - -
m2 1.15 - - - 1.15
m2 1.15 - - - 1.15
- - - -
m3 0.94 - - - 0.94
m2 1.15 - - - 1.15
m3 0.88 - - - 0.88
- - - -
m3 0.05 - - - 0.05
m3 0.13 - - - 0.13
- - - -
m3 0.53 - - - 0.53
m2 7.01 - - - 7.01
- - - -
und 1.00 - - - 1.00
- - - -
m2 2.04 - - - 2.04
- - - -
und 1.00 - - - 1.00
- - -
- - -
m2 46.94 46.94 46.94 -
m2 46.94 46.94 46.94 -
- - -
m3 41.75 41.75 41.75 -
m2 21.5 21.50 21.50 -
m3 51.88 51.88 51.88 -
- - -
m3 4.66 4.66 4.66 -
- - -
m3 15.69 15.69 15.69 -
kg 785.99 785.99 785.99 -
m2 93.48 93.48 93.48 -
- - -
m2 93.48 93.48 93.48 -
- - -
m2 38.72 38.72 38.72 -
m2 32.62 32.62 32.62 -
- - -
und 1.00 1.00 1.00 -
und 1 - - 1.00
und 1.00 - - 1.00
und 2.00 1.00 1.00 1.00
- - - -
m2 38.72 - - - 38.72
m2 33.62 - - - 33.62
- - - -
und 1.00 - - - 1.00
und 1 - - - 1.00
und 1.00 - - - 1.00
- - - -
- - - -
m2 0.36 0.36 0.36 -
m2 0.36 0.36 0.36 -
- - -
m3 0.22 0.22 0.22 -
m2 0.36 0.36 0.36 -
m3 0.36 0.36 0.36 -
- - -
m3 0.48 0.48 0.48 -
kg 18.83 18.83 18.83 -
m2 1.00 1.00 1.00 -
- - -
m2 2.00 2.00 2.00 -
- - - -
m2 2.00 2.00 2.00 -
- - - -
glb 1.00 - - - 1.00
- - - -
- - - -
m2 220.00 - - - 220.00
m2 220.00 - - - 220.00
- - - -
m3 18.00 - - - 18.00
m3 4.50 - - - 4.50
m2 45.00 - - - 45.00
m3 16.88 - - - 16.88
- - - -
m3 18.03 - - - 18.03
- - - -
m 220.00 - - - 220.00
und 1.00 - - - 1.00
m2 396.00 - - - 396.00
- - - -
- - - -
m2 840.50 840.50 - 840.50 -
m2 840.50 840.50 - 840.50 -
- - - -
m3 840.50 - 60.00 60.00 780.50
m 1681.00 - 120.00 120.00 1,561.00
m 1,681.00 - 120.00 120.00 1,561.00
m 1681.00 - 120.00 120.00 1,561.00
m3 672.40 - 48.00 48.00 624.40
- - - -
m 356.00 - - - 356.00
m 275.00 - - - 275.00
m 744 - - - 744.00
m 186.00 - - - 186.00
m 120.00 - 120.00 120.00 -
- - - -
m 1,681.00 - - - 1,681.00
- - - -
- - - -
m2 2.43 - - - 2.43
m2 2.43 - - - 2.43
- - - -
m3 1.46 - - - 1.46
m2 2.43 - - - 2.43
m3 1.46 - - - 1.46
- - - -
m3 1.51 - - - 1.51
m2 28.35 - - - 28.35
- - - -
m2 28.35 - - - 28.35
- - - -
m2 12.72 - - - 12.72
- - - -
und 3.00 - - - 3.00
- - - -
m2 22.95 - - - 22.95
- - - -
und 3.00 - - - 3.00
- - - -
- - - -
m2 8.64 - - - 8.64
m2 8.64 - - - 8.64
- - - -
m3 4.92 - - - 4.92
m2 4.60 - - - 4.60
m3 4.68 - - - 4.68
- - - -
m3 0.20 - - - 0.20
m3 0.52 - - - 0.52
- - - -
m3 2.28 - - - 2.28
m2 12.84 - - - 12.84
- - - -
und 4.00 - - - 4.00
- - - -
m2 8.16 - - - 8.16
- - - -
und 4 - - - 4.00
- - - -
- - - -
m2 4.32 - - - 4.32
m2 4.32 - - - 4.32
- - - -
m3 3.88 - - - 3.88
m2 4.32 - - - 4.32
m3 4.64 - - - 4.64
- - - -
m3 4.08 - - - 4.08
m2 12.96 - - - 12.96
- - - -
und 4.00 - - - 4.00
- - - -
m2 15.68 - - - 15.68
- - - -
und 2 - - - 2.00
und 2.00 - - - 2.00
- - - -
- - - -
m2 316.80 - - - 316.80
m2 316.80 - - - 316.80
- - - -
m3 168.96 - - - 168.96
m2 211.2 - - - 211.20
m3 95.20 - - - 95.20
m3 168.96 - - - 168.96
- - - -
m3 8.45 - - - 8.45
m2 10.56 - - - 10.56
- - - -
und 88 - - - 88.00
- - - -
- - - -
- - - -
m2 1,560.00 1,560.00 - 1,560.00 -
m2 1,560.00 1,560.00 - 1,560.00 -
- - - -
m3 1,248.00 400.00 848.00 1,248.00 -
m 3,120.00 1,000.00 2,120.00 3,120.00 -
m 3120.00 1,000.00 2,120.00 3,120.00 -
m 3,120.00 1,000.00 2,120.00 3,120.00 -
m3 936.00 300.00 636.00 936.00 -
- - -
m 3,120.00 1,000.00 2,120.00 3,120.00 -
- - - -
m 3120 - - - 3,120.00
- - - -
- - - -
m2 1.85 - - - 1.85
m2 1.85 - - - 1.85
- - - -
m3 1.90 - - - 1.90
m2 1.55 - - - 1.55
m3 1.9 - - - 1.90
- - - -
m2 2.56 - - - 2.56
m3 0.07 - - - 0.07
m3 0.04 - - - 0.04
m2 0.75 - - - 0.75
- - - -
m3 0.91 - - - 0.91
m2 10.16 - - - 10.16
kg 27.10 - - - 27.10
- - - -
m2 0.91 - - - 0.91
- - - -
m2 3.60 - - - 3.60
- - - -
und 1.00 - - - 1.00
- - - -
m2 2.00 - - - 2.00
- - - -
und 1 - - - 1.00
- - - -
- - - -
m2 23.04 23.04 23.04 -
m2 23.04 23.04 23.04 -
- - -
m3 5.12 5.12 5.12 -
m2 10.24 10.24 10.24 -
m3 6.4 6.40 6.40 -
- - -
m3 1.02 1.02 1.02 -
- - -
m3 12.02 12.02 12.02 -
kg 280.76 280.76 280.76 -
m2 50.98 50.98 50.98 -
- - -
m2 50.98 50.98 50.98 -
- - - -
m2 24.75 24.75 24.75 -
m2 43.38 43.38 43.38 -
- - -
und 1.00 1.00 1.00 -
und 1.00 - - 1.00
und 1 - - 1.00
und 2.00 1.00 1.00 1.00
- - -
m2 33.92 - - - 33.92
m2 24.08 - - - 24.08
- - - -
und 1.00 - - - 1.00
und 1.00 - - - 1.00
und 1 - - - 1.00
- - - -
- - - -
m2 0.36 0.36 0.36 -
m2 0.36 0.36 0.36 -
- - -
m3 0.22 0.22 0.22 -
m2 0.36 0.36 0.36 -
m3 0.36 0.36 0.36 -
- - -
m3 0.48 0.48 0.48 -
kg 18.83 18.83 18.83 -
m2 1.00 1.00 1.00 -
- - -
m2 2.00 2.00 2.00 -
- - -
m2 2.00 2.00 2.00 -
- - - -
glb 1 - - - 1.00
- - -
- - -
m2 7.81 7.81 7.81 -
m2 7.81 7.81 7.81 -
- - -
m3 16.46 16.46 16.46 -
m2 7.81 7.81 7.81 -
m3 9.76 9.76 9.76 -
- - -
m3 0.03 0.03 0.03 -
- - -
m3 7.17 7.17 7.17 -
m2 73.75 73.75 73.75 -
kg 87.06 87.06 87.06 -
- - -
m2 73.75 73.75 73.75 -
- - - -
m2 37.53 37.53 37.53 -
- - - -
und 2.00 - - - 2.00
- - - -
m2 21.81 - - - 21.81
- - - -
und 1.00 - - - 1.00
- - - -
- - - -
m2 1060.00 1,060.00 - 1,060.00 -
m2 1,060.00 1,060.00 - 1,060.00 -
- - - -
m3 1,060.00 1,060.00 1,060.00 -
m 2,120.00 2,120.00 2,120.00 -
m 2120.00 2,120.00 2,120.00 -
m 2,120.00 2,120.00 2,120.00 -
m3 848.00 848.00 848.00 -
- - -
m 314.00 314.00 314.00 -
m 282.00 282.00 282.00 -
m 385.00 385.00 385.00 -
m 1,139.00 1,139.00 1,139.00 -
- - - -
m 2,120.00 - - - 2,120.00
- - - -
- - - -
m2 2.43 - - - 2.43
m2 2.43 - - - 2.43
- - - -
m3 1.46 - - - 1.46
m2 2.43 - - - 2.43
m3 1.46 - - - 1.46
- - - -
m3 1.51 - - - 1.51
m2 28.35 - - - 28.35
- - - -
m2 28.35 - - - 28.35
- - - -
m2 12.72 - - - 12.72
- - - -
und 3.00 - - - 3.00
- - - -
m2 22.95 - - - 22.95
- - - -
und 3.00 - - - 3.00
- - - -
- - - -
m2 4.32 - - - 4.32
m2 4.32 - - - 4.32
- - - -
m3 1.96 - - - 1.96
m2 2.30 - - - 2.30
m3 1.84 - - - 1.84
- - - -
m3 0.09 - - - 0.09
m3 0.25 - - - 0.25
- - - -
m3 1.14 - - - 1.14
m2 6.42 - - - 6.42
- - - -
und 2.00 - - - 2.00
- - - -
m2 4.08 - - - 4.08
- - - -
und 2.00 - - - 2.00
- - - -
- - - -
m2 4.32 - - - 4.32
m2 4.32 - - - 4.32
- - - -
m3 3.88 - - - 3.88
m2 4.32 - - - 4.32
m3 4.64 - - - 4.64
- - - -
m3 4.08 - - - 4.08
m2 12.96 - - - 12.96
- - - -
und 4.00 - - - 4.00
- - - -
m2 15.68 - - - 15.68
- - - -
und 1.00 - - - 1.00
und 3.00 - - - 3.00
- - - -
- - - -
m2 126.00 - - - 126.00
m2 126.00 - - - 126.00
- - - -
m3 67.2 - - - 67.20
m2 84.00 - - - 84.00
m3 42.20 - - - 42.20
m3 67.20 - - - 67.20
- - - -
m3 3.36 - - - 3.36
m2 4.2 - - - 4.20
- - - -
und 35.00 25.00 10.00 35.00 -
- - - -
- - - -
- - - -
m2 1,380.00 1,380.00 - 1,380.00 -
m2 1380.00 1,380.00 - 1,380.00 -
- - - -
m3 1,104.00 1,104.00 1,104.00 -
m 2760.00 2,760.00 2,760.00 -
m 2,760.00 2,760.00 2,760.00 -
m 2,760.00 2,760.00 2,760.00 -
m3 828.00 828.00 828.00 -
- - -
m 2,760.00 2,760.00 2,760.00 -
- - - -
m 2760 - - - 2,760.00
- - - -
- - - -
m2 5.67 - - - 5.67
m2 5.67 - - - 5.67
- - - -
m3 3.40 - - - 3.40
m2 5.67 - - - 5.67
m3 3.4 - - - 3.40
- - - -
m3 3.53 - - - 3.53
m2 66.15 - - - 66.15
- - - -
m2 66.15 - - - 66.15
- - - -
m2 66.15 - - - 66.15
- - - -
und 7.00 - - - 7.00
- - - -
m2 53.55 - - - 53.55
- - - -
und 7 - - - 7.00
- - - -
- - - -
m2 6.90 - - - 6.90
m2 6.90 - - - 6.90
- - - -
m3 5.61 - - - 5.61
m2 6.90 - - - 6.90
m3 5.26 - - - 5.26
- - - -
m3 0.27 - - - 0.27
m3 0.75 - - - 0.75
- - - -
m3 3.15 - - - 3.15
m2 42.06 - - - 42.06
- - - -
und 6.00 - - - 6.00
- - - -
m2 20.4 - - - 20.40
- - - -
und 10 - - - 10.00
- - - -
- - - -
m2 7.81 7.81 7.81 -
m2 7.81 7.81 7.81 -
- - -
m3 16.46 16.46 16.46 -
m2 7.81 7.81 7.81 -
m3 9.76 9.76 9.76 -
- - -
m3 0.03 0.03 0.03 -
- - -
m3 7.17 7.17 7.17 -
m2 73.75 73.75 73.75 -
kg 87.06 87.06 87.06 -
- - -
m2 73.75 73.75 73.75 -
- - - -
m2 37.53 37.53 37.53 -
- - - -
und 2 - - - 2.00
- - - -
m2 21.81 - - - 21.81
- - - -
und 1.00 - - - 1.00
- - - -
- - - -
m2 23.04 23.04 23.04 -
m2 23.04 23.04 23.04 -
- - -
m3 5.12 5.12 5.12 -
m2 10.24 10.24 10.24 -
m3 6.40 6.40 6.40 -
- - -
m3 1.02 1.02 1.02 -
- - -
m3 12.02 12.02 12.02 -
kg 280.76 280.76 280.76 -
m2 50.98 50.98 50.98 -
- - -
m2 50.98 50.98 50.98 -
- - -
m2 24.75 24.75 24.75 -
m2 43.38 43.38 43.38 -
- - -
und 1 1.00 1.00 -
und 1.00 - - 1.00
und 1 - - 1.00
und 2 1.00 1.00 1.00
- - - -
m2 32.92 - - - 32.92
m2 24.08 - - - 24.08
- - - -
und 1.00 - - - 1.00
und 1.00 - - - 1.00
und 1.00 - - - 1.00
- - - -
- - - -
m2 0.36 0.36 0.36 -
m2 0.36 0.36 0.36 -
- - -
m3 0.22 0.22 0.22 -
m2 0.36 0.36 0.36 -
m3 0.36 0.36 0.36 -
- - -
m3 0.48 0.48 0.48 -
kg 18.83 18.83 18.83 -
m2 1.00 1.00 1.00 -
- - -
m2 2.00 2.00 2.00 -
- - -
m2 2.00 2.00 2.00 -
- - - -
glb 1 - - - 1.00
- - - -
- - - -
m2 3,514.00 3,514.00 - 3,514.00 -
m2 3,514.00 3,514.00 - 3,514.00 -
- - - -
m3 3,514.00 2,814.00 450.00 3,264.00 250.00
m 7,028.00 5,628.00 900.00 6,528.00 500.00
m 7,028.00 5,628.00 900.00 6,528.00 500.00
m 7,028.00 5,628.00 900.00 6,528.00 500.00
m3 2,811.20 2,251.20 360.00 2,611.20 200.00
- - -
m 1,027.00 527.00 527.00 500.00
m 2,687.00 2,687.00 2,687.00 -
m 868 868.00 868.00 -
m 1,546.00 1,546.00 1,546.00 -
m 900.00 - 900.00 900.00 -
- - - -
m 7,028.00 - - - 7,028.00
- - - -
- - - -
m2 1.62 - - - 1.62
m2 1.62 - - - 1.62
- - - -
m3 0.97 - - - 0.97
m2 1.62 - - - 1.62
m3 0.97 - - - 0.97
- - - -
m3 1.01 - - - 1.01
m2 18.90 - - - 18.90
- - - -
m2 18.90 - - - 18.90
- - - -
m2 8.48 - - - 8.48
- - - -
und 2.00 - - - 2.00
- - - -
m2 15.3 - - - 15.30
- - - -
und 2 - - - 2.00
- - - -
- - - -
m2 4.32 - - - 4.32
m2 4.32 - - - 4.32
- - - -
m3 1.96 - - - 1.96
m2 2.30 - - - 2.30
m3 1.84 - - - 1.84
- - - -
m3 0.09 - - - 0.09
m3 0.25 - - - 0.25
- - - -
m3 1.14 - - - 1.14
m2 6.42 - - - 6.42
- - - -
und 2.00 - - - 2.00
- - - -
m2 4.08 - - - 4.08
- - - -
und 2.00 - - - 2.00
- - - -
- - - -
m2 3.24 2.16 2.16 1.08
m2 3.24 2.16 2.16 1.08
- - -
m3 2.91 1.94 1.94 0.97
m2 3.24 2.16 2.16 1.08
m3 3.48 2.32 2.32 1.16
- - -
m3 3.06 2.04 2.04 1.02
m2 9.72 6.48 6.48 3.24
- - -
und 3 - - 3.00
- - -
m2 11.76 - - 11.76
- - -
und 1.00 1.00 1.00 -
und 2.00 1.00 1.00 1.00
- - - -
- - - -
m2 172.80 - - - 172.80
m2 172.80 - - - 172.80
- - - -
m3 92.16 - - - 92.16
m2 115.20 - - - 115.20
m3 55.20 - - - 55.20
m3 92.16 - - - 92.16
- - - -
m3 4.61 - - - 4.61
m2 5.76 - - - 5.76
- - - -
und 48.00 48.00 48.00 -
- - - -
- - - -
- - - -
m2 824.50 824.50 - 824.50 -
m2 824.50 824.50 - 824.50 -
- - - -
m3 659.60 - 184.00 184.00 475.60
m 1,649.00 - 460.00 460.00 1,189.00
m 1,649.00 - 460.00 460.00 1,189.00
m 1,649.00 - 460.00 460.00 1,189.00
m3 494.70 - 138.00 138.00 356.70
- - - -
m 460.00 - 460.00 460.00 -
m 180.00 - - - 180.00
m 520.00 - - - 520.00
m 489.00 - - - 489.00
- - - -
m 1,649.00 - - - 1,649.00
- - - -
- - - -
m2 1.62 - - - 1.62
m2 1.62 - - - 1.62
- - - -
m3 0.97 - - - 0.97
m2 1.62 - - - 1.62
m3 0.97 - - - 0.97
- - - -
m3 1.01 - - - 1.01
m2 18.9 - - - 18.90
- - - -
m2 18.90 - - - 18.90
- - - -
m2 8.48 - - - 8.48
- - - -
und 2.00 - - - 2.00
- - - -
m2 15.3 - - - 15.30
- - - -
und 2.00 - - - 2.00
- - - -
- - - -
- - - -
m2 1.85 - - - 1.85
m2 1.85 - - - 1.85
- - - -
m3 1.90 - - - 1.90
m2 1.55 - - - 1.55
m3 2.37 - - - 2.37
- - - -
m2 2.56 - - - 2.56
m3 0.07 - - - 0.07
m3 0.04 - - - 0.04
m2 0.75 - - - 0.75
- - - -
m3 0.87 - - - 0.87
m2 10.16 - - - 10.16
kg 27.10 - - - 27.10
- - - -
m2 0.87 - - - 0.87
- - - -
m2 6.24 - - - 6.24
- - - -
und 1.00 - - - 1.00
- - - -
m2 5.72 - - - 5.72
- - - -
und 1.00 - - - 1.00
- - - -
- - - -
m2 1,287.87 1,287.87 - 1,287.87 -
m2 1,287.87 1,287.87 - 1,287.87 -
- - - -
m3 1287.87 659.15 659.15 628.72
m 2,575.73 1,318.29 1,318.29 1,257.44
m 2,575.73 1,318.29 1,318.29 1,257.44
m 2,575.73 1,318.29 1,318.29 1,257.44
m3 1030.29 527.32 527.32 502.97
- - -
m 2,406.50 1,149.06 1,149.06 1,257.44
m 169.23 169.23 169.23 -
- - - -
m 2,575.73 - - - 2,575.73
- - - -
- - - -
m2 1.62 - - - 1.62
m2 1.62 - - - 1.62
- - - -
m3 0.97 - - - 0.97
m2 1.62 - - - 1.62
m3 0.97 - - - 0.97
- - - -
m3 1.01 - - - 1.01
m2 18.90 - - - 18.90
- - - -
m2 18.90 - - - 18.90
- - - -
m2 8.48 - - - 8.48
- - - -
und 2 - - - 2.00
- - - -
m2 15.30 - - - 15.30
- - - -
und 2.00 - - - 2.00
- - - -
- - - -
m2 4.32 - - - 4.32
m2 4.32 - - - 4.32
- - - -
m3 1.96 - - - 1.96
m2 2.30 - - - 2.30
m3 1.84 - - - 1.84
- - - -
m3 0.09 - - - 0.09
m3 0.25 - - - 0.25
- - - -
m3 1.14 - - - 1.14
m2 6.42 - - - 6.42
- - - -
und 2 - - - 2.00
- - - -
m2 4.08 - - - 4.08
- - - -
und 2.00 - - - 2.00
- - - -
- - - -
m2 4.32 - - - 4.32
m2 4.32 - - - 4.32
- - - -
m3 3.88 - - - 3.88
m2 4.32 - - - 4.32
m3 4.64 - - - 4.64
- - - -
m3 4.08 - - - 4.08
m2 12.96 - - - 12.96
- - - -
und 4.00 - - - 4.00
- - - -
m2 15.68 - - - 15.68
- - - -
und 1.00 - - - 1.00
und 3.00 - - - 3.00
- - - -
- - - -
m2 36.00 - - - 36.00
m2 36 - - - 36.00
- - - -
m3 19.20 - - - 19.20
m2 24.00 - - - 24.00
m3 17.2 - - - 17.20
m3 19.20 - - - 19.20
- - - -
m3 0.96 - - - 0.96
m2 1.20 - - - 1.20
- - - -
und 10.00 - - - 10.00
- - - -
- - - -
glb 1.00 1.00 - 1.00 -
glb 1.00 0.90 0.90 0.10
- - - -
- - - -
m2 517.22 517.22 - 517.22 -
m2 517.22 517.22 - 517.22 -
- - - -
m3 517.22 513.61 3.61 517.22 -
m 1,034.43 994.90 39.53 1,034.43 -
m 1,034.43 994.90 39.53 1,034.43 -
m 1,034.43 994.90 39.53 1,034.43 -
m3 362.05 362.02 0.03 362.05 -
- - -
m 1034.43 994.90 39.53 1,034.43 -
- - -
m 1,034.43 994.90 39.53 1,034.43 -
- - - -
- - - -
m2 210.61 210.61 - 210.61 -
m2 210.61 210.61 - 210.61 -
m 210.61 210.61 - 210.61 -
- - - -
m3 210.61 210.61 210.61 -
m 421.21 421.21 421.21 -
m 421.21 421.21 421.21 -
m 421.21 421.21 421.21 -
m3 252.73 252.73 252.73 -
- - -
m 421.21 421.21 421.21 -
- - -
m 421.21 421.21 421.21 -
- - - -
- - - -
- - - -
m2 28.15 28.15 - 28.15 -
m2 28.15 28.15 - 28.15 -
- - - -
m3 32.37 32.37 - 32.37 -
m2 28.15 28.15 - 28.15 -
m2 80.93 80.93 - 80.93 -
m3 40.46 40.46 40.46 -
- - - -
m3 3.27 3.27 - 3.27 -
m3 1.27 1.15 1.15 0.12
m3 19.79 19.79 - 19.79 -
m3 80.93 80.93 - 80.93 -
- - - -
m3 28.15 28.15 - 28.15 -
m2 540.85 540.85 - 540.85 -
kg 34.75 34.75 - 34.75 -
und 14 14.00 - 14.00 -
- - - -
m2 115.67 115.67 - 115.67 -
- - - -
- - - -
m2 30.16 28.15 28.15 2.01
m2 30.16 28.15 28.15 2.01
- - -
m3 67.86 64.54 64.54 3.32
m2 30.16 28.15 28.15 2.01
m2 169.65 161.35 161.35 8.30
m3 84.82 79.17 79.17 5.65
- - -
m3 3.51 3.37 3.37 0.14
m3 1.36 1.27 1.27 0.09
m3 35.72 33.34 33.34 2.38
m2 169.65 158.34 158.34 11.31
- - -
m3 30.16 28.15 28.15 2.01
m2 37.23 34.75 34.75 2.48
kg 579.48 540.85 540.85 38.63
und 15.00 14.00 14.00 1.00
- - -
m2 206.87 193.08 193.08 13.79
- - - -
- - - -
m2 8.04 - - - 8.04
m2 8.04 - - - 8.04
- - - -
m3 44.23 - - - 44.23
m2 8.04 - - - 8.04
m2 110.58 - - - 110.58
m3 55.29 - - - 55.29
- - - -
m3 0.93 - - - 0.93
m3 0.36 - - - 0.36
m3 20.96 - - - 20.96
m2 110.58 - - - 110.58
- - - -
m3 8.04 - - - 8.04
m2 154.53 - - - 154.53
kg 9.93 - - - 9.93
und 4 - - - 4.00
- - - -
m2 120.51 - - - 120.51
- - - -
- - - -
m2 237.60 - 16.20 16.20 221.40
m2 237.60 - 16.20 16.20 221.40
- - - -
m3 237.60 - 16.20 16.20 221.40
m2 528.00 - 36.00 36.00 492.00
m3 528.00 - 36.00 36.00 492.00
m3 528.00 - 36.00 36.00 492.00
- - - -
m3 8.45 - - - 8.45
m2 8.45 - - - 8.45
- - - -
und 88.00 - - - 88.00
- - - -
- - - -
- - - -
- - - -
m2 328.86 328.86 - 328.86 -
m2 328.86 328.86 - 328.86 -
- - -
- - -
m3 81.40 81.40 - 81.40 0.00
m3 101.59 101.59 - 101.59 -
- - -
m3 71.69 71.69 71.69 (0.00)
m2 198.07 198.07 - 198.07 0.00
m3 12.38 12.38 - 12.38 0.00
m3 37.80 35.40 35.40 2.40
m 94.5 - - 94.50
- - - -
- - - -
m3 113.95 - - - 113.95
m3 142.44 - - - 142.44
m2 137.34 - - - 137.34
- - - -
m3 207.14 - - - 207.14
kg 974.50 - - - 974.50
m3 33.79 - - - 33.79
- - - -
- - - -
m2 98.91 92.63 92.63 6.28
kg 644.87 644.87 644.87 -
m3 15.67 14.68 14.68 0.99
- - - -
m2 688.21 666.36 666.36 21.85
- - - -
m2 295.63 - - - 295.63
m2 120.02 - - - 120.02
- - - -
m2 97.97 - - - 97.97
- - - -
- - - -
m 22.47 - - - 22.47
m 53.03 - - - 53.03
- - - -
m2 283.12 - - - 283.12
- - - -
- - - -
m2 98.28 - - - 98.28
m2 47.38 - - - 47.38
- - - -
und 189.00 - - - 189.00
und 63.00 - - - 63.00
- - - -
- - - -
m3 1.8 - - - 1.80
m3 2.36 - - - 2.36
- - - -
m3 1.80 - - - 1.80
m2 260.13 - - - 260.13
- - - -
m3 4.94 - - - 4.94
kg 345.40 - - - 345.40
m2 130.35 - - - 130.35
- - - -
m2 39.50 - - - 39.50
- - - -
m2 116.20 - - - 116.20
- - - -
- - - -
und 63.00 - - 63.00
und 63.00 - - - 63.00
und 63.00 - - - 63.00
und 378.00 366.00 366.00 12.00
und 378.00 366.00 366.00 12.00
und 63.00 61.00 61.00 2.00
und 252.00 244.00 244.00 8.00
pto 63.00 61.00 61.00 2.00
und 126.00 - - - 126.00
und 189.00 - - - 189.00
- - - -
pto 252.00 - - - 252.00
m 420.84 267.20 140.28 407.48 13.36
und 189.00 120.00 63.00 183.00 6.00
und 252.00 160.00 84.00 244.00 8.00
und 126.00 80.00 42.00 122.00 4.00
und 126.00 80.00 42.00 122.00 4.00
und 126.00 80.00 42.00 122.00 4.00
und 63.00 - - 63.00
und 63.00 40.00 21.00 61.00 2.00
und 126.00 - - 126.00
- - - -
- - - -
m2 1,523.34 1,474.98 1,474.98 48.36
m2 1,523.34 1,474.98 1,474.98 48.36
- - - -
- - - -
- - - -
m3 35.91 34.77 34.77 1.14
m2 37.80 36.60 36.60 1.20
m3 44.89 43.47 43.47 1.42
- - -
m2 143.64 139.08 139.08 4.56
kg 87.32 84.55 84.55 2.77
m3 18.77 18.18 18.18 0.59
- - -
m2 167.58 162.26 162.26 5.32
- - -
m2 167.58 162.26 162.26 5.32
- - -
m2 57.96 - - - 57.96
- - - -
und 126.00 122.00 122.00 4.00
- - -
m3 89.11 86.28 86.28 2.83
m3 44.55 43.13 43.13 1.42
m 278.46 269.62 269.62 8.84
- - - -
- - - -
- - - -
m3 6.62 6.41 6.41 0.21
m2 13.23 12.81 12.81 0.42
m3 8.27 8.01 8.01 0.26
- - - -
m3 3.34 3.24 3.24 0.10
m3 47.25 45.75 45.75 1.50
- - - -
m3 19.22 18.61 18.61 0.61
kg 44.32 42.91 42.91 1.41
m3 0.66 0.64 0.64 0.02
- - -
m2 42.53 41.18 41.18 1.35
- - -
m2 42.53 41.18 41.18 1.35
- - - -
m2 19.22 - - - 19.22
- - - -
- - - -
m3 230.20 222.89 222.89 7.31
m3 37.80 36.60 36.60 1.20
m3 287.75 278.61 278.61 9.14
- - -
m2 132.30 128.10 128.10 4.20
- - -
und 63.00 63.00 63.00 -
- - -
- - -
m3 28.35 27.45 27.45 0.90
m2 35.44 34.32 34.32 1.12
m3 35.44 34.32 34.32 1.12
- - - -
m3 13.24 12.82 12.82 0.42
m3 114.66 111.02 111.02 3.64
- - -
m2 23.47 22.73 22.73 0.74
kg 58.34 56.49 56.49 1.85
m3 1.77 1.72 1.72 0.05
- - -
m2 114.66 111.02 111.02 3.64
- - -
m2 114.66 111.02 111.02 3.64
- - - -
und 126.00 122.00 122.00 4.00
und 126.00 122.00 122.00 4.00
und 63.00 61.00 61.00 2.00
- - - -
m3 114.51 110.88 110.88 3.63
m3 57.25 55.43 55.43 1.82
m 357.84 346.48 346.48 11.36
- - -
- - -
m3 9.45 9.15 9.15 0.30
m2 18.90 18.30 18.30 0.60
m3 17.48 16.92 16.92 0.56
- - -
m3 3.78 3.66 3.66 0.12
m3 51.03 49.41 49.41 1.62
- - -
m3 25.83 25.01 25.01 0.82
kg 58.34 56.49 56.49 1.85
m3 0.95 0.92 0.92 0.03
- - -
m2 51.03 49.41 49.41 1.62
- - -
m2 51.03 49.41 49.41 1.62
- - - -
m2 24.57 - - - 24.57
- - - -
- - - -
m3 142.13 - 90.24 90.24 51.89
m2 177.66 - 112.80 112.80 64.86
m3 71.06 - 45.12 45.12 25.94
m3 124.36 - 78.96 78.96 45.40
- - - -
m3 26.65 - 16.92 16.92 9.73
m3 26.65 - 16.92 16.92 9.73
m3 40.08 - 25.45 25.45 14.63
