Académique Documents
Professionnel Documents
Culture Documents
ON
SUBMITTED BY:-
R.S. MISHRA
(Head OF Department)
CIVIL ENGINEERING
DECLARATION
We hereby declare that the project entitled “MULTI-STOREY RESIDENTIAL BUILDING
(G+3)” Submitted by us in the partial fulfillment of the requirements for the award of the degree
of bachelor of technology (civil engineering) from Abdul kalam technical university is record
by our owns work carried under the supervision and guidance of Mr. BALRAM YADAV
(Project Guide).
To the best of my knowledge this project has not been submitted to Abdul kalam Technical
university or any institute for the award of any degree.
Title Page I
Table of content II - IV
Certificate V
Preface VI
Acknowledgements VII
Location of site VIII
CHAPTER – 1 SPECIFICATION 7 - 18
1.1 Earth work in excavation of foundation of walls and column concrete block in
foundation 8
1.2 First class brick in 1:6 cement, sand mortar in foundation up to plinth 8-9
1.3 Cement concrete block in foundation 9” thick having ratio of 1:5:10 9 - 10
1.4 Earth work in filling to raise the level of ground 10-11
1.5Laying of D.P.C. 4 cm thick with 1:2:4 cement concrete with
2% damp proofing powder 11-12
1.6 First class brick work in 1:6cement, sand mortar in superstructure 12-13
1.7 R.C.C. work in slab, beams and lintel in 1:2:4cement, concrete mix
(M-20) grade 14
1.8 Mild steel frames for doors and windows having 40 x 40 x 6 mm angle section 15-16
1.9 Teak wood works in doors and windows shutters 16-17
1.10 Plastering on ceiling with 1:4 cement, sand mortar 17
1.11 Plastering on walls with 1:5 cement, sand mortar 18
1.12 Mosaic flooring over base concrete 18
1.13 Glazed tile work in kitchen and toilet up to door level 19
1.14 Roof terracing work with tiles said over mud phaska 19
1.15 White and colour washing on walls 19
CHAPTER – 2 DESIGNING 20 - 27
2.1 Design of slab for residential building
2.2 Design of beam for residential building 20 - 40
2.3 Design of column for residential building 41 – 55
2.4 Design of footing for residential building 56-59
2.5 Design of stair case for residential building 60-- 66
CHAPTER - 3 ESTIMATING 71 - 73
4.1 Estimates for item of ground floor 71-72
4.2 Estimate fir item of first floor 73
CHAPTER – 4 ABSTRACT OF COST 74-78
7.1 Abstract of cost of the G+3 residential building
SPECIFICATION
SLAB = 1
From 23⁚2⁚1
l/d = 26*M.F
Let % of steel = 0.4%
The M.F = 1.5
1.692*1000/d = 26*1.5
d = 43.98 ≈ 50mm
The total depth D = 50+ⱷ/2 +20
= 75mm
Effective span
Width support = 230mm
Clear span = 1692-230
= 1462mm
1/12*1462 = 121.83 < 230
ley= 2m
lex= 1.692m
LOAD CALCULATION
Self wt. of slab = 25*75*10-3 = 1.875KN/m2
Floor finishing = 1*1 = 1 KN/m
Live load = 1*4 = 4KN/m
Total load = 6.875KN/m2
Factored load = 1.5*6.875
= 10.3 KN/m2
Design moment
MX = αxwlx2
MY = αywlx2
ley/lex = 1.18
αx negative = (0.048-0.043)/(1.2-1.1)*(1.18-1.1)+0.043
= 0.047
αy positive = (0.036-0.032)/(1.2-1.1)*(1.18-1.1)+0.032
= 0.0352
⸫ αy negative = 0.037
αy positive = 0.028
Moment calculation
+Mx = 0.0352*10.31*1.6922
= 1.03KNm
-Mx = 0.047*10.31*1.6922
= 1.38KNm
+My = 0.028*10.31*1.6922
= 0.826KNm
-My = 0.037*10.31*1.6922
= 1.092KNm
DESIGN OF SLAB 2
From 23⁚2⁚1
l/d = 26*M.F
Let Pt. = 0.4%
The M.F = 1.5
