1. Introduction ........................................................................................................................ 3
2. Scope .................................................................................................................................... 3
3. Standard .............................................................................................................................. 3
4. Reference ............................................................................................................................. 3
9. Personnel ............................................................................................................................. 5
2. Scope
This method statement is applicable for G.I. sheet metal ductworks for the ventilating and
air-conditioning systems employing the approved materials.
This method statement also focuses within site materials inspection, installation, testing
method to ensure that the G.I. sheet metal ductworks for the ventilating and air-conditioning
systems supplied, installed, inspected and tested for the works is in accordance with project
requirements. The work method summarizes into the following:
2.1 Preparation works
2.2 Delivery, inspection and storage of materials
2.3 Setting out plans
2.4 Fabrication and Installation of G.I. sheet metal ductworks for the ventilating and air-
conditioning systems
2.5 Inspection and testing of G.I. sheet metal ductworks for the ventilating and air-
conditioning systems
3. Standard
TCXD 232:1999: Ventilating, air-conditioning and Cooling system-Manufacture,
installation and acceptance
TCVN 5687:2010 : Ventilation-air conditioning – Design standard
4. Reference
6. Specification Clause
Refer to General requirements for Mechanical System (special in HVAC Item).
8. Construction Equipment
PPE for all staff and labors
Measuring tapes
Setting out markers
Spirit levels
Electric hand grinders
9. Personnel
A management team will handle the entire project and manpower which includes staff,
engineers, logistics, site coordination, etc.
Prior deployment, selected and well trained staff and engineers to be stationed to site will be
organized, oriented and dispatched to their various specific assignments on site.
Teams of skilled labors, specialized technicians, helpers will be deployed specifically to
undertake the installation of air ducting works.
The entire teams of managers, staff, engineers and labors will undergo the sub-contractor in-
house safety training prior dispatching to site. Moreover, the entire sub-contractor team will
undergo site HSE orientation as part of project requirement.
10. Materials
All G.I. sheet metal ductworks and associated accessories for the ventilating and air-
conditioning systems will be delivered to site as per the approved materials and
manufacturer's method of unloading, storing and handling.
Prior inspection, all necessary related documents will be prepared and copies to be issued to
the inspecting team.
All G.I. sheet metal ductworks, fittings and accessories delivered to site will be inspected as
per approved materials submittals.
All G.I. sheet metal ductworks materials delivered to site will be inspected by the store-in-
charge, the QA/QC, site engineer. Any defective and damaged materials will not be accepted
and will be replaced with new materials.
Upon completion of inspection, store-in-charge will ensure that the materials unloaded will
be stored in well ventilated, dry and shaded area. Proper tagging will be displayed to ensure
correct issuance and dispatching to site personnel.
Site engineers upon material request will inspect materials prior installation
Site engineers and supervisors will ensure proper handling and shifting of delivered materials
from store to site.
12.2.2 Material of Support: Material of Support for ducting system using Angle bar
40~50mm for Rectangular Duct & Hanger bar for Spiral duct.
*.Installation work:
Ducting system had installed by scaffolding & forklift car depend on
condition and duct size.
No Use Chair
Plate Form
Safety Safety
Board Board
H of Hand Rail is
09~1.0m
Don’t standing Safety Control
on scaffolding Board Panel
during time
moving it. Safety
Board
Signal
Board
Step 3:Cover prevent dirty. Step 4: Fixed support for Spiral duct.
13. Responsibility
13.1 Project Engineer-in-charge: The project engineer-in-charge is responsible for
carrying out detailed engineering and manpower planning within the scope of
21. Subcontractor
24. Inspection
As per attached ITP form