Vous êtes sur la page 1sur 46

ELECTRICITY NETWORK AFFAIRS

ELECTRICITY NETWORK PLANNING DEPARTMENT


Material Standards & Specification Section

KM Standard Specification: ED-02-091 Version #5/ Revision #0 for


DISTRIBUTION PACKAGE SUBSTATION (DPS)

Main Sub Description Page No


Clause Clause
1.0 SCOPE 3
2.0 APPLICABLE STANDARDS 3
3.0 ENVIRONMENTAL AND SYSTEM CONDITIONS 5
3.1 Environmental Conditions 5
3.2 System Conditions 6
4.0 GENERAL DESIGN FEATURES OF DPS 6
5.0 TRANSFORMER DETAILS 8
5.1 General Design Requirements 8
5.2 Rating & Characteristics 11
Transformer Operating Conditions & Temperature rise
5.3 limits 11
5.4 Fittings & Accessories 12
5.5 Corrosion protection & Paint Work 15
5.6 Transformer Tests 16
6.0 RING MAIN UNIT (NON-EXTENSIBLE) 16
6.1 General Design & Construction Features 16
6.2 Rating & Characteristics 21
6.3 Operational Features 22
6.4 Combined Rating & Data Plates 24
6.5 Cleaning & Painting 24
6.6 Tests 25
LOW VOLTAGE DISTRIBUTION BOARD
7.0 (FEEDER PILLAR)
26
7.1 General Design & Construction Features 26
Incomer Unit with Switch-Disconnector (for
7.2 transformer Control) 28
7.3 Outgoing Distributor Unit 29
7.4 Electrical Ratings & Characteristics 31
7.5 Cleaning & Painting 32
7.6 Accessories Fitted 32
7.7 Tests 35
8.0 THE HOUSING OF DPS 35
8.1 Construction 35
8.2 Corrosion Protection & Painting 37
8.3 Earth Fault Blinking device 37
8.4 Restricted Earth Fault (REF) Tripping Mechanism 38

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 1 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

8.5 Accessories to be supplied as spares (free of cost) 39


8.6 Test to be conducted on paint work of DPS 39
8.7 Tests on DPS 39
9.0 QUALITY STANDARDS 40
10.0 TESTING, INSPECTION & DELIVERY 40
INFORMATION/DOCUMENTS TO BE
11.0 SUBMITTED BY 41
BIDDERS/MANUFACTURER
12.0 LIST OF DEVIATION TO THE SPECIFICATION 44
13.0 WARRANTY 44
14.0 RESTRICTIONS ON OUT SOURCING 44
DRAWING STD-EQP-63 RATING PLATE & CONNECTION DIAGRAM 45
DRAWING STD-EQP-64 EARTHING TERMINAL & LIFTING LUGS 46

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 2 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

1.0 SCOPE

This specification details about requirements for design, manufacture, testing, packing, transport
and supply of 11KV Distribution Package Substation Units (DPS) with housing intended for use
on public electricity 11KV/433V distribution network in the state of Qatar.

Distribution Package Substation Unit comprises of an Enclosure, Transformer, 11kV Ring main
unit(RMU) and LV Sub-station cable distribution board (SCDB) (also known as FEEDER
PILLAR), HV & LV inter-connections, auxiliary equipment and circuits, in a single transportable
unit ready for operation on being placed in position and jointed into the network.

The DPS shall be able to provide a minimum service life of 30 years under the specified
environmental, climatic, system and service conditions specified, with minimum maintenance
requirements.

DPS are intended to install, outdoor, exposed to direct sunlight. However, each component or
compartment of DPS (i.e., transformer, HV & LV S/G units) shall also individually be capable of
withstanding these conditions in outdoor.

Different Power ratings of the DPS are: 315, 500, 1000, and 1600KVA.

KAHRAMAA preferred Physical size of enclosures of different ratings of DPS are mentioned IN
below table
DPS Rated Overall size of Enclosure Clearance Clearance Clearance
Capacity Width (W), x Depth (D) x between the between left between
Height (H) equipment (FP - side wall of Right wall*
RMU) DPS to FP of DPS to
RMU
kVA mm mm mm mm
315 1800 x 1800 x 1800 500 100 200
500 3000 x 2300 x 2800 500 100 200
1000 3000 x 2300 x 2800 500 100 200
1600 3000 x 2300 x 2800 500 100 200
* The portion of wall of DPS at RMU side equivalent to RMU dimensions, shall be removable
from inner side bolts which never be accessed from outer side. This is to facilitate easy
connection or testing of cables on RMU. The RMU and Feeder Pillar should be at different
horizontal level.

2.0 APPLICABLE STANDARDS


The specification refers to the current issues of IEC and BS Standards as listed below

Package Sub-station Units


IEC 62271-202 High-voltage/low voltage prefabricated substations
IEC 60404-8-7:2008 Specification for CRGO Electrical steel strips & sheets
Transformers
IEC 60076 Power Transformers
IEC 60296/BS 148 Insulating oil for transformers and switchgear.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 3 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

IEC 60076-7 Loading Guide for Oil immersed power transformers


IEC 60076-10 Method of Measurement of Sound levels in Transformers
IEC 60404-8-7:2008 Specification for CRGO Electrical steel strips & sheets
IEC/TR 60616 Terminal and tapping markings for power transformers
BS 2562 Specification for Cable boxes for Transformers and reactors
IEC 60214-1 Off Load Tap changer

Ring Main Unit


IEC 62271-1 High Voltage Switchgear & Control gear – Common specifications
IEC 62271-100 High-voltage switchgear and control gear – AC circuit-breakers
High Voltage AC metal-enclosed switchgear and control gear for rated
IEC 62271-200
voltages above 1 kV and less than 52 kV
AC disconnectors & earthing switches for voltages above 1 kV and up to and
IEC 62271-102
including 52 kV
IEC 60265-1 High-voltages switches for rated voltages above 1 kV and less than 52 kV
High-voltages AC switch-fuse combinations for rated voltages above 1 kV and
IEC 62271-105
less than 52 kV
BS 2562 Specification for Cable boxes for Transformers & Wiping glands
IEC 61243-5 Live working – Voltage detective systems
ESI 12-6 TLF Fuse-links

LV Feeder Pillar
IEC 60439-1 & 5 Low voltage switchgear and control gear assemblies.
IEC 60947-1 & 3 Low voltage switchgear and control-gear
BS 88-5 Cartridge fuses for voltages up to and including 1000V AC and 1500V DC
BS 1363 Specification for 13A plugs, switched and un-switched socket outlet.
BS 1361 Specification for cartridge fuses for AC circuits in domestic and similar premises.
ENATS 37-2 Low voltage Distribution boards

Other Common Standards


IEC 60529 Degrees of Protection (IP code)
IEC 62262 Degrees of Protection (IK code)
ISO 3864 Graphical symbols, Safety labels, Safety colours & Safety signs
IEC 60044-1 Current Transformers
BS 6480:1997 Paper Insulated Cables
BS 6231 PVC insulated cables for switchgear and control gear wiring.
IEC 60502 XLPE Cables

Fasteners
ISO 272/4759-1 ISO Metric Precision Hexagonal Bolts, Screws and Nuts
BS 7371-1 to 12 Coatings on metal fasteners
ISO 272/885/888/ ISO Metric black hexagonal bolts, screws and nuts.
4759/1

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 4 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
Surface preparation, coating & painting work
BS 381C 1996 Specification for colours for identification, coding and special purposes.
Hot dip galvanized coating on ferrous materials – Gravimetric determination of
ISO 1460
the mass per unit area
Hot dip galvanized coatings on fabricated Iron and steel Articles – specification
BS EN ISO 1461
and test methods
ISO 2081 Electroplated coatings of zinc on iron or steel
Chemical conversion coatings – Black oxide coating on iron and steel –
ISO 11408
Specification and test methods
Sprayed Metal Coatings- Protection of Iron and Steel Against Corrosion and
BS2569-2
Oxidation at Elevated Temperatures
General introduction to standards for preparation of steel substrates before
BS7079
application of paints and related products
ISO 12944-1 to 8 Corrosion Protection of Steel Structures by Protective Paint Systems
ISO 8501-part - 1 Preparation of steel substrates before application of paints and related products.
to 4
ISO 8502-part 1 to Preparation of steel substrates before application of paints and related products -
12 Tests for the assessment of surface cleanliness.
ISO 8503-part 1 to Preparation of Steel Substrates Before Application of Paints and Related Products
5 - Surface Roughness Characteristics of Blast-Cleaned Steel Substrates
Thermal spraying Metallic and other inorganic coatings Zinc, aluminium and their
ISO 2063
alloys
ISO 9227 Corrosion tests in artificial atmospheres – Salt spray test
ISO 4628-1 to 5 Paints & varnishes – Evaluation of degradation of paint coatings
Protection against Iron & Steel Structures – Zinc and Aluminium Coating –
ISO 14713
Guidelines.
ISO 1519 Paints & varnishes – Bend Test
ISO 2808 Paints & Varnishes – Determination of Film thickness
ISO 2409 Paints & Varnishes – Cross cut test
ISO 1520 Paints & Varnishes – Cupping test
ISO 6272 Paints & Varnishes – Rapid deformation (Impact resistance) test
ISO 2812-1 to 2 Paints & Varnishes – Determination of resistance to liquids
ISO 6270 Paints & Varnishes – Determination of resistance to humidity
ISO 11997 Paints & Varnishes – Determination of resistance to cyclic corrosion conditions
ISO 7784 Paints & Varnishes – Determination of resistance to abrasion

3.0 ENVIRONMENTAL AND SYSTEM CONDITIONS

3.1 Environmental conditions

The following conditions prevail throughout in the State of Qatar:-


1. Altitude - low lying, generally close to sea level, no part exceeding 100m above sea level.
2. Maximum air temperature 50oC( 46oC).
3. Minimum air temperature 0oC ( 10 oC typical)
0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 5 of 46
ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
4. Mean maximum summer air temperature, 45 oC typical.
5. Mean maximum exposed sunlight temperature, 75oC
6. Solar radiation- peak, 1030 Watts/sq.m.
7. Humidity - 100% humidity is common throughout the year and may occur at air
temperature of 30oC or more.
8. Rainfall - very low on average. The winter season may bring infrequent very heavy
rainfall.
9. General atmospheric conditions: A hot atmosphere containing very fine, highly
penetrating dust particles. In parts the atmosphere contains a highly corrosive salt laden
sea mist. Prevailing winds generally from the north west, mostly light but occasionally
gusting in excess of 30 knots

3.2 System conditions

The 11kV system has three phase and earth

a) Nominal Voltage ....................................................................11kV


b) Maximum Voltage ............................................................... 12kV
c) Maximum Symmetrical fault level ....................................... 25KA
d) Limited earth fault current through earthing transformer.....4.5KA
e) Impulse Voltage....................................................................75kV
f) Rated Frequency ..................................................................50 Hz

The LV System has 5 wires i.e. 3 Phase + Neutral + Earth. Neutral and earth is directly
shorted at the Distribution Substation end. A consumer earth terminal is provided.

g) Nominal Voltage.................................................................. 415/240V


h) Highest Symmetrical fault level............................................44kA
i) The highest fuse rating..........................................................400 A
j) Fault duration is limited by HRC fuses, Type J to BS 88.

4.0 GENERAL DESIGN FEATURES OF DPS

1. The Distribution Package Substation (DPS) units with housing are intended to be installed in
residential areas in which the general public has the access. As such the housing shall have
high level of personal safety and vandal proof design to protect from un-authorized access.

2. The DPS shall be operated from outside (non-walk-in type) at ‘ground level’ (on concrete
plinth), and shall be suitable for mounting on concrete plinth.

3. Operator access shall be only from front side. Side access for operation is not acceptable.
Sufficient clearance shall be provided, for safe and easy access to transformer tap-changer,
oil-level indicator & temperature gauge, from the front in between FP & RMU. (Refer clause
1.0 physical sizes of enclosure.)

4. Design and construction of the housing shall have good aesthetic & pleasant appearance and
blend with the surrounding buildings

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 6 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
5. DPS shall comprise a Transformer, non-extensible Ring Main Unit (RMU) and LV feeder
pillar. RMU and LV Feeder Pillar are directly mounted on to the transformer on same side.
(i.e one side of transformer tank). Their Electrical connections to transformer are made
through bus-bars and mounted through steel trunking pieces having standard flange faces.
The connections can also be made through suitably rated flexible cables with heat shrinkable
terminations. (plug in type terminations are not acceptable).

