Académique Documents
Professionnel Documents
Culture Documents
I
n the process of passing through the Conceptual and instrument during the EPC phase. For ease in under-
Front End Engineering Design (FEED) phase of a proj- standing, it is recommended to simultaneously refer to
ect, there is a logical reasoning ready in the mindset Figure-1: Lifecycle of a Field Instrument.
of a chemical engineer (often called as process engineer)
l Once the chemical engineer stamps the P&IDs as
to justify the use of various types of field instruments –
‘Approved for Design/Detailing’ it becomes the key in-
sensors (pressure transmitters, flow meters, etc.) and final
put document for all other engineering disciplines. To
elements (control valves, on-off valves, etc.). Chemical
reach up to this stage, the P&IDs have to pass through
design engineers involved in preparation of Piping and
series of interdisciplinary checks and end-user approv-
Instrumentation Diagrams (P&IDs) request technical in-
als.
puts from instrumentation design engineers and allied
discipline engineers. These inputs may be required to se- Pre-ordering phase
lect the correct type of field instrument for a specific pro-
cess fluid under consideration or whether or not a field l The instrument engineer sets his target to prepare a
instrument is really required. While preparing a P&ID, key deliverable called as ‘Instrument Index/List’. This
a collaborative approach between a chemical and instru- document summarizes all the field instruments as seen
ment engineer is a must for smooth execution of the en- on the P&IDs and becomes a master database docu-
tire project, as frequent revisions in the P&IDs may burn ment which supports all other instrumentation engi-
useful man-hours of various engineering disciplines and neering activities right till the commissioning stage
ultimately affect the overall cost dynamics of the project. and afterwards as well.
Refer to Figure-2: Instrument Index (For Process Gas
Lifecycle Area).
Let us now see the details in the lifecycle of a field The figure shows a typical instrument index with
Figure 2: Instrument Index For Process Gas Area (Area No: 029)
Field
Sr. Loop
Instrument Fluid Service Description Instrument Description Location Line No./Equipment No. P&ID No Data Sheet Junction Hook-up No Scope Remarks
No Box No Drawing No
Tag No. No
Liquid / Process Cooling Water From Pumps (029-P-101A/B) 029-KT-1-PID- 029-CMS-P0004- Later Later
1 029-FE-1234 To Cooling Gas Quench Tower (029-V-101) Orifice Flow Element Field 100-W-5204-W01-NI IS-4-001A EPC contractor
Water 1001, Rev.1
2 029-FT-1234 Liquid / Process Cooling Water From Pumps (029-P-101A/B) Differential Pressure Type Trans- Field 029-KT-1-PID- 029-CMS-P0004-
Across Orifice FE-1234 029-JB-A1-001 Later Later EPC contractor
Water To Cooling Gas Quench Tower (029-V-101) mitter (Flow) 1001, Rev.1 IS-4-002A
some standard columns that are found in any well pre- mentation deliverables prepared simultaneously that are
pared instrument index. Based on end-user criteria, there directly related to the field instruments. Some of these in-
may be additional columns giving extra details related to clude:
field instruments. • Junction Box (JB) schedule
• Cable schedule
Development of other deliverables like: Instrument
• Hook-up drawings
design basis, instrument philosophies, I/O list, control
• Installation sketches
system architecture drawing, etc. also proceeds simulta-
• Material take-offs
neously.
• Loop wiring drawings
l Preparation of ‘Instrument Datasheets’ for all field in- • Interlock logics, etc.
struments proceeds using inputs/deliverables received
All these deliverables are also updated after vendor
from chemical, mechanical, piping, etc. engineering
order placement and on receipt of drawings/documenta-
disciplines. The instrument datasheets after completion
tion from the selected vendor.
are reviewed thoroughly within the instrument project
team and also sometimes by other discipline engineers Post-ordering phase
for incorporating important technical inputs that are a
must and need to be taken care by the instrument ven- l Based on the engineering schedule agreed between
dor/manufacturer. the selected vendor and the EPC contractor, the ‘Post-
Order Vendor Documentation’ is submitted by the
l Preparation of ‘Request For Quotation’ (RFQ) docu- vendor to the instrument engineer for checking and
mentation is finalized for each field instrument and approval. This checking and approval cycle is a sub-
along with the respective instrument datasheets, the stantial time consuming process as a lot of co-ordina-
complete technical pack is sent for a quotation to pro- tion is usually required between instrumentation team
curement discipline for onward transmission to select- and other engineering disciplines especially for field
ed/approved instrument vendors/manufacturers. instruments like control/ESD valves, analysers, etc.
l On receipt of offers from vendors, ‘Technical Bid Some typical vendor documentation where interac-
Evaluation’ (TBE) begins and it is at this stage that all tion is a must includes:
specified technical requirements for the field instru-
ments under consideration is evaluated, so that the General Arrangement (GA) drawings, calculations,
purchase order placement process could be initiated for wiring details, inspection and test plans, statutory ap-
a technically competent vendor. Before recommending proval documentation, etc.
any vendor as ‘technically approved’, there is usually The above phase allows the instrument engineer to
a series of technical queries/clarifications sheet that is consider/incorporate any final technical changes (some-
exchanged between the vendor and the instrument times with commercial implications) that may be re-
engineer and for critical instruments like control/ESD quired because of changes in P&IDs/other project docu-
valves, analysers, etc. almost always between other dis- mentation.
cipline engineers and instrument engineers. This is a l On receipt of documentation/drawings stamped as
key stage which needs strict control and checking so as ‘Approved for Manufacturing’, the vendor proceeds
to avoid any technical lapses that may escalate cost at a with ‘Manufacturing’ the field instrument and subse-
later stage of the project. quently calls for an ‘Inspection and Test’ at their works.
l For every field instrument, procurement discipline Before placing the inspection call, vendors make sure
then prepares to finalize the ‘Purchase Order’ (PO) for that the instrument is tested and calibrated according
the technically recommended vendor and also for the to an approved test plan and datasheets. After the test
vendor that is commercially most viable. and final technical clearance from the inspection engi-
As the above proceeds, there are many other instru- neer, the field instrument is ‘Dispatched on Site’.