Académique Documents
Professionnel Documents
Culture Documents
Abstract: Best-value (BV) procurement is increasingly used in conventional design-bid-build (DBB) delivery, which raises questions
regarding the influence of qualifications-based evaluation criteria when selecting construction contractors. The objectives of this study
Downloaded from ascelibrary.org by Universitas Indonesia on 04/23/19. Copyright ASCE. For personal use only; all rights reserved.
are to (1) examine BV procurement outcomes that can be expected from DBB projects, (2) determine which evaluation criteria have the
greatest dispersion among competing contractors, and (3) identify whether a relationship exists between cost- and qualifications-based
proposal submissions. A sample of 162 public institutional BV-procured DBB projects was collected that include evaluation results of
684 contractor proposals. Both descriptive and inferential statistics were used, including coefficient of variation and correlation analy-
sis of evaluation criteria. The results show that BV-selected contractors offer substantial qualifications benefits in comparison with
lowest- and average-bidder alternatives. Certain qualifications-based criteria, such as technical proposals, contractor interview scores,
and safety proposals were found to have a greater dispersion among competing bidders than cost proposals. Contributions of this study
to the body of knowledge include a sizable empirical data set of BV-procured DBB projects in the vertical sector and a unit of measure
that considers dispersion among competing contractor proposals. In current construction industry practice, it is recommended that
project owners consider BV for complex DBB projects and prioritize certain qualifications-based criteria that are well-suited for differ-
entiating between competing contractor proposals. DOI: 10.1061/(ASCE)CO.1943-7862.0001550. © 2018 American Society of Civil
Engineers.
Author keywords: Best-value procurement; Design-bid-build; Bidding cost; Qualifications-based evaluation criteria; Coefficient of
variation; Kruskal-Wallis H test.
detail.
BV Procurement in Construction
Literature Review BV procurement theoretically achieves a balance between LB and
QBS methodologies by considering both cost and qualifications
A number of studies have discussed different procurement proc-
criteria. Previous research has demonstrated various benefits of BV
esses used in the construction industry. The typical procurement
procurement in the construction industry compared with the tradi-
procedures are LB, QBS, and BV.
tional LB system. For example, Perrenoud et al. (2017) found that
contractors who received more favorable qualifications-based
LB Procurement in Construction evaluation scores tended to achieve better performance in project
LB traditionally provides several benefits to construction owners. quality, professionalism, risk communication, and overall customer
The first benefit is in terms of short-term monetary savings because satisfaction. BV has also been shown to achieve a reduction in cost
the owner is guaranteed to achieve the lowest cost option at the time growth, schedule growth, disputes, and claims (Abdelrahman et al.
of bidding. The second benefit relates to simplicity of the procure- 2008).
ment selection process (Yu and Wang 2012). In highway construc- Researchers have found that BV procurement brings benefits to
tion projects, LB is often supported by federal, state, and municipal both construction owners and contractors. For example, Gransberg
legislation due to the transparency it fosters in the evaluation pro- and Shane (2015) identified BV as a procurement method which
cess as the lowest bidder is readily discernable (Gransberg and can achieve greater consistency in long-term project performance.
Ellicott 1997; Tran et al. 2016). Abdelrahman et al. (2008) reported that BV has been found to
Despite its advantages and widespread use, LB procurement has achieve positive project performance due to its emphasis on
several drawbacks. For example, LB excludes quality considera- value-added services and qualifications-based criteria. Ahmed et al.
tions during the evaluation process, such as a contractor’s technical (2012) emphasized the need for BV in contractor selection for high-
proposal, past performance, and other qualifications-based criteria way projects rather than conventional LB due to the ability to con-
(Ahmed et al. 2012). Researchers (e.g., El Wardani et al. 2006; sider the contractor’s responsibility for maintenance across the
Richey 2012) have also found that LB has been linked to incon- project’s operational life span. According to Sullivan and Guo
sistent performance during the construction phase. Through analyz- (2009), BV procurement can benefit contractors by providing im-
ing 70 vertical construction projects, El Wardani et al. (2006) found proved cash flow and increased profitability because it can lead to a
that LB-procured projects suffered 9 and 5.6% greater cost and more performance-based project environment.
schedule growth, respectively, when compared with similar proj- It is important that many professional organizations in the de-
ects procured via BV methods. Richey (2012) noted a new library sign and construction industry support the use of BV for procuring
project in Palo Alto, California, that accrued $1.7 million in change construction services and have lobbied for its continued growth.
