Vous êtes sur la page 1sur 7

462 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 24, NO.

1, FEBRUARY 2009

Optimal Capacitor Allocation in a Distribution


System Considering Operation Costs
Jong-Young Park, Jin-Man Sohn, and Jong-Keun Park, Senior Member, IEEE

Abstract—This paper proposes the planning method for capac- switched capacitors, is considered, replacement can be deferred,
itor installation in a distribution system to reduce the installation which is extremely important under limited budget conditions.
costs and minimize the loss of electrical energy. The expected life- Extensive research has been conducted on the problem of op-
time of devices with moving parts depends on the total number
of operations, which affects the replacement period and replace- timal capacitor allocation. Initially, the voltage-independent re-
ment decisions for aging equipment under a limited budget. In active current model was widely used in the formulation and
this paper, the expected device lifetimes are included in the for- was solved using analytical methods [1]–[3].
mulation, and the optimal operation status of the devices is deter- Later, a general formulation was applied to balance invest-
mined using a genetic algorithm. The optimal numbers and loca- ment costs, the cost of energy or power losses, as well as con-
tions for capacitor installation are determined based on the optimal
operation status. Simulation results in a 69-bus distribution system straints such as voltage limits, budget limits, and the number
show that the proposed technique performs better than conven- of fixed or switched capacitors. Many applications use iterative
tional methods. methods [4]–[11] in which optimization is not used, but the best
Index Terms—Distribution system, genetic algorithm, operation option can be selected by evaluating a limited number of candi-
cost, planning, shunt capacitor, under-load tap changer. dates while maintaining the constraints. More recently, attention
has focused on the use of optimization techniques [12]–[29].
Approaches include mixed-integer nonlinear programming [12]
I. INTRODUCTION and graph theory [15], [16]. With more extensive constraints, the
optimal capacitor allocation problem can be solved using tabu-
S HUNT capacitors are installed for a variety of reasons in
industrial, distribution, and transmission systems. Fixed or
switched shunt capacitors are mainly used to reduce resistive
search algorithms [13], [14], simulated annealing [17], [18], and
genetic algorithms (GAs) [19]–[29].
power losses and to control the level of voltage supplied to The main objective considered in this paper is the reduction of
the customer. This is achieved by reducing or eliminating the installation costs and real power losses, which is similar to that
voltage drop in the system caused by inductive or reactive loads. of other research. However, the effect of device lifetime on the
Interest has been increasing in identifying the type, size, and lo- switching operation of devices such as ULTC transformers or
cation of shunt capacitors using optimization techniques. Such switched capacitors is added in the objective function as a func-
techniques systematically attempt to balance two types of utility tion of the annual number of operations of the device. The annu-
costs in the planning, operation, and design process: the cost of alized installation costs depend on the device lifetimes, which
capital investment and maintenance and the cost of power or en- comprise a function of the total number of operations.
ergy losses. Candidate buses for installing capacitors are determined
The utilization and aging of power system equipment is an using sensitivity analysis [8], [9], [17], [20], and annual load
emergent issue with the restructuring and privatization of utili- forecasts are approximated in several sections for planning
ties, regulators, and other market participants. A compromise is purposes. Then, the optimal operation of all devices for each
required between overloading and underutilization; overloading section is determined by a GA. The number of capacitors to
increases the loss of life and the probability of premature failure, be installed is calculated based on this optimal operation. This
while underutilization is considered a redundancy or a waste. In reduces both the total annual cost of installation for the devices
the planning process, if the lifetime of equipment with moving and the real power losses. The proposed method was imple-
parts, such as under-load tap changer (ULTC) transformers or mented on a 69-bus radial distribution system and compared to
the conventional method.
Manuscript received December 12, 2007; revised August 25, 2008. Current
version published January 21, 2009. This work was supported by a grant from
the Center for Applied Superconductivity Technology of the 21st Century Fron-
II. PROBLEM FORMULATION
tier R&D Program funded by the Ministry of Education, Science, and Tech-
nology, Republic of Korea. Paper no. TPWRS-00931-2007.
The main objective of the capacitor allocation problem is to
J.-Y. Park is with the Electric Power Research Division, Korea Electrotech- minimize installation costs and energy losses. However, the life-
nology Research Institute (KERI), Changwon, Korea (e-mail: drago@snu.ac. times of capacitors and tap changers, as well as their annualized
kr).
J.-M. Sohn is with the LS Industrial System, Anyang, Korea (e-mail:
installation costs, vary with the number of operations. There-
jmsohn@plaza.snu.kr). fore, considering the operation of each device is reasonable in
J.-K. Park is with the School of Electrical Engineering, Seoul National Uni- calculating the installation costs of devices for efficient plan-
versity, Seoul, Korea. ning. This paper formulates an objective function that considers
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. the lifetime of each device as a practical measure to reduce total
Digital Object Identifier 10.1109/TPWRS.2008.2009489 installation costs.
0885-8950/$25.00 © 2009 IEEE

