Jadwal OH PLTU Pelabuhan Tarahan Unit 2

ID Task Name Duration Start Finish


06 Nov '16 Predecessors
Resource 13 Nov '16 20 Nov '16
Names 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1 OH SIMPLE INSPECTION UNIT 1 11,71 days? Sat 12/11/16 Wed 23/11/16
2 Scope Mekanik 11 days Sat 12/11/16 Tue 22/11/16
3 Turbin area 10,96 days Sat 12/11/16 Tue 22/11/16
4 Condensate Pump 3,63 days Sat 12/11/16 Tue 15/11/16
5 Condensate Pump 1 1,38 days Sat 12/11/16 Sun 13/11/16
6 Check (Impeler & housing , bearing, baut 1 day Sat 12/11/16 Sat 12/11/16 328
pengikat, gland packing, gasket suction &
discharge, drain plug)
7 Alignment ulang dan test running 2 hrs Sun 13/11/16 Sun 13/11/16 6;213
8 Run Test 1 hr Sun 13/11/16 Sun 13/11/16 7
9 Condensate pump 2 1,38 days Mon 14/11/16Tue 15/11/16
10 Check (Impeler & housing , bearing, baut 1 day Mon Tue 15/11/16 7;217
pengikat, gland packing, gasket suction & 14/11/16
discharge, drain plug)
11 Alignment ulang dan test running 2 hrs Tue 15/11/16 Tue 15/11/16 10
12 Run Test 1 hr Tue 15/11/16 Tue 15/11/16 11
13 Water Jet pump 4 days Sat 12/11/16 Tue 15/11/16
14 Water Jet Pump 1 2 days Sat 12/11/16 Sun 13/11/16
15 Pompa 1,25 days Sat 12/11/16 Sun 13/11/16
16 Check (Impeler & housing , bearing, baut 1 day Sat 12/11/16 Sat 12/11/16 6SS
pengikat, gland packing, gasket suction &
discharge, drain plug)
17 Alignment ulang dan test running 2 hrs Sun 13/11/16 Sun 13/11/16 16
18 Check Valve 1 day Sun 13/11/16 Sun 13/11/16
19 Check, Repair & Cleaning 1 day Sun 13/11/16 Sun 13/11/16 16
20 Ejector 0 days Sat 12/11/16 Sat 12/11/16 12/11
21 Check, Repair & Cleaning 0 days Sat 12/11/16 Sat 12/11/16 12/11
22 Water jet pump 2 2 days Mon 14/11/16Tue 15/11/16
23 Pompa 1,25 days Mon 14/11/16Tue 15/11/16
24 Check (Impeler & housing , bearing, baut 1 day Mon Mon 19
pengikat, gland packing, gasket suction & 14/11/16 14/11/16
discharge, drain plug)
25 Alignment ulang dan test running 2 hrs Tue 15/11/16 Tue 15/11/16 24
26 Check Valve 1 day Tue 15/11/16 Tue 15/11/16
27 Check, Repair & Cleaning 1 day Tue 15/11/16 Tue 15/11/16 24
28 Ejector 1 day? Sat 12/11/16 Sat 12/11/16
29 Check, Repair & Cleaning 1 day? Sat 12/11/16 Sat 12/11/16
30 Condensor 6,75 days Sat 12/11/16 Fri 18/11/16
31 Condensor side A (arah gunung) 5,67 days Sat 12/11/16 Thu 17/11/16
32 Open main hole condensor side A (arah 1,33 hrs Sun 13/11/16 Sun 13/11/16 328FS+1
gunung) day
33 Hidro test after cleaning 4 hrs Wed 16/11/16Wed 16/11/16335;37;39
34 Pengecekan cathodic protection (pasang kalau 1 day Sun 13/11/16 Mon 32
belum ada) 14/11/16
35 Close main hole condensor side A (arah 1 day Wed Thu 17/11/16 33
gunung) 16/11/16
36 Remove elbow inlet side A (arah gunung) 5 hrs Sat 12/11/16 Sat 12/11/16 328SS