1.81*1000/d = 26*1.5
d = 46.41 ≈ 50mm provided
total depth = D = 50+5+20
D = 76mm
Effective span
1/12*(1816-230) = 132.1< 230
⸫ lex = 1.816m
ley = 2m
Load calculation
Self-wt. = 75*25*1000
= 1.875KN/m
Floor finishing = 1KN/m
Live load = 4KN/m
Total Load = 6.875KN/m
Factored load = 1.5*6.875
= 10.31KN/m
Design moment
MX = αxwlx2
MY = αywlx2
ley/lex = 2/1.816 = 1.101
⸫ αx negative = 0.043
αy positive = 0.032
⸫ αy negative = 0.037
αy positive = 0.028
Moment calculation
Mx –ve = 0.043*10.31*1.8162
= 1.46KNm
My +ve = 0.032*10.31*1.8162
= 1.088KNm
My –ve = 0.037*10.31*1.8162
= 1.258KNm
My +ve = 0.028*10.31*1.8162
= 0.952KNm
Reinforcement calculation at mid span
Along lx
Mx = 1.088KNm
% of steel = 50*fck/fy [1-√1-4.6Mu/fckbd2]
= 50*20/415[1-√1-4.6*1.088*106/20*1000*502]
= 0.123
Astx = 0.123/100*1000*75
= 92.25mm2
Bars of 10mm dia is provided
⸫ Spacing = S = ^/4*102/92.25*1000 = 851.38 ≈ 845mm spacing provided
Reinforcement along B20
Pt. = 0.12%
Ast = 0.12/100*1000*100
Ast = 120
Providing 10mm dia bars
Spacing = ^/4 *102/120*1000
= 654.49 ≈ 650mm provided
Reinforcement at B4 & B22
My –ve = 1.258
% of steel = 50*fck/fy [1-√1-4.6Mu/fckbd2]
= 50*20/415[1-√1-4.61*0.258*106/20*1000*502]
= 0.143
Ast = 0.143/100*1000*75
= 107.25mm
Bar of 10mm dia provided
⸫ Spacing = S = ^/4*102/93*1000
= 844.51 ≈ 840mm is provided
Reinforcement at B23
Mx –ve = 1.46KNm
% of steel = 50*fck/fy [1-√1-4.6Mu/fckbd2]
= 50*20/415[1-√1-4.6*1.46*106/20*1000*502]
= 0.167
Ast = 0.157/100*1000*75
= 117.75mm2
10mm bar provided
S = ^/4*102/117.75*1000
= 667.00
S = 665mm provided
Reinforcement at edge
Pt. = 0.12%
Ast = 0.12/100*1000*75
= 90mm2
⸫ 10mm bars are provided
S = ^/4*102/90*1000
= 872.66mm
= 870mm spacing provided
Design of Slab 3
l/d = 26*M.F
Pt. = 0.4%
⸫ M.F
⸫1.945*1000/d = 1.5*26
= d = 49.87mm ≈ 50mm
⸫ The total depth = D = 50+5+20
D = 75mm
Effective span
1/12*(1.945-0.230)*103
= 142 < 230
⸫ lex = 1.945m
ley = 3.508m
Along ly
My = 0.952 KNm
% of steel = 50*fck/fy [1-√1-4.6Mu/fckbd2]
= 50*20/415[1-√1-4.6*0.952*106/20*1000*752]
= 0.134
Asty = 0.134/100*1000*75
= 100.5
Bars of 10mm dia is provided
⸫ Spacing = S = ^/4*102/100.5*1000
= 781.49 ≈ 780 mm spacing is provided
αy –ve = 0.037
αy +ve = 0.028
Moment calculation
+Mx = 0.0488*10.31*1.9452
= 1.903KNm
-Mx = 0.0648*10.31*1.9452
= 2.52KNm
+My = 0.028*10.31*1.9452
= 1.092KNm
-My = 0.037*10.31*1.9452
= 1.443KNm
Reinforcement calculation at mid span
Along lx
Pt. = 50*20/415[1-√1-4.6*1.903*106/20*1000*502]
= 0.221
Astx = 0.221/100*1000*75
= 165.75mm2
If bars of 10mm dia is provided
⸫ The spacing = S = ^/4*102/165.75*1000
= 473.84 ≈ 470 is provided
Along ley +My = 1.092*106Nmm
dy = 50-5 = 45mm
Pt. = 50*20/415[1-√1-4.61.092*106/20*1000*452]
= 0.154
Asty = 0.154/100*1000*75
= 115.5mm2
Bars of 10mm dia is provided,
The spacing, S = ^/4*102/115.5*1000
= 679.99 ≈ 675mm provided
Reinforcement at B3, B23, B5
-My = 1.443*106 Nmm
Pt. = 50*20/415[1-√1-4.6*1.443*106/20*1000*502]
= 0.165
Ast = 0.165/100*1000*75
= 123.75mm2
⸫ Bars of 10mm dia is provided
⸫ Spacing = ^/4*102/123.75*1000
= 634.66
S = 630mm spacing provided
Reinforcement at B6
-Mx = 1.38*106 KNm
Pt. = 50*20/415[1-√1-4.6*1.38*106/20*1000*452]
= 0.196
Ast = 0.196/100*1000*75
= 147mm2
Bars of 10mm dia provided
Spacing = ^/4*102/147*1000