- - - -
m2 177.66 - 112.80 112.80 64.86
m 296.10 - 188.00 188.00 108.10
- - - -
- - - -
- - - -
m2 182.70 172.26 10.44 182.70 -
m2 182.70 172.26 10.44 182.70 -
- - -
- - -
m3 45.22 42.63 2.59 45.22 -
m3 56.44 53.21 3.23 56.44 -
- - -
m3 39.83 37.56 2.27 39.83 -
m2 110.04 103.76 6.28 110.04 -
m3 6.88 6.49 0.39 6.88 0.00
m3 21.00 13.20 13.20 7.80
m 52.50 33.00 33.00 19.50
- - - -
- - - -
m3 63.31 - 1.81 1.81 61.50
m3 79.14 - 2.26 2.26 76.88
m2 76.30 - 2.18 2.18 74.12
- - - -
m3 115.08 - 3.29 3.29 111.79
kg 541.39 - 15.47 15.47 525.92
m3 18.77 - 0.54 0.54 18.23
- - - -
- - - -
m2 54.95 51.81 51.81 3.14
kg 358.26 337.78 20.48 358.26 -
m3 8.71 8.21 8.21 0.50
- - -
m2 382.34 360.50 360.50 21.84
- - - -
m2 164.24 - 148.26 148.26 15.98
m2 66.68 - 49.94 49.94 16.74
- - - -
m2 54.43 - - - 54.43
- - - -
- - - -
m 12.48 - - - 12.48
m 29.46 - - - 29.46
- - - -
m2 157.29 - - - 157.29
- - - -
- - - -
m2 54.60 - - - 54.60
m2 26.32 - - - 26.32
- - - -
und 105.00 - - - 105.00
und 35.00 - - - 35.00
- - - -
- - - -
m3 1.00 - - - 1.00
m3 1.31 - - - 1.31
- - - -
m3 1.00 - - - 1.00
m2 144.52 - - - 144.52
- - - -
m3 2.74 - - - 2.74
kg 191.89 - - - 191.89
m2 72.41 - - - 72.41
- - - -
m2 21.95 - - - 21.95
- - - -
m2 64.56 - - - 64.56
- - - -
- - - -
und 35.00 - - - 35.00
und 35.00 - - - 35.00
und 35.00 - 30.00 30.00 5.00
und 210.00 198.00 12.00 210.00 -
und 210.00 198.00 12.00 210.00 -
und 35.00 33.00 2.00 35.00 -
und 140.00 132.00 8.00 140.00 -
pto 35.00 33.00 2.00 35.00 -
und 70.00 - - - 70.00
und 105.00 - - - 105.00
- - - -
pto 140.00 - - - 140.00
m 233.80 146.96 73.48 220.44 13.36
und 105.00 66.00 33.00 99.00 6.00
und 140.00 88.00 44.00 132.00 8.00
und 70.00 44.00 22.00 66.00 4.00
und 70.00 44.00 22.00 66.00 4.00
und 70.00 44.00 22.00 66.00 4.00
und 35.00 - - 35.00
und 35.00 22.00 11.00 33.00 2.00
und 70.00 - - - 70.00
- - - -
- - - -
m2 846.30 797.94 797.94 48.36
m2 846.30 797.94 797.94 48.36
- - - -
- - - -
- - - -
m3 19.95 18.81 18.81 1.14
m2 21.00 19.80 19.80 1.20
m3 24.94 23.51 23.51 1.43
- - -
m3 79.80 75.24 75.24 4.56
kg 48.51 45.73 45.73 2.78
m3 10.43 9.83 9.83 0.60
- - -
m2 93.10 87.78 87.78 5.32
- - -
m2 93.10 87.78 87.78 5.32
- - -
m2 32.20 - - 32.20
- - -
und 70.00 66.00 66.00 4.00
- - -
m3 49.50 46.67 46.67 2.83
m3 24.75 23.33 23.33 1.42
m 154.70 145.86 145.86 8.84
- - - -
- - - -
- - - -
m3 3.68 3.47 3.47 0.21
m2 7.35 6.93 6.93 0.42
m3 4.59 4.33 4.33 0.26
- - -
m3 1.86 1.76 1.76 0.10
m3 26.25 24.75 24.75 1.50
- - -
m3 10.68 10.07 10.07 0.61
kg 24.62 23.21 23.21 1.41
m3 0.37 0.35 0.35 0.02
- - -
m2 23.63 22.28 22.28 1.35
- - -
m2 23.63 22.28 22.28 1.35
- - - -
m2 10.68 - - - 10.68
- - - -
- - - -
m3 127.89 120.58 120.58 7.31
m3 21.00 19.80 19.80 1.20
m3 159.86 - - - 159.86
- - - -
m2 73.50 69.30 69.30 4.20
- - - -
und 35.00 33.00 33.00 2.00
- - - -
- - - -
m3 15.75 14.85 14.85 0.90
m2 19.69 18.56 18.56 1.13
m3 19.69 18.56 18.56 1.13
- - -
m3 7.35 6.93 6.93 0.42
m3 63.70 60.06 60.06 3.64
- - -
m3 13.04 12.29 12.29 0.75
kg 32.41 30.55 30.55 1.86
m3 0.98 0.92 0.92 0.06
- - -
m2 63.70 60.06 60.06 3.64
- - -
m2 63.70 60.06 60.06 3.64
- - -
und 70.00 66.00 66.00 4.00
und 70.00 66.00 66.00 4.00
und 35.00 33.00 33.00 2.00
- - -
m3 63.62 59.99 59.99 3.63
m3 31.81 29.99 29.99 1.82
m 198.80 187.44 187.44 11.36
- - - -
- - - -
m3 5.25 4.95 4.95 0.30
m2 10.50 9.90 9.90 0.60
m3 9.71 9.16 9.16 0.55
- - -
m3 2.10 1.98 1.98 0.12
m3 28.35 26.73 26.73 1.62
- - -
m3 14.35 13.53 13.53 0.82
kg 32.41 30.55 30.55 1.86
m3 0.53 0.50 0.50 0.03
- - -
m2 28.35 26.73 26.73 1.62
- - -
m2 28.35 26.73 26.73 1.62
- - - -
m2 13.65 - - - 13.65
- - - -
- - - -
m3 78.96 - 56.40 56.40 22.56
m2 98.70 - 70.50 70.50 28.20
m3 39.48 - 28.20 28.20 11.28
m3 69.09 - 49.35 49.35 19.74
- - - -
m3 14.81 - 10.58 10.58 4.23
m3 14.81 - 10.58 10.58 4.23
m3 22.27 - 15.91 15.91 6.36
- - - -
m2 98.70 - 70.50 70.50 28.20
m 164.50 - 117.50 117.50 47.00
- - - -
- - - -
- - - -
m2 250.56 245.34 245.34 5.22
m2 250.56 245.34 245.34 5.22
- - -
- - -
m3 62.02 60.72 60.72 1.30
m3 77.40 75.79 75.79 1.61
- - -
m3 54.62 53.49 53.49 1.13
m2 150.91 147.77 147.77 3.14
m3 9.43 9.23 9.23 0.20
m3 28.80 24.00 24.00 4.80
m 72.00 - - - 72.00
- - - -
- - - -
m3 86.82 - - - 86.82
m3 108.53 - - - 108.53
m2 104.64 - - - 104.64
- - - -
m3 157.82 - - - 157.82
kg 742.48 - - - 742.48
m3 25.74 - - - 25.74
- - - -
- - - -
m2 75.36 73.79 73.79 1.57
kg 491.33 481.09 481.09 10.24
m3 11.94 9.20 9.20 2.74
- - -
m2 524.35 513.43 513.43 10.92
- - - -
m2 225.24 - - - 225.24
m2 91.44 - - - 91.44
- - - -
m2 74.64 - - - 74.64
- - - -
- - - -
m 17.12 - - - 17.12
m 40.40 - - - 40.40
- - - -
m2 215.71 - - - 215.71
- - - -
- - - -
m2 74.88 - - - 74.88
m2 36.10 - - - 36.10
- - - -
und 144.00 - - - 144.00
und 48.00 - - - 48.00
- - - -
- - - -
m3 1.37 - - - 1.37
m3 1.80 - - - 1.80
- - - -
m3 1.37 - - - 1.37
m2 198.19 - - - 198.19
- - - -
m3 3.76 - - - 3.76
kg 263.16 - - - 263.16
m2 99.31 - - - 99.31
- - - -
m2 30.10 - - - 30.10
- - - -
m2 88.54 - - - 88.54
- - - -
- - - -
und 48.00 - - - 48.00
und 48.00 - - - 48.00
und 48.00 - - - 48.00
und 288.00 282.00 282.00 6.00
und 288.00 282.00 282.00 6.00
und 48.00 47.00 47.00 1.00
und 192.00 188.00 188.00 4.00
pto 48.00 47.00 47.00 1.00
und 96.00 - - - 96.00
und 144.00 - - - 144.00
- - - -
pto 192.00 - - - 192.00
m 320.64 313.96 313.96 6.68
und 144.00 141.00 141.00 3.00
und 192.00 188.00 188.00 4.00
und 96.00 94.00 94.00 2.00
und 96.00 94.00 94.00 2.00
und 96.00 94.00 94.00 2.00
und 48.00 - - 48.00
und 48.00 47.00 47.00 1.00
und 96.00 - - 96.00
- - -
- - -
m2 1,160.64 1,136.46 1,136.46 24.18
m2 1,160.64 1,136.46 1,136.46 24.18
- - -
- - -
- - -
m3 27.36 26.79 26.79 0.57
m2 28.80 28.20 28.20 0.60
m3 34.20 33.49 33.49 0.71
- - -
m3 109.44 107.16 107.16 2.28
kg 66.53 65.14 65.14 1.39
m3 14.30 14.00 14.00 0.30
- - -
m2 127.68 125.02 125.02 2.66
- - -
m2 127.68 125.02 125.02 2.66
- - -
m2 44.16 - - 44.16
- - -
und 96.00 94.00 94.00 2.00
- - - -
m3 67.89 66.48 66.48 1.41
m3 33.95 33.24 33.24 0.71
m 212.16 207.74 207.74 4.42
- - - -
- - - -
- - - -
m3 5.04 4.94 4.94 0.10
m2 10.08 9.87 9.87 0.21
m3 6.30 6.17 6.17 0.13
- - -
m3 2.54 2.48 2.48 0.06
m3 36.00 35.25 35.25 0.75
- - -
m3 14.64 14.34 14.34 0.30
kg 33.77 33.07 33.07 0.70
m3 0.50 0.49 0.49 0.01
- - -
m2 32.40 31.73 31.73 0.67
- - -
m2 32.40 31.73 31.73 0.67
- - - -
m2 14.64 - - - 14.64
- - - -
- - - -
m3 175.39 171.74 171.74 3.65
m3 28.80 28.20 28.20 0.60
m3 219.24 214.67 214.67 4.57
- - -
m2 100.80 98.70 98.70 2.10
- - -
und 48.00 47.00 47.00 1.00
- - - -
- - - -
m3 21.60 21.15 21.15 0.45
m2 27.00 26.44 26.44 0.56
m3 27.00 26.44 26.44 0.56
- - -
m3 10.09 9.88 9.88 0.21
m3 87.36 85.54 85.54 1.82
- - -
m3 17.88 17.51 17.51 0.37
kg 44.45 43.52 43.52 0.93
m3 1.35 1.32 1.32 0.03
- - -
m2 87.36 85.54 85.54 1.82
- - -
m2 87.36 85.54 85.54 1.82
- - -
und 96.00 94.00 94.00 2.00
und 96.00 94.00 94.00 2.00
und 48.00 47.00 47.00 1.00
- - - -
m3 87.24 85.42 85.42 1.82
m3 43.62 42.71 42.71 0.91
m 272.64 266.96 266.96 5.68
- - - -
- - - -
m3 7.20 7.05 7.05 0.15
m2 14.40 14.10 14.10 0.30
m3 13.32 13.05 13.05 0.27
- - - -
m3 2.88 2.82 2.82 0.06
m3 38.88 38.07 38.07 0.81
- - -
m3 19.68 19.27 19.27 0.41
kg 44.45 43.52 43.52 0.93
m3 0.72 0.71 0.71 0.01
- - -
m2 38.88 38.07 38.07 0.81
- - -
m2 38.88 38.07 38.07 0.81
- - - -
m2 18.72 - - - 18.72
- - - -
- - - -
m3 108.29 - - - 108.29
m2 135.36 - - - 135.36
m3 54.14 - - - 54.14
m3 94.75 - - - 94.75
- - - -
m3 20.30 - - - 20.30
m3 20.30 - - - 20.30
m3 30.54 - - - 30.54
- - - -
m2 135.36 - - - 135.36
m 225.60 - - - 225.60
- - - -
- - - -
- - - -
m2 52.20 36.54 36.54 15.66
m2 52.20 36.54 36.54 15.66
- - -
- - -
m3 12.92 9.04 9.04 3.88
m3 16.13 11.29 11.29 4.84
- - -
m3 11.38 7.97 7.97 3.41
m2 31.44 22.00 22.00 9.44
m3 1.97 1.38 1.38 0.59
m3 6.00 - - 6.00
m 15.00 - - - 15.00
- - - -
- - - -
m3 18.09 - - - 18.09
m3 22.61 - - - 22.61
m2 21.80 - - - 21.80
- - - -
m3 32.88 - - - 32.88
kg 154.68 - - - 154.68
m3 5.36 - - - 5.36
- - - -
- - - -
m2 15.70 9.42 9.42 6.28
kg 102.36 71.66 71.66 30.70
m3 2.49 1.49 1.49 1.00
- - -
m2 109.24 65.54 65.54 43.70
- - -
m2 46.93 - - - 46.93
m2 19.05 - - - 19.05
- - - -
m2 15.55 - - - 15.55
- - - -
- - - -
m 3.57 - - - 3.57
m 8.42 - - - 8.42
- - - -
m2 44.94 - - - 44.94
- - - -
- - - -
m2 15.60 - - - 15.60
m2 7.52 - - - 7.52
- - - -
und 30.00 - - - 30.00
und 10.00 - - - 10.00
- - - -
- - - -
m3 0.29 - - - 0.29
m3 0.38 - - - 0.38
- - - -
m3 0.29 - - - 0.29
m2 41.29 - - - 41.29
- - - -
m3 0.78 - - - 0.78
kg 54.83 - - - 54.83
m2 20.69 - - - 20.69
- - - -
m2 6.27 - - - 6.27
- - - -
m2 18.45 - - - 18.45
- - - -
- - - -
und 10.00 - - - 10.00
und 10.00 - - - 10.00
und 10.00 - - - 10.00
und 60.00 36.00 6.00 42.00 18.00
und 60.00 36.00 6.00 42.00 18.00
und 10.00 6.00 1.00 7.00 3.00
und 40.00 24.00 4.00 28.00 12.00
pto 10.00 6.00 1.00 7.00 3.00
und 20.00 - - - 20.00
und 30.00 - - - 30.00
- - - -
pto 40.00 - - - 40.00
m 66.80 - - - 66.80
und 30.00 - - - 30.00
und 40.00 - - - 40.00
und 20.00 - - - 20.00
und 20.00 - - - 20.00
und 20.00 - - - 20.00
und 10.00 - - - 10.00
und 10.00 - - - 10.00
und 20.00 - - - 20.00
- - - -
- - - -
m2 241.80 145.08 24.18 169.26 72.54
m2 241.80 145.08 24.18 169.26 72.54
- - - -
- - - -
- - - -
m3 5.70 3.42 0.57 3.99 1.71
m2 6.00 3.60 0.60 4.20 1.80
m3 7.13 4.28 0.71 4.99 2.14
- - - -
m3 22.80 13.68 2.28 15.96 6.84
kg 13.86 8.32 1.39 9.71 4.15
m3 2.98 1.79 0.30 2.09 0.89
- - - -
m2 26.60 15.96 2.66 18.62 7.98
- - - -
m2 26.60 15.96 2.66 18.62 7.98
- - - -
m2 9.20 - - - 9.20
- - - -
und 20.00 12.00 2.00 14.00 6.00
- - - -
m3 14.14 8.48 1.41 9.89 4.25
m3 7.07 4.25 0.71 4.96 2.11
m 44.20 26.52 4.42 30.94 13.26
- - - -
- - - -
- - - -
m3 1.05 0.64 0.11 0.75 0.30
m2 2.10 1.26 0.21 1.47 0.63
m3 1.31 0.79 0.13 0.92 0.39
- - - -
m3 0.53 0.32 0.05 0.37 0.16
m3 7.50 4.50 0.75 5.25 2.25
- - - -
m3 3.05 1.84 0.31 2.15 0.90
kg 7.04 4.22 0.70 4.92 2.12
m3 0.11 0.07 0.01 0.08 0.03
- - - -
m2 6.75 4.06 0.68 4.74 2.01
- - - -
m2 6.75 4.06 0.68 4.74 2.01
- - - -
m2 3.05 - - - 3.05
- - - -
- - - -
m3 36.54 21.92 3.65 25.57 10.97
m3 6.00 3.60 0.60 4.20 1.80
m3 45.68 27.41 4.57 31.98 13.70
- - - -
m2 21.00 12.60 2.10 14.70 6.30
- - - -
und 10.00 6.00 6.00 4.00
- - - -
- - - -
m3 4.50 2.70 0.45 3.15 1.35
m2 5.63 3.38 0.56 3.94 1.69
m3 5.63 3.38 0.56 3.94 1.69
- - - -
m3 2.10 1.26 0.21 1.47 0.63
m3 18.20 10.92 1.82 12.74 5.46
- - - -
m3 3.73 2.24 0.37 2.61 1.12
kg 9.26 5.56 0.93 6.49 2.77
m3 0.28 0.17 0.03 0.20 0.08
- - - -
m2 18.20 10.92 1.82 12.74 5.46
- - - -
m2 18.20 10.92 1.82 12.74 5.46
- - - -
und 20.00 12.00 2.00 14.00 6.00
und 20.00 12.00 2.00 14.00 6.00
und 10.00 6.00 1.00 7.00 3.00
- - - -
m3 18.18 10.91 1.82 12.73 5.45
m3 9.09 5.46 0.91 6.37 2.72
m 56.80 34.08 5.68 39.76 17.04
- - - -
- - - -
m3 1.50 0.90 0.15 1.05 0.45
m2 3.00 1.80 0.30 2.10 0.90
m3 2.78 1.67 0.28 1.95 0.83
- - - -
m3 0.60 0.36 0.06 0.42 0.18
m3 8.10 4.86 0.81 5.67 2.43
- - - -
m3 4.10 2.46 0.41 2.87 1.23
kg 9.26 5.56 0.93 6.49 2.77
m3 0.15 0.10 0.02 0.12 0.03
- - - -
m2 8.10 4.86 0.81 5.67 2.43
- - - -
m2 8.10 4.86 0.81 5.67 2.43
- - - -
m2 3.90 - - - 3.90
- - - -
- - - -
m2 28.20 - - - 28.20
m3 22.56 - - - 22.56
m3 11.28 - - - 11.28
m3 19.74 - - - 19.74
- - - -
m3 4.23 - - - 4.23
m3 4.23 - - - 4.23
m3 6.36 - - - 6.36
- - - -
m2 28.20 - - - 28.20
m 47.00 - - - 47.00
- - - -
- - - -
- - - -
m2 5.33 5.33 - 5.33 -
m2 5.33 5.33 - 5.33 -
- - - -
m3 2.72 2.72 2.72 -
m2 4.54 4.54 4.54 -
m3 0.53 0.53 0.53 -
m3 2.19 - - 2.19
- - -
m3 0.47 0.47 0.47 -
- - -
m3 2.21 2.21 2.21 -
kg 95.82 95.82 95.82 -
m2 20.72 20.72 20.72 -
- - -
m2 45.56 45.56 45.56 -
- - -
m2 9.12 9.12 9.12 -
m2 10.36 10.36 10.36 -
- - -
und 1.00 - - - 1.00
und 2.00 - - - 2.00
- - - -
- - - -
m2 1.16 1.16 - 1.16 -
m2 1.16 1.16 - 1.16 -
- - - -
m3 1.17 1.17 1.17 -
m2 1.16 1.16 1.16 -
m3 0.10 0.10 0.10 -
m3 1.34 1.34 1.34 -
- - -
m3 0.47 0.47 0.47 -
- - -
m3 0.47 - - 0.47
kg 92.60 92.60 92.60 -
m2 5.13 5.13 5.13 -
- - - -
m2 5.13 - - - 5.13
- - - -
m2 2.59 - - - 2.59
- - - -
und 2.00 - - - 2.00
und 2.00 - - - 2.00
- - - -
- - - -
m2 36.40 36.40 - 36.40 -
m2 36.40 36.40 - 36.40 -
- - - -
m3 96.46 96.46 - 96.46 -
m2 36.40 36.40 - 36.40 -
m3 15.30 15.30 15.30 -
m3 81.16 81.16 - 81.16 -
- - - -
m2 36.40 36.40 - 36.40 -
und 2.00 2.00 2.00 -
- - - -
m3 29.50 29.50 - 29.50 -
kg 1,566.28 1,566.28 - 1,566.28 -
m2 223.48 223.48 - 223.48 -
- - - -
m2 126.76 126.76 126.76 -
- - - -
m 5.00 - - - 5.00
m 5.00 - - - 5.00
und 1.00 - - - 1.00
und 1.00 - - - 1.00
und 3.00 - - - 3.00
und 2.00 - - - 2.00
- - - -
- - - -
m2 42.78 - - - 42.78
m2 42.78 - - - 42.78
- - - -
m3 115.71 - - - 115.71
m2 44.85 - - - 44.85
m3 23.76 - - - 23.76
m3 23.76 - - - 23.76
m3 9.15 - - - 9.15
m3 1.83 - - - 1.83
m3 3.97 - - - 3.97
m3 7.78 - - - 7.78
- - - -
m3 8.10 - - - 8.10
kg 500.17 - - - 500.17
m2 45.56 - - - 45.56
- - - -
m2 12.60 - - - 12.60
m2 2.93 - - - 2.93
- - - -
m2 58.43 - - - 58.43
- - - -
m 12.78 - - - 12.78
m 7.20 - - - 7.20
m2 35.00 - - - 35.00
- - - -
- - - -
m2 3.36 3.36 - 3.36 -
m2 3.36 3.36 - 3.36 -
- - - -
m3 3.32 3.32 3.32 -
m2 3.36 3.36 3.36 -
m3 6.92 6.92 6.92 -
- - -
m2 12.66 12.66 12.66 -
kg 92.60 92.60 92.60 -
m3 1.25 - - 1.25
- - - -
m2 12.66 - - - 12.66
- - - -
m2 8.24 - - - 8.24
- - - -
und 3.00 - - - 3.00
und 6.00 - - - 6.00
- - - -
m 35.00 - - - 35.00
- - - -
- - - -
m2 137.41 137.41 - 137.41 -
m2 37.61 37.61 - 37.61 -
- - - -
m3 625.23 625.23 - 625.23 -
m2 137.41 137.41 - 137.41 -
m3 781.54 781.54 - 781.54 -
- - - -
m3 20.94 6.98 6.98 13.96
- - -
m3 20.94 6.98 6.98 13.96
kg 1,378.44 459.48 459.48 918.96
m2 152.73 50.92 50.92 101.82
- - -
m2 333.75 111.26 111.26 222.50
- - -
m3 128.60 21.43 21.43 107.17
- - - -
m 36.00 - - - 36.00
m 18.00 - - - 18.00
- - - -
- - - -
m2 108.00 9.00 9.00 99.00
m2 108.00 9.00 9.00 99.00
- - -
m3 216.00 18.00 18.00 198.00
m 180.00 15.00 15.00 165.00
m 180.00 15.00 15.00 165.00
m 180.00 15.00 15.00 165.00
m3 97.20 8.10 8.10 89.10
- - -
m 180.00 15.00 15.00 165.00
- - - -
- - - -
m2 60.00 - - - 60.00
m2 60.00 - - - 60.00
- - - -
m3 2.98 - - - 2.98
m2 15.80 - - - 15.80
m3 0.60 - - - 0.60
m3 0.30 - - - 0.30
- - - -
m3 2.98 - - - 2.98
- - - -
m 120.00 - - - 120.00
und 1.00 - - - 1.00
m2 3.50 - - - 3.50
- - - -
glb 1.00 0.45 0.45 0.55
- - - -
glb 1.00 0.60 0.10 0.70 0.30
¤ Item I PN°
0 01
0 01.01
0 01.01.01
0 01.01.02
0 01.01.03
0 01.01.04
0 01.01.05
0 01.02
0 01.02.01
0 01.02.02
0 01.03
0 01.03.01
0 01.03.01.01
0 01.03.01.02
0 01.03.02
0 01.03.02.01
0 01.03.02.02
0 01.03.02.03
0 01.03.02.04
0 01.03.03
0 01.03.03.01
0 01.03.03.02
0 01.03.04
0 01.03.04.01
0 01.03.04.02
0 01.03.04.03
0 01.03.05
0 01.03.05.01
0 01.03.06
0 01.03.06.01
0 01.03.06.02
0 01.03.07
0 01.03.07.01
0 01.03.07.02
0 01.03.08
0 01.03.08.01
0 01.03.08.02
0 01.03.09
0 01.03.09.01
0 01.04
0 01.04.01
0 01.04.01.01
0 01.04.01.02
0 01.04.02
0 01.04.02.01
0 01.04.02.02
0 01.04.02.03
0 01.04.02.04
0 01.04.03
0 01.04.03.01
0 01.04.04
0 01.04.04.01
0 01.04.04.02
0 01.04.04.03
0 01.04.05
0 01.04.05.01
0 01.04.06
0 01.04.06.01
0 01.04.07
0 01.04.07.01
0 01.04.07.02
0 01.04.08
0 01.04.08.01
0 01.04.09
0 01.04.09.01
0 01.05
0 01.05.01
0 01.05.01.01
0 01.05.01.02
0 01.05.02
0 01.05.02.01
0 01.05.02.02
0 01.05.02.03
0 01.05.02.04
0 01.05.02.05 2
0 01.05.03
0 01.05.03.01
0 01.05.04
0 01.05.04.01
0 01.06
0 01.06.01
0 01.06.01.01
0 01.06.01.02
0 01.06.02
0 01.06.02.01
0 01.06.02.02
0 01.06.02.03
0 01.06.03
0 01.06.03.01
0 01.06.03.02
0 01.06.04
0 01.06.04.01
0 01.06.05
0 01.06.05.01
0 01.06.06
0 01.06.06.01
0 01.06.07
0 01.06.07.01
0 01.06.08
0 01.06.08.01
0 01.07
0 01.07.01
0 01.07.01.01
0 01.07.01.02
0 01.07.02
0 01.07.02.01
0 01.07.02.02
0 01.07.02.03
0 01.07.03
0 01.07.03.01
0 01.07.03.02
0 01.07.04
0 01.07.04.01
0 01.07.04.02
0 01.07.05
0 01.07.05.01
0 01.07.06
0 01.07.06.01
0 01.07.07
0 01.07.07.01
0 01.08
0 01.08.01
0 01.08.01.01
0 01.08.01.02
0 01.08.02
0 01.08.02.01
0 01.08.02.02
0 01.08.02.03
0 01.08.03
0 01.08.03.01
0 01.08.03.02
0 01.08.03.03
0 01.08.03.04
0 01.08.04
0 01.08.04.01
0 01.08.04.02
0 01.08.04.03
0 01.08.05
0 01.08.05.01
0 01.08.06
0 01.08.06.01
0 01.08.07
0 01.08.07.01
0 01.08.08
0 01.08.08.01
0 01.08.09
0 01.08.09.01
0 01.09
0 01.09.01
0 01.09.01.01
0 01.09.01.02
0 01.09.02
0 01.09.02.01
0 01.09.02.02
0 01.09.03
0 01.09.03.01
0 01.09.04
0 01.09.04.01
0 01.09.04.02
0 01.09.04.03
0 01.09.04.04
0 01.09.05
0 01.09.05.01
0 01.09.06
0 01.09.06.01
0 01.09.06.02
0 01.09.06.03
0 01.09.06.04
0 01.09.06.05
0 01.09.06.06
0 01.10
0 01.11
0 01.12
0 01.12.01
0 01.12.01.01
0 01.12.01.02
0 01.12.02
0 01.12.02.01
0 01.12.02.02
0 01.12.02.03
0 01.12.03
0 01.12.03.01
0 01.12.04
0 01.12.04.01
0 01.12.04.02
0 01.12.04.03
0 01.12.05
0 01.12.05.01
0 01.12.06
0 01.12.06.01
0 01.12.06.02
0 01.12.07
0 01.12.07.01
0 01.12.07.02
0 01.12.08
0 01.12.08.01
0 01.12.08.02
0 01.12.08.03
0 01.12.08.04
0 01.12.09
0 01.12.09.01
0 01.13
0 01.13.01
0 01.13.01.01
0 01.13.01.02
0 01.13.02
0 01.13.02.01
0 01.13.02.02
0 01.13.02.03
0 01.13.02.04
0 01.13.03
0 01.13.03.01
0 01.13.03.02
0 01.13.04
0 01.13.04.01
0 01.13.04.02
0 01.13.04.03
0 01.13.05
0 01.13.05.01
0 01.13.06
0 01.13.06.01
0 01.13.07
0 01.13.07.01
0 01.13.07.02
0 01.13.07.03
0 01.13.08
0 01.13.08.01
0 01.13.08.02
0 01.13.08.03
0 01.13.08.04
0 01.13.09
0 01.13.09.01
0 01.13.09.02
0 01.13.09.03
0 01.13.09.04
0 01.13.10
0 01.13.10.01
0 01.13.10.02
0 01.13.11
0 01.13.11.01
0 01.14
0 01.14.01
0 01.14.01.01
0 01.14.01.02
0 01.14.02
0 01.14.02.01
0 01.14.02.02
0 01.14.02.03
0 01.14.02.04
0 01.14.03
0 01.14.03.01
0 01.14.04
0 01.14.04.01
0 01.14.04.02
0 01.14.04.03
0 01.15
0 01.15.01
0 01.15.01.01
0 01.15.01.02
0 01.15.02
0 01.15.02.01
0 01.15.02.02
0 01.15.02.03
0 01.15.03
0 01.15.03.01
0 01.15.04
0 01.15.04.01
0 01.15.04.02
0 01.15.04.03
0 01.15.05
0 01.15.05.01
0 01.15.06
0 01.15.06.01
0 01.15.07
0 01.15.07.01
0 01.15.08
0 01.15.08.01
0 01.15.09
0 01.15.09.01
0 02 2
0 02.01 2
0 02.01.01 2
0 02.01.01.01 2
0 02.01.01.02 2
0 02.01.02 2
0 02.01.02.01 2
0 02.01.02.02 2
0 02.01.02.03
0 02.01.02.04
0 02.01.02.05 2
0 02.01.03 2
0 02.01.03.01
0 02.01.04 2
0 02.01.04.01 2
0 02.02 2
0 02.02.01 2
0 02.02.01.01 2
0 02.02.01.02 2
0 02.02.02 2
0 02.02.02.01 2
0 02.02.02.02 2
0 02.02.02.03 2
0 02.02.03 2
0 02.02.03.01 2
0 02.02.03.02 2
0 02.02.04 2
0 02.02.04.01 2
0 02.02.05 2
0 02.02.05.01 2
0 02.02.06 2
0 02.02.06.01 2
0 02.02.07 2
0 02.02.07.01 2
0 02.02.08 2
0 02.02.08.01 2
0 02.03 2
0 02.03.01 2
0 02.03.01.01 2
0 02.03.01.02 2
0 02.03.02 2
0 02.03.02.01 2
0 02.03.02.02 2
0 02.03.02.03 2
0 02.03.03 2
0 02.03.03.01 2
0 02.03.03.02 2
0 02.03.04 2
0 02.03.04.01 2
0 02.03.04.02 2
0 02.03.05 2
0 02.03.05.01 2
