Spicer, Satara
09 April 2019
Project Number 1:
WORK PLAN
1 Study about overall production process of SIPL Satara plant 02-Apr 3 04-Apr
Selection of 3rd party software and hardware required for the Barcode
5 integration 16-Apr 2 17-Apr
Determine the unit size and lot size of the raw material
purchase from the supplier and calculate the actual bins…
Talk with suppliers and make them ready with Barcode and
SRM Portal implementation.
Barcode Implementation
This project is being carried out in the Driveshaft manufacturing unit of Spicer India Pvt Ltd. at
Satara, Maharashtra.
BACKGROUND
This project is needed because the company wants to eliminate the manual booking process in
the SAP ERP after production of finished goods and decrease the material outward time.
OBJECTIVE The objective of this project is to automate the booking process in SAP ERP.
SCOPE In this project we visualize the overall operational flow of the material handling in the ERP.
1 Study about overall production process of SIPL Satara plant 02-Apr 3 04-Apr
Develop the action plan and define the resources and support
4 required. 24-Apr 7 30-Apr
Implementation Plan
5 1-May 14 15-May
GANTT CHART
2-Apr 12-Apr 22-Apr 2-May 12-May 22-May 1-Jun 11-Jun