= 534.28mm ≈ 530mm provided
Reinforcement at B7
Pt. = 0.12
Ast = 0.12/100*1000*75
= 90mm2
Bars of 10mm dia provided
S = ^/4*102/90*1000
= 872.66mm ≈ 870mm provided
DESIGN OF SLAB 5
l/d = 26*M.F
at Pt. = 0.4%
= 2.79*1000/d = 26*1.5
= d = 71.53mm
Total depth = D = 75+5+20
= 100mm
Effective span
Width support = 230mm
⸫ 1/12*(2.79-0.230)
= 0.213 < 230
⸫ lex = 2.79m
ley = 3.508m
Load Calculation
Self-wt. = 25*100*10-3 = 2.5KN/m
Floor finishing = 1KN/m
Live load = 4KN/m
Total load = 7.5KN/m
Factored load = 1.5*7.5 = 11.25KN/m
Design moment
MX = αxwlx2
MY = αywlx2
ley/lex = 3.508/2.79
= 1.25
αx –ve = (0.051-0.048)/ (1.3-1.2)*(1.25-1.2) +0.048
= 0.0495
αx +ve = (0.039-0.036)/ (1.3-1.2)*(1.25-1.2) +0.036
= 0.0375
αy -ve = 0.037
αy +ve = 0.028
Moment calculation
Mx +ve = 0.0375*11.25*2.792
= 3.28KNm
Mx –ve = 0.0495*11.25*2.792
= 4.33KNm
My –ve = 0.037*11.25*2.792
= 3.240KNm
My +ve = 0.0375*11.25*2.792
= 3.240KNm
My +ve = 0.0375*11.25*2.792
= 2.45KNm
Reinforcement Calculation
Reinforcement at mid span
Along lex
+ve Mex = 3.28KNm
Pt. = 50*20/415[1-√1-4.6*3.28*106/20*1000*752]
= 0.167
Ast = 0.167/100*1000*100
= 167mm2
Providing 10mm dia
⸫ spacing = ^/4 *102/167*1000
= 470.29≈ 465mm spacing provided
Reinforcement at mid span
Along ley
+ve Mey = 2.45KNm
dy = 70mm
Pt. = 50*20/415[1-√1-4.6*2.45*106/20*1000*702]
= 0.142
⸫ Ast = 0.142/100*1000*100
= 142mm
⸫ providing 10mm dia
Spacing = ^/4*102/142*1000
= 553.09 ≈ 550mm provided
Reinforcement along B9, B12, & B15
-ve My = 3.240KNm
Pt. = 50*20/415[1-√1-4.6*3.24*106/20*1000*752]
= 0.165mm2
Providing 10mm dia bars
Spacing = ^/4*102/165*1000
= 475.99 ≈ 470mm spacing provided
Reinforcement along B11
-Mex = 4.33KNm
Pt. = 50*20/415[1-√1-4.6*4.33*106/20*1000*752]
= 0.223
Ast = 0.223/100*1000*100
= 233mm2
Providing 10mm dia
Spacing = ^/4*102/223*1000
= 352.19mm ≈ 350mm provided
Reinforcement at B13
Pt. = 0.12/100*1000*100
= 120mm2
Providing 10mm dia
Spacing = ^/4*102/120*1000
= 654.44mm ≈ 650mm spacing provided
DESIGN OF SLAB 7
l/d = 26*M.F
Pt. = 0.4%
⸫ from IS 456⁚2000
M.F = 1.5
2.55*103/d = 26*1.5
d = 65.38 ≈ 75mm provided
Total depth = 75+5+20
= 100mm
Effective length
1/12 (2.55-0.230) = 193.3 < 230
ley = 3.945m
lex = 2.55m
Load Calculation
Moment Calculation
Mx –ve = 0.057*11.25*25.52
= 4.169KNm
Mx +ve = 0.044*11.25*25.52
= 3.218KNm
My -ve = 0.037*11.25*25.52
= 2.70KNm
My +ve = 0.028*11.25*25.52
= 2.04KNm
Reinforcement calculation at mid span
Along lex
Mx +ve = 3.218KNm
Pt. = 50*20/415[1-√1-4.6*3.218*106/20*1000*752]
Pt. = 0.164
Ast = 0.164/100*1000*100 = 164mm2
Providing 10mm dia bars
S = ^/4*102/164*1000
= 478.90mm ≈ 475mm provided
Along by
dy = 75-5
= 70mm
Pt. = 50*20/415[1-√1-4.6*2.04*106/20*1000*702]
= 0.118mm
Ast = 0.118/100*1000*100
= 118mm2
Providing 10mm dia bars
Spacing = ^/4*102/118*1000
= 665.59 ≈ 660mm provided
Reinforcement along B22, B6, B30
My –ve = 2.70KNm
Pt. = 50*20/415[1-√1-4.6*2.70*106/20*1000*752]
= 0.136
Ast = 0.136/100*1000*100
= 136mm2
Providing 10mm dia bars
Spacing = ^/4*102/136*1000
= 577.49 ≈ 570mm provided
Reinforcement along B24
Mx –ve = 4.169*106 Nmm
Pt. = 50*20/415[1-√1-4.6*4.169*106/20*1000*752]
= 0.214
Ast = 0.214/100*1000*100
= 214mm2
Providing 10mm dia bars
Spacing = ^/4*102/214*1000
= 367.00 ≈ 365mm provided.
