Académique Documents
Professionnel Documents
Culture Documents
Client:
IRCON INTERNATIONAL LIMITED
Register of Submissions
TABLE OF CONTENTS
PAGE
1 INTRODUCTION ............................................................................................ 6
1.1 General .....................................................................................................................................6
1.2 Aim and Scope of the Pre-Final Design Report and the Design Manual...........................6
1.3 Design Stages and Revisions ................................................................................................7
1.3.1 Revision 01 ...............................................................................................................................7
5 TUNNEL LAYOUT........................................................................................ 20
5.1 General Layout ......................................................................................................................20
5.2 Layout Criteria - Rescue Concept .......................................................................................21
5.2.1 Structural Escape Facilities .....................................................................................................22
5.2.2 Escape Distances ...................................................................................................................24
5.2.3 Access Roads .........................................................................................................................24
8.2.1 General....................................................................................................................................82
8.2.2 Materials ..................................................................................................................................82
8.2.3 Formwork Carriage .................................................................................................................82
8.2.4 Construction Tolerances of the Inner-Lining ...........................................................................82
8.2.5 Earthing ...................................................................................................................................83
8.2.6 Construction Sequence ...........................................................................................................83
8.2.7 Fire Protection .........................................................................................................................83
8.2.8 Structural Analysis of the Inner-Lining ....................................................................................84
APPENDICES
Appendix I: Pre-Final Design drawings
Appendix II: Quantity Calculations, Preliminary Excavation Material Transport Concept
Appendix III: Block Allocation for the Tunnels T49 and T50
Appendix IV: Calculations Portal Cuts
Appendix V: Calculations Inner-Lining
Appendix VI: Austrian Society for Geomechanics Guideline
Appendix VII: Cost comparison with Tunnel T48
1 INTRODUCTION
1.1 General
The State of Jammu and Kashmir is the northernmost part of India, extending deep into the
Himalaya. The Pir Panjal Range separates the Kashmir Valley from the lowlands of India. By
road, the state’s summer capital, Srinagar, is most easily reached through the Kashmir
Valley from Pakistan. From the Indian lowlands, all roads to Srinagar cross high mountain
ranges, most notably the National Highway 1A from Udhampur over the Pir Panjal range.
This highway, dating back to the time of British occupation, cannot cope with current traffic
volumes. It is considered one of India’s most dangerous highways, regularly blocked by rock
falls, landslides and avalanches. In winter, the route is often blocked by heavy snowfall. If
conditions are favourable, a car journey from Udhampur to Srinagar (approx. 300 km) on the
NH 1A takes a full day.
An alternative to the NH 1A is the even more hazardous Leh-Manali Highway from Himachal
Pradesh. This route, crossing the Rohtang and Taglang Passes, is the highest major road in
the world and impassable in winter.
A railway connection between the Kashmir Valley and lowlands of India is considered
essential; therefore the 292 km long Udhampur – Srinagar – Baramulla Rail Link Project was
declared as a “Project of National Importance” by the Government of India in March 2002.
The railway will be single-track, broad gauge (=5‘6“, 1676 mm), ballastless and electrified.
The design speed is 100 km/h and the maximum gradient is 1 in 80 (= 1.25 %).
The alignment is split into three legs shown in Table 1:
LEG EXECUTING AGENCY APPROX. LENGTH APPROX. NO.
OF TUNNELS (KM) BRIDGES
Leg 1: 25 km from Northern Railway 10.90 38
Udhampur to Katra
Leg 2: 148 km from Northern Railway 109.60 119
Katra to Qazigund KRCL
IRCON
Leg 3: 119 km from IRCON 0 704
Qazigund to Baramulla
Table 1: Sections of the USBRL
The 119 km Qazigund - Baramulla section was put into operation in October 2009.
IRCON International Ltd. has been entrusted with design and construction of the railway
alignment between Dharam and Qazigund.
1.2 Aim and Scope of the Pre-Final Design Report and the Design Manual
The aim and scope of this document is to provide an overview of the proposed works for the
Tunnels T49 and T50 on the Dharam-Qazigund section of Udhampur-Srinagar-Baramulla
New BG Railway Line Project to those involved in the preparation and review of the design. It
comprises mainly but not limited to:
• Final design criteria and standards;
• overview of the alignment;
• the safety management plan for operation (rescue concept):
• proposed tunnel cross sections (optimum tunnel sizing);
1.3.1 Revision 01
Revision 01 incorporates comments received from the Client on 19 September 2013. This
revision is intended to be the final version of the Pre-Final Design Report; further comments
will be respected in the Final Design Report.
Design of the tunnels considered the following documents, standards and guidelines:
2.2.1 Reports
[12] Inception Report Revision 05: March 2013
[13] Environmental Impact Assessment – Revision 00: March 2013
2.3.1 Standards
[16] UIC 779/9 (2003), International Union of Railways, Standard: Safety in Railway
Tunnels
[17] UIC 779/11 (2005), International Union of Railways, Standard: Determination of
railway cross-sectional areas on the basis of aerodynamic considerations
[18] IS 7894 (1975), Code of practice for stability analysis of earth dams
[19] BS 8004 (1986), Code of practice for foundations.
[20] IS 456 (2000), Plain and reinforced concrete – Code of practice
[21] IS 432 (1982), Specification for mild steel and medium tensile steel bars and hard-
drawn steel wire for concrete reinforcement, Part 2 – Hard-drawn steel wire
[22] IS 1893 (reaffirmed 2003) Criteria for earthquake resistant design of structures
[23] IS 1566 (reaffirmed 2004) Specification for hard-drawn steel wire fabric for concrete
reinforcement
[24] EUROCODE 1992-1 (2011), Design of Concrete Structures
[25] EUROCODE 1997-1 (2009), Geotechnical design, Part 1: General rules
2.3.2 Guidelines
[26] Indian Railways Schedule of Dimensions, 1676 Gauge (BG), Revised 2004
[27] Indian Railways Manual for Standards and Specification for Railway Stations, June
2009
[28] Indian Railways Permanent Way Manual 1986
[29] Northern Railway specification for material and work 1987
[30] Austrian ÖVBB Guideline for Tunnel Waterproofing, December 2012 (German
Version)
[31] Austrian ÖVBB Guideline for Tunnel Drainage Systems, April 2010
[32] European Directive 96/48/EC on the interoperability of the Trans-European high-
speed rail system - Technical specification for interoperability; Aspect “Safety in
railway tunnels” (2008)
[33] FHWA NHI-09-087 (2009), Corrosion/Degradation of soil reinforcements for
mechanically stabilized earth walls and reinforced soil slopes, Part 2 – Corrosion
[34] Austrian Society for Geomechanics (2010): Guideline for the Geotechnical Design of
Underground Structures with Conventional Excavation (Revision 2.1)
This section gives an overview of the alignment between approx. km 110 and km 125. It
comprises the length and location of structures on the alignment and basic parameters of the
layout as determined by the Client.
START END
L (M)
(KM) (KM)
Bridge
110.263 110.704 441
BR-2
Sumber
110.282 111.482 1200
Yard
Bridge
111.097 111.482 341
BR-3
Tunnel
111.500 124.258 12758
T-49
Bridge
124.266 124.301 35
BR-4
Tunnel
124.310 124.565 255
T-50
Bridge
124.637 124.783 146
BR-5
Arpinchala
123.926 125.126 1200
Yard
Details regarding the alignment between km 110 and 125 are given on the design drawings:
• II-T490_20-DR-0102-B
• II-T490_20-DR-0104-0
• II-T490_20-DR-0106-A
• II-T490_20-DR-0108-A
• II-T490_20-DR-0116-A
• II-T490_20-DR-0117-A
This report covers the construction of the tunnels in the project area. The bridges are
This section details the tunnel design criteria as defined by the Client or specific standards
and guidelines.
Rolling stock measures and operations measures do not directly affect tunnel civil works
design. All requirements are covered by the infrastructure measures. Consequently the
following sections give a measure-by-measure description of the "infrastructure" design
criteria following UIC779/9 recommendations. A cross-reference to the section of the design
manual relevant to the implementation of the measure is also given.
4.1.3.1 Prevention of incidents
4.1.3.1.1 I-1 Speed monitoring/signalling system
Classification: 0
Source in Design Manual: none
Remarks: Concept required for the entire railway line (not within
scope of this manual/DDC).
tender(s).
5 TUNNEL LAYOUT
Tunnel T49 runs from Sumber to the Khoda Nala gorge. For most of its length it has a single-
track profile. Due to the necessary length of the Arpinchala Yard, a double-track section of
approx. 338 m is provided near the north portal (T49-P2). Two Side Adits, named Higni Adit
and Kundan Adit intersect T49 in the northern part of the tunnel. A parallel escape tunnel is
provided between Sumber and the Higni Adit. 24 cross-passages connect the railway tunnel
and the escape tunnel. Every third cross-passage has sufficient space for vehicular
movement.