0 02.03.06 2
0 02.03.06.01 2
0 02.03.07 2
0 02.03.07.01 2
0 02.04 2
0 02.04.01 2
0 02.04.01.01 2
0 02.04.01.02 2
0 02.04.02 2
0 02.04.02.01 2
0 02.04.02.02 2
0 02.04.02.03 2
0 02.04.03 2
0 02.04.03.01 2
0 02.04.03.02 2
0 02.04.03.03 2
0 02.04.03.04 2
0 02.04.04 2
0 02.04.04.01 2
0 02.04.04.02 2
0 02.04.04.03 2
0 02.04.05 2
0 02.04.05.01 2
0 02.04.06 2
0 02.04.06.01 2
0 02.04.07 2
0 02.04.07.01 2
0 02.04.08 2
0 02.04.08.01 2
0 02.04.09 2
0 02.04.09.01
0 02.05 2
0 02.05.01 2
0 02.05.01.01 2
0 02.05.01.02 2
0 02.05.02 2
0 02.05.02.01 2
0 02.05.02.02 2
0 02.05.03 2
0 02.05.03.01 2
0 02.05.04 2
0 02.05.04.01 2
0 02.05.04.02 2
0 02.05.04.03 2
0 02.05.05 2
0 02.05.05.01 2
0 02.05.06 2
0 02.05.06.01 2
0 02.05.06.02 2
0 02.05.07 2
0 02.05.07.01 2
0 02.05.07.02 2
0 02.05.07.03 2
0 02.05.07.04 2
0 02.05.08 2
0 02.05.08.01 2
0 02.05.08.02 2
0 02.05.09 2
0 02.05.09.01 2
0 02.05.09.02 2
0 02.05.09.03 2
0 02.05.10 2
0 02.05.10.01 2
0 02.05.10.01.01 2
0 02.05.10.01.02 2
0 02.05.10.02 2
0 02.05.10.02.01 2
0 02.05.10.02.02 2
0 02.05.10.02.03 2
0 02.05.10.03 2
0 02.05.10.03.01 2
0 02.05.10.03.02 2
0 02.05.10.03.03 2
0 02.05.10.04 2
0 02.05.10.04.01 2
0 02.05.10.05 2
0 02.05.10.05.01 2
0 02.05.10.06 2
0 02.05.10.06.01 2
0 02.06 2
0 02.06.01 2
0 02.06.01.01 2
0 02.06.01.02 2
0 02.06.02 2
0 02.06.02.01 2
0 02.06.02.02 2
0 02.06.02.03
0 02.06.02.04
0 02.06.02.05 2
0 02.06.03 2
0 02.06.03.01
0 02.06.03.02 3
0 02.06.03.03
0 02.06.04 2
0 02.06.04.01 2
0 02.06.05 2
0 02.06.05.01 2
0 02.06.05.01.01 2
0 02.06.05.01.02 2
0 02.06.05.02 2
0 02.06.05.02.01 2
0 02.06.05.02.02 2
0 02.06.05.02.03 2
0 02.06.05.03 2
0 02.06.05.03.01 2
0 02.06.05.03.02 2
0 02.06.05.04 2
0 02.06.05.04.01 2
0 02.06.05.05 2
0 02.06.05.05.01 2
0 02.06.05.06 2
0 02.06.05.06.01 2
0 02.06.05.07 2
0 02.06.05.07.01 2
0 02.06.05.08 2
0 02.06.05.08.01 2
0 02.06.06 2
0 02.06.06.01 2
0 02.06.06.01.01 2
0 02.06.06.01.02 2
0 02.06.06.02 2
0 02.06.06.02.01 2
0 02.06.06.02.02 2
0 02.06.06.02.03 2
0 02.06.06.03 2
0 02.06.06.03.01 2
0 02.06.06.03.02 2
0 02.06.06.04 2
0 02.06.06.04.01 2
0 02.06.06.04.02 2
0 02.06.06.05 2
0 02.06.06.05.01 2
0 02.06.06.06 2
0 02.06.06.06.01 2
0 02.06.06.07 2
0 02.06.06.08 2
0 02.06.07 2
0 02.06.07.01 2
0 02.06.07.01.01 2
0 02.06.07.01.02 2
0 02.06.07.02 2
0 02.06.07.02.01 2
0 02.06.07.02.02 2
0 02.06.07.02.03 2
0 02.06.07.03 2
0 02.06.07.03.01 2
0 02.06.07.03.02 2
0 02.06.07.04 2
0 02.06.07.04.01 2
0 02.06.07.05 2
0 02.06.07.05.01 2
0 02.06.07.06 2
0 02.06.07.06.01 2
0 02.06.07.06.02 2
0 02.07 2
0 02.07.01 2
0 02.07.01.01 2
0 02.07.01.02 2
0 02.07.02 2
0 02.07.02.01 2
0 02.07.02.02 2
0 02.07.02.03 2
0 02.07.02.04 2
0 02.07.03 2
0 02.07.03.01 2
0 02.07.03.02 2
0 02.07.04 2
0 02.07.04.01 2
0 03 3
0 03.01 3
0 03.01.01 3
0 03.01.01.01 3
0 03.01.01.02 3
0 03.01.02 3
0 03.01.02.01 3
0 03.01.02.02 3
0 03.01.02.03
0 03.01.02.04
0 03.01.02.05 2
0 03.01.03 3
0 03.01.03.01
0 03.01.04 3
0 03.01.04.01 3
0 03.02 3
0 03.02.01 3
0 03.02.01.01 3
0 03.02.01.02 3
0 03.02.02 3
0 03.02.02.01 3
0 03.02.02.02 3
0 03.02.02.03 3
0 03.02.03 3
0 03.02.03.01 3
0 03.02.03.02 3
0 03.02.04 3
0 03.02.04.01 3
0 03.02.05 3
0 03.02.05.01 3
0 03.02.06 3
0 03.02.06.01 3
0 03.02.07 3
0 03.02.07.01 3
0 03.02.08 3
0 03.02.08.01 3
0 03.03 3
0 03.03.01 3
0 03.03.01.01 3
0 03.03.01.02 3
0 03.03.02 3
0 03.03.02.01 3
0 03.03.02.02 3
0 03.03.02.03 3
0 03.03.03 3
0 03.03.03.01 3
0 03.03.03.02 3
0 03.03.04 3
0 03.03.04.01 3
0 03.03.04.02 3
0 03.03.05 3
0 03.03.05.01 3
0 03.03.06 3
0 03.03.06.01 3
0 03.03.07 3
0 03.03.07.01 3
0 03.04 3
0 03.04.01 3
0 03.04.01.01 3
0 03.04.01.02 3
0 03.04.02 3
0 03.04.02.01 3
0 03.04.02.02 3
0 03.04.02.03 3
0 03.04.03 3
0 03.04.03.01 3
0 03.04.04 3
0 03.04.04.01 3
0 03.04.04.02 3
0 03.04.04.03 3
0 03.04.05 3
0 03.04.05.01 3
0 03.04.06 3
0 03.04.06.01 3
0 03.04.06.02 3
0 03.04.07 3
0 03.04.07.01 3
0 03.04.07.02 3
0 03.04.07.03 3
0 03.04.07.04 3
0 03.04.08 3
0 03.04.08.01 3
0 03.04.08.02 3
0 03.04.09 3
0 03.04.09.01 3
0 03.04.09.02 3
0 03.04.09.03 3
0 03.04.10 3
0 03.04.10.01 3
0 03.04.10.01.01 3
0 03.04.10.01.02 3
0 03.04.10.02 3
0 03.04.10.02.01 3
0 03.04.10.02.02 3
0 03.04.10.02.03 3
0 03.04.10.03 3
0 03.04.10.03.01 3
0 03.04.10.03.02 3
0 03.04.10.03.03 3
0 03.04.10.04 3
0 03.04.10.04.01 3
0 03.04.10.05 3
0 03.04.10.05.01 3
0 03.04.10.06 3
0 03.04.10.06.01 2
0 03.04.11 3
0 03.04.11.01 3
0 03.04.11.01.01 3
0 03.04.11.01.02 3
0 03.04.11.02 3
0 03.04.11.02.01 3
0 03.04.11.02.02 3
0 03.04.11.02.03 3
0 03.04.11.02.04 3
0 03.04.11.03 3
0 03.04.11.03.01 3
0 03.04.11.04 3
0 03.04.11.04.01 3
0 03.04.11.04.02 3
0 03.04.11.04.03 3
0 03.05 3
0 03.05.01 3
0 03.05.01.01 3
0 03.05.01.02 3
0 03.05.02 3
0 03.05.02.01 3
0 03.05.02.02 3
0 03.05.02.03
0 03.05.02.04
0 03.05.02.05 2
0 03.05.03 3
0 03.05.03.01
0 03.05.03.02 3
0 03.05.03.03
0 03.05.03.04
0 03.05.03.05
0 03.05.04 3
0 03.05.04.01 3
0 03.05.05 3
0 03.05.05.01 3
0 03.05.05.01.01 3
0 03.05.05.01.02 3
0 03.05.05.02 3
0 03.05.05.02.01 3
0 03.05.05.02.02 3
0 03.05.05.02.03 3
0 03.05.05.03 3
0 03.05.05.03.01 3
0 03.05.05.03.02 3
0 03.05.05.04 3
0 03.05.05.04.01 3
0 03.05.05.05 3
0 03.05.05.05.01 3
0 03.05.05.06 3
0 03.05.05.06.01 3
0 03.05.05.07 3
0 03.05.05.07.01 3
0 03.05.05.08 3
0 03.05.05.08.01 3
0 03.05.06 3
0 03.05.06.01 3
0 03.05.06.01.01 3
0 03.05.06.01.02 3
0 03.05.06.02 3
0 03.05.06.02.01 3
0 03.05.06.02.02 3
0 03.05.06.02.03 3
0 03.05.06.03 3
0 03.05.06.03.01 3
0 03.05.06.03.02 3
0 03.05.06.04 3
0 03.05.06.04.01 3
0 03.05.06.04.02 3
0 03.05.06.05 3
0 03.05.06.05.01 3
0 03.05.06.06 3
0 03.05.06.06.01 3
0 03.05.06.07 3
0 03.05.06.07.01 3
0 03.05.07 3
0 03.05.07.01 3
0 03.05.07.01.01 3
0 03.05.07.01.02 3
0 03.05.07.02 3
0 03.05.07.02.01 3
0 03.05.07.02.02 3
0 03.05.07.02.03 3
0 03.05.07.03 3
0 03.05.07.03.01 3
0 03.05.07.03.02 3
0 03.05.07.04 3
0 03.05.07.04.01 3
0 03.05.07.05 3
0 03.05.07.05.01 3
0 03.05.07.06 3
0 03.05.07.06.01 3
0 03.05.07.06.02 3
0 03.06 3
0 03.06.01 3
0 03.06.01.01 3
0 03.06.01.02 3
0 03.06.02 3
0 03.06.02.01 3
0 03.06.02.02 3
0 03.06.02.03 3
0 03.06.02.04 3
0 03.06.03 3
0 03.06.03.01 3
0 03.06.03.02 3
0 03.06.04 3
0 03.06.04.01 3
0 04
0 04.01
0 04.01.01
0 04.01.01.01
0 04.01.01.02
0 04.01.02
0 04.01.02.01
0 04.01.02.02
0 04.01.02.03
0 04.01.02.04
0 04.01.02.05 2
0 04.01.03
0 04.01.03.01
0 04.01.04
0 04.01.04.01
0 04.02 2
0 04.02.01 2
0 04.02.01.01 2
0 04.02.01.02 2
0 04.02.02 2
0 04.02.02.01 2
0 04.02.02.02 2
0 04.02.02.03 2
0 04.02.03 2
0 04.02.03.01 2
0 04.02.03.02 2
0 04.02.03.03 2
0 04.02.03.04 2
0 04.02.04 2
0 04.02.04.01 2
0 04.02.04.02 2
0 04.02.04.03 2
0 04.02.05 2
0 04.02.05.01 2
0 04.02.06 2
0 04.02.06.01 2
0 04.02.07 2
0 04.02.07.01 2
0 04.02.08 2
0 04.02.08.01 2
0 04.02.09 2
0 04.02.09.01
0 04.03
0 04.03.01
0 04.03.01.01
0 04.03.01.02
0 04.03.02
0 04.03.02.01
0 04.03.02.02
0 04.03.02.03
0 04.03.03
0 04.03.03.01
0 04.03.04
0 04.03.04.01
0 04.03.04.02
0 04.03.04.03
0 04.03.05
0 04.03.05.01
0 04.03.06
0 04.03.06.01
0 04.03.06.02
0 04.03.07
0 04.03.07.01
0 04.03.07.02
0 04.03.07.03
0 04.03.07.04
0 04.03.08
0 04.03.08.01
0 04.03.08.02
0 04.03.09
0 04.03.09.01
0 04.03.09.02
0 04.03.09.03
0 04.03.10
0 04.03.10.01
0 04.03.10.01.01
0 04.03.10.01.02
0 04.03.10.02
0 04.03.10.02.01
0 04.03.10.02.02
0 04.03.10.02.03
0 04.03.10.03
0 04.03.10.03.01
0 04.03.10.03.02
0 04.03.10.03.03
0 04.03.10.04
0 04.03.10.04.01
0 04.03.10.05
0 04.03.10.05.01
0 04.03.10.06
0 04.03.10.06.01 2
0 04.04
0 04.04.01
0 04.04.01.01
0 04.04.01.02
0 04.04.02
0 04.04.02.01
0 04.04.02.02
0 04.04.02.03
0 04.04.03
0 04.04.03.01
0 04.04.04
0 04.04.04.01
0 04.04.04.02
0 04.04.04.03
0 04.04.05
0 04.04.05.01
0 04.04.06
0 04.04.06.01
0 04.04.07
0 04.04.07.01
0 04.04.08
0 04.04.08.01
0 04.04.09
0 04.04.09.01
0 04.05
0 04.05.01
0 04.05.01.01
0 04.05.01.02
0 04.05.02
0 04.05.02.01
0 04.05.02.02
0 04.05.02.03
0 04.05.02.04
0 04.05.02.05 2
0 04.05.03
0 04.05.03.01
0 04.05.03.02
0 04.05.03.03
0 04.05.03.04
0 04.05.04
0 04.05.04.01
0 04.05.05
0 04.05.05.01
0 04.05.05.01.01
0 04.05.05.01.02
0 04.05.05.02
0 04.05.05.02.01
0 04.05.05.02.02
0 04.05.05.02.03
0 04.05.05.03
0 04.05.05.03.01 2
0 04.05.05.03.02
0 04.05.05.04
0 04.05.05.04.01
0 04.05.05.05
0 04.05.05.05.01
0 04.05.05.06
0 04.05.05.06.01
0 04.05.05.07
0 04.05.05.07.01
0 04.05.05.08
0 04.05.05.08.01
0 04.05.06
0 04.05.06.01
0 04.05.06.01.01
0 04.05.06.01.02
0 04.05.06.02
0 04.05.06.02.01
0 04.05.06.02.02
0 04.05.06.02.03
0 04.05.06.03
0 04.05.06.03.01
0 04.05.06.03.02
0 04.05.06.04
0 04.05.06.04.01
0 04.05.06.04.02
0 04.05.06.05
0 04.05.06.05.01
0 04.05.06.06
0 04.05.06.06.01
0 04.05.06.07
0 04.05.06.07.01
0 04.05.07
0 04.05.07.01
0 04.05.07.01.01
0 04.05.07.01.02
0 04.05.07.02
0 04.05.07.02.01
0 04.05.07.02.02
0 04.05.07.02.03
0 04.05.07.03
0 04.05.07.03.01
0 04.05.07.03.02
0 04.05.07.04
0 04.05.07.04.01
0 04.05.07.05
0 04.05.07.05.01
0 04.05.07.06
0 04.05.07.06.01
0 04.05.07.06.02
0 04.06
0 04.06.01
0 04.06.01.01
0 04.06.01.02
0 04.06.02
0 04.06.02.01
0 04.06.02.02
0 04.06.02.03
0 04.06.02.04
0 04.06.03
0 04.06.03.01
0 04.06.03.02
0 04.06.04
0 04.06.04.01
0 05
0 05.01
0 05.01.01
0 05.01.01.01
0 05.01.01.02
0 05.01.02
0 05.01.02.01
0 05.01.02.02
0 05.01.02.03
0 05.01.02.04
0 05.01.02.05 2
0 05.01.03
0 05.01.03.01
0 05.01.04
0 05.01.04.01
0 05.02
0 05.02.01
0 05.02.01.01
0 05.02.01.02
0 05.02.02
0 05.02.02.01
0 05.02.02.02
0 05.02.02.03
0 05.02.03
0 05.02.03.01 2
0 05.02.03.02
0 05.02.04
0 05.02.04.01
0 05.02.05
0 05.02.05.01
0 05.02.06
0 05.02.06.01
0 05.02.07
0 05.02.07.01
0 05.02.08
0 05.02.08.01
0 05.03
0 05.03.01
0 05.03.01.01
0 05.03.01.02
0 05.03.02
0 05.03.02.01
0 05.03.02.02
0 05.03.02.03
0 05.03.03
0 05.03.03.01
0 05.03.03.02
0 05.03.04
0 05.03.04.01
0 05.03.04.02
0 05.03.05
0 05.03.05.01
0 05.03.06
0 05.03.06.01
0 05.03.07
0 05.03.07.01
0 05.04
0 05.04.01
0 05.04.01.01
0 05.04.01.02
0 05.04.02
0 05.04.02.01
0 05.04.02.02
0 05.04.02.03
0 05.04.03
0 05.04.03.01
0 05.04.04
0 05.04.04.01
0 05.04.04.02
0 05.04.04.03
0 05.04.05
0 05.04.05.01
0 05.04.06
0 05.04.06.01
0 05.04.07
0 05.04.07.01
0 05.04.08
0 05.04.08.01
0 05.04.09
0 05.04.09.01
0 05.05
0 05.05.01
0 05.05.01.01
0 05.05.01.02
0 05.05.02
0 05.05.02.01
0 05.05.02.02
0 05.05.02.03
0 05.05.03
0 05.05.03.01
0 05.05.04
0 05.05.04.01
0 05.05.04.02
0 05.05.04.03
0 05.05.05
0 05.05.05.01
0 05.05.06
0 05.05.06.01
0 05.05.06.02
0 05.05.07
0 05.05.07.01
0 05.05.07.02
0 05.05.07.03
0 05.05.07.04
0 05.05.08
0 05.05.08.01
0 05.05.08.02
0 05.05.09
0 05.05.09.01
0 05.05.09.02
0 05.05.09.03
0 05.05.10
0 05.05.10.01
0 05.05.10.01.01
0 05.05.10.01.02
0 05.05.10.02
0 05.05.10.02.01
0 05.05.10.02.02
0 05.05.10.02.03
0 05.05.10.03
0 05.05.10.03.01
0 05.05.10.03.02
0 05.05.10.03.03
0 05.05.10.04
0 05.05.10.04.01
0 05.05.10.05
0 05.05.10.05.01
0 05.05.10.06
0 05.05.10.06.01 2
0 05.06
0 05.06.01
0 05.06.01.01
0 05.06.01.02
0 05.06.02
0 05.06.02.01
0 05.06.02.02
0 05.06.02.03
0 05.06.02.04
0 05.06.02.05 2
0 05.06.03
0 05.06.03.01
0 05.06.03.02
0 05.06.03.03
0 05.06.03.04
0 05.06.03.05
0 05.06.04
0 05.06.04.01
0 05.06.05
0 05.06.05.01
0 05.06.05.01.01
0 05.06.05.01.02
0 05.06.05.02
0 05.06.05.02.01
0 05.06.05.02.02
0 05.06.05.02.03
0 05.06.05.03
0 05.06.05.03.01 2
0 05.06.05.03.02
0 05.06.05.04
0 05.06.05.04.01
0 05.06.05.05
0 05.06.05.05.01
0 05.06.05.06
0 05.06.05.06.01
0 05.06.05.07
0 05.06.05.07.01
0 05.06.05.08
0 05.06.05.08.01
0 05.06.06
0 05.06.06.01
0 05.06.06.01.01
0 05.06.06.01.02
0 05.06.06.02
0 05.06.06.02.01
0 05.06.06.02.02
0 05.06.06.02.03
0 05.06.06.03
0 05.06.06.03.01
0 05.06.06.03.02
0 05.06.06.04
0 05.06.06.04.01
0 05.06.06.04.02
0 05.06.06.05
0 05.06.06.05.01
0 05.06.06.06
0 05.06.06.06.01
0 05.06.06.07
0 05.06.06.07.01
0 05.06.07
0 05.06.07.01
0 05.06.07.01.01
0 05.06.07.01.02
0 05.06.07.02
0 05.06.07.02.01
0 05.06.07.02.02
0 05.06.07.02.03
0 05.06.07.03
0 05.06.07.03.01
0 05.06.07.03.02
0 05.06.07.04
0 05.06.07.04.01
0 05.06.07.05
0 05.06.07.05.01
0 05.06.07.06
0 05.06.07.06.01
0 05.06.07.06.02
0 05.07
0 05.07.01
0 05.07.01.01
0 05.07.01.02
0 05.07.02
0 05.07.02.01
0 05.07.02.02
0 05.07.02.03
0 05.07.02.04
0 05.07.03
0 05.07.03.01
0 05.07.03.02
0 05.07.04
0 05.07.04.01
0 06
0 06.01
0 06.01.01
0 06.01.01.01
0 06.01.01.02
0 06.01.02
0 06.01.02.01
0 06.01.02.02
0 06.01.02.03
0 06.01.02.04
0 06.01.02.05 2
0 06.01.03
0 06.01.03.01
0 06.01.03.02
0 06.01.03.03
0 06.01.03.04
0 06.01.04
0 06.01.04.01
0 06.02
0 06.02.01
0 06.02.01.01
0 06.02.01.02
0 06.02.02
0 06.02.02.01
0 06.02.02.02
0 06.02.02.03
0 06.02.03
0 06.02.03.01 2
0 06.02.03.02
0 06.02.04
0 06.02.04.01
0 06.02.05
0 06.02.05.01
0 06.02.06
0 06.02.06.01
0 06.02.07
0 06.02.07.01
0 06.02.08
0 06.02.08.01
0 06.03
0 06.04
0 06.04.01
0 06.04.01.01
0 06.04.01.02
0 06.04.02
0 06.04.02.01
0 06.04.02.02
0 06.04.02.03
0 06.04.03
0 06.04.03.01
0 06.04.03.02
0 06.04.03.03
0 06.04.03.04
0 06.04.04
0 06.04.04.01
0 06.04.04.02
0 06.04.04.03
0 06.04.05
0 06.04.05.01
0 06.04.06
0 06.04.06.01
0 06.04.07
0 06.04.07.01
0 06.04.08
0 06.04.08.01
0 06.04.09
0 06.04.09.01
0 06.05
0 06.05.01
0 06.05.01.01
0 06.05.01.02
0 06.05.02
0 06.05.02.01
0 06.05.02.02
0 06.05.02.03
0 06.05.02.04
0 06.05.02.05 2
0 06.05.03
0 06.05.03.01
0 06.05.03.02
0 06.05.04
0 06.05.04.01
0 06.05.05
0 06.05.05.01
0 06.05.05.01.01
0 06.05.05.01.02
0 06.05.05.02
0 06.05.05.02.01
0 06.05.05.02.02
0 06.05.05.02.03
0 06.05.05.03
0 06.05.05.03.01 2
0 06.05.05.03.02
0 06.05.05.04
0 06.05.05.04.01
0 06.05.05.05
0 06.05.05.05.01
0 06.05.05.06
0 06.05.05.06.01
0 06.05.05.07
0 06.05.05.07.01
0 06.05.05.08
0 06.05.05.08.01
0 06.05.06
0 06.05.06.01
0 06.05.06.01.01
0 06.05.06.01.02
0 06.05.06.02
0 06.05.06.02.01
0 06.05.06.02.02
0 06.05.06.02.03
0 06.05.06.03
0 06.05.06.03.01
0 06.05.06.03.02
0 06.05.06.04
0 06.05.06.04.01
0 06.05.06.04.02
0 06.05.06.05
0 06.05.06.05.01
0 06.05.06.06
0 06.05.06.06.01
0 06.05.06.07
0 06.05.06.07.01
0 06.05.07
0 06.05.07.01
0 06.05.07.01.01
0 06.05.07.01.02
0 06.05.07.02
0 06.05.07.02.01
0 06.05.07.02.02
0 06.05.07.02.03
0 06.05.07.03
0 06.05.07.03.01
0 06.05.07.03.02
0 06.05.07.04
0 06.05.07.04.01
0 06.05.07.05
0 06.05.07.05.01
0 06.05.07.06
0 06.05.07.06.01
0 06.05.07.06.02
0 06.06
0 06.06.01
0 06.06.01.01
0 06.06.01.02
0 06.06.02
0 06.06.02.01
0 06.06.02.02
0 06.06.02.03
0 06.06.02.04
0 06.06.03
0 06.06.03.01
0 06.06.03.02
0 06.06.04
0 06.06.04.01
0 07
0 07.01
0 07.01.01
0 07.01.02
0 07.02
0 07.02.01
0 07.02.01.01
0 07.02.01.02
0 07.02.02
0 07.02.02.01
0 07.02.02.02
0 07.02.02.03
0 07.02.02.04
0 07.02.02.05 2
0 07.02.03
0 07.02.03.01
0 07.02.04
0 07.02.04.01
0 07.03
0 07.03.01
0 07.03.01.01
0 07.03.01.02
0 07.03.01.03
0 07.03.02
0 07.03.02.01
0 07.03.02.02
0 07.03.02.03
0 07.03.02.04
0 07.03.02.05 2
0 07.03.03
0 07.03.03.01
0 07.03.04
0 07.03.04.01
0 07.04
0 07.04.01
0 07.04.01.01
0 07.04.01.01.01
0 07.04.01.01.02
0 07.04.01.02
0 07.04.01.02.01
0 07.04.01.02.02
0 07.04.01.02.03
0 07.04.01.02.04
0 07.04.01.03
0 07.04.01.03.01
0 07.04.01.03.02
0 07.04.01.03.03
0 07.04.01.03.04
0 07.04.01.04
0 07.04.01.04.01
0 07.04.01.04.02
0 07.04.01.04.03
0 07.04.01.04.04
0 07.04.01.05
0 07.04.01.05.01
0 07.04.02
0 07.04.02.01
0 07.04.02.01.01
0 07.04.02.01.02
0 07.04.02.02
0 07.04.02.02.01
0 07.04.02.02.02
0 07.04.02.02.03
0 07.04.02.02.04
0 07.04.02.03
0 07.04.02.03.01
0 07.04.02.03.02
0 07.04.02.03.03
0 07.04.02.04
0 07.04.02.05
0 07.04.02.05.01
0 07.04.02.05.02
0 07.04.02.05.03
0 07.04.02.05.04
0 07.04.02.06
0 07.04.02.06.01
0 07.04.03
0 07.04.03.01
0 07.04.03.01.01
0 07.04.03.01.02
0 07.04.03.02
0 07.04.03.02.01
0 07.04.03.02.02
0 07.04.03.02.03
0 07.04.03.02.04
0 07.04.03.03
0 07.04.03.03.01
0 07.04.03.03.02
0 07.04.03.03.03
0 07.04.03.03.04
0 07.04.03.04
0 07.04.03.04.01
0 07.04.03.04.02
0 07.04.03.04.03
0 07.04.03.04.04
0 07.04.03.05
0 07.04.03.05.01
0 07.05
0 07.05.01
0 07.05.01.01
0 07.05.01.02
0 07.05.02
0 07.05.02.01
0 07.05.02.02
0 07.05.02.03
0 07.05.02.04
0 07.05.03
0 07.05.03.01
0 07.05.03.02
0 07.05.04
0 07.05.04.01
0 08
0 08.01
0 08.01.01
0 08.01.01.01
0 08.01.01.01.01
0 08.01.01.01.02
0 08.01.01.02
0 08.01.01.02.01
0 08.01.01.02.01.01
0 08.01.01.02.01.02
0 08.01.01.02.02
0 08.01.01.02.02.01
0 08.01.01.02.02.02
0 08.01.01.02.02.03
0 08.01.01.02.02.04
0 08.01.01.02.02.05
0 08.01.01.03
0 08.01.01.03.01
0 08.01.01.03.01.01
0 08.01.01.03.01.02
0 08.01.01.03.01.03
0 08.01.01.03.02
0 08.01.01.03.02.01
0 08.01.01.03.02.02
0 08.01.01.03.02.03
0 08.01.01.04
0 08.01.01.04.01
0 08.01.01.04.01.01
0 08.01.01.04.01.02
0 08.01.01.04.01.03
0 08.01.01.04.02
0 08.01.01.04.02.01
0 08.01.01.04.03
0 08.01.01.04.03.01
0 08.01.01.04.03.02
0 08.01.01.04.04
0 08.01.01.04.04.01
0 08.01.01.05
0 08.01.01.05.01
0 08.01.01.05.01.01
0 08.01.01.05.01.02
0 08.01.01.05.02
0 08.01.01.05.02.01
0 08.01.01.06
0 08.01.01.06.01
0 08.01.01.06.01.01
0 08.01.01.06.01.02
0 08.01.01.06.02
0 08.01.01.06.02.01
0 08.01.01.06.02.02
0 08.01.01.07
0 08.01.01.07.01
0 08.01.01.07.01.01
0 08.01.01.07.01.02
0 08.01.01.07.02
0 08.01.01.07.02.01
0 08.01.01.07.02.02
0 08.01.01.07.03
0 08.01.01.07.03.01
0 08.01.01.07.03.02
0 08.01.01.07.03.03
0 08.01.01.07.04
0 08.01.01.07.04.01
0 08.01.01.07.05
0 08.01.01.07.05.01
0 08.01.01.08
0 08.01.01.08.01
0 08.01.01.08.01.01
0 08.01.01.08.01.02
0 08.01.01.08.01.03
0 08.01.01.08.01.04
0 08.01.01.08.01.05
0 08.01.01.08.01.06
0 08.01.01.08.01.07
0 08.01.01.08.01.08
0 08.01.01.08.01.09
0 08.01.01.08.01.10
0 08.01.01.08.02
0 08.01.01.08.02.01
0 08.01.01.08.02.02
0 08.01.01.08.02.03
0 08.01.01.08.02.04
0 08.01.01.08.02.05
0 08.01.01.08.02.06
0 08.01.01.08.02.07
0 08.01.01.08.02.08
0 08.01.01.08.02.09
0 08.01.01.08.02.10
0 08.01.02
0 08.01.02.01
0 08.01.02.01.01
0 08.01.02.01.02
0 08.01.02.02
0 08.01.02.02.01
0 08.01.02.02.01.01
0 08.01.02.02.01.01.01
0 08.01.02.02.01.01.02
0 08.01.02.02.01.01.03
0 08.01.02.02.01.02
0 08.01.02.02.01.02.01
0 08.01.02.02.01.02.02
0 08.01.02.02.01.02.03
0 08.01.02.02.01.03
0 08.01.02.02.01.03.01
0 08.01.02.02.01.04
0 08.01.02.02.01.04.01
0 08.01.02.02.01.05
0 08.01.02.02.01.05.01
0 08.01.02.02.01.06
0 08.01.02.02.01.06.01
0 08.01.02.02.02
0 08.01.02.02.02.01
0 08.01.02.02.02.02
0 08.01.02.02.02.03
0 08.01.02.03
0 08.01.02.03.01
0 08.01.02.03.01.01
0 08.01.02.03.01.01.01
0 08.01.02.03.01.01.02
0 08.01.02.03.01.01.03
0 08.01.02.03.01.02
0 08.01.02.03.01.02.01
0 08.01.02.03.01.02.02
0 08.01.02.03.01.03
0 08.01.02.03.01.03.01
0 08.01.02.03.01.03.02
0 08.01.02.03.01.03.03
0 08.01.02.03.01.04
0 08.01.02.03.01.04.01
0 08.01.02.03.01.05
0 08.01.02.03.01.05.01
0 08.01.02.03.01.06
0 08.01.02.03.01.06.01
0 08.01.02.03.02
0 08.01.02.03.02.01
0 08.01.02.03.02.01.01
0 08.01.02.03.02.01.02
0 08.01.02.03.02.01.03
0 08.01.02.03.02.02
0 08.01.02.03.02.02.01
0 08.01.02.03.02.03