Design of Slab 8
l/d = 26*M.F
Pt. = 0.4%
⸫ M.F = 1.5 from IS 456⁚2000
2.55*1000/d = 26*1.5
d = 65.38 ≈ 75mm provided
Total depth = D = 75+5+20
= 100mm
Effective span
1/12*(2.55-0.230) = 0.193 < 230
lex = 2.55mm
ley = 3.641mm
Load calculation
Self-wt. = 25*100*10-3 = 2.5KNm
Floor finishing = 1KNm
Live load = 4KNm
Total load = 7.5KNm
Factored load = 1.5*7.5 = 11.25KNm
Design moment
MX = αxwlx2
MY = αywlx2
ley/lex = 3.641/2.55
= 1.42
αx –ve = (0.057-0.055)/(1.5-1.4)*(1.42-1.4)+0.055
= 0.0554
αx +ve = (0.044-0.041)/(1.5-1.4)*(1.42-1.4)+0.8041
= 0.0416
αy –ve = 0.037
αy +ve = 0.028
Moment calculation
Mx –ve = 0.0544*11.25*2.252
= 3.97KNm
Mx +ve = 0.0416*11.25*2.252
= 3.043KNm
My –ve = 0.037*11.25*2.252
= 2.70KNm
My +ve = 0.028*11.25*2.252
= 2.04KNm
Design of slab
l/d=26 M.F
d=0.4%
M.F=1.5
2.00x1000/d=26x1.5
d=51.28mm
d~50 mm (provided)
total depth
D=50+5+20
D = 75mm
Effective length
=1/12(2 – 0.230 )
= 0.147 <0.230mm
lex =2.0m
ley =2.55m
Load Calculation
Sl.wt. =75x25x10-3 = 1.875
F.F = 1
L.L =4
T.L =6.875 Kn/m
F.L = 10.31Kn/m
Moment calculation
Mx = αxwlex2
My = αywlex2
ley/lex = 1.275
αx –ve =(0.051 – 0.048)/(1.3 – 1.2) x (1.275 -1.8)+0.048
=0.05025
α x+ve =(0.039 – 0.036)/(1.3-1.2)x(1.275 – 1.2)+0.036
= 0.03825
α y –ve = 0.037
α y +ve =0.028
Moment Calculation -
Mx-ve = 0.05025x10.31x22
= 2.072 KN-m
Mx+ve = 0.03825x10.31x22
= 1.577 KN-m
My-ve = 0.037x10.31x22
= 1.525KN-m
My+ve = 0.028x10.31x22
= 1.154KN-m
Reinforcement Calculation –
Reinforcements – B19 & B28
Mx-ve = 2.072 KN-m
Pt = (50x20/415)x(1-(1-(4.6x2.07x10/1000x20x4152))1/2)
Pt = 0.241
Ast = (0.241/100)x1000x75
= 180 mm2
Providing 10mm bars:
Spacing = ((3.14x102)/180x4)x1000
= 436.11
~ 435mm provided
At mid span:
Along ley; dey = 15 mm
+veMey = 1.154 KN-m
Pt = ((50x20)/415)x(1-(1-(4.6x1.15x10/20x1000x452))1/2)
= 0.163
Ast = (0.163/100)x1000x75
= 122.25 mm2
Providing 10mm thikness:
Spacing = ((3.14x102)/122.25x4)x1000)
= 462.12
~ 460 mm provided
Reinforcement at mid span along:
Mx+ve = 1.577 KN-m
Pt = (50x20/415)x(1-(1-(4.6x1.577x106/20x100x502))1/2)
=0.181
Ast = 0.181/100 x1000 x 75
= 135.75 mm2
Providing 10mm dia bars
Spacing =π/4x 102/135.75 x1000
= 578.56mm
~575 mm provided
Reinforcement along B25 & B26
My –ve =1.525Knm
Pt=[50x20/415][1-{1-(4.6x1.525x106/20x1000x502)}1/2]
=0.175
Ast=0.175/100x1000x75
=131.25mm2
Providing 10mm dia
Spacing=π/4 x102/131.25 x1000
=598.39
~595mm providing
Design of slab
l/d = 26 x M.F
From Is 456:2000
For pt=0.4%
2x1000/d=26x1.5
d= 51.28
d~50mm
Total Depth=50+5+20
D=75mm
Effective Length
lex =1/12x(2-0.230)
ley=0.147< 0.230
when evterior support= 0.230
lex=2m
ley=2.55m
Load calculation
self wt.=25x75x10-3
f.f= 1 kn/m
L.L= 4Kn/m
T.L= 6.875 Kn/m
F.L= 10.81 Kn/m
Moment Calculation
Mx= αxwex2
My= αywley2
ley/ley = 2.55/2 = 1.275
From table = 26
αx –ve = (0.051 – 0. 048)/ (1.3 -1.2)x(1.276-1.2) +0.048
