Académique Documents
Professionnel Documents
Culture Documents
Adding Resources
• The most common method for shortening project time is
to assign additional staff and equipment to activities.
• However, there are limits to how much time can be saved.
• Doubling the workforce won't necessarily halve the time.
• This would only be correct when activities can be
partitioned so minimal communication is needed between
workers, as in harvesting a crop or repaving a highway.
• Most projects aren't set up that way; extra staff increase
communication requirements to coordinate their work.
• For example, doubling a team by adding two workers
requires six times as much pair-wise intercommunication
than is required in the original two-person team.
ECTE350 Lecture 2 Slide 12 © P. A. J. Larkin 2013
Scheduling Overtime
• Overtime has disadvantages and must be used judiciously.
• First, hourly workers are normally paid overtime rates,
which can vary greatly between sectors and regions.
• Sustained overtime by salaried employees may incur
intangible costs such as divorce, burnout and turnover.
• Turnover is a key concern when there are staff shortages.
• Also, it is an oversimplification to assume that, over an
extended period of time, a person is as productive during
their eleventh hour at work as during their third.
• There are natural limits to what is humanly possible, and
extended overtime may actually lead to an overall decline
in productivity when fatigue sets in.
ECTE350 Lecture 2 Slide 16 © P. A. J. Larkin 2013
Fast-Tracking
• Sometimes it is possible to rearrange the logic of the
project network so that critical activities are done in
parallel (concurrently) rather than sequentially.
• If the project situation is right, this is a good alternative.
• As noted in Chapter 6, one of the most common methods
for restructuring activities is to change a finish-to-start
relationship (dependency) to a start-to-start relationship,
i.e., changing activities from sequential to parallel. (See
the end of the Lecture 1 for dependency relationships.)
• Changing activities from sequential to parallel usually
requires closer coordination among those responsible for
the activities affected but can produce huge time savings.
ECTE350 Lecture 2 Slide 20 © P. A. J. Larkin 2013
Compromise Quality
• Reducing quality is always an option, but it is rarely
acceptable or used.
• If quality is sacrificed, it may be possible to reduce the
time of an activity on the critical path.
• In practice the methods most commonly used to crash
projects are scheduling overtime, outsourcing, and adding
resources.
• Each of these maintains the essence of the original plan.
• Options that depart from the original project plan include
do it twice and fast-tracking.
• Rethinking of project scope, customer needs, and timing
become major considerations for these techniques.
ECTE350 Lecture 2 Slide 24 © P. A. J. Larkin 2013
Constructing a PCDG
Simplified Example
• For example, activity D can be reduced from a normal
time of 11 time units to a crash time of 7 time units, or a
maximum of 4 time units.
• The positive slope for activity D is calculated as follows:
Crash cost - Normal cost
Cost slope =
Normal time - Crash time
$150 - $50
=
11 - 7
$100
=
4
= $25 per period reduced
ECTE350 Lecture 2 Slide 42 © P. A. J. Larkin 2013
Constructing a PCDG
Simplified Example
• The total direct cost for 22 time units is $525.
• Now a 3rd critical path A-B-E-G; all activities are critical.
• The least-cost method for reducing the project duration to
21 time units is the combination of the circled activities
C, D, E which cost $30, $25, $30, respectively, and
increase total direct costs to $610.
Constructing a PCDG
Simplified Example
• With the total direct costs for the array of specific project
durations found, the next step is to collect the indirect
costs for these same durations.
• These costs are typically a rate per day and are easily
obtained from the accounting department.
• Figure 9.5 following presents the total direct costs, total
indirect costs, and total project costs.
• These same costs are plotted in Figure 9.6 following.
Practical Considerations
Using the Project Cost-Duration Graph …
• This graph is valuable to compare any proposed
alternative or change with the optimum cost and time.
• More importantly, the creation of such a graph keeps the
importance of indirect costs in the forefront of decision
making.
• Indirect costs are frequently forgotten in the field when
the pressure for action is intense.
• Finally, such a graph can be used before the project
begins or while the project is in progress.
Practical Considerations
Crash Times
• Collecting crash times for even a moderate-size project
can be difficult.
• The meaning of crash time is difficult to communicate.
• What is meant when you define crash time as "the
shortest time you can realistically complete an activity"?
• Crash time is open to different interpretations and
judgments, and some estimators feel very uncomfortable
providing crash times.
• Regardless of the comfort level, the accuracy of crash
times and costs is frequently rough at best, when
compared with normal times and costs.
ECTE350 Lecture 2 Slide 54 © P. A. J. Larkin 2013
Practical Considerations
Choice of Activities to Crash Revisited
• The cost-time crashing method relies on choosing the
cheapest method for reducing the duration of the project.
• There are other factors that should be assessed beyond
simply cost:
1. The inherent risks involved in crashing particular
activities need to be considered.