orders and a one-year delay. The LB-selected contractor was The AIA promotes the potential of qualifications-based evaluation
awarded with an initial bid that was $8 million below the estimated criteria in providing better contractor selection outcomes in terms
cost of $32 million. In this project, a dispute arose when the owner of cost savings and value engineering (Sandquist 2007). The
alleged the contractor had bid as low as possible and then submitted Construction Management Association of America (CMAA) has
an unreasonable number of requests for information and change promoted the use of qualifications-based criteria as an essential as-
orders. Conversely, the contractor argued that the design and spec- pect of procuring construction management services which poten-
ifications were not explicitly defined, which caused substantial cost tially increases project performance (McKeon 2016). A joint
growth and delays (Richey 2012). Such disputes are not uncommon publication between the AGC and the NASFA advocated for
in traditional LB systems (Sandquist 2007). and defined recommended best practices for owners to use in
BV procurement (AGC and NASFA 2008). Additionally, both
the Design-Build Institute of America (DBIA) and AGC identified
QBS in Construction qualifications-based criteria as important in achieving lower final
QBS is defined as a procurement system which completely concen- project costs regardless of project delivery method (DBIA 2012;
trates on the evaluation of qualifications-based criteria and does not AGC 2009).
include consideration of cost proposals. The use of QBS in the con-
struction sector is rare and generally confined to APDM projects.
BV Procurement in DBB Projects
Previous research has indicated that owners tend to favor noncost
criteria over time when they become more experienced in using Although LB is still the predominant method for procuring con-
APDMs (Gransberg and Shane 2015). Traditionally, architecture tractors in DBB projects, BV is becoming increasingly common.
Step 1 St ep 2 St ep 3 Step 4
of request for proposal (RFP), evaluation matrices/scores, and bid- laboratories, and office spaces. The majority of projects were ren-
ding costs. Step 3 performed descriptive analysis to identify selec- ovations, and inspection revealed no substantial difference between
tion outcomes of BV-procured DBB projects and inferential procurement procedures or contractor proposal responses for new
statistics analysis to investigate the COV among evaluation scores construction and renovation projects, likely due to the similarity in
for competing bidders as well as the relationship between contrac- owner organizations, facilities, and construction scopes. Further-
tor bid costs and their respective evaluation scores based on more, all projects in the data sample used virtually identical BV
qualifications-based criteria. Step 4 was the collation of key find- procurement procedures, including virtually identical evaluation
ings. The following sections present data collection and data analy- criteria, similar weighting schemes, and consistent evaluation scor-
sis in detail. ing procedures in the owners’ RFPs.
The BV procurement processes in the data sample considered
similar evaluation criteria centered on both qualifications (technical
Data Collection proposal, past performance, contractor interview scores, and safety)
Initially, more than 177 BV-procured DBB construction projects and nonqualifications (cost and schedule) items. Table 1 provides
were collected from both the horizontal and vertical sectors. Project descriptive statistics related to the evaluation weights for each
records were collected for analysis rather than via a survey meth- evaluation criterion as established in the owner’s RFP. The evalu-
odology. The following project records were collected for each ation weights shown are normalized to a 100% scale to show the
project in the data set: the project RFP, the owner’s evaluation ma- relative importance the owners placed on each criterion. For exam-
trix and associated evaluation scores of all competing contractors, ple, the cost criterion examined from 162 projects was found to
and bid costs from all competing contractors. The final data set was have a median of 25% of the total evaluation weight, whereas
limited to projects in the North American vertical sector. All proj- the remaining 75% was distributed in the schedule and other
ects were procured by public owners in the institutional sector, in- qualifications-based criteria. The evaluation criteria were analyzed
cluding state, city, and municipal agencies as well as elementary, in isolation to understand the ranking of selected contractors, the
secondary, and postsecondary school systems. The final data set differential in evaluation scores between selected contractors and
consisted of 162 projects that met the above criteria. their competitors, the COV in evaluation scores among competing
In the data sample, the projects were filtered to ensure similar bidders, and the relationships between bidding costs and
construction scopes, facility types, and BV procurement proce- qualifications-based criteria evaluations.
dures. All projects were vertical construction in institutional facili- The owner’s evaluation matrix from each project in the data
ties. The scopes were largely consistent in terms of functional sample (n ¼ 162) was reviewed. Each project’s evaluation matrix
use of the buildings, which mainly consisted of classrooms, contained the owner evaluation committee’s scoring results for
Relationship between Qualifications-Based Evaluation study clearly indicate the ability of BV procurement to provide con-
Criteria and Bid Costs struction owners with a selection outcome that balances cost- and
qualifications-based criteria.