= 0.05025
αx+ve =(0.039 – 0.036)/(1.3 – 1.2)x(1.275-1.2) + 0.036
= 0.03825
αy –ve = 0.027
αy +ve = 0.028
Moment calculation
Mx +ve=0.03825x 10.31x 22
= 1.577 Knm
Mx –ve =0.0502 x 10.31 x 22
= 2.07 Knm
My +ve =0.028 x 10.31 x 22
= 1.154 Knm
My –ve =0.037 x10.31 x 22
= 1.521 Knm
Reinforcement calculation
At mid span along Lex
Mx +ve = 1.577
Pt = 50 x20 /415 x[ 1- {1-( 1.577
x106x4.6)/(20x1000x502)}1/2]
Pt = 0.181
Ast = (0.181/100) x 1000 x 75
=135.75
Providing reinforcement 0f 10mm
Spacing =( π/4x102)/135.7 x1000
=578.77
~ 575mm c/c
At mid span along Ley
My +ve =1.154 x 106
Pt = 50x20/415 [1-{1- (4.6x1.154x106/20x1000x502)}]
=0.13150
Ast=0.13150/100x1000x75
Ast=98.62 mm2
Providing 10mm dia spacing =(π/4x102)/98.62x1000
= 796.38
= 795 mm C/C
Reinforcement along B19 & B18
Mx –ve =2.07 knm
Pt=50x20/415x[1 – (1- 4.6x2.07x106/20x1000x502)
Pt = 0.24155
Ast= 0.24155/100x1000x75
Ast = 181.16 mm2
Providing 10mm dia bars
Spacing =( π/4x102/181.16)x1000
= 433.53
~430 mm C/C
Reinfoecement alon B25
MY –ve =1.52 knm
Pt= 50x20/415x [1- (1- 4.6x1.52x106/20x1000x502)]
Pt= 0.17482
Ast = 0.17482x1000x75/100
= 131.11 mm2
Providing 10mm dia bars
Spacing =( π/4)x102x1000/131.11
= 599.03
~ 590 mm (c/c)
Reinforcement at
Pt = 0.12
Ast = 0.12x1000x75/100
= 90 mm2
Providing 10mm dia
Spacing =( π/4)x102x1000/100
= 785.39 mm
~ 785 mm (c/c)
Design of slab 10
l/d = 26xM.F
pt = 0.41
M.F = 1.5
5.515x1000/d = 26x1.5
d = 141.4
~ 140 mm
Total depth = 140+25
D = 165 mm
Effective span
( 1/12)x(5.515-0.230)
0.440<0.220
Lex = 5.515+0.140
= 5.656 mm
Ley = 9.583+0.140
= 9.723 mm
Load calculation
Self wt. = 25x140x10-3 = 3.64 Kn/m
L.L. = 410 Kn/m
F.F. = 1 Kn/m
T.L. = 8.64Kn/m
F.L. = 12.96 Kn/m
Moment calculation
Mx=αxwlex2
My=αywlex2
ley/lex= 1.719
αx –ve = (0.064-0.057)/(1.75-1.5)x(1.719-1.5) + 0.057
=0.06313
α x+ve =(0.048-0.044)/(1.7-1.5)x(1.719-1.5)+0.044
=0.0475
α y –ve = 0.037
α y +ve = 0.028
Mx –ve =0.06313 x11.93x5.515
= 4.512Knm
Mx+ve =0.0475x12.96x5.515
=3.395Knm
My –ve =0.037x12.96x5.515
= 2.644Knm
My+ve=0.028x12.96x5.515
=2.00Knm
Reinforcement in mid span
At mid span along lex
Mx+ve= 3.395 KNm
Pt=50x20/415 x[1-{1-(4.6x3.396x106/20x1000x1482)}1/2]
Pt=0.0484
Ast=0.0484/100x1000x165
Ast=80.00mm2
Providing 10mm dia
Spacing =π/4x102/80.00x1000
=981.74
~980mm c/c
along ley
My+ve = 2 KN-m
P = (50x20/415)x(1-(1-(4.6x2x10/20x1000x102))1/2)
t
= 0.0284
Ast = (0.0284/100)x1000x165
= 46.2 mm2
Providing 10mm dia:
Spacing = (3.14x102/46.2x4)x1000
=1699.134
~ 1690 mm c/c
Mx-ve = 0.6008x12.11x3.932
= 11.302 KN-m
Mx+ve = 0.04576x12.11x3.932
= 8.608 KN-m
My-ve = 0.037x12.18x3.932
= 6.96 KN-m
My+ve = 0.028x12.18x3.932
= 5.267 KN-m
Reinforcement Calculation
At mid span
Along lex
Mx+ve = 8.608 KN-m
Pt = (50x20/415)x(1-(1-(4.6x8.608x106/20x1000x105))1/2)
= 0.251
Ast = 0.251x1000x125
= 313.75 mm2
Providing 10mm dia bars