6. RMU and Feeder Pillar should be at different horizontal level.

7. HV inter-connecting bus-bars shall be fully insulated. The HV & LV trunking pieces shall be
flange connected to transformer body, and their IP protection shall be not be less than IP65.

8. All main components of DPS shall be mounted on structural steel base frame through bolted
joints (welded joints not acceptable) to form a rigid distortion-free structure. DPS shall have
completely bolted enclosure for easy assembly and retrofit.

9. DPS shall be single transportable unit, and able to be lifted or transported without
dismantling any of its components or enclosure.

10. Design & construction of DPS shall primarily need to conform to the requirements of IEC
62271-202. It is acceptable that part of the enclosure of a component becomes part of
substation enclosure. In such case, this part shall comply with the applicable requirements of
both this standard (IEC 62271-202) and relevant product standard of the component.

11. DPS shall withstand climatic & environmental conditions prevailing in the State of Qatar.

12. Internal arc rating of the DPS shall be IAC-AB, 20KA @ 1 sec. Pressure relief system/vent(s)
shall be on the top of enclosure to allow safe passage of gases released in the event of internal
arc inside DPS unit

13. Cooling of DPS unit shall be through natural ventilation. Exhaust fans are not allowed.

14. IP protection Class of DPS enclosure shall be IP23D, with all its ventilation apertures closed
with vermin-proof, non-corrosive metallic screens having not more than 1 mm size apertures.
Even the cable entry ducts at the bottom shall be closed with the vermin-proof screens.

15. ‘Temperature class’ of the enclosure (refer clause 8.2 of IEC 62271-202) shall be class-5. The
manufacturer needs to produce evidence about its compliance to the designated ‘temperature
class’ by conducting heat-run test.

16. 100% utilization of rated capacity mentioned on the name plate of DPS shall be possible
without de-rating the transformer locally. Capacity of the transformer shall be pre-designed in
co-relation with the temperature class of enclosure, and its IP protection class, to ensure no
de-rating of transformer.

17. All type tests as prescribed in latest IEC standards shall be conducted, on representative
sample of essentially same design and ratings, at reputed independent laboratories.

18. Plinth matrix and size of 500KVA, 1000KVA & 1600KVA DPS units shall be same,
implying that position of bottom cable entry ducts, of all these three sizes shall be identical.
However, 315KVA DPS may have different plinth size & matrix.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 7 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
19. Earthing: Main earthing conductor system shall be provided with an earth bar of not less than
40mm by 2.5mm hard drawn high conductivity copper strip. The earth bar shall be bolted to
the main frame so as to provide convenient facilities for earthing all metallic bodies. The
earth bar shall be connected directly to the transformer body, the LV feeder pillar body and
the feeder pillar earth bus-bar, the enclosure of HV switchgear, cable sheaths, and earthing
connections of automatic controls and remote control devices. A suitable connection point
shall be provided for connection of the substation to the earthing rod. Joints shall be brazed,
welded or tinned and bolted to ensure that adequate electrical continuity exists between all
stationary metalwork.

20. All covers, doors and other accessible metallic parts of the enclosure shall be designed to
carry at least 30ADC current from them-selves and to the main earthing point of DPS, with a
voltage drop of maximum 3V. This is a safety requirement.

21. Earth fault blinking device on top of the DPS shall be provided. The specification for the
same is given hereunder at clause 8.3.

22. Restricted earth fault (REF) tripping mechanism shall be provided as per the details given
hereunder at clause 8.4.

23. Name Plate: Each DPS unit shall be provided with durable and clearly legible name plate,
made from metallic plate. It shall contain the following details:

a) Manufacturer’s name
b) Type/model designation
c) KVA rating of DPS
d) Internal arc classification
e) Serial number
f) Month & Year of Manufacture
g) KM tender & Purchase Order number

Note: In addition to this, all main components (Transformer, LV & HV switchgear units)
shall be fitted with individual Rating Plates, in such a manner that they shall be easily visible
from front.
24. Details of main components (Transformer, HV & LV Switchgear) are explained in following
sections.

5.0 TRANSFORMER DETAILS.

5.1 General Design Requirements

1. The transformers shall be hermetically sealed, oil-immersed radiator panel or corrugated type.
Pressure excursions in case of radiator type are absorbed by inert gas (preferably by nitrogen
gas) cushion placed above the oil surface in a sealed-tank system. In case of corrugated fins
type, pressure excursions are to be absorbed by fins movement. Tank shall be filled with
oil without any gas /air.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 8 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
2. Applicable standards: Shall comply with the requirements of IEC 60076, except where
otherwise covered by this specification. Oil shall comply with IEC 60294/Class-II of
BS148. Other applicable standards are shown in the preceding sections.

3. Winding: Winding shall be Oil immersed and made of high conductivity electrolytic
copper. Insulating material of high quality shall be used. 11KV and LV windings shall
be separate.

4. Thermal Insulation: Thermal insulation requirements of the windings shall not be less
than ‘insulation system temperature’ of 1050C (Thermal class-A), IEC 60085

5. HV & LV bushings and Terminations: These shall be mounted on the same side of the
tank (i.e on one side of the transformer), so that access to the substation shall be only via
one side (i.e facilitating front access). Top mounting of bushings on tank cover is not
acceptable. HV & LV Terminations & bushings, and flanges shall comply with BS 2562

6. Rated power: Transformer power capacities shall be 315, 500, 1000 and 1600 kVA.
Design of these ratings shall be arrived after duly taking in to account the de-rating
factors required due to all influencing factors such as special service conditions, DPS
Enclosure thermal class, IP rating and specified temperature rise limits.

7. Magnetic Core: The magnetic core shall be made of high permeability, low loss, non-aging,
grain oriented, cold- rolled silicon steel laminations. Each lamination shall be insulated with
high quality coating without burrs.

i. High grade CRGO steel laminations, having ‘specific watt loss’ of not more than 0.95 w/kg at
1.7T and 50Hz, shall be used. It shall conform to IEC 60404-8-7:2008. Details of actual grade
used, name of manufacturer, country of origin, product catalogue need to be submitted along
with tender offer, or technical submittal for approval against external projects.
ii. All limbs and yokes shall be designed for keeping noise levels, no load losses, and hot spot
temperature in core as low as possible.
iii. Core and its clamping plates shall form in to rigid unit structure, to withstand all stresses
caused by S/C conditions, shipment, transportation, and installation.
iv. Ensure to secure uniformly distributed mechanical pressure over all laminations, to limit noise
& vibrations to minimum level.
v. Complete core assembly shall be provided with suitable lifting eyes to facilitate its removal
from the tank.
8. Parameters of Tank Designs:

i. The under-base of transformers shall be in the form of skids. The skid shall be provided
with 42 mm diameter holes on axle at each end, clear of the jacking position.

ii. All the bolts used in the transformers for mounting/fixing tank cover, Cable box mounting
flanges, bushings, radiators, etc, shall have consistency in its size & length, and the fixing
shall be such that, at least 2 or 3 threads of the bolt shall come out of nut outer face.

iii. All the nuts & bolts used for fixing HV & LV bushing Clamps, shall be accessible from
outside the tank for easy opening or tightening. They should be accessible without opening
the top tank cover.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 9 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
iv. All welds are required to be tested for oil tightness. Oil pressure test to be conducted on
each transformer, at least at a pressure of not less than 0.3bar for a period of 16 hours to
verify effectiveness of all welded joints and gaskets against oil leaks. The test results are to
be included in the routine test reports being submitted.

v. The welding work need to be carried out through automated or robotic welding process to
ensure consistency in quality of welding

9. Tap changer:

i) The tap changer design & its performance shall generally conform to IEC 60214-1

ii) Tap changing shall be carried out with the transformer off circuit, by means of an
externally operated self-positioning tapping switch, which shall be mounted on one
end of the transformer tank. . The moving contacts shall be spring loaded, self-
aligning roller type. The tap changer selector switch shall be easily accessible to the
operator from convenient height from floor/ground.

iii) Switch position No. 1 shall correspond to the maximum plus tapping. Provision
shall be made for locking of the tapping switch handle at any position, such means
incorporating a hole for accommodating a padlock having a 7mm diameter shackle.
The switch shall be retained in a safe position if a padlock with a 7mm diameter
shackle is used.

iv) The tap-changer assembly shall be of a robust construction and shall be capable of
carrying the same current as the windings when under conditions of short circuit.
Current ratings of contacts used in tap changers shall not be less than 63 amps for
1000KVA, 1250KVA & 1600KVA transformers, and not less than 30 amps for
500KVA, 800KVA transformers.

v) Numerical digits need to be used as indication of the tap positions, shall be embossed
or engraved permanently on the knob.

vi) Tap changer shall be of high quality product; type tested according to the
requirements of IEC 60214-1, and shall be sourced from internationally reputed
manufacturers only.

10. Tank: Hermetically sealed type tank with bolted and gasketted top cover, and so
designed that there is no deformation of the unit when lifted with oil, and with the ring
main unit and feeder pillar attached. The thickness of the side walls shall not be less than
5mm, and the top and bottom not less than 4.5mm. Radiators shall be of the panel type
or corrugated fins type. In case of corrugated fins, fins wall thickness shall be 1.5 ±0.1
mm. All welds are required to be tested for oil tightness.

11. Gaskets: All Gaskets (both nitrile rubber and rubberized cork) shall be heat and oil-
resistant, and do not contain any joints. They shall be of one piece construction only.
Rubberized cork sheets shall be 5mm thick (un-compressed). Nitrile rubber seals and o-
rings shall be placed in suitable grooves, in order not to slip from their positions, when
tightened. Hemp material or neoprene gaskets are not acceptable.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 10 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
12. Terminal Markings: Terminals shall be identified by characters of a type, which cannot
be obliterated, marked on plates of durable and non-corrodible metal securely fastened
to the tank. High Voltage terminals shall be marked as (left to right): A.B.C., and Low
voltage terminals shall be marked as (left to right): c,b,a,n.

13. Oil: Mineral oil shall meet the requirements of BS 148/IEC 60296.

5.2 Ratings & Characteristics

a) Rated Power : 315/500/1000/1600KVA (as explained above)


b) Type of Cooling : ONAN-Outdoor application (in side enclosure)
c) Voltage ratio : 11,000/433V
d) No. Of phases : 3-Phase
e) Connections : Delta-Star, as per vector group –Dyn11
f) Rated frequency : 50HZ
g) Thermal Insulation of winding : Not less than Class-A (1050C)
h) Maximum Flux density : ≤ 1.6 Tesla at normal voltage & frequency
i) Taping range & steps : +5% to -5%, in 4-steps each of 2.5%
j) Rated insulation levels:
Parameter Name HV Side LV Side
Rated Voltage (U) 11KV 433/250V(at no load)
Rated Highest Withstand Voltage (Um) 12KV 1.1KV
Rated Lightning impulse withstand (peak) 75KV -
Rated power frequency withstand voltage 28KV 3KV

k) Guaranteed values of load & no-load losses, and percentage impedance, measured at
principal tap and corrected to reference temperature of 750C.

KVA Rating Max. No-Load Losses Max. Load-Losses % impedance


(watts) (watts)
315 565 6,700 4.00±10%
500 900 7,200 4.75±10%
1000 1350 10,600 5.45±10%
1600 1875 15,300 6.00±10%

5.3 Transformer Operating Conditions & Temperature rise limits

a) Temperature class of the DPS enclosure……………………………………………class-5


b) Average Ambient Temperature outside the DPS unit………………………………30°C
c) Maximum ambient Temperature out side the DPS unit…………………………….500C
d) Maximum top oil temperature rise above Ambient for continuous rated load……. 40°K
e) Maximum average winding temp. rise, above Ambient for rated continuous load...45°K

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 11 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
f) Maximum hot spot temperature for Continuous rated load………………………...98°C
g) Oil temperature shall not exceed 105°C under any conditions.
h) Hot spot temperature shall not exceed 118°C under any conditions.
Note: In the event, the DPS enclosure is designed for class-10 enclosure, top oil temperature
rise and winding temperature rise shall be 35 0 k and 40 0 k respectively.