Authorized licensed use limited to: UNIVERSIDADE ESTADUAL DE CAMPINAS. Downloaded on March 20, 2009 at 13:18 from IEEE Xplore. Restrictions apply.
PARK et al.: OPTIMAL CAPACITOR ALLOCATION IN A DISTRIBUTION SYSTEM CONSIDERING OPERATION COSTS 463

The relationship between the incremental loss and the Jaco-


bian is given by [6] as

then

(8)

Hence

(9)

where and are the submatrices


of .
Fig. 1. Daily load and load duration curve corresponding to it. (a) Daily load.
(b) Load duration curve.
The buses are ordered in descending order according to their
value calculated above. The top two or three buses in each lateral
branch are selected as candidate locations.
A. Load Forecast and System Data The control variables for capacitor allocation problems are
The load pattern plays an important role in the efficient instal- generally locations and capacities of capacitors. However, the
lation of capacitors in a distribution system. Because using exact number of operations of each device is required to calculate the
load data in the planning phase is difficult, forecast data must lifetime in the proposed method. The variables for the operation
be used. In this paper, the annual load is divided into three cat- status of devices are defined as
egories: summer, winter, and spring/fall, and each load section
category has a daily load pattern. A load duration curve (LDC) is
..
created for each daily load pattern, then each LDC is partitioned .
into three load levels as shown in Fig. 1. As a result, the annual .. ..
load is classified into nine sections, which is represented by . .. .
.
(1)
(10)
(2)
(11)
The candidate buses where capacitors are installed are deter-
mined by sensitivity analysis, which helps to reduce the search where is a number of capacitors connected to bus in the
space for the optimization procedure. The sensitivity analysis th section, is the tap position of the ULTC during the th
selects the buses with maximum impact on the real power losses section, is the total number of candidate buses for installation,
in the system with respect to the nodal reactive power. and is the total number of sections. All the capacitors used in
The complex power loss is given by this paper are standard capacitors with the same capacity.
The number of capacitors to be installed at each bus is de-
(3) termined by in (10). The number of fixed capacitors and
and hence switched capacitors at each bus is calculated by

(4) (12)
(13)
The sensitivity of the real power losses in the system with
respect to the nodal reactive power is given by where and are the numbers of fixed and switched capac-
itors, respectively, installed on bus . The number of installed
(5) capacitors is used to calculate the installation costs.
With and , the number of operations for each device can
Taking the partial derivatives of with respect to and also be inferred by the periodicity of the load change during a
gives day. The load level changes from in Fig. 1(b) to
passing through , and then changes again to
(6) during a day. The operation status of each load level changes
accordingly, as shown in Fig. 2. Based on this assumption, the
number of daily operations of each device is computed by
(7)
(14)

Authorized licensed use limited to: UNIVERSIDADE ESTADUAL DE CAMPINAS. Downloaded on March 20, 2009 at 13:18 from IEEE Xplore. Restrictions apply.
464 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 24, NO. 1, FEBRUARY 2009

where is the annual interest rate and is the installation cost


of a device. The present value for the annualized installation
cost, is

(18)

Fig. 2. Change of operation status during a day. The present values of (17) and (18) should be the same, so
that the annualized cost, is

