MASS BALANCE
Perhitungan mass balance menggunakan Sequencing Batch Batch Reactor (SBR) sebagai
pengolahan biologis seperti Gambar. 4.1 di bawah ini :
Sludge
Sludge Sludge
Drying Bed Thickener
3
Q = 0.48 m /s
%TSS = 100% %TSS = 100% Grit Chamber %TSS = 95% Bak Ekualisasi %TSS = 95%
Removal Removal
kg/hari kg/hari 5% kg/hari 0% kg/hari
mass TSS = 8709.12 mass TSS = 8709.12 TSS mass TSS = 8273.664 TSS mass TSS = 8273.664
Sumur Pengumpul TSS, Removal Removal
2% 0%
BOD, COD, N, P BOD BOD %BOD = 98%
Influent
Removal Removal
2% 0% kg/hari
COD COD mass BOD = 7722.086
Removal Removal
Removal 0% 0% 0%
%BOD = 100% %BOD = 100% N %BOD = 98% N %COD = 98%
Removal Removal
kg/hari kg/hari 0% kg/hari 0% kg/hari
mass BOD = 7879.68 mass BOD = 7879.68 P mass BOD = 7722.086 P mass COD = 17476.3
%COD = 100% %COD = 100% %COD = 98% %N = 100%
mass COD = 17833 kg/hari mass COD = 17832.96 kg/hari mass COD = 17476.3 kg/hari mass N = 1658.88 kg/hari
%N = 100% %N = 100% %N = 100% %P = 100%
mass N = 1658.88 kg/hari mass N = 1658.88 kg/hari mass N = 1658.88 kg/hari mass P = 290.304 kg/hari
%P = 100% %P = 100% %P = 100%
mass P = 290.304 kg/hari mass P = 290.304 kg/hari mass P = 290.304 kg/hari
Pada sumur pengumpul tidak terjadi penyisihan parameter air limbah, karena fungsi
utamanya adalah mengumpulkan dan menyetabilkan debit air limbah yang masuk ke IPAL.
Diagram alir mass balance di sumur pengumpul dapat dilihat pada Gambar 4.3
Pada bar screen tidak terjadi penyisihan parameter air limbah, karena fungsi utamanya
adalah menyisihkan benda atau partikel berukuran besar, seperti daun dan ranting yang terbawa
oleh air limbah. Nilai parameter dan beban yang keluar dari bar screen sama. Diagram alir mass
balance di bar screen dapat dilihat pada Gambar 4.4
= 25 kg/hari Q min
Pada mass balance grit chamber dihitung besarnya beban yang masuk ke unit grit chamber,
beban yang teremoval, dan beban pada effluent. Hasil perhitungan mass balance grit chamber
dapat dilihat pada perhitungan berikut. Diagram alir mass balance di grit chamber dapat dilihat
pada Gambar 4.5.
BOD = 2%
COD = 2%
TSS = 5%
BOD =7879.6 kg/hari BOD =7722.09 kg/hari
P = 0%
COD = 17833 kg/hari COD = 17476.3 kg/hari
N = 0%
TSS = 8709.12 kg/hari TSS =8273.66 kg/hari
P = 0 kg/hari
N = 0 kg/hari
EFFLUEN = MBOD*(100%-%removal)
EFFLUEN = MCOD*(100%-%removal)
EFFLUEN = MTSS*(100%-%removal)
d. Mass Balance P
= 94 kg/hari Q peak
= 25 kg/hari Q min
EFFLUEN = MP*(100%-%removal)
= 94 kg/hari Q peak
= 25 kg/hari Q min
e. Mass Balance N
EFFLUEN = MN*(100%-%removal)
4.1.4 Sedimentasi I
Pada mass balance Sedimentasi I dihitung besarnya beban yang masuk ke unit Sedimentasi
I beban yang teremoval, dan beban pada effluent. Hasil perhitungan mass balance Sedimentasi I
dapat dilihat pada perhitungan berikut. Diagram alir mass balance di Sedimentasi I dapat dilihat
pada Gambar 4.6
BOD = 35%
COD = 35%
BOD = 5019.356 kg/hari
BOD =7722.09 kg/hari TSS = 55%
COD = 11359..6 kg/hari
COD =17476.3 kg/hari P = 15%
TSS = 3723.1 kg/hari
TSS =8273.66 kg/hari N = 15%
P = 246.7584 kg/hari
P = 290.3 kg/hari
N = 1410.04 kg/hari
N = 1658.8 kg/hari
P = 43.54 kg/hari
N = 248.832 kg/hari
EFFLUEN = MBOD*(100%-%removal)
EFFLUEN = MCOD*(100%-%removal)
REMOVAL = MTSS*%removal
d. Mass Balance P
= 94 kg/hari Q peak
= 25 kg/hari Q min
EFFLUEN = MP*(100%-%removal)
= 80 kg/hari Q peak
= 20 kg/hari Q min
e. Mass Balance N
EFFLUEN = MN*(100%-%removal)
Sg = 1,02 gr/cm3
ρ air = 1 gr/cm3
𝑀𝑠𝑜𝑙𝑖𝑑
Debit lumpur = 𝑆𝑔 𝑥 𝜌𝑎𝑖𝑟 𝑥 %𝑠𝑜𝑙𝑖𝑑 𝑥 1000
COD = 85%
BOD=5019.356 kg/hari BOD = 558.47 kg/hari
TSS = 85%
COD=11359..6 kg/hari COD =1703.939 kg/hari
P = 90%
TSS= 3723.1 kg/hari TSS = 558.47 kg/hari
N = 87%
P= 246.7584 kg/hari P = 24.67 kg/hari
P = 222.08 kg/hari
N = 1226.7 kg/hari
Gambar 4.5 Mass Balance SBR Menggunakan Qaverage
a. Mass Balance BOD
INFLUEN = (Q*BOD)/1000
EFFLUEN = MBOD*(100%-%removal)
INFLUEN = (Q*COD)/1000
EFFLUEN = MCOD*(100%-%removal)
INFLUEN = (Q*TSS)/1000
REMOVAL = MTSS*%removal
EFFLUEN = MTSS*(100%-%removal)
d. Mass Balance P
INFLUEN = (Q*P)/1000
= 38 kg/hari Q average
= 96 kg/hari Q peak
= 20 kg/hari Q min
EFFLUEN = MP*(100%-%removal)
= 2 kg/hari Q min
e. Mass Balance N
INFLUEN = (Q*N)/1000
EFFLUEN = MN*(100%-%removal)
= 15 kg/hari Q min
Sg = 1,02 gr/cm3
ρ air = 1 gr/cm3
𝑀𝑠𝑜𝑙𝑖𝑑
Debit lumpur = 𝑆𝑔 𝑥 𝜌𝑎𝑖𝑟 𝑥 %𝑠𝑜𝑙𝑖𝑑 𝑥 1000