5.4 Fittings & Accessories

The following fittings & Accessories are required:

a) Sealed filler boss: The design shall be such that water cannot collect in the vicinity of the
boss.

b) Lifting fittings: These shall be provided suitable for lifting the whole unit without the
housing, by crane and chains. Fittings shall be so located that DPS can be fitted without
tilting. Lifting fittings shall be fitted to the sides of the tank not the top.

c) Jacking lugs: Four to be fitted, one of each corner of the tank at 400+5mm above ground
level.

d) Skids: Designed to support the unit and attached switchgear as necessary. Skids shall
have four 42mm diameter axle holes.

e) Drain Valve and Sampling Device


Transformer shall be equipped with drain and filler valves. The nominal size of drain
valve shall be 1 inch. Good quality, non-corrosive, gate valve type, hand wheel operated
valves to be used for this purpose. There shall be separate outlets for oil draining and
sampling on the same device. The sampling outlet shall be smaller in size and at right
angle direction to the main drain outlet. The valve handles should have locking
arrangement. This device shall facilitate filling, draining, sampling, and venting of oil.
The location of the drain valve cum sampling device shall be so selected that it is easily
accessible, and its operation shall not be hindered by any other component installed on
transformer.

f) Earthing terminal: A stainless steel earthing flag, approximately 60 sq. mm surface area,
and not less than 6mm thick as shown in Drawing STD-EQP-64. A central hole, 14mm
diameter shall be included. It shall be provided on front side of operator access.

g) Prismatic oil gauge: This will provide indication of the oil levels over the full range of
normal temperature excursions. It will be calibrated to show the normal oil level at 35°C.
Markings for the maximum and minimum oil levels should be clearly marked on the
instrument. [Note: Instruments with colour code indications are not acceptable.]

h) Oil temperature indicator with alarm contacts: A dial type thermometer to indicate the
temperature of the oil at the top of the tank needs to be provided. It’s scale shall be
graduated in degrees Centigrade and cover the range of 20°C to 120°C with increment
marks at not more than 5°C intervals and following features.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 12 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
i) The dial shall be fitted with pointers to indicate the present oil temperature, and its
maximum value. The maximum temperature pointer, alarm & trip contacts shall be
manually re-settable type from the front. Alarm contacts (2NO+1NC or 2C/O) rated
@ 10A, 240VAC, for maximum setting, shall be incorporated.
ii) The IP protection of alarm contacts and cable entry gland shall be IP67.
iii) A permanent wiring, with suitably rated cable, to be made to the junction box
mounted on side walls of transformer tank, through rain tight conduit & conduit
fittings. Cable/conduit entry to the thermometer alarm contacts shall be from bottom.
iv) The winding oil temperature alarm & trip values shall be pre-set at 95 oC and 105 0C
respectively, by default.
v) The Standard thermometer size as described below shall be used.

Nominal dial size: Approx 100mm


Sensing element type Bimetallic, stem type
Bezel & Casing material: Stainless steel (SS-316)
Dial & Pointer: Black pointer on white dial
Maximum Pointer Red Pointer
Measuring Range: 20-140 oC.
Connection type: Radial bottom
Stem size & material: 120mm(L)x12mm(D), stainless steel.
Process Connection: G½ inch male nut, stainless steel fitting.
Thermometer pocket(thermo-well): Welded to tank, W/matching thread.
O-Ring suitable size of O ring shall be used.

i) Additional Thermometer Pocket


An additional thermometer pocket (thermo-well without thermometer) of same size shall
be fitted in the tank, for the purpose of routine testing & measuring with portable
instruments. The thermo-well opening shall be closed with matching cap/plug.

j) Pressure relief valve: With a fixed pressure setting, assigned by the manufacturer to
permit pressure relief when the transformer is subject to abnormal operating conditions,
or an internal fault.
The device shall be equipped with two re-settable auxiliary switches (which may have a
common pole), one of which is normally open, the other normally closed. Operation of
the switches shall coincide with operation of the pressure relief device.
The pressure relief valve shall also be fitted with 2 re-settable auxiliary switches, one
normally open, the other normally closed. Operation of the switches shall coincide with
operation of the pressure relief valve. The limit switch containing these auxiliary switches
shall be totally concealed under the PRV outer cover, or a separate shade/cover shall be
provided over the limit-switch to protect it from the external environment and rain. The
limit switch body & gland/conduit fitting shall be conforming to IP67 requirements.
A permanent wiring from the limit-switch contacts to be made, with suitably rated cable,
to the junction box mounted on side walls of transformer tank, through rain tight conduit
& conduit fittings. Cable/conduit entry to the limit-switch shall be from the bottom.

The device shall also be fitted with a prominent indicator, which shall remain in place
after an operation of the device. The indicator shall be readily visible from the front of the

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 13 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
substation. Any cable entry holes meant for wiring auxiliary switch unit shall be closed
with temporary plugs.
k) Junction Box (for control wiring)
A suitable junction box (control box) made of sheet steel body with protective covering
and painting, shall be fixed on suitable side wall of tank. It shall be fitted with suitably
rated terminal strip, cable gland/conduit fittings, front hinged door and gaskets, etc. The
location of the junction box is such that it facilities easy access to its connections. The
box shall not hinder functions of any transformer operations or other components. IP
rating of the box shall not be less than IP65.

Two inlet and two outlet electrical cable entries shall be provided to the box through rain-
tight conduit fittings. All cable/conduit entries shall be from bottom only. Inlet
connections shall be wired from thermometer alarm contacts, and PRV limit switch
through conduits. Outgoing terminal connections shall be left free, to make connections
during installation. The outgoing cable/conduit entry holes shall be closed individually
with suitable caps/plugs. A permanent label showing terminal wiring diagram, terminal
markings, functions of all terminal connections, shall be fixed inside the front door of the
junction box. The front door shall have provision for fixing KM standard pad-lock having
7mm shackle.

l) Pressure Gauge with Isolating Valve (Applicable for Radiator type Transformers)

A pressure gauge capable of measuring negative and positive pressures of nitrogen gas
inside the tank, over the atmospheric pressure, shall be fitted on the inlet oil pipe line of
each transformer. The pressure gauge shall be along with an isolating valve as a
combination, capable of isolating the gauge in normal conditions, and measure gas
pressure only when required. Suitable manifold, if required, to be used at the Oil inlet
valve, to accommodate this ‘pressure gauge + isolating valve’ combination.

Suitable gaskets/seals/O-rings, shall be used at all joints of the fittings to ensure no gas
leaks during their service life. There should not be any joints or openings in the gaskets
used.

The gauge nominal diameter shall not be less than 100mm. The bezel & casing of the
gauge, isolating valve, and their fittings shall be made of stainless steel (SS316). The dial
of the gauge shall have linier graduated scale; with centre zero reading, covering required
measuring ranges on both negative and positive pressures.

An additional pressure gauge (‘Master gauge’) is to be supplied, free of cost, as an


accessory, for every 100 transformers supplied.

m)Connection plate: A connection plate shall be provided which shall give full details of tap
positions and winding connections as per vector group diagram. The sequence of
terminals shall be as per enclosed drawings.

n) Rating Plate: The rating plate shall be made of metal and shall be durable in the arduous
climate encountered in Qatar. It shall be fitted to the front of the unit. It shall contain the
following information as per STD-EQP-63.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 14 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
Manufacturer’s Name
Specification Number
KM Tender number
Manufacturer’s serial Number
Month & Year of Manufacture
Rated Power
Rated Frequency
Rated Voltage
Rated Currents
Connection Symbol
Impedance voltage at rated current at 75°C
Type of cooling
Total mass of the unit with oil, with and without RMU & feeder pillar
Mass of insulating oil
Temperature rise
Insulation level

5.5 Corrosion protection & Paint Work


1) The definitive guideline document is BS EN ISO 12944 Parts #1 to 8, & BS EN ISO 14713.

2) The atmospheric corrosive category of local environmental conditional is considered to be


close to C5-M (as per ISO 12944-2), and it is imperative for the manufacturer to provide a
painting system suitable for this classification.

3) It is the responsibility of the manufacturer to select suitable paint system, in accordance with
above referred standards withstanding the specified local climatic & environmental
conditions, and to give a service life of at least 15+ years.

4) The selection of surface preparation processes, protective paint systems, execution and
supervision of paint work shall be made in accordance with the requirements specified above.

5) The exact Specification & procedure of surface preparation and painting system followed by
the manufacturer shall be submitted at time of tender. The manufacturer shall clearly justify
the selected paint system meeting above mentioned requirements (Refer tables of BS EN
ISO 12944 and BS EN ISO 14713)

6) The final coat on the exterior shall be Dark Admiralty Grey, Colour conforming to 632 of BS
381C, or a near equivalent.

7) The manufacturer should possess required testing equipment in their laboratory to test the
paint work in accordance with BS EN ISO 12944-6. These test reports should be submitted
along with each consignment of delivery.

8) KM Engineers shall have the option of witnessing the tests on painting work, before delivery
of each consignment.

The manufacturer may offer an alternative, provided that it is of no less quality than the
above. The colour is mandatory.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 15 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

5.6 Transformer Tests

Type Tests
1. Temperature rise test(IEC 60076-2)
2. Dielectric type tests (IEC 60076-3)

Special Tests
1. Dielectric special tests
2. Short circuit withstand test
3. Determination of sound levels
4. Measurement of insulation resistance to earth of windings
5. Measurement of dissipation factor (tan delta) of the insulation system capacitance

Routine Tests on Transformer


1. Measurement of winding resistance
2. Measurement of voltage ratio and check of phase displacement.
3. Measurement of short-circuit impedance and load losses
4. Measurement of no-load loss and current
5. Separate source AC withstand voltage test
6. Short duration induced AC withstand voltage test.
7. Main tank Oil pressure test at 0.3 bar for 16 hrs on each transformer.
8. Oil Breakdown voltage test (BDV) and oil acidity test.

A. TESTS ON PAINTING WORK

1) Measurement of thickness of protective coating (ISO 2808)


2) Specular gloss factor at 60 deg (ISO 2813): 90±5%
3) Falling weight test (ISO 6272): 1kg/50cm
4) Cross cut test (ISO 2409): classification: 0
5) Cupping test (ISO 1520): 08mm
6) Bending test – Cylindrical mandrel test (ISO 1519): 3.0mm
7) Salt spray (fog) test (ISO 7253): 1000hrs

Tests on accessories
1. All type tests to be carried out on off load tap changer, as per IEC 60214-1

6.0 THE RING MAIN UNIT(NON-EXTENSIBLE)

6.1 General Design & Constructional Features

Scope
1. The RMU comprises two ring switches (for feeder control) and one circuit breaker (for
transformer control) as integral parts, all stored in a single common SF6 tank. The arc
interruption medium shall be SF6 or vacuum. The insulation medium with in the tank
shall be SF6. The vacuum bottles used should be from Europe, North American or Japan.
0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 16 of 46
ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
Compliance standards & Function
2. RMU shall generally conform to the requirements of IEC 62271-200, IEC 62271-1, IEC
62271-100. RMU will control DPS on 11KV side

Housing, body, components & materials


3. The switchgear shall be fully insulated and enclosed, including incoming and outgoing
cable boxes. No exposure to live parts. Its housing shall be made of galvanized steel with
highly durable protective coating & painting. All bus-bars shall be made of high purity
electrolytic copper with electro-tin plating.

4. All materials used, as far as possible, shall be non-hygroscopic, non-flammable. All


insulating materials shall have highest resistance to tracking.

5. All gaskets shall be of superior quality having long life, and capable of withstanding
sever climatic and operating conditions.

6. Steel pockets shall be provided on the inner walls of each door for keeping drawings and
operating instructions.

Gas pressure system


7. Gas tightness of the SF6 chamber shall conform to ‘sealed pressure system’ as defined in
clause 5-15-3 of IEC 62271-1. Expected operating life of ‘sealed pressure system’ shall
not be less than 20 years, and the leakage rate shall not be more than 0.1% per year. No
filing of gas required during its life time.

8. Facility to monitor the SF6 gas pressure shall be made available through gauge. The
gauge shall be able to be replaced, when required, without interfering with gas medium.
The gauge dial shall have graduated scale for indicating actual pressure, and colour
coding to indicate operating and non-operating zones. Gauge shall be fitted with alarm
contacts, as an integral part, to facilitate remote indication of low pressure.

9. The SF6 gas container shall be designed with automatic pressure relief in case of pressure
build up due to internal arcing.

Mounting & Connections


10. The RMU shall be directly mounted to transformer through flange connections,
conforming to Flange-E of BS 2562 with suitable steel trunkings. Electrical connections
(of CB unit) are made through bus-bars, without cable connections. However, RMU
bottom frame work shall be bolted to the DPS base frame.

Operation & Switching requirements


11. The C/B is capable of making and/or breaking rated short circuit currents specified. The
ring switches are fault-making and load-breaking type. Each ring switch and C/B shall
have 3 operating positions: ON, OFF, and EARTH.