2. The timing of activities needs to be considered.
3. The impact crashing would have on the morale and
motivation of the project team needs to be assessed.
Practical Considerations
Time Reduction Decisions and Sensitivity …
• How far to reduce the project time from the normal time
toward the optimum depends on the sensitivity of the
project network.
• A network is sensitive if it has several critical or near-
critical paths, and it requires careful analysis.
• Slack reduction in a project with several near-critical
paths reduces scheduling flexibility and increases the risk
of being late.
Practical Considerations
Time Reduction Decisions and Sensitivity
• Insensitive networks are not a rarity in practice; they
occur in perhaps 25% of all projects.
• Insensitive networks with high indirect costs can produce
large savings.
Organisational Structures
• The purpose of an organisation is to coordinate the efforts
of many to accomplish goals.
• Organisational structure shows reporting relationships.
• Organisational structure impacts on projects in two ways:
1. The organisational structure of the customer organisation
2. The organisational structure of the project team itself
• Chapter 3 reviews the primary types of organisation used
for projects and the reasons they are designed that way.
• It discusses the framework which must be established and
well understood by all involved at the start of the project.
• If not, it will be impossible to get important decisions made
and adhered to, and the project will most likely fail.
ECTE350 Lecture 2 Slide 70 © P. A. J. Larkin 2013
Organisational Structures
• Galbraith described three basic forms of organisation:
1. Functional
2. Project
3. Matrix
• Each form of organisation has its own benefits, and each
works well in certain types of environments.
• The appropriate organisational structure depends on the
goal of the organisation, the type of work it is supposed to
do, and the environment within which it operates.
• There are many variations to the three basic structures.
• The textbook also describes the Network structure.
ECTE350 Lecture 2 Slide 72 © P. A. J. Larkin 2013
Organisational Structures
1. Functional
Advantages Disadvantages
• No Structural Change • Lack of Focus
• Flexibility • Poor Integration
• In-Depth Expertise • Slow
• Easy Post-Project • Lack of Ownership
Transition
Organisational Structures
2. Project
• The great advantage of the project structure is focus:
everyone on the project team is there for one purpose.
• However, there are some problems as well:
• Team members may get out of touch with what is going
on in their "home" departments, including important and
useful technical developments.
• Functional managers may feel they have little control or
influence over what project teams are doing and this
makes it difficult to impose functional policies.
• Perhaps the biggest problem is that project teams can be
inefficient in their use of resources, especially people.
ECTE350 Lecture 2 Slide 76 © P. A. J. Larkin 2013
Organisational Structures
3. Matrix
• If an organisation continually operates in a project mode
(many do in construction, IS/IT and consulting), there is a
need to quickly create large project groups.
• The matrix organisation form is a grid-like structure of
reporting and authority relationships overlaying
traditional functional organisation (see Figure 3.4).
• It is used within organisations that make more than
minimal use of project teams or product groups.
• The improved coordination obtained from project
organisation is combined with the strengths for each
specialty that are provided by functional forms of
organisation and is more resource-efficient.
ECTE350 Lecture 2 Slide 78 © P. A. J. Larkin 2013
Organisational Structures
3. Matrix
• Weak Form:
• The authority of the functional manager predominates
and the project manager has indirect authority.
• Balanced Form:
• The project manager sets the overall plan and the
functional manager determines how work to be done.
• Strong Form:
• The project manager has broader control and functional
departments act as subcontractors to the project.
Organisational Structures
Network
• An alliance of several organisations for the purpose of
creating products or services.
• A "hub" or "core" firm with strong core competencies
outsources key activities to a collaborative cluster of
satellite organisations.
Advantages Disadvantages
• Cost Reduction • Coordination of
• High Level of Expertise Breakdowns
• Flexible • Loss of Control
• Conflict
ECTE350 Lecture 2 Slide 82 © P. A. J. Larkin 2013
Summary
• How far to reduce the project duration from the normal
time toward the optimum depends on the sensitivity of the
project network.
• A sensitive network is one that has several critical or
near-critical paths.
• Great care should be taken when shortening sensitive
networks to avoid increasing project risks.
• Conversely, insensitive networks represent opportunities
for potentially large project cost savings by eliminating
some overhead costs with little downside risk.
References
Cadle, J. and Yeates, D. (2008), Project Management for Information
Systems, 5th ed., Pearson Education Limited, Harlow, England.
Larson, E. W. and Gray, C. F. (2011), Project Management: The
Managerial Process, 5th ed., McGraw-Hill/Irwin, New York.
(Textbook)
Turner J. R. (2009), The Handbook Of Project-Based Management:
Leading Strategic Change in Organisations, McGraw-Hill, London.
Yardley, D. (2002), Successful IT Project Delivery: Learning the
Lessons of Project Failure, Pearson Education Ltd., Edinburgh Gate.
For other references see the textbook.