13.1. GENERAL
The volume of work is the calculation of physical work which will be implemented in
the location. The calculation of the volume of work (BOQ) is one part to estimate the project
budget. Analysis of BOQ will produce a large volume of a building. Output of BOQ analysis
will be used as the basis of calculation of the RAB project, which will produce cost of capital
(Investment Cost).
Unit volume work’s Calculation of adjusted for each work item, item of work that can
be used for PLTG/MG/GU Sorong-2 (50 MW) are work of Site Development, Soil
Improvement, trestle dock etc. This calculation uses cubic unit is in m3, cm3 or more units.
The process of RAB calculation is using the unit m3. The number of jobs in Sorong
PLTG/MG/GU Sorong-2 (50 MW) is calculated using the following formula:
The location of PLTG/MG/GU Sorong-2 (50 MW) that is used for the BOQ’s calculation
is located at Sorong-2.
13.2. BOQ’S PLTG/MG/GU SORONG-2 (50 MW) SORONG LOCATION
Information:
Building 1 is at Cross Section B-B
Building 2 is at Cross section C-C to cross section F-F
Cut
Backfill
Cut Backfill
Cut Backfill
Cut Backfill
Cut Backfill
Struktur
Structure : :Road
Jalan 8 meter
8 meter
Item
Item of Works
Pekerjaan : :Road Works Jalan
Pekerjaan
Area Volume
Distance
Concrete T Concrete T Lean Concrete T 7
Road Side Lean Concrete T 7 cm Road Side
20 cm 20 cm cm
(m2) (m2) (m2) (m) (m3) (m3) (m3)
2. Drainage’s Working
a. Total of drainage of the PLTG/MG/GU = 2 Pieces (right and left shoulder road)
b. Box Culvert 95 x 110 cm
The total of drainage length of the PLTG/MG/GU = 1,272.54 m
3. Rip-Rap’s Working
The total of Rip-Rap Length = 208.80 m
Pekerjaan Batu
Area Pasangan Rata-Rata Area
Volume
Batu Pasangan Batu
Jarak
Potongan
Rip-rap Rip -rap Rip - rap
(B-B) 0.53
50.00 0.53 26.50
(C-C) 0.53
50.00 0.53 26.50
(D-D) 0.53
50.00 0.53 26.50
(E-E) 0.53
50.00 0.53 26.50
(F-F) 0.53
8.80 0.27 2.33
(F-F) + 8.80 0.53
Structure : Fence
Item of Works : Concrete Works
Area Volume
Distance
Fence Fence
Volume
No. Item of Work Unit
Estimation
I. Soil Work
A. Work of Cutting Soil
A.1. Stripping H = 0.50 meter
1 Ground Leveling Building 1 at level + 3.90 (m3) 6,560.49
3
2 Ground Leveling Building 2 at level + 3.90 (m ) 12,045.26
Depth of Striping H = 0.50 m ; Total Volume of Stripping 18,605.75
D. Works
D.1. Rip-Rap
1 Rip-rap Stone D = 0.30 m (m3) 108.33
Table 13.2. Bill Of Quantity Recapitulation For Piling Works PLTG/MG/GU Sorong-2
(50 MW) Located In Sorong
TOTAL
LENGTH
DESCRIPTION QUANTITY LENGTH
ITEM NO. UNIT OF PILE
CIVIL WORKS (Pcs) OF PILE
(m)
(m)
I CIVIL WORKS
I.1 PILING WORKS
Circular hollow pre-stressed concrete piles with 600 mm m' 504 18 9072
minimum diameter accordance to site conditions
Circular hollow pre-stressed concrete piles with 400 mm m' 144 18 2592
minimum diameter accordance to site conditions
Circular hollow pre-stressed concrete piles with 400 mm m' 280 18 5040
minimum diameter accordance to site conditions.
Circular hollow pre-stressed concrete piles with 400 mm m' 136 12 1632
minimum diameter accordance to site conditions.
Circular hollow pre-stressed concrete piles with 600 mm m' 100 18 1800
minimum diameter accordance to site conditions
Circular hollow pre-stressed concrete piles with 400 mm m' 441 18 7938
minimum diameter accordance to site conditions.
TOTAL
LENGTH
DESCRIPTION QUANTITY LENGTH
ITEM NO. UNIT OF PILE
CIVIL WORKS (Pcs) OF PILE
(m)
(m)
Circular hollow pre-stressed concrete piles with 400 mm m' 16 18 288
minimum diameter accordance to site conditions.
B. Pump Shelter
Circular hollow pre-stressed concrete piles with 400 mm m' 221 18 3978
minimum diameter accordance to site conditions.
C. Electrical Building
Circular hollow pre-stressed concrete piles with 600 mm m' 126 18 2268
minimum diameter accordance to site conditions
E. MV Switchgear Building
TOTAL
LENGTH
DESCRIPTION QUANTITY LENGTH
ITEM NO. UNIT OF PILE
CIVIL WORKS (Pcs) OF PILE
(m)
(m)
I.1.12 WAREHOUSE AND WORKSHOP
Circular hollow pre-stressed concrete piles with 600 mm m' 280 18 5040
minimum diameter accordance to site conditions
B. Garage
Circular hollow pre-stressed concrete piles with 400 mm m' 104 18 1872
minimum diameter accordance to site conditions.
C. Laboratory Building
D. Guard House
F. Mosque (N/A)
Circular hollow pre-stressed concrete piles with 400 mm m' 100 18 1800
minimum diameter accordance to site conditions.
CHAPTER 13 .......................................................................................................................................................... 1
13.1. GENERAL ................................................................................................................................................ 1
13.2. BOQ’S PLTG/MG/GU SORONG-2 (50 MW) SORONG LOCATION ................................................... 1
CHAPTER 13 .......................................................................................................................................................... 1
Table 13.1. Recapitulation of BOQ PLTG/MG/GU Sorong-2 (50 MW) Located in Sorong ........................ 10
Table 13.2. Bill Of Quantity Recapitulation For Piling Works PLTG/MG/GU Sorong-2 (50 MW) Located
In Sorong 11