Tunnel T50 lies within the Arpinchala Yard and is therefore has a double-track profile. No
lateral exits or escape tunnels are required.
Bridge 4 (see report of Bridge 4), which crosses the Khoda Nala gorge, connects tunnels T49
and T50.
Figure 2 gives an overview of the tunnel structures in this project section.
Further details of the tunnel layout can be found on the design drawings:
• II-T490_20-DR-0102-0
• II-T490_20-DR-0104-0
• II-T490_20-DR-0106-0
• II-T490_20-DR-0108-0
• II-T490_20-DR-0119-0
Persons escaping from in the railway tunnel enter the side adit either via the railway tunnel,
or the escape tunnel. Both side adits lead directly to the surface. As both adits are longer
than 150 m, they are dimensioned to accommodate road vehicles (measure I-45, UIC 779/9).
The layout and longitudinal sections of these adits are shown on the design drawings:
• II-T490_20-DR-0116-0
• II-T490_20-DR-0117-0
Since there is no escape possibility between T49 and T50 (Bridge 4 is fully enclosed) T49
from Kundan Adit onwards, Bridge 4 and T50 are therefore considered as one integral
rescue section (III).
As per UIC779/9 measure I-43, distances between safe places shall be maximum 1000 m
resulting in a mean escape distance of 500 m. Based on Client project-specific decisions
([03] and [04]), the finally determined tunnel layout results in the following maximum escape
distances:
Section I: Under the assumption that one cross passage is blocked due to the accident,
the maximum escape distance to a safe place in section I is 375 m.
Section II: Under the assumption that the Kundan Adit is not blocked in case of an
accident (low probability and hence an acceptable risk), the longest possible
escape distance to a safe place is approx. 1090 m.
Section III: Under the same assumptions as for Section II, the longest possible escape
distance in Section III is approx. 885 m
This section of the Design Manual describes the design of the following tunnel profiles:
• Railway Tunnel
• Escape Tunnel
• Lay By
• Walkable Cross Passage
• Driveable Cross Passage
• Side Adit
• Ventilation Cavern and Adit
All information given shall be read together with the corresponding design drawings.
6.1 Cross-Sections
6.1.1 Preface
6.1.1.1 Clearance Profile
In these subsections the clearance profiles for the proposed tunnel cross sections are
described. The geometry of each clearance profile mainly depends on the following criteria:
• Utilisation of the tunnel
- Railway tunnel (single or double-track)
- Escape purposes (e.g., Escape Tunnel, Cross-Passages)
- Ventilation (e.g., Ventilation Adit)
• Traction (in Railway Tunnels)
• Basic design parameters
- Maximum speed potential
- Minimum radius of curves
• Rolling stock
- Normal stock
- Wide stock (3660 mm)
• Walkways
Under consideration of the above mentioned criteria, the sizes of the clearance profile are
chosen in accordance with the following specific guidelines and standards and as mentioned
in Section 2.3:
• Indian Railways Schedule of Dimensions, 2004 revision
• UIC Guideline 779/9, 2003
In case further guidelines or instructions (e.g. client defined measures) are followed, it is
explicitly stated in the particular section.
The proposed tunnel profile shall consider all criteria mentioned in Table 12 to ensure a safe
and proper operation. It shall accommodate the clearance profile and all necessary
equipment, but shall not be oversized to keep construction efforts and cost low and
economically efficient.
On the inside of curves, the clearance between the track centreline and any structure shall
be increased due to the lean of the carriage and locomotives (Figure 4) and the necessary
allowance for curvature (Figure 5).
This increase of the clearance profile shall be calculated in accordance with the Appendix in
the Schedule of Dimensions [26]. Table 15 shows the horizontal values (rounded up to the
nearest 5 mm) to be added on the inside of the curve for the basic design parameters given
in section 4.1:
NO. HEIGHT ABOVE RAIL LEVEL ADDITIONAL HORIZONTAL VALUES
1 from 0 mm to 840 mm 80 mm
2 from 840 mm to 4420 mm 455 mm
3 at 5410 mm 560 mm
Table 15: Horizontal distances from centre of track to any structure on the inside of curves
At the outside of the curve, the allowance at the end of the vehicle, as shown in Figure 5,
shall be added to the horizontal values of the structural clearance profile on straight
alignment. As per the Appendix of the Schedule of Dimensions [26], Paragraph 9 the values
to be added for the basic design parameters (section 4.1) are as given in Table 16:
NO. HEIGHT ABOVE RAIL LEVEL ADDITIONAL HORIZONTAL VALUES
1 any height 21 mm
Table 16: Horizontal distances from centre of track to any structure on the outside of curves
As already mentioned in section 5.2.1.1 walkways with a width of 1.20m are recommended
at both sides due to sections without a parallel escape tunnel. The proposed tunnel geometry
(Figure 7) - a result of the minimum horizontal distances of structures and necessary
equipment to the centreline of the track - provides enough space for walkways on both sides
without enlargement of the required tunnel profile.
Figure 6 shows the clearance profile resulting from the criteria specified above. It contains:
• The maximum future moving dimensions (including opened doors) and a 1.20 m wide
walkway on both sides (highlighted in red)
• The minimum distances from the track centreline for structures on straight alignment
(highlighted in blue)
• The minimum horizontal distance from the track centreline for structures on a curve
with 640 m radius and at a speed of 100 kmph (highlighted in green).
• Space for the electrification system.
Figure 6: Clearance Profile - Railway Tunnel Single Track (see drawing II-T490_20-DR-0120)
typical cross section for the single-track railway tunnel including the moving dimensions in a
curve with a radius of 640 m (highlighted in red) and the resulting structural clearance profile
(highlighted in green). The walkway on the inside of the curve is reduced to 1.03 m, but still
within the limits given in [16], measure I-40. A jet fan, which is the determining size of
equipment, can be accommodated on the outside of the curve, just above the clearance area
of the walkway.
Figure 7: Standard Cross-Section – Railway Tunnel Single Track, Clearance Profile for R = 640 m (see
drawing II-T490_20-DR-0120)
Table 17 shows the main design parameters of the typical single-track railway tunnel cross-
section:
NO. ELEMENT VALUE REMARKS
1 Excavation Area approx. 58 m² (without invert) The exact excavation area depends
approx. 65 m² (with invert) on the prevailing geological /
geotechnical conditions the actual
approx. 70 m² (with deep invert)
support class.
2 Inner clearance approx. 38.5 m² Area above top of rail within the
inner-lining.
3 Height of tunnel 6.15 m above top of rail Dimension determined on the inner
side of the inner-lining.
4 Thickness of Inner- 350 mm As justified by structural analysis
lining (see section 8)
5 Construction maximum 150 mm
tolerance for inner-
lining
Table 17: Single-Track Railway Tunnel - Main Design Parameters
Figure 9: Standard Cross-Section – Railway Tunnel Double-Track, Clearance Profile for straight alignment
(see drawing II-T490_20-DR-0121)
Table 18 shows the main design parameters of the typical double-track railway tunnel cross-
section:
NO. ELEMENT VALUE REMARKS
1 Excavation Area approx. 109 m² (without invert) The exact excavation area depends
approx. 123 m² (with invert) on the prevailing geological /
geotechnical conditions and the
actual support class.
2 Inner clearance approx. 80.1 m² Area above top of rail within the
inner-lining.
3 Height of tunnel 7.52 m above top of rail Dimension determined on the inner
side of the inner-lining.
4 Thickness of Inner- 350 mm
lining
5 Construction maximum 150 mm
tolerance for inner
lining
Table 18: Double Track Railway Tunnel - Main Design Parameters
Figure 10: Clearance Profile – Escape Tunnel Figure 11: Clearance Profile – Lay By
Figure 12: Standard Cross Section – Escape Figure 13: Standard Cross Section – Lay By (see
Tunnel (see drawing II-T490_20-DR-0122) drawing II-T490_20-DR-0122)
Table 19 shows the main design parameters of the typical Escape Tunnel and Lay By cross-
sections:
NO. ELEMENT VALUE REMARKS
1 Excavation Area Escape Tunnel: The exact excavation area depends
approx. 28.5 m² (without on the prevailing geological /
invert) geotechnical conditions and the
actual support class.
approx. 32.7 m² (with invert)
Lay By:
Figure 14: Clearance Profile – Cross-Passage Type Figure 15: Clearance Profile – Cross-Passage Type
A, Door Area A, Tunnel Area
Table 20 shows the main design parameters of the typical Cross-Passage Type A cross
section:
NO. ELEMENT VALUE REMARKS
1 Excavation Area approx. 16.8 m² (without invert) The exact excavation area depends
approx. 18.8 m² (with invert) on the prevailing geological /
geotechnical conditions and the
actual support class.