(19)

where

(20)

Fig. 3. Number of operations and lifetime of the device.


is the annualizing coefficient for the installation cost of a device.
With this result, the annualized installation cost, is

where is the number of daily operations of the th device


during the th section. The annual number of operations is com-
puted by (21)
(15)
where , , and are the installation costs of the ULTC,
the switched capacitor, and the fixed capacitor, respectively; ,
where is the annual number of operations of the th device , and are the expected lifetime of the ULTC, the switched
and is the number of days during the th section. capacitor, and the fixed capacitor, respectively; and and
The annual number of operations in (15) is accurate enough are the annual number of operations of the ULTC and the th ca-
for planning distribution systems although it may differ from pacitor, respectively. The terms in (21) represent the annualized
the actual number of operations. The number of capacitors to be installation costs of the ULTC, the switched capacitor, and the
installed in (12) and (13) and the annual number of operations fixed capacitor; the lifetimes of the fixed capacitors are a con-
each device in (15) are used to calculate the installation costs in stant value, .
the proposed planning method. The cost for real power losses, , with the operation of
devices by and is calculated as
B. Cost Functions
The annualized installation costs for each device vary ac- (22)
cording to the lifetime of the device, and the number of oper-
ations influences the lifetime of the device. Switched capacitors where is the price of real energy ($/kWh), is the number
and a ULTC have a rated lifetime and a maximum number of of days during the th section, and is the daily real
operations. Assuming that the expected lifetime of a device is energy losses during the th section with the operation of de-
inversely proportional to its number of operations, the expected vices by and (kWh/day).
lifetime of th device, is As a result, the objective function for the capacitor
allocation problem is
(16)

where is the rated lifetime of the device and is the


maximum number of operations. As shown in Fig. 3, if the an-
nual number of operations is less than , the device
works during its full rated lifetime; otherwise, its lifetime is re-
duced as in (16). In the proposed method, the expected lifetime (23)
model in any form other than (16) can be used.
Given the expected lifetime of devices and the annualized such that
installation cost, is calculated as follows. The present value
for all periodic installations of a device with the period of its
lifetime, is

(17)

Authorized licensed use limited to: UNIVERSIDADE ESTADUAL DE CAMPINAS. Downloaded on March 20, 2009 at 13:18 from IEEE Xplore. Restrictions apply.
PARK et al.: OPTIMAL CAPACITOR ALLOCATION IN A DISTRIBUTION SYSTEM CONSIDERING OPERATION COSTS 465

where is the power flow equation during


the th section; and are the allowable minimum
and maximum voltages, respectively; is the voltage mag-
nitude at bus during the th section; is the maximum
number of installed capacitors on a bus; and are
the minimum and maximum tap positions of the ULTC, respec-
tively; and is the maximum number of daily operations
of the th device.
The objective function in (23), which deals with the decaying
lifetime effect of equipment, can be applied to the capacitor al-
location problem using other methodologies to produce more Fig. 4. Flowchart to find the optimal solution by genetic algorithm.
realistic solutions.

III. SOLUTION METHODS


In this paper, the solution for the optimization problem of (23)
is determined by a GA. GAs are simple, robust, flexible, and able
to find the global optimal solution. They are especially useful
in finding solutions to problems in which other deterministic
methods encounter difficulties [25].
Variables and in (10) and (11) are coded into chromo-
somes for finding optimal solutions using a GA. All variables
in the problem have integer values, so chromosome is repre-
sented by a string of integers instead of a string of binary num-
bers to make the GA easier to manipulate. The structure of each
chromosome is Fig. 5. Candidate buses for capacitor installation in 69-bus radial distribution
system.

TABLE I
.. .. .. PRICES OF CAPACITORS AND ULTC
. . .

(24)

where corresponds to in (10), corresponds to in


(11), is the maximum number of installed capacitors at
bus , and and are the minimum and maximum tap
positions of the ULTC, respectively. The length of chromosome
is , and all integer genes correspond directly to
each variable.
The evaluation function for the GA, , is
TABLE II
RATED LIFETIME AND MAXIMUM OPERATION NUMBERS
(25)

where is the penalty function for the constraints.