Spacing = 3.14x100x1000/313.75x4
= 250.19
~ 250 mm
Along lex
My+ve = 5.287 KN-m
Pt = (50x20/415)x(1-(1-(4.6x5.287x106/20x1000x1002))1/2)
= 0.150
Ast = 0.150x1000x125/100
= 187.5 mm2
Providing 10mm dia bars:
Spacing = 3.14x100x1000/187.5x4
= 418.66
~ 415 mm (c/c)
Reinforcement along B23 & B34 & B10
My-ve = 6.96 KN-m
Pt = (50x20/415)x(1-(1-(4.6x 6.96x106/20x1000x1002))1/2)
= 0.201
Ast = 0.201x1000x198/100
= 251.25 mm2
Providing 10mm dia bars :
Spacing = 3.14x100x1000/251.25x4
= 312.45
~ 310 mm (c/c)
Reinforcement along B28 & B39
Mx-ve = 11.302 KN-m
Pt = (50x20/415)x(1-(1-(4.6x11.302x106/1000x20x1002))1/2)
= 0.125
Ast = 0.125x1000x125/100
= 156.25 mm2
Provide 10mm dia bar
Spacing=(𝜋/4x100/156.25)x1000
=502.65 mm
~ 500 mm (c/c)
Reinforcement at outer edge
Pt=0.12%
Ast=0.12/100x1000x125
=150 mm2
Provide 10 mm bar
Spacing=(π/4x100)/150x1000
=523.59 mm
~520mm(c/c)
Design of slab 14
l/d=26XM.F
pt=0.4%
M.F= 1.5
2x1000/d=26x1.5
d=51.28 mm
d =50mm
total depth D=50+20+5
=75 mm
Effective length
1/12(2-0.230)
=0.147<0.230
The Lex=2m
Ley =2.802m
Load Calculation:
Self wt. = 75x20 x10-3
= 1.875 KN/m
F.F. = 1 KN/m
L.L. = 4 KN/m
T.L. = 6.875 KN/m
L.T.L. = 1.5 x 6.875
= 10.31 KN/m
Moment calculation:-
Mx+ve = 0.041 x 10.31 x 22
= 1.89 KN-m
Mx-ve = 0.055 x 10.31 x 22
= 1.134 KN-m
My+ve = 0.028 x 10.31 x 22
= 1.154 KN-m
My-ve = 0.037 x 10.31 x 22
= 1.82 KN-m
Reinforcement calculation:
At mid span
Along ley
My+ve = 1.154 KN-m
Pt = (50x20/415) x (1-(1-(4.6 x 1.154 x
106/1000x20x1002))1/2)
= 0.131
Ast = 0.131x1000x75/100
= 98.25 mm2
Providing 10mm dia bars
Spacing = (π/4)x102x1000/98.25
= 799.14
Along lex
Mx+ve = 1.69Knm
Pt = (50x20/415)x[1-{1-(4.6x1.69x106/20x1000x502)}1/2]
= 0.195
Ast = 0.195x1000x75/100
= 146.25 mm2
Providing 10mm dia bars
Spacing =( π/4)x102x1000/146.25
= 537.02
~ 530 mm c/c
At side edge (B43 & B45)
Pt = 0.12
Ast = 0.12x1000x75/100
Ast = 90 mm2
Providing 10mm
Spacing=π/4 x102/90 x1000
=827.66m
= 820 mm c/c
Shorter span = l
For one way slab
m.f = 1.3
l/d = 28 x m.f
0.8516/d = 26x1.3
d = 0.8516/26x1.3
d = 25.19
d ~ 50 mm
overall depth (D) = d + @/2 + dmax
D = 50 + 10/2 + 20
= 75 mm
Effective span:
Support width < 1/12 x clear span
Clear span = 621.6 mm
230 < 1/12 x621.6
230> 51.8
(1) Clear span – 51.8 + 50 = 101.8mm (c/c)
(2) 851.6 mm
Lex = 101.8 mm
Ley = 101.8 mm
Load calculation:
Dead load –
Self as t = 0.115x 25
= 2.875 KN/m
Floor finish = 1 KN/m
Dead load = 3.875 KN/m
f.d.l. = 1.5x 3.875 = 5.81
live load: 4x1 =4
f.l.l. = 1.5x4 = 6
B.M. Calculation:
At B0
MDL = 1/12 x 5.81 x(0.101)2
= 5.017 x 10-3 KN-m
MLL = 1/10 x 6 x(0.101)2
= 6.12 x 10-3 KN-m
DESIGN OF BEAM
BEAM DESIGN
Load on B28
Self-wt. of slab 9 = 25*0.075*1 = 2.1KN/m
F.F = 1KN/m
W1 = T.L = 3.1KNm
Self –wt. of slab 10 = 25*0.165*1 = 4.125 KN/m
F.F = 1KN/m
W1 = 5.125KN/m
1) D.L of slab =
3.1*2/3 + 2*5.125/2 (1-1/ (9.583/5.515)2)