12. RMU CB is ‘independent manually operated’ with the help of operating handle, through
spring assisted mechanism. Its closing operation sequence shall be ‘TRIP/OFF-RESET-
ON’. CB opening shall be possible through a) manual ‘TRIP’ button, b) ‘SHUNT-TRIP’
coil, and c) C/C & E/F trip coils of protection circuit.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 17 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
13. RMU Ring switches shall be capable of operated both manually & electrically. Manual
operation is done with the help of operating handle, capable of ‘independent manual
operated’ spring assisted mechanism. Electrical operation is accomplished through linear
motor actuators, operated from external power source (supply voltage 24VDC), fitted to
the ring-switches. Mounting of electric motor actuators on ring switches shall not become
hindrance to their manual operation.

14. Two cam operated selector switches shall be fitted on front of each ring-switch panel to
select ‘LOCAL-OFF-REMOTE’, and ‘OPEN-OFF-CLOSE’ of electrical operation.
These switches shall have pad-locking facility. Selector switch for ‘LOCAL-OFF-
REMOTE’ shall have stay put action, selector switch for ‘OPEN-OFF-CLOSE’ shall
have momentary action.

15. All operations shall be possible from front of the unit. Mimic and position indicators
(mechanical type) shall be provided for operator guidance. Required interlocks need to be
provided, with padlocking facilities, to prohibit unintended operations

16. The switchgear unit shall be fitted with operations counter.

17. If the switching operation is not successful, its mechanism should not get stuck-up in
intermediate position. The mechanism should automatically come back to OFF position.
The mechanism should never get stopped in intermediate position.

Protection, and control


18. The RMU CB unit shall be equipped with O/C and E/F protection unit (for transformer
protection), using CT operated (self energising type) trip coils with provision for using
TLF fuse links. The protection circuit shall include 3-trip coils and one additional trip coil
for REF (if required) out of which one shall be dedicated to earth-fault protection. The
trip coil for REF shall be connected to terminals in the control compartment. The
protection system shall provide correct discrimination with BS: 88 J-type fuses used on
LV side.

19. The CT ratio for the protection circuit shall be 100/50/5A (dual ratio)

20. The unit shall be provided, on front of the panel, with ‘TLF fuse link port/compartment’
for easy replacement of fuses, and a CT ratio adjustable ‘port/compartment’ with shorting
links for easy adjustment of CT ratio depending up on the transformer capacity

21. The C/B shall be equipped with 30VDC/240VAC (dual rating) shunt trip coil. There shall
be a provision to connect alarm contacts of transformers temperature indicator, auxiliary
contacts of transformer PRV in the shunt trip circuit, through inter-trip facility.

22. A chart showing details of TLF fuse-link ratings, corresponding to each CT ratio verses
different KVA ratings of transformer, shall be fixed on front of the panel.

23. A Circuit diagram for control shall be fixed permanently on the non removable part of the
control compartment.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 18 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
Integral Cable Testing Facilities.
24. All test access shall be possible from front. Each ring switch, as well as transformer
control unit (CB) shall be provided with integral facilities, which enable the testing of
connected apparatus.
25. It should be possible to make testing of the cable without disconnection. The bushings
shall be built in and no portable equipment shall be required.

The testing facilities shall be insulated to withstand 50kV D.C. between phases with the
mid-point earthed and 32.5 kV D.C. to earth for 1 minute and shall be capable of carrying
200A continuously.

The contact resistance measured from the terminals for connection of the main outgoing
cables shall not be greater than 500 microhm.

26. Test access covers shall be provided with padlocking facilities. Screws or nuts used for
securing such covers shall be captive and have hexagonal faces for tightening only with a
spanner. They shall not be slotted. Test access covers shall be fitted with seals to prevent
ingress of water and dust

Capacitive Voltage Detectors, Neon lamp indicators & Phase comparators


27. Each ring switch shall be equipped with Capacitive Voltage detective system with
capacitor coupling electrodes conforming to IEC 61243-5, neon indicators (glow
discharge lamps) for ‘LIVE’ phase indication, and standard sockets for 11 kV phase
comparison between ring switches. The glow discharge lamps are to be located on the
front of the panel.
28. The test jacks (probes) of portable Phase comparator instrument shall match with test
sockets mentioned above.
29. One portable Phase comparator set complete with all accessories and carrying case, are
required to be supplied with every 10 numbers of DPS units.

Earth-Fault Indicator
30. One-through-earth fault indicator with core-balance type CT, shall be installed on left-
hand side ring-switch of each RMU. Its flag shall be mechanical type. The unit shall
function without integral battery power. Both auto & manual resetting options shall be
available for the unit. Provision for auto resetting through 240Vac auxiliary supply
(external source) shall also be made available.

31. Earth-Fault Indicator (EFI) unit shall be complete with all accessories including relay
unit, ZCT, connecting cables, full technical information concerning its functioning,
method of connections with CT location, instruction manual, etc.

32. The EFI unit shall be automation compatible, and have provision for remote indication,
and remote resetting facility.

33. EFI relay unit shall have IP65 rated housing, and capable of withstanding the prevailing
ambient conditions.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 19 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
Cable boxes
34. All cable entries shall be from bottom, and the cable boxes are to be fitted with un-
insulated brass wiping gland of suitable size. All Cable terminals shall be positioned not
less than 800mm above ground level. A clearance of not less than 650mm shall be
provided between bottom gland support plate and cable bushings.

35. Cable boxes of ring switches shall be suitable for terminating cables up to 3Cx300sq.mm
copper conductor, XLPE insulated, SWA cables conforming to IEC 60502.

36. All cable boxes shall be fitted with insulated brass wiping glands with armour clamp,
conforming to ‘size-Y, as per BS: 2562 figure 32. Each cable gland shall be fitted with
full fault rated copper earthing braid and connected to equipment earth.

37. The cable termination shall be so arranged that any externally mounted CT, for earth-fault
indication purpose, shall have sufficient clearance for easy connection.

38. Suitably rated and type tested insulated bushings with required creepage distances and
anti-tracking properties shall be mounted for cable connection with adequate clearances.
The connecting terminals on bushings shall be integral male stud type with nuts, and
suitable for installing heat-shrink type terminations with right angled boots.

39. Cable boxes will be designed to permit ventilation, but such openings shall have
protection to not less than IP54. Provision shall also be made to prevent a build up of
water within the box such as may arise from heat cycling and condensation.

40. Phasing of all primary terminals shall be positively marked on the main structure and not
on removable covers. The phasing shall be marked by characters of a type which cannot
easily be obliterated

Remote monitoring & Control


41. Each ring switch and CB unit need to be suitably wired to handle outgoing/incoming
signals of position indications, alarms, commands, and 24VDC auxiliary power lines
from future RTUs. They shall include but not limited to below mentioned details.
Type of Control Control Detail From To
Status Indications ON, OFF, EARTH Ring switches RTU
Status Indications ON, OFF Earth Switch RTU
Status Indications MAIN ON, OFF Circuit Breaker RTU
Alarm SHUNT TRIP Circuit Breaker RTU
Alarm O/C & E/F TRIP Circuit Breaker RTU
Status Indications ON C/B Earth Position Selected RTU
Alarm LOW GAS SF6 gauges RTU
Status Indications FAULT/RESET Earth fault relays RTU
Command CLOSE/OPEN RTU Motor Actuator
Alarm Trip REF RTU

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 20 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
42. A dedicated terminal box prewired with all outputs from auxiliary switches, limit
switches other sensors (if any), all meant for remote monitoring & control of the unit,
shall be mounted on the switchgear unit. All terminals shall be clearly marked with proper
identifications. A wiring diagram indelibly printed with all details of incoming/outgoing
terminals, on water-proof medium, shall be permanently fixed inside the box cover.

Pad Locking facilities


43. All covers, doors, operating mechanisms/handles, mechanical interlocks, selector
switches, shall have facilities, as specified, for pad-locking.

44. Wherever padlocking facilities are specified, it shall be possible to fit a padlock having
the following description:

Pad lock: Body Height = 33.5 + 1mm


Body Width = 34 + 1mm
Body Thickness = 15.5 + 1mm
Shackle Diameter = 5mm
The receiving hole for the padlock shackle = 8mm in diameter
For operational locks: When closed the shackle should accommodate a bar of up
to 19mm diameter.
For Safety locks: When closed should have a minimum clearance dimension to
accommodate an elliptical bar having a major axis of 30mm and a minor axis of
19mm.

Circuit Labels
45. Each switch shall be provided with a circuit label size 150mm x 50mm secured to the
front of the equipment by four non-rusting screws. In addition each cable box shall have
affixed in close proximity to it a label for the purpose of circuit identification. These
labels shall be easily removable for engraving. Circuit labels shall not be positioned on
movable covers and must be close to the control point to which they refer. All circuit
labels shall be inscribed with black letters on a white background; they shall be suitable
for outdoor use and must have non-fading properties.

6.2 Ratings & Characteristics

1. IP & IK Protection:
IP protection of Enclosure, Cable boxes, remote control box shall be at-least IP54
IK protection of Enclosure, Cable boxes, remote control box shall be at-least IK08 (5J)

2. Internal arc Protection


RMU shall be so designed and tested that an internal arc inside the tank shall not result in
risk of injury to an operator. The protection against internal arc shall at least conform to
the classification IAC-AF, 20KA for 1 sec. as per IEC 62271-200. Type test report issued
from reputed independent laboratory need to be submitted.

3. Electrical Ratings - General:

Frequency.............................................................................. 50 Hz
0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 21 of 46
ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
No. of Phases......................................................................... 3
Nominal Voltage.....................................................................11kV
Maximum Voltage..................................................................12kV
Rated Voltage........................................................................ 12kV
Rated Impulse withstand voltage Level................................75kV (1.2/50)
Rated short duration power frequency withstand voltage......28kA

4. Electrical Ratings - Ring Switches


Rated normal current of Bus-bar.............................................630A
Rated short-time withstand current of bus-bars......................20kA, 3 seconds
Rated peak withstand current of bus-bars...............................50kA
Rated nominal current (switch to feeder)................................630A
Rated breaking capacity, feeder switch...................................630A
Rated short-time withstand current, feeder switch.................20kA, 3 seconds
Rated peak withstand current, feeder switch..........................50kA
Rated short circuit making current, feeder switch...................50kA (Peak)

Circuit Breakers
Rated normal current, Bus-bar................................................630A
Rated short-time withstand current of bus-bars......................20kA, 3 seconds
Rated nominal current, CB......................................................200A
Rated breaking capacity, CB...................................................20kA
Rated short-time withstand current, CB.................................20kA, 3 seconds
Rated peak withstand current, CB..........................................50kA
Rated short circuit making current, CB...................................50kA (peak)

Earth switches
Rated short time withstand current, earth switch....................20kA 3 seconds
Rated peak withstand current, earth switch............................50kA
Rated short circuit making capacity, earth switch...................50kA (peak)

6.3 Operational Features

1. Operations

Ring switches shall incorporate a switch or switches which enable the outgoing feeder to
be: ON - connected to the bus-bars : OFF - isolated in the tank: or EARTHED -
connected to the earthing system of the switchgear.

The circuit breaker shall incorporate a manually operated switch between the bus-bars
and the circuit breaker. This switch shall be capable of being operated between the ON
position (bus-bar connected to circuit breaker), or the EARTH position (transformer HV
winding connected to earth). It shall not be possible to operate this isolator switch unless
the circuit breaker is in the OFF position.

All the switches shall be of the independent manual type i.e. a stored energy operation
where the energy originates from manual power, is stored and released in one continuous
operation, such that the speed and force of the operation are independent of the action of
the operator. It shall not be possible for the operating mechanism(s) to be left in such a
0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 22 of 46
ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
condition that any energy stored in the initial part of the operation remains in the spring
when the switch is in the 'ON', 'OFF', and 'EARTH ON' positions. In addition movement
of an operating handle against an interlock shall not charge any spring to any significant
extent.

Lockable storage facilities shall be provided for removable operating handles in a position
readily accessible from the front of the equipment.

It shall be possible to lock the operating mechanism(s) in any operating position and
independently to lock off the 'ON', 'OFF', and 'EARTH ON' positions. In addition it shall
be necessary, before it is possible to operate from 'OFF' to 'EARTH ON' to move a
captive device which can be padlocked and which shall be labelled 'MOVE BEFORE
EARTHING'. The same device must prevent operation from 'EARTH OFF' to 'ON' until
the device is removed.

Mechanical indication of the operating positions of the switches and circuit breaker shall
be provided.