2 Inner clearance approx. 9.61 m² Area above top of rail within the
inner-lining.
3 Height of tunnel 3.33 m above ±0.000 Dimension determined on the inner
side of the inner-lining.
As per [15] Summary of Meetings / Discussions held between IRCON and BERNARD on
April 5th and 6th 2013, point 13 , all Cross Passages of Type A are changed to Cross
Passages of Type B
Figure 17: Standard Cross Section – Side Adit (see drawing II-T490_20-DR-0124)
Table 17 shows the main design parameters of the Side Adit cross-section:
NO. ELEMENT VALUE REMARKS
1 Excavation Area approx. 58 m² (without invert) The exact excavation area depends
approx. 65 m² (with invert) on the prevailing geological /
geotechnical conditions and the
approx. 70 m² (with deep invert)
actual support class.
2 Inner clearance approx. 38.5 m² Area above ± 0.000 within the inner-
lining.
3 Height of tunnel 6.15 m above ± 0.000 Dimension determined on the inner
side of the inner-lining.
4 Thickness of inner- 350 mm
lining
5 Construction maximum 150 mm
tolerance for inner
lining
Table 22: Side Adit - Main Design Parameters
Figure 18: Standard Cross Section – Trolley Niches (see drawing II-T490_20-DR-0125)
Table 17 shows the main design parameters of the Trolley Niche cross-section:
NO. ELEMENT VALUE REMARKS
1 Excavation Area approx. 21 m²
2 Inner clearance approx. 12.1 m² Area above ± 0.000 within the inner-
lining.
3 Height of tunnel 3.46 m above ± 0.000 Dimension determined on the inner
side of the inner-lining.
4 Thickness of inner- 200 mm
lining
5 Construction maximum 100 mm
tolerance for inner
lining
Table 23: Side Adit - Main Design Parameters
- Cleaning niches
• Surface water discharge and wastewater basin (water treatment)
Clean groundwater is collected in sidewall and invert drainage pipes (see 6.2.1.4). At specific
intervals, the collected water is lead to a longitudinal collector pipe. The surface water and
other fluids are discharged at track level towards the tunnel portal where they are collected
and discharged to a wastewater basin. Since there are no low points in the completed
tunnels, pumping is not required.
6.2.1.3 Primary Drainage System - Waterproofing
The main purpose of the waterproofing system is to prevent water from penetrating into the
tunnel and to provide a protection for all technical equipment against moisture penetration,
corrosion and aggressive water throughout its operational life span. Additionally the
waterproofing system prevents clean groundwater from mixing with polluted surface water. It
is installed in sections with a concrete inner-lining and where considered necessary.
The type of waterproofing system shall be determined in accordance with the
hydrogeological survey results. Mainly there are two types of waterproofing systems:
•Umbrella system: In case seepage water occurs, the waterproofing system is usually
designed as a water pressure relieving system. If the tunnel is situated below the
groundwater level and sidewall- and invert drainages are provided, the waterproofing
system is additionally water pressure relieving (umbrella seal). In both cases a
protective felt (geotextile) is necessary to protect the waterproof membrane and allow
water flow to the drainage pipes.
• Full-round system: In case no water pressure relieving is proposed, the waterproofing
system shall be designed as a water pressure holding system. In this case, no
sidewall and invert drainage pipes are installed and the full water pressure acts on
the tunnel structure.
Table 25 gives a brief comparison of the two waterproofing systems
NO. CRITERION UMBRELLA SYSTEM FULL-ROUND
SYSTEM
1 Efforts during construction Low High
2 Impact on requirements of other construction
Low High
elements
3 Interference with water regime (after
High Low
construction phase)
4 Efforts for maintenance works throughout the
High Low
lifetime of the structure
5 Impact of remedial works on tunnel operation
Medium to Low High
in case of damage
6 Effort in case of damage Medium High
Table 25: Comparison of the waterproofing systems
The necessary maintenance works in case of a water pressure relieving system can be
carried out sectional (e.g. between two cleaning niches) and during general tunnel
maintenance. These works have therefore no major impact on tunnel operation. However,
remedial works for a water pressure holding system are very difficult and would significantly
impact tunnel operation.
For the tunnels T49 and T50, a water pressure relieving system is proposed. Figure 20
shows where this waterproofing system is installed (highlighted in green).
Figure 20: Umbrella Seal - Overview Figure 21: Waterproofing System - Detail
The main elements of such a waterproofing system, as shown in Figure 21, are (from the
sprayed concrete lining towards the inner-lining):
• A prepared, clean and smoothened surface;
• a protective felt (geotextile);
• a waterproofing membrane
The installation of the waterproofing system, the materials used and all necessary measures
shall be in accordance with the project Technical Specifications [14].
6.2.1.4 Secondary Drainage System
The task of the secondary drainage system is to discharge collected groundwater. The main
principles are as follows:
• A clear and easy concept for allowing fast discharge of the water without any
obstructions;
• the gradient of drainage pipes shall be at least 0.5 %;
• drainage pipes shall be as straight as possible. If a change of direction is necessary,
the deviation angle shall not exceed 15°, in exceptions 30°;
• the design shall maintain a flow velocity in pipes which avoids sinter.
Furthermore, the access for maintenance of the drainage system is necessary. In the
following sections the main elements of the drainage system are described.
6.2.1.4.1 Sidewall Drainage
Sidewall drains are located on both sides of the tunnel (Figure 22). The main elements are:
• Perforated PVC pipe with appropriate diameter for the expected amount of
groundwater;
• pipe bedding;
• single grain concrete as a drainage body (seeping water drain packing).
Connections to the longitudinal collector pipe are to be provided in accordance with section
6.2.1.4.4. During construction work, the pipe needs protection against penetration of slurry
and other construction material.
The general geometry of the abutment for the inner-lining is designed to provide a defined
base for the drainage pipe and to ensure the required gradient. The detailed dimensions of
all structural elements, such as the abutment, the width of the construction joint, the
embedment etc. shall be in accordance with the design drawings. Figure 23 illustrates the
cross sectional elements of a sidewall drainage.
Figure 22: Sidewall Drainage - Overview Figure 23: Sidewall Drainage - Detail
The proposed diameters of the sidewall drainage for different cross sections are as shown in
Table 26.
NO. CROSS SECTION INNER DIAMETER
1 Railway Tunnel 200 mm
2 Escape Tunnel 150 mm
3 Cross Passages 150 mm
4 Side Adit 200 mm
Table 26: Proposed diameters of sidewall drainages
In Lay By sections of the Escape Tunnel, the sidewall drainage pipes are partly substituted
by drainage gutters (Figure 24 and Figure 25).
Figure 24: Drainage Gutter in Lay By Sections – Figure 25: Drainage Gutter in Lay By Sections –
Cross Section (see drawing II-T490_20-DR-0233) Layout (see e.g. drawing II-T490_20-DR-0232)
drainage pipes for different cross sections are as shown in Table 27.
NO. CROSS SECTION INNER DIAMETER
1 Railway Tunnel 150 mm
2 Escape Tunnel 150 mm
3 Cross Passages 100 mm
4 Side Adit 150 mm
Table 27: Proposed diameters of invert drainage pipes
Water flow at the base of the tunnel towards the invert drainage pipe is through a no-fines
concrete layer and a lateral slope towards the tunnel centre line.
6.2.1.4.3 Longitudinal Collector Pipe
The sidewall and invert drainage pipe discharge into a longitudinal collector pipe. This
collector pipe is located below the invert drainage pipe (Figure 26). The pipe shall be a
HDPE type with appropriate diameter of at least 300 mm and up to 400 mm. The diameter at
different sections depends on the amount of groundwater. Pipe diameters in flow direction
may only remain constant or increase in size.
Figure 26: Invert drainage and longitudinal collector pipe – Overview (see cross section drawings e.g.
drawing II-T490_20-DR-0120)
Figure 27 shows the proposed distribution of the maintenance elements in the tunnels. The
spacing in the Escape Tunnel varies due to different distances between each cross-section
(constant spacing of cross-sections based the Railway Tunnel axis). But distances shall not
exceed the maximum allowed values. No cleaning niches are located in the cross-passages.
Figure 28: Main Tunnel - cleaning niches with transversal Figure 29: Cleaning Niche - Layout
connection pipe (see drawing II-T490_20-DR-0126)
To allow an easy maintenance access, the minimum shaft dimensions in cleaning niches
shall be as follows:
NO. ELEMENT VALUE SOURCE
1 (Clear) width Austrian ÖVBB Guideline for
600 mm Tunnel Drainage Systems
[31]
2 (Clear) length Austrian ÖVBB Guideline for
1400 mm Tunnel Drainage Systems
[31]
Table 29: Cleaning Niches – dimensions of shaft
Water in cross passages discharge towards the Escape Tunnel. Since the entire escape
tunnel and all cross-passages fall within Section I, the collected groundwater flows towards
Dasa Nala at Sumber.
