Official Acceptance Report

Krueng Isep Hidro Power Plant


As per commissioning stage at Krueng Isep Hidro Power Plant has begun, we stated the commissioning
of all unit has checked and tested by Gugler Commissioning Supervisor. As for the works item mentioned
below :

A. Unit 1 and 2
1. Turbine Data
 Operating time for :
- Main Inlet Valve
- Jet Deflector
- Jet Actuators
 Pressure in the cylinder
- Hy- System : Main Inlet valve, Jet deflector, jet adjustment
- Pressure for filter : Cooling and lubrication system
- Nitrogen filling operation
 Alarm and Shutdown
- Generator Bearing DE
- Generator bearing NDE
- Stator
- HPU
- Vibration
2. Dry test
 Gneeral Check
 Hydraulic connection :
- Hydraulic power unit
- Main inlet valve actuator
- Jet deflector actuator
 Fluid and gas level
- Hydraulic power unit oil level
- Oil filters installed / pressure adjusted
- Niutrogen filling HPU
- HPU Pump motor
3. Function checks
 Electric function
- HPU
- Bypass
 Hydraulic function and operating times
- HPU motor rotation
- Open and close nozzle
- Open and close jet deflector
- Open and close the main inlet valve
 Effective operating time
- Main inlet Valve
- Jet deflector
- Nozzles
B. Unit 3
1. Turbine Data
 Operating time for :
- Main Inlet Valve
- Jet Deflector
- Jet Actuators
 Pressure in the cylinder
- Hy- System : Main Inlet valve, Jet deflector, jet adjustment
- Pressure for filter : Cooling and lubrication system
- Nitrogen filling operation
 Alarm and Shutdown
- Generator Bearing DE
- Generator bearing NDE
- Stator
- HPU
- Vibration
2. Dry test
 Gneeral Check
 Hydraulic connection :
- Hydraulic power unit
- Main inlet valve actuator
- Jet deflector actuator
 Fluid and gas level
- Hydraulic power unit oil level
- Oil filters installed / pressure adjusted
- Niutrogen filling HPU
- HPU Pump motor
 electrical connection
- Control system
- HPU
- Bypass
- Sensor and potentiometer
3. Function checks
 Electric function
- HPU
- Bypass
 Hydraulic function and operating times
- HPU motor rotation
- Open and close nozzle
- Open and close jet deflector
- Open and close the main inlet valve
 Effective operating time
- Main inlet Valve
- Jet deflector
- Nozzles

Beside that, there are some works should continue after the civil works ready. The works item stated
below :

A. Unit 1 and 2
1. Dry test
 General check
- Control system
- HPU
- Bypass
- Sensor and potentiometer
 Function check
- Electrical signal
2. Generator checking
3. Wet test
4. Load test
B. Unit 3
1. Generator checking
2. Wet test
3. Load test

And from your side should prepare the civil works like below :

A. Steel ribs of penstock bifurcation near power house.


B. Penstock bifurcation near power house should be concreted before start load rejection.
C. Result of hydrotest that stated the pipeline has acceptable.

Best Regards,

David Siegl