The indicators shall be positively driven in both directions so as to show whether the
switch circuit breaker contacts are in the ON, OFF or EARTH ON positions. The
positions shall be clearly indicated and the indicators shall be inscribed.

Status Letters Background


ON White Red
OFF White Green
EARTH Black Yellow
ON

The height of the letters shall be approximately 10mm. Indication of only one of these
three positions shall be visible at any one time.

The direction of movement of any operating handle to attain any position shall be readily
apparent. A label for this purpose shall be provided on the fixed portion positioned close
to the midpoint of the operating stroke and shall incorporate arrows to indicate the
direction of movement to achieve the final handle position of the selected operation.

It shall not be possible to operate a non fault breaking switch from ON to OFF, or an
earth switch from EARTH ON to EARTH OFF for a minimum period of three seconds
subsequent to achievement of the ON or EARTH ON positions respectively. The
detachable handle concept considered adequate for this purpose.

2. Interlocks

Interlocks shall be mechanical, positively driven and clearly labelled. They shall be robust
and designed and manufactured to minimise the possibility of malfunction.

They shall prevent the following operations:

a) When testing entails the removal of an integral earth connection from built in
bushings, by the action of opening the access cover:

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 23 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

For Ring Switches:

i) The opening of the test access when the switch equipment is in any other than the
EARTH position.
ii) Movement from EARTH ON position with the test access open.

For circuit breaker transformer control:

i) Movement of the off, load selector from ON to EARTH ON, or from EARTH ON
to ON with the circuit breaker closed.
ii) Movement of the off load isolator from EARTH ON to ON with the test access
open.
iii) Opening of the access cover with the off-load selector not set to EARTH ON
position.

b) For Ring Switches:


The operation from ON to OFF or an earth switch from EARTH ON to EARTH OFF
for a minimum period of three seconds subsequent to achievement of the ON or
EARTH ON positions respectively. In addition it shall be necessary, before it is
possible to operate from OFF to EARTH ON to move a captive device which can be
padlocked and which shall be labelled MOVE BEFORE EARTHING. The same
device must present operation from EARTH OFF to ON until the device is removed.

6.4 Combined Rating and Data Plate


The rating plate shall be made of metal and shall be durable in the arduous climate
encountered in Qatar. It shall be fitted to the front of the unit. It shall contain the
following information:

a) Manufacturers Name and Address


b) Type/Model Reference of RMU
c) Serial No.
d) Month & Year of Manufacture
e) KM Tender number
f) Rated Voltage (Ur)
g) Rated short duration power frequency withstand voltage (Ud)
h) Rated lightning impulse withstand voltage (Up)
i) Rated frequency (fr)
j) Rated normal current (Ir), at ambient conditions – of CB unit/Ring switch/bus-bar
k) System Highest Voltage (Um)
l) Rated short time withstand current(Ik), at 3 Second duration – of CB/Feeder
switch/bus-bar/Earth switch
m) Rated Peak withstand current (Ip)-of CB/Feeder switch/bus-bar/Earth switch
n) Testing Standard

6.5 Cleaning & Painting

The following represents the minimum acceptable quality:

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 24 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

All ferrous external surfaces shall be cleaned of scale and rust by shot blasting and shall
then be treated on the same day, without outdoor exposure with a zinc spray. The zinc
shall be applied by the flame gun process to thickness ZN4, in accordance with BS EN
22063 : 1994.

External surfaces shall be taken to refer to all surfaces outside weatherproof gasketed
joints whether or not they are exposed to sun or rain.

The final coat of paint on all exterior surfaces shall be Dark Admiralty Grey matt finish
colour 632 of BS 381C.

The manufacturer may offer his own recommendations for the paint finish, but if so, these
details shall be provided at the time of tender. The colour is mandatory.

6.6 Tests

Type Tests:

Representative sample of RMU shall be type tested in reputed independent testing laboratory
in accordance with relevant latest IEC standards, including but not limited to IEC 60060,
60265, 62271-100, 62271-200, and 60420. Copies of valid type test reports shall be
submitted for verification.

1. Verification of Insulation Levels through:


-
Lighting Impulse withstand voltage test
-
Power frequency voltage withstand test
-
Partial discharge tests
2. Temperature Rise Tests:
3. Measurement of resistance of main circuit
4. Short time current withstand and peak withstand current
5. Verification of breaking and making capacities
6. Mechanical Operating test
7. Gas tightness test
8. Verification of Degree of protection
9. Arcing due to internal fault
10. Type testing of insulated bushings

Routine Tests:

The following tests shall be performed, on each unit of the switchgear (100% quantity).

1. Power frequency voltage on the main circuit.


2. Dielectric tests on auxiliary and control circuits.
3. Measurement of Resistance of the main circuit.
4. Verification of protection against electrical shock (Electrical continuity of earthed
metallic parts)
5. Mechanical operating tests.
6. Functional tests
7. Tests on auxiliary devices.
0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 25 of 46
ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
8. Verification of correct wiring
9. Gas tightness test
10. Check of interlocks
11. Partial discharge measurements
12. Design & visual checks

7.0 THE LOW VOLTAGE DISTRIBUTION BOARD (FEEDER PILLAR)

7.1 General Design & Constructional Features


1. The substation distribution board (also known as ‘FEEDER PILLAR’-FP) is an
assembly, made of sheet steel enclosure, for direct connection to distribution transformer
(without intervening cable), consisting of incoming circuits (switch-disconnector),
outgoing functional units, instrument panel, secondary wiring & accessories. Incomer
unit is connected via bus-bars to outgoing functional units (fuse disconnectors) so as to
provide protection for, and means of isolating and controlling, the outgoing circuits.

2. The design & construction shall generally conform to the latest versions of IEC 60439-1
and IEC 60439-5, and Technical specification # 37-2 of Energy Network Association.

3. The feeder pillars shall be designed to take up the following arrangements:

Type A: 2500 A Busbars


2500 A incoming transformer unit:

Nominal size of cables up to 800 sq.mm.


Six 630A outgoing distribution units.
Instrument panel.

The framework shall be arranged to accommodate the equipment in the following order reading
from the front, left to right :

Distributor units
Transformer unit
Instrument panel

Type B: 2500 A Busbars


2 x 2500 A incoming transformer units:

Nominal size of cables up to 800 sq.mm.


Four 630 A outgoing distribution units.
Two Instrument panels.

The framework shall be so arranged to accommodate the equipment in the following order
reading from the front, left to right :

Instrument panel
Transformer unit
Distributor units
Transformer unit
Instrument panel

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 26 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

4. The FP shall be constructed only of materials capable of withstanding the mechanical,


electrical and thermal stresses as well as the effects of humidity which are likely to be
encountered in normal service. The insulating materials used for barriers, and other
insulating parts shall have resistance to thermal stress and flame retardant properties in
accordance with clause 8.2.102 of IEC 60439-5.

5. Protection against corrosion shall be ensured by the use of suitable materials or by the
application of equivalent protective coatings to the exposed surface, taking into account
of the intended conditions of use and maintenance. The materials of coating shall pass
the appropriate tests of clause 8.2.103 of IEC 60439-5.

6. The shell of the FP shall be robust construction, and manufactured from sheet steel. Its
mechanical properties shall comply with the requirements specified under clause 8.2.101
of IEC 60439-5.

7. IP protection of FP enclosure shall not be less than be IP 41 in closed door condition.


However, adequate ventilation shall be provided to permit natural circulation of air. The
ventilation apertures shall be covered with corrosion-proof metallic screens to prevent
entry of vermin and other foreign bodies.

8. Access to the front of the FP cabinet is to be via a double door, fitted with a locking bar
to secure them top and bottom. The locking bar shall be operated by a single robust
handle which shall be arranged to permit locking by a padlock with a 52 x 49mm body,
8.5mm diameter shackle, having a clear inside width of 29mm and inside length of 41 to
55mm. The holes provided for the shackle shall be not less than 10mm diameter. A
heavy duty lamp with shall be provided in the feeder pillar with limit switch interlocked
with door open/close.

9. The FP cabinet shall be designed to ensure that adequate clearances shall be provided to
permit closing & locking of main doors, even when the incoming transformer circuit
isolator’s blades are fully left in an open or closed position, and pad locked with its
protection cover.

10. The front apron plate, along with any associated structural members, at cable entry point
of the cabinet, shall be removable type to facilitate easy installation or reshuffling of
outgoing units cables. Rear access to the cabinet shall not be provided.

11. Provision shall be made for supporting the lower half of the cabinet by two adjustable
supports that shall bear against the tank of the transformer when the cabinet is in
position. These shall be adjustable in length from inside the cabinet and shall have end
caps to prevent damage to the transformer paintwork. Alternatively, root frame work of
the FP cabinet may be bolted to the PSU bottom frame work.

12. The design shall be such that cables can be terminated from the front through bottom
entry. All Parts of equal size and rating shall be interchangeable. The general design
shall be such that the number of joints shall be kept to a minimum. Corrosion proof
(with electro-nickel plated) steel bolts shall be used for electrical joints. All bolts and
studs shall be plated to BS 3382 and shall be corrosion proof.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 27 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
13. Bus-bars shall be situated at the rear of the equipment. Bus-bars shall be of made of
nickel/tin-plated high conductivity electrolytic copper and un-insulated. Phase bus-bars
shall be colour marked (at least one inch width strip) in sequence from top to bottom,
red, yellow, blue and the neutral bus-bar shall be marked black (at least one inch width
strip) and the earth bus-bar mounted at the bottom shall be unmarked.

14. A bolted link-bar of same rating as neutral bar, shall be provided between the neutral
and earth bus-bars. The metal framework of the fuse cabinet shall be bonded to the earth
bar.

15. Where live metal is adjacent to the framework a sheet of Bakelite or other suitable low
voltage insulating material shall be fixed to the inner side walls of the fuse cabinet. It
shall extend to at least 200mm above the red phase (upper phase) top contact and an
equal distance below the blue phase (lower phase bottom contact). The thickness of the
insulating material shall not be less than 2.0mm. The width of the insulating sheet shall
approximate to that of the sidewall of the fuse cabinet. The sheet of the insulating
material shall be suitably fixed. The fixing shall not incorporate metallic parts, which
protrude towards live metal work. If adhesives are used, the quality shall be such as to
ensure proper adhesion under the temperature/humidity conditions stated in this
Specification.

16. Insulated dividing barriers shall be provided between incomer unit, outgoing distributor
units and instrument panels. The fixing of the insulated dividing barriers shall be such
that they shall not swing.

17. All CTs should be complied with thermal class insulation ‘ F’.

7.2 Incomer Unit with Switch-Disconnector (for transformer Control)

1. The mechanical connection between the transformer and the feeder pillar cabinet shall
be through flange connection conforming to Flange: F, fig 25 of BS 2562 with suitable
steel trunking. The electrical connections are made through suitable bus-bar connecting-
links to match LV mono-block type bushing unit, conforming to BS 2562.

2. The incomer unit consists of 3 independent single pole switch-disconnectors, each pole
independently operated through operating handle. Each pole corresponds to matching
phase of the incoming transformer circuit.

3. The incomer switch-disconnetor unit shall be a type tested product conforming to the
requirements of IEC 60947-3 & IEC 60947-1. It shall be dependent manual operated,
with utilization category of AC21A. Making and breaking capacities shall be at least 1.5
times its rated operational current. Product type test certificates, issued from reputed
independent laboratory shall be submitted for verification.

4. The switch-disconnector contacts shall include a contact-tightening device on both the


top fixed contact, the bottom hinged contact, designed to obviate slackening when
subject to vibration, and good contact shall not depend upon the neutral spring of the
contact. Reasonably good contact shall be made on closing the switch so that the full
current can be safely carried in the interval prior to the tightening of the contacts

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 28 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
5. The contact tightening device shall be operated by crank action using the insulated
operating handle; the same end of the operating handle shall be used for tightening or
slackening the contact tightening device as is used for opening or closing the switch-
disconnector blades. When the device is being tightened or slackened the operating
handle end shall remain in the device. The total movement of the contact tightening
device, from full slackness to full tightness, shall not be more than 140° of angular
rotation. ISOLATING MOVING BLADES SHOULD REMAIN IN ITS
POSSITION WITHOUT DROPPING BY ITS OWN WEIGHT, EVEN IN OPEN
POSITION.

6. Each switch-disconnector pole shall be equipped with transparent polycarbonate safety


barrier at front, with pad-locking facilities. Pad-locking shall be possible when the
switch contacts are either in fully open or closed positions. When the switch contact
blade is in fully opened condition, the blade shall not touch the front safety barrier, and
shall have at least 20mm clearance. It shall be possible to close main door of the FP
when the contact blade is fully opened and pad-locked.