Since there is a positive gradient throughout the section from Sumber to Arpinchala,
collected surface water flows towards Sumber. Drainage gutters are provided at Higni Adit
Junction and the tunnel portals in the Sumber area to collect the surface waters and fluids.
Water/fluids from sections II, III, IV and V will be discharged through the Higni Adit to a
wastewater basin located at Higni. Water/fluids from section I will be discharged to a basin
situated at Sumber. At the Portal T50-P2 (Arpinchala) a drainage gutter shall be provided to
prevent surface water from entering the tunnel. The amount of surface water in the side adits
is considered low as there will be no regular traffic. Therefore no wastewater basin is
provided at Kundan Adit portal area.
Figure 34: Fire-Fighting Pipe Railway Tunnel Figure 35: Fire-Fighting Pipe Side Adit
Figure 36: Fire Fighting Niche – Depth (see drawing II-T490_20-DR- Figure 37: Fire Fighting Niche –
0127) Cross Section (see drawing II-
T490_20-DR-0127)
Figure 38: Cable Duct in the Railway Tunnel - Figure 39: Cable Duct in the Railway Tunnel - with
without Fire-Fighting Pipe Fire-Fighting Pipe
In the Escape Tunnel and Cross Passages, space for cable ducts is available under the
concrete pavement in the sub base layer (Figure 40). In Side Adits, cable ducts are laid in
concrete on one side of the tunnel (Figure 41).
Figure 40: Cable ducts in the Escape Tunnel and Figure 41: Cable ducts in the Side Adits
Cross Passages
sections 6.2.2.4, 6.2.4.1.2, 6.2.4.1.4 and 6.2.4.1.6 are shown in Figure 42.
and railway personnel. The tunnel radio shall be independent of emergency telephones.
6.2.4.1.6 Signage
Signs shall guide people towards the nearest exits in case of an emergency. They shall show
the distances to two different exits in opposite directions. They are provided at least at every
fifty meters on both sidewalls on possible escape routes in the Railway Tunnel, the Escape
Tunnel and the Side Adit (Figure 42). The signs are lit.
7.1 Background
The design approach for NATM design was systemized by the Austrian Society for
Geomechanics in their Guideline, which we announced as one of the basics for the subject
tunnel design.
This Empirical Design Approach of NATM has also found acceptance in EUROCODE 7
([25]).
The following diagram is an outline of the design steps. Further, the guideline describes in
detail the steps and the background of this particular design approach starting at page 7.
The Guideline is enclosed as Appendix V of this report.
RR14 TH B For immediate local rock support use friction anchored rock bolts
7.3.1 Calculations
7.3.1.1 Assumptions and Method
Calculations are not the prime input for the design of support classes, they only serve as a
check for possible scenarios, of upper and lower limits and orders of magnitude, see OeGG
Guideline chapter 4.3.
For such, ground types GT03, GT05, GT07, GT08 and GT09 were selected. The GT not
selected are either not representative, of minor appearance or of similar nature to other GTs.
The behaviour of all selected Ground Types where analysed for various overburden
situations.
For the analyses the finite element program Phase 2 (Rocscience) V.8.012 was used.
The modelling was done in 2D (plane strain). The constitutive law was an elastoplastic with
Hoek-Brown failure criterion. The Finite Element mesh consists of 6-noded triangles.
Figure 47: Finite Element Mesh simulating Rail and Escape Tunnel
In the above shown system GT parameters and overburden was varied in order to obtain
indications on increase of stresses and resulting deformations at the edges of cavity.
Stratification and discontinuities are considered through respective parameters.
7.3.1.2 FEM - Results
The most useful information derived from the FEM analyses are the crown settlements (x)
and the horizontal displacements at the sidewalls (y = convergence), on the base of which
the complexity of tunnelling can be anticipated.
The following diagrams indicate deformations up to 120 mm without consideration of any
tunnel support. Each diagram shows Main Tunnel (MT) in red graphs and Escape Tunnel
(ET) in blue graphs. The displacement scale of the diagrams vary
Figure 48: GT 03 – Crown settlements and Figure 49: GT 09 - Crown settlements and
convergence of few mm only convergence of few mm only t
Figure 50: GT 05 - Crown settlements and Figure 51: GT 07 - Crown settlements and
convergence with increasing magnitude convergence with increasing magnitude
but still in a moderate range
Figure 52: GT 08 - Crown settlements and convergence at maximum 80 to 100 mm; such magnitudes are
of no particular concern. The left graph shows the related displacement vectors
GT_03
GT_09
GT_05
GT_07
GT_08
Figure 53: Comparison of displacements between the analysed ground types with a constant colour
scale. GT 07 shows medium and GT 08 significant depths of displacements into the rock
mass under the maximum overburden.
7.3.1.3 Conclusion
All ground types, even in high overburden situation, show small to moderate deformation
behaviour. This indicated that tunnelling will not face major problems and confirm the
impressions gained during the field missions.
However singular locations where unfavourable situations superimpose cannot be localized
neither by site investigations nor by analyses. For such situations a spectrum of support
classes are designed with the background of experience. In any case, contractors need to be
capable to master such unfavourable situations.
The geometry (e.g., diameter of steel bars) of the wire mesh and the steel grade shall be as
defined in the technical specifications, the design drawings and Indian Standard 1566-1982
([23]). Sheets shall be used instead of rolls, which has a positive impact on evenness and
transport volume.
7.3.2.2 Sprayed Concrete
Sprayed concrete is a mixture of Portland cement, aggregates, water and additives, shot into
place by means of compressed air through a spray nozzle. If sprayed concrete is properly
proportioned, mixed, placed and cured, it forms a very hard, high-strength concrete. Sprayed
concrete secures excavated surfaces against loosening and undue yielding of the rock,
therefore acting as an immediate form of support. It can be used in its “dry” or “wet” form and
as for concrete mixes, additives and admixtures can be used to change its properties to suit
the situation.
The thickness of the sprayed concrete layer depends on the support class. Installation of
sprayed concrete, specification of materials and machinery used shall be as defined in the
technical specifications and on design drawings. The use of steel fibre reinforced shotcrete
(SFRS) shall be in accordance with the technical specifications.
7.3.2.3 Rock bolts
Rock bolts are part of the primary support, with the purpose of activating the composite
action between the surrounding rock and the sprayed concrete, contributing to the load
bearing capacity of the primary tunnel lining. Depending on the geology and behaviour of the
ground, they can be installed either locally or in a systematic pattern in the roof, sidewalls,
and invert of the tunnels. Rock bolts can also be used for support of the tunnel face during
the advance. Bolts are secured in solid rock at one end, and with a faceplate and nut at the
other.
Types of rock bolts to be used for support of the excavation of the proposed tunnels are as
follows:
• Expanding friction anchored rock bolts; minimum breaking load 100 kN
• Mortar embedded (SN type) rock bolts, minimum breaking load 250 kN
• Self-drilling (SD) rock bolts, minimum breaking load 250 kN
• Self-drilling rock (SD) bolts, minimum breaking load 500 kN
Materials used and installation shall be as per the technical specifications ([14]) and as per
the design drawings.
7.3.2.4 Forepoling Pipes
7.3.2.4.1 General Observations
Tunnelling in loose ground material is only possible due to the dome-like, three-dimensional
load transfer in longitudinal tunnel direction across the temporarily unsupported tunnel arch.
In order to reduce, respectively avoid an overstressing of the arch and face, loose ground
has to be reinforced by support ahead of the face. These support measures ahead of the
face protect respectively avoid parts of the ground to drop. An excavation according to the
theoretical profile induces shorter span and hence the displacements in the tunnel and on the
surface become a minimum. The installation of ahead-support depends to a high extent on
the quality of workmanship.
The scope of the ahead-supports may be defined as:
• Achievement of the theoretical excavation profile
• Maximization of the length of round
• Immediate adjustment to the local ground properties resp. behaviour
• Minimum time of production
• Minimum of cost
The requirements to ahead-support appear to be the merging of contradictions: On the one
hand, the ground requires improvement, in order that it does not collapse during stress
redistribution and on the other hand, the ground is disturbed during the installation of such
ahead-support. Therefore the main target after installation of the steel elements is to
compensate the disturbance which has been caused due to installation. In most of the
designs it is assumed that an ahead-support when combined with grouting improves the
ground. As can be seen along the excavation contour during excavation this first target is
often not achieved. Theory and practical aspects somehow counteract in this respect and
only careful execution can achieve the approximation between theory and field - application.
ungrouted. Due to the smaller diameter of the drill hole the ground will be compacted while
the pipes are driven in. Hence a good profile shape can be achieved. The production of the
drill holes shall be adapted to the ground conditions either with air or water flushing.