Mengetahui, Dibuat Oleh,

Hendra Tanjung Rendal Har


2
Jadwal OH PLTU Pelabuhan Tarahan Unit 2

ID Task Name Duration Start Finish


06 Nov '16 Predecessors
Resource 13 Nov '16 20 Nov '16
Names 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
37 Instal elbow inlet side A (arah gunung) 5 hrs Sun 13/11/16 Sun 13/11/16 336
38 Remove outlet side A (arah gunung) 0 hrs Sun 13/11/16 Sun 13/11/16 37 13/11
39 Install Elbow outlet A (arah gunung) 0 hrs Sun 13/11/16 Sun 13/11/16 337 13/11
40 Condensor side B (arah Laut) 5 days Sun 13/11/16 Fri 18/11/16
41 Open main hole condensor side B (arah laut) 4 hrs Sun 13/11/16 Mon 14/11/1639
42 Hidro test after cleaning 4 hrs Thu 17/11/16 Thu 17/11/16 339;46;48
43 Pengecekan cathodic protection (pasang kalau 1 day Mon Tue 15/11/16 41
belum ada) 14/11/16
44 Remove elbow inlet side B (arah laut) 1 day Thu 17/11/16 Fri 18/11/16 42
45 5 hrs Sun 13/11/16 Mon 14/11/1641SS
46 Instal elbow inlet side B(arah laut) 5 hrs Mon 14/11/16Tue 15/11/16 340
47 Remove outlet side B(arah laut) 0 hrs Tue 15/11/16 Tue 15/11/16 46 15/11
48 Instal elbow outlet side B (arah laut) 0 hrs Tue 15/11/16 Tue 15/11/16 341 15/11
49 LO System 5,96 days Thu 17/11/16 Tue 22/11/16
50 MOT 0,25 days Thu 17/11/16 Thu 17/11/16
51 Pengecekan dan perbaikan motor exhaust 0,25 days Thu 17/11/16 Thu 17/11/16
venting
52 Check, Repair & Cleaning 2 hrs Thu 17/11/16 Thu 17/11/16 329

53 Line Lubrication 0,13 days Thu 17/11/16 Thu 17/11/16


54 Line Check 1 hr Thu 17/11/16 Thu 17/11/16 52
55 HP, AC & DC Oil Pump 1,5 days Sat 19/11/16 Sun 20/11/16
56 Check, Repair & Cleaning 2 hrs Sat 19/11/16 Sat 19/11/16 238SS
57 Realignment & Run Test 4 hrs Sun 20/11/16 Sun 20/11/16 56;231;235;239
58 Cooling system 5,96 days Thu 17/11/16 Tue 22/11/16
59 Oil Cooler no 1 (arah gunung) 0,92 days Thu 17/11/16 Thu 17/11/16
60 Open top cover dan bottom cover oil cooler1,33 hrs Thu 17/11/16 Thu 17/11/16 52SS
61 Hidro test dengan oli setelah cleaning tube 0,67 hrs Thu 17/11/16 Thu 17/11/16 343
62 Close top cover dan bottom cover oil cooler1,33 hrs Thu 17/11/16 Thu 17/11/16 61
63 Oil Cooler no 2 (arah laut) 0,92 days Thu 17/11/16 Fri 18/11/16
64 Open top cover dan bottom cover oil cooler1,33 hrs Thu 17/11/16 Fri 18/11/16 62
65 Hidro test dengan oli setelah cleaning tube 0,67 hrs Fri 18/11/16 Fri 18/11/16 345
66 Close top cover dan bottom cover oil cooler1,33 hrs Fri 18/11/16 Fri 18/11/16 65
67 Strainer cooling system 0,5 days Fri 18/11/16 Sat 19/11/16
68 Remove instal cover inlet strainer cooling oil 2 hrs Fri 18/11/16 Sat 19/11/16 66
cooler
69 Instal cover inlet strainer cooling oil cooler 1 hr Sat 19/11/16 Sat 19/11/16 68
70 Pengecekan dan pembersihan inlet strainer 1 hr Sat 19/11/16 Sat 19/11/16 69
generator cooling
71 Generator water cooling 3,63 days Sat 19/11/16 Tue 22/11/16
72 Pengecekan open close valve inlet dan 1 day Sat 19/11/16 Sun 20/11/16 70
outlet genertaor water cooling
73 Open cover tube generator cooling 2 hrs Sun 20/11/16 Sun 20/11/16 72
74 Close cover tube generator cooling 2 hrs Tue 22/11/16 Tue 22/11/16 75
75 Hidro test setelah pembersihan tube inlet 1 hr Tue 22/11/16 Tue 22/11/16 376
dan outlet generator water cooling

