Académique Documents
Professionnel Documents
Culture Documents
method of
construction
incremenatal
balanced
span by span launching
cantilever
method
using under
with launching using form
slung launching
truss traveller
truss
1) SURVEY WORK: Center line marking for foundation of trestles will be done with the
help of theodolite/ total station.
• Fixing shutters.
• Concreting of Pier.
• Curing.
3) CONSTRUCTION OF CANTILEVER
FORM TRAVELER (FT)
• The FT is a large piece of equipment that, once assembled and attached to the
edge of the bridge deck, will allow the bridge deck to be built over the inlet.
• The FT gets locked to the completed deck area, a new deck area is concreted in
front of it and the traveler moves to that edge to begin the process again
4. The interior formwork assembly is advanced, and the top deck slab soffit and wall forms are
leveled and fixed into place.
5. Reinforcing steel and post-tensioning tendons are placed in the deck slab.
6. Concrete is placed in the bottom slab, web walls, and deck slab.
8. The internal and external formwork is stripped from the cast and cure segment, and the
Form Traveler is launched to the next segment.
4) CONSTRUCTION OF END SPAN.
Casting of end span is done after the cantilever construction. Activities involved remains
the same as explained for pier head construction.
After casting of span, the remaining portion of length 2.50m segment is to be stitched.
• This type of bridge could be erected without any scaffoldings from the ground.
• Accordingly erection need not to be affected by the land condition (River, Sea,
Valley, and Ravine) and/or road, railway surrounding the erection spot.
• Useful where span length is more but launching of girder is not possible.
DISADVANTAGES
• Shear stress can be very high at hinges hence there are very congested with steel.
Each load added or moved causes the deck to deflect. Creep and shrinkage increases the
deflection. The objective is to get the vertical alignment correct for some stage after
construction, usually when the bridge is opened to traffic or at some time after that.
1 Model FT-S
Longitudinal 7%
Max. Bridge
11
Slope
Transverse 5%
• The incremental launching method is one of the highly mechanized erection methods
used in bridge construction.
• The horizontal jack to push the structure forward to achieve the launching purpose,
• Then vertical jack is released and entire structure laid down on temporary pad beam to
complete a launching process.
SLIDING BEARING
• The sliding bearings were installed on all permanent and temporary piers.
• The sliding bearings consist of concrete blocks covered with stainless steel and Teflon-
coated reinforced elastomeric pads.
• Steel/neoprene/Teflon plates were placed between the leading box girder and these
bearings to keep the friction to a minimum.
• The friction recorded at each launching operation was approximately five percent,
which was close to the assumption made during the design.
• All signals from sensors and measuring equipment are then transmitted to the main
control computer to go on data analysis and processing
Withdrawing Lifting
Launching Descending
LAUNCHING PROCESS
Step 1 lifting: the lifting oil cylinder is activated to uplift the entire girder structure from the pad
beam.
Step 2 launching: the launching oil cylinder is activated to move the girder structure and the
upper part of the launching system forward.
Step 3 descending: the lifting oil cylinder is released and descended, the girder structure is laid
down on temporary pad beam.
Step 4 withdrawing: the launching oil cylinder is released and the whole launching system back
to initial state, a launching cycle completed and prepare for next repetition.
FORMWORK
• Formwork used is stationary which is laid in the prefabricated area near the abutment.
• Steel forms are used when there are many repetition of work.
• Timber forms can also be used.
• I sections are used to support the formwork
• Double T beam can be used where only one formwork for both internal and external .
They are fixed together and can be hydraulically lowered outwards and inwards
respectively.
LAUNCHING NOSE
A stiffened steel plate girder is fixed to the tip of the bridge, its length being normally 60% of
the regular span length.
The nose usually consists of two braced main girders of steel. Its length is 60 to 65 % of the span
of the bridge.
Its weight ranges between 1 and 2 t/m, or more if the length is over 30 m.
ADVANTAGES
• This is particularly valuable for projects with high piers, in urban areas, spanning over
deep water, over roads and over railways.
• Most of the construction operations take place in the same location, which may be
organized as a pre casting yard.
• The pre casting work is thus more easily supervised, giving a high quality of
workmanship.
DISADVANTAGE
• This form of construction can be used for bridges having constant cross sectional
• The bridge should be straight or have constant horizontal and vertical curvatures.
• After construction of one unit, hardening of concrete and subsequent launching require
one week
Max. Longitudinal 7%
10 Bridge
Slope Transverse 5%