Latest development for forepoling pipes is the so called “Power Set” which combines drilling
and installation by means of an ordinary steel pipe, a hexagonal drill rod in the pipe and a
sacrificial drill bit.
Grouted forepoling pipes:
Forepoling pipes of 3 to 4 meter lengths with holes or slots for grouting purposes are
installed like the above described ungrouted fore poling pipes and are grouted in the
succeeding working step. Good compound is achieved between the grout and the ground
and an exact profile shape is the result.
7.3.2.4.3 General Rules for the Execution of Forepoling Pipes
The target of any advance support is to install the support elements into the ground ahead of
the face in the shape of the excavation profile, so that the excavation profile can be achieved
without major overbreak. Due to the installation of the ahead-support the ground experiences
a certain disturbance which is to be compensated with appropriate grouting measures. The
use of steel ribs is a precondition for the installation of the ahead-support, as the steel rib
with shotcrete forms the support of the ahead-support at the place of the nearest rib to the
face. The effectiveness of an ahead-support depends also on the length of round; principally,
ahead-support with forepoling poles or spiles are only effective with lengths of rounds of less
than 1.2 meters in loose ground. When installing ahead-support, the shotcrete lining above
the steel rib shall be kept open for installation of forepoling and only when the ahead-support
has been placed, the shotcrete shall be applied in these places in order to achieve an
appropriate support and embedment for forepoling at the steel rib next to the face. Attention
shall be paid that forepoling is embedded in shotcrete also between the steel rib next to the
face and the tunnel face, which will result in a minimum overbreak during the excavation of
the next round, see picture 6.
As the grout mortar shall have sufficient strength before opening the next excavation step,
the use of accelerated cement is favourable; the use of accelerated cement increases time
for cleaning and wear, in certain cycles normal cement can be used when timing the working
cycle in such a way that between the grouting and the opening of the face activities such as
the installation of rockbolts or invert arch can be done in between, see picture 5.
Figure 56: Sprayed concrete between steel rib and face (yellow area) lead to good profile-shape during
the upcoming excavation-step
The selection of the length of ahead-support should consider that the steel rods or pipes
have sufficient support lengths in the ground and on the steel ribs.
Forepoling pipes shall not have grout holes for approximately 1 meter at its ends in order to
avoid the issue of the grout at the tunnel face. Prior to grouting, the mouth of the boreholes
shall be sufficiently sealed in order to achieve sufficient grouting embedment of the pipes. In
order to enable a certain build up grouting pressure, a mechanical packer including a tap
should be attached at every end of the pipes, which can be reused of course.
In loose ground, the flushing of self-drilling rods should be done by means of cement grout
as this method warrants best results without any loosening effects.
Longer ahead-support with self-drilling bolts with a length of 6 meters which may then be
installed only every second round have turned out to be not ideal, as the material tends to
overbreak at least as far as to the installed rods; so this “saw-tooth” profile requires a
considerable amount of excess of shotcrete, which is uneconomic.
7.3.2.5 Lattice Girders/Steel Rib
Steel rib is effective as protection and primary support immediately after excavation and
subsequently acts as reinforcement and load distributing members for the sprayed concrete
lining. Lattice girders are three dimensional, lightweight steel frames manufactured of round
steel bars in compliance with the required excavation geometry of the tunnel. They give
additional profile control and support forepoling bars. Figure 57 details a view of a cross
section with lattice girder.
The proposed lattice girders can be manufactured on site. Details of the three different types
of lattice girders to be used are shown in the following sections. Materials used and
installation shall be as per the Technical Specifications ([14]) and as per the design
drawings:
• II-T490_20-DR-0190-0
• II-T490_20-DR-0191-0
• II-T490_20-DR-0192-0
7.3.2.5.1 50/20/30
The main parameters of the 50/20/30 type lattice girder are as follows:
ITEM VALUE
Height between outer and inner steel bars 50 mm
Diameter of outer steel bars (“rock side”) 20 mm
Diameter of inner steel bar (“air side”) 30 mm
Diameter of the connection bars 10 mm
Table 34: Lattice girder 50/20/30 – main parameters
7.3.2.5.2 70/22/32
The main parameters of the 70/22/32 type lattice girder are as follows:
ITEM VALUE
Height between outer and inner steel bars 70 mm
Diameter of outer steel bars (“rock side”) 22 mm
Diameter of inner steel bar (“air side”) 32 mm
Diameter of the connection bars 10 mm
Table 35: Lattice girder 70/22/32 – main parameters
7.3.2.5.3 100/22/32
The main parameters of the 100/22/32 type lattice girder are as follows:
ITEM VALUE
Height between outer and inner steel bars 100 mm
Diameter of outer steel bars (“rock side”) 22 mm
Diameter of inner steel bar (“air side”) 32 mm
Diameter of the connection bars 10 mm
Table 36: Lattice girder 100/22/32 – main parameters
Figure 64: Standard support detail –lining stress Figure 65: Standard support detail –installed lining
controllers (see drawing II-T490_20-DR-0193) stress controllers (see drawing II-T490_20-DR-0193)
In tunnel sections with lining stress controllers, the plates of the rock bolts should be fitted
with deformation pipes.
Figure 66: Standard support detail –anchor plate with deformation pipes (scheme) (see drawing II-
T490_20-DR-0193)
GBT
GBT 1, 5, 8, SC 1 SC 2 SC 2 SC 3 SC 3 SC 4 SC 3 SC 4
GBT 4 SC 4 SC 5 SC 5 SC 5 SC 5 SC 6 L SC 5 SC 6 L
GBT 11 SC 4 SC 5 SC4 SC 5 SC 5 SC 5 SQ SC 5 SQ SC 6 SQ
In the following sections, a general description of the range of Support Classes and their
support elements is given. Details for support classes for each cross section are given in [14]
and on the relevant drawings.
7.3.4.1 Support class SC1 – Competent Rock Mass
Excavation carried out in competent rock mass by drill and blast; for scaling of faces a tunnel
excavator is to be provided.
Top Heading:
The TH face shall be opened with lengths of round not exceeding 3.0 metres as shown on
the drawings.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• 1 layer of wire mesh (100 x 100 x 5 mm);
• 10 cm of sprayed concrete lining; alternatively steel fibres may substitute the mesh.
• 4 friction anchored rock bolts with 3 m lengths at locations required by the
discontinuity pattern.
Bench:
The unsupported length of the bench faces shall not exceed 6.0 metres as shown on the
drawings. Bench excavation shall be done “half sided” some 200 metres behind the TH face
in order not hamper advance and production at the TH face. A maximum distance between
the faces of TH and B from the viewpoint of design is not required to be specified.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• 1 layer of wire mesh (100 x 100 x 5 mm);
• 10 cm of sprayed concrete lining, alternatively steel fibres may substitute the mesh.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• 1 layer of wire mesh (100 x 100 x 5 mm);
• 10 cm of sprayed concrete lining; alternatively steel fibres may substitute the mesh.
• lattice girder steel ribs (50/20/30) every other round, connected to the lattice girders in
the top heading;
• 1 layer of wire mesh (100 x 100 x 5 mm); alternatively steel fibres may substitute the
mesh.
• 15 cm of sprayed concrete lining.
the drawings
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• lattice girder steel ribs (70/22/32) every round;
• 2 layers of wire mesh (100 x 100 x 5 mm) alternatively steel fibres may substitute the
first (outer) layer of mesh.
• 20 cm of sprayed concrete lining;
• forepoling pipes, ungrouted, 4 m length (for the next round);
• a systematic SN rock bolt pattern with 4 m lengths, with orientations required by the
discontinuity pattern.
Bench:
The unsupported length of the bench faces shall not exceed 2.6 metres as shown on the
drawings. Bench excavation shall be done “half sided” not more that 200 metres behind the
TH face in order not hamper advance and production at the TH face. The distance between
the faces of TH and B may be shortened depending on displacement behaviour of the Top
Heading.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• lattice girder steel ribs (70/22/32) every round, connected to the lattice girders in the
top heading;
• 2 layers of wire mesh (100 x 100 x 5 mm); alternatively steel fibres may substitute the
first (outer) layer of mesh
• 20 cm of sprayed concrete lining;
• a systematic SN rock bolt pattern with 4 m lengths, with orientations required by the
discontinuity pattern.
Invert:
The invert shall be excavated in two steps at lengths of 2.6 m (lengths of round of
5.2 metres) advancing from the bench face backwards as shown on the drawings.