Each solution in the initial randomly created population is
evaluated by (25) and selected by rank. Then, a population is re-
produced by one-point crossover and mutation. The newly cre-
ated population is evaluated, and this generational process is re-
peated until a termination condition has been reached. Fig. 4
transformer is at the distribution substation [24], [29]. The ca-
shows the process used to find the optimal solution using the
pacity of each capacitor is 300 kvar. The installation costs for
GA.
capacitors and ULTC are shown in Table I [30]. The rated life-
times and the maximum number of operations for devices are
IV. APPLICATION shown in Table II based on the actual data used by the Korean
The 69-bus distribution system shown in Fig. 5 was used to Electric Power Corporation [31]. The ULTC was assumed to
evaluate the performance of the proposed method, in which the have 21 taps within a range of , and the load to consist of
transmission system is modeled as an infinite bus and an ULTC 50% constant power and 50% constant impedance.

Authorized licensed use limited to: UNIVERSIDADE ESTADUAL DE CAMPINAS. Downloaded on March 20, 2009 at 13:18 from IEEE Xplore. Restrictions apply.
466 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 24, NO. 1, FEBRUARY 2009

TABLE III TABLE V


CLASSIFICATION DATA FOR ANNUAL LOAD FORECAST DATA IN SIMULATIONS PLANNING BY THE PROPOSED METHOD (CASE 2)

TABLE IV
PLANNING BY THE CONVENTIONAL METHOD (CASE1)

TABLE VI
DETAILED DATA FOR ANNUALIZED COSTS FOR TWO CASES

The annual assumed load for the simulations is shown in


Table III, where the amount of load is expressed as a factor of
the base load data in [24], and the total load of the base load data
is 11 375.7 kW and 8080.8 kvar. The capacity of the transformer
was not considered in the simulations. The eight candidate buses
for capacitor installation, those that had the largest sensitivity
values, were determined as shown in Fig. 5 using (9). The size
of variables and were (8 9) and (1 9), respectively, so
the length of chromosome in (24) for the GA was 81 integers.
The conventional planning method, which does not consider
the device lifetime, was compared to the proposed method in a
simulation. The expected lifetime of a device in (21) is treated
as constant in the conventional method, but calculated by (16) from it are shown. The annualized installation costs are calcu-
in the proposed method taking into account the number of op- lated by (21) with the expected device lifetimes. Table VI shows
erations of a device. the detailed data for all costs, including the expected lifetimes
Planning for capacitor allocation in the 69-bus distribution and annualized installation costs for each device and the costs
system was conducted by both the conventional method (Case of the real power loss in each case.
1) and the proposed method (Case 2), and then the results were The significant difference between the two cases is the
compared. Tables IV and V show the optimal solutions deter- number of operations of the ULTC and the resulting expected
mined by the conventional and proposed methods respectively; lifetime. With the conventional method, the number of opera-
the GA solution and the number of installed capacitors derived tions did not affect the value of the objective function, so the

Authorized licensed use limited to: UNIVERSIDADE ESTADUAL DE CAMPINAS. Downloaded on March 20, 2009 at 13:18 from IEEE Xplore. Restrictions apply.
PARK et al.: OPTIMAL CAPACITOR ALLOCATION IN A DISTRIBUTION SYSTEM CONSIDERING OPERATION COSTS 467