0 08.01.02.03.02.03.01

0 08.01.02.03.03
0 08.01.02.03.03.01
0 08.01.02.03.03.01.01
0 08.01.02.03.03.01.02
0 08.01.02.03.03.01.03
0 08.01.02.03.03.02
0 08.01.02.03.03.02.01
0 08.01.02.03.03.02.02
0 08.01.02.03.03.03
0 08.01.02.03.03.03.01
0 08.01.02.03.03.03.02
0 08.01.02.03.03.03.03
0 08.01.02.03.03.04
0 08.01.02.03.03.04.01
0 08.01.02.03.03.05
0 08.01.02.03.03.05.01
0 08.01.02.03.03.06
0 08.01.02.03.03.06.01
0 08.01.02.03.03.06.02
0 08.01.02.03.03.06.03
0 08.01.02.03.04
0 08.01.02.03.04.01
0 08.01.02.03.04.02
0 08.01.02.03.04.03
0 08.01.02.03.05
0 08.01.02.03.05.01
0 08.01.02.03.05.01.01
0 08.01.02.03.05.01.02
0 08.01.02.03.05.01.03
0 08.01.02.03.05.02
0 08.01.02.03.05.02.01
0 08.01.02.03.05.02.02
0 08.01.02.03.05.03
0 08.01.02.03.05.03.01
0 08.01.02.03.05.03.02
0 08.01.02.03.05.03.03
0 08.01.02.03.05.04
0 08.01.02.03.05.04.01
0 08.01.02.03.05.05
0 08.01.02.03.05.05.01
0 08.01.02.03.05.06
0 08.01.02.03.05.06.01
0 08.01.02.04
0 08.01.02.04.01
0 08.01.02.04.01.01
0 08.01.02.04.01.02
0 08.01.02.04.01.03
0 08.01.02.04.01.04
0 08.01.02.04.02
0 08.01.02.04.02.01
0 08.01.02.04.02.02
0 08.01.02.04.02.03
0 08.01.02.04.03
0 08.01.02.04.03.01
0 08.01.02.04.03.02
0 08.02
0 08.02.01
0 08.02.01.01
0 08.02.01.01.01
0 08.02.01.01.02
0 08.02.01.02
0 08.02.01.02.01
0 08.02.01.02.01.01
0 08.02.01.02.01.02
0 08.02.01.02.02
0 08.02.01.02.02.01
0 08.02.01.02.02.02
0 08.02.01.02.02.03
0 08.02.01.02.02.04
0 08.02.01.02.02.05
0 08.02.01.03
0 08.02.01.03.01
0 08.02.01.03.01.01
0 08.02.01.03.01.02
0 08.02.01.03.01.03
0 08.02.01.03.02
0 08.02.01.03.02.01
0 08.02.01.03.02.02
0 08.02.01.03.02.03
0 08.02.01.04
0 08.02.01.04.01
0 08.02.01.04.01.01
0 08.02.01.04.01.02
0 08.02.01.04.01.03
0 08.02.01.04.02
0 08.02.01.04.02.01
0 08.02.01.04.03
0 08.02.01.04.03.01
0 08.02.01.04.03.02
0 08.02.01.04.04
0 08.02.01.04.04.01
0 08.02.01.05
0 08.02.01.05.01
0 08.02.01.05.01.01
0 08.02.01.05.01.02
0 08.02.01.05.02
0 08.02.01.05.02.01
0 08.02.01.06
0 08.02.01.06.01
0 08.02.01.06.01.01
0 08.02.01.06.01.02
0 08.02.01.06.02
0 08.02.01.06.02.01
0 08.02.01.06.02.02
0 08.02.01.07
0 08.02.01.07.01
0 08.02.01.07.01.01
0 08.02.01.07.01.02
0 08.02.01.07.02
0 08.02.01.07.02.01
0 08.02.01.07.02.02
0 08.02.01.07.03
0 08.02.01.07.03.01
0 08.02.01.07.03.02
0 08.02.01.07.03.03
0 08.02.01.07.04
0 08.02.01.07.04.01
0 08.02.01.07.05
0 08.02.01.07.05.01
0 08.02.01.08
0 08.02.01.08.01
0 08.02.01.08.01.01
0 08.02.01.08.01.02
0 08.02.01.08.01.03
0 08.02.01.08.01.04
0 08.02.01.08.01.05
0 08.02.01.08.01.06
0 08.02.01.08.01.07
0 08.02.01.08.01.08
0 08.02.01.08.01.09
0 08.02.01.08.01.10
0 08.02.01.08.02
0 08.02.01.08.02.01
0 08.02.01.08.02.02
0 08.02.01.08.02.03
0 08.02.01.08.02.04
0 08.02.01.08.02.05
0 08.02.01.08.02.06
0 08.02.01.08.02.07
0 08.02.01.08.02.08
0 08.02.01.08.02.09
0 08.02.01.08.02.10
0 08.02.02
0 08.02.02.01
0 08.02.02.01.01
0 08.02.02.01.02
0 08.02.02.02
0 08.02.02.02.01
0 08.02.02.02.01.01
0 08.02.02.02.01.01.01
0 08.02.02.02.01.01.02
0 08.02.02.02.01.01.03
0 08.02.02.02.01.02
0 08.02.02.02.01.02.01
0 08.02.02.02.01.02.02
0 08.02.02.02.01.02.03
0 08.02.02.02.01.03
0 08.02.02.02.01.03.01
0 08.02.02.02.01.04
0 08.02.02.02.01.04.01
0 08.02.02.02.01.05
0 08.02.02.02.01.05.01
0 08.02.02.02.01.06
0 08.02.02.02.01.06.01
0 08.02.02.02.02
0 08.02.02.02.02.01
0 08.02.02.02.02.02
0 08.02.02.02.02.03
0 08.02.02.03
0 08.02.02.03.01
0 08.02.02.03.01.01
0 08.02.02.03.01.01.01
0 08.02.02.03.01.01.02
0 08.02.02.03.01.01.03
0 08.02.02.03.01.02
0 08.02.02.03.01.02.01
0 08.02.02.03.01.02.02
0 08.02.02.03.01.03
0 08.02.02.03.01.03.01
0 08.02.02.03.01.03.02
0 08.02.02.03.01.03.03
0 08.02.02.03.01.04
0 08.02.02.03.01.04.01
0 08.02.02.03.01.05
0 08.02.02.03.01.05.01
0 08.02.02.03.01.06
0 08.02.02.03.01.06.01
0 08.02.02.03.02
0 08.02.02.03.02.01
0 08.02.02.03.02.01.01
0 08.02.02.03.02.01.02
0 08.02.02.03.02.01.03
0 08.02.02.03.02.02
0 08.02.02.03.02.02.01
0 08.02.02.03.02.03

0 08.02.02.03.02.03.01

0 08.02.02.03.03
0 08.02.02.03.03.01
0 08.02.02.03.03.01.01
0 08.02.02.03.03.01.02
0 08.02.02.03.03.01.03
0 08.02.02.03.03.02
0 08.02.02.03.03.02.01
0 08.02.02.03.03.02.02
0 08.02.02.03.03.03
0 08.02.02.03.03.03.01
0 08.02.02.03.03.03.02
0 08.02.02.03.03.03.03
0 08.02.02.03.03.04
0 08.02.02.03.03.04.01
0 08.02.02.03.03.05
0 08.02.02.03.03.05.01
0 08.02.02.03.03.06
0 08.02.02.03.03.06.01
0 08.02.02.03.03.06.02
0 08.02.02.03.03.06.03
0 08.02.02.03.04
0 08.02.02.03.04.01
0 08.02.02.03.04.02
0 08.02.02.03.04.03
0 08.02.02.03.05
0 08.02.02.03.05.01
0 08.02.02.03.05.01.01
0 08.02.02.03.05.01.02
0 08.02.02.03.05.01.03
0 08.02.02.03.05.02
0 08.02.02.03.05.02.01
0 08.02.02.03.05.02.02
0 08.02.02.03.05.03
0 08.02.02.03.05.03.01
0 08.02.02.03.05.03.02
0 08.02.02.03.05.03.03
0 08.02.02.03.05.04
0 08.02.02.03.05.04.01
0 08.02.02.03.05.05
0 08.02.02.03.05.05.01
0 08.02.02.03.05.06
0 08.02.02.03.05.06.01
0 08.02.02.04
0 08.02.02.04.01
0 08.02.02.04.01.01
0 08.02.02.04.01.02
0 08.02.02.04.01.03
0 08.02.02.04.01.04
0 08.02.02.04.02
0 08.02.02.04.02.01
0 08.02.02.04.02.02
0 08.02.02.04.02.03
0 08.02.02.04.03
0 08.02.02.04.03.01
0 08.02.02.04.03.02
0 08.03
0 08.03.01
0 08.03.01.01
0 08.03.01.01.01
0 08.03.01.01.02
0 08.03.01.02
0 08.03.01.02.01
0 08.03.01.02.01.01
0 08.03.01.02.01.02
0 08.03.01.02.02
0 08.03.01.02.02.01
0 08.03.01.02.02.02
0 08.03.01.02.02.03
0 08.03.01.02.02.04
0 08.03.01.02.02.05
0 08.03.01.03
0 08.03.01.03.01
0 08.03.01.03.01.01
0 08.03.01.03.01.02
0 08.03.01.03.01.03
0 08.03.01.03.02
0 08.03.01.03.02.01
0 08.03.01.03.02.02
0 08.03.01.03.02.03
0 08.03.01.04
0 08.03.01.04.01
0 08.03.01.04.01.01
0 08.03.01.04.01.02
0 08.03.01.04.01.03
0 08.03.01.04.02
0 08.03.01.04.02.01
0 08.03.01.04.03
0 08.03.01.04.03.01
0 08.03.01.04.03.02
0 08.03.01.04.04
0 08.03.01.04.04.01
0 08.03.01.05
0 08.03.01.05.01
0 08.03.01.05.01.01
0 08.03.01.05.01.02
0 08.03.01.05.02
0 08.03.01.05.02.01
0 08.03.01.06
0 08.03.01.06.01
0 08.03.01.06.01.01
0 08.03.01.06.01.02
0 08.03.01.06.02
0 08.03.01.06.02.01
0 08.03.01.06.02.02
0 08.03.01.07
0 08.03.01.07.01
0 08.03.01.07.01.01
0 08.03.01.07.01.02
0 08.03.01.07.02
0 08.03.01.07.02.01
0 08.03.01.07.02.02
0 08.03.01.07.03
0 08.03.01.07.03.01
0 08.03.01.07.03.02
0 08.03.01.07.03.03
0 08.03.01.07.04
0 08.03.01.07.04.01
0 08.03.01.07.05
0 08.03.01.07.05.01
0 08.03.01.08
0 08.03.01.08.01
0 08.03.01.08.01.01
0 08.03.01.08.01.02
0 08.03.01.08.01.03
0 08.03.01.08.01.04
0 08.03.01.08.01.05
0 08.03.01.08.01.06
0 08.03.01.08.01.07
0 08.03.01.08.01.08
0 08.03.01.08.01.09
0 08.03.01.08.01.10
0 08.03.01.08.02
0 08.03.01.08.02.01
0 08.03.01.08.02.02
0 08.03.01.08.02.03
0 08.03.01.08.02.04
0 08.03.01.08.02.05
0 08.03.01.08.02.06
0 08.03.01.08.02.07
0 08.03.01.08.02.08
0 08.03.01.08.02.09
0 08.03.01.08.02.10
0 08.03.02
0 08.03.02.01
0 08.03.02.01.01
0 08.03.02.01.02
0 08.03.02.02
0 08.03.02.02.01
0 08.03.02.02.01.01
0 08.03.02.02.01.01.01
0 08.03.02.02.01.01.02
0 08.03.02.02.01.01.03
0 08.03.02.02.01.02
0 08.03.02.02.01.02.01
0 08.03.02.02.01.02.02
0 08.03.02.02.01.02.03
0 08.03.02.02.01.03
0 08.03.02.02.01.03.01
0 08.03.02.02.01.04
0 08.03.02.02.01.04.01
0 08.03.02.02.01.05
0 08.03.02.02.01.05.01
0 08.03.02.02.01.06
0 08.03.02.02.01.06.01
0 08.03.02.02.02
0 08.03.02.02.02.01
0 08.03.02.02.02.02
0 08.03.02.02.02.03
0 08.03.02.03
0 08.03.02.03.01
0 08.03.02.03.01.01
0 08.03.02.03.01.01.01
0 08.03.02.03.01.01.02
0 08.03.02.03.01.01.03
0 08.03.02.03.01.02
0 08.03.02.03.01.02.01
0 08.03.02.03.01.02.02
0 08.03.02.03.01.03
0 08.03.02.03.01.03.01
0 08.03.02.03.01.03.02
0 08.03.02.03.01.03.03
0 08.03.02.03.01.04
0 08.03.02.03.01.04.01
0 08.03.02.03.01.05
0 08.03.02.03.01.05.01
0 08.03.02.03.01.06
0 08.03.02.03.01.06.01
0 08.03.02.03.02
0 08.03.02.03.02.01
0 08.03.02.03.02.01.01
0 08.03.02.03.02.01.02
0 08.03.02.03.02.01.03
0 08.03.02.03.02.02
0 08.03.02.03.02.02.01
0 08.03.02.03.02.03

0 08.03.02.03.02.03.01

0 08.03.02.03.03
0 08.03.02.03.03.01
0 08.03.02.03.03.01.01
0 08.03.02.03.03.01.02
0 08.03.02.03.03.01.03
0 08.03.02.03.03.02
0 08.03.02.03.03.02.01
0 08.03.02.03.03.02.02
0 08.03.02.03.03.03
0 08.03.02.03.03.03.01
0 08.03.02.03.03.03.02
0 08.03.02.03.03.03.03
0 08.03.02.03.03.04
0 08.03.02.03.03.04.01
0 08.03.02.03.03.05
0 08.03.02.03.03.05.01
0 08.03.02.03.03.06
0 08.03.02.03.03.06.01
0 08.03.02.03.03.06.02
0 08.03.02.03.03.06.03
0 08.03.02.03.04
0 08.03.02.03.04.01
0 08.03.02.03.04.02
0 08.03.02.03.04.03
0 08.03.02.03.05
0 08.03.02.03.05.01
0 08.03.02.03.05.01.01
0 08.03.02.03.05.01.02
0 08.03.02.03.05.01.03
0 08.03.02.03.05.02
0 08.03.02.03.05.02.01
0 08.03.02.03.05.02.02
0 08.03.02.03.05.03
0 08.03.02.03.05.03.01
0 08.03.02.03.05.03.02
0 08.03.02.03.05.03.03
0 08.03.02.03.05.04
0 08.03.02.03.05.04.01
0 08.03.02.03.05.05
0 08.03.02.03.05.05.01
0 08.03.02.03.05.06
0 08.03.02.03.05.06.01
0 08.03.02.04
0 08.03.02.04.01
0 08.03.02.04.01.01
0 08.03.02.04.01.02
0 08.03.02.04.01.03
0 08.03.02.04.01.04
0 08.03.02.04.02
0 08.03.02.04.02.01
0 08.03.02.04.02.02
0 08.03.02.04.02.03
0 08.03.02.04.03
0 08.03.02.04.03.01
0 08.03.02.04.03.02
0 08.04
0 08.04.01
0 08.04.01.01
0 08.04.01.01.01
0 08.04.01.01.02
0 08.04.01.02
0 08.04.01.02.01
0 08.04.01.02.01.01
0 08.04.01.02.01.02
0 08.04.01.02.02
0 08.04.01.02.02.01
0 08.04.01.02.02.02
0 08.04.01.02.02.03
0 08.04.01.02.02.04
0 08.04.01.02.02.05
0 08.04.01.03
0 08.04.01.03.01
0 08.04.01.03.01.01
0 08.04.01.03.01.02
0 08.04.01.03.01.03
0 08.04.01.03.02
0 08.04.01.03.02.01
0 08.04.01.03.02.02
0 08.04.01.03.02.03
0 08.04.01.04
0 08.04.01.04.01
0 08.04.01.04.01.01
0 08.04.01.04.01.02
0 08.04.01.04.01.03
0 08.04.01.04.02
0 08.04.01.04.02.01
0 08.04.01.04.03
0 08.04.01.04.03.01
0 08.04.01.04.03.02
0 08.04.01.04.04
0 08.04.01.04.04.01
0 08.04.01.05
0 08.04.01.05.01
0 08.04.01.05.01.01
0 08.04.01.05.01.02
0 08.04.01.05.02
0 08.04.01.05.02.01
0 08.04.01.06
0 08.04.01.06.01
0 08.04.01.06.01.01
0 08.04.01.06.01.02
0 08.04.01.06.02
0 08.04.01.06.02.01
0 08.04.01.06.02.02
0 08.04.01.07
0 08.04.01.07.01
0 08.04.01.07.01.01
0 08.04.01.07.01.02
0 08.04.01.07.02
0 08.04.01.07.02.01
0 08.04.01.07.02.02
0 08.04.01.07.03
0 08.04.01.07.03.01
0 08.04.01.07.03.02
0 08.04.01.07.03.03
0 08.04.01.07.04
0 08.04.01.07.04.01
0 08.04.01.07.05
0 08.04.01.07.05.01
0 08.04.01.08
0 08.04.01.08.01
0 08.04.01.08.01.01
0 08.04.01.08.01.02
0 08.04.01.08.01.03
0 08.04.01.08.01.04
0 08.04.01.08.01.05
0 08.04.01.08.01.06
0 08.04.01.08.01.07
0 08.04.01.08.01.08
0 08.04.01.08.01.09
0 08.04.01.08.01.10
0 08.04.01.08.02
0 08.04.01.08.02.01
0 08.04.01.08.02.02
0 08.04.01.08.02.03
0 08.04.01.08.02.04
0 08.04.01.08.02.05
0 08.04.01.08.02.06
0 08.04.01.08.02.07
0 08.04.01.08.02.08
0 08.04.01.08.02.09
0 08.04.01.08.02.10
0 08.04.02
0 08.04.02.01
0 08.04.02.01.01
0 08.04.02.01.02
0 08.04.02.02
0 08.04.02.02.01
0 08.04.02.02.01.01
0 08.04.02.02.01.01.01
0 08.04.02.02.01.01.02
0 08.04.02.02.01.01.03
0 08.04.02.02.01.02
0 08.04.02.02.01.02.01
0 08.04.02.02.01.02.02
0 08.04.02.02.01.02.03
0 08.04.02.02.01.03
0 08.04.02.02.01.03.01
0 08.04.02.02.01.04
0 08.04.02.02.01.04.01
0 08.04.02.02.01.05
0 08.04.02.02.01.05.01
0 08.04.02.02.01.06
0 08.04.02.02.01.06.01
0 08.04.02.02.02
0 08.04.02.02.02.01
0 08.04.02.02.02.02
0 08.04.02.02.02.03
0 08.04.02.03
0 08.04.02.03.01
0 08.04.02.03.01.01
0 08.04.02.03.01.01.01
0 08.04.02.03.01.01.02
0 08.04.02.03.01.01.03
0 08.04.02.03.01.02
0 08.04.02.03.01.02.01
0 08.04.02.03.01.02.02
0 08.04.02.03.01.03
0 08.04.02.03.01.03.01
0 08.04.02.03.01.03.02
0 08.04.02.03.01.03.03
0 08.04.02.03.01.04
0 08.04.02.03.01.04.01
0 08.04.02.03.01.05
0 08.04.02.03.01.05.01
0 08.04.02.03.01.06
0 08.04.02.03.01.06.01
0 08.04.02.03.02
0 08.04.02.03.02.01
0 08.04.02.03.02.01.01
0 08.04.02.03.02.01.02
0 08.04.02.03.02.01.03
0 08.04.02.03.02.02
0 08.04.02.03.02.02.01
0 08.04.02.03.02.03