Mengetahui, Dibuat Oleh,

Hendra Tanjung Rendal Har


3
Jadwal OH PLTU Pelabuhan Tarahan Unit 2

ID Task Name Duration Start Finish


06 Nov '16 Predecessors
Resource 13 Nov '16 20 Nov '16
Names 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
76 Pengecekan kondisi tube cooling generator 1 hr Tue 22/11/16 Tue 22/11/16 75
dari bawah generator
77 Heat Exchanger turbine 4,38 days Sun 13/11/16 Thu 17/11/16
101 Boiler area 10 days Sun 13/11/16 Tue 22/11/16
102 PAF 3,38 days Sun 13/11/16 Wed 16/11/16
103 Tranducer PAF 3,38 days Sun 13/11/16 Wed 16/11/16
104 Pengecekan,Pembersihan dan perbaikan 3 hrs Sun 13/11/16 Sun 13/11/16 264SS
kebocoran pada front cover dan rear cover
tranducer dari oli
105 Pengecekan dan penggantian oli (level ±75 % 1 hr Sun 13/11/16 Sun 13/11/16 104
dari level glass)
106 Pengecekan joint coupling 1 hr Sun 13/11/16 Sun 13/11/16 105
107 Pengecekan cooling line 1 hr Sun 13/11/16 Sun 13/11/16 106
108 Pengecekan valve cooling line 1 hr Sun 13/11/16 Sun 13/11/16 107
109 Aligment (pasang baut adjuster jika belum 8 hrs Tue 15/11/16 Wed 108;266
ada) 16/11/16
110 Damper 0,88 days Tue 15/11/16 Tue 15/11/16
111 Pengecekan fan Primary 1 hr Tue 15/11/16 Tue 15/11/16 330FS+3 days
112 Pengecekan inside housing PAF 2 hrs Tue 15/11/16 Tue 15/11/16 111
113 Pengecekan perdeam suara dan screen 2 hrs Tue 15/11/16 Tue 15/11/16 112
pelindung
114 Pengecekan lock damper 2 hrs Tue 15/11/16 Tue 15/11/16 113
115 SAF 6,25 days Sun 13/11/16 Sat 19/11/16
116 Tranducer SAF 5,75 days Sun 13/11/16 Fri 18/11/16
117 Pengecekan dan perbaikan kebocoran pada 2 hrs Sun 13/11/16 Sun 13/11/16 104SS
front cover dan rear cover tranducer dari oli
118 Pengecekan,Pembersihan dan penggantian oli 4 hrs Sun 13/11/16 Sun 13/11/16 117
(level ±75 % dari level glass)
119 Pengecekan joint coupling 2 hrs Sun 13/11/16 Sun 13/11/16 118
120 aligment (pasang baut anjuster jika belum ada)1 day Thu 17/11/16 Fri 18/11/16 119;270
121 Damper 0,5 days Fri 18/11/16 Sat 19/11/16
122 Pengecekan fan Secondary 1 hr Fri 18/11/16 Fri 18/11/16 120
123 Pengecekan inside housing SAF 1 hr Fri 18/11/16 Fri 18/11/16 122
124 Pengecekan perdeam suara dan screen 1 hr Sat 19/11/16 Sat 19/11/16 123
pelindung
125 Pengecekan lock damper 1 hr Sat 19/11/16 Sat 19/11/16 124
126 IDF 1 day Tue 22/11/16 Tue 22/11/16
127 Tranducer IDF 1 day Tue 22/11/16 Tue 22/11/16
128 Pengecekan dan perbaikan kebocoran pada 2 hrs Tue 22/11/16 Tue 22/11/16 374
front cover dan rear cover tranducer dari oli
129 Pengecekan,Pembersihan dan penggantian oli 2 hrs Tue 22/11/16 Tue 22/11/16 128
(level ±75 % dari level glass)
130 Pengecekan joint coupling 2 hrs Tue 22/11/16 Tue 22/11/16 129
131 Pengecekan cooling line 1 hr Tue 22/11/16 Tue 22/11/16 130
132 Pengecekan valve cooling line 1 hr Tue 22/11/16 Tue 22/11/16 131
133 Damper 1 day Tue 22/11/16 Tue 22/11/16
134 Pengecekan fan IDF 4 hrs Tue 22/11/16 Tue 22/11/16 128SS

Mengetahui, Dibuat Oleh,

Hendra Tanjung Rendal Har


4
Jadwal OH PLTU Pelabuhan Tarahan Unit 2

ID Task Name Duration Start Finish


06 Nov '16 Predecessors
Resource 13 Nov '16 20 Nov '16
Names 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
135 Pengecekan inside housing IDF 2 hrs Tue 22/11/16 Tue 22/11/16 134
136 Pengecekan lock damper 2 hrs Tue 22/11/16 Tue 22/11/16 135
137 Recycle Air Fan 0,5 days Sun 13/11/16 Sun 13/11/16
138 Pompa root blower 0,5 days Sun 13/11/16 Sun 13/11/16
139 Penambahan atau penggantian oli dan 2 hrs Sun 13/11/16 Sun 13/11/16 104SS
Pembersihan (level ±75 % dari level glass)
140 Pengecekan check valve 1 hr Sun 13/11/16 Sun 13/11/16 139
141 Pengecekan kekencang v- belt 1 hr Sun 13/11/16 Sun 13/11/16 140
142 Super Heater 6 days Tue 15/11/16 Sun 20/11/16
143 Pengecekan manual valve exhaust blow up 1 day Tue 15/11/16 Tue 15/11/16 330FS+3 days
144 Pengecekan valve back wash pada elevasi 7000 1 hr Wed 16/11/16Wed 16/11/16143
145 Pengecekan drainage valve blowdown super 2 hrs Wed Wed 144
heater 16/11/16 16/11/16
146 Pengecekan valve sampling water superheater 2 days Wed Fri 18/11/16 145
(penggatian tabung water sampling) 16/11/16
147 Pengecekan Hanger of Superheater and 1 day Sun 20/11/16 Sun 20/11/16 348
Wearproof Cover
148 Economizer 0 days Sun 20/11/16 Sun 20/11/16 20/11
149 Perbaikan (berdasarkan hasil pengecekan 0 days Sun 20/11/16 Sun 20/11/16 350 20/11
operasi)
150 Steam Drum 1,13 days Tue 15/11/16 Wed 16/11/16
151 Pengecekan Drum Hanger 2 hrs Tue 15/11/16 Tue 15/11/16 143SS
152 Pengecekan level sigh glass steam drum arah laut 1 hr Tue 15/11/16 Tue 15/11/16 151