solution minimized only the power losses with fixed installation [2] J. J. Grainger and S. H. Lee, “Optimum size and location of shunt ca-
costs. The numbers of installed capacitors for the two cases pacitors for reduction of losses on distribution feeders,” IEEE Trans.
Power App. Syst., vol. PAS-100, no. 3, pp. 1105–1118, Mar. 1981.
were different at buses 50, 55, 62, and 65. The total annualized [3] J. J. Grainger and S. H. Lee, “Capacity release by shunt capacitor place-
cost for Case 2 differed from that of Case 1 by US $2824, which ment on distribution feeders: A new voltage-dependent model,” IEEE
is about 10% of the annualized installation costs, although the Trans. Power App. Syst., vol. PAS-101, no. 5, pp. 1236–1244, May
1982.
cost of power losses increased slightly. The expected lifetime of [4] R. E. Rinker and D. L. Rembert, “Using the reactive current profile of a
the ULTC was 27 years in Case 1 and 30 years in Case 2. Thus, feeder to determine optimal capacitor placement,” IEEE Trans. Power
the rated lifetime of the ULTC was extended by about three Del., vol. 3, no. 1, pp. 411–416, Jan. 1988.
[5] Y. T. Hsiao and C. Y. Chien, “Optimisation of capacitor allocation
years and the annualized cost was reduced by the proposed using an interactive trade-off method,” Proc. Inst. Elect. Eng., Gen.,
method. The average lifetime of switched capacitors was 17.14 Transm., Distrib., vol. 148, no. 4, pp. 371–374, Jul. 2001.
years in Case 1 and 19.57 years in Case 2, so the annualized [6] M. Y. Cho and Y. W. Chen, “Fixed/switched type shunt capacitor plan-
ning of distribution systems by considering customer load patterns and
installation costs of capacitors also decreased. simplified feeder model,” Proc. Inst. Elect. Eng., Gen., Transm., Dis-
Using the proposed method for capacitor allocation planning trib., vol. 144, no. 6, pp. 533–540, Nov. 1997.
did not make a large difference in the number of capacitors (the [7] M. H. Haque, “Capacitor placement in radial distribution systems for
loss reduction,” Proc. Inst. Elect. Eng., Gen., Transm., Distrib., vol.
difference was 4), but the total annualized cost, which is the sum 146, no. 5, pp. 501–505, Sep. 1999.
of costs for device installation and the real power losses, was [8] J. L. Bala, Jr, P. A. Kuntz, and M. J. Pebles, “Optimal capacitor alloca-
reduced considerably despite increases in real power losses. tion using a distribution-analyzer-recorder,” IEEE Trans. Power Del.,
vol. 12, no. 1, pp. 464–469, Jan. 1997.
In addition, the quantification of the number of device opera- [9] S. F. Mekhamer, M. E. El-Hawary, S. A. Soliman, M. A. Moustafa, and
tions in the proposed method is useful in the operations phase as M. M. Mansour, “New heuristic strategies for reactive power compen-
well as the planning phase. In many previous papers on control sation of radial distribution feeders,” IEEE Trans. Power Del., vol. 17,
no. 4, pp. 1128–1135, Oct. 2002.
methods for reactive power, the number of operations was con- [10] J. R. S. Mantovani and A. V. Garcia, “A heuristic method for reactive
sidered in the optimization. However, representing the number power planning,” IEEE Trans. Power Syst., vol. 11, no. 1, pp. 68–74,
of operations as a function of cost is difficult, so that a fuzzy Feb. 1996.
[11] K. Iba, H. Suzuki, K. I. Suzuki, and K. Suzuki, “Practical reactive
formulation was usually used to formulate an objective func- power allocation/operation planning using successive linear program-
tion that included the number of operations with the other costs ming,” IEEE Trans. Power Syst., vol. 3, no. 2, pp. 558–566, May 1988.
such as the energy cost. With (16)–(21), the number of opera- [12] M. E. Baran and F. F. Wu, “Optimal capacitor placement on radial dis-
tribution systems,” IEEE Trans. Power Del., vol. 4, no. 1, pp. 725–734,
tions can be considered as the cost so that it can be included in Jan. 1989.
the objective function directly without fuzzification. As a result, [13] Y.-C. Huang, H.-T. Yang, and C.-L. Huang, “Solving the capacitor
