INDICATIVE QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMP

Name of the Customer: NUCLEAR POWER CORPORATION


QAP FOR submersible pump QAP no :
OF INDIA LIMITED.

Rev. no : 0
Name of the EPC Contractor: VENDOR: M/s
Date :

Name of the Project: No of Pages: Page 1 of 3


SUB PO NO:
KAKRAPAR ATOMIC POWER PROJECT - 3 & 4 Ref. Our W. O. No.:

1 2 3 4 5 6 7 8 9 10 11
SL. COMPONENT CHARACTERISTICS CATEGORY TYPE / METHOD QUANTUM REFERENCE ACCEPTANCE NORM FORMAT AGENCY REMARKS
NO. OF CHECK OF CHECK DOC. OF REMARK
RECORD P W R
1 RAW MATERIAL INSPECTION
1.1 Motor Body Suction Chemical & Mechanical CRITICAL CHEMICAL & PER HEAT LM6 IS:617-4600 LM6 IS:617-4600 OR BS-1490 MTC 3 2 1 Ref. General
Shell Discharge Properties MECHANICAL OR BS-1490 Note No.1
Sheet Diffuser Top CHECK
End Shield Bottom
End Shield

Visual & Dimensional MAJOR VISUAL & 100% As per relevant As per relevant standard & IR 3 2 1
MEASUREMENT Critical standard & Drawing
Dimensions Drawing
only
1.2 Impeller Chemical & Mechanical CRITICAL CHEMICAL & PER HEAT Bronze LTB2 Bronze LTB2 IS:318 MTC 3 2 1 Ref. General
Properties MECHANICAL IS:318 Note No.1
CHECK

Visual & Dimensional MAJOR VISUAL & 100% As per relevant As per relevant standard & IR 3 2 1
MEASUREMENT standard & Drawing
Drawing
1.3 Base Plate Chemical & Mechanical MAJOR CHEMICAL & PER HEAT C.I. C.I. MTC 3 2 1 Ref. General
Properties MECHANICAL IS:210 FG 200 IS:210 FG 200 Note No.1
CHECK

Visual & Dimensional MAJOR VISUAL & 100% As per relevant As per relevant standard & IR 3 2 1
MEASUREMENT Critical standard & Drawing
Dimensions Drawing
only
1.4 Wear Plate Chemical & Mechanical MAJOR CHEMICAL & PER HEAT SS AISI-304 SS AISI-304 MTC 3 2 1
Properties MECHANICAL OR CF8 OR CF8
CHECK

Visual & Dimensional MAJOR VISUAL & 100% As per relevant As per relevant standard & IR 3 2 1
MEASUREMENT Critical standard & Drawing
Dimensions Drawing
only
INDICATIVE QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMP
Name of the Customer: NUCLEAR POWER CORPORATION
QAP FOR submersible pump QAP no :
OF INDIA LIMITED.

Rev. no : 0
Name of the EPC Contractor: VENDOR: M/s
Date :

Name of the Project: No of Pages: Page 2 of 3


SUB PO NO:
KAKRAPAR ATOMIC POWER PROJECT - 3 & 4 Ref. Our W. O. No.:
1.5 Shaft Chemical & Mechanical CRITICAL CHEMICAL & PER HEAT SS AISI 431 SS AISI 431 MTC 3 2 1 Ref. General
Properties MECHANICAL Note No.1 & 2
CHECK

Visual & Dimensional MAJOR VISUAL & 100% As per relevant As per relevant standard & IR 3 2 1
MEASUREMENT Critical standard & Drawing
Dimensions Drawing
only
1.6 Bolting Material Chemical & Mechanical MAJOR CHEMICAL & As per A193 GR.B7 / A193 GR.B7 / MTC 3 2 1
Properties MECHANICAL material A194 GR.2H A194 GR.2H
CHECK specificatio
n
Visual & Dimensional MAJOR VISUAL & 100% As per relevant As per relevant standard & IR 3 2 1
MEASUREMENT standard & Drawing
Drawing

2.0 ASSEMBLY & TESTING


2.1 Performance Test Q v/s H MAJOR Measurement 100% ISI4220 ISI4220 IR 3 2 1 C.H.P. Ref.
Q v/s P As per approved As per approved procedure General Note
Q v/s n procedure No.5
Minimum submergence

2.2 Overall Dimension MAJOR Measurement Sampling Approved Drawing Approved Drawing IR 3 2 1

3.0 FINAL
INSPECTION
3.1 Complete Pump Visual / record checking MAJOR Record Checking 100% Assembly record Approved drawing / approved Earlier 3 2 1 C.H.P.
and Test Data sheet defined
Certificate
3.2 Painting & packing MAJOR Visual 100% Mfg Standard Mfg Standard ………… 3 2 1
….
3.3 Documentation Verification of MAJOR Verification 100% As per contract As per contract Spec. End 3 2 1
documentation Spec. Document
LEGENDS :
P - PERFORMING AGENCY 1 - NPCIL IR - INSPECTION REPORT
R - REVIEWING AGENCY 2 - CONTRACOR DP - DYE PENTRATION TEST
W - WITNESING AGENCY 3 - MANUFACTURER
CHP- CUSTOMER HOLD POINT
INDICATIVE QUALITY ASSURANCE PLAN FOR SUBMERSIBLE PUMP
Name of the Customer: NUCLEAR POWER CORPORATION
QAP FOR submersible pump QAP no :
OF INDIA LIMITED.

Rev. no : 0
Name of the EPC Contractor: VENDOR: M/s
Date :

Name of the Project: No of Pages: Page 3 of 3


SUB PO NO:
KAKRAPAR ATOMIC POWER PROJECT - 3 & 4 Ref. Our W. O. No.:

GENERAL NOTES :

1) Compliance test certificat shall be submitted.

2) All test reports, test certificates and inspection reports shall be reviewed by Manufacturer before submitting the same for verification by Purchaser.

3) Calibrated instruments shall be used during inspection, examination and testing.

4) Equipment shall be suitably packed with proper supports / covered and care shall be taken for transportation.

5) Spares shall undergo same checks as mentioned QAP.

6) Balancing will be done at reduced speed. However, allowable un-balance shall be calculated at rated speed.

7) Hydro test shall be done on suction shell and discharge shell. Test pressure shall be two times of duty points or 1.5 times shut of head, whichever is higher.

8) NPCIL will inspect the components visually and review Compliance Certificate submitted by PUMP VENDOR for dimensional inspection.

Any deviation to this QAP shall be brought out by vendor in his offer failing which this QAP shall be complied duly.

Prepared by Reviewed by Checked by Checked by APPROVED by

Pump VENDOR Pump VENDOR VENDOR NPCIL NPCIL