For each round, invert support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• 2 layers of wire mesh (100 x 100 x 5 mm)
• 20 cm of sprayed concrete lining.
The second layer of mesh shall only be installed after the application of the first layer of
shotcrete
7.3.4.6 Support class SC6L – Loose Ground
Excavation carried out in loose ground by means of tunnel excavator in subdivisions of the
face with simultaneous face sealing of each excavation step. Excavator and shotcreting
device shall be operational at the face at the same time.
Loose ground is sensitive to water, which shall be drained away before the openening of the
respective face by drainage holes as shown on the drawings. Ponding water shall not be
allowed.
Top Heading:
The tunnel face shall be opened in subdivisions with maximum lengths of round of
1.0 metres as shown on the drawings and immediately sealed with 50 mm of sprayed
concrete prior to the opening of the next subdivision.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• lattice girder steel ribs (100/22/32) every round;
• 2 layers of wire mesh (100 x 100 x 5 mm) (first layer prior to installing of the lattice
girder);
• 25 cm of sprayed concrete lining; alternatively steel fibres may substitute the first
(outer) layer of mesh
• forepoling pipes (power set pipes or similar), 4 m length (for the next round);
• a systematic self drilling rock bolt pattern (as determined by the collapse of drillholes)
with 6 m lengths, with radial orientations.
• A temporary invert arch supported with 15°cm of sprayed concrete and 1 layer of wire
mesh (100 x 100 x 5 mm)
Bench:
The tunnel face shall be opened with maximum lengths of round of 2.0 metres as shown on
the drawings.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• lattice girder steel ribs (100/22/32) every round, connected to the lattice girders in the
top heading;
• 2 layers of wire mesh (100 x 100 x 5 mm), (first layer prior to installing of the lattice
girder);
• 20 cm of sprayed concrete lining; alternatively steel fibres may substitute the first
(outer) layer of mesh
• a systematic self drilling rock bolt pattern (as determined by the collapse of drillholes)
with 6 m lengths, with radial orientations.
Invert:
The invert shall be excavated in two steps at lengths of 2.0 m (lengths of round of
4.0 metres) advancing from the bench face backwards as shown on the drawings.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• 2 layers of wire mesh (100 x 100 x 5 mm)
• 25 cm of sprayed concrete lining.
The second layer of mesh shall only be installed after the application of the first layer of
shotcrete.
The minimum ring closure distance shall be within 6 rounds of the Top Heading excavation
face. The maximum ring closure distance shall be within 12 rounds of the Top Heading
excavation face.
7.3.4.7 Support class SC4SQ – Mild Squeezing, Weak Fractured Rock Mass
Excavation carried out in squeezing, weak fractured rock mass by drill and blast by means of
loosening shots and/or tunnel excavator.
In the event of sensitivity of the rock mass to water this requires particular care: Water shall
be kept away from exposed rock surfaces by suitable means. Ponding water shall not be
allowed.
The minimum ring closure distance shall be within 8 rounds of the Top Heading excavation
face. The maximum ring closure distance shall be within 16 rounds of the Top Heading
excavation face.
Top Heading:
The tunnel face shall be opened with maximum lengths of round of 1.7 metres as shown on
the drawings and immediately sealed with 50 mm of sprayed concrete. Support core may
become necessary.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• lattice girder steel ribs (70/22/32)
• 2 layers of wire mesh (100 x 100 x 5 mm) with steel rib for fixing of the wire mesh
(first layer prior to installing of the lattice girder);
• 20 cm of sprayed concrete lining;
• forepoling pipes ungrouted, 4 m length (for the next round);
• a systematic SN and/or self-drilling rock bolt pattern (as determined by the collapse of
drillholes) with 6 m lengths, with orientations required by the discontinuity pattern.
Bench:
The tunnel face shall be opened with maximum lengths of round of 3.4 metres as shown on
the drawings.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• lattice girder steel ribs (70/22/32) every round, connected to the lattice girders in the
top heading;
• 2 layers of wire mesh (100 x 100 x 5 mm) with steel rib for fixing of the wire mesh
(first layer prior to installing of the lattice girder);
• 20 cm of sprayed concrete lining;
• a systematic SN and/or self-drilling rock bolt pattern (as determined by the collapse of
drillholes) with 6 m lengths, with orientations required by the discontinuity pattern.
Invert:
The invert shall be excavated in two steps at lengths of 3.4 m advancing from the bench face
backwards as shown on the drawings.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• 2 layers of wire mesh (100 x 100 x 5 mm)
• 20 cm of sprayed concrete lining.
The second layer of mesh shall only be installed after the application of the first layer of
shotcrete.
The minimum ring closure distance shall be within 8 rounds of the Top Heading excavation
face. The maximum ring closure distance shall be within 16 rounds of the Top Heading
excavation face.
allowed.
The minimum ring closure distance shall be within 8 rounds of the Top Heading excavation
face. The maximum ring closure distance shall be within 16 rounds of the Top Heading
excavation face.
Top Heading:
The tunnel face shall be opened in subdivisions with maximum lengths of round of
1.3 metres as shown on the drawings and immediately sealed with 50 mm of sprayed
concrete prior to the opening of the next subdivision. The central subdivision remains as a
supporting wedge and is only excavated in the subsequent round.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• lattice girder steel ribs (100/22/32);
• 2 layers of wire mesh (100 x 100 x 5 mm), (first layer prior to installing of the lattice
girder);
• Lining stress controllers in 2 positions and necessary fixing elements;
• 25 cm of sprayed concrete lining;
• forepoling pipes without mortar, 4 m length (for the next round);
• self-drilling rock bolts in the excavation face, 6 m lengths;
• a systematic SN and/or self-drilling rock bolt pattern (as determined by the collapse of
drillholes) with 8 m lengths, with orientations required by the discontinuity pattern.
Bench:
The tunnel face shall be opened with maximum lengths of round of 2.6 metres as shown on
the drawings.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• lattice girder steel ribs (100/22/32) every round, connected to the lattice girders in the
top heading;
• 2 layers of wire mesh (100 x 100 x 5 mm) with steel rib for fixing of the wire mesh
(first layer prior to installing of the lattice girder);
• 25 cm of sprayed concrete lining;
• a systematic SN and/or self-drilling rock bolt pattern (as determined by the collapse of
drillholes) with 6 m lengths, with orientations required by the discontinuity pattern.
Invert:
The invert shall be excavated in at lengths of 2.0 m (lengths of round of 2.0 metres)
advancing from the bench face backwards as shown on the drawings.
For each round, tunnel support shall be installed in the following order prior to excavation of
the subsequent round, consisting of:
• 2 layers of wire mesh (100 x 100 x 5 mm)
• 25 cm of sprayed concrete lining.
The minimum ring closure distance shall be within 8 rounds of the Top Heading excavation
face. The maximum ring closure distance shall be within 16 rounds of the Top Heading
excavation face.
The minimum ring closure distance shall be within 8 rounds of the Top Heading excavation
face. The maximum ring closure distance shall be within 16 rounds of the Top Heading
excavation face. Modification of the ring closure distance may become necessary depending
on the deformation behaviour of the Rock Mass – Tunnel Support System.
LC16 TH B Sprayed concrete at > 90% of capacity = visual inspection to check for cracks
LC17 TH B Sprayed concrete at > 90% of capacity = inspect sprayed concrete invert
8 CIVIL WORKS
8.1.1 General
All portals on the alignment require cuts. The slope stability where the cuts are constructed
has been evaluated and slope will be stabilized by rock bolts and reinforced sprayed
concrete. The design parameters are described in the following sections.
Table 41 shows the calculated Hoek-Brown Criterion Parameters for each ground type. The
MB and S values are strength parameters of rock mass. Erm means the deformation
modulus for rock mass. Nue is the Poisson ratio and Gamma the unit weight of rock mass.
ERM GAMMA
GROUND TYPE MB S ΝUE [-]
[-] [KN/M³]
GT_01 2.0046 0.0067379 16739.5 0.3 27
GT_04 0.7013 0.0022181 894.6 0.3 26.5
GT_04_disc 1.7125 0.0356740 2931.3 0.3 26.5
ERM GAMMA
GROUND TYPE MB S ΝUE [-]
[-] [KN/M³]
GT_05_disc 2.2875 0.0497871 39263.7 0.3 26.5
GT_07 1.4026 0.0022181 12300.7 0.3 26
GT_10 0.1663 0.0001234 52.2 0.4 24
Table 41: Hoek-Brown Criterion Parameters
In accordance with the geological reports, different joint networks are considered. Therefore
the joints in field are projected on the tunnel alignment and 90 degree to the alignment. The
following table shows the properties of the joint networks. If there is no dominant joint system
in the field, the ground was modelled as a continuum. For each portal various cross sections
were calculated. The persistence value means the space from joint end to the beginning of
the next joint in percent of the joint length.