153 Pengecekan level sigh glass steam drum arah 1 hr Tue 15/11/16 Tue 15/11/16 152
gunung
154 Pengecekan valve venting steam drum dan 4 hrs Tue 15/11/16 Tue 15/11/16 153
penggantian
155 Pengecekan safety valve steam drum 1 hr Wed 16/11/16Wed 16/11/16154
156 Pengecekan mainhole steam drum arah laut 0 days Wed Wed 155 16/11
(open ) 16/11/16 16/11/16
157 Pengecekan mainhole steam drum arah gunung 0 days Wed Wed 156 16/11
(open) 16/11/16 16/11/16
158 Water Wall 0,75 days Sat 19/11/16 Sat 19/11/16
159 Pengecekan Front Water Wall 1 hr Sat 19/11/16 Sat 19/11/16 364
160 Pengecekan Back Water Wall 1 hr Sat 19/11/16 Sat 19/11/16 159
161 Pengecekan Side Water Wall 1 hr Sat 19/11/16 Sat 19/11/16 160
162 Pengecekan Header Water Wall 1 hr Sat 19/11/16 Sat 19/11/16 161
163 Pengecekan Fixed Device for Water Wall 1 hr Sat 19/11/16 Sat 19/11/16 162
164 Pengecekan Water Cooled Plenum 1 hr Sat 19/11/16 Sat 19/11/16 163
165 Blowdown 2,38 days Wed 16/11/16Fri 18/11/16
170 Air Heater 4,5 days Fri 18/11/16 Tue 22/11/16
183 Furnace 5,5 days Sun 13/11/16 Fri 18/11/16
190 Cyclone 0,13 days Sat 19/11/16 Sat 19/11/16
193 Burner 0,5 days Sun 20/11/16 Sun 20/11/16
198 ESP 1,88 days Mon 21/11/16Tue 22/11/16
208 Scope Listrik 11 days Sat 12/11/16 Tue 22/11/16
Mengetahui, Dibuat Oleh,