This study found that, in BV-procured DBB projects contractor
qualifications have no direct association with bid cost. All contrac-
tor bids from the data sample were normalized against the low-bid
Conclusion, Contributions, and Limitations
alternative and the average bid on a per-project basis. As shown in
Table 10, neither measure of contractor bid cost was found to have a As BV procurement expands across the construction industry,
statistically significant correlation with the qualifications-based cri- construction owners are gradually coming to view it as an appro-
teria of technical proposals, contractor interviews, or safety propos- priate option for DBB projects. However, few owners have direct
als. Contractor bid cost compared with the lowest-bid alternative experience in applying BV procurement in the DBB delivery sys-
did have a statistically significant and inversely proportional cor- tem. For this reason, this research aimed to add to the existing
relation with past performance; however, the correlation coefficient literature, which lacks extensive empirical data sets on this in-
(rs ¼ −0.109) was so weak that it represented no association of creasingly relevant topic, by exploring BV procurement imple-
practical significance to the industry (Zou et al. 2003). Therefore, mentation. Toward this end, the authors quantitatively analyzed
the research hypothesis that greater evaluation scores for each project’s RFP and evaluation matrix, which included all bid-
qualifications-based evaluation criteria correspond with greater ding and evaluation scoring data for every participating contrac-
bid costs was rejected. tor’s BV proposal (n ¼ 684), via both descriptive and inferential
This study found no evidence that, when owners determine that statistics.
a contractor has demonstrated greater qualifications than compet- This study found that BV procurement achieves a balance be-
itors, that contractor’s corresponding bid cost is higher than com- tween LB and QBS procurement in that it results in selection of the
peting bids. This result was somewhat surprising given the best-qualified contractor in 52% of cases and the lowest-bid con-
conventional wisdom that firms with greater qualifications may tractor in slightly less than half. In the analysis, BV-selected con-
command higher fees (Yu et al. 2013). A potential explanation tractors ranked as the top-qualified and lowest-cost bidders nearly a
is that qualified contractors may leverage their experience and tech- quarter of the time, ranked in the top two for qualifications and cost
nical expertise to execute the construction phase more efficiently 67% of the time, and ranked in the top three 88% of the time.
than their competitors, which can lead to overall cost savings BV-selected contractors also had substantially greater qualifica-
and in turn result in competitive bid costs. This is supported by tions when compared with the lowest- and average-bid alternatives.
the fact that 67% of BV-selected contractors ranked among the Owner evaluation scores for qualifications-based criteria were
top two bidders in both cost and qualifications criteria and 88.3% found to have statistically significant greater COV values than cost
were ranked among the top three. In this manner, the results of this proposals, indicating that a range of contractor qualifications is
Table 10. Spearman’s correlation of all evaluation criteria versus lowest bid and average bid
Code Variable (1) (2) (3) (4) (5) (6) (7)
(1) Cost versus lowest bid 1 — — — — — —
(2) Cost versus average bid 0.797a 1 — — — — —
(3) Technical proposal −0.057 0.013 1 — — — —
(4) Past performance −0.109a −0.057 0.034 1 — — —
(5) Contractor interview −0.091 −0.030 0.131b 0.169a 1 — —
(6) Schedule −0.030 0.026 −0.125a −0.007 0.209b 1 —
(7) Safety 0.053 0.035 0.024 −0.019 0.050 −0.054 1
a
Significant at the 0.01 level (2-tailed).
b
Significant at the 0.05 level (2-tailed).
the horizontal sector, this study assembled a data set made up en- design, 169–171. New York: Wiley.
tirely of vertical construction projects. The unit of measurement in ACEC (American Council of Engineering Companies). 2018. “The Brooks
this paper also contributes an analysis of evaluation scores deter- Act: Federal Government Selection of Architects and Engineers.”
mined by the owner evaluation committee for each bidder (both Accessed June 23, 2018. https://www.acec.org.
selected and unselected) in the data set. Previous studies have more AGC and NASFA (Associated General Contractors and National Associ-
commonly focused on owner weighting of evaluation criteria rather ation of State Facilities Administrators). 2008. Best practices for use of
than evaluation scores themselves, and rarely included data from all best value selections, 5–49. Houston: AGC and NASFA.
competing bidders. AGC (Associated General Contractors). 2009. “Qualifications based
selection of contractors.” Accessed October 10, 2017. https://www
This study also provides several contributions to industry practi-
.aiacc.org.
tioners in both owner and contractor organizations. First, the em-
AGC (Associated General Contractors). 2017. “Construction is not a
pirical results demonstrate that BV procurement achieves a ‘commodity’.” Accessed October 10, 2017. https://www.agc.org.
