PT-2
REPORT DATE
12/1/2018
PROJECT STATUS
On track
COMPLETED
62%
Budget REJECTIONS
6
Actual 4
2
Planned
1
0
20 30 40 50 60 70 80 90 100 ARD EOD ETD SRD
Task Table
Tasks TOTAL PT Start
TOTAL BFF 2017 6 9/2/2018
TOTAL HANDED OVER TO T&R 39 9/3/2022
FINAL STAGE 4 9/7/2022
TRIAL 0 9/9/2022
TURRET INTEGRATION 1 9/11/2022
StATIC 1 9/16/2022
ASSY 5 9/17/2022
SUSPENSION 2 9/24/2022
WIRING 2 10/2/2022
PAINTING 5
RECLAMATION 4
WASHING 7 10/5/2022
STRIPPING 3 /6/2022
TOTAL AS ON DATE 79 10/9/2022
Budget
Planned 87
Actual 79
REJECTIONS
ARD 5
EOD 2
ETD 2
SRD 4
End Days Status
9/3/2022 1462 COMPLETE
9/7/2022 4 COMPLETE
9/12/2022 5 COMPLETE
9/11/2022 2 IN PROGRESS
9/15/2022 4 IN PROGRESS
9/17/2022 1 IN PROGRESS
9/21/2022 4 IN PROGRESS
10/2/2022 8 NOT STARTED
10/5/2022 3 NOT STARTED
NOT STARTED
NOT STARTED
10/7/2022 2 NOT STARTED
10/9/2022 #VALUE! NOT STARTED
10/10/2022 1