7. Each phase and neutral of the incomer unit shall be colour marked to correspond with
the bus-bars to which they relate.

8. The insulated operating handle shall be kept in the slots of clips provided on the
framework to store this when not in use. The amount of bare metal on the pole shall be
kept to a minimum.

9. Each switch-disconnector pole shall be equipped with one current transformer (details
specified elsewhere). It shall be possible to easily change current transformers, without
dismantling any major components.

10. A bolted link of not less than 1250A rating shall be provided to disconnect the neutral.

11. Robust and rigid insulated dividing barriers, of not less than 5mm thickness, shall be
provided between each pole of incomer unit. The fixing of these insulating dividing
barriers shall be such that under normal operating conditions it is not possible for contact
to be made between live metalwork of different phases or between live and earthed
metalwork.

7.3 Outgoing Distributor units


1. Each distributor unit shall be drilled for mounting at 145 +5mm centres apart. It shall be
possible to change any single bus-bar or cable connection without affecting other
phases.

2. Contact assemblies shall be supported from the steel frame-work by means of strips,
rods, bars or mouldings of insulating materials. The arrangement of supports shall be
such that mechanical stresses produced in service by the temperature rise of connections
shall not adversely affect the alignment of the contact surfaces.

3. The fixed contact assembly shall be suitable for accommodating a fuse carrier with a 92
mm terminal centre fuse-link type 'J' in accordance with BS 88. Fuse carriers shall be
supplied with the pillars. Each fuse carrier shall be suitable for inserting in a phase of the
unit by hinge action pivoted on the lower contact and for withdrawing by snatch action.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 29 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
The contacts shall be arranged to permit contact tightening and the contact surfaces shall
be flat and accurately aligned in pairs.

4. The phase cable side fuse contacts shall be designed with long and short reach and shall
be fitted with forward projecting M16 captive steel studs, one per contact complete with
a full nut. A lock washer, and plain washer with lock nut shall be provided. The contacts
shall be so designed that they provide adequate spacing and are fully interchangeable to
permit terminating the phase conductors of a cable whatever their lay.

5. The phase cable side contact groove (for receiving the fuse) shall be centrally and
symmetrically placed, so that, even if this contact is fixed in reverse side, its fixing
centre shall not miss its alignment for fixing fuses. Further, if these contacts are made in
‘L-shape’, the gap between adjacent contacts, when fitted in reverse directions, shall be
at least 25mm. Alternatively, if these contacts are made in ‘I’ shape, these contacts shall
be fitted with additional copper spacer rings of 6mm thickness, so that the outgoing
cable insulation will not touch the hot bus-bars, when connected.

6. Insulated dividing barriers shall be provided between phase contact assemblies and
phase and neutral contact assemblies which shall make it impossible to insert a fuse link
between contacts of different phases.

7. There shall be no separate neutral isolating link on each outgoing unit. The neutral
conductor of each cable (of outgoing unit) shall be terminated on to a contact bar, rated
at 315A, mounted below the corresponding outgoing distributor unit, between the
neutral bus-bar and the insulated support strut. The bottom fixing of the insulated
support strut shall be mounted above the neutral contact bar so as to allow the neutral
core an unimpeded approach to the desired fixing position. This neutral contact bar shall
be drilled in two positions and fitted with a high tensile M16 steel bolt, nut, and lock-
washer or plain washer with locknut shall be provided. The neutral bus-bar shall be
fitted 460mm above the centre line of cable cleats at bottom.
8. Bottom plate of the feeder pillar with cable entry holes, shall be divided into two
portions. By removing the front portion, and front apron plate, it shall be suitable to
connect, disconnect, or interchange any cable connection. All holes shall be closed with
dummy plates which are removable at the time of connections.

9. Cable support shall be provided by a suitable wooden-cleats mounted at the bottom of


the cabinet (inside cabinet) in such a manner that the cable entry to the cabinet is sealed
by the wooden cleat and that the cable is clear of any adjacent metalwork with the help
of suitable grommets. It shall comply with the requirements of IP41, not allowing any
vermin to enter.

10. The cleat shall clamp directly on to the PVC over sheath of the cable. The cable cleat
and its fixings shall be adequate to support the outgoing cable in normal service and
when subjected to the short circuit duty specified elsewhere.

11. Cable termination arrangement shall be suitable for accommodating up to and including
300mm² 4 core stranded copper conductor either I) paper insulated lead sheathed double
steel tape armoured PVC over sheathed cables to BS 6480 or ii) XLPE insulated steel
wire armoured PVC over sheath of the cable as per IEC 60502.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 30 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
12. Required number of holes shall be drilled on earth bar and fixed with M16 bolts, nuts &
washers, for terminating Cable earths from each out going cable.

13. All cable connections shall be suitable for terminating using heat shrinkable materials
and crimping lugs. (Heat shrink terminations & cable lugs are not in the scope of
supply).

14. Provision shall be made on each outgoing feeder ways to affix and padlock a suitable
insulated device to prevent fuse links being installed or removed. Two such devices shall
be provided with each feeder pillar. The device shall not obstruct the feeder pillar doors
from closing when in position or when stored within the feeder pillar. It is essential that
the device can be safely fitted whilst the pillar and each feeder is alive.

15. The device shall be marked with the following wording in English and Arabic and be
clearly visible when viewed from the front with the feeder pillar doors open:

"CAUTION -MEN WORKING - DO NOT INTERFERE WITH THIS


APPARATUS”

16. Blank circuit labels suitable for engraving black letter on white background shall be
provided for all outgoing circuits. The support for the circuit labels shall not be on any
live part.

7.4 Electrical Ratings & Characteristics

1. Rated operational voltage (Ue) : 415/240Vac


2. Rated insulation Voltage (Ui) : 415/240Vac
3. Rated impulse withstand voltage (Uimp) : 6kV
4. Rated frequency : 50 Hz

5. Rated Normal currents


Rated normal
For PSU/ Rated normal Rated normal
No. of outgoing current rating of
Transformer Rating current of Incomer current of Phase
(KVA) * Ways in FP each Outgoing
units * Bus-bars *
unit *
315 800A 800A 2 630A
500 1600A 1600A 4 630A
1000 1600A 1600A 6 630A
1600 2500A 2500A 6 630A
*These ratings have reference to local ambient conditions stated in the Specification.

6. Rated short circuit withstand current and Peak withstand currents


For PSU/ Transformer Rated normal current Rated Short circuit Rated peak withstand
Rating (KVA) of Incomer units withstand current (Icw) current (Ipk)
315 800A 20kA @ 1 Sec 50kA
500 1600A 20kA @ 1 Sec 50kA
1000 1600A 35.5kA @ 1 Sec 88 kA
1600 2500A 40 kA @ 1 Sec 100kA

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 31 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
7. Clearances
For all connections in air the clearance and creepage distances shall be not less than
25mm between conductors and 20mm from conductors to earth.

8. Temperature rise limits

The distribution fuse-board shall be so designed as to ensure that thermal interaction does
not unduly affect the performance of any of the components
Temperature rise test on the FP shall be conducted in accordance with clause 8.2.1.3 of
IEC 60439-1 (by using current on all apparatus) with all its components, including fuse-
links, fitted, and all circuits are fully loaded. The test shall be carried out with the base
closed, door(s) shut and mouth of the throat piece through which pass the incoming
connections, shall be effectively blanked off.
All the measurements shall be taken with the help of thermocouples and thermometers.
The FP shall be capable of withstanding the guaranteed temperature rise limits specified
in IEC 60439-1/ cl# 7.3/Table-2. However actual temperatures rises of over ambient
temperature outside the FP shall not cross the limits as specified below.

Sr. No Part/component of the Assembly Temperature rise limits, K


1 All temporary incoming connections
2 Interconnecting point between Tx and FP
3 Top contacts of each phase of the isolator
45
4 Top contacts of each phase of O/G fuse units
5 All cable lugs/terminals
6 All bus-bars
7 All other built-in components In accordance with limits
specified in relevant product
standards requirements, less
250K

Evidence shall be submitted that temperature rise tests have been carried out on a completed
FP, to demonstrate that it does comply with this Clause.

7.5 Cleaning and Painting

The following is the minimum standard. Manufacturers may offer an alternative, at the time
of tender.

A ferrous surface and edges shall be cleaned of scale and rust by shot blasting and shall then
be treated on the same day, without outdoor exposure, with a zinc spray.

The zinc shall be applied by flame gun process of a thickness ZN4 in accordance with BS
EN 22063 : 1994.

The treatment shall be followed by application of one coat of zinc chromate base priming
paint, an undercoat and final coat of durable oil and weather resisting paint. The final coat
shall be dark admiralty grey colour 632 in BS 381 C.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 32 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

7.6 Accessories Fitted

1. Fuse Carriers
Fuses for Distributor Circuits
Fuse Links : These will be supplied by the purchaser.

Fuse Carriers:
A thorough grip shrouded fuse carrier of high quality non-inflammable and non-
hygroscopic, DMC insulating material approved by Kahramaa shall be provided on each
phase. Each carrier shall be complete with two insulated contact tightening thumbscrews.
Reasonably good contact shall be made by wedge action on inserting the fuse carrier so that
current can be safely carried in the interval prior to the tightening of the contact tightening
thumbscrews. Wedge action material shall be of brass and screws shall be of anti corrosive
material. There shall be one standard size of fuse-carrier which shall carry a 92mm terminal
centre fuse-link to type 'J' BS 88.

2. Fuses For Auxiliary Supply


Fuse carriers for auxiliary circuits shall be of the withdraw-able handle insulated type with a
rating of 60A and shall accommodate cylindrical cartridge type fuse-links of 32A with
dimensions 57x22 mm, in accordance with type 11a fuses in BS 1361:1986.

3. Neutral and Earth Connections


Separate neutral and earth bars shall be provided. They shall be solidly bolted together. The
neutral bar shall be insulated from the shell, but the shell be bonded to the earth bar. A
sideways projecting M 12 x 50mm captive stud complete with washer, nut, and lock nut
connected to the earth bar shall project outwards from the shell.

4. Current Transformers
The current transformers of ratio 800/5A, 1600/5A or 2400/5A as specified shall be provided
on the incoming circuit of respective Feeder Pillars and securely fixed. The current
transformers shall comply with the requirements of BS 7626 and IEC 60044 and shall be of
5VA output, Class 1 accuracy. They shall be suitable for the operation of thermal demand
ammeters. The current transformers shall be of epoxy cast resin type capable of withstanding
required temperature limits. The mounting of CTs shall be such that, in the event of failure,
they shall be easily replaceable without the need for dismantling any major component. Only
single ratio CTs are to be used.

5. Instrument Panels And Auxiliary Supply Circuits

An instrument panel suitably wired shall be provided to accommodate three thermal demand
ammeters (96x96mm size) with instantaneous pointer having a twenty-minute lag and with
direct reading quadrant scales. The scales readings shall be in one side. Measuring ranges
shall be 0-960A, 0-1960A and 0-2880A for C.T. ratios 800/5A, 1600/5A, and 2400/5A
respectively. The cable connections shall be of sufficient length to allow for the removal of
the indicators from the front panel.

The following additional equipment shall be supplied:-

13A switched socket outlet to BS 1363.


0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 33 of 46
ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

60A fuse base and carrier for socket, substation supplies and earth fault indicator reset
supply.

The instrument panel shall be mounted in such a position that neither cable installation nor
jointing is impeded. Where it is mounted in front of the cables it shall be removable.

The substation supplies circuit shall be wired to terminals on the side of the fuse-cabinet
mounted below the level of the neutral bar. A 25 mm cable gland is to be equipped at right
front corner of bottom plate, to terminate an outgoing 2 core 16mm² PVC insulated steel wire
armoured cable. It shall be possible to safely connect the outgoing cable with the remainder
of the pillar live in normal service. The terminal block shall be fully shrouded.

6. Small Wiring

Small wiring shall be carried out in PVC insulated cable coloured black to BS 6231 Type B
with 7/0.67 mm conductors and with cores ferruled. The substation supplies circuit shall be
wired to the terminal block with 16mm² PVC insulated conductors having Red & Black
colour insulation. The terminal block shall be identified with permanent labels.

The secondary wiring of the group of current transformers shall be connected to earth at a
single point on the terminal block, which shall be accessible from the front the pillar or fuse-
cabinet. In addition to this, all secondary wires of CT are to be routed through TB.

