KONKAN RAILWAY CORPORATION LIMITED

INTERNSHIP PROJECT
FOOTOVER BRIDGE MURDESHWAR
QUANTITY CALCULATION OF RCC AND PCC WORK
S.NO ITEM Nos L B H Qty Total qty Unit
1 PCC (1:3:6)
1.1 F6 2 3.9 2.1 0.1 1.638
1.2 F5 2 5.7 1.3 0.1 1.482
1.3 F4 2 5.2 5.2 0.1 5.408
1.4 F3 6 3.9 2.2 0.1 5.148
1.5 F2 2 4.7 3.9 0.1 3.666
1.6 F1 4 3.9 2.2 0.1 3.432 20.774 cum
1.7 F7 2
2 RCC(FOUNDATION)
2.1 F1 4 3.7 2 0.6 17.76
2.2 F2 2 4.5 3.7 0.6 19.98
2.3 F3 6 3.7 2 0.6 26.64
2.4 F4 2 5 5 0.6 30
2.5 F5 2 5.5 1.1 2 24.2
2.6 F6 2 3.7 2 0.3 4.44 123.02 cum
3 RCC(COLUMNS)
3.1 F1
3.1.1 4 2.265 0.35 0.35 1.10985
3.1.2 4 2.965 0.35 0.35 1.45285
3.2 F2 8 3.665 0.35 0.35 3.5917
3.3 F3 0
3.3.1 4 4.385 0.4 0.4 2.8064
3.3.2 4 5.065 0.4 0.4 3.2416
3.3.3 4 5.765 0.4 0.4 3.6896
3.4 F4 8 6.315 0.4 0.4 8.0832 23.9752 CUM
3.5 F6
4 RCC(BEAMS)
4.1 F1 4 2.95 0.35 0.6 2.478
4.2 F2 4 2.95 0.35 0.6 2.478
4 3.15 0.35 0.6 2.646
4.3 F3 6 3 0.4 0.6 4.32
4.4 F4 4 3 0.4 0.6 2.88
4 3 0.4 0.75 3.6
4 3.4 0.4 0.6 3.264
4 3.4 0.4 0.75 4.08 25.746 CUM

TOTAL QTY 193.5152 CUM