Hendra Tanjung Rendal Har


5
Jadwal OH PLTU Pelabuhan Tarahan Unit 2

ID Task Name Duration Start Finish


06 Nov '16 Predecessors
Resource 13 Nov '16 20 Nov '16
Names 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
209 Turbine area 8,5 days Sat 12/11/16 Sun 20/11/16
210 Condensate Pump 3,63 days Sat 12/11/16 Tue 15/11/16
211 Motor 1 1,38 days Sat 12/11/16 Sun 13/11/16
212 Check (housing motor, terminal motor, 6 hrs Sat 12/11/16 Sat 12/11/16 328
bearing, belitan stator)
213 Cleaning & Grasing 2 hrs Sat 12/11/16 Sat 12/11/16 212
214 Run test 1 hr Sun 13/11/16 Sun 13/11/16 8FF
215 Motor 2 2,38 days Sun 13/11/16 Tue 15/11/16
216 Check (housing motor, terminal motor, 6 hrs Sun 13/11/16 Sun 13/11/16 7
bearing, belitan stator)
217 Cleaning & Greasing 2 hrs Mon 14/11/16Mon 14/11/16216
218 Run Test 1 hr Tue 15/11/16 Tue 15/11/16 12FF
219 Water Jet Pump 4 days Sat 12/11/16 Tue 15/11/16
220 Motor 1 3,5 days Sat 12/11/16 Tue 15/11/16
221 Check (housing motor, terminal motor, 6 hrs Sat 12/11/16 Sat 12/11/16 16SS
bearing, belitan stator)
222 Cleaning & Greasing 2 hrs Sat 12/11/16 Sat 12/11/16 221
223 Run Test 1 hr Tue 15/11/16 Tue 15/11/16 11FF
224 Motor 2 2 days Mon 14/11/16Tue 15/11/16
225 Check (housing motor, terminal motor, 2 hrs Mon Mon 24SS
bearing, belitan stator) 14/11/16 14/11/16
226 Cleaning & Greasing 2 hrs Mon 14/11/16Mon 14/11/16225
227 Run Test 1 hr Tue 15/11/16 Tue 15/11/16 27FF
228 Oil Pump Motor 3,5 days Thu 17/11/16 Sun 20/11/16
229 DC Oil Pump 3,5 days Thu 17/11/16 Sun 20/11/16
230 Check (panel, terminal motor, belitan, 7 hrs Thu 17/11/16 Thu 17/11/16 329
pressure indicator)
231 Cleaning & Greasing 1 hr Thu 17/11/16 Thu 17/11/16 230
232 Run test 1 hr Sun 20/11/16 Sun 20/11/16 57FF
233 AC Oil Pump 2,5 days Fri 18/11/16 Sun 20/11/16
234 Check (panel, terminal motor, belitan, 7 hrs Fri 18/11/16 Fri 18/11/16 231
pressure indicator)
235 Cleaning & Greasing 1 hr Fri 18/11/16 Fri 18/11/16 234
236 Run Test 1 hr Sun 20/11/16 Sun 20/11/16 57FF
237 HP Oil Pump 1,5 days Sat 19/11/16 Sun 20/11/16
238 Check (panel, terminal motor, belitan, 7 hrs Sat 19/11/16 Sat 19/11/16 235
pressure indicator)
239 Cleaning & Greasing 1 hr Sat 19/11/16 Sat 19/11/16 238
240 Run Test 1 hr Sun 20/11/16 Sun 20/11/16 57FF
241 Heataer 0,38 days Sat 19/11/16 Sat 19/11/16
242 High Pressure Heater 0,13 days Sat 19/11/16 Sat 19/11/16
243 Pengecekan keakuratan level HPH local dan DCS1 hr Sat 19/11/16 Sat 19/11/16 328FS+7 days
244 Low Pressure Heater 0,13 days Sat 19/11/16 Sat 19/11/16
245 Pengecekan keakuratan level LPH local dan DCS1 hr Sat 19/11/16 Sat 19/11/16 243
246 Gland Steam Heater 0,13 days Sat 19/11/16 Sat 19/11/16
247 Pengecekan fungsional kerja turbine hotwell 1 hr Sat 19/11/16 Sat 19/11/16 245
level PID Control
Mengetahui, Dibuat Oleh,

Hendra Tanjung Rendal Har


6
Jadwal OH PLTU Pelabuhan Tarahan Unit 2

ID Task Name Duration Start Finish


06 Nov '16 Predecessors
Resource 13 Nov '16 20 Nov '16
Names 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
248 Governing system 0,56 days Tue 15/11/16 Tue 15/11/16
249 Electric motor speed adjusment 0,13 days Tue 15/11/16 Tue 15/11/16
250 Check & Cleaning (terminal motor, mounting) 0,5 hrs Tue 15/11/16 Tue 15/11/16 330FS+3 days
251 Run Test 0,5 hrs Tue 15/11/16 Tue 15/11/16 250
252 Manual adjusment speed 0,13 days Tue 15/11/16 Tue 15/11/16
253 Pengecekan handle speed adjusment 0,5 hrs Tue 15/11/16 Tue 15/11/16 251
254 Pengecekan fungsi kerja handle speed 0,5 hrs Tue 15/11/16 Tue 15/11/16 253
adjusment
255 Emergency tripped Local (koordinasi dengan Li 0,31 days Tue 15/11/16 Tue 15/11/16
Chun)
256 Check, Repair & Cleaning 1 hr Tue 15/11/16 Tue 15/11/16 254
257 Test 1,5 hrs Tue 15/11/16 Tue 15/11/16 256
258 Elektrik motor turning gear 0,38 days Thu 17/11/16 Thu 17/11/16
259 Check (terminal, rotor, stator, belitan) 1 hr Thu 17/11/16 Thu 17/11/16 329
260 Cleaning & Greasing 1 hr Thu 17/11/16 Thu 17/11/16 259
261 Run Test Local & Remote 1 hr Thu 17/11/16 Thu 17/11/16 260
262 Boiler Area 9,38 days Sun 13/11/16 Tue 22/11/16
263 Elektrik motor PAF 2,38 days Sun 13/11/16 Tue 15/11/16
264 Check (Housing, Terminal, rotor, stator, belitan, 2 days Sun 13/11/16 Mon 328FS+1
Bearing) 14/11/16 day
265 Cleaning & Greasing 2 hrs Tue 15/11/16 Tue 15/11/16 264
266 Run Test No Load 1 hr Tue 15/11/16 Tue 15/11/16 265
267 Elektrik motor SAF 2,38 days Tue 15/11/16 Thu 17/11/16
268 Check (Housing, Terminal, rotor, stator, belitan, 2 days Tue 15/11/16 Thu 17/11/16 266
Bearing)
269 Cleaning & Greasing 2 hrs Thu 17/11/16 Thu 17/11/16 268
270 Run Test No Load 1 hr Thu 17/11/16 Thu 17/11/16 269
271 Elektrik motor IDF 2,38 days Sun 20/11/16 Tue 22/11/16
272 Check (Housing, Terminal, rotor, stator, belitan, 2 days Sun 20/11/16 Mon 330FS+8
Bearing) 21/11/16 days
273 Cleaning & Greasing 2 hrs Tue 22/11/16 Tue 22/11/16 272
274 Run Test No Load 1 hr Tue 22/11/16 Tue 22/11/16 273
275 Elektrik motor RAF 1 day Thu 17/11/16 Fri 18/11/16
276 Check (Housing, Terminal, rotor, stator, belitan, 7 hrs Thu 17/11/16 Fri 18/11/16 270
Bearing)
277 Run Test 1 hr Fri 18/11/16 Fri 18/11/16 276
278 Super Heater 0,5 days Wed 16/11/16Wed 16/11/16
279 Pengecekan electrik valve exhaust blow up 1 hr Wed 16/11/16Wed 16/11/16330FS+4 days
280 Cek thermocouple 1 hr Wed 16/11/16Wed 16/11/16279
281 Pengecekan Spray Type Desuperheater 1 hr Wed 16/11/16Wed 16/11/16280
282 Pengecekan drainage valve blowdown super 1 hr Wed Wed 281
heater 16/11/16 16/11/16
283 Burner 6,5 days Mon 14/11/16Sun 20/11/16
284 Main Oil Pump 0,5 days Sun 20/11/16 Sun 20/11/16
285 Pengecekan motor 4 hrs Sun 20/11/16 Sun 20/11/16 195SS
286 Electric system 1 day Mon 14/11/16Mon 14/11/16
287 Pengecekan supply power 2 hrs Mon 14/11/16Mon 14/11/16330FS+2 days
Mengetahui, Dibuat Oleh,

