Académique Documents
Professionnel Documents
Culture Documents
1 Cost Estimation
A capital investment is required for any industrial process and determination of the necessary
investment is an important part of a plant design project.
Before industrial plant can put into operation, a large sum of money must be supplied to purchase
and install the necessary machinery and equipment. Land and service facilities must be obtained
and the plant must be erected complete with all piping, controls and service. In addition, it is
necessary to have money available for the payment of expenses involved in the plant operation.
The total capital required for the installation and working of a plant is called total capital
investment.
The capital needed to supply the necessary manufacturing and plant facilities is called fixed capital
investment. The fixed capital is further subdivided into followings,
i. Direct Cost
ii. Indirect Cost
1) Direct Cost
The direct cost items arc incurred in the construction of the plant in addition to the cost of
equipment.
2) Indirect Cost
The capital required for the operation of the plant is known as working capital. Working capital
includes following things to be considered,
An estimate of the capital investment for a process may vary, pre-design estimated based on little
information except the size of the proposed project to a detailed estimate prepared from complete
drawings and specifications.
Between these two extremes of capital investment estimates there can be numerous, other
estimates which vary in accuracy depending on the stage of development of the project. These
estimates are called by a variety of names, but the following five categories represent the accuracy
range and designation normally used for the design purposes,
Ratio-estimated based on similar previous cost date, probable accuracy of estimate over ± 30%
Based on sufficient data to permit the estimate to be gazetted probable accuracy of estimate
within ± 20%
It is based on almost complete data but before completion of drawings and specifications,
probable accuracy of estimate within ±10%
A cost is nearly an index value for a given point in time showing the cost at that time relative to
certain base time. So, present cost is estimated from cost index as follows:
Many different types of cost indices are published regularly. Some of these can be used for
estimating equipment cost; others apply specifically to labor, construction, materials or other
specialized fields.
Length = 9.46 m
Diameter = 1.33 m
Material Factor = 2
= 10000*2*1.4
𝐼𝑛𝑑𝑒𝑥 𝑖𝑛 2018
Cost in 2018 = Cost in 2004 × 𝐼𝑛𝑑𝑒𝑥 𝑖𝑛 2004
= $ 23174.02
3 Cyclone Separator
Flow rate = 303.41 m3/hr
= 2500*1
= $ 2500
= $ 4153.03
Length = 34.70 m
Diameter = 1.96 m
Material Factor = 1
= 10000 × 1 × 2.2
= $ 22000
𝐼𝑛𝑑𝑒𝑥 𝑖𝑛 2018
Cost in 2018 = Cost in 2004 × 𝐼𝑛𝑑𝑒𝑥 𝑖𝑛 2004
= $ 29989.91
5 Cost of Absorber
Diameter of column = 1.042 m
Pressure = 30 bar
= 12000 × 2 × 1.4
𝐼𝑛𝑑𝑒𝑥 𝑖𝑛 2018
Cost in 2018 = Cost in 2004 × 𝐼𝑛𝑑𝑒𝑥 𝑖𝑛 2004
πD2 H
Volume of packing V = 4
V = 0.85 m3
6 Cost of Stripper
Diameter of column = 0.713 m
Height of Column = 15 m
= 8000 × 2 × 1
= $ 16000
2004 index = 541.2
𝐼𝑛𝑑𝑒𝑥 𝑖𝑛 2018
Cost in 2018 = Cost in 2004 × 𝐼𝑛𝑑𝑒𝑥 𝑖𝑛 2004
πD2 H
Volume of packing V = 4
V = 0.43 m3
7 Heat Exchanger
As there are two Exchangers of same specifications (E-101 & E-102) so,