0 08.04.02.03.02.03.01

0 08.04.02.03.03
0 08.04.02.03.03.01
0 08.04.02.03.03.01.01
0 08.04.02.03.03.01.02
0 08.04.02.03.03.01.03
0 08.04.02.03.03.02
0 08.04.02.03.03.02.01
0 08.04.02.03.03.02.02
0 08.04.02.03.03.03
0 08.04.02.03.03.03.01
0 08.04.02.03.03.03.02
0 08.04.02.03.03.03.03
0 08.04.02.03.03.04
0 08.04.02.03.03.04.01
0 08.04.02.03.03.05
0 08.04.02.03.03.05.01
0 08.04.02.03.03.06
0 08.04.02.03.03.06.01
0 08.04.02.03.03.06.02
0 08.04.02.03.03.06.03
0 08.04.02.03.04
0 08.04.02.03.04.01
0 08.04.02.03.04.02
0 08.04.02.03.04.03
0 08.04.02.03.05
0 08.04.02.03.05.01
0 08.04.02.03.05.01.01
0 08.04.02.03.05.01.02
0 08.04.02.03.05.01.03
0 08.04.02.03.05.02
0 08.04.02.03.05.02.01
0 08.04.02.03.05.02.02
0 08.04.02.03.05.03
0 08.04.02.03.05.03.01
0 08.04.02.03.05.03.02
0 08.04.02.03.05.03.03
0 08.04.02.03.05.04
0 08.04.02.03.05.04.01
0 08.04.02.03.05.05
0 08.04.02.03.05.05.01
0 08.04.02.03.05.06
0 08.04.02.03.05.06.01
0 08.04.02.04
0 08.04.02.04.01
0 08.04.02.04.01.01
0 08.04.02.04.01.02
0 08.04.02.04.01.03
0 08.04.02.04.01.04
0 08.04.02.04.02
0 08.04.02.04.02.01
0 08.04.02.04.02.02
0 08.04.02.04.02.03
0 08.04.02.04.03
0 08.04.02.04.03.01
0 08.04.02.04.03.02
0 09
0 09.01
0 09.01.01
0 09.01.01.01
0 09.01.01.02
0 09.01.02
0 09.01.02.01
0 09.01.02.02
0 09.01.02.03
0 09.01.02.04
0 09.01.03
0 09.01.03.01
0 09.01.04
0 09.01.04.01
0 09.01.04.02
0 09.01.04.03
0 09.01.05
0 09.01.05.01
0 09.01.06
0 09.01.06.01
0 09.01.06.02
0 09.01.07
0 09.01.07.01
0 09.01.07.02
0 09.02
0 09.02.01
0 09.02.01.01
0 09.02.01.02
0 09.02.02
0 09.02.02.01
0 09.02.02.02
0 09.02.02.03
0 09.02.02.04
0 09.02.03
0 09.02.03.01
0 09.02.04
0 09.02.04.01
0 09.02.04.02
0 09.02.04.03
0 09.02.05
0 09.02.05.01
0 09.02.06
0 09.02.06.01
0 09.02.07
0 09.02.07.01
0 09.02.07.02
0 09.03
0 09.03.01
0 09.03.01.01
0 09.03.01.02
0 09.03.02
0 09.03.02.01
0 09.03.02.02
0 09.03.02.03
0 09.03.02.04
0 09.03.03
0 09.03.03.01
0 09.03.03.02
0 09.03.04
0 09.03.04.01
0 09.03.04.02
0 09.03.04.03
0 09.03.05
0 09.03.05.01
0 09.03.06
0 09.03.06.01
0 09.03.06.02
0 09.03.06.03
0 09.03.06.04
0 09.03.06.05
0 09.03.06.06
0 09.04
0 09.04.01
0 09.04.01.01
0 09.04.01.02
0 09.04.02
0 09.04.02.01
0 09.04.02.02
0 09.04.02.03
0 09.04.02.04
0 09.04.02.05
0 09.04.02.06
0 09.04.02.07
0 09.04.02.08
0 09.04.03
0 09.04.03.01
0 09.04.03.02
0 09.04.03.03
0 09.04.04
0 09.04.04.01
0 09.04.04.02
0 09.04.05
0 09.04.05.01
0 09.04.06
0 09.04.06.01
0 09.04.06.02
0 09.04.06.03
0 09.05
0 09.05.01
0 09.05.01.01
0 09.05.01.02
0 09.05.02
0 09.05.02.01
0 09.05.02.02
0 09.05.02.03
0 09.05.03
0 09.05.03.01
0 09.05.03.02
0 09.05.03.03
0 09.05.04
0 09.05.04.01
0 09.05.05
0 09.05.05.01
0 09.05.06
0 09.05.06.01
0 09.05.06.02
0 09.05.07
0 09.05.07.01
0 09.06
0 09.06.01
0 09.06.01.01
0 09.06.01.02
0 09.06.02
0 09.06.02.01
0 09.06.02.02
0 09.06.02.03
0 09.06.03
0 09.06.03.01
0 09.06.04
0 09.06.04.01
0 09.06.04.02
0 09.06.04.03
0 09.06.05
0 09.06.05.01
0 09.06.06
0 09.06.06.01
0 09.06.07
0 09.06.07.01
0 09.06.07.02
0 09.07
0 09.07.01
0 09.07.01.01
0 09.07.01.02
0 09.07.02
0 09.07.02.01
0 09.07.02.02
0 09.07.02.03
0 09.07.02.04
0 09.07.02.05 2
0 09.07.03
0 09.07.03.01
0 09.08
0 09.08.01
0 09.08.01.01
0 09.08.01.02
0 09.08.02
0 09.08.02.01
0 09.08.02.02
0 09.08.02.03
0 09.08.02.04
0 09.08.03
0 09.08.03.01
0 09.08.04
0 09.08.04.01
0 09.08.04.02
0 09.08.04.03
0 10
0 10.01
0 11
0 11.01
Descripción
OBRAS GENERALES
OBRAS PROVISIONALES
ALMACEN, OFICINA Y CASETA DE GUARDIANIA
CARTEL DE IDENTIFICACION DE OBRA DE 5.40x3.60 m.
TRANSPORTE DE MATERIALES Y EQUIPOS
MOVILIZACION Y DESMOVILIZACION DE EQUIPO (AGUA)
ZANJAS DE CORONACION BOCATOMA, DE DRENAJE EN ZONAS DE PTAR PTAP
SEÑALIZACION
MALLA PLASTICA SEÑALIZACION C/LIMITES SEGURIDAD DE OBRA
CARTEL DE SEÑALIZACION PREVENTIVA
BOCATOMA (01 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO NORMAL C/ PRESENCIA DE AGUA
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERIAL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO CICLOPEO f'c=175KG/CM2 +30% P.M.
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
CARPINTERIA METALICA
MARCO Y COMPUERTA VOLANTE DE TIPO-1 (0.80x0.90M)
REJILLA METALICA PREFABRICADA (0.90x1.30M)
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
PINTURA ANTICORROCIVA A DOS MANOS
VALVULAS, ACCESORIOS Y TUBERIAS
SALIDA DE CAPTACION DE DN 110MM
DESARENADOR (01 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERIAL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
CARPINTERIA METALICA
MARCO Y COMPUERTA VOLANTE DE TIPO-1 (0.30x0.30m)
MARCO Y COMPUERTA TIPO BAFLE
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
VALVULAS, ACCESORIOS Y TUBERIAS
ACCESORIO Y TUBERIA
LINEA DE CONDUCCION (14+240 KM)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 110 MM C/ANILLO
PRUEBA DE CALIDAD
DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
VALVULA DE AIRE (26 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIOS VALVULA DE AIRE D=110MM
VALVULA DE PURGA (05 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO E=0.10m
CONCRETO f'c = 140 kg/cm2
OBRAS DE CONCRETO ESTRUCTURA
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
CAMARA ROMPE PRESION (01 UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX 6", E=20m
CONCRETO f'c=100 kg/cm2
CONCRETO f'c=140 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIO DE CAMARA ROMPE PRESION
PASE AEREO L=15.00m (09 UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
CONCRETO EN DADO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
REVOQUES Y ENLUCIDOS
TARRAJEO EN COLUMNAS
ACCESORIOS PASE AEREO
CABLE DE ACERO TIPO BOA DE 3/8"
PENDOLAS DE CABLE DE ACERO LISO DE 1/4"
GRAPA TIPO CROSBY DE A°G° PARA CABLE DE 25 mm2.
TUBERIA HDPE SDR7 DE 110MM
LANZAMIENTO Y FIJACION
SUMINISTRO
------------------------------------------
------------------------------------------
PREFILTRO (02 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
PINTURA ANTICORROCIVA A DOS MANOS
SUMINISTRO E INST. DE COMPONENTES DEL LECHO FILTRANTE
FILTRO DE GRAVA 15mm
FILTRO DE GRAVA 10mm
FILTRO DE GRAVA 5mm
FILTRO DE GRAVA 1/2"
SUMINISTRO E INSTALACION DE ACCESORIOS
ACCESORIO DEL PREFILTRO
FILTRO LENTO (01 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
CORTE C/MAQUINARIA EN TERRENO DE MATERIAL COMPACTO
REFINE Y NIVELACION DE PLATAFORMA
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX 4", E=10m
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
JUNTAS
JUNTAS WATERSTOP DE PVC DE 6"
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
MORTERO CON PENDIENTE EN FONDO C.A. 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
MARCO Y VERTEDERO METALICO PREFABRICADO E=1/4",(0.50x0.70M.)
MARCO Y VERTEDERO METALICO PREFABRICADO E=1/4",(0.40x0.70M.)
ESCALERA METALICA PREFABRICADA DE TUB F°G° DE 11/2", H=3.20M
FILTROS
FILTRO DE GRAVA DE 19 - 50 MM
FILTRO DE GRAVA DE 9.5 - 19 MM
FILTRO DE GRAVA DE 3 - 9.5 MM
FILTRO DE GRAVA DE ARENA GRUESA
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
PINTURA ANTICORROCIVA A DOS MANOS
VALVULAS, ACCESORIOS Y TUBERIA
ACCESORIOS PARA INGRESO DE PRE FILTRO DN 160MM
CERCO PERIMETRICO (L=240.00 m)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140 kg/cm2
CERCO PERIMETRICO CON MALLA OLIMPICA GALVANIZADA
CERCO PERIMETRICO DE ALAMBRE DE PUAS
PUERTA DE MADERA CON MARCO O SOPORTES
PINTURA ESMALTE EN PUERTAS Y VENTANAS A DOS MANOS
CAMARA DE DISTRIBUCION DE CAUDALES 03 SALIDAS (01 UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
SERVICIO DE AGUA POTABLE ALTO UNINI
LINEA DE ADUCCION (3+671.22 KM) ALTO UNINI
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO
PRUEBA DE CALIDAD
DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
VALVULA DE AIRE (08 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ABRAZADERA PVC SP CON REDUCCION DN 63 MM A Ø 1"
VALVULA DE PURGA (02 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO E=0.10m
CONCRETO f'c = 140 kg/cm2
OBRAS DE CONCRETO ESTRUCTURA
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
CAMARA ROMPE PRESION (02 UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX 6", E=20m
CONCRETO f'c=100 kg/cm2
CONCRETO f'c=140 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIO DE CAMARA ROMPE PRESION
RESERVORIO DE UNINI V=15M3 (01UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
CORTE C/MAQUINARIA EN TERRENO DE MATERIAL COMPACTO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
ESCALERA INTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
VENTILACION DE F°G° DE DN=75MM
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
PINTURA ANTICORROCIVA A DOS MANOS
VALVULAS, ACCESORIOS Y TUBERIA
ACCESORIO P/INGRESO DE RESERVORIO DN 63MM
ACCESORIO P/SALIDA DE RESERVORIO
ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA
CASETA DE CLORACION (01 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
SUMINISTRO E INSTALACION DE ACCESORIOS
SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE CLORACION
RED DE DISTRIBUCION UNINI (L=4+622.78m)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2"
PRUEBA DE CALIDAD
DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA DE AGUA
VALVULA DE AIRE DISTR (03 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ABRAZADERA PVC SP CON REDUCCION DN 50 MM A Ø 1"
VALVULA DE PURGA DISTR (04 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO E=0.10m
CONCRETO f'c = 140 kg/cm2
OBRAS DE CONCRETO ESTRUCTURA
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 50MM
VALVULA DE CONTROL (03 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS V. CONTROL 1"
ACCESORIOS V. CONTROL 3/4"
CONEXIONES DOMICILIARIAS ALTO UNINI (63 UNID.)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CONEXIONES DOMICILIARIA (63 UNID)
SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN CONEXIONES DOMICIALIARIAS
SERVICIO DE AGUA POTABLE MONTE SINAI
LINEA DE ADUCCION (1+473 KM)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO
PRUEBA DE CALIDAD
DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
VALVULA DE AIRE (03 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ABRAZADERA PVC SP CON REDUCCION DN 63 MM A Ø 1"
VALVULA DE PURGA (01 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO E=0.10m
CONCRETO f'c = 140 kg/cm2
OBRAS DE CONCRETO ESTRUCTURA
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
RESERVORIO MONTE SINAI V=25M3 (01UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
CORTE C/MAQUINARIA EN TERRENO DE MATERIAL COMPACTO
REFINE Y NIVELACION DE PLATAFORMA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
ESCALERA INTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
VENTILACION DE F°G° DE DN=75MM
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
PINTURA ANTICORROCIVA A DOS MANOS
VALVULAS, ACCESORIOS Y TUBERIA
ACCESORIO P/INGRESO DE RESERVORIO DN 63MM
ACCESORIO P/SALIDA DE RESERVORIO
ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA
CASETA DE CLORACION (01 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
SUMINISTRO E INSTALACION DE ACCESORIOS
SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE CLORACION
CERCO PERIMETRICO (L=220.00 m)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140 kg/cm2
CERCO PERIMETRICO CON MALLA OLIMPICA GALVANIZADA
MALLA OLIMPICA GALVANIZADA 2"X2" #12 DE h=1.43m CON MARCO ANGULAR 1 1/2"x1 1/2"x1/8"
PUERTA C/MALLA DE TUBO F°G° Ø=1 1/2", DE 4.0x1.80M.TIPO II
PINTURA ESMALTE EN PUERTAS Y VENTANAS A DOS MANOS
RED DE DISTRIBUCION MONTE SINAI (L=1+681.00m)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2"
TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO
PRUEBA DE CALIDAD
DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
VALVULA DE AIRE (03 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ABRAZADERA PVC SP CON REDUCCION DN 50 MM A Ø 1"
VALVULA DE PURGA DISTR (04 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO E=0.10m
CONCRETO f'c = 140 kg/cm2
OBRAS DE CONCRETO ESTRUCTURA
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 50MM
VALVULA DE CONTROL (04 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS V. CONTROL 1"
ACCESORIOS V. CONTROL 3/4"
CONEXIONES DOMICILIARIAS MONTE SINAI (88 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CONEXIONES DOMICILIARIA (88 UNID)
SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN CONEXIONES DOMICIALIARIAS
SERVICIO AGUA POTABLE PIRIARI
LINEA DE ADUCCION (3+120.00 KM)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 75MM C/ANILLO
PRUEBA DE CALIDAD
DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
CAMARA ROMPE PRESION (01 UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX 6", E=20m
CONCRETO f'c=100 kg/cm2
CONCRETO f'c=140 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIO DE CAMARA ROMPE PRESION
RESERVORIO DE PIRIARI V=10M3 (01UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
CORTE C/MAQUINARIA EN TERRENO DE MATERIAL COMPACTO
REFINE Y NIVELACION DE PLATAFORMA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
ESCALERA INTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
VENTILACION DE F°G° DE DN=75MM
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
PINTURA ANTICORROCIVA A DOS MANOS
VALVULAS, ACCESORIOS Y TUBERIA
ACCESORIO P/INGRESO DE RESERVORIO DN 63MM
ACCESORIO P/SALIDA DE RESERVORIO
ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA
CASETA DE CLORACION (01 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
SUMINISTRO E INSTALACION DE ACCESORIOS
SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE CLORACION
CAMARA DE DISTRIBUCION DE CAUDALES 02 SALIDAS (01 UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
RED DE DISTRIBUCION PIRIARI (L=2+120.00 m)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2"
PRUEBA DE CALIDAD
DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA DE AGUA
VALVULA DE AIRE (03 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ABRAZADERA PVC SP CON REDUCCION DN 50 MM A Ø 1"
VALVULA DE PURGA (02 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO E=0.10m
CONCRETO f'c = 140 kg/cm2
OBRAS DE CONCRETO ESTRUCTURA
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 32 MM
VALVULA DE CONTROL (04 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS V. CONTROL 1"
ACCESORIOS V. CONTROL 3/4"
CONEXIONES DOMICILIARIAS PIRIARI (35 UNID.)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CONEXIONES DOMICILIARIA (35 UNID)
SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN CONEXIONES DOMICIALIARIAS
SERVICIO DE AGUA POTABLE VISTA ALEGRE
LINEA DE CONDUCCION (2+760KM)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 75MM C/ANILLO
PRUEBA DE CALIDAD
DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
VALVULA DE AIRE (07 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ABRAZADERA PVC SP CON REDUCCION DN 63 MM A Ø 1"
VALVULA DE PURGA (06 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO E=0.10m
CONCRETO f'c = 140 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
CAMARA DE DISTRIBUCION DE CAUDALES 02 SALIDAS (01 UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
RESERVORIO DE VISTA ALEGRE V=8 M3 (01UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
CORTE C/MAQUINARIA EN TERRENO DE MATERIAL COMPACTO
REFINE Y NIVELACION DE PLATAFORMA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO PULIDO
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
ESCALERA INTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
ESCALERA EXTERIOR METALICA PREFABRICADA DE TUB F°G° DE 11/2"
VENTILACION DE F°G° DE DN=75MM
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
PINTURA ANTICORROCIVA A DOS MANOS
VALVULAS, ACCESORIOS Y TUBERIA
ACCESORIO P/INGRESO DE RESERVORIO DN 63MM
ACCESORIO P/SALIDA DE RESERVORIO
ACCESORIO P/BY PASS DE RESERVORIO Y TUBERIA
CASETA DE CLORACION (01 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
SUMINISTRO E INSTALACION DE ACCESORIOS
SUMINISTRO E INST. DE ACCESORIOS EN CASETA DE CLORACION
RED DE DISTRIBUCION VISTA ALEGRE (L=7+028.00 m)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2"
TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO
PRUEBA DE CALIDAD
DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA DE AGUA
VALVULA DE AIRE (02 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIOS VALVULA DE AIRE D=110MM
VALVULA DE PURGA (02 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO E=0.10m
CONCRETO f'c = 140 kg/cm2
OBRAS DE CONCRETO ESTRUCTURA
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
VALVULA DE CONTROL (03 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS V. CONTROL 1"
ACCESORIOS V. CONTROL 3/4"
CONEXIONES DOMICILIARIAS VISTA ALEGRE (48 UNID.)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CONEXIONES DOMICILIARIA (48 UNID)
SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN CONEXIONES DOMICIALIARIAS
SERVICIO DE AGUA POTABLE RAMAL PIRIARI VISTA ALEGRE
LINEA DE ADUCCION RAMAL (1+649 KM)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 63MM C/ANILLO
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1- 1/2"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
PRUEBA DE CALIDAD
DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
VALVULA DE AIRE (02 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIOS VALVULA DE AIRE D=63 MM
------------------------------------------
CAMARA ROMPE PRESION (01 UNID)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA MORTERO 1:8+30% DE P.M. MAX 6", E=20m
CONCRETO f'c=100 kg/cm2
CONCRETO f'c=140 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIO DE CAMARA ROMPE PRESION
RED DE DISTRIBUCION RAMAL (L=2+575 m)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
INSTALACION DE TUBERIA
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 1/2"
TUBERIA DE PVC C - 10 NTP ISO 399.002 Ø 3/4"
PRUEBA DE CALIDAD
DOBLE PRUEVA HIDRAULICA Y DESENFICCION DE TUBERIA DE AGUA
VALVULA DE AIRE (02 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
ACCESORIOS VALVULA DE AIRE D=63MM
VALVULA DE PURGA (02 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
ASENTAMIENTO DE PIEDRA CHANCADA Ø= 1/2" COMPACTADO Y APISONADO E=0.10m
CONCRETO f'c = 140 kg/cm2
OBRAS DE CONCRETO ESTRUCTURA
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS P/VALVULA DE PURGA DE DN 63MM
VALVULA DE CONTROL (04 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CARPINTERIA METALICA
MARCO Y TAPA METALICA SANITARIA DE 0.60x0.60m, E=1/4"
PINTURA
PINTURA LATEX SATINADO A DOS MANOS
ACCESORIOS
ACCESORIOS V. CONTROL 1"
ACCESORIOS V. CONTROL 3/4"
CONEXIONES DOMICILIARIAS RAMAL (10 UNID.)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CONEXIONES DOMICILIARIA (10 UNID)
SUMINISTRO E INSTALACION DE VALVULA Y ACCESORIO EN CONEXIONES DOMICIALIARIAS
SERVICIO DE ALCANTARILLADO SANITARIO MONTE SINAI (88 UND)
OBRAS PROVISIONALES
TRANSPORTE DE MATERIALES (ALCANTARILLADO)

MOVILIZACION FLETE DE MATERIALES (ALCANTARILLADO)


RED DE COLECTORES (L=1034.43 m)
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
LIMPIEZA MANUAL DE TERRENO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
SUMINISTRO E INSTALACION DE TUBERIAS
SUMINISTRO E INSTALACION DE TUBERIA PVC S-20 NTP ISO 4435 DN 160MM C/ANILLO
PRUEBA DE CALIDAD
DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
RED DE EMISORES (L=421.21 m)
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
LIMPIEZA MANUAL DE TERRENO
SEÑALIZACION PARA LIMITES DE SEGURIDAD VIAL
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN ZANJA EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.50x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
SUMINISTRO E INSTALACION DE TUBERIAS
SUMINISTRO E INSTALACION DE TUBERIA PVC S-20 NTP ISO 4435 DN 160MM C/ANILLO
PRUEBA DE CALIDAD
DOBLE PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA DE AGUA
BUZONES TIPO
BUZON DE ALCANTARILLADO TIPO I Øint=1.20, H=0.80 - 1.50m (14 und)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
PERFILADO MANUAL DE LAS PAREDES DE BUZONES
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
CONCRETO f'c=140 kg/cm2,
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESNCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
MARCO DE FIERRO FUNDIDO Y PLATINA DE DE BORDE TAPA (segun diseño)
REVOQUES
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
BUZON DE ALCANTARILLADO TIPO II Øint=1.20 H=1.50m - 3.00m (05 und)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
PERFILADO MANUAL DE LAS PAREDES DE BUZONES
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
CONCRETO f'c=140 kg/cm2,
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
MARCO DE FIERRO FUNDIDO Y PLATINA DE DE BORDE TAPA (segun diseño)
REVOQUES
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
BUZON DE ALCANTARILLADO TIPO III Øint=1.20m H=MAYORES A 5.0m (06 und)

TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA AGUA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
PERFILADO MANUAL DE LAS PAREDES DE BUZONES
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
CONCRETO f'c=140 kg/cm2,
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
MARCO DE FIERRO FUNDIDO Y PLATINA DE DE BORDE TAPA (segun diseño)
REVOQUES
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
INSTALACION DE CONEXION DOMICILIARIA (88 UNID.)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL
CONEXIONES DOMICILIARIA (88 UNID)
CONEXION DE DESAGUE D= 160 MM TERRENO SEMIROC. HASTA 4.00M
SERVICIO DE SANEAMIENTO BASICO
UNIDAD BASICA UNINI (63 UND)
CASETA
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
CIMIENTO CORRIDO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO CORRIDO
ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO
CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE CIMIENTO
ENCOFRADO Y DESENCOFRADO NORMAL
SARDINEL DE DUCHA h=0.20 m
LOSA PISO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
ELIMINACION MATERAIL EXCEDENTE
REFINE Y NIVELACION PARA LOSA
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
MUROS Y COLUMNAS
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2 PARA COLUMNETAS
MUROS Y TABIQUERIA
MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm ACABADO PULIDO
PISOS Y PAVIMENTO
CONTRAPISO ACABADO PULIDO DE 2"
COBERTURAS
ESTRUCTURA DE MADERA
CORREAS DE MADERA TORNILLO DE 2"x2"

CORREAS DE MADERA TORNILLO DE 2"x3"


COBERTURAS LIVIANA DE CALAMINA
COBERTURA CON CALAMINA GALVANIZADA
PUERTAS Y VENTANAS
CARPINTERIA DE MADERA
MARCO Y PUERTA DE MADERA C/ CALAMINA GALVANIZADA
VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 X 0.80)
CERRAJERIA
BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2"
CERRADURA TIPO PERILLA ALUMINIO 60mm
LAVADERO DOMICIARIO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO LAVADERO
CONTRAPISO e=4 cm.ACABADO TIPO VEREDA
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=175 kg/cm2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
MUROS Y TABIQUERIA
MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
INSTALACIONES SANITARIAS AGUA
APARATOS Y ACCESORIOS SANITARIO
INODORO TANQUE BAJO INC./COLOCACION
LAVADERO DE PARED
DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE MEZCLADORA
CODO PVC SAL 2"x90º
CODO PVC SAL 2"x45º
TEE PVC SAL 2"
YEE PVC SAL 2"
SALIDA DE PVC SAL DE VENTILACION DE 2"
SUMIDERO DE BRONCE ROSCADO 2"
REGISTRO DE BRONCE 2"
ACCESORIO DE AGUA
SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2"
RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2"
TEE PVC SP 1/2"
CODO PVC SP 1/2"x90º
UNION UNIVERSAL PVC 1/2"
NIPLE C/ROSCA DE F°G° 1/2", L=1"
ADAPTADOR C/ROSCA PVC 1/2"
VALVULA COMPUERTA DE BRONCE 1/2"
VALVULA ESFERICA DE 1/2"
GRIFO BRONCE DE 1/2"
EVACUACION DE AGUAS RESIDUALES
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
SISTEMA DE AGUAS GRISES
TRAMPA DE NATAS Y SOLIDOS
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
TEE PVC SAL 2"
RED DE DESAGÜE 2"
EXCAVACION A MANO EN TERRENO NORMAL
CAMA DE APOYO C/MATERIAL DE PRESTAMO
SUMINISTRO Y COLOCACION TUBERIA PVC DE 2"
SISTEMA DE AGUAS NEGRAS
CAJA DE REGISTRO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
SUMINISTRO E INSTALACION BIODIGESTOR
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
SOLADO e=4", CONCRETO C:H, 1:10
ACCESORIOS
BIODIGESTOR AUTOLIMPIABLE V=750 lts