Hendra Tanjung Rendal Har


7
Jadwal OH PLTU Pelabuhan Tarahan Unit 2

ID Task Name Duration Start Finish


06 Nov '16 Predecessors
Resource 13 Nov '16 20 Nov '16
Names 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
288 Pengecekan fungsional maju mundur elektric 2 hrs Mon Mon 287
motor 14/11/16 14/11/16
289 Pengeckan Igintion system 2 hrs Mon 14/11/16Mon 14/11/16288
290 Pengecekan push bottom fungsional burner 2 hrs Mon 14/11/16Mon 14/11/16289
291 ESP 1 day Wed 16/11/16Wed 16/11/16
292 Pengecekan Elektrik Motor Rapping Anode 2 hrs Wed 16/11/16Wed 16/11/16330FS+4 days
293 Pengecekan Elektrik Motor Rapping Cathode 2 hrs Wed 16/11/16Wed 16/11/16292
294 Pengecekan Elektric & Pneumatic Box Panel 2 hrs Wed Wed 293
control 16/11/16 16/11/16
295 Pengecekan keramik isolator 2 hrs Wed 16/11/16Wed 16/11/16294
296 Steam Drum 1 day Wed 16/11/16Thu 17/11/16
297 Pengecekan electrode steam drum level 4 hrs Wed 16/11/16Wed 16/11/16282
298 Pengecekan level steam drum transmitter 4 hrs Thu 17/11/16 Thu 17/11/16 297
299 Main Generator 3 days Sun 20/11/16 Tue 22/11/16
300 Body generator 1 day Sun 20/11/16 Sun 20/11/16
301 Cleaning inside outside 4 hrs Sun 20/11/16 Sun 20/11/16 328FS+8 days
302 Check & Cleaning all instrument sensors 4 hrs Sun 20/11/16 Sun 20/11/16 301
303 Support bearing arah Laut 1 day Mon 21/11/16Mon 21/11/16
304 Check & Cleaning all instrument sensors 8 hrs Mon Mon 328FS+9
21/11/16 21/11/16 days
305 Carbon Brush 1 day Tue 22/11/16 Tue 22/11/16
306 Check & Cleaning slip ring 1 day Tue 22/11/16 Tue 22/11/16 304
307 PROTECTION RELAY PANEL & EXCITATION SYSTEM 1,25 days Thu 17/11/16 Fri 18/11/16
PANEL
308 Cleaning panel 4 hrs Thu 17/11/16 Thu 17/11/16 328FS+5
days
309 Pengencangan koneksi busbar 4 hrs Thu 17/11/16 Thu 17/11/16 308
310 Pengecekan insulation power cable 1 hr Fri 18/11/16 Fri 18/11/16 309
311 Simulasi Local & Remote CCR 1 hr Fri 18/11/16 Fri 18/11/16 310