JOINT PERSISTENCE
CROSS- INCLINATION SPACING LENGTH PHI
DESCRIPTION NET-
SECTION [°] [M] [M] [%] [°]
WORK
T49-P1 1 40 0.6 7 90 40
(Sumber) B-B
2 -54 3 10 80 40
1 11 0.6 10 50 40
Portal
2 -72 0.6 7 90 40
ET-P1 1 37 0.6 7 90 40
(Sumber) B-B 2 55 0.8 10 50 40
3 -58 0.6 10 80 40
1 24 0.8 10 50 40
Portal 2 69 0.6 7 90 40
3 -45 0.6 10 80 40
Higni Adit 1 -4 1.3 10 80 40
B-B
2 35 1.3 7 90 40
1 -69 1.3 10 80 40
A-A
2 20 1.3 7 90 40
T50-P2
continuum
(Arpinchala)
T50-P1
continuum
(Khoda Nala))
T49-P2 1 65 1 infinite 100 20
B-B
(Khoda Nala) 2 35 2 3 0.76 30
1 65 1 infinite 100 20
A-A
2 35 2 3 0.76 30
JOINT PERSISTENCE
CROSS- INCLINATION SPACING LENGTH PHI
DESCRIPTION NET-
SECTION [°] [M] [M] [%] [°]
WORK
Portal 1 65 1 infinite 100 20
Kundan Adit 1 80 0.5 infinite 100 20
A-A
2 35 2 3 0.76 30
Table 42: Joint Networks along the project alignment
On site visit hydrogeological mapping could not determine the location of the groundwater
table. To avoid water pressure on the sprayed concrete wall after rainfall, pressure relief
holes have to be considered.
The modelling of the slopes was done in 2D (plane strain). The constitutive law was an
elastoplastic with Hoek-Brown failure criterion. The Finite Element mesh consists of 6-noded
triangles.
For most portal cuts the FOS is higher than the required. But the calculated length and
number of rock bolts is not affected by the maximum bolt force but is determined by the
jointed rock mass.
For corrosion protection galvanizing protection measures have to be considered. On the soil
nail heads local sprayed concrete shall be applied after the nails are installed and the plates
and nuts are in position.
8.2 lnner-Lining
8.2.1 General
Except from the ventilation duct, a secondary lining (concrete inner-lining) has been
designed for all tunnel cross sections. This secondary lining is typically unreinforced. The
proposed block length in the Railway tunnel and the Side Adits is 12.5 m: Hence all required
intervals of tunnel elements/features such as e.g., cross passages, cleaning niches are
multiples of the block length for minimizing construction efforts. An overview of the proposed
block allocation is given in the Appendix III. In the Escape Tunnel a general block length of
10.0 m is used. Block lengths are standardised so that the formwork carriages remain
consistent.
The main purposes of the inner-lining are as follows:
• Cater for all the final structural loading cases;
• fulfil the final safety margin;
• guarantee the required service lifetime;
• provide a architectural finish;
• enable installation of E&M equipment.
The thickness of the concrete inner lining at the top in each tunnel cross section is as given
in Section 6.1. The exact geometry of the inner-lining is as per the detailed design drawings.
8.2.2 Materials
The materials (e.g., concrete, steel) used for each structure shall be as per the Technical
Specifications [14] and as shown on the design drawings.
Figure 68: Inner Lining – Scheme Construction Figure 69: Inner Lining – Detail Construction
Tolerance Tolerance
8.2.5 Earthing
Earthing flat bars of galvanized iron are installed in the inner lining. They are provided in
each abutment in longitudinal direction and every 250 m in lateral direction. At fire-fighting
and trolley niches earthing sockets are proposed. The dimension of the flat bar is 40 x 4 mm
and they are laid before concreting.
Table 46 gives detailed information about the temperature as a function of time for the
EUREKA curve.
Time [min] 0 5 60 170
Temperature [°C] 0 1200 1200 0
Table 46: Values EUREKA curve
Figure 72: Material Properties – Non-linear material behaviour (for details see Appendix V)
Main Tunnel
5 18,300,000.00 0.30 3.825 6,440,422.32 1.30 11,895,000.00 5,947,500.00
Single Track
Main Tunnel
5 18,300,000.00 0.30 16.250 1,515,976.33 1.30 11,895,000.00 5,947,500.00
Single Track
Main Tunnel
5 18,300,000.00 0.30 15.750 1,564,102.56 1.00 Invert
Single Track
Main Tunnel
5 18,300,000.00 0.30 6.100 4,038,461.54 1.00 Deep Invert
Single Track
Main Tunnel
2 67,800,000.00 0.30 3.825 23,861,236.80 1.30 44,070,000.00 22,035,000.00
Single Track
Main Tunnel
2 67,800,000.00 0.30 16.250 5,616,568.05 1.30 44,070,000.00 22,035,000.00
Single Track
Main Tunnel
2 67,800,000.00 0.30 15.750 5,794,871.79 1.00 Invert
Single Track
Main Tunnel
2 67,800,000.00 0.30 6.100 14,962,168.98 1.00 Deep Invert
Single Track
8.2.8.4 Loads
The following loads are determined by the calculations:
• Dead load for determination of setting durations and strength
• Ground loading due to rock mass
8.2.8.4.1 Dead Load
Unreinforced concrete has a unit weight of 24.0 kN/m
8.2.8.4.2 Ground Loading
Two different types of ground load distributions have been considered:
• Squeezing rock conditions (left picture below)
• Loosened rock (right picture below)
Figure 73: Load Scheme for squeezing rock Figure 74: Load Scheme for loosened rock
conditions
Figure 75: Cross Section without invert: GT5 Deformations due to dead load (for details see Appendix V)
Figure 76: Cross Section without invert: GT5 Bending moments due to dead load (for details see
Appendix V)
Figure 77: Cross Section with invert: GT5 Deformations due to load case “loosened rock” (for details
see Appendix V)
Figure 78: Cross Section with invert: GT5 Bending moments due to load case “loosened rock”
8.2.8.6 Conclusion
8.2.8.6.1 Time for Removal of Formwork and Lining Strength
For construction work, the following values shall be adhered to:
• average compression strength: 3.0 – 3.5 N/mm²
• average young modulus: 1500 N/mm²
• cement CEM 32.5N (class S)
9.1 Lots
The structures in this project area are remote and have only restricted access and space for
site installation and construction. Tunnel portals are far of each other in terms of travel time
and distance, and are reachable only by single-lane site access roads. Therefore, it is
proposed to split the works by location. This eliminates the need of providing space and
infrastructure for different contractors at each location. Furthermore, potential conflicts
between two contractors influencing the work of each other are reduced to a minimum and
bundled at manageable interfaces such as the lot boundary. The proposed lots are as
follows:
• Lot T49A
• Lot T49B and T50
• Double-track
rack Railway Tunnel T50
• Ventilation Cavern and Adit,
Adit, including the connection to the Railway Tunnel
• Technical rooms
• Site roads
• Bridge 4, rock fall protection bridge for double track yard
• Piers and foundations of bridge 5 (3 3 span composite bridge for double track yard)
yard
The provisional length of the single-track section,, measured along the Railway Tunnel is
7195 m. This length may vary depending on the progress of work in this lot and the southern
neighbouring lot (T49A). The length of the double-track
double section is 593 m. The Side Adits
have lengths of 275 m (Higni) and 725 m (Kundan)
• Portal Cuts
• Earth and rock excavation works
• Mucking
2 • Slope Support and auxiliary works
• Monitoring
• Tunnelling
• Excavation and support of tunnels, ducts and niches
• Dewatering
• Mucking
3 • Monitoring
• Civil Works
• Drainage + Waterproofing
• Inner Lining including pipes and ducts
• Monitoring
4 • Continous approval of works
Figure 79:
79 Construction sequence for tunnels – overview
5688_Pre_Final_Design_Report_Tunnel_Rev01
_Report_Tunnel_Rev01-A.docxBERNARD Ingenieure ZT GmbH Page 91 of 108
DETAILED DESIGN CONSULTANCY SERVICES FOR CONSTRUCTION OF KM 110 TO KM 125 OF
DHARAM-QAZIGUND SECTION OF UDHAMPUR SRINAGAR-BARAMULLA NEW BG RAILWAY LINE PROJECT
PRE FINAL DESIGN REPORT TUNNEL REV. 01
• lighting;
• supply and distribution of industrial and potable water;
• supply and distribution of compressed air;
• waste disposal, toilet blocks, sewage lines, septic tanks and filters;
• medical and first-aid facilities; and,
• fire-fighting equipment.
Figure 80: Potential muck deposits in the Sumber area (yellow areas). The confluence of the Dasa and
the Anchah Nala to Sumber Nala is In the foreground.