reasonable balance between LB and QBS methods and that LB- Ahmed, J., N. Gharaibeh, and I. Damnjanovic. 2012. “Best-value bid
procured projects rarely select the best qualified contractor. This selection methods for performance-based roadway maintenance
finding may serve as motivation for owners to increasingly consider contracts.” Transp. Res. Rec. 2292 (1): 12–19. https://doi.org/10
BV as an appropriate procurement option for DBB projects in sit- .3141/2292-02.
uations where it would be beneficial to hire a contractor with Alleman, D., A. Antoine, D. Gransberg, and K. Molenaar. 2017. “Compari-
impressive qualifications. Furthermore, the results refute the per- son of qualifications-based selection and best-value procurement for
ception that greater qualifications are correlated with higher bid construction manager-general contractor highway construction.”
costs, meaning that owners do not have to pay a substantial pre- Transp. Res. Rec. 2630: 59–67. https://doi.org/10.3141/2630-08.
mium to partner with more highly qualified contractors. Finally, Amiri, S. 2016. “Revisiting inference of coefficient of variation: Nuisances
analysis of competing contractor proposals found larger dispersion parameters.” Stat. 5 (1): 234–241. https://doi10.1002/sta4.116.
California State Senate. 2015. “Senate Bill 762: Competitive bidding: Best
among qualifications-based criteria than in cost proposals, which
value: Pilot program: Design-build.” Accessed February 24, 2018.
supports the viewpoint of numerous design and construction pro- http://www.leginfo.ca.gov/pub/15-16/bill/sen/sb_0751-0800/sb_762
fessional organizations that advocate construction as a professional _bill_20151008_chaptered.pdf.
service rather than a commodity. This information is also beneficial Chinowsky, P. S., and G. A. Kingsley. 2009. An analysis of issues pertain-
for construction contractors in strategizing their proposal develop- ing to qualifications-based selection. Washington, DC: American
ment efforts when participating in a BV procurement; that is, con- Council of Engineering Companies and American Public Works
tractors have greater opportunities to differentiate themselves from Association.
competitors in their qualifications-based proposal submissions than Christodoulou, S., F. Griffis, L. Barrett, and M. Okungbowa. 2004.
in their bid cost. “Qualifications-based selection of professional A/E services.” J. Man-
age. Eng. 20 (2): 34–41. https://doi.org/10.1061/(ASCE)0742-597X
(2004)20:2(34).
Limitations and Recommendations for Future CMAA (Construction Management Association of America). 2012. An
Research owner’s guide to project delivery methods, 10. McLean, VA: CMAA.
Curto, J. D., and J. C. Pinto. 2008. “The coefficient of variation asymptotic
A limitation of this study was that project closeout data (in terms distribution in the case of non-iid random variables.” J. Appl. Stat.
of final cost and schedule growth) were not available in the data 36 (1): 21–32. https://doi.org/10.1080/02664760802382491.
set. Although this paper was focused on the bidding stage, future DBIA (Design-Build Institute of America). 2012. “DBIA position
studies are recommended to collect final cost and schedule per- statement—Qualification based selection.” Accessed October 15,
formance data for BV-procured DBB projects. These additional 2017. https://www.dbia.org.
data on cost and schedule growth will enable researchers to more El Wardani, M., J. Messner, and M. Horman. 2006. “Comparing procure-
clearly identify the project performance implications of BV ment methods for design-build projects.” J. Constr. Eng. Manage.
procurement. 132 (3): 230–238. https://doi.org/10.1061/(ASCE)0733-9364(2006)
132:3(230).
Another limitation of this study was that the data set was re-
Forkman, J. 2009. “Estimator and tests for common coefficients of varia-
stricted to vertical construction projects in public institutional sec-
tion in normal distributions.” Commun. Stat. Theory Methods 38 (2):
tors. The current body of knowledge will benefit from future 233–251. https://doi.org/10.1080/03610920802187448.
studies that compile data from other areas of the vertical sector, Forkman, J., and S. Verrill. 2008. “The distribution of McKay’s approxi-
including private construction owners and projects in the commer- mation for the coefficient of variation.” Stat. Probab. Lett. 78 (1):
cial, healthcare, and residential sectors. Similar empirical data sets 10–14. https://doi.org/10.1016/j.spl.2007.04.018.
can also be collected from the horizontal, manufacturing, and Fung, W. K., and T. S. Tsang. 1998. “A simulation study comparing
power generation sectors of the construction industry. tests for the equality of coefficients of variation.” Stat. Med. 17 (17):