312 Panel AVR 1,13 days Fri 18/11/16 Sat 19/11/16


313 Cleaning Panel 4 hrs Fri 18/11/16 Fri 18/11/16 328FS+6
days
314 Pengencangan Terminal 4 hrs Fri 18/11/16 Fri 18/11/16 313

315 Check & test protection relay 1 hr Sat 19/11/16 Sat 19/11/16 314
316 TRANSFORMATOR 20kV 2 days Fri 18/11/16 Sat 19/11/16
317 General Check 4 hrs Fri 18/11/16 Fri 18/11/16 328FS+6 days
318 Pengencangan terminal 4 hrs Fri 18/11/16 Fri 18/11/16 317
319 Cleaning trafo 4 hrs Sat 19/11/16 Sat 19/11/16 318
320 Check semua sensor dan instrumentasi 4 hrs Sat 19/11/16 Sat 19/11/16 319
321 Panel 3 days Sat 19/11/16 Mon 21/11/16
322 400 V 1 day Sat 19/11/16 Sat 19/11/16 328FS+7 days
323 6 KV 1 day Sun 20/11/16 Sun 20/11/16 322
324 20 KV 1 day Mon 21/11/16Mon 21/11/16323
325 Scope Operasi 11,71 days Sat 12/11/16 Wed 23/11/16
326 STOP UNIT 5 days Sat 12/11/16 Wed 16/11/16
Mengetahui, Dibuat Oleh,

Hendra Tanjung Rendal Har


8
Jadwal OH PLTU Pelabuhan Tarahan Unit 2

ID Task Name Duration Start Finish


06 Nov '16 Predecessors
Resource 13 Nov '16 20 Nov '16
Names 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
330 BOILER STOP 0 days Sat 12/11/16 Sat 12/11/16 12/11
331 Turbine Area 6,58 days Sat 12/11/16 Fri 18/11/16
332 Water Eject Tank 1 day Sat 12/11/16 Sat 12/11/16
333 cleaning tanki air water Eject pump 1 day Sat 12/11/16 Sat 12/11/16 328SS
334 Condensor side A (arah gunung) 3,54 days Sat 12/11/16 Wed 16/11/16
335 Cleaning inside turbe inlet dan outlet 3 days Sun 13/11/16 Wed 16/11/1632
336 Cleaning strainer inlet condensor 4 hrs Sat 12/11/16 Sun 13/11/16 36
337 Cleaning cone strainer outlet condensor 0 hrs Sun 13/11/16 Sun 13/11/16 38 13/11
338 Condensor side B (arah laut) 3 days Mon 14/11/16Thu 17/11/16
339 Cleaning inside turbe inlet dan outlet 3 days Mon 14/11/16Thu 17/11/16 41
340 Cleaning strainer inlet condensor 4 hrs Mon 14/11/16Mon 14/11/1645
341 Cleaning cone strainer outlet condensor 0 hrs Tue 15/11/16 Tue 15/11/16 47 15/11
342 Oil Cooler 1 0,5 days Thu 17/11/16 Thu 17/11/16
343 Cleaning tube oil cooler 4 hrs Thu 17/11/16 Thu 17/11/16 60
344 Oil Cooler 2 0,5 days Fri 18/11/16 Fri 18/11/16
345 Cleaning tube oil cooler 4 hrs Fri 18/11/16 Fri 18/11/16 64
346 Boiler Area 10,58 days Sat 12/11/16 Tue 22/11/16
347 Super Heater 1 day Sat 19/11/16 Sat 19/11/16
348 Cleaning 1 day Sat 19/11/16 Sat 19/11/16 364
349 Economizer 1 day Sun 20/11/16 Sun 20/11/16
350 Cleaning 1 day Sun 20/11/16 Sun 20/11/16 348
351 1st Primary Air Heater 0,5 days Mon 21/11/16Mon 21/11/16
352 Cleaning 4 hrs Mon 21/11/16Mon 21/11/16350
353 Secondary Air Heater 0,5 days Mon 21/11/16Mon 21/11/16
354 Cleaning 4 hrs Mon 21/11/16Mon 21/11/16352
355 Gas duct 2 days Sun 20/11/16 Mon 21/11/16
356 Cleaning 2 days Sun 20/11/16 Mon 21/11/16330FS+8 days
357 Cute + casing coal feeder 1, 2 & 3 1 day Sat 12/11/16 Sat 12/11/16
358 Cleaning Cute + casing coal feeder 1 day Sat 12/11/16 Sat 12/11/16 328SS
359 Safety Explosive rooms 0,25 days Fri 18/11/16 Fri 18/11/16
360 Cleaning 2 hrs Fri 18/11/16 Fri 18/11/16 364SS
361 Cyclone 6 days Sun 13/11/16 Fri 18/11/16
362 Drain pasir 1 day Sun 13/11/16 Sun 13/11/16 330FS+1 day
363 Lepas nozle 1 day Mon 14/11/16Mon 14/11/16366SS
364 cleaning tumpukan fly ash 1 day Fri 18/11/16 Fri 18/11/16 371
365 Furnance 3 days Mon 14/11/16Wed 16/11/16
366 Drain pasir 1 day Mon 14/11/16Mon 14/11/16330FS+2 days
367 Cek refactory 1 day Tue 15/11/16 Tue 15/11/16 366
368 cek nozle 1 day Tue 15/11/16 Tue 15/11/16 367SS
369 cek refactory air chamber 1 day Wed 16/11/16Wed 16/11/16330FS+4 days
370 SAF 1 day Thu 17/11/16 Thu 17/11/16
371 cek air swing 1 day Thu 17/11/16 Thu 17/11/16 369
372 ESP 3 days Sat 19/11/16 Mon 21/11/16
373 Cleaning dan cek visual 2 days Sat 19/11/16 Sun 20/11/16 348SS
374 Ash Tank 2 days Sun 20/11/16 Mon 21/11/16356SS
375 Generator Water Cooling 2 days Sun 20/11/16 Tue 22/11/16