REGISTRO DE LODOS
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
ACCESORIOS
ADAPTADOR C/ROSCA PVC 2"
UNION UNIVERSAL DE PVC SP 2"
VALVULA COMPUERTA DE BRONCE 2"
RED DE DESAGÚE 4"
EXCAVACION A MANO EN TERRENO NORMAL
CAMA DE APOYO C/MATERIAL DE PRESTAMO
SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4"
CAJA DISTRIBUIDORA DE CAUDALES
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ZANJAS DE INFILTRACION
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION FONDO ZANJA
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
RELLENO CON MATERIAL SELECCIONADO
RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - 2"
RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 1/2" - 2"
RELLENO CON MATERIAL PROPIO
ACCESORIOS
MATERIAL INFILTRANTE EN ZANJAS
TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO
UNIDAD BASICA PIRIARI (35 UND)
CASETA
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
CIMIENTO CORRIDO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO CORRIDO
ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO
CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE CIMIENTO
ENCOFRADO Y DESENCOFRADO NORMAL
SARDINEL DE DUCHA h=0.20 m
LOSA PISO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
ELIMINACION MATERAIL EXCEDENTE
REFINE Y NIVELACION PARA LOSA
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
MUROS Y COLUMNAS
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2 PARA COLUMNETAS
MUROS Y TABIQUERIA
MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm ACABADO PULIDO
PISOS Y PAVIMENTO
CONTRAPISO ACABADO PULIDO DE 2"
COBERTURAS
ESTRUCTURA DE MADERA
CORREAS DE MADERA TORNILLO DE 2"x2"

CORREAS DE MADERA TORNILLO DE 2"x3"


COBERTURAS LIVIANA DE CALAMINA
COBERTURA CON CALAMINA GALVANIZADA
PUERTAS Y VENTANAS
CARPINTERIA DE MADERA
MARCO Y PUERTA DE MADERA C/ CALAMINA GALVANIZADA
VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 X 0.80)
CERRAJERIA
BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2"
CERRADURA TIPO PERILLA ALUMINIO 60mm
LAVADERO DOMICIARIO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO LAVADERO
CONTRAPISO e=4 cm.ACABADO TIPO VEREDA
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=175 kg/cm2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
MUROS Y TABIQUERIA
MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
INSTALACIONES SANITARIAS AGUA
APARATOS Y ACCESORIOS SANITARIO
INODORO TANQUE BAJO INC./COLOCACION
LAVADERO DE PARED
DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE MEZCLADORA
CODO PVC SAL 2"x90º
CODO PVC SAL 2"x45º
TEE PVC SAL 2"
YEE PVC SAL 2"
SALIDA DE PVC SAL DE VENTILACION DE 2"
SUMIDERO DE BRONCE ROSCADO 2"
REGISTRO DE BRONCE 2"
ACCESORIO DE AGUA
SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2"
RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2"
TEE PVC SP 1/2"
CODO PVC SP 1/2"x90º
UNION UNIVERSAL PVC 1/2"
NIPLE C/ROSCA DE F°G° 1/2", L=1"
ADAPTADOR C/ROSCA PVC 1/2"
VALVULA COMPUERTA DE BRONCE 1/2"
VALVULA ESFERICA DE 1/2"
GRIFO BRONCE DE 1/2"
EVACUACION DE AGUAS RESIDUALES
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
SISTEMA DE AGUAS GRISES
TRAMPA DE NATAS Y SOLIDOS
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
TEE PVC SAL 2"
RED DE DESAGÜE 2"
EXCAVACION A MANO EN TERRENO NORMAL
CAMA DE APOYO C/MATERIAL DE PRESTAMO
SUMINISTRO Y COLOCACION TUBERIA PVC DE 2"
SISTEMA DE AGUAS NEGRAS
CAJA DE REGISTRO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
SUMINISTRO E INSTALACION BIODIGESTOR
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
SOLADO e=4", CONCRETO C:H, 1:10
ACCESORIOS
BIODIGESTOR AUTOLIMPIABLE V=750 lts

REGISTRO DE LODOS
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
ACCESORIOS
ADAPTADOR C/ROSCA PVC 2"
UNION UNIVERSAL DE PVC SP 2"
VALVULA COMPUERTA DE BRONCE 2"
RED DE DESAGÚE 4"
EXCAVACION A MANO EN TERRENO NORMAL
CAMA DE APOYO C/MATERIAL DE PRESTAMO
SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4"
CAJA DISTRIBUIDORA DE CAUDALES
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ZANJAS DE INFILTRACION
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION FONDO ZANJA
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
RELLENO CON MATERIAL SELECCIONADO
RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - 2"
RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 1/2" - 2"
RELLENO CON MATERIAL PROPIO
ACCESORIOS
MATERIAL INFILTRANTE EN ZANJAS
TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO
UNIDAD BASICA VISTA ALEGRE (48 UND)
CASETA
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
CIMIENTO CORRIDO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO CORRIDO
ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO
CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE CIMIENTO
ENCOFRADO Y DESENCOFRADO NORMAL
SARDINEL DE DUCHA h=0.20 m
LOSA PISO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
ELIMINACION MATERAIL EXCEDENTE
REFINE Y NIVELACION PARA LOSA
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
MUROS Y COLUMNAS
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2 PARA COLUMNETAS
MUROS Y TABIQUERIA
MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm ACABADO PULIDO
PISOS Y PAVIMENTO
CONTRAPISO ACABADO PULIDO DE 2"
COBERTURAS
ESTRUCTURA DE MADERA
CORREAS DE MADERA TORNILLO DE 2"x2"

CORREAS DE MADERA TORNILLO DE 2"x3"


COBERTURAS LIVIANA DE CALAMINA
COBERTURA CON CALAMINA GALVANIZADA
PUERTAS Y VENTANAS
CARPINTERIA DE MADERA
MARCO Y PUERTA DE MADERA C/ CALAMINA GALVANIZADA
VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 X 0.80)
CERRAJERIA
BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2"
CERRADURA TIPO PERILLA ALUMINIO 60mm
LAVADERO DOMICIARIO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO LAVADERO
CONTRAPISO e=4 cm.ACABADO TIPO VEREDA
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=175 kg/cm2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
MUROS Y TABIQUERIA
MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
INSTALACIONES SANITARIAS AGUA
APARATOS Y ACCESORIOS SANITARIO
INODORO TANQUE BAJO INC./COLOCACION
LAVADERO DE PARED
DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE MEZCLADORA
CODO PVC SAL 2"x90º
CODO PVC SAL 2"x45º
TEE PVC SAL 2"
YEE PVC SAL 2"
SALIDA DE PVC SAL DE VENTILACION DE 2"
SUMIDERO DE BRONCE ROSCADO 2"
REGISTRO DE BRONCE 2"
ACCESORIO DE AGUA
SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2"
RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2"
TEE PVC SP 1/2"
CODO PVC SP 1/2"x90º
UNION UNIVERSAL PVC 1/2"
NIPLE C/ROSCA DE F°G° 1/2", L=1"
ADAPTADOR C/ROSCA PVC 1/2"
VALVULA COMPUERTA DE BRONCE 1/2"
VALVULA ESFERICA DE 1/2"
GRIFO BRONCE DE 1/2"
EVACUACION DE AGUAS RESIDUALES
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
SISTEMA DE AGUAS GRISES
TRAMPA DE NATAS Y SOLIDOS
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
TEE PVC SAL 2"
RED DE DESAGÜE 2"
EXCAVACION A MANO EN TERRENO NORMAL
CAMA DE APOYO C/MATERIAL DE PRESTAMO
SUMINISTRO Y COLOCACION TUBERIA PVC DE 2"
SISTEMA DE AGUAS NEGRAS
CAJA DE REGISTRO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
SUMINISTRO E INSTALACION BIODIGESTOR
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
SOLADO e=4", CONCRETO C:H, 1:10
ACCESORIOS
BIODIGESTOR AUTOLIMPIABLE V=750 lts

REGISTRO DE LODOS
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
ACCESORIOS
ADAPTADOR C/ROSCA PVC 2"
UNION UNIVERSAL DE PVC SP 2"
VALVULA COMPUERTA DE BRONCE 2"
RED DE DESAGÚE 4"
EXCAVACION A MANO EN TERRENO NORMAL
CAMA DE APOYO C/MATERIAL DE PRESTAMO
SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4"
CAJA DISTRIBUIDORA DE CAUDALES
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ZANJAS DE INFILTRACION
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION FONDO ZANJA
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
RELLENO CON MATERIAL SELECCIONADO
RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - 2"
RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 1/2" - 2"
RELLENO CON MATERIAL PROPIO
ACCESORIOS
MATERIAL INFILTRANTE EN ZANJAS
TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO
UNIDAD BASICA RAMAL (10 UND)
CASETA
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
CIMIENTO CORRIDO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO CORRIDO
ENCOFRADO Y DESENCOFRADO DE SOBRE CIMIENTO
CONCRETO f'c=140kg/cm2+25%P.M. EN SOBRE CIMIENTO
ENCOFRADO Y DESENCOFRADO NORMAL
SARDINEL DE DUCHA h=0.20 m
LOSA PISO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
ELIMINACION MATERAIL EXCEDENTE
REFINE Y NIVELACION PARA LOSA
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
MUROS Y COLUMNAS
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2 PARA COLUMNETAS
MUROS Y TABIQUERIA
MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
TARRAJEO EN COLUMNAS MORTERO C:A 1:5, E=1.5cm ACABADO PULIDO
PISOS Y PAVIMENTO
CONTRAPISO ACABADO PULIDO DE 2"
COBERTURAS
ESTRUCTURA DE MADERA
CORREAS DE MADERA TORNILLO DE 2"x2"

CORREAS DE MADERA TORNILLO DE 2"x3"


COBERTURAS LIVIANA DE CALAMINA
COBERTURA CON CALAMINA GALVANIZADA
PUERTAS Y VENTANAS
CARPINTERIA DE MADERA
MARCO Y PUERTA DE MADERA C/ CALAMINA GALVANIZADA
VENTANA DE MADERA V1, C/ MALLA MOSQUITERO (0.94 X 0.80)
CERRAJERIA
BISAGRAS CAPUCHINA ALUMINIZADA DE 3 1/2 X 3 1/2"
CERRADURA TIPO PERILLA ALUMINIO 60mm
LAVADERO DOMICIARIO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100kg/cm2 +30% P.M. CIMIENTO LAVADERO
CONTRAPISO e=4 cm.ACABADO TIPO VEREDA
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=175 kg/cm2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
MUROS Y TABIQUERIA
MUROS DE LADRILLO ARTESANAL DE ARCILLLA K.K.0.23x0.12x0.08M
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
INSTALACIONES SANITARIAS AGUA
APARATOS Y ACCESORIOS SANITARIO
INODORO TANQUE BAJO INC./COLOCACION
LAVADERO DE PARED
DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE MEZCLADORA
CODO PVC SAL 2"x90º
CODO PVC SAL 2"x45º
TEE PVC SAL 2"
YEE PVC SAL 2"
SALIDA DE PVC SAL DE VENTILACION DE 2"
SUMIDERO DE BRONCE ROSCADO 2"
REGISTRO DE BRONCE 2"
ACCESORIO DE AGUA
SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2"
RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2"
TEE PVC SP 1/2"
CODO PVC SP 1/2"x90º
UNION UNIVERSAL PVC 1/2"
NIPLE C/ROSCA DE F°G° 1/2", L=1"
ADAPTADOR C/ROSCA PVC 1/2"
VALVULA COMPUERTA DE BRONCE 1/2"
VALVULA ESFERICA DE 1/2"
GRIFO BRONCE DE 1/2"
EVACUACION DE AGUAS RESIDUALES
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
SISTEMA DE AGUAS GRISES
TRAMPA DE NATAS Y SOLIDOS
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ACCESORIOS
TEE PVC SAL 2"
RED DE DESAGÜE 2"
EXCAVACION A MANO EN TERRENO NORMAL
CAMA DE APOYO C/MATERIAL DE PRESTAMO
SUMINISTRO Y COLOCACION TUBERIA PVC DE 2"
SISTEMA DE AGUAS NEGRAS
CAJA DE REGISTRO
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
SUMINISTRO E INSTALACION BIODIGESTOR
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
SOLADO e=4", CONCRETO C:H, 1:10
ACCESORIOS
BIODIGESTOR AUTOLIMPIABLE V=750 lts

REGISTRO DE LODOS
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
ACCESORIOS
ADAPTADOR C/ROSCA PVC 2"
UNION UNIVERSAL DE PVC SP 2"
VALVULA COMPUERTA DE BRONCE 2"
RED DE DESAGÚE 4"
EXCAVACION A MANO EN TERRENO NORMAL
CAMA DE APOYO C/MATERIAL DE PRESTAMO
SUMINISTRO Y COLOCACION TUBERIA PVC SAL 4"
CAJA DISTRIBUIDORA DE CAUDALES
MOVIMIENTO DE TIERRAS
EXCAVACION A MANO EN TERRENO NORMAL
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140kg/cm2+25%P.M.
ENCOFRADO Y DESENCOFRADO NORMAL
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO PARA SARDINEL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
PINTURA
PINTURA ANTICORROCIVA A DOS MANOS
ZANJAS DE INFILTRACION
MOVIMIENTO DE TIERRAS
REFINE Y NIVELACION FONDO ZANJA
EXCAVACION A MANO EN TERRENO NORMAL
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
RELLENO CON MATERIAL SELECCIONADO
RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1" - 2"
RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1 1/2" - 2"
RELLENO CON MATERIAL PROPIO
ACCESORIOS
MATERIAL INFILTRANTE EN ZANJAS
TUBERIA PARA PERCOLACION SEGUN DETALLE PLANO
PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES
CAMARA DE REJAS Y DESARENADOR (01 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERIAL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
CARPINTERIA METALICA
REJA S NORMA RNC 30MM (e=15 t=30mm abertura 25mm)
COMPUERTAS
CAMARA REPARTIDORA DE CAUDALES(01 UND)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERIAL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=100 kg/cm2
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:5, E=1.5 cm, ACABADO FROTACHADO
CARPINTERIA METALICA
TAPA Y MARCO FFD PESADO
COMPUERTAS
TANQUE SEPTICO
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERIAL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
SOLADO e=3" MEZCLA 1:2 CEMENTO HORMIGON
DADO DE CONCRETO PARA ANCLAJE TUBERIA - CAMARA
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2 P/LOSA DE FONDO - PISO
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC S-25 NTP ISO 4435 DN 200MM C/ANILLO
SUMINISTRO E INSTALACION DE TUBERIA PVC S-20 NTP ISO 4435 DN 160MM C/ANILLO
SUMINISTRO INST. VALVULA DE COMPUERTA DE HDF PARA TUB. PVC UF DN 200
SUMINISTRO E INSTALACION DE TEE SANITARIA DN=200mm
SUMINISTRO E INSTALACION DE TEE SANITARIA DN=160mm
VENTILACION DE F°G° DE DN=75MM
LECHO DE SECADO
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
RELLENO C/AFIRMADO
RELLENO C/AGREGADO ARENA GRUESA E=0.35M
RELLENO CON GRAVA SUELTO DE 1/2"
RELLENO CON GRAVA SUELTO DE 3/4"
ELIMINACION MATERIAL EXCEDENTE
OBRAS DE CONCRETO ARMADO
CONCRETO f'c=210KG/CM2 P/LOSA DE FONDO - PISO
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
REVOQUES Y ENLUCIDOS
TARRAJEO EN INTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
TARRAJEO EN EXTERIOR C/MORTERO C.A., 1:3, C/IMPERMEABILIZANTES
MUROS Y TABIQUERIA
MURO DE LADRILLO K.K. APAREJO DE SOGA E=0.12m (ESP. HORIZONTAL E=0.10m)
COBERTURA
VIGA DE MADERA TORNILLO 3"x6"
CORREAS DE MADERA TORNILLO DE 2"x2"
PLANCHA DE CALAMINA TIPO TEJA ANDINA 0.72x1.14M
CAMARA DISTRIBUIDORA DE CAUDALES (03)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION PARA LOSA
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO ARMADO
ENCOFRADO Y DESENCOFRADO NORMAL
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
CONCRETO f'c=210KG/CM2
CURADO DE CONCRETO
CURADO CON PRODUCTO QUIMICO
REVOQUES Y ENLUCIDOS
TARRAJEO CON IMPERMEABILIZANTE C.A., 1:3, DILUCION IMP. AGUA 1:10; E=1.5 cm, ACABADO PULIDO
CARPINTERIA METALICA
TAPA Y MARCO FFD PESADO
COMPUERTAS
ACCESORIOS
TUBERIA PVC SAL DE 4"
POZO DE PERCOLACION (06)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
ELIMINACION MATERIAL EXCEDENTE
CONCRETO SIMPLE
CONCRETO CILOPEO PARA CIMIENTACION 1:10 + 30% P.G.
CONCRETO ARMADO
CONCRETO f'c=175 kg/cm2
ACERO CORRUGADO f'y=4200 kg/cm2, GRADO 60
ENCOFRADO Y DESENCOFRADO NORMAL
TABIQUERIA EN FORMA CIRCULAR
MURO LADRILLO K.K. DE ARCILLA 18 H. (0.09x0.13x0.24) AMARRE DE CANTO MORTERO 1:1:5
RELLENO CON GRAVA
RELLENO CON MATERIAL SELECIONADO GRAVA Ø=1"
ACCESORIOS
TUBERIA DE PVC C - 7.5 NTP ISO 1452 DN 160MM
TUBERIA PVC SAL DE 2"
INSTALACION DE TUBERIAS (180m)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR C/ EQUIPO
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE MATERIAL SUELTO EN ZANJA
REFINE Y NIVELACION MANUAL DE ZANJA EN TERRENO MATERIAL COMPACTADO
CAMA DE APOYO PARA TUBERIA (0.60x0.10m)
RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO (0.60 x 0.20 m)
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
TENDIDO DE TUBERIA
SUMINISTRO Y COLOCACION DE TUBERIA DE PVC C-7.5 NTP 1452 DN 200MM
CERCO PERIMETRICO (L=120.00 m)
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO
TRAZO Y REPLANTEO PRELIMINAR P / ESTRUCTURA
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO DE MATERIAL COMPACTADO
REFINE Y NIVELACION DE FONDO DE TERRENO
RELLENO Y COMPACTADO C/MATERIAL PROPIO ZARANDEADO
ELIMINACION MATERAIL EXCEDENTE
OBRAS DE CONCRETO SIMPLE
CONCRETO f'c=140 kg/cm2
CERCO PERIMETRICO CON MALLA OLIMPICA GALVANIZADA
CERCO PERIMETRICO DE ALAMBRE DE PUAS
PUERTA DE MADERA CON MARCO O SOPORTES
PINTURA ESMALTE EN PUERTAS Y VENTANAS A DOS MANOS
CAPACITACION Y EDUCACION
DESAROLLO DE LAS CAPACITACIONES Y/O TALLERES ENSIBILIZACION, EDUCACION Y PARTICIPACION CIUDADANA DE APOYO A LA GESTION DE
MITIGACION DEL IMPACTO AMBIENTAL
MITIGACION DEL IMPACTO AMBIENTAL
Und. Metrado Precio (S/.) Parcial (S/.)
1,131,181.33
96,882.40
glb 1.00 3,600.00 3,600.00
und 1.00 1,986.12 1,986.12
glb 1.00 71,745.59 71,745.59
glb 1.00 16,220.45 16,220.45
m3 96.00 34.69 3,330.24
911.78
m 2.00 120.97 241.94
und 2.00 334.92 669.84
44,400.82
113.28
m2 92.85 0.53 49.21
m2 92.85 0.69 64.07
5,553.56
m3 118.98 34.69 4,127.42
m2 11.44 1.04 11.90
m3 29.74 15.72 467.51
m3 89.23 10.61 946.73
17,643.29
m3 71.64 211.19 15,129.65
m3 11.54 217.82 2,513.64
12,342.25
m3 14.86 366.40 5,444.70
m2 125.46 21.45 2,691.12
kg 1,043.78 4.03 4,206.43
92.87
m2 103.19 0.90 92.87
2,765.92
m2 109.69 20.68 2,268.39
m2 26.38 18.86 497.53
1,509.64
und 1.00 1,149.82 1,149.82
und 1.00 359.82 359.82
3,430.69
m2 136.07 10.13 1,378.39
m2 109.69 18.71 2,052.30
949.32
und 1.00 949.32 949.32
11,261.94
21.92
m2 17.82 0.54 9.62
m2 17.82 0.69 12.30
729.06
m3 15.26 34.69 529.37
m2 16.62 1.06 17.62
m3 3.81 15.93 60.69
m3 11.44 10.61 121.38
361.58
m3 1.66 217.82 361.58
6,327.70
m3 7.45 351.00 2,614.95
kg 775.96 4.05 3,142.64
m2 26.20 21.76 570.11
23.92
m2 26.58 0.90 23.92
512.16
m2 27.58 18.57 512.16
2,683.92
und 2.00 542.14 1,084.28
und 2.00 799.82 1,599.64
196.83
m2 19.43 10.13 196.83
404.85
und 1.00 404.85 404.85
623,099.68
14,311.20
m2 7,120.00 0.53 3,773.60
m2 7,120.00 1.48 10,537.60
333,956.48
m3 5,696.00 26.52 151,057.92
m 14,240.00 1.06 15,094.40
m 14,240.00 4.70 66,928.00
m 14,240.00 2.71 38,590.40
m3 4,272.00 14.58 62,285.76
267,142.40
m 14,240.00 18.76 267,142.40
7,689.60
m 14,240.00 0.54 7,689.60
16,906.30
26.11
m2 21.06 0.54 11.37
m2 21.06 0.70 14.74
491.64
m3 12.64 26.52 335.21
m2 21.06 1.06 22.32
m3 12.64 10.61 134.11
7,274.93
m3 13.10 335.08 4,389.55
m2 132.60 21.76 2,885.38
119.34
m2 132.60 0.90 119.34
1,714.23
m2 110.24 15.55 1,714.23
1,894.36
und 26.00 72.86 1,894.36
1,190.59
m2 110.24 10.80 1,190.59
4,195.10
und 26.00 161.35 4,195.10
3,836.32
7.14
m2 5.75 0.54 3.11
m2 5.75 0.70 4.03
176.68
m3 4.68 26.52 124.11
m2 5.75 1.06 6.10
m3 4.38 10.61 46.47
190.13
m3 0.23 28.93 6.65
m3 0.63 291.24 183.48
1,643.95
m3 2.63 335.08 881.26
m2 35.05 21.76 762.69
364.30
und 5.00 72.86 364.30
85.17
m2 10.20 8.35 85.17
1,368.95
und 5.00 273.79 1,368.95
1,147.04
2.30
m2 1.85 0.54 1.00
m2 1.85 0.70 1.30
72.19
m3 1.90 26.52 50.39
m2 1.55 1.06 1.64
m3 1.90 10.61 20.16
182.05
m2 2.56 54.70 140.03
m3 0.07 217.82 15.25
m3 0.04 261.29 10.45
m2 0.75 21.76 16.32
650.25
m3 0.91 351.00 319.41
m2 10.16 21.76 221.08
kg 27.10 4.05 109.76
0.82
m2 0.91 0.90 0.82
55.98
m2 3.60 15.55 55.98
72.86
und 1.00 72.86 72.86
21.60
m2 2.00 10.80 21.60
88.99
und 1.00 88.99 88.99
43,661.08
486.58
m2 392.40 0.54 211.90
m2 392.40 0.70 274.68
2,038.44
m3 54.90 26.52 1,455.95
m3 54.90 10.61 582.49
196.04
m3 0.90 217.82 196.04
20,712.52
m3 18.52 351.00 6,500.52
m3 28.80 335.08 9,650.30
m2 66.96 21.76 1,457.05
kg 766.58 4.05 3,104.65
1,041.23
m2 66.96 15.55 1,041.23
19,186.27
m 150.30 37.74 5,672.32
und 99.00 53.82 5,328.18
und 117.00 14.62 1,710.54
m 126.00 22.91 2,886.66
glb 9.00 312.80 2,815.20
und 9.00 85.93 773.37

125,496.56
178.56
m2 144.00 0.54 77.76
m2 144.00 0.70 100.80
13,238.34
m3 453.10 26.52 12,016.21
m2 144.00 1.06 152.64
m3 100.80 10.61 1,069.49
1,568.30
m3 7.20 217.82 1,568.30
65,668.81
m3 79.98 351.00 28,072.98
kg 5,228.36 4.05 21,174.86
m2 754.64 21.76 16,420.97
244.89
m2 272.10 0.90 244.89
11,816.12
m2 174.40 18.12 3,160.13
m2 458.96 18.86 8,655.99
8,418.66
m2 174.40 8.35 1,456.24
m2 458.96 15.17 6,962.42
22,285.20
m3 18.90 125.31 2,368.36
m3 37.80 119.31 4,509.92
m3 75.60 125.31 9,473.44
m3 31.08 190.91 5,933.48
2,077.68
glb 2.00 1,038.84 2,077.68
149,269.73
150.25
m2 121.17 0.54 65.43
m2 121.17 0.70 84.82
17,611.04
m3 204.89 74.64 15,292.99
m2 49.38 1.06 52.34
m3 17.97 15.72 282.49
m3 186.92 10.61 1,983.22
26,906.02
m2 8.90 100.20 891.78
m3 119.43 217.82 26,014.24
74,404.63
m3 96.56 351.00 33,892.56
kg 7,736.61 4.05 31,333.27
m2 421.82 21.76 9,178.80
86.90
m2 96.56 0.90 86.90
998.81
m 53.10 18.81 998.81
6,704.58
m2 312.75 12.11 3,787.40
m2 183.10 12.11 2,217.34
m2 57.79 12.11 699.84
1,550.87
und 1.00 72.86 72.86
und 1.00 200.82 200.82
und 3.00 180.82 542.46
und 3.00 244.91 734.73
18,724.20
m3 10.00 184.91 1,849.10
m3 5.00 190.91 954.55
m3 5.00 190.91 954.55
m3 100.00 149.66 14,966.00
1,552.71
m2 183.10 8.35 1,528.89
m2 1.57 15.17 23.82
579.72
und 1.00 579.72 579.72
7,753.58
147.60
m2 120.00 0.54 64.80
m2 120.00 0.69 82.80
599.69
m3 14.11 26.02 367.14
m2 35.28 1.04 36.69
m3 3.53 15.72 55.49
m3 13.23 10.61 140.37
3,694.64
m3 14.14 261.29 3,694.64
3,311.65
m 240.00 12.57 3,016.80
und 1.00 95.75 95.75
m2 10.00 19.91 199.10
6,554.10
9.69
m2 7.81 0.54 4.22
m2 7.81 0.70 5.47
548.35
m3 16.46 26.52 436.52
m2 7.81 1.06 8.28
m3 9.76 10.61 103.55
6.53
m3 0.03 217.82 6.53
4,474.06
m3 7.17 351.00 2,516.67
m2 73.75 21.76 1,604.80
kg 87.06 4.05 352.59
275.83
m2 73.75 3.74 275.83
707.82
m2 37.53 18.86 707.82
72.86
und 1.00 72.86 72.86
185.17
m2 21.81 8.49 185.17
273.79
und 1.00 273.79 273.79
380,796.28
134,747.45
3,707.93
m2 1,835.61 0.54 991.23
m2 1,835.61 1.48 2,716.70
93,886.48
m3 1,762.19 26.52 46,733.28
m 3,671.22 1.06 3,891.49
m 3,671.22 4.70 17,254.73
m 3,671.22 2.71 9,949.01
m3 1,101.37 14.58 16,057.97
34,730.03
m 3,671.25 9.46 34,730.03
2,423.01
m 3,671.22 0.66 2,423.01
4,736.48
8.04
m2 6.48 0.54 3.50
m2 6.48 0.70 4.54
151.30
m3 3.89 26.52 103.16
m2 6.48 1.06 6.87
m3 3.89 10.61 41.27
2,277.80
m3 4.03 344.91 1,389.99
m2 40.80 21.76 887.81
36.34
m2 40.38 0.90 36.34
527.46
m2 33.92 15.55 527.46
582.88
und 8.00 72.86 582.88
366.34
m2 33.92 10.80 366.34
786.32
und 8.00 98.29 786.32
1,637.06
2.85
m2 2.30 0.54 1.24
m2 2.30 0.70 1.61
70.60
m3 1.87 26.52 49.59
m2 2.30 1.06 2.44
m3 1.75 10.61 18.57
73.00
m3 0.09 28.93 2.60
m3 0.25 281.59 70.40
667.24
m3 1.05 344.91 362.16
m2 14.02 21.76 305.08
145.72
und 2.00 72.86 145.72
34.07
m2 4.08 8.35 34.07
643.58
und 2.00 321.79 643.58
2,336.78
4.57
m2 3.69 0.54 1.99
m2 3.69 0.70 2.58
144.01
m3 3.79 26.52 100.51
m2 3.10 1.06 3.29
m3 3.79 10.61 40.21
378.67
m2 5.12 54.70 280.06
m3 0.14 217.82 30.49
m3 0.14 253.43 35.48
m2 1.50 21.76 32.64
1,329.04
m3 1.81 368.69 667.33
m2 20.32 21.76 442.16
kg 54.21 4.05 219.55
1.63
m2 1.81 0.90 1.63
111.96
m2 7.20 15.55 111.96
145.72
und 2.00 72.86 145.72
43.20
m2 4.00 10.80 43.20
177.98
und 2.00 88.99 177.98
13,456.59
36.16
m2 29.16 0.54 15.75
m2 29.16 0.70 20.41
208.08
m3 7.22 15.55 112.27
m3 9.03 10.61 95.81
810.29
m3 3.72 217.82 810.29
6,438.62
m3 10.10 368.69 3,723.77
kg 324.86 4.05 1,315.68
m2 64.30 21.76 1,399.17
240.48
m2 64.30 3.74 240.48
1,675.20
m2 32.55 18.12 589.81
m2 59.90 18.12 1,085.39
867.41
und 1.00 72.86 72.86
und 1.00 169.91 169.91
und 1.00 294.82 294.82
und 2.00 164.91 329.82
1,583.58
m2 38.72 17.42 674.50
m2 33.62 27.04 909.08
964.35
und 1.00 208.62 208.62
und 1.00 366.59 366.59
und 1.00 389.14 389.14
632.42
0.44
m2 0.36 0.54 0.19
m2 0.36 0.70 0.25
10.03
m3 0.22 26.52 5.83
m2 0.36 1.06 0.38
m3 0.36 10.61 3.82
274.99
m3 0.48 368.69 176.97
kg 18.83 4.05 76.26
m2 1.00 21.76 21.76
7.48
m2 2.00 3.74 7.48
32.32
m2 2.00 16.16 32.32
307.16
glb 1.00 307.16 307.16
199,623.47
4,923.26
m2 2,311.39 0.54 1,248.15
m2 2,311.39 1.59 3,675.11
154,373.06
m3 2,311.39 26.52 61,298.06
m 4,622.78 1.06 4,900.15
m 4,622.78 4.70 21,727.07
m 4,622.78 2.71 12,527.73
m3 3,698.22 14.58 53,920.05
27,992.70
m 2,428.78 8.00 19,430.24
m 299.00 4.49 1,342.51
m 1,895.00 3.81 7,219.95
4,021.82
m 4,622.78 0.87 4,021.82
2,323.14
3.01
m2 2.43 0.54 1.31
m2 2.43 0.70 1.70
56.79
m3 1.46 26.52 38.72
m2 2.43 1.06 2.58
m3 1.46 10.61 15.49
1,137.71
m3 1.51 344.91 520.81
m2 28.35 21.76 616.90
25.52
m2 28.35 0.90 25.52
197.80
m2 12.72 15.55 197.80
218.58
und 3.00 72.86 218.58
247.86
m2 22.95 10.80 247.86
435.87
und 3.00 145.29 435.87
2,986.07
10.72
m2 8.64 0.54 4.67
m2 8.64 0.70 6.05
185.01
m3 4.92 26.52 130.48
m2 4.60 1.06 4.88
m3 4.68 10.61 49.65
152.22
m3 0.20 28.93 5.79
m3 0.52 281.59 146.43
1,043.38
m3 2.28 335.08 763.98
m2 12.84 21.76 279.40
291.44
und 4.00 72.86 291.44
68.14
m2 8.16 8.35 68.14