= 6.629KN/m
Masonry wall = 0.115*(3.15-0.1)*20
= 6.555KN/m
Sl. Wt. of Rib = 1.06KN/m
= 14.238
F.L = 21.347 KN/m
Factored line load = 4*2/2*(1-1/3*(9.583/5.515)2)
= 6.22
F.L.L = 9.33 KN/m
T.L = 30.68
Total load on B30
= 53.89 KN/m
Total load B27 = 55.14 KN/m
Total load B28 = 30.68KN/m
Design of Beam 30
Mbd = wl2/8 = 53.89/8*3.9452
= 104.83KNm
⸫ l/d = 26
3.945/d =26
= d = 159.73mm
d = 151.73mm ≈ 225mm provided
b = 300-mm D = 250mm
Xu max./d = 0.48
= 0.48 = 0.87*415*Ast/0.36*20*300*225
= Ast max = 646.445mm2
From G⁚1⁚1
Mu = 0.87*fy *Ast d*(1-Ast fy /bd fck)
= 104.83*106 =0.87*415*Ast*225*(1-Ast 415/360*20)
= 104.83*106 = 81236.25 Ast
= 24.93Ast2
Ast = 129.5mm2
Design of shear
↊v = Vu/bd
Vu = Wl/2 = 53.89*3.945/2 = 106.29KN
⸫ ↊v = Vu/bd = 106.29*103/300*400 = 0.88N/mm2
Pt. = 100Ast/bd = 100*850.9/300*400 = .70
⸫ ↊c = (0.56-0.48)/(0.752-0.5)*(0.75-0.7)+0.48
= 0.496
↊v < ↊c
Shear reinforcement design
Total shear force = 106.29*103
Shear resisted by concrete = bd↊c
= 300*400*0.496
= 59.520KN
Shear resisted by reinforcement = 106.29-59.520
= 46.70KN
Using 6mm bars in 2 legs of Fe 415
Vvs = 0.87*415/δv*2*^/4*62 *400
46.770*103 = 0.87*415/δv*2*^/4*62*400
δv = 174.61mm
= 172cc
DESIGN OF FOOTING
Page-1; Design of Footing –
Total load from two column = 255.5+312.51
= 568.01 KN
Approx wt. of footing = 10% of 568.01
= 56.2 KN
Total load from method = 624.81 KN
Safe bearing capacity of soil = 99.64 KN/m
Area of foundation = 624.81/99.64
= 6.27 m2
Distance of the resultant column load from the axis of the column A;
x̅ = (312.5 x 1.692) / (312.5+255.51)
= 0.93 m
(300+250)xdx1.80=(312.5-90.62x0.5x0.25)
D = 308.79m
Bending moment calculation
1- Load on column c3 = 255.51KN
2- Load on column c4 =312.5KN
Reaction of soil on footing per meter = 312.5+255.51/2.86
= 198.60KN/m
Bending moment on column c3
Mc3 = 198.60x0.52/2
= 24.82KN-m
Mc4 = 198.60x0.652/2
= 41.95KN-m
Page-5; ks = 0.5+0.98
= 1.48
Ks = 1.0
τc’ = τc = 0.25(σu)1/2
= 1.47 N/m2
Load transfer from column to footing
The nominal bearing stress in the column concrete
σbt = Pu/Ac
= (1.5x891.84x1000)/(300x280)
= 15.92 N/mm2
Allowable bearing stress = 0.48xσch
= 15.75 N/m2
Then the column can not transfer by bearing
Load Calculation
i. Roof :-
Live load = 1.5KN/m2
S.W of slab = 0.165*25 = 4.1KN/m
Roof finish = 1.5KN/m2
T.L = 7.1 KN/m
Factored load = 18.65KN/m
Typical Floor
L.L = 4KN/m
S.W of slab = 0.165*25 = 4.12KN/m2
F.F = 1KN/m
T.L = 9.1KN/m
F.L = 13.68KN/m
Walls:-
Wt. of internal walls = [0.115*(3.05-0.4)*20]
= 6.325KN/m
Main beam =
Size of beam = 0.3*0.4
= 0.12mm
Wt. of beam = (0.3*(0.4-0.1))*25
= 2.25KN/m
Secondary beam
Size of beam = 230*300mm
Wt. of beam = [0.23*(0.30-0.165)*25)
= 0.77
Factored load = 1.5*0.77 = 1.15KN/m
Floor transfer load to column = 3.78*4.02
= 15.19KNm2
Load on column
Pu = 891.84 KN
Length of column = 3.215m
M30 ⸫ Fu = 30N/mm2