Wiring shall be fixed and where wiring cleats are used they shall be of the insulated limited
compression type. Both the main connection from the phase bus-bar to the fuse and the main
connection from the neutral bus-bar shall be hard drawn high conductivity copper not less
than 75mm² cross-section.
If necessary use heat resistant grade wires for the small wiring to withstand the required
temperature limits.

7. Circuit Labels & Permanent Wiring Diagrams

A circuit label 75x50mm made of insulating material shall be mounted on the barrier
between red and yellow phases of each circuit unit. This label shall be securely held without
the use of screws or other metallic fixings and it shall be possible to slot into position and
remove label from the front of the barrier. The labels shall be suitable for engraving black
letters on a white background. The supports of the labels shall not be fixed to live parts.

A permanent, indelible schematic & wiring diagrams, clearly indicating all terminal
markings, components, shall be fixed inside the FP front door.

7.7 Tests
1. Type tests
The following type tests are to be conducted in reputed independent laboratory and copies
of test reports shall need to be submitted.
a) Verification of temperature rise limits (IEC 60439-5/8.2.1)
b) Verification of Dielectric properties (IEC 60439-5/8.2.2)

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 34 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
c) Verification of short circuit withstand strength (IEC 60439-5/8.2.3)
d) Verification of clearances and creepage distances (IEC 60439-5/8.2.5)
e) Verification of mechanical operation (IEC 60439-5/8.2.6)
f) Verification of degree of protection (IEC 60439-5/8.2.7)
g) Verification of mechanical strength (IEC 60439-5/8.2.101)
h) Verification of resistance to abnormal heat and flame (IEC 60439-5/8.2.102)
i) Verification of corrosion and aging resistance (IEC 60439-5/8.2.103)
2. Routine Tests

Routine tests are to be carried out on every new assembly after it has been assembled at
factory. One set of routine test reports of each FP shall be fixed inside the FP cabinet in a
strong water-proof envelope. The following routine tests are to be carried out.
a) Inspection of assembly, including wiring, and electrical operation test(8.3.1)
b) Dielectric test (IEC 60439-5/8.3.2)
c) Electrical continuity (IEC 60 439-5/8.3.3)
d) Insulation resistance (IEC 60439-5/8.3.4)

8.0 THE HOUSING OF DPS

8.1 Construction

1. Overall dimensions: Overall dimensions shall be as per the clause 1.0 above.
Manufacturer may propose a compact design with the same clearances between the
equipment mentioned in the clause, however, KAHRAMAA reserves the right to accept
or not.

2. The main components (Transformer, LV & HV Switchgear) shall be mounted on robust


base made of structural steel frame, through bolted joints. Welded joints are not
acceptable. This shall facilitate easy replacement of components when required.

3. It shall be four sided, with walls having removable type panels on three sides, and two
access doors at the front, for HV & LV switchgear compartments individually. Each
front access shall be of double leaved hinged type doors. In order to facilitate the cable
connection, the portion of the wall at RMU side equivalent to RMU dimensions shall be
removable from inner side bolts which never be accessed from outer side.

4. All main components of DPS shall be mounted on structural steel base frame through
bolted joints to form a rigid distortion-free structure. DPS shall have completely bolted
enclosure for easy assembly and retrofit.

5. The DPS shall be operated from outside at ‘ground level’ (on concrete plinth), and shall
be suitable for mounting on concrete plinth.

6. Plinth matrix of 500KVA, 1000KVA & 1600KVA DPS units shall be same. These units
shall be designed to fit on the same size plinth. This implies the position of bottom cable
entry ducts, of all these three sizes shall align with the common plinth matrix. This shall
permit replacement of any unit by any other, irrespective of rating, by disconnection and
reconnection of 11kV and LV cables only. However, 315KVA DPS may have different
plinth size & matrix
0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 35 of 46
ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
7. Bottom cable entry openings of PSU shall align with respective cable ducts on concrete
plinth. The cable entry opening shall be closed with removable type covers to maintain
IP protection of the enclosure.

8. The walls, door and roof shall be made of sheet steel with reinforcement as may be
necessary. The sheet steel thickness before paint shall not be less than 2.0mm.

9. The roof of the enclosure shall have double roof-system, separated by large volume of
air, to serve as insulation against direct solar radiation.

10. Pressure relief system/vent(s) shall be provided on the top of enclosure to allow safe
passage of gases released in the event of internal arc inside DPS unit.

11. The design and construction of the modules shall be such that when all modules are
assembled together on the steel base frame, it shall form a strong and distortion-free
structure.

12. Suitable lifting arrangements shall be provided such that DPS along with or without the
housing can be lifted or transported to site as a single unit. The lifting fittings shall be
suitable for lifting the PDS with crane and chains without damaging the enclosure.

13. The roof shall be pitched in all directions, and shall include extensions over the walls of
approximately 100mm.

14. The enclosure shall be removable type, from its base, without dismantling any of its
components.

15. The enclosure shall withstand all mechanical stresses including roof-load, wind-loads,
and external mechanical impacts. Covers, doors, and ventilation openings shall be able
to withstand mechanical impacts corresponding to a degree of protection IK10 (20J).

16. The door hinges shall be robust and made from stainless steel. All doors shall have
suitable mechanism to toggle its position when fully opened, as well as through half
way. A heavy duty lamp with shall be provided in the enclosure of DPS with limit switch
interlocked with door open/close.

17. The doors of the housing shall be so placed as to permit an operator to carry out
switching operations from outside of the unit, including cable fault testing, operation of
the tap changer etc

18. Each door shall be in two parts. Left hand door shall be fixed with two 178mm brass
tower bolts. Right hand side door shall be fixed with stainless steel 458mm L-Drop,
spindle dia. 16mm and accessory.

19. The doors shall be lockable by a padlock with a 52mm x 49mm body, and 8.5mm
diameter shackle having a clear inside width of 29mm and an inside length of 41 to
55mm. The purchaser will supply this.

20. Earthing: Each of the modules of PSU shall be effectively electrically bonded and an
earthing terminal shall be provided. This earthing terminal shall be connected to the
main earthing on the transformer with a 70mm² earthing conductor. The main earthing
terminal on the transformer will be connected to the earth electrodes
0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 36 of 46
ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

8.2 Corrosion Protection & Painting


1. The definitive guideline documents are BS EN ISO 12944 Parts #1 to 8, & BS EN ISO
14713. The procedure should clearly indicate its relationship to the appropriate parts and
tables of BS EN ISO 12944 and BS EN ISO 14713
2. It is the responsibility of the manufacturer to assess environmental classification, select
suitable surface preparation process, protective paint system, execution and supervision
process, in accordance with above referred standards and requirements.
3. The painting work should render a service life of at least 25 years to the equipment,
withstanding local ambient climatic & environmental conditions.
4. The exact Specification & painting procedure going to be followed by the manufacturer
shall be submitted at time of tender.
5. The process shall contain the following steps as minimum requirement:
a) Surface cleaning
b) Degreasing
c) Automated Zinc phosphate chemical treatment followed by chromatic passivization
d) Surface drying at 130-1600C
e) 3 coats of electrostatic powder coating (normal spray painting not acceptable)
f) Curing of paint work in oven at 180-2100C, as appropriate.(curing by natural air
drying process is not acceptable)
g) Final coat colour shall be light grey or beige
6. The manufacturer should posses required laboratory testing equipment, in their factory, to
test the samples in accordance with BS EN ISO 12944-6. These test reports should be
submitted along with each consignment of delivery.

8.3 Earth Fault Blinking Device


a) The Blinking lamps shall be fixed on the top of package unit with Provision to adjust
the angle of view by means of opening and fixing the device such a way to view the
indication lamp by sitting in the vehicle or standing position, either from front side
or lateral.
b) The blinking lamp shall have a view range from not less than 50m.
c) The Blinking lamp shall be incorporated in housing with highly solid material
(polycarbonate) proper weather proof and viewing glass with oval shaped metallic
cover on top (Similar to traffic signals). All the cables should be laid through metallic
weatherproof conduit with proper /cable trays with covering.
d) The Earth Fault Indicator should consists of i) Reading Instrument (Surface mounted),
ii) Sensor with cable and iii) Blinking lamp. The power supply shall be performed by
lithium battery long life (Minimum 10 Years) and of Auxiliary supply 240V, AC
supply. Test button should also be provided.
e) The indicator shall have facility for i) Manual reset, ii) Self resets when the 240V,AC
supply resumes, iii) Resets automatically after a pre-set time. This pre-set reset time
shall be adjustable and shall 0 to 8 hrs in steps and iv) Provision for connection to
reset from remote.
f) The impulse duration of blinking light shall be adjustable between 50 to 1000
milliseconds. The fault Indicator shall be provided with enough length of cable to fix
in appropriate location.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 37 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
g) The Earth fault current sensor shall be suitable for mounting on 12kV various types of
HV cables in KAHRAMAA distribution system. Suitable belt with self locking
facility shall be provided on the sensor to hold it firmly on the cable.
h) The earth fault operating current shall be able to set from 10,20,40,60 and 100 Amps.
The sensitivity (operating current) of the EFI shall be set at 30 Amps
The indicators including the cables should be weather proof enclosed with front side
glass for proper view (IP65).

8.4 Restricted Earth Fault (REF) Tripping Mechanism

a) The purpose of this mechanism is to trip the 11kV side of the Transformer Switch
(TX Switch) in RMU from the REF scheme on LV side of Transformer, in which CTs
are provided in the feeder pillar, which Protect an earth fault within in the protected
zone of the scheme, ie LV winding up to the CT location.
b) The scheme shall have 4 Nos. of class X CTs (1 no. each for phase and 1 no. for
neutral) and shall be mounted inside the feeder pillar.
c) The secondary of all these CTs shall be connected in parallel (i.e. the same polarity
terminals connected together ) for the REF scheme, and the wires from the these CTs
(common terminals) shall be connected to a trip coil of the transformer C.B. of the
RMU.
d) All the CTs used for the REF scheme shall have same ratio, magnetization
characteristics, winding resistance, etc and shall be from same manufacturer. The
knee point voltage of CTs must be higher than the stabilization voltage for maximum
external fault current.
e) CT ratio and knee point voltage shall be depending up on TX capacity Calculation
shall be provided by the supplier with Transformer and CT parameters (Resistance of
CTs, TX % Impedance etc.
f) To achieve the stability during external fault proper short time rated variable
stabilizing resistor in series with the trip coil shall be provided. The stabilizing resistor
shall be easily accessible and shall be easily replaceable. Same methodology for REF
scheme calculation shall be adopted for the above.
g) PVC insulated, sheathed and armoured 2x 4 sq.mm copper cable shall be used for
interconnecting the CT wires between the feeder pillar and RMU. The cable shall be
properly glanced at both ends.
h) Terminal Blocks having isolating link and CT shorting facility shall be used at feeder
pillar and RMU for terminating secondary wires of CTs. The single point earthing of
CT secondary circuit shall be confirmed.
i) All wires shall be provided with ferrules for identification. For example, wires at CT
terminals shall be ferruled as S1 and S2. At TBs on RMU these shall be REF-S1 and
REF-S2.
j) The 2 leads from the REF CTs shall be connected to a dedicated TRIP coil.
k) Provision of dedicated Trip coil for REF trip shall be made in RMU (similar to the
one provided for putting TLF).
l) A very low burden current operated series Mechanical Flag relay should be
connected in series with CT output leads from REF CTs
m) The trip coil shall be connected in series with variable stabilizing resistor and series
mechanical current operated flag relay with minimum burden which is to be fixed in
the instrument panel of F.P.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 38 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
n) The stabilizing resistor is selected in such a way that, during maximum through fault
condition, the voltage developed across the shunt trip coil (or the current through the
shunt trip coil) shall not trip the transformer switch.
o) The scheme shall be tested for, CTs to prove ratio, polarity, magnetization curve and
winding resistance, ratio checks for confirming that the installed CTs are adequate for
the REF scheme and also the stability checks and Tripping shall be proved.
p) Sensitivity of the scheme shall be tested by Primary injection. Also the stability of the
scheme shall be tested for external faults.
q) Certification with test results complying above requirements shall be provided with
each unit.
r) All the CT calculation is similar to high impedance Restricted Earth Fault scheme.
Only the difference is instead of relay in the REF scheme, the dedicated coil for RMU
TX switch is connected and direct tripping of transformer switch is achieved, without
auxiliary supply and REF relay