the optimization of the control for reactive power can be more placement problem in a radial distribution system using Tabu search
approach,” IEEE Trans. Power Syst., vol. 11, no. 4, pp. 1868–1873,
definite with the consistent objective function. Nov. 1996.
[14] R. A. Gallego, A. J. Monticelli, and R. Romero, “Optimal capacitor
placement in radial distribution networks,” IEEE Trans. Power Syst.,
V. CONCLUSIONS vol. 16, no. 4, pp. 630–637, Nov. 2001.
[15] J. C. Carlisle and A. A. El-Keib, “A graph search algorithm for optimal
This paper proposed a planning method for capacitor alloca- placement of fixed and switched capacitors on radial distribution sys-
tion in a distribution system considering the change in the annu- tems,” IEEE Trans. Power Del., vol. 15, no. 1, pp. 423–428, Jan. 2000.
[16] T. Gomez, I. J. Perez-Arriaga, J. Lumbreras, and V. M. Parra, “A se-
alized device installation costs. The annualized costs are related curity-constrained decomposition approach to optimal reactive power
to the lifetime of devices, which is related to the number of oper- planning,” IEEE Trans. Power Syst., vol. 6, no. 3, pp. 1069–1076, Aug.
ations. The relationship between the number of operations and 1991.
[17] H. D. Chiang, J. C. Wang, O. Cockings, and H. D. Shin, “Optimal
the expected lifetime was formulated, and the total annualized capacitor placements in distribution systems. I. A new formulation
costs, including the installation costs and the costs for real en- and the overall problem,” IEEE Trans. Power Del., vol. 5, no. 2, pp.
ergy losses, were calculated using that relationship. The optimal 634–642, Apr. 1990.
[18] C. Hsiao-Dong, W. Jin-Cheng, T. Jianzhong, and G. Darling, “Op-
solution for costs was determined using a GA. timal capacitor placement, replacement and control in large-scale un-
The proposed method was applied to a 69-bus radial distribu- balanced distribution systems: Modeling and a new formulation,” IEEE
tion system with an ULTC transformer, and the result was com- Trans. Power Syst., vol. 10, no. 1, pp. 356–362, Feb. 1995.
[19] L. L. Lai and J. T. Ma, “Application of evolutionary programming to
pared to that of the conventional method in which the lifetime of reactive power planning-comparison with nonlinear programming ap-
devices is not considered. The results show that the annualized proach,” IEEE Trans. Power Syst., vol. 12, no. 1, pp. 198–206, Feb.
costs were lower with the capacitor allocation determined by the 1997.
[20] K. N. Miu, H. D. Chiang, and G. Darling, “Capacitor placement,
proposed method. The aging of equipment with moving parts replacement and control in large-scale distribution systems by a
can be reduced and replacement deferred, so that the proposed GA-based two-stage algorithm,” IEEE Trans. Power Syst., vol. 12, no.
method will be an effective tool for distribution system planning 3, pp. 1160–1166, Aug. 1997.
[21] M. Delfanti, G. P. Granelli, P. Marannino, and M. Montagna, “Optimal
and design under limited budget constraints. The formulation of capacitor placement using deterministic and genetic algorithms,” IEEE
the annualized installation cost can be applied to other capacitor Trans. Power Syst., vol. 15, no. 3, pp. 1041–1046, Aug. 2000.
allocation methods to make those solutions more realistic. [22] G. Levitin, A. Kalyuzhny, A. Shenkman, and M. Chertkov, “Optimal
capacitor allocation in distribution systems using a genetic algorithm
and a fast energy loss computation technique,” IEEE Trans. Power Del.,
REFERENCES vol. 15, no. 2, pp. 623–628, Apr. 2000.
[23] B. A. Souza, H. N. Alves, and H. A. Ferreira, “Microgenetic algorithms
[1] H. Dura, “Optimum number, location, and size of shunt capacitors in and fuzzy logic applied to the optimal placement of capacitor banks
radial distribution feeders: A dynamic programming approach,” IEEE in distribution networks,” IEEE Trans. Power Syst., vol. 19, no. 2, pp.
Trans. Power App. Syst., vol. PAS-87, no. 9, pp. 1769–1774, Sep. 1968. 942–947, May 2004.

