Vous êtes sur la page 1sur 2

by Miguel Gutierrez , OMICRON electronics, USA

36

Colombian Blackout
Blackout Watch

2007
Blackout Watch
Understanding what happened can Some questions arise:
Why didn’t the interlocking control system of the
help us prevent it in the future. busbar arrangement prevent the operator from making a
wrong maneuver?
Also, why did the power lines trip when they became
overloaded, thereby accelerating the breakdown of the CEPS?
On April 26th, 2007, at 9:58 am, the country of The Torca substation is one of the main 230 KV
Colombia suffered a total blackout that affected 25 million substations in the area surrounding the capital city of
The Colombian Blackout

people; with a cost of US $130 million, it was the worst Colombia, Bogota. There is one main busbar sectionalized in
blackout in the last 22 years in Colombia. two (B1 Sec. 1 and B1 Sec. 2) and a transference busbar (Barra
This blackout was due to human error at the 230 KV 3) linked with a breaker, as is shown in Figure 1.
Torca substation: An operator at the substation didn't One day before the maintenance maneuver, on April 25th,
follow the correct sequence of maneuvers when transferring the National Dispatch Center (NDC) in Colombia analyzed
circuits from one busbar to another before a scheduled the risk of the maintenance activity and then confirmed that
maintenance task in one sectionalizer. The wrong maneuver the CEPS was not vulnerable to an unwanted tripping of the
overloaded the inter-bus breaker, and breaker failure operation power line Torca-Guavio 1, and therefore they authorized the
de-energized the whole Torca substation, igniting a cascade maintenance operation. In fact, previous to the blackout, the
of events that brought down the entire Colombian Electric CEPS was in a very favorable situation under N-2 conditions.
Power System (CEPS). In 2007 the CEPS relied entirely on an automatic load
The power was reestablished after four hours and 30 shedding scheme (ALS) to regain balance in the different
minutes. subareas of the interconnected system in case of a contingency

1 Torca Substation Arrangement


Torca is one
Costa Oriente
of several
218 MW
Sochagota
Bacata'

main 230 kV
Torca Substation
Barra 3
substations 478 MW Chivor
Bacata'
Noroeste

in the area
Z
B1 S2

660 MW

surrounding
478 MW Guavio
B1 Sec. 1 B1 Sec. 2
478 MW
478 MW

Guavio
B1 S2

Bogota - the 478 MW


B1 S2

1120 MW
capital of Circo
Tunal

Colombia. Bogota'

PAC.AUTUMN.2009
37
affecting the frequency. As a consequence of the outage at shut down in sequence, thus collapsing the entire CEPS and Miguel
the Torca substation, six power lines and three 230/115KV leaving the whole country without electricity. Gutierrez
transformers were shut down, and a sequence of events took The restoration of the CEPS took between 4-5 hours, as received his Bach-
place: Firstly, the lines Guavio-Circo were overloaded and the NDC coordinated activities with 40 transmission control elor in electronic
tripped. Secondly, the outage of these lines (Figure 2) caused centers, generation companies and regional transmission and Licenciatura
a reduction in voltage and overload conditions in some operators. in Power System
regions. Approximately 600 power lines (23,000 km), 193 from the Uni-
In spite of the weakened condition of the CEPS, the biggest transformers and 52 power plants had to be reestablished. versity of Costa
power plants in the region, Chivor and Guavio, and other The restoration started with power plants with black start Rica in 1985 and
smaller power plants, remained online, with about 2100 capacity, and the interconnection lines with Ecuador and 1988. He worked
MW, 31% of the country’s total demand (6644 MW) at that Venezuela. Post contingency guides developed previously as a field protec-
moment. were used in successful restoration of the Colombian power tion engineer at
The only remaining links (Guavio-Tunal and system. the Costa Rican
Guavio-Reforma-Tunal) became overloaded, so frequency and The adverse experience of the blackout was used as a Institute of Electric-
bus voltages collapsed beyond the safe limits, thus causing source of improvement in different areas. Some of the most ity.and taught
the islanding of this area from the rest of the interconnected important results were: protection system
system with the opening of the lines Guavio-Tunal and Definition of guidelines to minimize the risk of at the University
Tunal- Reforma. blackouts in the future of Costa Rica. In
With the partition of the CEPS into two areas, A and B Improvements of the standard procedures for the 1999 he joined
(Boyaca and Santander regions), there was a deficit of power in execution of substation maneuvers OMICRON electron-
area A which collapsed the frequency in this area and a power Determination of critical substations which have to have ics (USA) as a sales
surplus in area B which created an over-frequency situation in special procedures for maintenance programming and application
area B. The evolution of the frequency in the areas A and B Definition of a management plan for events of big engineer, currently
during the contingency is shown in Figure 3. impact on the system for Central and
The severity of the contingency didn't give the ALS a Improvement of the training programs for operators South America with
chance to compensate the power unbalance in area A. The Definition of supplementary protection schemes and primary respon-
ALS worked as it was designed to work, but it had to work protection settings review sibilities in sales,
under an unexpected contingency and could not control the Improvement of the communication channels among training, technical
drop in frequency. the control centers assistance. He is
Figure 3 shows the interval where the ALS worked (see Improvement of the coordination schemes during the member of the
the box highlighted in blue). Colombia was then isolated from operation and restoration of the interconnected national IEEE.
Ecuador’s electric power system, and all the power plants system

2 Substations around Bogota 3 Frequency during the contingency


Event Development
Area B, Frequency >>
Area A, Frequency << 59.90

5 Sochagota 59.70
Paipa
Area B, Frequency >>
Bacata'
S.I.N.
59.50
Chivor ALS Operation
Balsillas Noroeste Torca 1,2,3,4, Area A, Frequency <<
5,6,7,8
1
Guavio
1,2,3,4,5 59.30
Bogota' 2 No Frequency
Eastern
Mesa Area Torca outage
3 58.00
'
Guaca Paraiso Circo
4 57.9 Hz
3.3 s
San Mateo Reforma
Tunal
57.00
60.7 0.00 12.00 15.00 20.00

# The sequence of tripping elements ALS: Automatic Load Shedding

PAC.AUTUMN.2009

Vous aimerez peut-être aussi