Mengetahui, Dibuat Oleh,

Hendra Tanjung Rendal Har


9
Jadwal OH PLTU Pelabuhan Tarahan Unit 2

ID Task Name Duration Start Finish


06 Nov '16 Predecessors
Resource 13 Nov '16 20 Nov '16
Names 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
376 Pengecekan dan pembersihan inlet dan outlet 2 days Sun 20/11/16 Tue 22/11/16 73
generator water cooling
377 Start Unit 5,71 days Fri 18/11/16 Wed 23/11/16
378 Boiler 5,5 days Fri 18/11/16 Wed 23/11/16
379 Pra Start Boiler 4,5 days Fri 18/11/16 Tue 22/11/16
380 Pengisian pasir 2 days Fri 18/11/16 Sun 20/11/16 189
381 Bubbling test 4 hrs Tue 22/11/16 Tue 22/11/16 374
382 IDF running test 4 hrs Tue 22/11/16 Tue 22/11/16 381SS
383 PAF running test 4 hrs Tue 22/11/16 Tue 22/11/16 381SS
384 SAF running test 4 hrs Fri 18/11/16 Fri 18/11/16 371
385 Recycle Air Fan 4 hrs Tue 22/11/16 Tue 22/11/16 381SS
386 Boiler Start 1 day Tue 22/11/16 Wed 23/11/16
387 Start up sd sinkron 8 hrs Tue 22/11/16 Wed 23/11/16381
388 Turbin 0,88 days Tue 22/11/16 Wed 23/11/16
389 Heating line 2 hrs Tue 22/11/16 Wed 23/11/1676
390 Sinkron turbin 5 hrs Wed 23/11/16Wed 23/11/16389
391 Scope Tambahan 1 day? Sat 12/11/16 Sat 12/11/16
392 Deep well 1 day Sat 12/11/16 Sat 12/11/16
393 Persiapan pemindahan pompa dozing dearator 1 day? Sat 12/11/16 Sat 12/11/16
394 Pengecekan cyclone 1 day? Sat 12/11/16 Sat 12/11/16
395 Penggantian valve di area steam drum dan top header 1 day? Sat 12/11/16 Sat 12/11/16
super heater
396 Penggantian Inverter SAF 110 kW 1 day? Sat 12/11/16 Sat 12/11/16
397 Perbaikan MSV 1 day? Sat 12/11/16 Sat 12/11/16
398 Penggantian Inverter SAF 110 kW 1 day? Sat 12/11/16 Sat 12/11/16
399 Simulasi trafo ESP 2 1 day? Sat 12/11/16 Sat 12/11/16
400 Penggantian Spiral Wound Gasket (SWG) area steam 1 day? Sat 12/11/16 Sat 12/11/16
drum dan top Header superheater
401 Pengecekan steam drum inside (Masuk standart 1 day? Sat 12/11/16 Sat 12/11/16
scope durasi setahun sekali)
402 Aktifkan ball cleaning condenser unit 2 1 day? Sat 12/11/16 Sat 12/11/16
403 Penggantian baut strainer condensor 1 day? Sat 12/11/16 Sat 12/11/16

404 Pembuatan Main Hole di flue gas (elbow) 1 day? Sat 12/11/16 Sat 12/11/16

405 Cleaning outer tube area flue gas 1 day? Sat 12/11/16 Sat 12/11/16

406 Penambahan temperature gauge outlet economzer 1 day? Sat 12/11/16 Sat 12/11/16