Authorized licensed use limited to: UNIVERSIDADE ESTADUAL DE CAMPINAS. Downloaded on March 20, 2009 at 13:18 from IEEE Xplore. Restrictions apply.
468 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 24, NO. 1, FEBRUARY 2009

[24] B. Venkatesh and R. Ranjan, “Fuzzy EP algorithm and dynamic Jin-Man Sohn received the B.S., M.S., and Ph.D. degrees from Seoul National
data structure for optimal capacitor allocation in radial distribution University, Seoul, Korea, in 1994, 1996, and 2006, respectively.
systems,” Proc. Inst. Elect. Eng., Gen., Transm., Distrib., vol. 153, no. He worked at Hyundai Engineering Co., Ltd. and Hyundai Engineering and
1, pp. 80–88, Jan. 2006. Construction Co., Ltd. from 1996 to 2000 and was a Researcher at the Korea
[25] D. E. Goldberg, Genetic Algorithms in Search, Optimization and Ma- Electrical Engineering and Science Research Institute from 2000 to 2003. He
chine Learning. Reading, MA: Addison-Wesley, 1989. is currently a Senior Research Engineer at LS Industrial Systems Co., Ltd. His
[26] A. J. Urdaneta, J. F. Gomez, E. Sorrentino, L. Flores, and R. Diaz, “A research interests include the reliability and power quality in distribution net-
hybrid genetic algorithm for optimal reactive power planning based works and IT applications to energy management systems.
upon successive linear programming,” IEEE Trans. Power Syst., vol.
14, no. 4, pp. 1292–1298, Nov. 1999.
[27] K. Y. Lee, X. Bai, and Y. M. Park, “Optimization method for reactive
power planning by using a modified simple genetic algorithm,” IEEE Jong-Keun Park (SM’98) was born in YuSeong, Korea, on October 21, 1952.
Trans. Power Syst., vol. 10, no. 4, pp. 1843–1850, Nov. 1995. He received the B.S. degree in electrical engineering from Seoul National Uni-
[28] K. Y. Lee and F. F. Yang, “Optimal reactive power planning using evo- versity, Seoul, Korea, in 1973 and the M.S. and Ph.D. degrees in electrical engi-
lutionary algorithms: A comparative study for evolutionary program- neering from the University of Tokyo, Tokyo, Japan, in 1979 and 1982, respec-
ming, evolutionary strategy, genetic algorithm, and linear program- tively.
ming,” IEEE Trans. Power Syst., vol. 13, no. 1, pp. 101–108, Feb. 1998. He worked as a Researcher at the Toshiba Heavy Apparatus Laboratory in
[29] B. Das, “Reactive power compensation for radial distribution net- 1982. He was a Visiting Professor with the Technology and Policy Program
works using genetic algorithm,” Elect. Power Energy Syst., vol. 24, and Laboratory for Electromagnetic and Electronic Systems, Massachusetts In-
pp. 573–581, 2002. stitute of Technology, Cambridge, in 1992. He is currently a Professor in the
[30] F. Alvarado, B. Borissov, L. D. Kirsch, and L. R. Christensen, Reac- School of Electrical Engineering, Seoul National University.
tive Power as an Identifiable Ancillary Service, Transmission Admin- Dr. Park is a Senior Member of the Japan Institute of Electrical Engineers
istrator of Alberta, Ltd., 2003. (JIEE). In addition, he is presently acting as a Fellow of the Institution of Elec-
[31] H. K. Kim, Power Systems Laboratory, KEPRI, private communica- trical Engineers (IEE) and is a Life Member of the Korean Institute of Electrical
tion, Apr. 2007. Engineers (KIEE) and the Korean representative of the study committee SC5
“Electricity Markets and Regulation” in CIGRE.

Jong-Young Park received the B.S., M.S., and Ph.D. degrees from Seoul Na-
tional University, Seoul, Korea, in 1999, 2001, and 2007, respectively.
Currently, he is a Senior Researcher at the Korea Electrotechnology Research
Institute (KERI). His research interests include the control of reactive power, IT
applications to energy management systems, and the application of the super-
conducting fault current limiter in power systems.

Authorized licensed use limited to: UNIVERSIDADE ESTADUAL DE CAMPINAS. Downloaded on March 20, 2009 at 13:18 from IEEE Xplore. Restrictions apply.

Vous aimerez peut-être aussi