und 4.00 308.79 1,235.16


3,003.42
4.02
m2 3.24 0.54 1.75
m2 3.24 0.70 2.27
117.52
m3 2.91 26.52 77.17
m2 3.24 1.06 3.43
m3 3.48 10.61 36.92
1,182.75
m3 3.06 317.40 971.24
m2 9.72 21.76 211.51
173.37
und 3.00 57.79 173.37
98.20
m2 11.76 8.35 98.20
1,427.56
und 4.00 136.56 546.24
und 11.00 80.12 881.32
24,258.45
234.36
m2 189.00 0.54 102.06
m2 189.00 0.70 132.30
7,920.15
m3 189.00 26.52 5,012.28
m2 204.00 1.06 216.24
m3 70.20 15.49 1,087.40
m3 151.20 10.61 1,604.23
2,104.08
m3 6.05 320.59 1,939.57
m2 7.56 21.76 164.51
13,999.86
und 63.00 222.22 13,999.86
188,269.20
50,939.28
1,487.73
m2 736.50 0.54 397.71
m2 736.50 1.48 1,090.02
34,544.79
m3 589.20 26.52 15,625.58
m 1,473.00 1.06 1,561.38
m 1,473.00 4.70 6,923.10
m 1,473.00 2.71 3,991.83
m3 441.90 14.58 6,442.90
13,934.58
m 1,473.00 9.46 13,934.58
972.18
m 1,473.00 0.66 972.18
1,916.94
3.01
m2 2.43 0.54 1.31
m2 2.43 0.70 1.70
56.79
m3 1.46 26.52 38.72
m2 2.43 1.06 2.58
m3 1.46 10.61 15.49
853.74
m3 1.51 344.91 520.81
m2 15.30 21.76 332.93
13.77
m2 15.30 0.90 13.77
197.80
m2 12.72 15.55 197.80
218.58
und 3.00 72.86 218.58
137.38
m2 12.72 10.80 137.38
435.87
und 3.00 145.29 435.87
803.79
1.43
m2 1.15 0.54 0.62
m2 1.15 0.70 0.81
35.49
m3 0.94 26.52 24.93
m2 1.15 1.06 1.22
m3 0.88 10.61 9.34
38.06
m3 0.05 28.93 1.45
m3 0.13 281.59 36.61
330.13
m3 0.53 335.08 177.59
m2 7.01 21.76 152.54
72.86
und 1.00 72.86 72.86
17.03
m2 2.04 8.35 17.03
308.79
und 1.00 308.79 308.79
36,260.71
57.74
m2 46.94 0.54 25.35
m2 46.94 0.69 32.39
1,221.61
m3 41.75 15.54 648.80
m2 21.50 1.04 22.36
m3 51.88 10.61 550.45
1,044.40
m3 4.66 224.12 1,044.40
11,002.13
m3 15.69 368.69 5,784.75
kg 785.99 4.05 3,183.26
m2 93.48 21.76 2,034.12
349.62
m2 93.48 3.74 349.62
1,345.47
m2 38.72 18.86 730.26
m2 32.62 18.86 615.21
867.41
und 1.00 72.86 72.86
und 1.00 169.91 169.91
und 1.00 294.82 294.82
und 2.00 164.91 329.82
1,583.58
m2 38.72 17.42 674.50
m2 33.62 27.04 909.08
964.35
und 1.00 208.62 208.62
und 1.00 366.59 366.59
und 1.00 389.14 389.14
632.42
0.44
m2 0.36 0.54 0.19
m2 0.36 0.70 0.25
10.03
m3 0.22 26.52 5.83
m2 0.36 1.06 0.38
m3 0.36 10.61 3.82
274.99
m3 0.48 368.69 176.97
kg 18.83 4.05 76.26
m2 1.00 21.76 21.76
7.48
m2 2.00 3.74 7.48
32.32
m2 2.00 16.16 32.32
307.16
glb 1.00 307.16 307.16
17,191.98
272.80
m2 220.00 0.54 118.80
m2 220.00 0.70 154.00
775.85
m3 18.00 26.52 477.36
m3 4.50 15.93 71.69
m2 45.00 1.06 47.70
m3 16.88 10.61 179.10
4,711.06
m3 18.03 261.29 4,711.06
11,432.27
m 220.00 12.55 2,761.00
und 1.00 287.95 287.95
m2 396.00 21.17 8,383.32
67,820.73
1,790.27
m2 840.50 0.54 453.87
m2 840.50 1.59 1,336.40
46,331.72
m3 840.50 26.52 22,290.06
m 1,681.00 1.06 1,781.86
m 1,681.00 4.70 7,900.70
m 1,681.00 2.71 4,555.51
m3 672.40 14.58 9,803.59
10,392.55
m 356.00 3.81 1,356.36
m 275.00 4.49 1,234.75
m 744.00 6.96 5,178.24
m 186.00 8.00 1,488.00
m 120.00 9.46 1,135.20
1,462.47
m 1,681.00 0.87 1,462.47
2,323.14
3.01
m2 2.43 0.54 1.31
m2 2.43 0.70 1.70
56.79
m3 1.46 26.52 38.72
m2 2.43 1.06 2.58
m3 1.46 10.61 15.49
1,137.71
m3 1.51 344.91 520.81
m2 28.35 21.76 616.90
25.52
m2 28.35 0.90 25.52
197.80
m2 12.72 15.55 197.80
218.58
und 3.00 72.86 218.58
247.86
m2 22.95 10.80 247.86
435.87
und 3.00 145.29 435.87
2,986.07
10.72
m2 8.64 0.54 4.67
m2 8.64 0.70 6.05
185.01
m3 4.92 26.52 130.48
m2 4.60 1.06 4.88
m3 4.68 10.61 49.65
152.22
m3 0.20 28.93 5.79
m3 0.52 281.59 146.43
1,043.38
m3 2.28 335.08 763.98
m2 12.84 21.76 279.40
291.44
und 4.00 72.86 291.44
68.14
m2 8.16 8.35 68.14
1,235.16
und 4.00 308.79 1,235.16
2,534.51
5.35
m2 4.32 0.54 2.33
m2 4.32 0.70 3.02
156.71
m3 3.88 26.52 102.90
m2 4.32 1.06 4.58
m3 4.64 10.61 49.23
1,577.00
m3 4.08 317.40 1,294.99
m2 12.96 21.76 282.01
231.16
und 4.00 57.79 231.16
130.93
m2 15.68 8.35 130.93
433.36
und 2.00 136.56 273.12
und 2.00 80.12 160.24
30,527.75
392.83
m2 316.80 0.54 171.07
m2 316.80 0.70 221.76
8,013.90
m3 168.96 26.52 4,480.82
m2 211.20 1.06 223.87
m3 95.20 15.93 1,516.54
m3 168.96 10.61 1,792.67
2,938.78
m3 8.45 320.59 2,708.99
m2 10.56 21.76 229.79
19,182.24
und 88.00 217.98 19,182.24
229,414.03
114,619.44
3,135.60
m2 1,560.00 0.53 826.80
m2 1,560.00 1.48 2,308.80
72,483.84
m3 1,248.00 26.02 32,472.96
m 3,120.00 1.04 3,244.80
m 3,120.00 4.70 14,664.00
m 3,120.00 2.71 8,455.20
m3 936.00 14.58 13,646.88
36,972.00
m 3,120.00 11.85 36,972.00
2,028.00
m 3,120.00 0.65 2,028.00
1,162.83
2.30
m2 1.85 0.54 1.00
m2 1.85 0.70 1.30
72.19
m3 1.90 26.52 50.39
m2 1.55 1.06 1.64
m3 1.90 10.61 20.16
181.74
m2 2.56 54.70 140.03
m3 0.07 217.82 15.25
m3 0.04 253.43 10.14
m2 0.75 21.76 16.32
666.35
m3 0.91 368.69 335.51
m2 10.16 21.76 221.08
kg 27.10 4.05 109.76
0.82
m2 0.91 0.90 0.82
55.98
m2 3.60 15.55 55.98
72.86
und 1.00 72.86 72.86
21.60
m2 2.00 10.80 21.60
88.99
und 1.00 88.99 88.99
12,275.39
28.57
m2 23.04 0.54 12.44
m2 23.04 0.70 16.13
158.37
m3 5.12 15.55 79.62
m2 10.24 1.06 10.85
m3 6.40 10.61 67.90
228.60
m3 1.02 224.12 228.60
6,678.05
m3 12.02 368.69 4,431.65
kg 280.76 4.05 1,137.08
m2 50.98 21.76 1,109.32
190.67
m2 50.98 3.74 190.67
1,284.94
m2 24.75 18.86 466.79
m2 43.38 18.86 818.15
867.41
und 1.00 72.86 72.86
und 1.00 169.91 169.91
und 1.00 294.82 294.82
und 2.00 164.91 329.82
1,242.01
m2 33.92 17.42 590.89
m2 24.08 27.04 651.12
964.35
und 1.00 208.62 208.62
und 1.00 366.59 366.59
und 1.00 389.14 389.14
632.42
0.44
m2 0.36 0.54 0.19
m2 0.36 0.70 0.25
10.03
m3 0.22 26.52 5.83
m2 0.36 1.06 0.38
m3 0.36 10.61 3.82
274.99
m3 0.48 368.69 176.97
kg 18.83 4.05 76.26
m2 1.00 21.76 21.76
7.48
m2 2.00 3.74 7.48
32.32
m2 2.00 16.16 32.32
307.16
glb 1.00 307.16 307.16
6,804.09
9.69
m2 7.81 0.54 4.22
m2 7.81 0.70 5.47
560.84
m3 16.46 26.52 436.52
m2 7.81 2.66 20.77
m3 9.76 10.61 103.55
6.72
m3 0.03 224.12 6.72
4,600.90
m3 7.17 368.69 2,643.51
m2 73.75 21.76 1,604.80
kg 87.06 4.05 352.59
275.83
m2 73.75 3.74 275.83
707.82
m2 37.53 18.86 707.82
145.72
und 2.00 72.86 145.72
187.78
m2 21.81 8.61 187.78
308.79
und 1.00 308.79 308.79
82,425.37
2,215.40
m2 1,060.00 0.53 561.80
m2 1,060.00 1.56 1,653.60
57,859.04
m3 1,060.00 26.02 27,581.20
m 2,120.00 1.04 2,204.80
m 2,120.00 4.70 9,964.00
m 2,120.00 2.71 5,745.20
m3 848.00 14.58 12,363.84
14,254.12
m 314.00 3.81 1,196.34
m 282.00 4.49 1,266.18
m 385.00 6.96 2,679.60
m 1,139.00 8.00 9,112.00
1,844.40
m 2,120.00 0.87 1,844.40
2,323.14
3.01
m2 2.43 0.54 1.31
m2 2.43 0.70 1.70
56.79
m3 1.46 26.52 38.72
m2 2.43 1.06 2.58
m3 1.46 10.61 15.49
1,137.71
m3 1.51 344.91 520.81
m2 28.35 21.76 616.90
25.52
m2 28.35 0.90 25.52
197.80
m2 12.72 15.55 197.80
218.58
und 3.00 72.86 218.58
247.86
m2 22.95 10.80 247.86
435.87
und 3.00 145.29 435.87
1,451.20
5.35
m2 4.32 0.54 2.33
m2 4.32 0.70 3.02
73.94
m3 1.96 26.52 51.98
m2 2.30 1.06 2.44
m3 1.84 10.61 19.52
73.00
m3 0.09 28.93 2.60
m3 0.25 281.59 70.40
501.54
m3 1.14 317.40 361.84
m2 6.42 21.76 139.70
145.72
und 2.00 72.86 145.72
34.07
m2 4.08 8.35 34.07
617.58
und 2.00 308.79 617.58
2,478.07
5.35
m2 4.32 0.54 2.33
m2 4.32 0.70 3.02
156.71
m3 3.88 26.52 102.90
m2 4.32 1.06 4.58
m3 4.64 10.61 49.23
1,577.00
m3 4.08 317.40 1,294.99
m2 12.96 21.76 282.01
231.16
und 4.00 57.79 231.16
130.93
m2 15.68 8.35 130.93
376.92
und 1.00 136.56 136.56
und 3.00 80.12 240.36
12,126.91
153.72
m2 126.00 0.53 66.78
m2 126.00 0.69 86.94
3,212.27
m3 67.20 26.02 1,748.54
m2 84.00 1.04 87.36
m3 42.20 15.72 663.38
m3 67.20 10.61 712.99
1,131.62
m3 3.36 309.98 1,041.53
m2 4.20 21.45 90.09
7,629.30
und 35.00 217.98 7,629.30
404,172.09
101,490.72
2,787.60
m2 1,380.00 0.54 745.20
m2 1,380.00 1.48 2,042.40
64,175.52
m3 1,104.00 26.02 28,726.08
m 2,760.00 1.06 2,925.60
m 2,760.00 4.70 12,972.00
m 2,760.00 2.71 7,479.60
m3 828.00 14.58 12,072.24
32,706.00
m 2,760.00 11.85 32,706.00
1,821.60
m 2,760.00 0.66 1,821.60
5,730.79
7.03
m2 5.67 0.54 3.06
m2 5.67 0.70 3.97
132.25
m3 3.40 26.52 90.17
m2 5.67 1.06 6.01
m3 3.40 10.61 36.07
2,656.95
m3 3.53 344.91 1,217.53
m2 66.15 21.76 1,439.42
59.54
m2 66.15 0.90 59.54
1,028.63
m2 66.15 15.55 1,028.63
510.02
und 7.00 72.86 510.02
578.34
m2 53.55 10.80 578.34
758.03
und 7.00 108.29 758.03
6,102.71
8.49
m2 6.90 0.54 3.73
m2 6.90 0.69 4.76
209.09
m3 5.61 26.02 145.97
m2 6.90 1.06 7.31
m3 5.26 10.61 55.81
219.00
m3 0.27 28.93 7.81
m3 0.75 281.59 211.19
1,970.73
m3 3.15 335.08 1,055.50
m2 42.06 21.76 915.23
437.16
und 6.00 72.86 437.16
170.34
m2 20.40 8.35 170.34
3,087.90
und 10.00 308.79 3,087.90
6,804.09
9.69
m2 7.81 0.54 4.22
m2 7.81 0.70 5.47
560.84
m3 16.46 26.52 436.52
m2 7.81 2.66 20.77
m3 9.76 10.61 103.55
6.72
m3 0.03 224.12 6.72
4,600.90
m3 7.17 368.69 2,643.51
m2 73.75 21.76 1,604.80
kg 87.06 4.05 352.59
275.83
m2 73.75 3.74 275.83
707.82
m2 37.53 18.86 707.82
145.72
und 2.00 72.86 145.72
187.78
m2 21.81 8.61 187.78
308.79
und 1.00 308.79 308.79
12,257.97
28.57
m2 23.04 0.54 12.44
m2 23.04 0.70 16.13
158.37
m3 5.12 15.55 79.62
m2 10.24 1.06 10.85
m3 6.40 10.61 67.90
228.60
m3 1.02 224.12 228.60
6,678.05
m3 12.02 368.69 4,431.65
kg 280.76 4.05 1,137.08
m2 50.98 21.76 1,109.32
190.67
m2 50.98 3.74 190.67
1,284.94
m2 24.75 18.86 466.79
m2 43.38 18.86 818.15
867.41
und 1.00 72.86 72.86
und 1.00 169.91 169.91
und 1.00 294.82 294.82
und 2.00 164.91 329.82
1,224.59
m2 32.92 17.42 573.47
m2 24.08 27.04 651.12
964.35
und 1.00 208.62 208.62
und 1.00 366.59 366.59
und 1.00 389.14 389.14
632.42
0.44
m2 0.36 0.54 0.19
m2 0.36 0.70 0.25
10.03
m3 0.22 26.52 5.83
m2 0.36 1.06 0.38
m3 0.36 10.61 3.82
274.99
m3 0.48 368.69 176.97
kg 18.83 4.05 76.26
m2 1.00 21.76 21.76
7.48
m2 2.00 3.74 7.48
32.32
m2 2.00 16.16 32.32
307.16
glb 1.00 307.16 307.16
255,122.64
7,484.82
m2 3,514.00 0.54 1,897.56
m2 3,514.00 1.59 5,587.26
193,705.74
m3 3,514.00 26.52 93,191.28
m 7,028.00 1.06 7,449.68
m 7,028.00 4.70 33,031.60
m 7,028.00 2.71 19,045.88
m3 2,811.20 14.58 40,987.30
42,900.78
m 1,027.00 3.81 3,912.87
m 2,687.00 4.49 12,064.63
m 868.00 6.96 6,041.28
m 1,546.00 8.00 12,368.00
m 900.00 9.46 8,514.00
6,114.36
m 7,028.00 0.87 6,114.36
1,593.08
2.00
m2 1.62 0.54 0.87
m2 1.62 0.70 1.13
37.73
m3 0.97 26.52 25.72
m2 1.62 1.06 1.72
m3 0.97 10.61 10.29
759.62
m3 1.01 344.91 348.36
m2 18.90 21.76 411.26
17.01
m2 18.90 0.90 17.01
131.86
m2 8.48 15.55 131.86
145.72
und 2.00 72.86 145.72
165.24
m2 15.30 10.80 165.24
333.90
und 2.00 166.95 333.90
1,451.20
5.35
m2 4.32 0.54 2.33
m2 4.32 0.70 3.02
73.94
m3 1.96 26.52 51.98
m2 2.30 1.06 2.44
m3 1.84 10.61 19.52
73.00
m3 0.09 28.93 2.60
m3 0.25 281.59 70.40
501.54
m3 1.14 317.40 361.84
m2 6.42 21.76 139.70
145.72
und 2.00 72.86 145.72
34.07
m2 4.08 8.35 34.07
617.58
und 2.00 308.79 617.58
1,872.66
4.02
m2 3.24 0.54 1.75
m2 3.24 0.70 2.27
117.52
m3 2.91 26.52 77.17
m2 3.24 1.06 3.43
m3 3.48 10.61 36.92
1,182.75
m3 3.06 317.40 971.24
m2 9.72 21.76 211.51
173.37
und 3.00 57.79 173.37
98.20
m2 11.76 8.35 98.20
296.80
und 1.00 136.56 136.56
und 2.00 80.12 160.24
16,663.17
214.27
m2 172.80 0.54 93.31
m2 172.80 0.70 120.96
4,423.35
m3 92.16 26.52 2,444.08
m2 115.20 1.06 122.11
m3 55.20 15.93 879.34
m3 92.16 10.61 977.82
1,562.51
m3 4.61 311.75 1,437.17
m2 5.76 21.76 125.34
10,463.04
und 48.00 217.98 10,463.04
149,770.57
52,702.79
1,665.49
m2 824.50 0.54 445.23
m2 824.50 1.48 1,220.26
38,342.55
m3 659.60 26.02 17,162.79
m 1,649.00 1.06 1,747.94
m 1,649.00 4.70 7,750.30
m 1,649.00 2.71 4,468.79
m3 494.70 14.58 7,212.73
11,606.41
m 460.00 9.46 4,351.60
m 180.00 8.00 1,440.00
m 520.00 6.96 3,619.20
m 489.00 4.49 2,195.61
1,088.34
m 1,649.00 0.66 1,088.34
1,593.08
2.00
m2 1.62 0.54 0.87
m2 1.62 0.70 1.13
37.73
m3 0.97 26.52 25.72
m2 1.62 1.06 1.72
m3 0.97 10.61 10.29
759.62
m3 1.01 344.91 348.36
m2 18.90 21.76 411.26
17.01
m2 18.90 0.90 17.01
131.86
m2 8.48 15.55 131.86
145.72
und 2.00 72.86 145.72
165.24
m2 15.30 10.80 165.24
333.90
und 2.00 166.95 333.90

1,219.23
2.30
m2 1.85 0.54 1.00
m2 1.85 0.70 1.30
77.18
m3 1.90 26.52 50.39
m2 1.55 1.06 1.64
m3 2.37 10.61 25.15
182.65
m2 2.56 54.70 140.03
m3 0.07 224.12 15.69
m3 0.04 265.13 10.61
m2 0.75 21.76 16.32
635.66
m3 0.87 351.00 305.37
m2 10.16 21.76 221.08
kg 27.10 4.03 109.21
0.78
m2 0.87 0.90 0.78
97.03
m2 6.24 15.55 97.03
72.86
und 1.00 72.86 72.86
61.78
m2 5.72 10.80 61.78
88.99
und 1.00 88.99 88.99
90,693.31
2,704.53
m2 1,287.87 0.54 695.45
m2 1,287.87 1.56 2,009.08
70,296.93
m3 1,287.87 26.02 33,510.38
m 2,575.73 1.04 2,678.76
m 2,575.73 4.70 12,105.93
m 2,575.73 2.71 6,980.23
m3 1,030.29 14.58 15,021.63
9,928.61
m 2,406.50 3.81 9,168.77
m 169.23 4.49 759.84
2,240.89
m 2,575.73 0.87 2,240.89
1,593.08
2.00
m2 1.62 0.54 0.87
m2 1.62 0.70 1.13
37.73
m3 0.97 26.52 25.72
m2 1.62 1.06 1.72
m3 0.97 10.61 10.29
759.62
m3 1.01 344.91 348.36
m2 18.90 21.76 411.26
17.01
m2 18.90 0.90 17.01
131.86
m2 8.48 15.55 131.86
145.72
und 2.00 72.86 145.72
165.24
m2 15.30 10.80 165.24
333.90
und 2.00 166.95 333.90
1,451.20
5.35
m2 4.32 0.54 2.33
m2 4.32 0.70 3.02
73.94
m3 1.96 26.52 51.98
m2 2.30 1.06 2.44
m3 1.84 10.61 19.52
73.00
m3 0.09 28.93 2.60
m3 0.25 281.59 70.40
501.54
m3 1.14 317.40 361.84
m2 6.42 21.76 139.70
145.72
und 2.00 72.86 145.72
34.07
m2 4.08 8.35 34.07
617.58
und 2.00 308.79 617.58
2,478.07
5.35
m2 4.32 0.54 2.33
m2 4.32 0.70 3.02
156.71
m3 3.88 26.52 102.90
m2 4.32 1.06 4.58
m3 4.64 10.61 49.23
1,577.00
m3 4.08 317.40 1,294.99
m2 12.96 21.76 282.01
231.16
und 4.00 57.79 231.16
130.93
m2 15.68 8.35 130.93
376.92
und 1.00 136.56 136.56
und 3.00 80.12 240.36
3,562.16
44.64
m2 36.00 0.54 19.44
m2 36.00 0.70 25.20
1,012.33
m3 19.20 26.52 509.18
m2 24.00 1.06 25.44
m3 17.20 15.93 274.00
m3 19.20 10.61 203.71
325.39
m3 0.96 311.75 299.28
m2 1.20 21.76 26.11
2,179.80
und 10.00 217.98 2,179.80
338,348.71
86,745.59
glb 1.00 15,000.00 15,000.00
glb 1.00 71,745.59 71,745.59
56,431.40
1,044.79
m2 517.22 1.48 765.49
m2 517.22 0.54 279.30
27,756.99
m3 517.22 26.52 13,716.67
m 1,034.43 1.06 1,096.50
m 1,034.43 4.70 4,861.82
m 1,034.43 2.71 2,803.31
m3 362.05 14.58 5,278.69
26,946.90
m 1,034.43 26.05 26,946.90
682.72
m 1,034.43 0.66 682.72
26,619.88
2,531.53
m2 210.61 1.48 311.70
m2 210.61 0.54 113.73
m 210.61 10.00 2,106.10
12,837.83
m3 210.61 26.52 5,585.38
m 421.21 1.06 446.48
m 421.21 4.70 1,979.69
m 421.21 2.71 1,141.48
m3 252.73 14.58 3,684.80
10,972.52
m 421.21 26.05 10,972.52
278.00
m 421.21 0.66 278.00
113,344.39
41,532.92
34.91
m2 28.15 0.54 15.20
m2 28.15 0.70 19.71
3,749.98
m3 32.37 35.36 1,144.60
m2 28.15 1.06 29.84
m2 80.93 26.52 2,146.26
m3 40.46 10.61 429.28
9,315.71
m3 3.27 225.68 737.97
m3 1.27 149.93 190.41
m3 19.79 334.83 6,626.29
m3 80.93 21.76 1,761.04
26,040.26
m3 28.15 368.69 10,378.62
m2 540.85 21.76 11,768.90
kg 34.75 4.05 140.74
und 14.00 268.00 3,752.00
2,392.06
m2 115.67 20.68 2,392.06
47,090.48
37.40
m2 30.16 0.54 16.29
m2 30.16 0.70 21.11
7,830.56
m3 67.86 35.36 2,399.53
m2 30.16 1.06 31.97
m2 169.65 26.52 4,499.12
m3 84.82 10.61 899.94
12,956.17
m3 3.51 225.68 792.14
m3 1.36 149.93 203.90
m3 35.72 334.83 11,960.13
m2 169.65 21.76 3,691.58
18,296.70
m3 30.16 368.69 11,119.69
m2 37.23 21.76 810.12
kg 579.48 4.05 2,346.89
und 15.00 268.00 4,020.00
4,278.07
m2 206.87 20.68 4,278.07
24,720.99
9.97
m2 8.04 0.54 4.34
m2 8.04 0.70 5.63
5,091.70
m3 44.23 35.36 1,563.97
m2 8.04 1.06 8.52
m2 110.58 26.52 2,932.58
m3 55.29 10.61 586.63
9,688.11
m3 0.93 225.68 209.88
m3 0.36 149.93 53.97
m3 20.96 334.83 7,018.04
m2 110.58 21.76 2,406.22
7,439.06
m3 8.04 368.69 2,964.27
m2 154.53 21.76 3,362.57
kg 9.93 4.05 40.22
und 4.00 268.00 1,072.00
2,492.15
m2 120.51 20.68 2,492.15
55,207.45
1,354.32
m2 237.60 4.24 1,007.42
m2 237.60 1.46 346.90
21,718.75
m3 237.60 26.52 6,301.15
m2 528.00 2.66 1,404.48
m3 528.00 15.93 8,411.04
m3 528.00 10.61 5,602.08
2,892.86
m3 8.45 320.59 2,708.99
m2 8.45 21.76 183.87
29,241.52
und 88.00 332.29 29,241.52
1,222,637.29
493,758.08
290,104.48
407.78
m2 328.86 0.54 177.58
m2 328.86 0.70 230.20
31,050.00
3,236.60
m3 81.40 26.52 2,158.73
m3 101.59 10.61 1,077.87
27,813.40
m3 71.69 217.86 15,618.38
m2 198.07 28.85 5,714.32
m3 12.38 293.49 3,633.41
m3 37.80 23.40 884.52
m 94.50 20.77 1,962.77
25,241.63
4,654.10
m3 113.95 26.52 3,021.95
m3 142.44 10.61 1,511.29
m2 137.34 0.88 120.86
20,587.53
m3 207.14 23.40 4,847.08
kg 974.50 4.05 3,946.73
m3 33.79 349.03 11,793.72
55,074.49
10,174.94
m2 98.91 21.17 2,093.92
kg 644.87 4.05 2,611.72
m3 15.67 349.03 5,469.30
33,935.64
m2 688.21 49.31 33,935.64
8,672.39
m2 295.63 17.98 5,315.43
m2 120.02 27.97 3,356.96
2,291.52
m2 97.97 23.39 2,291.52
11,478.72
2,166.90
m 22.47 12.30 276.38
m 53.03 35.65 1,890.52
9,311.82
m2 283.12 32.89 9,311.82
21,464.57
16,478.75
m2 98.28 147.52 14,498.27
m2 47.38 41.80 1,980.48
4,985.82
und 189.00 15.98 3,020.22
und 63.00 31.20 1,965.60
16,677.63
72.78
m3 1.80 26.52 47.74
m3 2.36 10.61 25.04
6,869.39
m3 1.80 217.86 392.15
m2 260.13 24.90 6,477.24
5,698.43
m3 4.94 311.75 1,540.05
kg 345.40 4.05 1,398.87
m2 130.35 21.17 2,759.51
1,947.75
m2 39.50 49.31 1,947.75
2,089.28
m2 116.20 17.98 2,089.28
128,709.66
74,334.33
und 63.00 226.19 14,249.97
und 63.00 170.09 10,715.67
und 63.00 43.22 2,722.86
und 378.00 17.80 6,728.40
und 378.00 17.80 6,728.40
und 63.00 10.40 655.20
und 252.00 17.80 4,485.60
pto 63.00 109.61 6,905.43
und 126.00 106.57 13,427.82
und 189.00 40.82 7,714.98
54,375.33
pto 252.00 88.44 22,286.88
m 420.84 21.03 8,850.27
und 189.00 9.26 1,750.14
und 252.00 9.26 2,333.52
und 126.00 7.54 950.04
und 126.00 10.47 1,319.22
und 126.00 8.79 1,107.54
und 63.00 62.61 3,944.43
und 63.00 59.11 3,723.93
und 126.00 64.36 8,109.36
203,653.60
1,888.94
m2 1,523.34 0.54 822.60
m2 1,523.34 0.70 1,066.34
23,980.60
17,739.19
1,461.87
m3 35.91 26.52 952.33
m2 37.80 0.88 33.26
m3 44.89 10.61 476.28
10,266.12
m2 143.64 23.40 3,361.18
kg 87.32 4.05 353.65
m3 18.77 349.03 6,551.29
150.82
m2 167.58 0.90 150.82
3,465.55
m2 167.58 20.68 3,465.55
1,084.43
m2 57.96 18.71 1,084.43
1,310.40
und 126.00 10.40 1,310.40
6,241.41
m3 89.11 26.52 2,363.20
m3 44.55 50.30 2,240.87
m 278.46 5.88 1,637.34
150,246.39
4,497.87
274.94
m3 6.62 26.52 175.56
m2 13.23 0.88 11.64
m3 8.27 10.61 87.74
2,085.91
m3 3.34 293.49 980.26
m3 47.25 23.40 1,105.65
859.61
m3 19.22 23.40 449.75
kg 44.32 4.05 179.50
m3 0.66 349.03 230.36
38.28
m2 42.53 0.90 38.28
879.52
m2 42.53 20.68 879.52
359.61
m2 19.22 18.71 359.61
107,725.27
9,635.34
m3 230.20 26.52 6,104.90
m3 37.80 12.63 477.41
m3 287.75 10.61 3,053.03
3,086.56
m2 132.30 23.33 3,086.56
95,003.37