Fy = 415N/mm2
Size of column = 300mm
Effective length = 0.8*l
= 0.8*3.215 = 2.572m
The area of steel in column should be
Asc = 1% Ag
Ac = 99% Ag
Area of rectangle
Length (x) * width (y) = 83345.63
300 * y = 83345.63
Y = 277.81 ≈ 280mm
Hence we provide 300mm*280mm rectangular column
Area of reinforcement
Asc = 0.01*Ag
Asc = 0.01*83345.63
Asc = 833.45mm2
Providing 18mm dia beams
⸫ no. of beam = 833.45/^/4*182
= 3.27 ≈ 4
Hence providing 4bars of 18mm
Spacing: - min. of
1} 300mm
2} Least lateral length = 280mm
3} 16*ⱷ = 16*16 = 256mm
⸫ 250mm is provided as spacing
1) Roof:-
Typical floor
L.L = 4KN/ m2
S.W of slab = 0.100*25 = 2.5KN/ m2
F.F = 1KN/ m2
T.L = 7.5KN/ m2
F.L = KN/ m2
Walls
Main beam
Length of walls
= 1+1.39
= 2.39m
Load on column
Walls = 2.39*6.095
= 14.56KN/ m2
Asc = 1% of Ag
Ac = 99% of Ag
Or 318.58*103 = 0.4*20*0.99Ag+0.67*415*0.01Ag
Ag = 29772.44mm2
Lateral tiles
Spacing
300m
L. lateral length = 250mm
16*16 = 256mm
DESIGN OF C3 &C7
1) Roof:-
Typical floor
L.L = 4KN/ m2
S.W of slab = 0.075*25 = 1.875KN/ m2
F.F = 1KN/ m2
T.L = 6.875KN/ m2
F.L = 10.31KN/ m2
Walls
Main beam
Secondary beam
Length of walls
= 1+0.97+0.846
= 2.816m
Length of beam
= 2.816m
Load of column
= 122.63+52.04
= 174.67KN
⸫ Pu = 255.51KN
⸫ Length of column = 3.215m
M30 = fck =30N/mm2
Fy = 415N/mm2
Asc = 1% of Ag
Ac = 99% of Ag
Or 255.51*103 = 0.4*30*0.99Ag+0.67*415*0.01Ag
Ag = 17431.46mm2
Total cost =
759696.432 ≈
₹ 800000
12. Plastering on 951.2 m3 43.81 41672.07
interior wall
(both side)
13. Plastering on 794.461 m3 43.61 34805.33
external wall
(both side)
Total amount =
1099391.14 ≈
₹1100000
We can conclude that there is difference between the theoretical and practical work
done. As the scope of understanding will be much more when practical work is
done. As we get more knowledge in such a situation where we have great
experience doing the practical work.
Knowing the loads we have designed the slabs depending upon the ratio of
longer to shorter span of panel. In this project we have designed slabs as two way
slabs depending upon the end condition, corresponding bending moment. The
coefficients have been calculated as per I.S. code methods for corresponding lx/ly
ratio. The calculations have been done for loads on beams and columns and
designed frame analysis by moment distribution method. Here we have moderate
bearing capacity, and Isolated footing & Combine footing is done.
REFERENCES
.
0.3000 3.4000
0.2500
2.1900
0.7800
0.9300 0.650
0.5000
PLAN OF COMBINE FOOTING
0.600
0 0.845
0.845
0.5005 5 0.650
0 4 Bars of
dia
0
4 bars of dia
Elevation 5 bars of dia 12 mm
of combined 16 mm
0.3000
Ground level
columns bar
20 mm O 120 c/c
1.5000
0.6000 0.5500
Drawing of isolated footing
1 legged 6 mm Q
@ 250 mm c/c
0.3000 16 mm Q
single
legged
6 mm dia 3.1250
0.2500 bars
4 bars 16 mm Q
PLAN VIEW
STUDENTS PROFILE