8.5 Accessories to be supplied as spares (free of cost)

a) In Case of cable connection Termination kits


for interconnecting HV & LV Cables.: 10% of total quantity of DPS
b) In Case of connection through bus bar, HV & LV
trunking box with gaskets and identification labels.: 1% of total quantity of DPS
c) Complete set of REF CTs.: 3% of total quantity of DPS

8.6 Test to be conducted on paint work of DPS

The paint work shall pass following tests


a) Measurement of thickness of protective coating (ISO 2808)
b) Specular gloss factor at 60 deg (ISO 2813): 90±5%
c) Falling weight test (ISO 6272): 1kg/50cm
d) Cross cut test (ISO 2409): classification: 0
e) Cupping test (ISO 1520): 08mm
f) Bending test – Cylindrical mandrel test (ISO 1519): 3.0mm
g) Salt spray (fog) test (ISO 7253): 1000hrs

8.7 Tests on DPS


In addition to the type tests conducted on individual components (Transformer, RMU and
Feeder Pillar), DPS as a whole unit need to be type tested in accordance with the
requirements of IEC 62271-202. Copy of type test reports issued from reputed independent
laboratories need to be submitted.
1. Type tests
a) Tests to verify the insulation levels of PSU (IEC 62271-202/6.2)
b) Tests to prove the temperature rise of main components in PSU (IEC 62271-202/6.3)
c) Test to prove the capability of main and earthing circuits to be subjected to the rated
peak and the rated short-time with stand currents (IEC 62271-202/6.4)
d) Functional tests to prove satisfactory operation of the assembly (IEC 62271-202/6.5)
e) Tests to verify the degree of protection (IEC 62271-202/6.6)
f) Test to verify the withstand of the enclosure of the PSU against mechanical stress
(IEC 62271-202/6.7)
0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 39 of 46
ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
g) For PSU substation class (IAC-AB @ 20kA-1 sec) tests to assess the effects of arcing
due to an internal fault (IEC 62271-202/6.8)
h) Tests to verify the sound level of the PSU (IEC 62271-202/Annexure-B)

2. Routine tests on DPS


Routine tests are to be carried out on every new assembly after it has been assembled at
factory. One set of routine test reports of each PSU shall be fixed inside the PSU cabinet
in a strong water-proof envelope. The following routine tests are to be carried out.
a) Dielectric test on HV interconnection (IEC 62271-202/7.1)
b) Test on auxiliary and control circuits (IEC 62271-202/7.2)
c) REF stability checks / tests.
d) Functional tests (IEC 62271-202/7.3)
e) Verification of correct wiring (IEC 62271-202/7.4)
f) Tests on paint work as specified above.

9.0 QUALITY STANDARDS

The manufacturers of the equipment specified shall possess certification issued by a body
authorised to do so, which indicates that the manufacturing unit operates to a standard
equivalent to ISO 9001. Copy of a valid certificate shall be submitted along with the tender.

Submission shall include documents to indicate the quality control procedures adopted by the
manufacturer of the housing.

10 TESTING, INSPECTION & DELIVERY

1. Before commencing the production/manufacturing of 1st lot, against KM tenders, the


manufacturer is obliged to produce samples of DPS units and inform Kahramaa for
inspection and acceptance through witnessing factory acceptance tests, and routine tests. KM
reserves the right to choose option of inspecting these proto-type samples either at KM
workshop or at factory.
2. For every subsequent lot, the manufacturer is obliged to inform Kahramaa, at least 20 days
before dispatch, and obtain clearance for dispatch. KM Engineers have the option of
inspecting & witnessing all factory acceptance tests, including routine tests, at
manufacturer’s factory premises for each lot.
3. Acceptance by KM Engineer(s)/Representative(s) of any DPS unit shall not relieve the
manufacturer from any of their responsibilities, guarantees, or from other obligations, to
comply with product requirements.
4. Type tests are to be carried out on specimen DPS unit, essentially of same design and ratings,
as being offered. Manufacturer is obliged to provide details of test procedures being
followed, to the KM inspection team before commencing factory accepting tests.
5. Each DPS unit need to be subjected to all routine tests at factory before delivery. One unit in
each lot will be subjected to prescribed tests on paint work. Further, each unit may be
subjected to inspection on receiving them at DOHA to verify its healthiness and its
conformity with the guaranteed design data.
6. All tests should be performed in accordance with the latest issue of relevant IEC standards

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 40 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
7. Three sets (copies) of routine tests & FAT reports to be prepared. One set to be attached with
the body of switchgear unit, in a strong water-proof envelope. Second copy to be sent along
with delivery note. Third copy to be sent to the end-user department.
8. A detailed function drawing shall be engraved on metal plate and fixed at inner side suitable
location of H.V compartment.
9. FAT report shall include copy of ‘quality control report’ containing ‘list of check points’
verified/inspected at factory against each switchgear unit.
10. Each delivery note shall include the details of ‘serial number’ and ‘month/year’ of
production of each switchgear unit.
11. Both the manufacturing date (i.e month/year) and delivery date should be shown on the
rating plate of each transformer, and the time difference between these two dates should not
be more than 6-months.
12. The manufacturer needs to organize training workshops for KM technical staff, to familiarize
with installation, operation & Maintenance, trouble shooting guidelines.
13. The manufacturer need to submit 6 copies of:
a) Manuals for Operation, Maintenance & Condition Monitoring (Details of condition
monitoring parameters, its required data values, frequency of monitoring of each
parameter, etc.)
b) Installation Instructions,
c) Trouble shooting manual,
d) Technical data-sheets and product catalogues of all main equipment (Transformer,
feeder pillar & ring main unit) and accessories mounted on the transformers [i.e,
Magnetic core material, PRV assembly, Tap-changer assembly, thermometer
assembly, drain valve cum sampling device, LV bushing assembly, HV bushings,
pressure gauge & isolating valve assembly, oil-level gauge, all gaskets, REF, CTs etc]

11.0 INFORMATION/DOCUMENTS TO BE SUBMITTED BY BIDDERS/MANUFACTURER

Each manufacturer must supply the following information along with their offer:

A Distribution Package substation unit

1. Brief description of product being offered along with details of name of manufacturer,
product type / model, country of origin, quantity being offered, mobilization
period/execution plan.
2. Detailed layout drawing with all views including plan. Elevation, side elevation, dimensions,
components.
3. Complete set schematic diagrams for power & control protection system.
4. A plan showing the minimum clearances required around a DPS on site when installed
5. Details of materials used in frame and cladding
6. Detailed drawing of interconnection between transformer and RMU
7. Detailed drawing of interconnection between transformer and LV Feeder pillar

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 41 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
8. Details of ventilation arrangements
9. Details of arc pressure relief device in the housing
10. Details of door locking arrangements and lifting arrangements
11. Detailed technical data sheets containing rated values and characteristics.
12. Approximate envelope dimensions of the whole unit, without housing.
13. Approximate envelope dimensions including housing.
14. Centre of gravity (plan position and height).
15. Copies of Type test reports
16. Original Product catalogues (photo copies not acceptable)
17. Sourcing details of all main components
18. Copy of valid ISO 9001;2000 certificate to be submitted
19. Set of installation, operation and maintenance instructions/manuals
20. Set of instructions for storage, transport
21. Weight of the DPS without and with housing.
22. A set of assembly instructions
23. Previous sales history of related supplies made to the clients in GCC and other countries.
The details should include client name, equipment ratings, quantity delivered, year etc.
24. Compliance statement against each clause of this specification document
25. List of Deviations against each clause of the KM technical specification

B Transformer
1) Technical data-sheets, containing all technical details including, ratings, parameters, vector
group, connections symbols, losses, max. flux density, cooling, tank details, winding details,
oil details, temperature rise limits, % impedance values, insulation levels, efficiency,
regulation, etc, of the transformer
2) All technical details, parameters, data-sheets belong to each of the accessories fitted to the
transformer, including tap-changer, thermometer, PRV, HV & LV bushings, Oil level
indicator, gas pressure gauge with isolating valve, drain valve with sampling device, etc.
3) All Type tests & Special test certificates of the transformer
4) Type test certificates of tap-changer
5) Type test certificates of HV & LV bushings
6) Specific Product catalogues of the transformer, tap-changer, Oil-level indicator, PRV,
Thermometer, HV & LV Bushings, various gaskets used, gas pressure gauge etc.
7) Details of Painting system applied to the transformer
8) Detailed Operation & maintenance manuals of transformer.
9) Valid proof of documents showing the sourcing of tap-changer, magnetic core laminations,
HV & LV bushings from internationally reputed manufacturers.
10) Valid ISO 9001 certification of the Transformer manufacturer
11) Compliance/deviation statement against each clause of this specification document.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 42 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
12) Two sets of Complete drawings, as stated below
13) Complete sales history of the proposed product, indicating details of the Transformer rating,
Client name, Year of supply, quantity supplied etc. The list should highlight the supplies
made to clients in GCC countries.

C Ring Main Unit (RMU)


1. Detailed layout drawing with all views, dimensions, components
2. Detailed technical data sheets containing rated values and characteristics
3. Pictorial views of gas pressure system, explaining how the gas medium is isolated with the
gas pressure gauge, and its replacement procedure.
4. Single line diagrams, controls circuits, wiring diagrams, list of inputs/outputs for remote
monitoring & control (where applicable), for each switchgear unit described in the
specification, need to be submitted.
5. Linear Motor Drive Actuators: Details of Motor characteristic, arrangements of actuators,
wiring diagrams of Motors and Control Box shall be submitted to Kahramaa for prior
approval
6. O/C & E/F protection: Details of tripping mechanism, tripping characteristics and applicable
setting shall be submitted with the Bid.
7. Earth fault relay: Product technical details, catalogues, installation instructions & manuals
should be submitted.
8. Type test reports, belong to all CTs & VTs, Vacuum bottles
9. Sourcing details of all components like vacuum bottles, CTs, VTs, shall be furnished.
10. Latest type test certificates and reports
11. Copy of valid ISO 9001;2000 certificate to be submitted
12. Original Product catalogues (photo copies not acceptable)

D L.V Feeder Pillar


1. A full set of type test certificates as specified
2. As built construction drawing with all views and sections, containing all dimensions, details
of components, Size and arrangement of busbars, neutral bar, earth bar and neutral/earth
link, Dimensions of cabinet gauge of metal used.

3. Technical data-sheets of main feeder pillar, and its components


4. Paint work specification
5. Installation, operation & maintenance instructions.

12.0 LIST OF DEVIATION TO THE SPECIFICATION.

The bidders are required to attach a separate deviation list to their Technical Offer and include it
in the Technical Package if the offered equipments do not meet the requirements of any clause
of the Specification.
Offers without any deviation list attached to the Technical Offer and included in the Technical
Package shall mean that the offer meets the requirements of the Specifications on all the clauses.
0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 43 of 46
ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section
Offers with deviations listed out shall mean that the offer meets the requirements of the
Specification on all the other clauses not included in the deviation list.

13.0 WARRANTY

Manufacturer need to provide a warranty of minimum 3 years from the date of delivery, or 2
years from the date of installation (whichever is earlier) against each unit supplied against any
design, manufacture, and material defects. Manufacturer shall also provide 20 years guarantee
against SF6 gas leaks.

Any switchgear unit failed during service, with in the warranty period, need to be replaced with
new unit free of cost. Further, the faulty units(s) need (s) to be get analyzed with reputed
independent agencies and fault-analysis reports to be submitted.
Further, it is the responsibility of the manufacturer to arrange for investigation of any
abnormalities/defects observed during service period, even if it is out of warranty period.

14.0 RESTRICTIONS ON OUT-SOURCING

1) Once the DPS is pre-qualified or short listed for tenders, based on manufacturer approval for
the main equipment (Transformer, Ring Main Unit & L.V. feeder pillar) and manufacturing
facilities for major components (DPS enclosure, transformer tank body, radiators, paint work,
magnetic core assembly, winding coils etc), outsourcing of the same is not permitted.
2) Out sourcing of any of the main components or work need to be declared in the beginning it-
self, before the DPS is pre-qualified or short listed for tenders. In such case, the manufacturer
is responsible for quality of work for the main equipment & components. Further, the
manufacturer should arrange accessing the manufacturing facilities of out-sourced
components to KAHRAMAA Engineers, to verify their quality parameters.

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 44 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 45 of 46


ELECTRICITY NETWORK AFFAIRS
ELECTRICITY NETWORK PLANNING DEPARTMENT
Material Standards & Specification Section

0 ED-02-091 Version – 5 Rev. 0 Issue Date July 2010 Page 46 of 46

Vous aimerez peut-être aussi