und 63.00 1,507.99 95,003.37

21,700.64
1,159.05
m3 28.35 26.52 751.84
m2 35.44 0.88 31.19
m3 35.44 10.61 376.02
6,568.85
m3 13.24 293.49 3,885.81
m3 114.66 23.40 2,683.04
1,403.26
m2 23.47 23.40 549.20
kg 58.34 4.05 236.28
m3 1.77 349.03 617.78
103.19
m2 114.66 0.90 103.19
2,371.17
m2 114.66 20.68 2,371.17
10,095.12
und 126.00 17.75 2,236.50
und 126.00 18.08 2,278.08
und 63.00 88.58 5,580.54
10,833.21
m3 114.51 26.52 3,036.81
m3 57.25 50.30 2,879.68
m 357.84 13.74 4,916.72
5,489.40
452.70
m3 9.45 26.52 250.61
m2 18.90 0.88 16.63
m3 17.48 10.61 185.46
2,303.49
m3 3.78 293.49 1,109.39
m3 51.03 23.40 1,194.10
1,172.28
m3 25.83 23.40 604.42
kg 58.34 4.05 236.28
m3 0.95 349.03 331.58
45.93
m2 51.03 0.90 45.93
1,055.30
m2 51.03 20.68 1,055.30
459.70
m2 24.57 18.71 459.70
27,537.67
6,142.58
m3 142.13 26.52 3,769.29
m2 177.66 0.88 156.34
m3 71.06 12.63 897.49
m3 124.36 10.61 1,319.46
6,268.52
m3 26.65 108.81 2,899.79
m3 26.65 108.81 2,899.79
m3 40.08 11.70 468.94
15,126.57
m2 177.66 17.06 3,030.88
m 296.10 40.85 12,095.69
274,313.71
161,170.22
226.55
m2 182.70 0.54 98.66
m2 182.70 0.70 127.89
17,251.11
1,798.06
m3 45.22 26.52 1,199.23
m3 56.44 10.61 598.83
15,453.05
m3 39.83 217.86 8,677.36
m2 110.04 28.85 3,174.65
m3 6.88 293.49 2,019.21
m3 21.00 23.40 491.40
m 52.50 20.77 1,090.43
14,022.59
2,585.80
m3 63.31 26.52 1,678.98
m3 79.14 10.61 839.68
m2 76.30 0.88 67.14
11,436.79
m3 115.08 23.40 2,692.87
kg 541.39 4.05 2,192.63
m3 18.77 349.03 6,551.29
30,598.68
5,654.29
m2 54.95 21.17 1,163.29
kg 358.26 4.05 1,450.95
m3 8.71 349.03 3,040.05
18,853.19
m2 382.34 49.31 18,853.19
4,818.08
m2 164.24 17.98 2,953.04
m2 66.68 27.97 1,865.04
1,273.12
m2 54.43 23.39 1,273.12
6,377.02
1,203.75
m 12.48 12.30 153.50
m 29.46 35.65 1,050.25
5,173.27
m2 157.29 32.89 5,173.27
11,924.67
9,154.77
m2 54.60 147.52 8,054.59
m2 26.32 41.80 1,100.18
2,769.90
und 105.00 15.98 1,677.90
und 35.00 31.20 1,092.00
9,264.24
40.42
m3 1.00 26.52 26.52
m3 1.31 10.61 13.90
3,816.41
m3 1.00 217.86 217.86
m2 144.52 24.90 3,598.55
3,164.27
m3 2.74 311.75 854.20
kg 191.89 4.05 777.15
m2 72.41 21.17 1,532.92
1,082.35
m2 21.95 49.31 1,082.35
1,160.79
m2 64.56 17.98 1,160.79
71,505.36
41,296.85
und 35.00 226.19 7,916.65
und 35.00 170.09 5,953.15
und 35.00 43.22 1,512.70
und 210.00 17.80 3,738.00
und 210.00 17.80 3,738.00
und 35.00 10.40 364.00
und 140.00 17.80 2,492.00
pto 35.00 109.61 3,836.35
und 70.00 106.57 7,459.90
und 105.00 40.82 4,286.10
30,208.51
pto 140.00 88.44 12,381.60
m 233.80 21.03 4,916.81
und 105.00 9.26 972.30
und 140.00 9.26 1,296.40
und 70.00 7.54 527.80
und 70.00 10.47 732.90
und 70.00 8.79 615.30
und 35.00 62.61 2,191.35
und 35.00 59.11 2,068.85
und 70.00 64.36 4,505.20
113,143.49
1,049.41
m2 846.30 0.54 457.00
m2 846.30 0.70 592.41
13,323.20
9,855.89
812.16
m3 19.95 26.52 529.07
m2 21.00 0.88 18.48
m3 24.94 10.61 264.61
5,704.17
m3 79.80 23.40 1,867.32
kg 48.51 4.05 196.47
m3 10.43 349.03 3,640.38
83.79
m2 93.10 0.90 83.79
1,925.31
m2 93.10 20.68 1,925.31
602.46
m2 32.20 18.71 602.46
728.00
und 70.00 10.40 728.00
3,467.31
m3 49.50 26.52 1,312.74
m3 24.75 50.30 1,244.93
m 154.70 5.88 909.64
83,471.16
2,501.42
152.76
m3 3.68 26.52 97.59
m2 7.35 0.88 6.47
m3 4.59 10.61 48.70
1,160.14
m3 1.86 293.49 545.89
m3 26.25 23.40 614.25
478.76
m3 10.68 23.40 249.91
kg 24.62 4.05 99.71
m3 0.37 349.03 129.14
21.27
m2 23.63 0.90 21.27
488.67
m2 23.63 20.68 488.67
199.82
m2 10.68 18.71 199.82
59,847.39
5,352.98
m3 127.89 26.52 3,391.64
m3 21.00 12.63 265.23
m3 159.86 10.61 1,696.11
1,714.76
m2 73.50 23.33 1,714.76
52,779.65

und 35.00 1,507.99 52,779.65

12,053.16
643.93
m3 15.75 26.52 417.69
m2 19.69 0.88 17.33
m3 19.69 10.61 208.91
3,647.73
m3 7.35 293.49 2,157.15
m3 63.70 23.40 1,490.58
778.45
m3 13.04 23.40 305.14
kg 32.41 4.05 131.26
m3 0.98 349.03 342.05
57.33
m2 63.70 0.90 57.33
1,317.32
m2 63.70 20.68 1,317.32
5,608.40
und 70.00 17.75 1,242.50
und 70.00 18.08 1,265.60
und 35.00 88.58 3,100.30
6,018.75
m3 63.62 26.52 1,687.20
m3 31.81 50.30 1,600.04
m 198.80 13.74 2,731.51
3,050.44
251.49
m3 5.25 26.52 139.23
m2 10.50 0.88 9.24
m3 9.71 10.61 103.02
1,279.72
m3 2.10 293.49 616.33
m3 28.35 23.40 663.39
652.04
m3 14.35 23.40 335.79
kg 32.41 4.05 131.26
m3 0.53 349.03 184.99
25.52
m2 28.35 0.90 25.52
586.28
m2 28.35 20.68 586.28
255.39
m2 13.65 18.71 255.39
15,299.72
3,412.55
m3 78.96 26.52 2,094.02
m2 98.70 0.88 86.86
m3 39.48 12.63 498.63
m3 69.09 10.61 733.04
3,483.52
m3 14.81 108.81 1,611.48
m3 14.81 108.81 1,611.48
m3 22.27 11.70 260.56
8,403.65
m2 98.70 17.06 1,683.82
m 164.50 40.85 6,719.83
376,188.54
221,028.04
310.69
m2 250.56 0.54 135.30
m2 250.56 0.70 175.39
23,656.21
2,465.98
m3 62.02 26.52 1,644.77
m3 77.40 10.61 821.21
21,190.23
m3 54.62 217.86 11,899.51
m2 150.91 28.85 4,353.75
m3 9.43 293.49 2,767.61
m3 28.80 23.40 673.92
m 72.00 20.77 1,495.44
19,230.11
3,546.05
m3 86.82 26.52 2,302.47
m3 108.53 10.61 1,151.50
m2 104.64 0.88 92.08
15,684.06
m3 157.82 23.40 3,692.99
kg 742.48 4.05 3,007.04
m3 25.74 349.03 8,984.03
41,961.61
7,752.68
m2 75.36 21.17 1,595.37
kg 491.33 4.05 1,989.89
m3 11.94 349.03 4,167.42
25,855.70
m2 524.35 49.31 25,855.70
6,607.40
m2 225.24 17.98 4,049.82
m2 91.44 27.97 2,557.58
1,745.83
m2 74.64 23.39 1,745.83
8,745.54
1,650.84
m 17.12 12.30 210.58
m 40.40 35.65 1,440.26
7,094.70
m2 215.71 32.89 7,094.70
16,354.00
12,555.28
m2 74.88 147.52 11,046.30
m2 36.10 41.80 1,508.98
3,798.72
und 144.00 15.98 2,301.12
und 48.00 31.20 1,497.60
12,705.38
55.43
m3 1.37 26.52 36.33
m3 1.80 10.61 19.10
5,233.40
m3 1.37 217.86 298.47
m2 198.19 24.90 4,934.93
4,340.37
m3 3.76 311.75 1,172.18
kg 263.16 4.05 1,065.80
m2 99.31 21.17 2,102.39
1,484.23
m2 30.10 49.31 1,484.23
1,591.95
m2 88.54 17.98 1,591.95
98,064.50
56,635.68
und 48.00 226.19 10,857.12
und 48.00 170.09 8,164.32
und 48.00 43.22 2,074.56
und 288.00 17.80 5,126.40
und 288.00 17.80 5,126.40
und 48.00 10.40 499.20
und 192.00 17.80 3,417.60
pto 48.00 109.61 5,261.28
und 96.00 106.57 10,230.72
und 144.00 40.82 5,878.08
41,428.82
pto 192.00 88.44 16,980.48
m 320.64 21.03 6,743.06
und 144.00 9.26 1,333.44
und 192.00 9.26 1,777.92
und 96.00 7.54 723.84
und 96.00 10.47 1,005.12
und 96.00 8.79 843.84
und 48.00 62.61 3,005.28
und 48.00 59.11 2,837.28
und 96.00 64.36 6,178.56
155,160.50
1,439.20
m2 1,160.64 0.54 626.75
m2 1,160.64 0.70 812.45
18,270.86
13,515.23
1,113.79
m3 27.36 26.52 725.59
m2 28.80 0.88 25.34
m3 34.20 10.61 362.86
7,821.48
m3 109.44 23.40 2,560.90
kg 66.53 4.05 269.45
m3 14.30 349.03 4,991.13
114.91
m2 127.68 0.90 114.91
2,640.42
m2 127.68 20.68 2,640.42
826.23
m2 44.16 18.71 826.23
998.40
und 96.00 10.40 998.40
4,755.63
m3 67.89 26.52 1,800.44
m3 33.95 50.30 1,707.69
m 212.16 5.88 1,247.50
114,470.38
3,424.20
209.37
m3 5.04 26.52 133.66
m2 10.08 0.88 8.87
m3 6.30 10.61 66.84
1,587.86
m3 2.54 293.49 745.46
m3 36.00 23.40 842.40
653.87
m3 14.64 23.40 342.58
kg 33.77 4.05 136.77
m3 0.50 349.03 174.52
29.16
m2 32.40 0.90 29.16
670.03
m2 32.40 20.68 670.03
273.91
m2 14.64 18.71 273.91
82,076.40
7,341.22
m3 175.39 26.52 4,651.34
m3 28.80 12.63 363.74
m3 219.24 10.61 2,326.14
2,351.66
m2 100.80 23.33 2,351.66
72,383.52

und 48.00 1,507.99 72,383.52

16,534.93
883.06
m3 21.60 26.52 572.83
m2 27.00 0.88 23.76
m3 27.00 10.61 286.47
5,005.53
m3 10.09 293.49 2,961.31
m3 87.36 23.40 2,044.22
1,069.60
m3 17.88 23.40 418.39
kg 44.45 4.05 180.02
m3 1.35 349.03 471.19
78.62
m2 87.36 0.90 78.62
1,806.60
m2 87.36 20.68 1,806.60
7,691.52
und 96.00 17.75 1,704.00
und 96.00 18.08 1,735.68
und 48.00 88.58 4,251.84
8,253.76
m3 87.24 26.52 2,313.60
m3 43.62 50.30 2,194.09
m 272.64 13.74 3,746.07
4,181.09
344.94
m3 7.20 26.52 190.94
m2 14.40 0.88 12.67
m3 13.32 10.61 141.33
1,755.04
m3 2.88 293.49 845.25
m3 38.88 23.40 909.79
891.83
m3 19.68 23.40 460.51
kg 44.45 4.05 180.02
m3 0.72 349.03 251.30
34.99
m2 38.88 0.90 34.99
804.04
m2 38.88 20.68 804.04
350.25
m2 18.72 18.71 350.25
20,980.06
4,680.06
m3 108.29 26.52 2,871.85
m2 135.36 0.88 119.12
m3 54.14 12.63 683.79
m3 94.75 10.61 1,005.30
4,775.00
m3 20.30 108.81 2,208.84
m3 20.30 108.81 2,208.84
m3 30.54 11.70 357.32
11,525.00
m2 135.36 17.06 2,309.24
m 225.60 40.85 9,215.76
78,376.96
46,049.83
64.73
m2 52.20 0.54 28.19
m2 52.20 0.70 36.54
4,930.20
513.78
m3 12.92 26.52 342.64
m3 16.13 10.61 171.14
4,416.42
m3 11.38 217.86 2,479.25
m2 31.44 28.85 907.04
m3 1.97 293.49 578.18
m3 6.00 23.40 140.40
m 15.00 20.77 311.55
4,005.46
738.82
m3 18.09 26.52 479.75
m3 22.61 10.61 239.89
m2 21.80 0.88 19.18
3,266.64
m3 32.88 23.40 769.39
kg 154.68 4.05 626.45
m3 5.36 349.03 1,870.80
8,742.97
1,616.01
m2 15.70 21.17 332.37
kg 102.36 4.05 414.56
m3 2.49 349.03 869.08
5,386.62
m2 109.24 49.31 5,386.62
1,376.63
m2 46.93 17.98 843.80
m2 19.05 27.97 532.83
363.71
m2 15.55 23.39 363.71
1,822.16
344.08
m 3.57 12.30 43.91
m 8.42 35.65 300.17
1,478.08
m2 44.94 32.89 1,478.08
3,407.05
2,615.65
m2 15.60 147.52 2,301.31
m2 7.52 41.80 314.34
791.40
und 30.00 15.98 479.40
und 10.00 31.20 312.00
2,647.16
11.72
m3 0.29 26.52 7.69
m3 0.38 10.61 4.03
1,091.30
m3 0.29 217.86 63.18
m2 41.29 24.90 1,028.12
903.24
m3 0.78 311.75 243.17
kg 54.83 4.05 222.06
m2 20.69 21.17 438.01
309.17
m2 6.27 49.31 309.17
331.73
m2 18.45 17.98 331.73
20,430.10
11,799.10
und 10.00 226.19 2,261.90
und 10.00 170.09 1,700.90
und 10.00 43.22 432.20
und 60.00 17.80 1,068.00
und 60.00 17.80 1,068.00
und 10.00 10.40 104.00
und 40.00 17.80 712.00
pto 10.00 109.61 1,096.10
und 20.00 106.57 2,131.40
und 30.00 40.82 1,224.60
8,631.00
pto 40.00 88.44 3,537.60
m 66.80 21.03 1,404.80
und 30.00 9.26 277.80
und 40.00 9.26 370.40
und 20.00 7.54 150.80
und 20.00 10.47 209.40
und 20.00 8.79 175.80
und 10.00 62.61 626.10
und 10.00 59.11 591.10
und 20.00 64.36 1,287.20
32,327.13
299.83
m2 241.80 0.54 130.57
m2 241.80 0.70 169.26
3,806.52
2,816.01
232.09
m3 5.70 26.52 151.16
m2 6.00 0.88 5.28
m3 7.13 10.61 75.65
1,629.76
m3 22.80 23.40 533.52
kg 13.86 4.05 56.13
m3 2.98 349.03 1,040.11
23.94
m2 26.60 0.90 23.94
550.09
m2 26.60 20.68 550.09
172.13
m2 9.20 18.71 172.13
208.00
und 20.00 10.40 208.00
990.51
m3 14.14 26.52 374.99
m3 7.07 50.30 355.62
m 44.20 5.88 259.90
23,849.77
715.66
43.60
m3 1.05 26.52 27.85
m2 2.10 0.88 1.85
m3 1.31 10.61 13.90
331.05
m3 0.53 293.49 155.55
m3 7.50 23.40 175.50
138.27
m3 3.05 23.40 71.37
kg 7.04 4.05 28.51
m3 0.11 349.03 38.39
6.08
m2 6.75 0.90 6.08
139.59
m2 6.75 20.68 139.59
57.07
m2 3.05 18.71 57.07
17,099.31
1,529.48
m3 36.54 26.52 969.04
m3 6.00 12.63 75.78
m3 45.68 10.61 484.66
489.93
m2 21.00 23.33 489.93
15,079.90

und 10.00 1,507.99 15,079.90

3,443.90
184.02
m3 4.50 26.52 119.34
m2 5.63 0.88 4.95
m3 5.63 10.61 59.73
1,042.21
m3 2.10 293.49 616.33
m3 18.20 23.40 425.88
222.51
m3 3.73 23.40 87.28
kg 9.26 4.05 37.50
m3 0.28 349.03 97.73
16.38
m2 18.20 0.90 16.38
376.38
m2 18.20 20.68 376.38
1,602.40
und 20.00 17.75 355.00
und 20.00 18.08 361.60
und 10.00 88.58 885.80
1,719.79
m3 18.18 26.52 482.13
m3 9.09 50.30 457.23
m 56.80 13.74 780.43
871.11
71.92
m3 1.50 26.52 39.78
m2 3.00 0.88 2.64
m3 2.78 10.61 29.50
365.63
m3 0.60 293.49 176.09
m3 8.10 23.40 189.54
185.79
m3 4.10 23.40 95.94
kg 9.26 4.05 37.50
m3 0.15 349.03 52.35
7.29
m2 8.10 0.90 7.29
167.51
m2 8.10 20.68 167.51
72.97
m2 3.90 18.71 72.97
4,371.01
975.02
m2 28.20 0.88 24.82
m3 22.56 26.52 598.29
m3 11.28 12.63 142.47
m3 19.74 10.61 209.44
994.95
m3 4.23 108.81 460.27
m3 4.23 108.81 460.27
m3 6.36 11.70 74.41
2,401.04
m2 28.20 17.06 481.09
m 47.00 40.85 1,919.95
162,771.12
4,211.77
6.61
m2 5.33 0.54 2.88
m2 5.33 0.70 3.73
132.67
m3 2.72 35.36 96.18
m2 4.54 1.06 4.81
m3 0.53 15.93 8.44
m3 2.19 10.61 23.24
106.07
m3 0.47 225.68 106.07
1,634.21
m3 2.21 359.85 795.27
kg 95.82 4.05 388.07
m2 20.72 21.76 450.87
41.00
m2 45.56 0.90 41.00
367.39
m2 9.12 18.86 172.00
m2 10.36 18.86 195.39
1,923.82
und 1.00 499.82 499.82
und 2.00 712.00 1,424.00
3,038.82
1.44
m2 1.16 0.54 0.63
m2 1.16 0.70 0.81
58.41
m3 1.17 35.36 41.37
m2 1.16 1.06 1.23
m3 0.10 15.93 1.59
m3 1.34 10.61 14.22
106.07
m3 0.47 225.68 106.07
655.79
m3 0.47 359.85 169.13
kg 92.60 4.05 375.03
m2 5.13 21.76 111.63
4.62
m2 5.13 0.90 4.62
48.85
m2 2.59 18.86 48.85
2,163.64
und 2.00 369.82 739.64
und 2.00 712.00 1,424.00
30,850.36
45.14
m2 36.40 0.54 19.66
m2 36.40 0.70 25.48
4,554.25
m3 96.46 35.36 3,410.83
m2 36.40 1.06 38.58
m3 15.30 15.93 243.73
m3 81.16 10.61 861.11
929.36
m2 36.40 23.36 850.30
und 2.00 39.53 79.06
21,821.93
m3 29.50 359.85 10,615.58
kg 1,566.28 4.05 6,343.43
m2 223.48 21.76 4,862.92
2,390.69
m2 126.76 18.86 2,390.69
1,108.99
m 5.00 36.55 182.75
m 5.00 26.05 130.25
und 1.00 101.29 101.29
und 1.00 86.86 86.86
und 3.00 54.86 164.58
und 2.00 221.63 443.26
16,949.15
53.05
m2 42.78 0.54 23.10
m2 42.78 0.70 29.95
6,889.32
m3 115.71 35.36 4,091.51
m2 44.85 1.06 47.54
m3 23.76 15.93 378.50
m3 23.76 56.36 1,339.11
m3 9.15 62.68 573.52
m3 1.83 64.93 118.82
m3 3.97 64.93 257.77
m3 7.78 10.61 82.55
5,931.87
m3 8.10 359.85 2,914.79
kg 500.17 4.05 2,025.69
m2 45.56 21.76 991.39
208.40
m2 12.60 12.14 152.96
m2 2.93 18.92 55.44
2,657.98
m2 58.43 45.49 2,657.98
1,208.53
m 12.78 51.67 660.34
m 7.20 16.20 116.64
m2 35.00 12.33 431.55
7,344.86
4.16
m2 3.36 0.54 1.81
m2 3.36 0.70 2.35
194.38
m3 3.32 35.36 117.40
m2 3.36 1.06 3.56
m3 6.92 10.61 73.42
1,118.62
m2 12.66 23.40 296.24
kg 92.60 4.05 375.03
m3 1.25 357.88 447.35
11.39
m2 12.66 0.90 11.39
170.40
m2 8.24 20.68 170.40
5,381.46
und 3.00 369.82 1,109.46
und 6.00 712.00 4,272.00
464.45
m 35.00 13.27 464.45
82,208.80
100.53
m2 137.41 0.54 74.20
m2 37.61 0.70 26.33
30,545.92
m3 625.23 35.36 22,108.13
m2 137.41 1.06 145.65
m3 781.54 10.61 8,292.14
3,534.25
m3 20.94 168.78 3,534.25
15,619.23
m3 20.94 320.59 6,713.15
kg 1,378.44 4.05 5,582.68
m2 152.73 21.76 3,323.40
16,984.54
m2 333.75 50.89 16,984.54
13,992.97
m3 128.60 108.81 13,992.97
1,431.36
m 36.00 36.82 1,325.52
m 18.00 5.88 105.84
15,515.86
218.16
m2 108.00 0.54 58.32
m2 108.00 1.48 159.84
8,670.10
m3 216.00 26.52 5,728.32
m 180.00 1.06 190.80
m 180.00 4.70 846.00
m 180.00 2.71 487.80
m3 97.20 14.58 1,417.18
6,627.60
m 180.00 36.82 6,627.60
2,651.50
74.40
m2 60.00 0.54 32.40
m2 60.00 0.70 42.00
108.52
m3 2.98 26.52 79.03
m2 15.80 1.06 16.75
m3 0.60 15.93 9.56
m3 0.30 10.61 3.18
794.74
m3 2.98 266.69 794.74
1,673.84
m 120.00 12.57 1,508.40
und 1.00 95.75 95.75
m2 3.50 19.91 69.69
30,000.00
glb 1.00 30,000.00 30,000.00
64,429.67
glb 1.00 64,429.67 64,429.67