Figure 81: Alternative muck deposit (yellow encircled area) south of Digdol on the Bishlari river bank
Figure 82: Muck deposit, approx. 2 km north of Ramsu in the Bishlari River Valley
Figure 84: Potential muck deposit area at the face of the Kundan Nala side Adit. Access to this deposit
would be by a new bridge on the right hand side. View from the road between Nachlana and Arpinchala.
muck deposit shall only be allowed after the prepared ground surface has been approved by
IRCON. After precipitation events, prepared ground surfaces which have not yet been
covered by muck shall be tested as described above to ensure the compactness of the
ground. If the values determined by tests do not conform to the above values, the ground
shall be re-compacted and re-tested until it does conform.
Appropriate measures shall be taken to capture and divert any water due to water-bearing
geological layers away from the deposit area (i.e., into a stream). This prevents soaking of
the deposited muck.
4. Properties of deposited material
Contaminated material may not be deposited. Limits for contaminants in solid matter and
eluate are given in the Environmental Impact Assessment (EIA) [13]. The testing regime shall
be in accordance with the specifications of the EIA [13].
The mechanical properties of excavated material should allow its use as landfill material.
Should this not be the case, the material shall be prepared or improved by the Contractor so
that it meets the requirements for deposit. For example, crushing may be necessary.
The maximum diameter of material to be disposed shall be limited to 250 mm.
Before and during the construction, the shear strength and bulk density of the material shall
be determined by large shear test (shear area of at least 30 x 30 cm). The test shall be
carried out for each change of material.
5. Placement methodology
Placement of muck shall be in layers of maximum compacted thickness 60 cm. To prevent
potential soaking of the loose muck, compaction shall take place immediately after
placement to the following minimum values:
• Degree of compaction (proctor) ≥ 100 %
• Deformation module with a 700 cm2 load plate ≥ 30 MN/m2
Compaction machinery shall be chosen so that the above values are achieved. Particular
care should be taken at the edges of the landfill body.
A 3 m high earth embankment shall be constructed directly at the boundary of the muck
disposal site as visual, noise and dust protection. The outer slope of the embankment shall
be covered with topsoil layers.
Each muck layer shall have a slope of 2 % as shown on drawings. And the top layer shall be
sloped to ensure that rain can run-off the surface.
To the greatest extent possible, deposit areas should be terraced, to enable future crop
growing by locals.
and to optimize excavation and support. NATM can therefore be considered an economical
tunnelling method; therefore causing less environmental impact than other conventional
tunnelling methods.
Almost all tunnel excavation will be carried out by the “drill and blast” technique; the cross-
section is sequentially excavated by splitting the face into “top heading”, “bench” and if
necessary due to ground behaviour and as defined by excavation and support classes,
“invert”.
Figure 85: Sub-division of tunnel excavation shown on longitudinal section: Top heading – red; temporary
invert – green; bench – blue; invert – yellow
The work cycle for excavation and support by drill and blast is shown in the following figure:
Figure 86: Excavation and support cycle for conventional tunnelling by drill and blast
Excavation is represented by the first steps of the cycle: Drilling, charging and blasting.
The face is drilled using a “hydraulic drill jumbo” to a pre-determined pattern and with a pre-
determined number of holes depending on the Support Class. The depth and diameter of the
holes are also determined by the Support Class. The holes are then “charged” by inserting
explosives into certain holes (approximately half of those drilled). Only non-electric blasting is
permissible and “smooth-blasting” techniques are to be applied, whereby micro-, milli- and
half-second delay detonators are used.
Before blasting it may also be necessary to reinforce the ground ahead of the excavation
face, e.g., in loose ground or in ground conditions which tend to produce overbreak,
collapses or material inflows immediately following excavation. This can be done either by
forepoling (spiles, forepoling bars or pipes, grouted or ungrouted) or pipe roof (grouted steel
pipes). Drillholes are bored by a hydraulic drill jumbo; pipe roofs require an attachment
mounted onto the jumbo.
To clear the dust caused by blasting, and to ensure visibility and a breathable atmosphere in
the tunnel, ventilation is provided by means of a tube at the top of the tunnel profile which
blows fresh air to the excavation face.
Scaling after blasting using a backhoe removes any loose material from intact rock surfaces
and helps to correct the tunnel profile.
The process of loading involves the removal of muck from the excavation face. Payloaders
shift the excavated material onto dumpers, which then transport the material out of the tunnel
to pre-defined disposal areas.
The final step of the cycle is supporting the freshly exposed ground by bolting and
shotcreting. Support elements include:
• wire mesh;
• steel ribs / lattice girders;
• sprayed concrete;
• rock bolts (e.g., friction anchored Swellex type, SN rock bolts, IBO anchors);
• lining stress controllers (in squeezing ground).
These support elements are described in Section 7.3.2.
In a separate operation following excavation and support, the waterproofing membrane,
concrete abutments and plastic drainage pipes are installed. The tunnel profile is checked
by scanning the surface and if necessary, corrected. The primary lining and the dowel heads
are covered with a smoothening layer of sprayed concrete in preparation for the installation
of the waterproofing system.
The secondary lining is typically unreinforced, cast-in-place concrete in 8 m to 12.5 m long
bays. Steel formwork mounted on a carrier is used to provide a high-quality surface.
Summarizing
• The excavation cycle shall be as shown on relevant drawings and as per the
technical specifications;
• subdivision of the excavation face into Top Heading, Bench and Invert is mandatory;
• all support elements shall be installed directly after the excavation took place and
prior to excavation of the next round;
• mucking shall be in accordance with the respective sections in this manual and other
relevant documents;
• depositing of excavated material shall be only at pre-defined muck deposits;
• monitoring shall be in accordance with the Section 9.5;
• probe drillings shall be in accordance with the Section 9.4.5.
Figure 87: Highly recommended work sequence for tunnel excavation and support with 3 independent
and fully equipped working groups (see drawing II-T490_20-DR-039)
9.4.3 Mucking
Mucking shall be done with appropriate equipment (e.g. in means of size). Details are given
in the technical specifications. Further details for muck deposits are given in the relevant
sections of this manual.
9.5.1 Preface
Geotechnical works such as e.g., the construction of tunnels and all related works,
excavation works and muck deposits involve risks because soil behaviour is difficult to
predict. The resulting uncertainty for the realization of such works requires a specific strategy
of design and construction that takes the management of uncertainties into account.
Geotechnical risks shall be identified and appropriate measures shall be implemented such
as:
•Optimization of the alignment (see Inception Report [12]) based on results of site
reconnaissance and investigations;
• appropriate construction method;
• geotechnical monitoring in construction phase,
While the first two points have already been discussed in this or previous reports, this section
focuses on geotechnical monitoring works to be carried out in this project. The scope of
geotechnical monitoring work is:
• Verification of the design parameters;
• determination of difference between assumptions and prevailing conditions;
• verify the sufficiency of the installed support;
• monitoring of construction methodology and quality;
• monitoring of ground/rock behaviour;
• monitoring of mitigation measures;
• predicting of changes ahead of the face (tunnelling);
• documentation of all relevant parameters and occurrences.
It requires:
• Definition of structures to be monitored;
• the definition of parameters to be monitored;
• time schedule for monitoring (e.g., every hour, every day, every week);
• predefined tolerance limits;
• the definition of permissible limits in form of values and criteria for warning and alarm,
ensuring that there is still time to take action when these limits are reached;
• the definition measures in case permissible limits are reached.
Geotechnical monitoring shall be done by an independent specialized team, not by the
Contractor. This team shall be dedicated to installation, maintenance, monitoring data
processing and visualizing data sets only.
Limiting values as a function of cut height (alert values and critical values) for displacement
of the rock are shown in the following table:
LEVEL ALERT CRITICAL
VALUE VALUE
0 - 10 m 1.5 cm 3.0 cm
10 - 20 m 2.5 cm 5.0 cm
20 - 30 m 3.0 cm 6.0 cm
Table 52: Limiting Values for rock displacement
Notes: Displacements given for the bench refer to additional displacements that occur due to
the excavation of the bench. Example: Maximum horizontal displacement of point 2 after the
excavation of the bench for level W1 for good/solid rock is 5mm + 3mm = 8mm.
Relative displacements:
Relative displacements can be determined using the measurements for the absolute
displacements. They are used to calculate the rate of displacements. This rate usually
decreases over time. However, a continuous and/or increasing rate shows that the ground
support is not sufficient.
The values of alert for relative displacements between two successive measures apply to all
soil types and are calculated as follows:
WARNING
VALUE
LEVEL
W1 vn = vn-1
W2 vn = 1.1 x vn-1
W3 vn = 1.2 x vn-1
Table 56: Tunnel Excavation: Maximum relative displacements