Check list for initial submission of details for preparation of CRF estimates.

Example:

Sl.No Details
A Basic Data / Statistics
1 Classification of road SH/MDR
2 Total Length of the road Km 0/0 to 20/0 :
20 kms
3 Length proposed for Km 0/0 to 15/0 :
improvements 15 kms
4 Strip Plan Enclosed Strip Plan for the entire road is
to be furnished. Surface, width
and proposed improvements are
also to be indicated.
5 Road Renewal Chart Enclosed Road Renewal Chart for the
entire road is to be furnished.
6 Existing crust details GSB: 150 mm
WMM/WBM: 130
mm
BT layers : 30 mm
Total : 310 mm
7 Details of CD works viz., Enclosed Inventory of all CD works in the
Pipe culverts / Slab culverts proposed stretch are to be
/ Minor Bridges / Major provided.
Bridges / causeways/
Unbridged Crossings etc.,
B Existing technical and
other parameters
1 Classification of soil BC soils
2 CBR of soil 2 to 3% CBR may be furnished from the
available RMS data. In case the
RMS data is not reflecting the
site conditions, CBR values to be
furnished by conducting at least
2 or 3 tests at vulnerable
locations.
3 Availability of side soils Yes/No
4 Are the side soils useful for Yes/No Side soils are useful, but side
forming embankment and soils are not available. Therefore
shoulders soils obtained from trench
excavation are used and balance
soils for forming embankment/
shoulders are proposed with a
lead of 3 kms. (Depending upon
the site condition)
5 If side soils not available, 3 kms Side soils are not available / not
Lead of borrow area useful for forming embankment/
shoulders. Therefore soils
obtained from trench
excavation are not used for
formation of embankment/
shoulders. Hence borrow soils
are provided with a lead of 3
kms.
6 Traffic Intensity CVPD 150 Year of census : 2017
7 Traffic Volume PCUs 4500 -do-
C Proposed Improvements
1 Design of Crust as per Separate sheet
IRC:SP:37- 2018 (Under enclosed
printing) / SP: 37-2012
2 Flexible pavement Km 5/0 to 10/0
3 Widening Km 5/0 to 10/0 From 3.66 m to 7.0 m
4 Provision in the widening
4.a GSB 200 mm
4.b WMM 250 mm
4.c DBM/BM 75/50 mm
4.d BC 30 mm
5 Strengthening Km 7/0 to 10/0
5.a WMM 150 mm
5.b DBM/BM 75/50 mm
5.b BC 30 mm
6 Rigid Pavement
6.a CC pavement Km 8/0 to 8/5 Widening from 3.66 to 7.0m/
Existing CC 7.0 m
D CD works / CC drains /
Retaining walls etc.,
1 Proposed improvements
to CD works,
1.a Proposed for widening 5 nos. Details separate sheet enclosed
1.b Proposed for 3 nos.
reconstruction
1.c New Construction 1 no.
2 CC drains Km 8/0 to 8/5
3 Retaining walls Km 9/100 to
9/200
E Others
1 Details of shifting of RWS/Electrical RWS pipe line from 9/200 to
utilities if any pipe lines 9/300 , Electrical poles Km 8/0
to 8/5
1.a Actual cost required for Rs. 10.00 lakhs Detailed estimate from the utility
shifting of utilities shifting department is to be enclosed
along with Detailed Estimates
2 Typical cross section Enclosed
proposed
3 Color Photos with date Enclosed
indicating the location and
reflecting the actual site
condition.
4 Encumbrance free land Enclosed
certificate.
5 Road Safety Interventions Enclosed
6 Improvements to WMM 150 mm On the existing c/w from Km
Longitudinal profile for 5/200 to 5/300
making up dips / low lying
areas
F Any other details as per
site requirements.
1

Note: The above is an illustration. Please don’t copy and paste